Assignment 01

1. Develop a Network digram using AON technique and calculate Critical path using follwing
table
2. Enter the information in the table into MS project.What is critical path.Display the network
diagram and Critical path

Estimated Duration
Activity Predecessor
(days)
A 1 None
B 3 A
C 4 B
D 2 B
E 1 C
F 3 C,D
G 3 E
H 1 F
I 2 G,H
J 5 I

Assignment 02
1.Using the information below,Complete the function point analysis in order to use the basic
COCOMO model to estmate the duration of the number of people needed to develop application
usin C++. Assume that the project is relatively simple and straightforword and that the team is
familier with both the problem and technology.You can use perform the calculation by hand
2. Check the results using webpage cost.jsc.nasa.gov/COCOMO.html

Complexity
Files Low Average High Total
ILF __*7= __ __ *10= __ __ *15= __
EIF __*5=__ __*7=__ __*10=__
EI __*3=__ __*4=__ __*6=__
EO __*4=__ __*5=__ __*7=__
EQ __*3=__ __*4=__ __*6=__

Complexity
Low averag High
e
ILF 4 2 0
EIF 0 1 0
EI 3 2 0
EO 5 7 3
EQ 2 5 2

Language Average source LOC


per function point
Basic 107
C 128
C++ 53
COBOL 107
Delphi 29
java 53
VB5 29

General System Chracteristics Degree of Influence


Data Communications 2
Distributed data Processing 3
Performence 3
Heavily used Configuration 4
Transaction rate 4
Online data entry 2
End user efficiency 2
Online update 2
Complex processing 2
Reusabilty 3
Installation ease 2
Operational ease 2
Multiple site 1
Faclitate change 1

Asssignment 03
Using the following information, conduct an earned value analysis to determine whether you
believe the project will remain within its original planned budget of $12,000. Use a spreadsheet
software package to determine the Estimate at Completion (EAC) for both typical and atypical
variances.
Planned Actual Percent Earned
Value Cost Complete Value
Phase 1: Test Planning
Develop Unit Test Plan $ 500 $ 500 100% $ 500
Develop integration test plan $ 600 $ 600 100% $ 600
Develop Acceptance test plan $ 550 $ 550 100% $ 550
Payment 1: $ 1,650 $ 1,650 $ 1,650

Phase 2: Unit Testing


Code walkthrough with team $ 600 $ 700 100% $ 600
Test software units $ 800 $ 1,200 100% $ 800
Identify programs that do not meet specifications $ 500 $ 500 100% $ 500
Modify code $ 1,200 $ 1,300 100% $ 1,200
Re-test units $ 300 $ 400 100% $ 300
Verify code meets standards $ 200 $ 200 100% $ 200
Payment 2: $ 3,600 $ 4,300 $ 3,600

Phase 3: Integration Testing


Test integration of all modules $ 600 $ 600 100% $ 600
Identify components that do not meet specifications $ 300 $ 500 75% $ 225
Modify code $ 1,400 $ 1,400 50% $ 700
Re-test integration of modules $ 400 $ 400 75% $ 300
Verify Components meet standards $ 200 $ 200 80% $ 160
Payment 3: $ 2,900 $ 3,100 $ 1,985

Phase 4: Acceptance Testing


Business Review with Client $ 400 0%
Client tests system $ 800 0%
Identify units and components that do not meet $ 550 0%
specifications
Modify code $ 800 0%
Retest units and components $ 700 0%
Verify that system meets standards $ 600 0%
Payment 4: $ 3,850

Assignment 4

Consider case study as final year project

1. Develop MOV and MOV table for the project

2. Prepare Business case by using the template given (page no 59-wiley text) for your project
and Explain
3. Prepare Project Charter by using the template given (page no 89 Wiley text).Explain

4. Develop SCOPE STATEMENT for the project

5. Develop DSC for the project and explain

6. Develop WBS for the project using MS visio and Explain

7. Develop the gantt chart for the project and Explain

8. Develop Network diagram for the project and Explain

9. Develop context level DFD and UCD for the project and Explain

Assignment 5

Case Study: Critical Path Analysis

This Activity is based around a decision by a food manufacturing business to install a new piece

of machinery to cope with anticipated demand leading up to a busy time of the year. The

machinery allows pre-packed food to be manufactured with 90% automation compared to the

existing machinery which relied far more on human input, making the whole process only 40%
automated.

