You are on page 1of 296

GUIDE

FOR
BUILDING AND
CLASSING

HIGH-SPEED CRAFT

OCTOBER 2001

American Bureau of Shipping


Incorporated by Act of the Legislature of
the State of New York 1862

Copyright  2001
American Bureau of Shipping
ABS Plaza
16855 Northchase Drive
Houston, TX 77060 USA
Foreword

This Guide has been prepared to update the requirements of the ABS “Guide for Building and Classing
High-Speed Craft October 1990”. An attempt has been made to update the Guide to incorporate current
design practice and various types of hull design, e.g. catamarans, hydrofoils. The new Section 5/1 “Craft
Intended to Carry Passengers” has also been developed in response to the needs from high-speed passenger
craft industry and operators.

The Guide specifies machinery requirements and hull construction requirements based on three different
materials, namely, steel, aluminum alloys and fiber reinforced plastics (FRP) which are considered to be
broadly applied in the design of high-speed craft. The construction requirements are contained in a single
booklet while the material requirements are published in two separate booklets, “Rule Requirements for
Materials and Welding Part 2” for steel and “Requirements for Materials and Welding Part 2 - Aluminum
and Fiber Reinforced Plastics (FRP)”. These two booklets specify the requirements for these materials as
applicable, welding (metals) and connections (FRP).

This Guide becomes effective immediately after publication in February 1997 and supersedes the 1990
version mentioned above.

Foreword to the 2001 Edition

This edition of the Guide has been published in October 2001, and the following changes have been made
from the original version:

− Part 1, Section 3, titled “Surveys After Construction” has been removed as a consequence of the
consolidated version of the ABS Rule Requirements for Survey After Construction – Part 7, 2001
being issued effective 1 January 2001. *

− The latest editions of the ABS Rule Requirements for Materials and Welding – Part 2 are applicable.

− Corrigenda/editorial items have been incorporated into the current edition.

* The PDF file of this booklet is available for download on the ABS website at:
www.eagle.org/rules/downloads.html.
GUIDE FOR BUILDING AND CLASSING
HIGH-SPEED CRAFT

Contents

PART

1 Classification and Testing

2 Rule Requirements for Materials and Welding - Chapters


1, 2, 3 and 4 (published as a separate booklet, 2001*)

Requirements for Materials and Welding, - Aluminum,


- Fiber Reinforced Plastics (FRP) - Sections 4 and 5
(published as a separate booklet, 1997)

3 Hull Construction and Equipment

4 Machinery Equipment and Systems

5 Specialized Craft and Services


* The PDF file of this booklet is available for downloading on the ABS Website at
www.eagle.org/rules/downloads.html.
PART 1
Contents
Classification and Testing

SECTION
1 Scope and Conditions of Classification
2 Testing and Trials During Construction - Hull
PART 1 SECTION 1

Scope and Conditions of Classification


1/1.1 Classification c The Bureau will release certain information to
the craft’s hull underwriters and P&I clubs for
1/1.1.1 Process underwriting purposes. Such information includes
The Classification process consists of a) the text of overdue conditions of classification, survey
development of rules, guides, standards and other due dates, and certificate expiration dates. The
criteria for the design and construction of marine craft Owners will be advised of any request and/or release
and structures, for materials, equipment and of information. In the case of overdue conditions of
machinery, b) the review of design and survey during classification, the Owners will be given the
and after construction to verify compliance with such opportunity to verify the accuracy of the information
rules, guides, standards or other criteria, c) the prior to release.
assignment and registration of class when such
compliance has been verified, and d) the issuance of a 1/1.1.3 Representations as to Classification
renewable Classification certificate, with annual Classification is a representation by the Bureau as to
endorsements, valid for five years. the structural and mechanical fitness for a particular
The Rules, Guides, and standards are developed use or service in accordance with its Rules, Guides
by Bureau staff and passed upon by committees made and standards. The Rules of the American Bureau of
up of naval architects, marine engineers, shipbuilders, Shipping are not meant as a substitute for the
engine builders, steel makers and by other technical, independent judgment of professional designers,
operating and scientific personnel associated with the naval architects and marine engineers nor as a
worldwide maritime industry. Theoretical research substitute for the quality control procedures of
and development, established engineering disciplines, shipbuilders, engine builders, steel makers, suppliers,
as well as satisfactory service experience are utilized manufacturers and sellers of marine vessels,
in their development and promulgation. The Bureau materials, machinery or equipment. The Bureau,
and its committees can act only upon such theoretical being a technical society, can only act through
and practical considerations in developing Rules, Surveyors or others who are believed by it to be
Guides and standards. skilled and competent.
For classification, the craft are to comply with The Bureau represents solely to the vessel Owner
both the hull and the machinery requirements of the or client of the Bureau that when assigning class it
Rules and Guides. will use due diligence in the development of Rules,
Guides and standards, and in using normally applied
1/1.1.2 Certificates and Reports testing standards, procedures and techniques as called
a Plan review and surveys during and after for by the Rules, Guides, standards or other criteria of
construction are conducted by the Bureau to verify to the Bureau for the purpose of assigning and
itself and its committees that a craft, structure, item of maintaining class. The Bureau further represents to
material, equipment or machinery is in compliance the vessel Owner or other client of the Bureau that its
with the Rules, Guides, standards or other criteria of certificates and reports evidence compliance only
the Bureau and to the satisfaction of the attending with one or more of the Rules, Guides, standards or
surveyor. All reports and certificates are issued other criteria of the Bureau in accordance with the
solely for the use of the Bureau, its committees, its terms of such certificate or report. Under no
clients and other authorized entities. circumstances whatsoever are these representations to
b The Bureau will release information from be deemed to relate to any third party.
reports and certificates to the Port State to assist in
rectification of deficiencies during port state control 1/1.1.4 Scope of Classification
intervention. Such information includes text of Nothing contained in any certificate or report is to be
conditions of classification, survey due dates, and deemed to relieve any designer, builder, Owner,
certificate expiration dates. The Owner will be manufacturer, seller, supplier repairer, operator, other
advised of any request and/or release of information. entity or person of any warranty express or implied.
Any certificate or report evidences compliance only
with one or more of the Rules, Guides, standards or
other criteria of American Bureau of Shipping and is

PART 1 SECTION 1|1 Scope and Conditions of Classification


issued solely for the use of the Bureau, its 1/1.2.3 Special Notations
committees, its clients or other authorized entities. If the survey requirements related to maintenance of
Nothing contained in any certificate, report, plan or special notations are not carried out as required, the
document review or approval is to be deemed to be in suspension or cancellation may be limited to those
any way a representation or statement beyond those special notations only.
contained in 1/1.1.3. The validity, applicability and
interpretation of any certificate, report, plan or 1/1.2.4 Suspension of Class Includes:
document review or approval are governed by the a Class is suspended for any use, operation,
Rules, Guides and standards of American Bureau of loading condition or other application of any craft for
Shipping who shall remain the sole judge thereof. The which it has not been approved and which affects or
Bureau is not responsible for the consequences may affect classification or the structural integrity,
arising from the use by other parties of the Rules, quality or fitness for a particular use or service.
Guides, standards or criteria of the American Bureau b If the periodical surveys required for
of Shipping, without review, plan approval and maintenance of class are not carried out by the due
survey by the Bureau. date and no Rule allowed extension has been granted,
The term "approved" shall be interpreted to mean class will be suspended.
that the plans, reports or documents have been c If recommendations issued by the Surveyor are
reviewed for compliance with one or more of the not carried out within their due dates, class will be
Rules, Guides, standards, or other criteria of the suspended.
Bureau. d Class is suspended for any damage, failure,
The Guide is published on the understanding that deterioration or repair that has not been completed as
responsibility for stability and trim, for reasonable recommended.
handling and loading, as well as for avoidance of e If proposed repairs as referred to in 1/3.1.1
distributions of weight which are likely to set up have not been submitted to the Bureau and agreed
abnormally severe stresses in vessels does not rest upon prior to commencement, class may be
upon the Committee. Speed is to be appropriately suspended.
reduced with increasing sea conditions in order to
limit dynamic hull responses. 1/1.2.5 Cancellation of Class
a If the circumstances leading to suspension of
1/1.2 Suspension and Cancellation of Class class are not corrected within the time specified, the
vessel's class will be canceled.
1/1.2.1 Termination of Classification b A vessel's class is canceled immediately when
The continuance of the Classification of any craft is a vessel proceeds to sea without having completed
conditional upon the Guide requirements for recommendations which were required to be dealt
periodical, damage and other surveys being duly with before leaving port.
carried out. The Committee reserves the right to
reconsider, withhold, suspend, or cancel the class of 1/1.3 Classification Symbols
any craft or any part of the machinery for
noncompliance with the Guide, for defects reported 1/1.3.1 Class Notation
by the Surveyors which have not been rectified in Craft which have been built to the satisfaction of the
accordance with their recommendations, or for Surveyors to the Bureau to the full requirements of
nonpayment of fees which are due on account of this Guide, or equivalent, where approved by the
Classification, Statutory and Cargo Gear Surveys. Committee for unrestricted ocean service, will be
Suspension or cancellation of class may take effect classed and distinguished in the Record by the
immediately or after a specified period of time. symbols !A1 HSC !AMS indicating compliance
with the hull and machinery requirements of the
1/1.2.2 Notice of Surveys Guide.
It is the responsibility of the Owner to ensure that all
surveys necessary for the maintenance of class are 1/1.3.2 Special Requirements
carried out at the proper time. The Bureau will give Craft which have been built to the satisfaction of the
proper notice to an Owner of upcoming surveys. This Surveyors to the Bureau to the requirements as
may be done by means of a letter, a quarterly vessel contained in this Guide for special types of craft and
status or other communication. The non-receipt of which are approved by the Committee for restricted
such notice, however, does not absolve the Owner service will be classed and distinguished in the
from his responsibility to comply with survey Record by the symbols !A1 HSC followed by the
requirements for maintenance of class. appropriate notation, namely Passenger Craft (A),
Passenger Craft (B), Ro/Ro Passenger Craft (A),
Ro/Ro Passenger Craft (B), Cargo Craft; the (A)

PART 1 SECTION 1|2 Scope and Conditions of Classification


and (B) indicate a craft defined as a Category A 1/1.3.6 Equipment Symbol
Passenger Craft, a Category B Passenger Craft The symbol placed after the symbols of
respectively in accordance with the International classification, thus; !Al , will signify that the
Code of Safety for High Speed Craft. The notation equipment of anchors and cables of the craft is in
“Cargo Craft” defines a vessel that is certified in compliance with the requirements of the Guide or
accordance with the IMO International Code of with the requirements corresponding to the service
Safety for High Speed Craft. limitation noted in the craft’s classification, which
have been specially approved for the limited service.
1/1.3.3 Special Purpose Craft
Special purpose craft, which have been built to the 1/1.3.7 !AMS Symbols
satisfaction of the Surveyors to the Bureau to Machinery constructed and installed to the
arrangements and scantlings approved for the satisfaction of the Surveyors to the Bureau to the full
particular purpose, where approved by the Committee requirements of the Guide, when found satisfactory
for the particular service will be classed and after trial and approved by the Committee, will be
distinguished in the Record by the symbols !A1 classed and distinguished in the Record by the
HSC followed by a description of the service for symbols !AMS.
which special modifications to the Rules have been
approved, e.g. Government Service etc. 1/1.3.8 AMS Symbols
Machinery which has not been constructed and
1/1.3.4 Service Limitations installed under survey to this Bureau, but which is
a Geographical Limitation Craft which have submitted for classification, will be subjected to a
been built to the satisfaction of the Surveyors to the special classification survey. Where found
Bureau to special modified requirements for a satisfactory and thereafter approved by the
restricted service, where approved by the Committee Committee, the machinery will be classed and
for that particular service, will be classed and distinguished in the Record by the symbols AMS.
distinguished in the Record by the symbols and The symbol ! signifying the survey during
notations as described in 1/1.3.1, 1/1.3.2 and 1/1.3.3 construction will be omitted.
above, but the symbols and notations will either be
followed by or have included in them the appropriate 1/1.3.9 ACCU or ABCU Symbols
restricted service, e.g., Gulf of Mexico Service, The automatic and remote-control systems are to be
Philippines Inter-Island Service, Coastal Service in accordance with the applicable requirements of
Less than 25 Miles, Harbor Service, etc. Section 4/11.
b Significant Wave Height Craft which have
been designed and built for limited service operation 1/1.5 Application
with a significant wave height less than 4 m (13 ft)
will be distinguished in the Record by the special 1/1.5.1 Application Limits
comment. Specific significant wave height to be used This Guide is applicable to high speed craft for
in the design is to be clearly indicated in operating commercial or governmental use constructed of steel,
manual for restriction of service.
aluminum, or FRP and having V / L not less than
1/1.3.5 Craft not Built under Survey 2.36 (1.30) where L is as defined in 3/1.1 and V is as
Craft not built under survey to this Bureau, but which defined in 3/8.1.1. Applicable craft type and length
are submitted for classification, will be subjected to a are as follows:
special classification survey. Where found
satisfactory and thereafter approved by the Vessel Type Applicable Length
Committee, they will be classed and distinguished in Mono-hull < 130 m (427 ft.)
the Record by the symbols and special notations as Multi-hull < 100 m (328 ft.)
described in 1/1.3.1 to 1/1.3.4 above, but the symbol Surface Effects Ship (SES) < 90 m (295 ft.)
! signifying the survey during construction will be Hydro Foil < 60 m (197 ft.)
omitted.

PART 1 SECTION 1|3 Scope and Conditions of Classification


case of novel designs; where structural displacement
is expected to influence (more than usually) structural
response; where hull propulsion or steering system
load transmission in the hull needs to be specially
addressed; to demonstrate the efficiency of novel
connection details on hull strength; etc.
For types of behavior or loading effects which are
not within the scope of classification of the vessel to
be classed, the Bureau will upon request provide
advice on what it feels constitutes an appropriate
analysis. Such analyses include those for vibration
and docking arrangements.
c Analysis Scope and Documentation The
The criteria contained in this Guide are meant to be
scope, details and manner of documenting the
applicable to those features that are permanent in
analyses are to be agreed with the Bureau before the
nature and can be verified by plan review,
analyses are done.
calculation, physical survey or other appropriate
means. Any statement in this Guide regarding any
1/1.5.3 Design by Testing
other feature is to be considered as guidance to the
Where it is intended to use physical testing (e.g. tank
designer, builder, owner, et al.
model testing, etc.) as the primary or supplementary
basis of design, the details of such testing and the
1/1.5.2 Direct Analyses
procedures to be followed to establish design values
a Required Analyses Direct analyses are
are to be agreed to by the Bureau, prior to the
required in particular cases to demonstrate the
performance of the testing.
adequacy of the structural design. When the length of
craft constructed of steel or aluminum exceeds 61m
1/1.5.4 Alternatives
(200 feet), when the length of craft constructed of
a General The Committee is at all times ready to
FRP exceeds 50m (164 feet) or when the operating
consider alternative arrangements and scantlings
speed (V) exceeds 50 knots, the design of the main
which can be shown, through either satisfactory
supporting members of the hull (e.g. web frames and
service experience or a systematic analysis based on
deep girders supporting stiffened plating) is to be
sound engineering principles, to meet the overall
demonstrated by the performance of suitable direct
safety and strength standards of the Guide.
analyses.
b National Standards The Committee will
Similarly for vessel designs having the length or
consider special arrangements or details of hull,
speed values exceeding the mentioned ones, a
equipment or machinery which can be shown to
suitable direct analysis is to be performed to
comply with standards recognized in the country in
demonstrate the adequacy of the hull girder strength.
which the craft is registered or built, provided they
(See also 3/6.1.1b and 3/6.3.1.)
are not less effective.
The direct analyses are to be performed using an
c Other Rules The Committee will consider hull,
acceptable finite element method computer program.
equipment or machinery built to the satisfaction of the
The extent of, and boundary conditions applied to, Surveyors to the Bureau in accordance with the plans
the analytical model(s) are to be appropriate to reflect that have been approved to the Rules of another
adequately the behavior of the structure. The loads to recognized classification society with verification of
be applied to the structural model are to be based on compliance by the Bureau. A notation will be entered
consideration of the design values; deck cargo and in the Record indicating that classification has
similar internal loads in the hull (accounting for incorporated the provisions of this subparagraph.
dynamic effects as appropriate); the external pressure Submission of plans is to be in accordance with
loads (see 3/8) and distribution specified in this 1/1.11.
Guide; and appropriate wave induced hull girder
bending moment and shear force effects. (For 1/1.5.5 Novel Features
example see 3/6.1.) Craft which have novel features of design in respect
b Supplementary Analyses In addition to the of the hull, machinery or equipment to which the
direct analyses required in a above, the Bureau may provisions of this Guide are not directly applicable
require the performance of additional direct analyses may be classed, when approved by the Committee, on
to demonstrate and document the adequacy of other the basis that this Guide insofar as applicable has
features of the hull structural design, which are been complied with and that special consideration has
been given to the novel features based on the best
considered to be within the scope of classification.
information available at the time.
The need to provide such analyses can arise: in the

PART 1 SECTION 1|4 Scope and Conditions of Classification


1/1.5.6 Effective Date of Rule Change 1/1.7.3 International Code of Safety for High
a Six Month Rule Changes to the Guide are to Speed Craft
become effective on the date specified by the Bureau. Where authorized by the Administration of a country
In general, the effective date is not less than six signatory to the SOLAS convention, and upon request
months from the date of their publication. However, of the Owners of an existing craft or a craft under
the Bureau may bring into force individual changes construction, the Bureau will review plans and survey
before that date if necessary or appropriate. the craft for compliance with the provisions of the
b Implementation of Rule Changes In general, Code and certify thereto in the manner prescribed in
the Code. Builders and owners are advised that
until the effective date, plan approval for designs will
Administrations may have special interpretations of
follow prior practice unless review under the latest
the requirements as given in the International Code of
Guide is specifically requested by the party signatory Safety for High Speed Craft and they should contact
to the application for classification. If one or more the Administration as to this at an early stage in the
vessels are to be constructed from plans previously design.
approved, no retroactive application of the latest
Guide changes will be required except as may be 1/1.7.4 Governmental Regulations
necessary or appropriate for all contemplated Where authorized by a government agency and upon
construction. request of the owners of a classed craft or one
intended to be classed, the Bureau will survey and
1/1.7 Regulations certify a new or existing craft for compliance with
particular regulations of that government on their
1/1.7.1 General particular regulations of that government on their
While the Guide covers the requirements for the behalf.
classification of new craft, the attention of Owners,
designers, and builders is directed to the regulations 1/1.9 IACS Audit
of international, governmental and other authorities The International Association of Classification
dealing with those requirements in addition to or over Societies (IACS) conducts audits of processes
and above the classification requirements. followed by all its member societies to assess the
degree of compliance with the IACS Quality System
1/1.7.2 International Conventions or Codes Certification Scheme requirements. For this purpose,
Where authorized by the Administration of a country auditors from IACS may accompany ABS personnel
signatory thereto and upon request of the Owners of a at any stage of the classification or statutory work
classed craft or one intended to be classed, the which may necessitate the auditors having access to
Bureau will survey a new or existing craft for the craft or access to the premises of the manufacturer
compliance with the provisions of International or shipbuilder.
Conventions or Codes including the following, and In such instances, prior authorization for the
certify thereto in the manner prescribed in the auditor's access will be sought by the local ABS
Convention or Code. office.

International Convention on Load Lines, 1966. 1/1.11 Submission of Plans


International Convention for the Safety of Life at Sea, Hull and machinery plans, as required below, are to
1974, as amended. be submitted to the Bureau for review and approval.
International Code for Safety for High Speed Craft Plans from designers and shipbuilders should
(HSC Code). generally be submitted in triplicate, one copy to be
International Convention on Tonnage Measurement returned to those making the submission, one copy
of Ships, 1969. for the use of the Surveyor where the craft is being
International Convention for the Prevention of built, and one copy to be retained in the ABS
Pollution from Ships, 1973/78, as amended. Technical office for record. Manufacturers plans are
to be submitted in quadruplicate where construction is
to be carried out at a plant other than that of the
shipbuilder. However, additional copies may be
required when the required attendance of the
Surveyor is anticipated at more than one location. All
plan submissions originating from manufacturers are
understood to be made with the cognizance of the
shipbuilder. A fee may be charged for the review of
plans for which there is no contract of classification.

PART 1 SECTION 1|5 Scope and Conditions of Classification


1/1.11.1 Hull Plans 1/1.11.3 Additional Plans
Plans showing the arrangements, scantlings, details of Where certification under 1/1.7.2 or 1/1.7.3 is
principal parts of the hull structure, and welding requested, submission of additional plans and
details of each craft to be built under survey are to be calculations may be required.
submitted and approved before construction is
commenced. These plans are to include such 1/1.11.4 FRP Building Process Description and
particulars as the design draft, displacement and Quality Manual
design speed. Where provision is to be made for any For FRP structure, the builder is to submit a process
special type of cargo or for any exceptional description of the construction before the construction
conditions of loading, particulars of the weights and commences. Details of the information to be
of their distribution are also to be given. In general submitted are given in Section 2/5.
the following plans are to be submitted for review or
reference. 1/1.13 Conditions for Surveys after Construction

Anchor handling arrangements 1/1.13.1 Damage, Failure and Repair


Bottom construction, floors, girders, inner bottom a Examination and Repair Damage, failure,
plating, etc. deterioration or repair to hull, machinery or
Bow framing equipment, which affects or may affect classification,
Capacity plan is to be submitted by the Owners or their
Craft Specifications representatives for examination by a Surveyor at first
Damage Control plan opportunity. All repairs found necessary by the
Deck plans Surveyor are to be carried out to the Surveyor’s
Framing plan satisfaction.
General Arrangement b Repairs Where repairs to hull, machinery or
Hatches and hatch-closing arrangements equipment, which affect or may affect classification,
Hull port and framing details are planned in advance to be carried out, a complete
Lines and body plan repair procedure including the extent of proposed
Machinery casings, engine and main auxiliary repair and the need for Surveyor's attendance is to be
foundations submitted to and agreed upon by the Bureau
Midship section reasonably in advance. Failure to notify the Bureau,
Miscellaneous nontight bulkheads which are used as in advance of the repairs, may result in suspension of
structural supports the craft’s classification until such time as the repair
Operating manual and where applicable, maintenance is redone or evidence submitted to satisfy the
manual (see 3/6.9) Surveyor that the repair was properly carried out.
Pillars and girders Note: The above applies also to repairs during voyage.
Scantling profile and decks The above is not intended to include maintenance
Shaft struts and overhaul to hull, machinery and equipment in
Shaft tunnels accordance with the recommended manufacturer's
Shell expansion procedures and established marine practice and which
Stem does not require Bureau approval; however, any
Stern frame and rudder repair as a result of such maintenance and overhauls
Stern framing which affects or may affect classification is to be
Superstructure and deckhouses, and their closing noted in the ship's log and submitted to the Surveyor
arrangements as required by 1/1.11.1a.
Through-hull penetrations for thrusters, stabilizers, c Representation Nothing contained in this
exhausts, and sea valves section or in a rule or regulation of any government
Ventilation systems on weather decks or other administration, or the issuance of any report
Watertight and deep-tank bulkheads or certificate pursuant to this section or such a rule or
Watertight doors and framing regulation, is to be deemed to enlarge upon the
Weathertight doors, framing, and sill heights representations expressed in 1/1.1.1 through 1/1.1.4
Welding Schedule and details, bonding details (FRP) hereof and the issuance and use of any such reports or
Window and framing details certificates are to be governed in all respects by
1/1.1.1 through 1/1.1.4 hereof.
1/1.11.2 Machinery Plans and Data
Plans and data required to be submitted to the Bureau
for review and approval are listed in 4/1.11.

