Professional Documents
Culture Documents
ccc
c
c
c
In the previous chapter on capital budgeting the project appraisal techniques were
applied on the assumption that the project will generate a given set of cash flows.
It is quite obvious that one of the limitations of DCF techniques is the difficulty in
estimating cash flows with certain degree of certainty. Certain projects when taken
up by the firm will change the business risk complexion of the firm.
This business risk complexion of the firm influences the required rate of return of the
investors. Suppliers of capital to the firm tend to be risk averse and the acceptance
of a project that changes the risk profile of the firm may change their perception of
required rates of return for investing in firm¶s project. Generally the projects that
generate high returns are risky. This will naturally alter the business risk of the firm.
Because of this high risk perception associated with the new project a firm is forced
to asses the impact of the risk on the firm¶s cash flows and the discount factor to be
employed in the process of evaluation.
Definition of Risk: Risk may be defined as the variation of actual cash flows from the
expected cash flows. The term risk in capital budge ting decisions may be defined as
the variability that is likely to occur in future between the estimated and the actual
returns. Risk exists on account of the inability of the firm to make perfect forecasts of
cash flows.
Risk arises in project evaluation because the firm cannot predict the occurrence of
possible future events with certainty and hence, cannot make any correct forecast
about the cash flows. The uncertain economic conditions are the sources of
uncertainty in the cash flows. For example, a company wants to produce and market
a new product to their prospective customers. The demand is affected by the general
economic conditions. Demand may be very high if the country experiences higher
economic growth. On the other hand economic events like weakening of US dollar,
sub prime crises may trigger economic slow down. This may create a pessimistic
demand drastically bringing down the estimate of cash flows. Risk is associated with
the variability of future returns of a project. The greater the variabil ity of the expected
returns, the riskier the project. Every business decision involves risk. Risk arises out
of the uncertain conditions under which a firm has to operate its activities. Because
of the inability of firms to forecast accurately cash flows of future operations the firms
face the risks of operations. The capital budgeting proposals are not based on
perfect forecast of costs and revenues because the assumptions about the future
behaviour of costs and revenue may change. Decisions have to be made in advance
assuming certain future economic conditions.
There are Many factors that affect forecasts of investment, cost and revenue.
ã The business is affected by changes in political situations , monetary policies,
taxation, interest rates, policies of the central bank of the country on lending by
banks etc.
2 Industry specific factors influence the demand for the products of the industry to
which the firm belongs.
3 Company specific factors like change in management, wage negotiations with the
workers, strikes or lockouts affect company¶s cost and revenue positions.
Therefore, risk analysis in capital budgeting is part and parcel of enterprise risk
management. The best business decisions may not yield the desired results
because the uncertain conditions likely to emerge in future can materially alter the
fortunes of the company. Every change gives birth to new challenges. New
challenges are the source of new opportunities. A proactive firm will convert every
problem into successful enterprise opportunities. A firm which avoids new
opportunities for the inherent risk associated with it, will stagnate and
degenerate. Successful firms have empirical history of successful management of
risks. Therefore, analysing the risks of the project to reduce the element of
uncertainty in execution has become an essential aspect of today¶s corporate project
management.
Both the projects have a payback period of 4 years. The project B is riskier than the
Project A because Project A recovers 8 of initial cash outlay in the first two years
of its operation where as Project B generates higher Cash inflows only in the latter
half of the payback period. This undermines the utility of payback period as a
technique of incorporating risk in project evaluation. This method considers only time
related risks and ignores all other risks of the project under consideration.
c
+
c
,
c
c
The basis of this approach is that there should be adequate reward in the form of
return to firms which decide to execute risky business projects. Man by nature is
riskaverse and tries to avoid risk. To motivate firms to take up risky projects returns
expected from the project shall have to be adequate, keeping in view the
expectations of the investors. Therefore risk premium need to be incorporated in
discount rate in the evaluation of risky project proposals.
