You are on page 1of 13

Geotechnical Engineering 130

12) Negative Skin Friction

z Side friction resistance:


- Relative movements between surrounding soils and pile for side
friction

In general Downdrag force

z Downdrag force develops when relative downward movements of soil to


the pile occur.
⇒ Observations show that relative displacements of 0.6(in) is needed to
generate full downdrag force.

z Downdrag movement caused by any increase of effective stress in


surrounding soil;
y Dewatering.
y Surface loads after installation of piles.
- Granular soil fill over clay
⇐ consolidation of clay layer by fill load
- Clay fill over granular soil
⇐ self-consolidation of clay fill
y Dissipation of excess pore water pressure induced by pile driving.

SNU Geotechnical and Geoenvironmental Engineering Lab.


Geotechnical Engineering 131

ex) Dewatering

Lowering

At excavation site, construction dewatering causes downdrag forces.


y Lower water level
→ Cause consolidation settlements by increase of vertical effective
stress

SNU Geotechnical and Geoenvironmental Engineering Lab.


Geotechnical Engineering 132

z Estimation of downdrag (similar to β method)

i) Clay fill over granular soils

y The unit negative skin friction on the pile is

f n = K 'σ v' tan δ (= N s' σ v' )

where K ' ≡ earth pressure coefficient


= K 0 = 1 − sin φ '

σ v' = γ f ' z

δ = soil-pile friction angle ≈ (0.5 − 0.7)φ '


y Hence the total downward drag force, Qn on a pil e is
Hf
Qn = ∫ { pK ' γ 'f tan δ ⋅ z}dz
0

1
= pK ' γ 'f H 2f tan δ
2
where p = perimeter of pile.

H f = height of fill.

SNU Geotechnical and Geoenvironmental Engineering Lab.


Geotechnical Engineering 133

ii) Granular soil fill over clay

z The negative skin friction on the pile exists from z=0 to z=L₁as shown
below.

SNU Geotechnical and Geoenvironmental Engineering Lab.


Geotechnical Engineering 134

z Neutral depth L1 : up to L1, the negative skin friction is activated.

( L − H f ) L − H f γ 'f H f 2γ 'f H f
L1 = [ + ]−
L1 2 γ' γ'

For end bearing piles, the neutral depth may be assumed to be located
at pile tip (L1=L-Hf).

L1 L1
Qn = ∫ pf n dz = ∫ pK ' (γ 'f H f + γ ' z ) tan δdz
0 0

1 2
= ( pK ' γ ' H f tan δ ) L1 + L1 pK ' γ ' tan δ
2

z Applying loads = Q pile cap + Qn

z Resistance = Qs + Q p (Qs not for fully embedded length of pile but only

for length where upward frictional resistance is


mobilized.)
Qs + Q p
z Qallow = ≥ Q pile cap + Qn
FS

z To reduce downdrag
1. Predrilled hole, then install pile (reduce K).
2. Coat the pile with bitumen(reducing δ ).

SNU Geotechnical and Geoenvironmental Engineering Lab.


Geotechnical Engineering 135

13) Drilled Piers and Caissons

i) Drilled Piers (Drilled Shafts)


z Cast-in-place pile with D>75cm

z Advantages

z Disadvantage

SNU Geotechnical and Geoenvironmental Engineering Lab.


Geotechnical Engineering 136

z Construction Procedures
1. Dry method of construction (Stiff soils above the water table).
a) initial drilling
b) starting concrete pour
c) placing rebar cage
d) completed shaft

SNU Geotechnical and Geoenvironmental Engineering Lab.


Geotechnical Engineering 137

2. Casing method of construction


a) initial drilling
b) drilling with slurry
c) introducing casing
d) casing is sealed and slurry is being removed from interior of casing

SNU Geotechnical and Geoenvironmental Engineering Lab.


Geotechnical Engineering 138

e) drilling below casing


f) underreaming
g) pouring concrete and removing casing
h) completing shaft
* Note : Either all casing or partial casing can be used.

SNU Geotechnical and Geoenvironmental Engineering Lab.


Geotechnical Engineering 139

3. Wet method of construction.


a) drilling to full depth with slurry (and slurry is removed)
b) placing rebar cage
c) pouring concrete
d) completing shaft

SNU Geotechnical and Geoenvironmental Engineering Lab.


Geotechnical Engineering 140

z Analytical approach to predict capacity


: Same procedures as driven piles
(but different values of fs are used)

ii) Caissons
z Substructure element used at wet construction sites such as rivers, lakes
and docks

z Types of Caissons
1) Open caissons

SNU Geotechnical and Geoenvironmental Engineering Lab.


Geotechnical Engineering 141

2) Box caissons

Should be leveled

SNU Geotechnical and Geoenvironmental Engineering Lab.


Geotechnical Engineering 142

3) Pneumatic caissons

SNU Geotechnical and Geoenvironmental Engineering Lab.

You might also like