PART 1 SECTION 1|6 Scope and Conditions of Classification


1/1.13.2 Notification and Availability for Survey 1/1.17.2 Surveyors
The Surveyors are to have access to classed craft at In case of disagreement between the Owners or
all reasonable times. For the purpose of Surveyor builders and the Surveyors regarding the material,
Monitoring, monitoring Surveyors shall also have workmanship, extent of repairs, or application of the
access to classed craft at all reasonable times. Such Guide relating to any craft classed or proposed to be
access may include attendance at the same time as the classed by this Bureau, an appeal may be made in
assigned Surveyor or during a subsequent visit writing to the Committee, who will order a special
without the assigned Surveyor. The Owners or their survey to be held. Should the opinion of the Surveyor
representatives are to notify the Surveyors on all be confirmed, the expense of this special survey is to
occasions when a craft can be examined in dry dock be paid by the party appealing.
or on a slipway.
The Surveyors are to undertake all surveys on 1/1.19 Limitation of Liability
classed craft upon request, with adequate notification, The combined liability of American Bureau of
of the Owners or their representatives and are to Shipping, its committees, officers, employees, agents,
report thereon to the Committee. Should the or subcontractors for any loss, claim, or damage
Surveyors find occasion during any survey, to arising from its negligent performance or
recommend repairs or further examination, nonperformance of any of its services or from breach
notification is to be given immediately to the Owners of any implied or express warranty of workmanlike
or their representatives in order that appropriate performance in connection with those services, or
action may be taken. The Surveyors are to avail from any other reason, to any person, corporation,
themselves for every convenient opportunity for partnership, business entity, sovereign, country or
carrying out periodical surveys in conjunction with nation, will be limited to the greater of a) $100,000 or
surveys of damages and repairs in order to avoid b) an amount equal to ten times the sum actually paid
duplication of work. for the services alleged to be deficient.
The limitation of liability may be increased up to
1/1.13.3 Attendance at Port State Request an amount twenty-five times that sum paid for
It is recognized that Port State authorities legally may services upon receipt of Client's written request at or
have access to a craft. In cooperation with Port before the time of performance of services and upon
States, ABS Surveyors will attend on board a classed payment by Client of an additional fee of $10.00 for
craft when so requested by a Port State, and upon every $1,000.00 in the limitation.
concurrence by the craft's master will carry out a
survey in order to facilitate the rectification of
reported deficiencies or other discrepancies that
affect or may affect classification. ABS Surveyors
will also cooperate with Port States by providing
inspectors with background information, if requested.
Such information includes text of conditions of class,
survey due dates, and certificate expiration dates.
Where appropriate, the vessel's flag state will be
notified of such attendance and survey.

1/1.15 Fees
Fees in accordance with normal ABS practice will be
charged for all services rendered by the Bureau.
Expenses incurred by the Bureau in connections with
these services will be charged in addition to the fees.
Fees and expenses will be billed to the party
requesting that particular service.

1/1.17 Disagreement

1/1.17.1 Guide
Any disagreement regarding either the proper
interpretation of the Guide, Rules, or translation of
this Guide from the English language edition, is to be
referred to the Bureau for resolution.

PART 1 SECTION 1|7 Scope and Conditions of Classification


PART 1 SECTION 2

Testing and Trials During Construction-Hull


1/2.1 Tank, Bulkhead and Rudder Tightness 1/2.1.4 Hose Testing
Testing Hose testing is to be carried out under simultaneous
inspection of both sides of the joint. The pressure in
1/2.1.1 General the hose is not to be less than 2.06 bar (2.1 kgf/cm2,
After all hatches and watertight doors are installed, 30 psi).
penetrations including pipe connections are fitted and
before cement work or ceiling is applied over joints, 1/2.2 Tank Tests for Structural Adequacy
all tanks and watertight bulkheads or flats are to be In order to demonstrate the structural adequacy,
tested and proven tight. Refer to Table 1/2.1 for representative hydrostatic testing of tanks may be
specific test requirements. Close visual examination required in connection with the approval of the
combined with non-destructive testing may be design. In general this would include at least one tank
accepted in certain areas where specially approved, as of each type of new or unusual vessel or tank design.
an alternative to hose testing.
1/2.3 Anchor Windlass Trials
1/2.1.2 Hydrostatic Testing Each anchor windlass is to be tested under normal
Unless air testing has been approved as an alternative, working conditions to demonstrate satisfactory
tanks are to be tested with a head of water to the operation. Each required anchor handling unit,
overflow or to the highest point to which the contents independently, is to be tested for braking, clutch
may rise under service conditions, whichever is functioning, power lowering, hoisting, and proper
higher. This may be carried out before or after the riding of the chain through the hawsepipe, over the
vessel is launched. Special coatings may be applied wildcat (chain wheel), through the chain pipe, and
before hydrostatic testing provided all welding at stowing in the chain locker. Also, it is to be
joints and penetrations is visually examined to the demonstrated that the windlass is capable of lifting
satisfaction of the Surveyor before special coating is each anchor with 82.5m (45 fathoms) length of chain
applied. submerged and hanging free. Where the available
Sliding watertight doors are to be tested with a water depth is insufficient, the proposed test method
head of water equivalent to the height of the bulkhead will be specially considered.
deck or freeboard deck at the maker’s works.
1/2.4 Bilge System Trials
1/2.1.3 Air Testing All elements of the bilge system are to be tested to
Where permitted in Table 1/2.1, air testing or demonstrate satisfactory pumping operation,
combined air testing and hydrostatic testing by an including emergency suctions and all controls. Upon
approved procedure may be accepted unless the completion of the trials, the bilge strainers are to be
specified test is deemed necessary by the Surveyor. opened, cleaned and closed up in good order.
Where air testing is adopted, all boundary welds,
erection joints, and penetrations including pipe 1/2.5 Steering Trials
connections are to be examined under the approved Refer to Section 4/8.8.2 for the technical details of
test procedure with a suitable leak indicator solution the steering trials.
prior to the application of special coatings. Air test
pressure differential should normally be 0.137 bar 1/2.6 Construction Welding and Fabrication
(0.14 kgf/cm2, 2 psi). Means are to be provided to For surveys of hull construction welding and
prevent accidental overpressuring of tanks during fabrication, refer to Section 2/3 and the ABS "Rules
testing. Air-pressure drop testing, i.e. checking for for Nondestructive Inspection of Hull Welds".
leaks by monitoring drop in pressure, is not an
acceptable substitute for required hydrostatic or 1/2.7 Hull Castings and Forgings
air/soap testing. For surveys in connection with the manufacture and
testing of hull castings and forgings, refer to Section
2/1.

PART 1 SECTION 2|1 Testing and Trials During Construction-Hull


1/2.8 Piping
For surveys in connection with the manufacture and
testing of piping, refer to Section 4/6.

TABLE 1/2.1
Initial Tank, Bulkhead and
Rudder Tightness Testing
Requirements
Item Test Method

Double Bottom Tanks Hydro Test *


Deep Tanks Hydro Test *
Forepeak & Afterpeak Tanks Hydro Test *
Ballast Tanks, Cargo Craft Hydro Test *
Forepeak Dry Space Hose Test *
Duct Keels Hydro Test *
Shaft Tunnels (clear of deep Hose Test
tanks)
Chain Lockers (aft of fore peak To be filled with water
bulkhead)
Hawse Pipes Hose Test
Weathertight Hatchcovers & Hose Test
Water/Weathertight Closing
Appliances
Watertight Bulkheads & Flats Hose Test *
Void Space Boundaries Required Hose Test *
to be Watertight
Double Plate Rudders and Skegs Hydro Test *

Note: Air test or combined air and hydrostatic testing may be


accepted for those items marked (*) under the conditions
specified in 1/2.1.3. Such test may also be considered for
other items where hydrotest is impracticable.

PART 1 SECTION 2|2 Testing and Trials During Construction-Hull


PART 2
Materials and Welding

The independent booklets, “Rule Requirements for Materials and Welding – Part 2” for steels,
irons, bronzes, etc. and “Requirements for Materials and Welding Part 2 - Aluminum, - Fiber
Reinforced Plastics (FRP)” are to be referred to. Each booklet consists of the following
Chapters/Sections:

Rule Requirements for Materials and Welding

CHAPTER*
1 Materials for Hull Construction and Equipment
2 Materials for Equipment
3 Materials for Machinery, Boilers, Pressure Vessels and Piping
4 Welding and Fabrication
Part A - Hull Construction
Part B - Boilers, Unfired Pressure Vessels, Piping and Engineering Structures
Part C - Weld Test

Appendices*
1 List of Destructive and Nondestructive Tests Required in Sections 2/1 and 2/2,
and Responsibility for Verifying
2 Requirements for Approval of Filler Metals
3 Application of ABS Filler Metals to ABS Steels

Requirements for Materials and Welding - Aluminum


- Fiber Reinforced Plastics (FRP)

SECTION
4 Materials for Hull Construction - Aluminum
5 Materials for Hull Construction - Fiber Reinforced Plastics (FRP)

Appendix
2/E Aluminum Welding in Hull Construction

* The original Sections 1 through 3 have been replaced by Chapters 1 through 4. Also,
the original Appendices 2/A through 2/C have been replaced by the Appendices 1
through 3, with Appendix 2/D having been removed.
PART 3
Contents
Hull Construction and Equipment

SECTION
1 Definitions
2 General
3 Subdivision and Stability
4 Keels, Stems, and Shaft Struts
5 Rudders
6 Primary Hull Strength
8 Design Pressures
9 Plating
10 Internals
12 Hull Structural Arrangement
14 Arrangement, Structural Details and Connections
18 Protection of Deck Openings
20 Bulwarks, Rails, Ports, Portlights, Windows, and Ventilators
21 Protective Coatings
22 Equipment
23 Welding, Forming, and Weld Design
24 Fire Safety Measures

Appendices
3/A Guidelines in Calculating Bending Moment and Shear Force in Rudders and
Rudder Stocks
3/B Guidance on Torsional Analysis of the cross Deck Structure of a Multi-Hull
Craft
3/C Guidance on First Ply Failure Analysis on FRP Sandwich Panels
PART 3 SECTION 1

Definitions
The following definitions of terms are to be 3/1.11 Bulkhead Deck
understood (in the absence of other specifications) The bulkhead deck is the highest deck to which
where they appear in the Guide. watertight bulkheads extend and are made effective.

3/1.1 Length 3/1.13 Strength Deck


L is the distance in meters or feet on the summer load The strength deck is the deck which forms the top of
line, or if applicable, the design load waterline in the the effective hull girder at any part of its length. See
displacement mode, from the fore side of the stem to Section 3/6.
the centerline of the rudder stock. For use with the
Guide, L is not to be less than 96% and need not be 3/1.15 Superstructure Deck
greater than 97% of the length on the summer load A superstructure deck is a deck above the freeboard
line, The forward end of L is to coincide with the deck to which the side shell plating extends or of
foreside of the stem on the waterline on which L is which the sides are fitted inboard of the hull side not
measured. more than 4% of the breadth, B. Except where
otherwise specified the term superstructure deck where
3/1.3 Breadth used in the Guide refers to the first such deck above
B is the greatest molded breadth in meters or feet. the freeboard deck

3/1.5 Depth 3/1.16 Superstructure


D is the molded depth in meters or feet, measured at A superstructure is an enclosed structure on the main
the middle of the length L, from the molded keel line weather deck having side plating as an extension of the
to the top of the freeboard deck beams at the side of shell plating, or not fitted inboard of the hull side more
the craft. On craft with rabbeted keel construction, D than 4% of the breadth B.
is to be measured from the rabbet line, In cases where
watertight bulkheads extend to a deck above the 3/1.17 Deckhouses
freeboard deck and are to be recorded in the Record as A deckhouse is an enclosed structure above the
effective to that deck, D is to be measured to the freeboard deck, having side plating set inboard of the
bulkhead deck, hull side-shell plating more than 4% of the breadth B
of the craft.
3/1.7 Draft for Scantlings
d is the draft, in meters or feet, measured at the middle 3/1.18 Displacement
of the length L from the molded keel or the rabbet line The displacement ∆, is the mass displacement of the
at its lowest point to the estimated summer load vessel in the design condition in metric tons (long
waterline or the design load waterline in the tons), unless otherwise specifically noted.
displacement mode, whichever is greater.
3/1.19 Gross Tonnage
3/1.9 Freeboard Deck The measurement of the internal volume of spaces
The freeboard deck is normally the uppermost within the craft as defined by the International
continuous deck having permanent means for Convention on Tonnage Measurement of Ships, 1969.
weathertight closing of all openings in its weather
portions, and below which all openings in the craft 3/1.20 Significant Wave Height
side are equipped with permanent means for watertight Significant wave height is the average height of the
closure. In cases where a craft is designed for a one-third highest observed wave heights over a given
special draft considerably less than that corresponding period.
to the least freeboard obtainable under the
International Load Line Regulations, the freeboard
deck for the purpose of the Rules may be taken as the
lowest actual deck from which the draft can be
obtained under those regulations.

PART 3 SECTION 1|1 Definitions


3/1.21 Speed c Yarn A twisted strand or strands suitable for
Speed is the design speed in knots with the craft weaving into a fabric.
running ahead at the maximum continuous rated shaft d Binder A polyester applied in small quantities
rpm and at the summer load waterline. Operational to fibers to hold them together in mat form.
speed is 90% of design speed. e Coupling Agent An active water soluble
chemical that allows resin to adhere to glass,
3/1.22 Rabbet Line (Fiber Reinforced Plastic) f Chopped-strand Mat A blanket of randomly
The rabbet line is the line intersection between the oriented chopped-glass strands held together with
outside of a craft’s bottom and a craft’s keel. Where binder.
there is no keel, the rabbet line is the bottom of the g Woven Roving A coarse fabric woven from
craft. rovings.
h Cloth A fabric woven from yarn
3/1.23 Administration i Peel-Ply An "E" glass fabric that does not have
The government of the state whose flag the craft is any coupling agent applied, used as a protective
intended to fly. covering on a laminate being prepared for a secondary
bond to keep foreign particles from adhering to the
3/1.25 Passenger Craft surface.
Any craft which carries more than twelve passengers. j Uni-directional A woven or non-woven
See also 5/1.3. reinforcement with substantially more fibers in one
principal axis of the reinforcing ply.
3/1.27 Cargo Craft k Double Biased A woven or non-woven
Any craft other than a passenger craft, which is reinforcement with fibers primarily at + 45° to the
capable of maintaining the main functions of safety principal axes of the reinforcing ply.
systems of unaffected spaces after damage in any one l Knitted or Stitched Fabrics Two or more layers
compartment on board. of unidirectional fabrics that are stitched together.
m Bi-axial Fabric A stitched or knitted
3/1.29 Passenger reinforcement with fibers primarily in the principal
A passenger is every person other than the master and axis of the reinforcing ply.
members of the crew or other persons employed or n Tri-axial Fabric A stitched or knitted
engaged in any capacity on board a craft on the reinforcement with fibers running in one principal axis
business of that craft, and a child under one year of of the ply and in addition, with fibers running at + and
age. -45° to the warp.
o Ply Principal Axes The two principal axes of a
3/1.31 Place of Refuge reinforcing ply are the axis that is parallel to the warp
Any naturally or artificially sheltered area which may and the axis that is parallel to the fill.
be used as shelter by a craft under conditions likely to p Warp The roving or yarn running lengthwise in
endanger its safety. woven fabric (in the “roll direction”).
q Fill, Weft or Woof The roving or yarn running
3/1.33 Fiber-Reinforced Plastic (FRP) at right angles to the warp in a woven fabric.
r “E” glass A family of glass reinforcement
FRP consists of two basic components: a glass- material of aluminoborosilicate composition and
filament or other material fiber reinforcement and a having high electrical resistivity.
plastic, or resin, in which the reinforcing material is s “S” glass A family of glass reinforcement
imbedded. material of magnesium aluminosilicate composition
that contains a higher silicon content and provides
3/1.33.1 Reinforcement higher strength and stiffness properties than “E” glass.
Reinforcement is a strong, inert material bonded into t Kevlar An aramid fiber reinforcement.
the plastic to improve its strength, stiffness and impact u Carbon Fiber A reinforcement material made
resistance. Reinforcements are usually fibers of glass of mostly carbon produced by the pyrolysis of organic
(a lime-alumina-silicate composition having a low precursor fibers in an inert environment.
alkali content) or other approved material such as
aramid or carbon fiber, in a woven or non-woven 3/1.33.2 Resin
form, with a strong adhesive bond to the resin. Resin is a highly reactive synthetic that in its initial
a Strand A bundle of continuous filaments stage is a liquid, but upon activation is transformed
combined in a single, compact unit. into a solid.
b Roving A band or ribbon of parallel strands a Accelerator A material that, when mixed with
grouped together. resin, speeds the cure time.

PART 3 SECTION 1|2 Definitions


b Additive A substance added to another b Uni-directional Laminate A laminate with
substance, usually to improve properties, such as substantially more of the fibers in the plane of the
plasticizers, initiators, light stabilizers and flame laminate oriented in one of the two principal axis of
retardants. the laminate plane so that the mechanical properties
c Catalyst or Initiator A material that is used to along that axis are appreciably higher than along the
activate resin, causing it to harden. other natural axis.
d Crazing Hairline cracks, either within or on the c Sandwich Laminate A laminate consisting of
surface of resin, caused by mechanical or thermal two fiber reinforced plastic skins attached to a non-
stresses. structural or structural core (see 3/1.33.4
e Cure To change resin from a liquid to a solid. Encapsulation),
f Cure time The time required for resin to change d Barcol Hardness A measurement of the
from a liquid to a solid after a catalyst has been added. hardness of a laminate and thereby the degree of
g Exothermic Heat The heat given off as the completion of the cure.
result of the action of a catalyst on resin. e Delamination The separation of the layers of
h Filler A material added to resin to modify its material in a laminate.
working properties or other qualities, or to lower costs. f Gel Coat The first resin applied to mold when
i Gel A partially cured resin in a semi-solid state fabricating a laminate to provide a smooth protective
similar to gelatin in consistency. surface for the laminate.
j Gel Time The time required to change a g Layup The process of applying to a mold the
flowable, liquid resin into a nonflowing gel. layers of resin and reinforcing materials that make up a
k Inhibitor A material that retards activation or laminate. These materials are then compressed or
initiation of resin, thus extending shelf life or densified with a roller or squeegee to eliminate
influencing exothermic heat or gel time. entrapped air and to spread resin evenly. Also a
l Polymerization The reaction that takes place description of the component materials and geometry
when resin is activated or initiated. of a laminate.
m Pot Life The length of time that a catalyzed h Peel Ply A partially impregnated, lightly
resin remains workable. bonded layer of glass, cloth or woven roving used to
n Shelf Life The length of time that an protect a laminate in anticipation of secondary
uncatalyzed resin maintains its working properties bonding, providing a clean, fresh bonding surface.
while stored in a tightly sealed, opaque container. i Secondary Bonding The practice of bonding
o Tack The degree of stickiness of the resin. fresh material to a cured or partially cured laminate.
p Thixotropy The property or phenomenon, j Verified Minimum Mechanical Property The
exhibited by some resins, of becoming jelly-like at rest mechanical properties, in 2/5, of laminates differing
but becoming fluid again when stirred or agitated. from the basic, verified by the appropriate test(s) listed
This facilitates the application of the resin to inclined in Table 2/5.1.
or vertical surfaces. k Laminate Principal Axes The two principal
q Polyester Resin A thermosetting resin that is axes of a square or rectangular plate panel are for the
formed by combining saturated and unsaturated application of this Guide those perpendicular and
organic acids. Such as otrhophthalic and isophthalic parallel to the plate panel edges.
acids. 1 Vacuum Bagging A method used to apply a
r Vinylester Resin A thermosetting resin that uniform pressure over an area by applying a vacuum to
consists of a polymer chain and an acrylate or that area.
methacrylate termination. m Resin Impregnation A process of construction
s Epoxy A resin that contains one or more of the for large layers of fabric that consists of running a roll
epoxide groups. of fabric through a resin bath to completely saturate
the fabric.
3/1.33.3 Laminate n Resin Transfer Molding A closed mold method
A laminate is a material composed of successive that mechanically pumps resin through dry fabric
bonded layers, or plies, of resin and fiber or other previously placed in the mold.
reinforcing substances. o Resin Infusion A method of FRP construction
a Bi-directional Laminate A laminate having that uses a vacuum (from a vacuum bag) to pull
essentially the same strength and elastic properties in catalyzed resin through dry fabric.
the two in plane principal axes. Bi-directional p Primary Bond The bond that is formed between
laminates may be constructed of bi-axial, double bias, two laminated surfaces when the resin on both surfaces
tri-axial, mat or unidirectional reinforcing layers, or a has not yet cured.
combination of any of these. q Secondary Bond The bond that is formed
between two laminated surfaces when the resin on one
of the two surfaces has cured.

PART 3 SECTION 1|3 Definitions


r Post Cure The act of placing a laminate in an
autoclave and raising the temperature to assist in the
cure cycle of the resin.
s Autoclave A large oven used in post curing
large laminated parts.

3/1.33.4 Encapsulation
The containment of a core material such as softwoods,
plywood, balsa, PVC (cross linked), or linear polymer
within FRP laminates. The cores may be structurally
effective or ineffective.
a Bedding Putty Material used to adhere the core
material to the FRP skins.
b Scores Slits cut into the core material to aid in
forming the core to complex shapes.

3/1.35 Units
These Rules are written in three systems of units SI
units, MKS units and US customary units. Each
system is to be used independently of any other
system.
The format of presentation in the Guide of the
three systems of units is as follows:

SI units (MKS units, US customary units)

unless indicated otherwise.