In previous years, the business has always suffered shortages as a result of the inadequacy of the

equipment they have had and this has caused some dissatisfaction amongst its customers. While

most have remained loyal, there have been one or two who have taken their business elsewhere

and this has prompted the business to act

The Activity requires two groups to analyse competing pieces of machinery. Both machines will

do the job that they are required to do, both have the same output ratios and initial cost but the

crucial thing for the business is how quickly the machines can be installed and begin production.

You must use Critical Path Analysis to advise the business on the most appropriate piece of

machinery out of the two.

You must consider the correct order for each task, draw out the network for the machine in

question, and indicate the earliest start time, latest finishing time and the critical path. All the

tasks below are those that need to be completed by the firm themselves - the new machine

construction, for example, refers to the work that needs to be done following delivery of the

equipment.

Machine A

Task Activity Estimated Time

1 Re-decoration of area 5 days

2 Lead time for new machine delivery 14 days

3 Re-routing of electrical supply 2 days

4 Delivery and inspection of new machine 1 day

5 Training of staff 2 days

6 Program software 4 days

7 Lead time for delivery of raw materials 5 days

8 Testing of new machine 2 days


9 Install and test network cabling for computerised machine 3 days

10 Complete hygiene treatment 1 day

11 Remove existing machinery 4 days

12 New machine construction 2 days

Machine B

Task Activity Estimated Time

1 Re-decoration of area 5 days

2 Lead time for new machine delivery 16 days

3 Re-routing of electrical supply 3 days

4 Delivery and inspection of new machine 1 day

5 Training of staff 3 days

6 Program software 5 days

7 Lead time for delivery of raw materials 3 days

8 Testing of new machine 2 days

9 Install and test network cabling for computerised machine 2 days

10 Complete hygiene treatment 1 day

11 Remove existing machinery 4 days

12 New machine construction 1 day

When considering the tasks, note that some tasks may have to be repeated more than once!

(Think about the context here).


Assignment 6
The activity information of a project is given in the table below

Normal Normal Crash Crash

Activity Predecessor Time Cost Time Cost

Days $ Days $

A - 7 1600 5 2600

B - 2 850 1 1000

C - 9 2500 7 3000

D B 10 2000 10 2000

E C 3 2000 2 2450

F A,B 9 950 6 2050


G D,E 13 1300 10 3000

H F,D 8 1000 6 1600

Identify the critical path in the project.

Determine the normal project completion time and cost


Calculate the cost for achieving a project completion
time of 22 days.
Determine which activities to crash and
by how much.

Determine what the minimum project completion time


that can be achieved.

Assignment 7

1.A project consisting of 12 distinct activities is to be analysed by using PERT.


Draw the PERT network. Indicate the expected total slack for each activity and

hence indicate the average critical path. With in how many days would you expect

theproject to be completed with 99% chances?


The following in formation is given ( the time estimates are in days)

ACTIVITY PREDECESSOR OPTIMISTIC NORMAL PESSIMISTIC

ACTIVITY TIME (days) TIME (days) TIME (days)

A - 2 2 2

B - 1 3 7

C A 4 7 8

D A 3 5 7

E B 2 6 9

F B 5 9 11

G C,D 3 6 8

H E 2 6 9

I C,D 3 5 8

J G,H 1 3 4

K F 4 8 11

L J,K 2 5 7

2. Given the following information, is this project in


trouble? Explain.
( REF WILEY BOOK
Communications management)
Task BCWS BCWP ACWP

A $ 384.62 $ 384.62 $ 384.62

B $ 576.92 $ 576.92 $ 576.92

C $1,461.54 $1,461.54 $1,096.15


Total $2,423.08 $2,423.08 $2,057.69

3.Three praposals (W,X and Y) have been rated on six criteria as follows
1-poor 2- average 3- good
Choose between the three proposals
A by simple rating method
B By weighted rating method

Criteria weight W X Y
Attention to quality .25 2 1 3
Cost .2 3 3 1
Project Plan .2 2 2 1
Project Organization .15 3 2 3
Likelihood of success .1 2 3 3
Contractor Credentials .1 2 2 3