Therefore the discount rate for appraisal of projects has two components. Those
components are
Risk free rate is computed based on the return on government securities. Risk
premium is the additional return that investors require as compensation for assumi ng
the additional risk associated with the project to be taken up for execution. The more
uncertain the returns of the project the higher the risk. Higher the risk greater the
premium. Therefore, risk adjusted Discount rate is a composite rate of risk free rate
and risk premium of the project.
%! :
$ :
ã. There are no objective bases of arriving at the risk premium. In this process the
premium rates computed become arbitrary.
2. The assumption that investors are risk ± averse may not be true in respect of
certain investorswho are willing to take risks. To such investors, as the level of risk
increases, the discountrate would be reduced.
3. Cash flows are not adapted to incorporate the risk adjustment for net cash in
flows.
c(% :
Under this method the risking uncertain, expected future cash flows are converted
into cash flows with certainty. Here we multiply uncertain future cash flows by the
certainty ± equivalent coefficient to convert uncertain cash flows into certain cash
flows. The certainty equivalent coefficient is also known as the risk ± adjustment
factor. Risk adjustment factor is normally denoted by Įt (Alpha . It is the ratio of
certain net cash flow to risky net cash flow
=Certainty Equivalent = Certain Cash flow / Risky Cash flow
The discount factor to be used is the risk free rate of interest. Certainty
equivalent coefficient is between and ã. This risk ± adjustment factor varies
inversely with risk. If risk is high a lower value is used for risk adjustment. If risk is
low a higher coefficient of certainty equivalent is used .
% :
%c :
There are many variables like sales, cost of sales, investments, tax rates etc which
affect the NPV and IRR of a project. Analysing the change in the project¶s NPV or
IRR on account of a given change in one of the variables is called Sensitivity
Analysis. It is a technique that shows t he change in NPV given a change in one of
the variables that determine cash flows of a project. It measures the sensitivity of
NPV of a project in respect to a change in one of the input variables of NPV.
The reliability of the NPV depends on the reliabili ty of cash flows. If fore casts go
wrong on account of changes in assumed economic environments, reliability of NPV
& IRR is lost. Therefore, forecasts are made under different economic conditions viz
pessimistic, expected and optimistic. NPV is arrived at for all the three assumptions.
Following steps are involved in Sensitivity analysis:
ã. Identification of variables that influence the NPV & IRR of the project.
c#cc'c
Many project decisions are complex investment decisions. Such complex investment
decisions involve a sequence of decisions over time. Decisions tree can handle the
sequential decisions of complex investment proposals. The decision of taking up an
investment project is broken into different stages. At each stage the proposal is
examined to decide whether to go ahead or not. The multi ± stages approach can be
handled effectively with the help of decision trees. A decision tree presents
graphically the relationship between a present decision and future events, future
decisions and the consequences of such decisions.
% cc
cc' :
3. Complex projects involve huge out lay and hence risky. There is the need to
define and evaluate scientifically the complex managerial problems arisi ng out of the
sequence of interrelated decisions with consequential outcomes of high risk. It is
effectively answered by decision tree approach.
4. Structuring a complex project decision with many sequential investment decisions
demands effective project risk management. This is possible only with the help of an
analytical tool like decision tree approach.
5. Able to eliminate unprofitable outcomes and helps in arriving at optimum decision
stages in time sequence.
$$c
Risk in project evaluation arises on account of the inability of the firm to predict the
performance of the firm with certainty. Risk in capital budgeting decision may be
defined as the variability of actual returns from the expected. There are many factors
that affect forecasts of investment, costs and revenues of a project. It is possible to
identify three type of risk in any project, viz standalone risk, corporate risk and
market risk. The sources of risks are:
a. Project
b. Competition
c. Industry
d. International factors and
e. Market
The techniques for incorporation of risk factor in capital budgeting decision could be
grouped into conventional techniques and statistical techniques.