PART 3 SECTION 1|4 Definitions


PART 3 SECTION 2

General
3/2.1 Materials 3/2.5.2 Openings
This Guide is intended for welded craft constructed of The structural arrangements and details are to be in
steel, welded craft constructed of aluminum, and fiber accordance with Section 3/14. In general, major
reinforced plastic (FRP) craft; complying with the openings such as doors, hatches, and large vent ducts
requirements of section 2/1, 2/4, and 2/5 respectively. are to be avoided in the hull in close proximity to the
The use of materials other than those specified in 2/1, gunwale. Corners of openings in strength structures
2/4, and 2/5 and the corresponding scantlings will be are to have generous radii. Compensation may be
specially considered. required for openings.

3/2.1.1 Selection of Material Grade


3/2.5.3 Brackets
For craft 61 m (200 ft) and over in length, steel a Steel Brackets Where brackets are fitted having
materials are not to be lower grades than those thicknesses as required by Table 3/2.1 and faces at
required by Table 3/2.1b for the material class given approximately 45 degrees with the bulkhead deck or
in Table 3/2.1a for the particular location. shell and the bracket is supported by a bulkhead, deck
or shell structural member, the length of each
3/2.1.2 Note for the Users member, l, may be measured at a point 25% of the
extent of the bracket beyond the toe of the bracket as
The attention of users is drawn to the fact that, when shown in Figure 3/2.1. The minimum overlap of the
fatigue loading is present, the effective strength of bracket arm along the stiffener is not to be less than
higher-strength steel in a welded construction may not obtained from the following equation.
be greater than that of ordinary-strength steel.
Precautions against corrosion fatigue may also be x = 1.4y +30 mm x = 1.4y + 1.2 in.
necessary.
x = length of overlap along stiffener in mm or in.
3/2.3 Workmanship y = depth of stiffener in mm or in.
All workmanship is to be of commercial marine
quality and acceptable to the Surveyor. Welding is to Where a bracket laps a member, the amount of
be in accordance with the requirements of Sections overlap generally is to be 25.5 mm (1 in.).
2/3, 2/E and 3/23. b Aluminum Brackets Aluminum brackets are
to comply with 3/2.5.3a except that the thicknesses
3/2.5 Design given in Table 3/2.1 are to be multiplied by 1.45 for
the same length of face.
3/2.5.1 Continuity
Care is to be taken to provide structural continuity. 3/2.5.4 Structural Design Details
Changes in scantlings are to be gradual. Strength The designer is to give consideration to the following:
members are not to change direction abruptly. Where a The thickness of internals in locations
primary structural members terminate at another susceptible to rapid corrosion.
structural member, tapering of the primary member b The proportions of built-up members to comply
may be required beyond the other structural member. with established standards for buckling strength.
Stanchions and bulkheads are to be aligned to provide c The design of structural details such as noted
support and to minimize eccentric loading. Major below, against the harmful effects of stress
appendages outside the hull and strength bulkheads in concentrations and notches:
superstructures are to be aligned with major structural 1 Details of the ends, the intersections of
members within the hull members and associated brackets.
2 Shape and location of air, drainage or
lightening holes.
3 Shape and reinforcement of slots or cut-
outs for internals.

PART 3 SECTION 2|1 General


4 Elimination or closing of weld scallops in Where the plating is an FRP sandwich laminate with a
way of butts, “softening” of bracket toes, flexurally and compressively ineffective (balsa, cross
reducing abrupt changes of section or linked PVC, or linear polymer) core, t in the above
structural discontinuities. equation is the thickness of a single skin laminate
d Proportions and thickness of structural having the same moment of inertia per unit width as
members to reduce fatigue response due to engine, the two skins of the sandwich about the neutral axis
propeller or wave-induced cyclic stresses, particularly of the sandwich, excluding the core.
for higher-strength steels. For a stiffening member along an opening, the
Standard construction details based on the above maximum effective width of plating is equal to either
considerations are to be indicated on the plans or in a one-half the stiffening member spacing or the width
booklet submitted for review and comment. obtained from the following equation, whichever is
less.
3/2.5.5 Termination of Structural Members w = 9t + b
Unless permitted elsewhere in the Guide, structural
members are to be effectively connected to the where w, t and b are as defined above.
adjacent structures in such a manner to avoid hard
spots, notches and other harmful stress 3/2.7.2 Steel and Aluminum Plating
concentrations. Where members are not required to a Primary Structural Members The effective
be attached at their ends, special attention is to be width of plating for deep supporting members is to
given to the end taper, by using soft-toed concave equal to the lesser of either one half the sum of
brackets or by a sniped end of not more than 30°. spacing on each side of the member, 0.33 time the
Bracket toes or sniped ends are to be kept within 25 unsupported span, l, or 750mm (30 in). For girders
mm (1.0 in.) of the adjacent member and the depth at and webs along hatch openings the effective width of
the toe or snipe end is generally not to exceed 15 mm plating is to be half of that obtained from the above.
(0.60 in.). Where a strength deck or shell longitudinal Due account is to be taken in regards to plate
terminates without end attachment it is to extend into buckling, see 3/9.1.1
the adjacent transversely framed structure or stop at a b All Other Structural Members The maximum
local transverse member fitted at about one transverse effective width of plating is equal to either one-half
frame space beyond the last floor or web that the sum of spacing on each side of the member or the
supports the longitudinal. width obtained from the following equation,
whichever is less.
3/2.7 Effective width of plating
The section modulus and moment of inertia of Steel Members: w = 80t
stiffening members are provided by the member and a
portion of the plating to which it is attached. The Aluminum Members: w = 60t
effective width is as given in the following sub-
sections. The section modulus and moment of inertia w = effective width of plating in mm or in.
of a shape, bar, fabricated section, or layed-up t = thickness of single skin plating in mm or in.
member not attached to plating is that of the member
only. For a stiffening member along an opening, the
maximum effective width of plating is one-half of the
3/2.7.1 FRP Laminates effective width given above.
Where the plating is an FRP single-skin laminate, the
maximum effective width of plating for floors,
frames, beams and bulkhead stiffeners is not to
exceed either the stiffening member spacing or the
width obtained from the following equation,
whichever is less. See Figure 3/2.2.
w = 18t + b
where:
w = effective width of plating in mm or in.
t = thickness of single skin plating in mm or in.
b = net width of stiffening member in mm or in.,
but not more than 18t

PART 3 SECTION 2|2 General


TABLE 3/2.1a
Material Class of Structural Members

Within 0.4L Outside 0.4L


Structural member Amidships Amidships
Material Class (1) Material Class
or Grade or Grade
Shell
Bottom plating including keel plate Class II Grade A(7)/AH
Bilge strake Class III (2),(3) Class II (4)
Side plating Class I Grade A(7)/AH
Sheer strake at strength deck (5) Class III (3) Class II (4)
Decks
Strength deck plating (6) Class II Grade A(7)/AH
Stringer plate in strength deck (5) Class III (3) Class II (4)
Strength deck plating within line of
hatches, and exposed to weather in Class I Grade A(7)/AH
general
Longitudinal Bulkhead
Lowest strake in single bottom vessels Class I Grade A(7)/AH
Uppermost strake including that of the
top wing tank Class II Grade A(7)/AH
Other Structures in General
External continuous longitudinal
members (excluding longitudinal hatch Class II Grade A(7)/AH
coamings) and bilge keels
Stern frames, rudder horns, rudders,
and shaft brackets – Class I
Strength members not referred to in
above categories and above local Grade A(7)/AH Grade A(7)/AH
structures
Notes
1 Special consideration will be given to vessels in restricted service.
2 May be class II in vessels with a double bottom over the full breadth B.
3 Single strakes required to be of material class III or E/EH are to have breadths not less than
800 + 5L mm (31.5 + 0.06L in.), but need not exceed 1800 mm (71 in.).
4 May be class I outside 0.6L amidships.
5 A radius gunwale plate may be considered to meet the requirements for both the stringer
plate and the sheerstrake, provided it extends a suitable distance inboard and vertically. For
formed material see 2-4-1/3.13
6 Plating at the corners of large hatch openings, is to be specially considered.
7 ASTM A36 steel otherwise tested and certified to the satisfaction of ABS may be used in
lieu of Grade A for a thickness up to and including 12.5 mm (0.5 in.) for plate and up to and
including 40 mm (1.57 in.) for sections.

PART 3 SECTION 2|3 General


TABLE 3/2.1b
Material Grades

Thickness t Material Class


mm (in.) I II III
t ≤ 15 (t ≤ 0.60) A(2), AH A, AH A, AH
15 < t ≤ 20 (0.60 < t ≤ 0.79) A, AH A, AH B, AH
20 < t ≤ 25 (0.79 < t ≤ 0.98) A, AH B, AH D, DH
25 < t ≤ 30 (0.98 < t ≤ 1.18) A, AH D, DH D (1), DH
30 < t ≤ 35 (1.18 < t ≤ 1.38) B, AH D, DH E, EH
35 < t ≤ 40 (1.38 < t ≤ 1.57) B, AH D, DH E, EH
40 < t ≤ 51 (1.57 < t ≤ 2.00) D, DH E, EH E, EH

Notes
1 Grade D, of these thicknesses, is to be normalized.
2 ASTM A36 steel otherwise tested and certified to the
satisfaction of ABS may be used in lieu of Grade A for a
thickness up to and including 12.5 mm (0.5 in.) for plate
and up to and including 40 mm (1.57 in.) for sections.

FIGURE 3/2.1
Bracket

TABLE 3/2.1
Brackets (Steel)
Thickness
Length of Face f, mm Millimeters Width of Flange, mm
Plain Flanged
Not exceeding 305 5.0 --- --
Over 305 to 455 6.5 5.0 38
Over 455 to 660 8.0 6.5 50
Over 660 to 915 11.0 8.0 63
Over 915 to 1370 14.0 9.5 75

Thickness
Length of Face f, in. Inches Width of Flange, in.
Plain Flanged
Not exceeding 12 3/16 -- --
Over 12 to 18 1/4 3/16 1½
Over 18 to 26 5/16 1/4 2
Over 26 to 36 7/16 5/16 2½
Over 36 to 54 9/16 3/8 3

PART 3 SECTION 2|4 General


FIGURE 3/2.2
Effective Width of FRP Plating

PART 3 SECTION 2|5 General


PART 3 SECTION 3

Subdivision and Stability


3/3.1 General a Passenger craft making voyages that are no
Craft of the following categories are to have more than 4 hours at operational speed and having
subdivision and stability in accordance with the design speeds greater than 3.7∇1/6m/sec (7.19∇1/6
criteria as shown. knots, 3.97∇1/6 knots) – IMO International Code of
Safety for High-Speed Craft – Chapter 2
3/3.3 Criteria b Other passenger craft – SOLAS Regulation
II-1/4 through 8
3/3.3.1 Intact Stability c Cargo craft ≥ 500 GT making voyages that are
All craft which have a length of 24 m (79 ft) or over no more than 8 hours at operation speed and having
as defined in the International Convention on Load design speeds greater than 3.7∇1/6m/sec (7.19∇1/6
Lines are to have intact stability guidance as required knots, 3.97∇1/6 knots) – IMO International Code of
by Regulation 10 of the International Convention on Safety for High-Speed Craft – Chapter 2
Load Lines. Following criteria may be used for d Other cargo craft ≥ 500 GT – SOLAS
classification purposes: Regulation II-1/25-1 through 25-8
a For all cargo craft ≥ 500 GT making voyages
that are no more than 8 hours at operational speed 3/3.5 Review Procedures
from a place of refuge and having design speeds
greater than 3.7∇1/6m/sec (7.19∇1/6 knots, 3.97∇1/6 3/3.5.1 Administration Review
knots) – IMO International Code of Safety for High- When the craft is issued an International Load Line
Speed Craft – Chapter 2 Certificate, Passenger Ship Safety Certificate, Cargo
b For all passenger craft making voyages that are Ship Safety Construction Certificate, or High Speed
no more than 4 hours at operational speed from a Craft Safety Certificate by the flag Administration or
place of refuge and having design speeds greater than its agent other than the Bureau, such Certificate will
3.7∇1/6m/sec (7.19∇1/6 knots, 3.97∇1/6 knots) – IMO be accepted as evidence that the craft has subdivision
International Code of Safety for High-Speed Craft – and stability in accordance with the above criteria.
Chapter 2 Where the Administration undertakes the review
c Other craft of all sizes – IMO Resolution of subdivision and stability and the Bureau is issuing
A167/A206 with A562 the above Certificate, the acceptance of subdivision
and stability by the Administration will be required
where before the certificate is issued.
∇ = the volumetric displacement of the vessel in
the design condition in m3 (m3, ft3) 3/3.5.2 Bureau Review
GT = the gross tonnage as defined in 3/1.19 In all other cases the information and calculations for
subdivision and stability are to be submitted to the
In case the above criteria are not applicable to a Bureau for review. Where the intact stability criteria
particular craft, the intact stability will be reviewed are not applicable to a particular craft, the review will
by the Bureau in accordance with other recognized be in accordance with other recognized criteria
criteria appropriate to the craft's type, size, and acceptable to the Bureau.
intended service.

3/3.3.2 Subdivision and Damage Stability


Craft of applicable size, type, and service are to have
subdivision and damage stability as required by the
International Code of Safety for High-Speed Craft, or
the International Convention for the Safety of Life at
Sea, 1974, as amended as follows:

PART 3 SECTION 3|1 Subdivision and Stability


PART 3 SECTION 4

Keels, Stems, and Shaft Struts


3/4.1 Materials L = length of craft in m or ft as defined in
Section 3/1
3/4.1.1 Ordinary Strength Steels
The requirements in the following subsections are Thicknesses and depths other than given above are
based upon ordinary strength steel. For higher acceptable provided the section modulii and moments
strength steels and aluminum alloys see 3/4.1.3. of inertia about the transverse horizontal axis are not
less than given above, nor h/t more than 4.5.
3/4.1.3 High Strength Steels and Aluminum
Alloys 3/4.2.2 Plate Keels
Unless otherwise specified, the required section The thickness of the steel plate keel throughout the
modulus and inertia for high strength steels and length of the craft is to be not less than the bottom
aluminum alloys are as follows: shell required in 3/9.

SM = SMs Q 3/4.4 Stems


I = Is Es / Eo
3/4.4.1 Bar Stems
SM,I = required section modulus and inertia. Where bar stems are fitted the thickness and depth is
Unless specifically stated otherwise, not to be less than obtained from the following
the properties about the minor axis equations.
(axis perpendicular to h or w) are to be
used. t = 0.625L + 6.35 mm t = 0.0075L + 0.25 in.
SMs, Is = Section modulus and inertia obtained w = 1.25L + 90 mm w = 0.015L + 3.5 in.
from the dimensions given for ordinary
strength steel. t = thickness in mm or in.
Q = as defined in 3/6.1.1a w = width in mm or in.
Es = 2.06 x 105 N/mm2 (21 x 103 kgf/mm2, L = length of craft in m or ft as defined in
30 x 106 psi) Section 3/1
Eo = modulus of the material being
considered in N/mm2 (kgf/mm2, psi) This thickness and width is to be maintained between
the keel and design load waterline. Above the
Use of materials other than steel or aluminum will be designed load waterline they may be gradually
specially considered. reduced until the area at the head is 70% of that
obtained from the equations.
3/4.1.5 Fiber Reinforced Plastic Thicknesses and widths other than given above
For fiber reinforced plastic hulls, keels and skegs are are acceptable provided the section modulii and
to have proportions as indicated in Figure 3/14.10 moments of inertia about the longitudinal axis are not
and Figure 3/14.11. less than above, nor w/t more than 5.5. The thickness
of the bar stem in general should also not be less than
3/4.2 Keels twice the shell thickness.

3/4.2.1 Bar Keels 3/4.4.3 Plate Stems


Where bar keels are fitted the thickness and depth is Where plate stems are used, they are not to be less in
not to be less than obtained from the following thickness than the bottom shell plating required in
equations. 3/9.1 and 3/9.3, where s is the frame spacing, or 610
mm (24 in.) if greater. Plate stems are to be suitably
t = 0.625L + 12.5 mm t = 0.0075L + 0.50 in. stiffened.
h = 1.46L + 100 mm h = 0.0175L + 4 in.

t = thickness in mm or in.
h = depth in mm or in.

PART 3 SECTION 4|1 Keels, Stems, and Shaft Struts


3/4.6 Stern Frames b Thickness The thickness of the streamlined
Craft that are fitted with stern frames, shoe pieces, section strut arm is not to be less than obtained from
rudder horns, and rudder gudgeons are to meet the the following equation.
applicable requirements in 3/4 of the Rules for
Building and Classing Steel Vessels. t1 = 0.515d

3/4.18 Shaft Struts t1 = thickness of strut (minor axis) in mm or in.


d = diameter of tail shaft in mm or in.
3/4.18.1 General
Tail-shaft (propeller-shaft) struts where provided may 3/4.18.4 Strut Length
be of the V or I type. The thickness of the strut barrel The length of the longer leg of a V strut or the leg of
or boss is to be at least one-fifth the diameter of the an I strut, measured from the outside perimeter of the
tail shaft. The length of the strut barrel or boss is to strut barrel or boss to the outside of the shell plating,
be adequate to accommodate the required length of is not to exceed 10.6 times the diameter of the tail
propeller-end bearings. The following equations are shaft. Where this length is exceeded, the width and
for solid struts having streamline cross-sectional thickness of the strut are to be increased, and the strut
shapes. For struts other than ordinary strength steel design will be given special consideration. Where
see 3/4.1. For hollow section and non-streamlined strut length is less than 10.6 x required tailshaft
struts, the equivalent cross sectional area, inertia, and diameter, the section modulus of the strut may be
section modulus (about the major axis) are not to be reduced in proportion to the reduced length, provided
less than required by 3/418.2 and 3/418.3. For a the section modulus is not less than 0.85 x Guide
streamlined cross-section strut, the inertia about the required section modulus.
longitudinal axis is wt3/25 and the section modulus
about the same axis is wt2/12.5.

3/4.18.2 V Strut
a Width The width of each streamlined section
strut arm is not to be less than obtained from the
following equation.

w = 2.27d

w = width of strut (major axis) in mm or in.


d = required diameter of ABS Grade 2 tail shaft
in mm or in. (see Section 4/7)

b Thickness The thickness of each streamlined


section strut arm is not to be less than obtained from
the following equation.

t = 0.365d

t = thickness of strut (minor axis) in mm or in.


d = required diameter of ABS Grade 2 tail shaft
in mm or in.

Where the included angle is less than 45 degrees, the


foregoing scantlings are to be specially considered.

3/4.18.3 I Strut
a Width The width of the streamlined section
strut arm is not to be less than obtained from the
following equation.

w1 = 3.22d

w1 = width of strut (major axis) in mm or in.


d = diameter of tail shaft in mm or in.

PART 3 SECTION 4|2 Keels, Stems, and Shaft Struts


PART 3 SECTION 5

Rudders

3/5.1 General 3/5.2 Design Loads

3/5.1.1 Application 3/5.2.1 Rudder Force


This section applies to flat plate and foil profile spade Where the rudder profile can be defined by a
rudders. Rudders having other profiles or with single quadrilateral, the rudder force is to be obtained
special arrangements for increasing rudder force, such from the following equation. Where the rudder angle
as fins, flaps, steering propellers or other means of φ, exceeds 35°, the rudder force, CR, is to be
steering will be subject to special consideration. increased by a factor of 1.74 sin (φ).
Where rudders are fitted on horns or shoepieces, they
are to comply with 3/5 of the Rules for Building and CR = nCSKTAV2 kN (tf, Ltf)
Classing Steel Vessels. The surfaces of rudder stocks
in way of exposed bearings are to be of non-corrosive CR = rudder force.
materials. Special consideration will be given to A = total projected area of rudder in m2 (ft2)
aluminum rudder stocks and fiber reinforced plastic KT = 1.463 ahead, 1.682 ahead behind fixed
rudders and rudder stocks. Material specifications are propeller nozzle.
to be listed on the plans. = 1.063 astern (1.2 for flat sided rudders
astern), 1.22 astern behind fixed propeller
3/5.1.2 Rudder and Rudder Stock Materials nozzle (1.38 for flat sided rudders astern
Rudders, rudder stocks, coupling bolts, and keys are behind fixed propeller nozzle).
to be made from material in accordance with the CS = Speed coefficient.
requirements of Section 2/1. Material tests for = 1.0 for Vd < 20 knots;
coupling bolts and torque transmitting keys need not 3
 V 
be witnessed by the Surveyor. The surfaces of rudder = . − 0.046 6  where Vd ≥ 20 knots,
 159
stocks in way of exposed bearings are to be of  ∆
noncorrosive material. but need not exceed 1.0 and is not to be
Material factors for castings and forgings used for taken less than 0.45.
the stock (Ks), bolts (Kb), and coupling flange (Kf), V = Vd for the ahead condition but is not to be
are to be obtained from the following equation. taken as less than Vmin.
= Va for the astern condition but is not to be
K = (ny/Y)e taken as less than 0.5Vd or 0.5Vmin,
whichever is greater.
ny = 235 N/mm2 (24 kgf/mm2, 34000 psi) Vd = the maximum speed in knots with the craft
Y = Specified minimum yield strength of the running ahead at the maximum continuous
material in N/mm2 (kgf/mm2, psi) but is not rated shaft rpm and at the summer load
to be taken as greater than 0.7U or 450 waterline.
N/mm2 (46 kgf/mm2, 65000 psi) whichever Va = maximum astern speed in knots.

U
is lesser.
= minimum tensile strength of material used in
Vmin = (Vd + 20 ) 3
N/mm2 (kgf/mm2, psi) ∆ = maximum craft displacement in metric tons
e = 1.0 for Y ≤ 235 N/mm2 (24 kgf/mm2, 34000 (long tons)
psi) n = 0.132 (0.0135, 0.0132)
= 0.75 for Y > 235 N/mm2 (24 kgf/mm2, 34000
psi)

3/5.1.3 Expected Torque


The torque considered necessary to operate the
rudder in accordance with 4/8.8.2 is to be indicated
on the submitted rudder or steering gear plan. See
4/8.1.3 and 3/5.2.2c.

PART 3 SECTION 5|1 Rudders


FIGURE 3/5.1 QR = Total rudder torque as defined in 3/5.2.2 in
Rudder kN-m (tf-m, Ltf-m)
Ks = Material factor for upper rudder stock as
defined in 3/5.1.2

3/5.3.2 Lower Rudder Stocks


The lower rudder stock diameter is to be determined
using the given rudder force and torque in 3/5.2.
Bending moments, shear forces and reaction forces
are to be determined from 3/5.3.3, and 3/5.7.3.

