Professional Documents
Culture Documents
RECENT CASES
Arbitration - Consolidation of Proceedings
Melville Homes PtyLtd v Prime Ceramics Services PtyLtd Act. In various sections, the expressions "a party", "the
and500 Collins Street PtyLtd, Supreme Court ofVictoria, parties", "any parties", "any of the parties", and "all of the
Southwell J., 12 July, 1990. parties" appear. The use of the different expressions
suggests that the use of the word "all" in section 26 was
500 Collins Street Pty Ltd ("the proprietor") was the significant. Significance had been attached to the use of
owner of a building under construction at that address. the word by SmartJ. inKB HutchersonPtyLtdvJanango
Melville Homes Pty Ltd ("the builder') was constructing Pty Ltd (unreported) 25 May 1988, when considering the
the building. Prime Ceramic Services Pty Ltd ("the corresponding New South Wales Act.
subcontractor") was carrying out certain tiling work under SouthwellJ. referred toRV Parsons [1983] 2 VR499
a contract with the builder. in which the Full Court of the Victorian Supreme Court
There was an arbitration clause in the agreement held that State Courts should give a consistent meaning to
between the proprietor and the builder and a further clause a Commonwealth Statute. By analogy, said Southwell J.,
in the agreement between the builder and the subcontrac- the courts should attempt to give consistent interpretations
tor. A dispute had arisen in relation to the tiling works. to common state legislation.
The builder submitted that the two arbitrations, that is the Having regard to the above comments, His Honour
arbitration under the head contract and the arbitration concluded that for the court to make an order for consoli-
under the subcontract, should be consolidated pursuant to dation pursuant to section 26, it was necessary that the
section 26 of the Commercial Arbitration Act 1984 (Vic). application be made by all of the parties.
The proprietor opposed the application. The proprietor - Phillip Greenham, Partner, Minter Ellison,
submitted that section 26 required an application for con- Solicitors, Melbourne.
solidation to be made to the court by all of the parties and
not some of the parties. Editorial Note:
The court examined a number of sections in the The problem of consolidation is discussed in Issue #6 of
Commercial Arbitration Act and noted that different ex- the Newsletter at page 3. See Issue #12 at page 48 for a
pressions in relation to parties appeared throughout the report on KB Hutcherson v Janango.
the behaviour expected of arbitrators. Their func- will not be contributing to any of the cost ordered against
tion is to stand between the parties, hearing submis- the arbitrator. Further, that Form 3 ofPractice Note 3Ahas
sions and adjudicating if required. Arbitrators are been redrafted to protect the Institute and its arbitrators
not mediators. It is not their function to deal against the possibility ofsuch an order for costs. To protect
directly with disputants where legal representa- the Institute and individual arbitrators, the Institute has
tives are retained. It must not be done. A further suggested that arbitrators should not accept nomination
matter of disquiet is that, despite being requested, until the parties have agreed to the inclusion of the dis-
the arbitrator refused to give a written undertaking claimercontained in paragraph 6, which is in the following
that he would abide by the orders of this court. terms:
Compounded to that lapse is an even more serious "6 Disclaimer
breach of etiquette and conduct and that is the Do parties agree that neither the nominating bodies
arbitrator wrote directly to the Judge, despite being (if any) nor any officer, member, servant or agent
given the opportunity to be heard or joined as a thereof, nor the arbitrator(s) shall be liable to any
party by the plaintiff. I perceive in some of the party for any act or omission in connection with the
arbitrator's conversation irritation with legal forms arbitration save that the arbitrator(s) shall be liable
and solemnities and a desire to despatch the arbitra- for fraud in respect of anything done or omitted to
tion. Both those expressions of view may be be done in that capacity Yes/No."
laudable in many circumstances, but in this case
they were misplaced. An arbitrator must present It is also understood that the Institute is likely to
himself to the parties as an unbiased adjudicator. publish a disclaimer in future with its lists of arbitrators,
This he failed to do. On one occasion he arrived at conciliators and mediators.
the building site in dispute in a vehicle driven by an Other nominating organisations should pay heed to
officer of the first-named defendant. That journey this case. Whilst Nathan J's comments "in passing" about
was over twenty kilometres, took some time and the nominating organisation standing behind its nominee
had been arranged directly between the arbitrator were of no effect in this case, one can imagine that they
and the first defendant. This is an inexcusable could encourage action to join a nominating organisation
alignment of the arbitrator with one party and as a co-defendant in future proceedings. If this were to
cannot be tolerated. The law in Victoria is clear: an occur, the sentiment expressed by Nathan J. might then
adjudicator in the position of an arbitrator must have effect. Yet further reason for industry organisations
isolate himself in any social or convivial context to vacate nomination and leave it to neutral disputes or-
with the 'disputants (see The Queen v The Magis- ganisations such as the Institute of Arbitrator~,Australia or
trates at Lilydale, Ex Parte Ciccone, [1973] VR the Australian Commercial Disputes Centre.
127 which was explicitly affirmed in Re J>R.L. - John Tyrril.
(1986) 161 CLR, 342.) ..."