The lower rudder stock diameter is not to be less


than obtained from the following equation.

Sl = S 6 1 + (4 3)( M QR ) mm (in)
2

S = upper stock required diameter from 3/5.3.1


in mm (in.)
Sl = lower stock required diameter.
M = bending moment at the station of the rudder
3/5.2.2 Rudder Torque for Scantlings stock considered in kN-m (tf-m, Ltf-ft)
a General The torque to be used for the rudder QR = rudder torque from 3/5.2.2 in kN-m (tf-m,
scantlings is to be as defined in 3/5.2.2b below. Ltf-ft)
b Rudder Blades The rudder torque for both the
ahead and astern conditions is to be determined from Where the diameter at the neck bearing differs from
the following equation. the diameter of the upper bearing or tiller, a gradual
QR = CRr kN-m (tf-m, Ltf-ft) transition is to be provided between the different
diameter stocks.
QR = rudder torque.
CR = rudder force as calculated in 3/5.2.1 3/5.3.3 Bending Moments
r = c(α-Af/A) (but not less than 0.1c for ahead The bending moment on the rudder and rudder stock
condition) may be determined in accordance with Appendix 3/A
c = mean breadth of rudder area in m (ft) from or in accordance with the following equations.
Fig. 3/5.1
α = 0.33 ahead, 0.66 astern. M n = C R ! n kN-m (Ltf-ft)
Af = Area of rudder blade situated forward of the
centerline of the rudder stock in m2 (ft2). A
M s = CR 1 ! c kN-m (Ltf-ft)
A is as defined in 3/5.2.1. A
c Trial Conditions The above values of QR are Mn = bending moment at neck bearing.
intended for the design of rudders and should not be Ms = bending moment at section under
directly compared with the torques expected during consideration.
the trial (see 3/5.1.3) or the rated torque of steering !n = distance from center of neck bearing to the
gear (see 4/8.1.3).
centroid of rudder area, m (ft)
3/5.3 Rudder Stocks
!c = distance from section under consideration to
the centroid of rudder area, A1, m (ft)
3/5.3.1 Upper Rudder Stocks A1 = area below section under consideration, m2
The upper rudder stock is that part of the rudder stock (ft2)
above the neck bearing or above the top pintle. At the CR and A are as defined in 3/5.2.1
upper bearing or tiller, the upper stock diameter is not
to be less than obtained from the following equation: 3/5.5 Rudder Couplings

S = N u 3 QR K s mm (in) 3/5.5.1 Flange Couplings


Rudder couplings are to be supported by an ample
S = Upper stock required diameter. body of metal worked out from the rudder stock. The
Nu = 42.0 (89.9, 2.39) material outside the bolt holes is not to be less than
two thirds the diameter of the bolt. Suitable means of

PART 3 SECTION 5|2 Rudders


locking the nuts are to be provided. The diameter of with hydraulic arrangements for mounting and
the bolts and the flange thicknesses are not to be less dismounting the coupling (mounting with oil injection
than obtained from the following equations. and hydraulic nut) the taper on the diameter is to be
a Horizontal Couplings There are to be at least 1/12 to 1/20, and the push-up oil pressure and the
six coupling bolts in horizontal couplings, and the push up length will be specially considered upon
diameter of each bolt is not to be less than obtained submission of calculations in each case.
by the following equation. b Keying Where the stock is keyed to the rudder
casting, torsional strength equivalent to that of the
d b = 0.62 d s K b
3
(nrK s ) mm (in) required upper stock diameter is to be provided. The
top of the keyway is to be located well below the top
db = bolt diameter. of the rudder. For higher strength materials, shear and
n = total number of bolts in coupling. bearing areas of keys and keyways are to be based on
r = mean distance in mm (in) of the bolt centers the lesser strength properties of the key and the
from the center of the system of bolts. materials in which keyways are cut, as appropriate.
ds = required diameter of stock in way of c Locking Nut The nut is to be proportioned in
coupling, S or Sl from 3/5.3.1 or 3/5.3.2 as accordance with the following and is to be fitted with
the case may be in mm (in) an effective locking device. (See Figure 3/5.2).
Kb = material factor for bolts as defined in 3/5.1.2
Ks = material factor for stock as defined in 3/5.1.2 external thread diameter dg ≥ 0.65 do

Coupling flange thickness is not to be less than the length of nut hn ≥ 0.6 dg
lesser of the following equations. outer diameter of nut dn ≥ 1.2du or 1.5dg
t f = d b K f Kb mm (in) t f = 0.9d b mm (in) whichever is greater

Kf = material factor for flange as defined in FIGURE 3/5.2


3/5.1.2 Tapered Couplings
db = required bolt diameter calculated for a
number of bolts not exceeding 8.

b Vertical Couplings There are to be at least eight


coupling bolts in vertical couplings and the diameter
of each bolt is not to be less than obtained from the
following equation.

d b = 0.81d s K b (nK s ) mm (in)

n = total number of bolts.


ds, Kb, Ks as defined above.

In addition, the first moment of area of the bolts


about the center of the coupling is not to be less than
given by the following equation.
m = 0.00043ds3 mm3 (in3)
m = first moment of area.
ds = diameter as defined in 3/5.5.1a

Coupling flange thickness is not to be less than db.


3/5.5.3 Keyless Couplings
Hydraulic and shrink fit keyless couplings will be
3/5.5.2 Tapered Stock Couplings
specially considered upon submittal of detailed
a Taper Ratio Tapered stocks secured to the
preloading and stress calculations and fitting
rudder casting by a nut on the end of the stock are to
instructions. The calculated torsional holding capacity
have a length of taper in the casting generally not less
is to be at least 2.0 times the transmitted torque based
than 1.5 times the diameter of the stock at the top of
on the steering gear relief valve setting. Preload stress
the rudder. Couplings without hydraulic arrangements
is not to exceed 70% of the minimum yield strength
for mounting and dismounting the coupling are to
of the rudder stock housing or the rudder stock
have a taper on diameter of 1/8 to 1/12. For couplings
materials.

PART 3 SECTION 5|3 Rudders


3/5.9 Double Plate Rudder The thickness of the rudder side or bottom plating is
to be at least 2 mm (0.08 in.) greater than that
3/5.9.1 Strength required by 3/9.1.2a for deep tank plating in
The section modulus and web area of the rudder association with a head h measured to the summer
mainpiece are to be such that the following stresses load line.
are not exceeded. b Diaphragm Plates Vertical and horizontal
In calculating the section modulus of the rudder, diaphragms are to be fitted within the rudder,
the effective width of side plating is to be taken as not effectively attached to each other and to the side
greater than twice the athwartship dimension of the plating. Vertical diaphragms are to be spaced
rudder. Generous radii are to be provided at abrupt approximately 1.5 times the spacing of horizontal
changes in section, and in way of openings, including diaphragms. Openings are in general not to be more
those with cover plates. than 0.5 times the depth of the web.
Moments and reaction forces are to be as given in The thickness of diaphragm plates is not to be less
3/5.3.3. than 70% of the required rudder side plate thickness
or 8 mm (0.31 in.) whichever is greater. Welding is to
bending stress σb 110 N/mm2 be in accordance with Section 2/3A and 3/23. Where
(11.2 kgf/mm2, inaccessible for welding inside the rudder, it is
16000 psi) recommended that diaphragms be fitted with flat bars
shear stress τ 50 N/mm2
and the side plating be connected to these flat bars by
(5.1 kgf/mm2,
7300 psi) continuous welds or by 75 mm (3 in.) slot welds
equivalent 120 N/mm2 spaced at 150 mm (6 in.) centers. The slots are to be
σ e = σb +3 τ 2
2
stress (12.2 kgf/mm2, fillet welded around the edge, and filled with a
17000 psi) suitable compound.
c Watertightness The rudder is to be watertight
The mainpiece of the rudder is to be formed by and is to be tested in accordance with Table 1/2.1.
the rudder side plating (but not more than the
effective width indicated above) and vertical 3/5.10 Single Plate Rudders
diaphragms extending the length of the rudder or the
extension of the rudder stock or a combination of 3/5.10.1 Mainpiece Diameter
both. The mainpiece diameter is calculated according to
The section modulus at the bottom of the rudder is 3/5.3.2. The lower third may be tapered down to 0.75
not to be less than one-third the required section times stock diameter at the bottom of the rudder.
modulus of the rudder at the top of the rudder or at
the center of the lowest pintle. 3/5.10.2 Blade Thickness
The blade thickness is not to be less than obtained
3/5.9.2 Rudder plating from the following equation.
a Side, Top and Bottom Plating The plating
tb = 0.0015sV + 2.5 mm
thickness is not to be less than obtained from the
following equation.
tb = 0.0015sV + 0.1 in

t =.0055sβ k 1 d + ( k 2 C R A) × Q + k 3 mm (in)
s = spacing of stiffening arms in mm (in), not to
exceed 1000 mm (39 in.)
V = speed as defined in 3/5.2.1
k1 = 1.0 (1.0, 0.305) 3/5.10.3 Arms
k2 = 0.1 (0.981, 10.7) The thickness of the arms is not to be less than the
k3 = 2.5 (2.5, 0.1) blade thickness obtained in 3/5.10.2. The section
d = Summer loadline draft of the ship in m (ft) modulus of each set of arms about the axis of the
CR = Rudder force according to 3/5.2 in kN (tf, rudder stock is not to be less than obtained from the
Ltf) following equation.
A = Rudder area in m2 (ft2)
s = smaller unsupported dimension of plating in SM = .0005 sCl2V2 cm3
mm (in) SM = .0000719 sCl2V2 in3
b = greater unsupported dimension of plating in
mm (in) Cl = horizontal distance from the aft edge of the
. − 0.5( s b) ; maximum 1.0 for b/s ≥ 2.5
2 rudder to the centerline of the rudder stock
β = 11
in m (ft)
Q = material factor for rudder plating as defined s, V are as defined in section 3/5.10.2.
in 3/6.1.1a

PART 3 SECTION 5|4 Rudders


3/5.11 Rudder Stops manufacturer’s recommended running clearance. For
spade rudders with a rudder stock diameter of 400mm
Strong and effective rudder stops are to be fitted. (15.75 in.) or less, the clearances on the diameter are
Where adequate positive stops are provided within not to be less than given below:
the gear, structural stops will not be required. See
also 4/8. Stock Metallic Synthetic
Diameter, Bushing, Bushing 1,
3/5.13 Supporting and Anti-Lifting Arrangements mm (in.) mm (in.) mm (in.)
400 (15.75) 1.15 (0.045) 1.15 (0.045) + E2
3/5.13.1 Rudder Stock Bearings 300 (11.81) 0.85 (0.033) 0.85 (0.033) + E
a Bearing Surfaces The bearing surface Ab for 200 (7.87) 0.78 (0.031) 0.78 (0.031) + E
rudder stocks, shafts and pintles is not to be less than 100 (3.94) 0.75 (0.030) 0.75 (0.030) + E
obtained from the following equation. Notes:
1. The bushing manufacturer’s recommended
Ab = 1000 P/qa mm2 Ab = 2240 P/qa in2 running clearance may be used as an alternative
to these clearances.
Ab = projected area of bearing surface = dllb 2. E = expansion allowance provided by bushing
where dl is the outer diameter of the liner manufacturer, mm (in.).
and lb is the bearing length not to be taken
greater than 1.2d. 3/5.13.2 Rudder Carrier and Anti Lifting Devices
P = Bearing reaction force in kN (tf, Ltf) .See Effective means are to be provided for supporting the
Appendix 3/A.1.4. weight of the rudder assembly. At least half of the
qa = allowable surface pressure as rudder carrier holding-down bolts are to be fitted
indicated in Table 3/5.2 depending on bearing bolts. Alternatively, other effective means of
material in N/mm2 (kgf/mm2, psi) preventing horizontal movement of the rudder may be
b Bearing Clearance With metal bearings specially considered. Means are also to be provided
clearance is not to be less than db/1000 + 1.0 mm, to prevent accidental unshipping, lifting or undue
(db/1000 + .04 in) on the diameter. If non-metallic movement of the rudder which may cause damage to
bearing material is applied, the bearing clearance is to the steering gear. See Appendix 3A for guidance.
be specially determined considering the material's
swelling and thermal expansion properties. This
clearance is in no case to be taken less than 1.5 mm
(0.06 in) on the diameter or the bushing
TABLE 3/5.2
Bearing Pressure
q aƒ
Bearing Material N/mm2 kgf/mm2 psi

lignum vitae 2.5 0.25 360


white metal, oil lubricated 4.5 0.46 650
synthetic material with hardness between 60 and 70 Shore D* 5.5 0.56 800
steel§, bronze and hot-pressed bronze-graphite materials 7.0 0.71 1000
ƒ Higher values than given in the table may be taken if they are verified by tests.
§ Stainless and wear-resistant steel in an approved combination with stock liner.
* Indentation hardness test at 23°C and with 50% moisture, according to a recognized standard. Synthetic
bearing materials to be of approved type.

PART 3 SECTION 5|5 Rudders


PART 3 SECTION 6

Primary Hull Strength


3/6.1 Longitudinal Hull Girder Strength K3 is not to be taken less than 1.
- Monohulls K4 = 1.0 for craft in Unrestricted Ocean Service.
The equations are, in general, valid for craft having = 0.9 for craft in restricted service
breadths, B, not greater than twice their depths, D, as C = 1.0 for steel craft, 0.90 for aluminum craft
defined in 3/1. and 0.80 for fiber-reinforced plastic craft
Q for steel
3/6.1.1 Section Modulus = 1.0 for ordinary strength steel
a All craft The required hull girder section = 0.78 for grade H32 steel
modulus SM at amidships is to be not less than given = 0.72 for grade H36 steel
by the following equation: Q for aluminum
= 0.9 + q5 but not less than Qo
SM = C1C2L2B(Cb+0.7)K3K4CQ cm2m (in.2ft) q5 = 115/σy , (12/σy , 17000/σy )
where: Qo = 635/(σy +σu), (65/(σy + σu), 92000/(σy +σu ))
σy = minimum yield strength of welded aluminum
C1 = 30.67 – 0.98L 12 ≤ L < 18 m in N/mm2 (kgf/mm2, psi)
= 22.40 – 0.52L 18 ≤ L < 24 m σu = minimum ultimate strength of welded
= 15.20 – 0.22L 24 ≤ L < 35 m aluminum in N/mm2 (kgf/mm2, psi)
= 11.35 – 0.11L 35 ≤ L < 45 m Q for fiber reinforced plastic
= 6.40 45 ≤ L < 61 m = 400/σu, (41/σu, 58000/σu )
= 0.0451L + 3.65 L ≥ 61 m σu = minimum ultimate tensile or compressive
C1 = 30.67 – 0.299L 40 ≤ L < 59 ft strength whichever is less, verified by
= 22.40 – 0.158L 59 ≤ L < 79 ft approved test results, in N/mm2 (kgf/mm2,
= 15.20 – 0.067L 79 ≤ L < 115 ft psi). See 2/5.5. Strength properties in the
= 11.35 – 0.033L 115 ≤ L < 150 ft longitudinal direction of the craft are to be
= 6.40 150 ≤ L < 200 ft used.
= 0.0137L + 3.65 L ≥ 200 ft
C2 = 0.01 (0.01, 1.44 x 10-4) b Craft 61 m (200 ft.) in Length and Over In
L = length of craft in m or ft as defined in Section addition to meeting the above criteria in 3/6.3.1a, craft
3/1 of 61 m (200 ft.) in length or greater are to comply
B = breadth in m of ft as defined in Section 3/1 with the following requirements.
V = maximum speed for the specified sea state, in 1 Sign Convention of Bending Moment and
knots Shear Force The sign convention of bending moment
Cb = block coefficient at design draft, based on the and shear force is as shown in Figure 3/6.1.
length, L, measured on the design load
waterline. Cb is not to be taken as less than
0.45 for L < 35m (115 ft) or 0.6 for L ≥ 61m FIGURE 3/6.1
(200 ft). Cb for lengths between 35m (115 ft) Sign Convention
and 61m (200ft) is to be determined by
interpolation.
 V 
+ 1.2 0 
K3 = (0.70 + 0.30  L ) SI/MKS units,
 
 3 .6 4 
 

 V 
+ 0 .6 6 
(0.70 + 0.30  L ) US Units;
 
 2 .0 1 
 

PART 3 SECTION 6|1 Primary Hull Strength


2 Wave Bending Moment Amidships The wave or
bending moment, expressed in kN-m (tf-m, Ltf-ft), may
∆ Lw
be obtained from the following equations.
( )
2
SM = 7 8 Yc g − 1 2 8 Y A − 5 0 C Q cm m
C2
2 -3
Mws = -k1C1L B(Cb + 0.7) x 10 Sagging Moment (in2ft)

Mwh = +k2C1L2BCb x 10-3 Hogging Moment


where:
k1 = 110 (11.22, 1.026)
k2 = 190 (19.37, 1.772) ∆ = maximum craft displacement in metric tons
(long tons)
C1, L, B, and Cb are as defined in 3/6.1.1a Lw = length of craft on design waterline in m (ft.)
3 Section Modulus The required hull-girder YF = vertical acceleration at forward end, generally
section modulus for 0.4L amidships is to be obtained taken as 1.2ncg, however where L is greater
from the following equation. than 61 meters, or where Vk is greater than 35
knots, it is to be determined by model tests
M t K 3 CQ and submitted for review.
SM = cm2m (in2ft)
ncg = as defined in 3/8.1.1
fp
C2 = 1320 SI and MKS units or 8380 US units
Ycg = vertical acceleration at longitudinal center of
K3, C, and Q are as defined in 3/6.1.1a
gravity, average 1/10 highest accelerations, in
In the case of restricted ocean service, consideration
g’s. Where Ycg is not submitted by the
may be given to a seakeeping analysis based on craft
designer, it is to be taken as not less than
speed and sea state to determine Mws and Mwh. In such
0.6ncg, where ncg is as given in 3/8.1.1a.
cases K3 and Fs are to be taken as 1.0
However, where L is greater than 61 m (200
ft), or where Vk is greater than 35 knots, the
Mt = Msw+MwFs
vertical acceleration is to be determined by
Msw = maximum still-water bending moment in the
model tests and submitted for review.
hogging condition and the sagging condition
YA = vertical acceleration at aft end. In general,
in kN-m (tf-m, Ltf-ft), generally Msw is not to
this is to be taken as 0, however where L is
be taken less than 0.5 Mws.
greater than 61 meters, or where Vk is greater
Mw = maximum wave induced bending moment in
than 35 knots, it is to be determined by model
kN-m (tf-m, Ltf-ft) as determined in
tests and submitted for review.
3/6.1.1(b)(2)
C = coefficient given in 3/6.1.1a
fp = 17.5 kN/cm2, (1.784 tf/cm2, 11.33ltf/in2)
Q = material coefficient given in 3/6.1.1a
Fs = restriction factor based on significant wave
Where displacement and speed vary with loading
height as shown in Table 3/6.1
condition, calculation above is to be performed for all
possible combinations of displacement and speed.
Table 3/6.1 Service Factor, Fs
3/6.1.2 Extension of Midship Section Modulus
Area of Significant Wave Height m (ft) Fs Where the still-water bending moment envelope is not
Operation submitted or where 3/6.1.1a or 3/6.1.1c govern, the
Unrestricted h1/3 ≥ 4.0 (13.0) 1.00 scantlings of all continuous, or effectively developed,
Service longitudinal material is to be maintained within the
Restricted 3.5 ≤ h1/3 ≤ 4.0 (11.5 ≤ h1/3 ≤ 13.0) 0.80 0.4L amidships and gradually tapered beyond.
Service
2.0 ≤ h1/3 ≤ 3.5 (8.5 ≤ h1/3 ≤ 11.5) 0.70 Where the scantlings are based on the envelope
0.5 ≤ h1/3 ≤ 2.5 (1.5 ≤ h1/3 ≤ 8.5) 0.50 curve of still-water bending moments, items included
in the hull-girder section modulus amidships are to be
c Planing and Semi-planing Craft Where the craft extended as necessary to meet the hull-girder section
speed exceeds 25 knots, the hull-girder section modulus required at the location being considered.
modulus is also to be not less than obtained by the The envelope curve of Mws and Mwh may be
following equations, whichever is greater: obtained by multiplying the midship value by the
distribution factor M in Figure 3/6.2.
∆ Lw
( )
2
SM = 1 2 8 Y F − 1 7 8 Yc g − 5 0 C Q cm m
C2
(in2ft)

PART 3 SECTION 6|2 Primary Hull Strength


FIGURE 3/6.2 All longitudinals of deck, sides, bottom, and
Distribution Factor M inner bottom

b Effective Areas Included in the Calculation In


general, the net sectional areas of longitudinal strength
members are to be used in the hull girder section
modulus calculations, except that small isolated
openings need not be deducted provided the openings
and the shadow area breadths of other openings in any
one transverse section do not reduce the section
modulus by more than 3%. The breadth or depth of
such openings is not to be greater than 25% of the
breadth or depth of the member in which it is located
with a maximum of 75 mm (3 in.) for scallops. The
shadow area of an opening is the area forward and aft
3/6.1.3 Moment of Inertia
of the opening enclosed by the lines tangential to the
The hull-girder moment of inertia, I, at amidships is to corners of the opening intersecting each other to form
be not less than given by the following equation: an included angle of 30 degrees.
L SM cm2m2 (in2ft2)
I = c Section Modulus to the Deck or Bottom The
Q K section modulus to the deck or bottom is obtained by
where: dividing the moment of inertia by the distance from
I = required hull girder inertia, in cm2m2 (in2ft2) the neutral axis to the molded deck at side amidships
SM = required hull girder section modulus in or baseline, respectively. Where a long deckhouse or
3/6.1.1,a b or c, whichever is greatest, in superstructure is considered as part of the hull girder,
cm2m (in2ft) the section modulus to the deck is obtained by
K = factor dependent on material and service as dividing the moment of inertia by the distance from
given in Table 3/6.2 the neutral axis to the top of the bulwark, deckhouse or
superstructure.
L and Q are as defined in 3/6.1.1.a.
3/6.1.5 Hull Girder Shear Strength Calculation
Table 3/6.2 Factor, K
Steel Aluminum FRP - For Craft 61m (200 ft.) in Length and
(ABS Basic Over
Laminate)1 a General The nominal total shear stresses due to
Restricted Service 40 13.33 1.8 still-water and wave-induced loads are to be based on
L < 90 m
the maximum algebraic sum of the shear force in still-
Unrestricted Service 50 13.33 1.8
L < 90 m water, Fsw , and the wave indicated shear force, Fw , at
Unrestricted Service 33.3 11.1 1.5 the location being considered. The thickness of the
L > 90 m side shell is to be such that the nominal total shear
stress as obtained by 3/6.1.5c are not greater than
Note: For fiber reinforced plastic laminates that are greater than 11.0/Q kN/cm2 (1.122/Q tf/cm2, 7.122/Q Ltf/in.2)
the ABS basic laminate (as defined in Part 2, Section 5) the
value of K can be adjusted by the ratio of Eo/Eb where
where Q is as defined in 3/6.1.1a. Consideration is
Eo = the elastic modulus of the actual hull laminate, also to be given to the shear buckling strength of the
in N/mm2 (kgf/mm2, psi) side shell plating.
Eb = 6890 N/mm2 (703 kgf/mm2, 1 × 106 psi) b Wave Shear Forces The envelopes of
maximum shearing forces induced by waves Fw as
3/6.1.4 Section Modulus and Moment of Inertia shown in Figures 3/6.3 and 3/6.4 may be obtained
Calculation from the following equations.
a Items Included in the Calculation In general,
the following items may be included in the calculation Fwp = +kF1C1LB(Cb + 0.7) x 10-2 For positive shear
of the section modulus and moment of inertia provided force
they are continuous or effectively developed within
Fwn = -kF2C1LB(Cb + 0.7) x 10-2 For negative shear
midship 0.4L, have adequate buckling strength, and
force
are gradually tapered beyond the midship 0.4L.

Deck plating (strength deck and other effective Fwp, Fwn = maximum shearing force induced by wave
decks) in kN (tf, Ltf)
Shell and inner bottom plating k = 30 (3.059, 0.2797)
Deck and bottom girders F1 = distribution factor as shown in Figure 3/6.3
Plating and longitudinal stiffeners of longitudinal F2 = distribution factor as shown in Figure 3/6.4
bulkheads C1, L, B, and Cb are as defined in 3/6.1.1a

PART 3 SECTION 6|3 Primary Hull Strength


FIGURE 3/6.3 d Hull-girder Shear Strength - FRP Craft Hull-
Distribution Factor F1 girder shear strength will be specially considered on
fiber reinforced plastic craft over 61m (200ft.) in
length.
e Craft of unusual proportion Craft having
unusual proportions will be specially considered.

3/6.1.6 Hull Girder Torsional Loads


Torsional calculations may be required for craft with
large deck openings. Racking load calculations may
be required for craft with tall superstructures.

3/6.3 Primary Hull Strength - Twin-Hulled


Craft

3/6.3.1 Longitudinal Hull Girder Strength


The longitudinal strength requirements for twin-hulled
FIGURE 3/6.4 craft are as given in 3/6.1. With the following
Distribution Factor F2 modifications
i B is to be taken as the sum of the waterline
breadths of each hull.
ii For craft less than 61m (200ft) longitudinal
shear strength need not be considered unless they have
unusual or highly concentrated loads. For craft over
61m (200ft) the shear strength will be specially
considered.
iii Items as listed in 3/6.1.3 may be included in
the longitudinal strength calculation for the total cross
section of the hulls, with the addition of the cross deck
bridging structure.

3/6.3.3 Transverse and Torsional Bending


Moments and Shear Force
c Shear Strength For craft without continuous The transverse primary bending moments and shear
longitudinal bulkheads, the nominal total shear stress fs force for the hull bridging structure (i.e. cross
in the side shell plating may be obtained from the structure) are obtained from the following equations:
following equation.
Mtb = K1∆Bcln kN-m (kgf-m, ft-lbs)
fs = (Fsw + FsFw)m/2tsI
Mtt = K2∆Ln kN-m (kgf-m, ft-lbs)
fs = nominal total shear stress in kN/cm2 (tf/cm2,
Ltf/in.2)
Qt = K1∆n kN (kgf, lbs)
I = moment of inertia of the hull girder section in
cm4 (in.4) at the section under consideration
Mtb = design transverse bending moment acting
m = first moment in cm3 (in.3), about the neutral
upon the cross structure connecting the hulls.
axis, of the area of the effective longitudinal
Mtt = design torsional moment acting upon the
material between the horizontal level at
cross structure connecting the hulls.
which the shear stress is being determined
Qt = design vertical shear force acting upon the
and the vertical extremity of effective
cross structure connecting the hulls.
longitudinal material, taken at the section
K1 = 2.5 (0.255, 0.255)
under consideration.
K2 = 1.25 (0.1275, 0.1275)
ts = thickness of the side shell plating in cm (in.)
∆ = craft displacement in tonnes (kg, lbs).
at the position under consideration.
Bcl = distance in meters or feet between the hull
Fsw = hull-girder shearing force in still-water in kN
centerlines.
(tf, Ltf)
L = length of craft in meters or feet as defined in
Fw = Fwp or Fwn as specified by 3/6.1.4b,
3/1.1.
depending upon loading.
n = vertical acceleration at the craft’s center of
Fs is as defined in 3/6.1.1b
gravity, see 3/8.1.1

PART 3 SECTION 6|4 Primary Hull Strength


3/6.3.4 Catamaran and SES Transverse and 3/6.3.6 Craft With More Than Two Hulls
Torsional Section Modulus and Shear Transverse and Torsional Strength of craft with more
Area than two hulls will be specially considered.
The required transverse section modulus and shear
area for catamarans and surface effect craft are 3/6.4 Strength Considerations for Hydrofoil
obtained from the following equations: Borne Craft

SMtb = Mtb/σa cm2m (in2ft) 3/6.4.1 Longitudinal Strength


The craft’s weight curve showing full load, light ship,
SMtt = Mtt/σab cm2m (in2ft) and partial load if more severe is to be submitted. The
support reactions for each of the hydrofoils are to be
Ast = Qt/τa cm2 (in2) shown. The resulting shear and bending moment
diagrams, as derived from these curves, are to be
SMtb= required section modulus of the cross submitted for approval.
structure Hull deflection under the condition of maximum
SMtt= required torsional section modulus of the bending moment is not to exceed 1/200 of the distance
cross structure between the forward and aft foil attachment points.
Ast = required shear area of the cross structure
Mtb = design transverse bending moment acting 3/6.4.2 Calculation of Loads from Hydrofoil
upon the cross structure connecting the hulls. Appendages
Mtt = design torsional moment acting upon the The maximum forces transmitted by any hydrofoil to
cross structure connecting the hulls. the craft structure is given by the following equations:
Qt = design vertical shear force acting upon the
cross structure connecting the hulls. FL = CUCLV2AP
σa = 0.66σy, tensile or compressive stress.
τa = 0.38σy, shear stress. FD = CUV2(CDFAFF + CDSAFS) + (Wetted surface drag)
σab = 0.75σy, combined or von Mises stress.
σy = minimum yield stress of the material, for FL = maximum lift force on craft exerted by
aluminum the yield stress is to be for the hydrofoil in kgf (lbs). This force is assumed
unwelded condition. to act perpendicular to the plane of the foil.
FD = maximum drag force on craft exerted by
3/6.3.5 Items included in Transverse Moment of hydrofoil plus strut in kgf (lbs). This force is
Inertia and Section Modulus Calculation assumed to act directly aft from the center of
The following items may be included in the calculation the foil.
of the transverse section modulus and moment of CU = 13.847 (2.835)
inertia provided that are continuous or effectively CL = peak coefficient of lift for the foil selected.
developed over the entire breadth of the cross structure CDF = peak coefficient of drag for the foil selected.
or wet deck, and have adequate buckling strength: CDS = peak coefficient of drag for the strut section
selected.
Deck plating, main deck and bottom shell of wet deck V = maximum craft speed in knots.
Transverse stiffeners on wet deck AP = plan view area of foil in m2 or ft2
Transverse bulkheads or web frames which span the AFF = frontal area of foil in m2 or ft2
wet deck AFS = frontal area of strut in m2 or ft2
Transverse girders or box beams
Continuous transom plating and horizontal stiffeners Total drag of foil and the strut (or similar appendage)
attached is the drag term as shown above, plus the frictional
drag of skin friction coefficient, as a function of
In general, the effective sectional area of the deck
wetted surface and Reynolds number.
for use in calculating the section modulus is to exclude
hatchways and other large openings in the deck. The bending moment of the foil and appendage
Superstructures and house tops are generally not to that acts on its attachment to the hull is to be
be included in the calculation of sectional properties of calculated and compared to the strength of the
the cross structure. Craft having unusual configuration connection. A safety factor of 2.0 against the
or large bracketed overhead “bent” type structures will maximum combined lift and drag loads is the
be specially considered minimum acceptance criteria. Calculations for
See appendix 3/B for guidance on calculating the bending moment, stiffness, and shear are to be carried
offered torsion strength of the craft. out and submitted by the designer.

PART 3 SECTION 6|5 Primary Hull Strength


Additionally, calculations supporting the “Fail- 3/6.9 Operating Manual
Safe” performance of each foil attachment structure Craft are to be furnished with an operating manual
are to be submitted. providing guidance on;
Watertight integrity of the shell is to be maintained a loading conditions on which the design of the
in the event of a collision of hydrofoil appendages craft has been based, including cargo loading on
with a solid object underwater. A design safety factor decks, loading ramps, and double bottoms.
of 3.0 against the yield strength or 2.0 against the b permissible limits of still-water bending
ultimate strength of the foil strut bearing are to be used moments and shear forces, for craft 61m (200 ft.) in
to assess the strength of the foil for the collision length or greater.
condition. c maximum operational speeds for the various sea-
3/6.5 Effective Decks states (significant wave heights) in which the craft is
To be considered effective for use in calculating the intended to operate.
hull girder section modulus, the thickness of the deck d other operational limits as applicable such as
plating is to comply with the requirements of Section distance from place of refuge.
3/9. The deck areas are to be maintained throughout
the midship 0.4L and may be gradually reduced to one
half their midship value at 0.15L from the ends. Only
that portion of deck which is continuous through the
transverse structure may be considered effective.

PART 3 SECTION 6|6 Primary Hull Strength


PART 3 SECTION 8

Design Pressures
3/8.1 Monohulls nxx = average of the 1/100 highest vertical
accelerations, at any section clear of LCG, in
3/8.1.1 Bottom Structure Design Pressure g’s. Can be determined by the following
The minimum bottom design pressure is to be the equation:
greater of a or b as given in the following equations, nxx = ncgKv
for the location under consideration. Bottom
N1 = 0.1 (.01, .069)
structure design pressures are dependent upon the
N2 = 0.0078 (0.0078, 0.0016)
service in which the craft operates. The bottom
N3 = 9.8 (1.0, 0.44)
pressure herein calculated applies to hull bottoms
below the chines or the turn of the bilge. ∆ = displacement at design waterline in kg or lbs
Lw = craft length on the waterline with the vessel
a Bottom Slamming Pressure at the design displacement and in the
displacement mode, in m or ft
N1∆
pbcg = [1 + ncg ]F D kN/m2 (tf/m2, psi) Bw = maximum waterline beam, in m or ft
Lw B w H = wave parameter, 0.0172L + 3.653m
 70 − β xx  (0.0172L + 11.98ft)
N1∆
pbxx = [1 + n xx ]  FD kN/m2 h1/3 = significant wave height, m (ft) for the sea
Lw B w  70 − β 
cg  state being considered, generally not to be
taken as less than Lw/12 except for restricted
(tf/m2, psi)
service operation as given in Table 3/8.1.
for craft less than 61m (200ft), pbxx may be taken as: τ = running trim at V, in degrees, but generally
not to be taken less than 4° for craft L<50m
N 1∆ (165 ft), nor less than 3° for L <125m
pbxx = [1 + ncg ]F D Fv kN/m2 (tf/m2, psi) (410ft). Special consideration will be given
Lw B w to designers values predicted from model
tests.
b Hydrostatic Pressure βcg = deadrise at LCG, degrees, generally not to
be taken less than 10° nor more than 30°.
pd = N 3 ( Fs H + d ) kN/m2 (tf/m2, psi) βxx = deadrise at any section clear of LCG, in
degrees, not to be taken less than 10° or
pbcg = bottom design pressure at LCG, kN/m2 greater than 50°
(tf/m2, psi) V = craft design speed in knots, generally
pbxx = bottom design pressure at any section clear maximum speed in calm water; considering
of LCG, kN/m2 (tf/m2, psi) service needs to limit vertical accelerations,
pd = bottom design pressure based on hydrostatic design service speeds may vary with
forces, kN/m2 (tf/m2, psi) significant wave height provided guidance is
ncg = average of the 1/100 highest vertical given in Operating Manual.
accelerations at LCG, corresponding to the FD = design area factor given in Figure 3/8.1 for
sea state, in g’s. g’s are the dimensionless given values of AD and AR. Generally not to
ratio of the acceleration to gravitational be taken less than 0.40.
acceleration at sea level (9.8 m/s2, 32.2 KV = vertical acceleration distribution factor given
ft/s2). Can be determined by the following in Figure 3/8.2.
equation: FV = vertical acceleration distribution factor given
in Figure 3/8.3.
 12 h 1 / 3  V 2
(B )2 g’s
n cg = N 2  + 1 . 0  τ [ 50 − β cg ] w AD = design area, cm2 (in2). For plating it is the
 Bw  ∆
actual area of the shell plate panel but not to
be taken as more than 2s2. For longitudinals,
stiffeners, transverses and girders it is the
shell area supported by the longitudinal

PART 3 SECTION 8|1 Design Pressures


stiffener, transverse or girder; for transverses ps = side design pressure due to hydrostatic
and girders the area used need not be taken forces, in kN/m2 (tf/m2, psi), but is not to be
less than 0.33l2. taken less than the following:
AR = reference area, cm2 (in2), 6.95∆/d cm2 = 0.05N3L kN/m2 (tf/m2, psi) at or below L/15
(1.61∆/d in2) above the base line or at any height above
s = spacing of longitudinals or stiffeners, in cm base line forward of 0.125L from the stem.
or in. = 0.033N3L kN/m2 (tf/m2, psi) above L/15
l = length of unsupported span of internals. See above the base line, aft of 0.125L from the
3/10.1.2a. stem.
d = stationary draft, in m or ft, vertical distance psf = side design pressure for forward of 0.125L
from outer surface of shell measured at from the stem.
centerline to design waterline at middle of y = distance above base line, m or ft, of location
design waterline length, but generally not to being considered.
be taken as less than 0.04L. L = craft length as defined in Section 3/1.1,
generally not to be taken less than 30m (98
Table 3/8.1 ft.)
Fs = factor as given in table 3/8.1
Area of Operation Significant Wave Height, m(ft) Fs CF = 0.0125L for L < 80m (0.00381L for L < 262
Unrestricted h1/3 ≥ 4.0 (13.0) 1.00 ft)
service
= 1.0 for L ≥ 80m (262 ft)
Restricted service 3.5 ≤ h1/3 ≤ 4.0 (11.5 ≤ h1/3 ≤ 13.0) 0.80
2.5 ≤ h1/3 ≤ 3.5 (8.5 ≤ h1/3 ≤ 11.5) 0.70 α = flare angle, the angle between a vertical line
0.5 ≤ h1/3 ≤ 2.5 (1.5 ≤ h1/3 ≤ 8.5) 0.50 and the tangent to the side shell plating,
measured in a vertical plane at 90° to the
3/8.1.2 Side and Transom Structure, Design horizontal tangent to the side shell.
Pressure β = entry angle, the angle between a longitudinal
The side design pressure, Ps is to be not less than line, parallel to the centerline and the
given by the equations: horizontal tangent to the side shell.

a Slamming Pressure 3/8.3 Hydrofoils, Air Cushion Vehicles, Surface


Effect Craft, and Multi-hull Craft
N1∆  70 − β xx 
p sxx = (1 + n xx )  FD kN/m2
Lw Bw  70 − β cg  3/8.3.1 Bottom Structure Design Pressure
  The minimum bottom design pressure is to be the
(tf/m2, psi) greater of a or b as given in the following equations,
for the location under consideration. Bottom
b Hydrostatic Pressure structure design pressures are dependent upon the
service in which the craft operates. The bottom
ps = N 3 ( Fs H + d − y ) kN/m2 (tf/m2, psi) pressure herein calculated applies to hull bottoms
below the chines or the turn of the bilge for
c Fore End catamarans, trimarans or other multihulled craft,
surface effect ship, and foil-borne craft. Twin hull
bottom of surface effect ships shall be considered as
psf = 028 . tanα)(04
. + 015
. Fs CF N3 (022 . V sin β + 06
. L) 2 catamaran hulls for purpose of calculation of the
kN/m2 (tf/m2) bottom slamming pressure.
psf = 092 . tanα)(04
. + 015
. Fs CF N3 (022 . V sin β + 033
. L)2
a Bottom Slamming Pressure
psi N 1∆
pbcg = [1 + ncg ]F D kN/m2 (tf/m2, psi)
N1, N3, ∆, Lw, V, nxx, βcg, H, d, and FD are as defined Lw N h B w
in 3/8.1.1. N1∆  70 − β xx 
pbxx = [1 + n xx ]  FD kN/m2
Bw = maximum waterline beam, in m or ft Lw N h B w  70 − β 
cg 
βxx = deadrise at any section clear of LCG, (tf/m2, psi)
degrees, not to be taken less than 10° and
not greater than 70°
psxx = side design pressure at any section clear of
LCG, in kN/m2 (tf/m2, psi)

PART 3 SECTION 8|2 Design Pressures


b Hydrostatic Pressure = 0.033N3L kN/m2 (tf/m2, psi) above L/15
pd = N 3 ( Fs H + d ) kN/m2 (tf/m2, psi) above the base line, aft of 0.125L from the
stem.
pbcg, pbxx, N1, N2, N3, ∆, Lw, V, ncg, FD, nxx, βxx, βcg, H, psf = side design pressure for forward of 0.125L
d, and FD are as defined in 3/8.1.1. from the stem.
y = distance above base line, m or ft, of location
ncg = average of the 1/100 highest vertical being considered.
accelerations at LCG, corresponding to the L = craft length as defined in Section 3/1.1
sea state, in g’s. Can be determined by the Fs = factor as given in table 3/8.1
following equation: CF = 0.0125L for L < 80m (0.00381L for L < 262
 12 h 1 / 3  V 2
( BN )2 ft)
n cg = N  + 1 . 0  τ [ 50 − β ] h
2
 w h
B N 
cg
∆ = 1.0 for L ≥ 80m (262 ft)
g’s α = flare angle, the angle between a vertical line
and the tangent to the side shell plating,
Bw = maximum waterline beam of one hull in m or
measured in a vertical plane at 90° to the
ft.
horizontal tangent to the side shell.
Nh = number of hulls
β = entry angle, the angle between a longitudinal
3/8.3.2 Side and Transom Structure, Design line, parallel to the centerline and the
Pressure horizontal tangent to the side shell.
The side design pressure, Ps is to be not less than
given by the equations: 3/8.3.3 Wet Deck or Cross Structure
The wet deck design pressure is to be determined by
a Slamming Pressure the greater of the following equations:

N1 ∆  70 − β xx 
p sxx = (1 + n xx )  FD kN/m2  ∆   GA 
Lw N h Bw  70 − β cg



pwd = N1  [Hb +nxx]1− FD
0.33(2LwNhBw +LwdWwd)  HW 
(tf/m2, psi) kN/m2 (tf/m2, psi)
b Hydrostatic Pressure
pwd = 0.20 pbxx FD kN/m2 (tf/m2, psi)
ps = N 3 ( Fs H + d − y ) kN/m2 (tf/m2, psi)
∆, Lw, ncg, pbxx, and FD are as defined in 3/8.1.1
N1 = 0.10 (0.010, 0.069)
c Fore End Bw = waterline beam of one hull in m or ft.
Nh = number of hulls
psf = 028 . tanα)(04
. + 015
. FsCF N3 (022 . V sinβ + 06
. L)2 Lwd = length of wet deck, overall, in m or ft.
kN/m2 (tf/m2) Wwd = width of wet deck between hull sides in m or
ft.
psf = 092
. FC
s F N3 (022 . tanα)(04
. + 015 . V sinβ + 033
. L)2 Hb = 1.0 for catamarans or hull borne surface
psi effect ship
= 0.0 for cushion-borne surface effect ship.
N1, N3, ∆, Lw, V, nxx, βcg, H, d, and FD are as defined GA = vertical distance, in m or ft., from lightest
in 3/8.1.1. Nh is as defined in 3/8.3.1 draft waterline to underside of wet deck, at
design point in question.
Bw = maximum waterline beam, in m or ft L L
βxx = deadrise at any section clear of LCG, Hw = 5[n cg ][ ] or h1/3 (from 3/8.1.1)
V 6 + 14 L
degrees, not to be taken less than 10° and whichever is greater, in m or ft.
not greater than 70°
psxx = side design pressure at any section clear of 3/8.4 Deck Design Pressures - All Craft
LCG, in kN/m2 (tf/m2, psi) The design pressures, Pd, are to be as given in Table
ps = side design pressure due to hydrostatic 3/8.2.
forces, in kN/m2 (tf/m2, psi), but is not to be
taken less than the following: 3/8.5 Superstructures and Deckhouses - All
= 0.05N3L kN/m2 (tf/m2, psi) at or below L/15 Craft
above the base line or at any height above The design pressures, Pd, are to be as given in Table
base line forward of 0.125L from the stem. 3/8.3.

PART 3 SECTION 8|3 Design Pressures


a. 0.01L + 0.15 m (0.01L + 0.5 ft)
3/8.6 Bulkhead Structure, Design Pressure - All b. 0.46 m (1.5 ft)
Craft Where L is the craft length as defined in
3/1.1
3/8.6.1 Tank Boundaries The heights of overflows are to be clearly
The design pressure for tank boundaries is to be not indicated on the plans submitted for approval.
less than given by the following equation: Pressurized tanks will be subject to special
consideration.
pt = N3h kN/m2 (tf/m2, psi)
3/8.6.2 Watertight Boundaries
N3 = as defined in 3/8.1.1. The design pressure for watertight boundaries is to be
h = greatest of the following distances in m or ft not less than given by the following equation:
from lower edge of plate panel or center of
area supported by stiffener, to: pw = N3h kN/m2 (tf/m2, psi)
1 A point located above the top of the tank, at
a distance of two-thirds the height from the N3 = as defined in 3/8.1.1.
top of the tank to the top of the overflow. h = distance in m or ft from the lower edge of
2 A point located at two-thirds of the distance plate panel or the center of area supported
to the main weather deck. by the stiffener to the bulkhead deck at
3 A point located above the top of the tank, centerline.
not less than the greater of the following:

Table 3/8.2 Deck Design Pressures, pd

2 2
Location kN/m tf/m psi
Exposed freeboard deck, and superstructure deck for 0.25L 0.20L + 7.6 0.020L + 0.77 0.0088L + 1.10
from forward
Freeboard deck inside enclosed superstructures, exposed 0.10L + 6.1 0.010L + 0.62 0.0044L + 0.88
superstructure deck aft of 0.25L forward, internal decks
Enclosed accommodations decks 5.0 0.50 0.71
W (1 + 0 .5 n x x ) W (1 + 0 .5 n x x ) W (1 + 0 .5 n x x )
1
Concentrated deck cargo loads

Enclosed store rooms, machinery spaces, etc. c h (1 + 0 .5 n xx ) c h (1 + 0 .5 n xx ) c h (1 + 0 .5 n xx )

Note:1) Concentrated deck cargo loads are in kN, tf, and Ltf respectively.
W = deck cargo load in kN/m2 (tf/m2 or psi)
nxx = average vertical acceleration at the location under consideration as defined in 3/8.1.1
c = 7.04 (0.715, 0.02)
h = height of enclosed store room, machinery space, etc., in m or ft.
L = craft length as defined in 3/1.1

Table 3/8.3 Superstructures and Deckhouses Design Pressures

Location L = 12.2m (40 ft.) & less L > 30.5m (100 ft)
2 2 2 2
kN/m (tf/m , psi) kN/m (tf/m , psi)
Superstructure and Deckhouse Front Plating 24.1 (2.46, 3.5) 37.9 (3.87, 5.50)
Superstructure and Deckhouse Front Stiffeners 24.1 (2.46, 3.5) 24.1 (2.46, 3.5)
Superstructure and Deckhouse Aft End and House Side Plating 10.3 (1.05, 1.5) 13.8 (1.41, 2.0)
Superstructure and Deckhouse Aft End and House Side Stiffeners 10.3 (1.05, 1.5) 10.3 (1.05, 1.5)
House Tops, Forward, Plating and Stiffeners 6.9 (0.70, 1.0) 8.6 (0.88, 1.25)
House Tops, Aft, Plating and Stiffeners 3.4 (0.35, 0.5) 6.9 (0.70, 1.0)

Note: For craft between 12.2 and 30.5m (40 and 100ft), design pressure is to be obtained by interpolation.
L = craft length as defined in 3/1.1

PART 3 SECTION 8|4 Design Pressures


PART 3 SECTION 8|5 Design Pressures
PART 3 SECTION 8|6 Design Pressures
PART 3 SECTION 8|7 Design Pressures
PART 3 SECTION 9

Plating
3/9.1 Aluminum or Steel C2 = 1.21 where stiffeners are T-sections or angle
bars
3/9.1.1 General = 1.10 where stiffeners are bulb plates
The bottom shell is to extend from the keel to the = 1.05 where stiffeners are flat bars
chine or upper turn of bilge. In general the side shell
is to be of the same thickness from its lower limit to 2 Critical Buckling Stress The critical buckling
the gunwale. stress in compression, σc, is determined as
follows:
3/9.1.2 Thickness
The thickness of the shell, deck or bulkhead plating is σc = σE when σE ≤ 0.5σy
to be not less than obtained by the following
 σy 
equations, whichever is greater: = σ y 1 −  when σE>0.5σy
a Lateral Loading  4σ E 
σy = yield stress of material, in N/mm2 (kgf/mm2,
pk pk psi).
t=s mm t = s in σE
1000σ a σa = elastic buckling stress calculated in
3/9.1.2b(1)

s = the spacing, in mm or in., of the shell, deck, 3 Calculated Compressive Stress The
superstructure, deckhouse or bulkhead compressive stresses are given in the following
longitudinals or stiffeners. formula
p = design pressure in kN/m2(tf/m2, psi) given in
Section 3/8 ( Fs M w + M sw ) y
k = plate panel aspect ratio factor, given in σ a = c5 N/mm2 (kgf/mm2,
Table 3/9.1 I
σa = design stress, in N/mm2 (kgf/mm2, psi), psi)
given in Table 3/9.2
σa = working compressive stress in panel being
b Buckling Strength considered, N/mm2 (kgf/mm2, psi), but
1 Elastic Buckling Stress generally not less than the following:
2
t 
σE = 0.9mE  b  N/mm2 (kgf/mm2, psi) SM R
 s fp N/mm2 (kgf/mm2, psi)
SM A
σE = elastic buckling stress in N/mm2 (kgf/mm2,
Fs = as given in Table 3/8.1
psi).
c5 = 105 (105 , 322,560)
m = 4.0 for longitudinally framed shell and deck
Mw = wave bending moment as given in
plating.
3/6.1.1b(3), kN-m (tf-m, Ltf-ft)
  s 2 
2
Msw = still water bending moment as given in
= C2 1+    , for transversely framed
 l 
3/6.1.1b(2), kN-m (tf-m, Ltf-ft)
y = vertical distance in m or ft from the neutral
shell and deck plating. axis to the considered location.
E = for steel; 2.06 x 105 N/mm2 (21,000 I = moment of inertia of the hull girder, cm4
kgf/mm2, 30 x 106 psi) (in4).
for aluminum; 6.9 x 104 N/mm2 (7,000 fp = 175 N/mm2 (24 kgf/mm2, 34,000 psi).
kgf/mm2,10 x 106 psi) SMR = hull girder section modulus as required in
tb = thickness of plating in mm or in. 3/6, cm2m (in2ft)
s = shorter side of plate panel in mm or in. SMA = section modulus of the hull girder at the
l = longer side of plate panel in mm or in. location being considered, cm2m (in2ft)

PART 3 SECTION 9|1 Plating


4 Permissible Buckling Stress The design tal = 0.52 L + 10
. mm
buckling stress, σc, of plate panels (as calculated
in 3/9.1.1b(2)) is to be such that: tal = 0.011 L + 0.04 in.
ts, tal, and L are as defined in 3/9.1.2(c)(1). However,
σc ≥ σa ts is not to be taken less than 3.0 mm (0.12 in.) and tal
is not to be taken less than 3.5mm (0.14 in.).
c Minimum Thickness The thickness of shell 5 Shell Reinforcement The thickness of the
plating, decks and bulkheads is to be not less than shell plating is to be increased 50% in way of
obtained from the following equations: skegs, shaft struts, howse pipes etc. Bow
1 Bottom Shell thruster tube thickness is to be equivalent to the
t s = 0.44 KL + 2.0 mm surrounding shell thickness.
t s = 0.009 KL + 0.08 in. d Wheel Loading Where provision is to be
t al = 0.70 L + 1.0 mm made for the operation or stowage of vehicles having
rubber tires, and after all other requirements are met,
t al = 0.015 L + 0.04 in. the thickness of steel deck plating is to be not less
ts = required thickness for steel craft, not to be than obtained from the following equation. Required
taken less than 3.5mm (0.14 in.) deck thickness for aluminum decks will be subject to
tal = required thickness for aluminum craft, not to special consideration.
be taken less than 4.0mm (0.16 in.)
L = craft length as defined in 3/1.1
= (ny/y)e  n 
K t = kKn 1.1W 1 + xx  mm (mm, in)
ny = 235 N/mm2 (24 kgf/mm2, 34,000 psi)  2 
y = specified minimum yield strength of the
material, in N/mm2 (kgf/mm2, psi), but is not k = 8.05 (25.2, 1)
to be taken greater than 0.7U or 510 N/mm2 K = as given in Figure 3/9.1
(52 kgf/mm2, 74,400 psi), whichever is less n = 1.0 where l/s > 2.0 and 0.85 where l/s = 1.0.
U = minimum tensile strength of the material For intermediate values of l/s, n is to be
used, in N/mm2 (kgf/mm2, psi) obtained by interpolation.
e = 1.0 for y ≤ 235 N/mm2 (24 kgf/mm2, 34,000 W = static wheel load in kN (tf, Ltf)
psi) nxx = average vertical acceleration at the location
= 0.75 for y > 235 N/mm2 (24 kgf/mm2, under consideration as defined in 3/8.1.1
34,000 psi) a = wheel imprint dimension, in mm or in,
2 Side Shell parallel to the longer edge, l, of the plate
t s = 0.40 KL + 2.0 mm panel, and in general the larger wheel
imprint dimension.
t s = 0.009 KL + 0.08 in. b = wheel imprint dimension, in mm or in,
t al = 0.62 L + 10
. mm perpendicular to the longer edge, l, of the
plate panel, and in general the lesser wheel
t al = 0.013 L + 0.04 in. imprint dimension.
ts, tal, and L are as defined in 3/9.1.2(c)(1). However, s = spacing of deck beams or deck longitudinals
ts is not to be taken less than 3.0 mm (0.12 in.) and tal in mm or in.
is not to be taken less than 3.5mm (0.14 in.). l = length of the plate panel in mm or in.
3 Strength Deck
t s = 0.40 KL + 1.0 mm For wheel loading, the strength deck plating thickness
is to be not less than 110% of that required by the
t s = 0.009 KL + 0.04 in. above equation, and platform deck plating thickness
tal = 0.62 L + 10
. mm is to be not less than 90% of that required by the
above equation.
tal = 0.013 L + 0.04 in. Where the wheels are close together, special
ts, tal, and L are as defined in 3/9.1.2(c)(1). However, consideration will be given to the use of the combined
ts is not to be taken less than 3.0 mm (0.12 in.) and tal imprint and load. Where the intended operation is
is not to be taken less than 3.5mm (0.14 in.). such that only the larger dimension of the wheel
4 Lower Decks, W.T. Bulkheads, Deep Tank imprint is perpendicular to the longer edge of the
Bulkheads plate panel, b above may be taken as the larger wheel
t s = 0.35 KL + 1.0 mm imprint dimension, in which case a is to be the lesser
one.
t s = 0.007 KL + 0.04 in.

PART 3 SECTION 9|2 Plating


FIGURE 3/9.1 Wheel Loading Curves of "K"

TABLE 3/9.1 - Aspect Ratio Coefficient for Isotropic Plates

l/s k k1
> 2.0 0.50 0.028
2.0 0.497 0.028
1.9 0.493 0.027
1.8 0.487 0.027
1.7 0.479 0.026
1.6 0.468 0.025
1.5 0.454 0.024
1.4 0.436 0.024
1.3 0.412 0.021
1.2 0.383 0.019
1.1 0.348 0.017
1.0 0.308 0.014
Note: s = shorter edge of plate panel in mm or in.
l = longer edge of plate panel in mm or in.

TABLE 3/9.2 - Design Stresses, σa, Aluminum and Steel Plating

Design Stress, σa,


Bottom and Side Shell Below Bulkhead 0.90σy
Deck with Slamming Pressure
Bottom and Side Below Bulkhead Deck 0.40σy
Hydrostatic Pressure
Side Shell above Bulkhead Deck - 0.90σy
Slamming Pressure
Side Shell above Bulkhead Deck - Sea 0.50σy
Pressure
Deck Plating - Strength Deck 0.60σy
Deck Plating - Lower Decks 0.60σy
Wet Deck Plating 0.90σy
Bulkheads - Tank Boundary 0.60σy
Bulkheads - Watertight 0.90σy
Superstructure and Deckhouses - Front, 0.60σy
Sides, Ends, Tops

Note: σy = yield strength of steel or of welded aluminum in N/mm2 (kgf/mm2, psi)

PART 3 SECTION 9|3 Plating


3/9.3 Fiber Reinforced Plastic
1 All Plating
3/9.3.1 General
The shell, decks and bulkheads may be either single pk pk
t = sc mm t = sc in
skin or sandwich construction. Where both are used, 1000σ a σa
a suitable transition is to be obtained between them
with a minimum 12: 1 taper ratio. 2 All Plating
The bottom shell is to extend to the chine or upper
bilge turn. A suitable transition is to be obtained pk 1 pk 1
between the bottom and side shell plating. The shell t = sc3 mm t = sc3 in
thickness in way of the keel is to be 50% greater and 1000k 2 E F k2 EF
in way of shaft struts and skegs is to be 100% greater
3 Strength deck and shell
than the thickness required by 3/9.3.3 equations a or
b, as applicable. For this purpose, pressure Pb as
obtained from 3/8.1.1 or 3/8.3.1 and actual frame t = k 3 (c1 + 0.26 L) q1 mm
spacing at the location of the member are to be used
t = k 3 (c1 + 0.0031L) q1 in.
for equation a. Suitable framing reinforcement is to
be provided in way of shaft struts. Bow thruster tube
thickness is to be equivalent to the surrounding shell
thickness. L is generally not to be taken less than 12.2m (40 ft).
The shell, deck or bulkhead laminates may be bi-
directional (having essentially same strength and 4 Strength deck and bottom shell
elastic properties in the two in-plane principal axes of
the shell, deck or bulkhead) or uni-directional (having s 0.6σ uc SM R
t= in mm or in.
different strength or elastic properties in the two kb Ec SM A
principal axes of the shell, deck or bulkhead panels).
Bonding angles or tapes are to have essentially same s = the spacing of the shell or deck longitudinals
strength and elastic properties as the plating laminate or superstructure, deckhouse or bulkhead
being bonded, and are in general to be in accordance stiffeners in mm or in., it is always to be the
with 3/14. lesser dimension of the unsupported plate
panels.
3/9.3.2 Fiber Reinforcement c = factor for plate curvature in the direction
The basic laminate given in 2/5 or other approved parallel to s, given by (1-A/s), but is not to
laminate of glass, aramid or carbon fiber in mat, be taken less than 0.70.
woven roving, cloth, knitted fabric or non-woven uni- A = distance in mm or in. measured
directional reinforcing plies may be used. Equivalent perpendicular from the chord length, s, to
strength and thickness of other than E-glass base
the highest point of the curved plate arc
laminate is to be assessed in a laminate stack
between the panel edges.
program on the basis of first ply failure, see Appendix
3/C for guidance. For the shell and deck a sufficient p = design pressure given in Section 3/8
number of plies are to be layed-up with the warp in k or k1= coefficient varying with plate panel aspect
the 0° (longitudinal) axis. Warp and fill directions ratio as given in Table 3/9.1
are to be aligned parallel to the respective edges of kb = 2.5 with longitudinal framing
the shell and deck panels as closely as practicable. = 2.5 with transverse framing and panel aspect
Depending on the directionality and fiber orientation ratio of 1.0
of these plies, other plies may be required or = 1.0 with transverse framing and panel aspect
permitted in the 90° (transverse) axis; reinforcing ratio of 2.0 to 4.0
plies in other axes such as + 45° (diagonal) may also σa = design stress given in Table 3/9.4
be used, when approved. k2 = for bottom plating; 0.015 for patrol boats
Where the strength and stiffness in the two and similar service craft, 0.01 for other craft.
principal axes of the panel are different, panel = for side plating; 0.020 for patrol boats and
bending in each of the panel principal axes is to be similar service craft, 0.015 for other craft.
considered. See 3/9.3.3b and 3/9.3.4b.
= for superstructures and deckhouse fronts;
0.025
3/9.3.3 Single Skin Laminate
= for other plating; 0.010
a With Essentially Same Properties in 0° and
EF = flexural modulus of laminate, in N/mm2
90° Axes The thickness of the shell, deck or (kgf/mm2, psi), in the direction parallel to s.
bulkhead plating is to be not less than given by the q1 = 170/F (17.5/F, 25,000/F)
following equations: L = craft length in m or ft as defined in 3/1.1

PART 3 SECTION 9|4 Plating


c1&k3 = factor for service and location, given in pk s
Table 3/9.3 1. t = sc mm
Ec = compressive modulus of elasticity in N/mm2 1000σ as
(kgf/mm2, psi)
pk s
F = minimum flexural strength of laminate, in t = sc in
N/mm2 (kgf/mm2, psi) σ as
σuc = minimum compressive strength of laminate
in N/mm2 (kgf/mm2, psi)
SMR = required hull-girder section modulus given pk l El
2. t = sc 4 mm
in Section 3/6 1000σ al Es
SMA = proposed hull-girder section modulus of
midship section. pk l El
t = sc 4 in
TABLE 3/9.3 - Fiber Reinforced Plastic Factor c1
σ al Es
and k3
s, c, and p as defined in 3/9.3.3
c1 k3 ks, kl = coefficient for plate panel aspect ratio,
Bottom Side Shell given in Table 3/9.5
mm (in.)
Shell & Deck σas = design stress, given in Table 3/9.4, based on
Unrestricted Service strength properties in the direction parallel
3.2 (0.125) 1.1 1.0
Restricted Service to s.
5.7 (0.225) 1.2 1.0 Es = flexural modulus of laminate, in N/mm2
(kgf/mm2, psi) in the direction parallel to s.
TABLE 3/9.4 - Design Stresses for FRP, σa σal = design stress, given in Table 3/9.4, based on
strength properties in the direction
Bottom Shell 0.33σu perpendicular to s.
Side Shell 0.33σu El = flexural modulus of laminate, in N/mm2
Decks 0.33σu (kgf/mm2, psi) in the direction
Superstructure and Deckhouses - 0.33σu perpendicular to s.
Front, Sides, Ends, and Tops
Tank Bulkheads 0.33σu TABLE 3/9.5 Aspect Ratio Coefficient for
Watertight Bulkheads 0.50σu Orthotropic Plates

ks kl
For single skin laminates: (l/s) 4 Es / El
σu = minimum flexural strength, in N/mm2 (kgf/mm2,
> 2.0 0.500 0.342
psi)
2.0 0.497 0.342
For sandwich laminates:
1.9 0.493 0.342
σu = for shell or deck outer skin, minimum tensile
1.8 0.487 0.342
strength, in N/mm2 (kgf/mm2, psi)
1.7 0.479 0.342
σu = for shell or deck inner skin, minimum 1.6 0.468 0.342
compressive strength, in N/mm2 (kgf/mm2, psi) 1.5 0.454 0.342
σu = for bulkheads, lesser of tensile or compressive 1.4 0.436 0.342
strength, in N/mm2 (kgf/mm2, psi) 1.3 0.412 0.338
Note: σu is to be verified from the approved test results. 1.2 0.383 0.333
See 2/5.5 1.1 0.348 0.323
< 1.0 0.308 0.308
b With Different Properties in 0° and 90° Axes
For laminates with different strength and elastic 3/9.3.4 Sandwich Laminate
properties in the 0° and 90° axes where the strength is a Laminate with essentially same bending
less or the stiffness greater in the panel direction strength and stiffness in 0° and 90° axes In general
perpendicular to s, the thickness is to be also not less the outer and inner skins are to be similar in lay-up
than given by the following equations: and in strength and elastic properties. Special
consideration will be given where this is not the case.
In general, single skin laminate is to be used in way
of the keel and in way of hull appendages such as
shaft struts, skegs and rudders and in way of deck
fittings, bolted connections, and other areas of
concentrated local loads.

PART 3 SECTION 9|5 Plating


The section modulus and moment of inertia about 1. In direction parallel to s
the neutral axis of a strip of sandwich panel, 1 cm (1
in.) wide are to be not less than given by the (sc) 2 pk s
following equations: SM o = cm3
6 × 10 σ aso
5

(sc) 2 pk (sc) 2 pk s
1. SM o = cm3 SM o = in3
6 × 10 σ ao 5
6σ aso
(sc) 2
pk
SM o = in3 2. In direction parallel to l
6σ ao
(sc) 2 pk l El 3
SM o = cm
(sc) 2 pk 6 × 10 σ alo
5
Es
SM i = cm3
(sc) 2 pk l
2.
6 × 105 σ ai El 3
SM o = in
(sc) 2 pk 6σ alo Es
SM i = in3
6σ ai 3. In direction parallel to s

(sc )3 pk1 (sc) 2 pk s


3. I= cm 4
SM i = cm3
120 × 10 5 × k 2 E tc 6 × 105 σ asi

I=
(sc )3 pk1 (sc) 2 pk s
SM i =
4
in in3
12k 2 E tc 6σ asi

s, c, p, k, k1 and k2 as defined in 3/9.3.3 4. In direction parallel to l

SMo = required section modulus, in cm3 or in3, to (sc) 2 pk l El


outer skin. SM i = cm3
SMi = required section modulus, in cm3 of in3, to 6 × 10 σ ali
5
Es
(sc) 2 pk l
inner skin.
required moment of inertia, in cm4 or in4 El
I = SM i = in3
σao = design stress, for outer skin, given in 6σ ali Es
Table 3/9.4, based on strength of outer
skin in direction parallel to s.
5. In direction parallel to s
σai = design stress, for inner skin, given in
Table 3/9.4, based on strength of inner
(sc) 3 pk 1
skin in direction parallel to s. I= cm4
Etc = 0.5(Ec + Et) 120 × 105 k 2 E s
Ec = mean of compressive modulii of inner and
outer skins, in N/mm2 (kgf/cm2, psi) (sc) 3 pk 1
Et = mean of tensile modulii of inner and outer
I= in4
12 k 2 E s
skins, in N/mm2 (kgf/cm2, psi)

b Laminates with different bending strength s, c, p, k1, k2 and Etc as defined in 3/9.3.3
and stiffness in 0° and 90° axes Where the strength
SMo = required section modulus, in cm3 or in3,
is less or the stiffness greater in the direction
to outer skin.
perpendicular to s, the section modulus and moment
SMi = required section modulus, in cm3 or in3,
of inertia about the neutral axis of a strip of sandwich,
to inner skin.
1 cm (1 in.) wide are also to be not less than given by
kl, ks = modified coefficient for plate panel
the following equations:
aspect ratio, given in Table 3/9.5.
σaso = design stress, for outer skin, given in
Table 3/9.4 based on strength properties
in direction parallel to s.

PART 3 SECTION 9|6 Plating


σalo = design stress, for outer skin, given in
Table 3/9.4 based on strength properties Location Density Minimum
in direction perpendicular to s. Density
kg/m3 (lbs/ft3) kg/m3 (lbs/ft3)
σasi = design stress, for inner skin, given in
Table 3/9.4 based on strength properties Bottom forward of 4dc (6.4dc) 120 (7.5)
in direction parallel to s. 0.4LWL; V≥ 25 kts
σali = design stress, for inner skin, given in Bottom forward of 4dc (6.4dc) 100 (6.25)
Table 3/9.4 based on strength properties 0.4LWL; V< 25 kts
in direction perpendicular to s. elsewhere; V ≥ 25 kts 3dc (4.8dc) 100 (6.25)
Es = 0.5 (Ets + Ecs) elsewhere; V < 25 kts 3dc (4.8dc) 80 (5.00)
El = 0.5 (Etl + Ecl)
Side forward 0.4LWL 2.5dc (4.0dc) 100 (6.25)
Ets, Ecs = respectively mean of tensile modulii of
inner and outer skins, and mean of elsewhere 2.0dc (3.2dc) 80 (5.0)
compressive modulii of inner and outer
skins, in N/mm2 (kgf/cm2, psi) in TABLE 3/9.6 - Coefficient ν for FRP Sandwich
direction parallel to s. Panels Shear Strength
Etl, Ecl = respectively mean of tensile modulii of
inner and outer skins, and mean of Plate Panel Aspect Ratio ν
compressive modulii of inner and outer l/s
skins, in N/mm2 (kgf/cm2, psi) in > 2.0 0.500
direction parallel to l. 2.0 0.500
1.9 0.499
1.8 0.499
c Shear Strength The thickness of core and 1.7 0.494
sandwich laminate is to be not less than given by the 1.6 0.490
following equation. Special consideration will be 1.5 0.484
given where cores differing from those in 2/5 are 1.4 0.478
proposed. See also 3/9.3.4e for minimum thickness 1.3 0.466
of skin. 1.2 0.455
1.1 0.437
νps
1.0 0.420
do + dc d o + d c νps
= mm = in. s = shorter edge of plate panel, in mm or in.
2 1000τ 2 τ l = longer edge of plate panel, in mm or in.
Note: Values of ν less than 0.5 may be used only where the
do = overall thickness of sandwich, excluding gel inner and outer skins have essentially the same strength and
coat, in mm or in. elastic properties in the 0° and 90° axes.
dc = thickness of core, in mm or in.
ν = coefficient varying with plate panel aspect TABLE 3/9.7 Core Shear Design Strength
ratio, given in Table 3/9.6, Where the elastic
properties of the skins are different in the Core Material Design Core Shear Strength
principal axes, ν is to be taken not less than
0.5.
Balsa Wood 0.3τu
s = lesser dimension of plate panel, in mm or in. PVC* 0.4τu
p = design pressure in kN/m2 (tf/m2, psi) as * may be taken as 0.55τu where sheer elongation
defined in Section 3/8. exceeds 40%.
τ = design stress, in N/mm2 (kgf/mm2, psi) as τu = minimum core shear strength, in N/mm2
shown in Table 3/9.7. (kgf/mm2, psi)

Where cores are scored to facilitate fitting, the d Skin Stability The skin buckling stress σc given
scores are to be filled with putty or resin. by the following equation, is in general to be not less
The density of polyvinyl chloride foam cores in than 2.0 σai and 2.0 σao
the shell plating is to be not less than given in the
following table: σ c = 0.63 E s ⋅ E cc ⋅ Gcc
Es = compressive modulus of skins, in N/mm2
(kgf/mm2, psi) in 0° and 90° in-plane axis of
panel.
Ecc = compressive modulus of core, in N/mm2
(kgf/mm2, psi) perpendicular to skins.

PART 3 SECTION 9|7 Plating


Gcc = core shear modulus, in N/mm2 (kgf/mm2,
psi) in the direction parallel to load.

e Minimum Skin Thickness After all other


requirements are met, the skin thicknesses of
laminates complying with basic laminate
requirements of 2/5 are in general to be not less than
given by the following equations.

tos=0.35k3 (C1 + 0.26L) mm


tos= 0.35k3 (C1 + 0.0031L) in.

tis=0.25k3 (C1 + 0.26L) mm


tis= 0.25k3 (C1 + 0.0031L) in.

where:
tos = thickness of outer skin in mm or in.
tis = thickness of inner skin in mm or in.
k3, C1= factors for service and location, given in
Table 3/9.3
L = craft length in m (ft), as defined in 2.1,
generally not to be taken as less than 12.2 m
(40 ft).

f Wheel Loading Special consideration will be


given to the required thickness where provision is
made for the operation or stowage of vehicles having
rubber tires after all other requirements are met.

PART 3 SECTION 9|8 Plating


PART 3 SECTION 10

Internals
3/10.1 Aluminum and Steel Stiffeners without end attachments are permitted on
watertight bulkheads provided the section modulus is
3/10.1.1 General increased by 50%.
Structural arrangements and details are to be in
accordance with Sections 3/12 and 3/14. Reference is to TABLE 3/10.1 - Design Stress, σa
be made to 1/1.5.2 regarding the requirement to perform
Location Steel and FRP
direct analysis to verify the design of the main supporting
Aluminum
structural components, which for example support the
plating and plating stiffeners. The scantlings obtained by Bottom Longitudinals - Slamming 0.65σy1 / 0.33σu
Pressure 0.55σy2
the application of the equation in this section are to be
considered minimum values. The purposes of direct Bottom Longitudinals - Sea 0.30σy 0.33σu
Pressure
analysis are to confirm the adequacy of the formula based
Side Longitudinals - Slamming 0.60σy 0.40σu
scantlings, or to provide the basis for increasing the initial
Pressure
scantlings to the values required based on allowable stress
Side Longitudinals - Sea Pressure 0.50σy 0.40σu
limits.
Deck Longitudinals - Strength 0.33σy 0.40σu
Decks
3/10.1.2 Strength and Stiffness
a Section Modulus The ends of members are to be Deck Longitudinals - Other Decks 0.40σy 0.40σu
effectively attached to the supporting structure. The Bottom Transverse - Slamming 0.80σy 0.33σu
section modulus of each longitudinal, stiffener, transverse Pressure
web, stringer and girder is to be not less than given by the Bottom Transverses - Sea Pressure 0.50σy 0.33σu
following equation: Side Transverses - Slamming 0.80σy 0.33σu
Pressure
83.3 × psl 2 144 × psl 2 3 Side Transverses - Sea Pressure 0.50σy 0.33σu
SM = cm3 SM = in
σa σa Deck Transverses - Strength Deck 0.75σy 0.33σu
Deck Transverses - Other Decks 0.75σy 0.33σu
where: Watertight Bulkheads 0.75σy 0.50σu
Tank Bulkheads 0.60σy 0.33σu
p = design pressure in kN/m2 (tf/m2, psi), given in Superstructure and Deckhouse 0.70σy 0.33σu
3/8.1
s = spacing in m or ft, of longitudinal, stiffener, σy = minimum yield strength, unwelded condition in
transverse web or girder, etc. N/mm2 (kgf/mm2, psi). For aluminum, minimum yield
l = length, in m or ft, of the longitudinal, stiffener, stress, welded condition in N/mm2, (kgf/mm2, psi)
σu = ultimate tensile strength in N/mm2 (kgf/mm2, psi)
transverse web or girder, between supports;
where bracketed end connections are supported Notes:
by bulkheads, l may be measured onto the 1) Craft less than 50m (164 ft) in length.
bracket, the distance given on Fig. 3/2.1, 2) Craft equal to and greater than 50m (164 ft) in length.
provided both bracket arms are about the same
length. Where transverse members span chines b Moment of Inertia The moment of inertia of each
or "knuckles", l is to be measured as shown in longitudinal, stiffener, transverse web, stringer or girder,
Figures 3/10.1 and 3/10.2. including the plating to which it is attached, is to be not
σa = design stress, in N/mm2 (kgf/mm2, psi) as given less than given by the following equation:
in Table 3/10.1
260 psl 3 54 psl 3 4
I= cm4 I= in
K4 E K4 E

PART 3 SECTION 10|1 Internals


SM R
p, s, and l are as given in 3/10.1.2. C1 N/mm2 (kgf/mm2, psi)
SM A
K4 = 0.0015 for shell and deep tank girders, stringers c5 = 105 (105, 322,560)
and transverse webs, constructed of steel. Fs is as given in Table 3/8.1.
= 0.0011 for deck girders and transverses Mw = wave bending moment as given in 3/6.1.1b(3),
constructed of steel. kN-m (tf-m, Ltf-ft)
= 0.0021 for shell and deep tank stringers and Msw = still water bending moment as given in
transverse webs constructed of aluminum. 3/6.1.1b(2), kN-m (tf-m, Ltf-ft)
= 0.0018 for deck girder and transverses y = vertical distance in m or ft from the neutral axis
constructed of aluminum. to the considered location.
E = tensile or compressive modulus, in N/mm2 I = moment of inertia of the hull girder, cm4 (in4)
(kgf/mm2, psi) representative of the basic value C1 = 175 N/mm2 (17.84 kgf/mm2, 25,380 psi)
used in the moment of inertia calculation. SMR = hull girder section modulus as required in 3/6,
cm2m (in2ft)
3/10.1.3 Buckling SMA = section modulus of the hull girder at the location
The moment of inertia of the deck or shell longitudinal being considered, cm2m (in2ft)
together with attached plating is not to be less than to
satisfy the following criteria: d Design Buckling Stress The design buckling stress,
a Elastic Buckling Stress σc, of the shell or deck longitudinal is to be such that:
EI a σc ≥ βσa
σE = 2
N/mm2 (kgf/mm2, psi)
C3 Al
β = 1.0 for web plating of stiffeners (local buckling)
σE = ideal elastic buckling stress in N/mm2 (kgf/mm2, = 1.1 for stiffeners
psi)
E = 2.06 x 105 N/mm2 (21,000 kgf/mm2, 30 x 106 psi) 3/10.1.4 Thickness
for steel The thickness of the webs and face bars of structural
Ia = moment of inertia, cm4 (in4) of longitudinal members is not to be less than determined by the
together with attached plating. following equations:
C3 = 1000 (1000, 144)
A = cross-sectional area in cm2 (in2)of longitudinal a Webs
together with attached plating.
dw σy
l = span of longitudinal in m or ft
t= mm (in.)
C σd
b Critical Buckling Stress The critical buckling
stress in compression, σc, is determined as follows:
t = total required thickness in mm or in.
dw = depth of the web in mm or in.
σc = σE when σE ≤ 0.5σy C = 70 for steel members
 σy  = 50 for aluminum members
= σ y 1 −  when σE>0.5σy σy = minimum yield strength of steel or aluminum in
 4σ E  the unwelded condition, N/mm2 (kgf/mm2, psi)
σd = for steel members; 235 N/mm2 (24 kgf/mm2,
σy = minimum yield strength, N/mm2 (kgf/mm2, psi) 34,000 psi)
σE = ideal elastic buckling stress calculated in = for aluminum members; 127.6 kN/mm2 (12.76
3/10.1.3a kgf/mm2, 18,500 psi)

c Calculated Compressive Stress

Fs M w + M ws
σ a = c5 y N/mm2 (kgf/mm2, psi)
Ia
σa = working compressive stress in panel being
considered, N/mm2 (kgf/mm2, psi), but generally
not less than the following:

PART 3 SECTION 10|2 Internals


The web thickness is also not to be less than the
following: Table 3/10.2 Design Stress τa

1000 psl 144 psl Location Aluminum Steel


t= mm t= in.
2d w τ a 2d wτ a Bottom Primary Members - Slamming 0.75τyw 0.75τy
Pressure
Bottom Primary Members - Sea 0.50τyw 0.50τy
t = total required thickness in mm or in. Pressure
p = design pressure in kN/m2 (tf/m2, psi) as given in Side Primary Members - Slamming 0.50τyw 0.50τy
Section 3/8 Pressure
s = width of shell or deck supported by the member Side Primary Members - Sea Pressure 0.50τyw 0.50τy
in m or ft
Deck Primary Members 0.50τyw 0.50τy
l = length of member in m or ft
dw = depth of the web in mm or in. τyw = minimum shear yield strength, welded condition
τa = design shear stress in N/mm2 (kgf/mm2, psi) τy = minimum shear, unwelded condition

b Face Bars and Flat Bars


FIGURE 3/10.1
d σy Transverse Side Frame
t= w mm (in.)
C σd

t = total required thickness in mm or in.


dw = depth of the flat bar or unsupported width of face
bar in mm or in.
C = 12 for steel members
= 9 for aluminum members
σy = minimum yield strength of steel or aluminum in
the unwelded condition, N/mm2 (kgf/mm2, psi)
σd = for steel members; 235 kN/mm2 (24 kgf/mm2,
34,000 psi)
= for aluminum members; 127.6 kN/mm2 (12.76
kgf/mm2, 18,500 psi)

3/10.1.5 Attachments
The lug weld attachment of the longitudinals to the
transverse webs are to have total weld throat area not less FIGURE 3/10.2
than the following equations: Transverse Side Frame

1000 psl 144 psl 2


aw = mm2 aw = in
τa τa

aw = tw x lw
tw = weld throat in mm or in.
lw = total length of weld in mm or in.
p = design pressure in kN/m2 (tf/m2, psi) as given in
Section 3/8
s = width of shell or deck supported by the member
in m or ft
l = length of member in m or ft
τa = design shear stress in N/mm2 (kgf/mm2, psi)

PART 3 SECTION 10|3 Internals


3/10.1.6 Direct Analysis - Design Stresses the transverse member that is continuous over the
longitudinal member.
a General This section relates to design stresses
when direct analysis is performed to verify the selected Where higher strength or higher modulus plies are used in
design scantlings in accordance with 3/10.1.1. the flange or crown of the internal, it may be advisable to
b Equivalent Stress The total equivalent stress (σe) provide similar higher strength, higher modulus local plies
obtained from conventional finite element analysis is to be in the shell or deck plating, in the direction parallel to the
based on the following equation: internal to balance the strength and stiffness of the high
strength and high modulus plies in the flange or crown of
σe = (σx2 + σy2 - σxσy + 3τ xy2) 1/2 the internal.

Where σx and σy are the direct (membrane) stresses 3/10.3.3 Strength and Stiffness
respectively in the x and y coordinate directions of the a Section Modulus The section modulus of each
elements, and τxy is the in-plane shearing stress. longitudinal, stiffener, transverse web and girder including
the plating to which it is attached is to be not less than
σe is to be less than or equal to the following design stress: given by the following equation:

steel: 0.833 σy 83.3 × psl 2 144 × psl 2 3


0.833 σyw
SM = cm3 SM = in
aluminum: σa σa
FRP: 0.367 σu
p, s, l and σa are as defined in 3/10.1.2.
where σy , σyw , and σu are defined in association with
Table 3/10.1. Where the shell, deck or bulkhead plating, and the webs
and flange and crown of the member are of different
strength or elastic property plies, consideration is to be
c Buckling Stresses Checking Reference is to be
given to the effect of the different modulii plies in
made to 3/10.1.3 on checks to be made when the direct
calculating the moment of inertia and section modulus; the
stress is compressive. Checks of buckling stress in case of
required section modulus is to be considered for each
shearing stress are also to be performed and documented
different strength laminate of the member. For uni-
when they control the design of structural elements.
directional laminates, strengths and modulii in the
direction parallel to the member are to be used.
3/10.3 Fiber Reinforced Plastic
b Moment of Inertia The moment of inertia of each
3/10.3.1 General longitudinal, stiffener, transverse web, stringer or girder,
The requirements for fiber reinforced plastic apply to craft including the plating to which it is attached, is to be not
of up to 61m (200ft) in length. Special consideration will less than given by the following equation:
be given to craft of greater length than this. The structural
260 psl 3 54 psl 3 4
arrangements and details are to be in accordance with I= cm4 I = in
Section 3/12 and 3/14. Laminates may be bi-directional K4 E K4 E
or uni-directional. Bonding angles or tapes are to comply
with 3/14. where p, s and l are as given in 3/10.1.2

3/10.3.2 Fiber Reinforcement K4 = 0.005 for shell and deep tank girders, stringers
The basic laminate given in 2/5, or other approved and transverse webs.
laminates of glass, aramid, or carbon fiber, in mat, woven = 0.004 for deck girders and transverses.
roving, cloth, knitted fabric, or non-woven uni-directional = 0.010 for all other members.
reinforcing plies may be used. The plies are in general to E = tensile or compressive modulus, in N/mm2
be layed-up parallel to the direction of the internal. The (kgf/mm2, psi) representative of the basic value
strength of the laminate in a direction perpendicular to the used in the moment of inertia calculation.
direction of the internal is in general not to be less than
25% of the warp strength except for the uni-directional c Shear Area The web area, A, of the member is to
caps of the flange or crown of the internal members. In be not less than given by the following equation:
way of continuous longitudinal members, the section 7.5 psl 108 psl 2
modulus and moment of inertia of transverse members are A= cm2 A= in
to be attained by the shell or deck plating and that part of τ τ

PART 3 SECTION 10|4 Internals


where p, s, and l are as given in 3/10.1.2 3/10.5.3 Permissible Load
The load a stanchion may carry is to be equal to or greater
A = net web area in cm2 or in2 at location being than the load on the stanchion obtained in 3/10.5.2. This
considered. permissible load is to be obtained from the following
τ = design shear stress in N/mm2 (kgf/mm2, psi) to be equations:
taken not greater than 0.4τu
τu = lesser of ultimate shear strength in N/mm2 a. Ordinary Strength Steel Stanchions
(kgf/mm2, psi) in either warp or fill of the web
laminate. Wa = (12.09 - 0.0444l/r) A kN
Wa = (1.232 - 0.00452l/r) A tf
3/10.3.4 Proportions Wa = (7.83 - 0.345l/r) A Ltf
The thickness of webs and flanges are to be in accordance
with 3/14. b. Aluminum-Alloy Stanchions

3/10.5 Stanchions Wa = (10.00 - 0.0582l/r) Aσy /165 kN


Wa = (1.02 - 0.00593l/r) Aσy /17 tf
3/10.5.1 General Wa = (6.49 - 0.452l/r) Aσy /24000 Ltf
Supports under stanchions are to be of sufficient strength
where:
to distribute the loads effectively. Stanchions above are to
be arranged directly over stanchions below wherever
Wa = permissible load in kN (tf, Ltf)
possible; where this is not possible, effective means are to
r = least radius of gyration of stanchion in cm or in.
be provided for transmitting the loads to the supports
A = area of stanchion in cm2 or in2
below. Stanchions in double bottoms and under the tops
l = unsupported length of stanchion in m or ft
of deep tanks are to be metal and solid in cross section.
σy = minimum yield strength of aluminum in kN/m2
Stanchions are in general not to be used in the bottom or
(tf/m2, psi) in the unwelded condition
double bottom structures where subject to high impact
loads in service.
The adoption of aluminum test values higher than given in
Part 2, Section 4 will be subject to special consideration.
3/10.5.2 Stanchion Load
The load on a stanchion is to be obtained from the
following equation:
3/10.5.4 FRP Stanchions
FRP stanchions will be subject to special consideration.
W = pbs kN or tf W = 0.064pbs Ltf
3/10.5.5 Support by Bulkheads
W = load in kN (tf, Ltf)
Bulkheads supporting girders or bulkheads fitted in lieu of
b = mean breadth in m rr ft of area supported.
stanchions are to be stiffened to provide support not less
s = mean length in m or ft of area supported.
effective than required for stanchions.
p = design pressure in kN/m2 (tf/m2, psi) given in
Section 3/8. Where a stanchion supports two or
more decks, p is to be the design pressure for the
deck at the top of the stanchion plus the sum of
the design pressures for all complete decks and
one-half the design pressure for all decks or
deck-house above the deck being directly
supported.

PART 3 SECTION 10|5 Internals


PART 3 SECTION 12

Hull Structural Arrangement

3/12.1 Structural Arrangement - All Materials The webs of all members are to be effectively
attached to the shell, deck or bulkhead plating, to
3/12.1.1 Framing, Webs, Girders, and Non-tight their supporting members and to face bars.
Structural Bulkheads
a General The shell, main weather, or freeboard 3/12.1.2 Watertight Bulkheads
deck, and the sides and tops of long superstructures a Collision bulkhead Craft having a length, as
are in general to be longitudinally framed; depending defined in Section 3/1, of or exceeding 15m (50ft) are
on craft length, speed and structural stability, craft to be provided with a collision bulkhead fitted not
may also be transversely framed. less than 0.05L, and for passenger craft not more than
Bulkheads, partial bulkheads or web frames are to 0.08L, abaft the stem at the design load waterline.
be arranged in the main hull and in long The bulkheads are to be intact except for approved
superstructures or deckhouses to provide effective pipe penetrations, and are to extend to the main
transverse rigidity. They are to be provided also in weather deck preferably in one plane. In craft having
the main hull under the ends of superstructures or long superstructures at the forward end, the bulkheads
deckhouses. are to be extended weathertight to the superstructure
Longitudinal frames are to be supported by deck. Provided the extensions are not less than 0.05L
transverse web frames, transverse bulkheads or other abaft the stem at the design load waterline they need
transverse structure. Longitudinals are in general to not be fitted directly over the collision bulkhead; in
be continuous in way of transverse supporting such cases, the part of the deck forming the step is to
members except at transverse bulkheads where they be weathertight. Special consideration will be given
may be intercostal provided continuity of strength and to the arrangements of collision bulkheads for
end fixity are maintained. Depending on craft length governmental service craft such as patrol boats,
and details, special consideration will be given to search and rescue craft etc.
longitudinals being intercostal at transverse webs. b Engine Room The engine room is to be
With transverse framing, deck and bottom girders are enclosed by watertight bulkheads extending to the
to be provided. Girders may be intercostal at main weather deck.
transverse bulkheads provided continuity of strength c Chain Locker Chain lockers located abaft of
is maintained and end fixity is provided. collision bulkheads and extending into forepeak tanks
Transverses are to be arranged as continuous web are to be watertight.
rings and girders are to be aligned with stiffeners at
bulkheads. Alternative arrangements that provide 3/12.1.3 Tanks
fixity at the ends of transverses and girders will be The arrangements of all integral tanks, their intended
specially considered. service, and the heights of the overflow pipes are to
Engines are to be supported and secured by be indicated clearly on the drawings submitted for
substantial girders, suitably stiffened, supported approval.
against tripping and supported at bulkheads. Where potable water tanks are fitted, water closets
Foundations for auxiliary machinery are to provide are not to be installed on top of the tanks nor are soil
for secure attachment of the equipment and are to be lines to run over the tops of the tanks. Pipes
effectively attached to the hull structure. containing non-potable liquids are not to be run
A substantial foundation and seating is to be through the tanks. Attention is directed to the
provided for the anchor winch or windlass. regulations of national authorities that might govern
b Attachments and stiffening At supporting the location, construction or design of such tanks.
members, the attachment of all internal structural Baffle or swash plates are to be provided.
members is to provide end fixity, and effective load Scantlings of pressurized tanks will be subject to
transmission. Special consideration will be given to special consideration.
reduced end fixity where the alternative structure has All tanks and void spaces are to be accessible for
equivalent strength. inspection and repair.

PART 3 SECTION 12|1 Hull Structural Arrangement


3/12.1.4 Shell Plating 3/12.3 Structural Arrangements - Additional
The bottom shell plating is to extend to the chine or Requirements for Steel and Aluminum
upper turn of bilge. Increases in thickness or Alloys
additional stiffening are required in way of sea inlet
boxes, propeller blades, skegs, shaft struts and hawse 3/12.3.1 Shell Plating
pipes. The bottom shell plating is to extend to the chine or
Where a bow thruster tube is fitted it is to be not upper turn of bilge. In general the side shell is to be
less than the surrounding shell thickness. of the same thickness from its lower limit to the
gunwale. Increases in thickness are required in way
3/12.1.5 Decks of skegs shaft struts hawse pipes etc. Bow thruster
Where a deck is stepped or has a break, suitable tube is to be equivalent to the surrounding shell
scarphing or brackets are to be provided at the side thickness.
shell.
Decks passing into superstructures within the 0.5L 3/12.3 Structural Arrangements - Additional
amidships are to be increased in way of the break. Requirements for Fiber Reinforced
Plastic Hulls
3/12.1.6 Means of Escape
At least two means of escape to the main weather 3/12.3.1 Tanks
deck are to be provided from the main hull spaces. In fiber reinforced plastic construction, non-integral
They are to be as far apart as practicable, and are to tanks are to be used whenever possible. When
be operable from both sides. integral tanks are used they are to be of single skin
construction, the only exception is the tank top
3/12.1.7 Double Bottoms plating can be of sandwich construction. No stiffeners
a Passenger Craft For passenger craft that are within integral tanks are to penetrate the tank
on international voyages that operate more than four boundaries. No gasoline tanks, or tanks containing
hours at operational speed from a port of refuge are to petroleum products with flash points less than 60°C
be fitted with a double bottom in accordance with 5/5 (150°F) are to be fitted integrally. The design and
of the Rules for Building and Classing Steel Vessels. arrangements of oil fuel tanks is to be such that there
b Cargo Craft Cargo craft that are on is no exposed horizontal section at the bottom that
international voyages that are more than eight hours could be exposed to a fire. Other fire protection
at operational speed from a port of refuge are to be arrangements for oil fuel tanks will be specially
fitted with double bottoms. The inner bottoms are to considered. For details of fire protection
be fitted fore and aft between the peaks or as near requirements see 3/24.
thereto as practicable. Where, for special reasons in All internal surfaces of FRP tanks are to be
design, it may be desired to omit the double bottom, covered with chopped strand mat weighing at least
the arrangements are to be clearly indicated on the 600 g/m2 (2 oz/ft2). This covering is to be in addition
plans when first submitted for approval. A double to the scantlings required by this Guide. A suitable
bottom need not be fitted in way of deep tanks coating is to be applied to this covering to prevent the
provided the safety of the ship in the event of bottom contents of the tank from impregnating the
damage is not thereby impaired. It is recommended surrounding laminates. The sides, tops, and baffles of
that the inner bottom be arranged to protect the bilges integral tanks are to have all connections taped on
as much as possible and that it be extended to the both sides. Fresh water tanks are to be coated with a
sides of the craft. The scantlings of the double non-toxic and non-tainting coat of resin that is
bottom are to be fitted in accordance with 3/8, 3/9, recommended by the resin manufacturer for potable
and 3/10. water tanks. Where outfit items are to be laminated
to the tank surface, the heavy coating of resin is to be
applied afterwards and the laminated brackets sealed
to prevent the ingress of moisture. The scantlings of
integral oil fuel and water tanks are to be in
accordance with 3/9 and 3/10. Integral tanks are to
be tested in accordance with Table 1/2.1.

PART 3 SECTION 12|2 Hull Structural Arrangement


PART 3 SECTION 14

Arrangement, Structural Details and


Connections
3/14.1 Structural Details Where in direct contact with aluminum, wood is to be
suitably coated, see Section 3/21.
3/14.1.1 Aluminum and Steel
a General Structural details are to be designed 3/14.1.2 Fiber Reinforced Plastic
and constructed to minimize hard spots, notches and a General Structural continuity is to be
other structural discontinuities. Openings in webs, maintained and where changes in thickness or
girders and other structural internal members are to structural section occur, they are to be gradual to
be arranged clear of concentrated loads or areas of prevent notches, hard spots and other structural
high stresses; slots in transverses and girders for discontinuities. The requirements of d, and e, below
longitudinals or beams in such locations are to be and of 3/14.3 and 3/14.5 are for the basic laminate
fitted with collars. Care is to be taken to ensure given in 2/5; special consideration will be given
structural continuity; sharp corners and abrupt where other laminates or resins are used. The ends of
changes in section are to be avoided; toes of brackets all internal structural members are to provide end-
and ends of members are not to terminate on plating fixity and load transmission to the supporting
without attachment to an adjacent member, unless member, departures from this may be considered
specially approved. where the alternative structure has equivalent
b Longitudinals Deck, bottom and inner bottom strength.
longitudinals are in general to be continuous unless b Changes in Laminate Thickness A gradual
specially approved otherwise, but in way of taper is to be used for all changes in laminate
bulkheads they may be intercostal provided continuity thickness. Where the construction changes from
of strength and end fixity are maintained by the end sandwich laminate to a solid laminate, the thickness
brackets. The ends of all internal structural members of the core material is in general, to be reduced by a
are to provide end-fixity and load transmission to the gradual taper of not less than 2:1.
supporting member. Departures from this may be c Openings Holes and Raw Edges Access and
considered where the alternative structure has lightening holes with suitably radiuses corners, are to
equivalent strength. be arranged as necessary and clear of areas of load
c Girders and Transverses Girders and concentration or high stresses. Their depths and
transverses are to have depths not less than twice the lengths are generally not to exceed, respectively, 0.5
depth of slots for longitudinals and beams or other and 0.75 the depths of the members. Air and limber
openings. Transverses are to be arranged as holes are to be arranged to eliminate air pockets and
continuous web rings, girders are to be aligned with avoid any accumulation of water or other liquids. In
stiffeners at bulkheads, alternative arrangements that general they are to be not less than 40 mm (1 1/2 in.)
provide fixity at the ends of transverses and girders radius not more than 1/3 the depth of the member.
will be specially considered. All exposed edges of FRP single-skin laminates are to
d Openings Access and lightening holes with be sealed with resin. Edges of sandwich panels and
suitably radiuses corners are to be arranged as edges of holes in sandwich panels are to be sealed
necessary and clear of areas of load concentration or with resin-impregnated mat. Ferrules installed in
high stresses. Their depths and lengths are generally sandwich panels or stiffeners for drains or wire
not to exceed respectively, 0.5 and 0.75 the depth of penetrations are to be set in bedding compound. All
the members. Air and limber holes are to be arranged hatch openings are to be supported by a system of
to eliminate air pockets and avoid any accumulation transverse and longitudinal stiffeners.
of water or other liquids. In general limber holes are d Piping and Wiring in Foam Piping or wiring
to be not less than 40 mm (1 1/2 in.) radius nor more passing through foam-filled spaces is to be installed
than 1/3 the depth of the member. in plastic tubing to facilitate removal and
e Bi-metallic Connections In aluminum replacement. The ends of the plastic tubing are to be
construction, where bi-metallic connections are joined to adjacent structure with resin impregnated
unavoidable, suitable insulation is to be provided. mat. See Figure 3/14.1

PART 3 SECTION 14|1 Arrangement, Structural Details and Connections


Figure 3/14.1 Piping or Opening through Figure 3/14.2 Proportions of Stiffeners
Foam Filled Space

e Stiffeners
1 General Stiffeners, frames, girders, deck
beams, bulkhead stiffeners, etc. used to support FRP
panels may be entirely of FRP, FRP laid over
nonstructural cores or forms, or composites of FRP or
other approved structural materials such as plywood
or wood.
2 Stiffeners without effective Cores or with
Nonstructural Cores Stiffeners without cores or with Where approved polyvinylchloride, balsa, or other
cores not indicated in Table 2/5.1 (i.e., Balsa Wood approved core material is used, thicknesses less than
and PVC) are to conform to Figure 3/14.2, and the given above may be accepted provided the buckling
thickness of the crown and web of the stiffeners is to stresses of the stiffener skins comply with the
be not less than obtained from the following buckling stress criteria in 3/9.3.4d are met.
equations: Hat-section stiffeners constructed by laying FRP
over premolded FRP forms (Figure 3/14.3) are to
t1 = w/20 mm or in. t = h/30 mm or in. conform with Figure 3/14.2 and the above equations;
the premolded forms may be considered structurally
t1 = thickness of stiffener crown in mm or in. effective if their physical properties are at least equal
t = thickness of stiffener webs in mm or in. to those of the overlay laminates.
w = width of stiffener crown in mm or in.
h = height of stiffener webs in mm or in. Figure 3/14.3 Premolded FRP Form
Where the stiffeners are of laminates with properties
differing from the basic laminate, the thickness is to
be modified by the factor:

C
7.7
E

E = compressive modulus of proposed laminate


in kg/cm2 or psi.
C = ultimate compressive strength of proposed
laminate in kg/cm2 or psi.
Premolded stiffeners bonded to the laminates with
FRP angles, flanges or tapes (Figure 3/14.4) are also
to conform to Figure 3/14.2 and the above equations.
The thickness of each bonding angle flange or tape is
to be not less than the thickness of the webs of the
stiffener, and the legs of the bonding angle, flange or
tape are to be of equal length in accordance with
Section 3/14.5. Joints in premolded stiffeners are to
be scarphed and spliced or otherwise reinforced to
maintain the full strength of the stiffeners.

PART 3 SECTION 14|2 Arrangement, Structural Details and Connections


Figure 3/14.4 Premolded Stiffener g Engine Foundations The engine beds are to
be of thicknesses and widths appropriate to the
holding-down bolts, are to be set in mat putty or resin
putty to assure uniform bearing against the girders,
and are to be bolted through the webs of the girders.
Figure 3/14.6 shows several typical, acceptable
engine foundations.

Figure 3/14.6 Engine Foundations

The thickness may be less than obtained from the


above equation if these members are suitably
stiffened and provided with adequate lateral stability.
The required minimum flange or tape laps onto such
members, as shown in Figure 3/14.2, if greater than
50 mm (2 in.), need not exceed 10t.
f Girders and Longitudinal Frames Girders and
longitudinal frames are to be continuous through
floors and web frames. Except in way of integral-
tank end bulkheads, girders and longitudinal frames
are also to be continuous through transverse
bulkheads. Where such members are intercostal,
attention is to be given to minimizing structural
discontinuities
An acceptable type of continuous girder and
longitudinal-frame FRP connection is shown in
Figure 3/14.5. The laps of the connections onto the
supporting structure are to be not less than the over-
all widths of the structural members including
flanges, and the thicknesses of the connections are to
be not less than the thicknesses of the structural-
member flanges or tapes.

Figure 3/14.5 Connection of


Longitudinals to Transverses

PART 3 SECTION 14|3 Arrangement, Structural Details and Connections


h Deck Fittings Deck fittings such as cleats and Figure 3/14.7 Boundary Angles for FRP
chocks are to be bedded in sealing compound or Components
gasketed, through-bolted, and supported by either
oversize washers or metal, plywood or wood backing
plates. Where washers are used, the laminate in way
of the fittings is to be increased at least 25% in
thickness.
i Through Hull Penetrations Generally all
through hull penetrations are to be formed by solid
FRP laminates. When sandwich construction is used
for the hull, the core material is to be completely
sealed off from the through hull penetration. All
through hull penetrations are to be taped on both 2 Plywood or Wood to FRP Plywood
sides of the penetration. bulkheads are to be bedded in foam, a slow-curing
k Boundary Angles, Flanges or Tapes polyester putty, a microballoon-and-resin mixture, or
1 FRP to FRP Secondary bonding of FRP other approved material. Boundary angles of FRP are
components by means of double boundary angles, to be applied over fillets made of the bedding
flanges or tapes is to be in accordance with 2/5. material. The nominal size, w, of each fillet is to be
Typical boundary angles for FRP components are 9.5 mm to 12.5 mm (0.375 in. to 0.50 in.) The
shown in Figure 3/14.7. At the end connections of boundary angles are to be at least equal in thickness
sandwich laminates the core shear strength is to be to one-half the thickness of the laminate, and the
effectively developed. The thickness of each width of each flange is to be as shown in Figure
boundary angle, flange or tape having similar strength 3/14.8. Secondary bonding of these angles to FRP is
to the members being connected is to be not less than to be in accordance with 2/5.
obtained from the following: Figure 3/14.8 Boundary Angles
Single-skin to Single-skin One-half the thickness
of the thinner of the two laminates being joined.
Connecting Plywood or Wood To FRP
Sandwich to Sandwich The greater of the mean
thicknesses of the skins of the sandwich panels being
attached.
Sandwich to Single Skin Either one-half the
thickness of the single-skin laminate or the mean
thickness of the skins of the sandwich panel being
attached, whichever is less.

The thickness of each FRP-to-FRP boundary angle


also is to be not less than obtained from the following
equation: 3/14.3 Welded and Mechanical Connections
t = 0.105L + 1.11 mm t = 0.00133L + 0.044 in 3/14.3.1 Steel and Aluminum
a General Components may be fastened by
Where: either welding or rivets. For welding see Sections
3/23, 2/3 and 2/4.
L = length, in m or ft, as defined in 3/1.1; need not b Expanding Rivets Rivets of the expanding
be taken as more than 46.6 m (153 ft). type (blind or "pop" rivets) may be used for lightly
loaded connections where lack of accessibility
The width of each flange, not including end taper is to prohibits the use of through fastenings. Such rivets
be not less than 10 times the thickness given above are not to be used for joining components having a
and including the end taper, 13 times the thickness total thickness exceeding 12.5 mm (0.50 in.), and are
given above, and in general not less than 50mm (2 not to be used for joining decks to hulls except as
in.) temporary or unstressed fastenings installed for the
sake of convenience or speed during assembly.
c Conventional Rivets Conventional rivets,
where used, are to be subject to special consideration,
and are to be of the cold-driven type. Washers,
essentially of the same material as the rivets, are to be
installed under both the heads and the points.

PART 3 SECTION 14|4 Arrangement, Structural Details and Connections


3/14.3.2 Fiber Reinforced Plastic Location Pitch1
a General Components may be fastened with Watertight connections below design waterline 10d
bolts, machine screws, or self-tapping screws. Where Connections in hull above design waterline to 15d
machine screws or self-tapping screws are used, they deck
are not to have countersunk heads. Shanks of all Hull to deck connections, bonded with approved 15d
threaded fastenings are to be long enough to pass structural adhesive
through the joints. Where watertight joints are Connections in deckhouses 20d
required, suitable sealants or bedding compounds are Deckhouse to deck connection, bonded with 15d
to be used in addition to the fastenings. Mechanical approved structural adhesive
fastenings are to be of material suitable for the service Minimum distance between reeled lines of bolts 3d
intended and are to be either galvanically compatible
Notes: 1. d is the diameter of the bolt.
with the materials being fastened or provided with the
2. Internal boundary sealing angle is to be
necessary insulation. Brass fastenings are not to be provided.
used. Non corrosion-resistant fastenings are to be
galvanized. Fastenings used with aluminum alloys All structural, single line, bolted connections
are to be austenitic corrosion-resistant (stainless) steel without adhesive bonding are to be in accordance
or suitable aluminum alloy. Sizes and specifications with the requirements in the following table.
are to be indicated on the submitted plans. The
diameter of a fastening is not to be less than the Location Pitch1
thickness of the thinner component being fastened, Manhole covers to fuel tanks 6d
with a minimum diameter of 6 mm (0.24 in.)
Manhole covers to water tanks 8d
b Bolts and Machine Screws Bolts or machine
Covers to void tanks/cofferdams 10d
screws are to be used where accessibility permits.
Bolted access hatches in decks 10d
The diameter of each fastener is to be at least equal to
the thickness of the thinner component being Bolted watertight door frames 8d
fastened. Bolts and machine screws less than 6.5 mm Window frames 8d
(0.25 in.) in diameter are not to be used. Where d is Note: 1. d is the diameter of the bolt
the fastener diameter, fastener centers are to be
spaced at a minimum of 3d apart and are to be set in Bolt holes are to be drilled, without undue
from edges of laminates a minimum of 3d. pressure at breakthrough, having a diametric
Generally in fiber reinforces plastic construction tolerance of two percent of the bolt diameter. Where
all bolted connections are to be made through solid bolted connections are to be made watertight, the hole
fiber reinforces plastic inserts. Where this is not is to be sealed with resin and allowed to cure before
possible, all low density core material is to be the bolt is inserted. In areas of high stress or where
replaced with a structurally effective insert. unusual bolting configurations, on the basis of
Diameters of fastening holes are not to exceed equivalence with the above requirements, are
fastening diameters by more than 0.4 mm (0.0156 in.) proposed, testing may be required.
Washers or backing plates are to be installed c Self-tapping Screws In general no self-tapping
under all fastening heads and nuts that otherwise screws are to be used in fiber reinforced plastic
would bear on laminates. Washers are to measure not construction. Self-tapping screws having straight
less than 2.25d in outside diameter and 0.1d in shanks may be used for non-structural connections
thickness. Nuts are to be either of the self-locking where lack of accessibility prohibits the use of
type, or other effective means are to be provided to through fastenings. Where used, self-tapping screws
prevent backing off. are to have coarse threads.
Care is to be taken to ensure that the nut or other
component into which the bolt is screwed are of 3/14.3.3 Backing Bars and Tapping Plates
materials having the same mechanical properties. The requirements for backing plates and bars will be
Where materials of different strength are used, this is individually considered, on the basis of the loading
to be considered in determining the length of thread imposed, details of which are to be indicated on the
engagement between members. submitted plans. Metal plates and bars are to be
Bolted connections are, in general, to be bonded suitably protected against corrosion. Tapping plates
along all mating surfaces using an accepted structural may be encapsulated within the laminate, laminated
adhesive, applied in accordance with the to or bolted to the structure. Tapping plate edges or
manufacturer’s requirements. corners are to be suitably rounded.
In general, all structural, bolted connections are to
use threads of bolts in accordance with the
requirements in the following table.

PART 3 SECTION 14|5 Arrangement, Structural Details and Connections


3/14.5 Deck-to-Hull Joints
Inch Units
3/14.5.1 Weather Joints Length Minimum Minimum Bolt Spacing (in.)
The connection is to develop the strength of the deck of Craft Width of Bolt Unrestricted Restricted
and shell laminate, whichever is stronger, by either a (ft ) Overlap Diameter Service Service
(in.) (in.)
bolted or bonded connection.
30 2.5 0.25 6.0 9.0
40 3.0 0.30 6.5 9.5
Figure 3/14.9Deck-to-Hull Weather Joints 50 3.5 0.35 7.0 10.0
60 4.0 0.40 7.5 10.5
70 4.5 0.45 8.0 11.0
80 5.0 0.50 8.5 11.5
90 5.5 0.55 9.0 12.0
100 6.0 0.60 9.5 12.5
110 6.5 0.65 10.0 13.0
120 7.0 0.70 10.5 13.5

Each joint is to be protected as shown in Figure


3/14.15 by a guard, molding, fender, or rail cap of
metal, wood, rubber, plastic, or other approved
material. The size and ruggedness of this protective
Where flanges are used, the hull flanges are to be
strip are to be consistent with the severity of the
equal in thickness and strength to the hull laminates
service for which the craft is intended. The strip is to
and the deck flanges are to be equal in strength and
be installed in such a manner that it may be removed
thickness to the deck laminates. Where bolts are used
for repair or replacement without endangering the
to develop the required strength of the connection, the
integrity of the deck-to-hull joint.
faying surfaces are to be set in bedding compound,
polyester putty, or other approved material.
3/14.5.2 Interior Joints
Minimum widths of overlaps, minimum bolt
Interior decks are to be connected to the hull by
diameters, and maximum bolt spacing are to be in
shelves, stringers, or other structural members on
accordance with Table 3/14.1. Intermediate values
both sides by FRP tapes. The connection is to
may be obtained by interpolation.
effectively develop the strength of the interior deck.
FRP bonding angles, where used, are to have
flanges of the same strength and of at least one-half
3/14.7 Shell Details
the thickness of single skin hull or deck laminate. On
sandwich laminates, they are to have the same
3/14.7.1 Keels
strength and thickness as the skin of a sandwich
Plate keels are to be not less than shown in Figure
laminate, based on the thicker of the two laminates
3/14.10a and 3/14.10b, and vertical keels or skegs are
being connected. The widths of the flanges are to be
to be not less than shown in Figure 3/14.11. Keels or
in accordance with the widths of overlaps in Table
skegs are to be adequate for docking loads, which are
3/14.1.
to be provided by the designer.
Table 3/14.1 Deck-to-Hull Joints
Metric Units:
Length Minimum Minimum Bolt Spacing (mm)
of Craft Width of Bolt Unrestricted Restricted
(m) Overlap Diameter Service Service
(mm) (mm)
9 63.5 6.50 152.5 228.5
12 75.0 7.75 165.0 241.5
15 87.5 9.00 177.5 254.0
18 100.0 10.25 190.5 266.5
21 112.5 11.50 203.0 279.5
24 125.0 12.75 216.5 292.0
27 137.5 14.00 228.5 305.0
30 150.0 15.25 241.5 317.5
33 162.5 16.50 254.0 330.0
36 175.0 17.75 266.5 343.0

PART 3 SECTION 14|6 Arrangement, Structural Details and Connections


Figure 3/14.10a Plate Keel in One-Piece 3/14.7.2 Chines and Transoms
Hull Chines and transoms are to be not less than shown in
Figure 3/14.12.

Figure 3/14.12 Chine or Transom

Figure 3/14.10b Plate Keel in Hull


Molded in Halves

Figure 3/14.11 Vertical Keel or Skeg

PART 3 SECTION 14|7 Arrangement, Structural Details and Connections


PART 3 SECTION 18

Protection of Deck Openings

3/18.1 General whole structure, when closed, is equivalent to the


unpierced bulkhead.
All openings in decks are to be framed to provide Doors for access openings into enclosed
efficient support and attachment for the ends of the superstructures are to be of steel or other equivalent
deck beams. The proposed arrangement and details material, permanently and strongly attached to the
for all hatchways are to be submitted for approval. bulkhead. The doors are to be provided with gaskets
and clamping devices, or other equivalent
3/18.3 Position of Deck Openings arrangements, permanently attached to the bulkhead
or to the doors themselves, and the doors are to be so
For the purpose of this Guide, two positions of deck arranged that they can be operated from both sides of
openings are defined as follows: the bulkhead.
Portlights in the end bulkheads of enclosed
Position 1 Upon exposed freeboard and raised superstructures are to be of substantial construction
quarter decks, and upon exposed and provided with efficient inside deadlights. Also
superstructure decks situated forward of see 3/20.7 and 3/20.8
a point located a quarter of the craft The location and means of the closing appliances
length from the forward perpendicular. for windows are to be in accordance with 3/20.8
Position 2 Upon exposed superstructure decks
situated abaft a quarter of the craft length 3/18.7.2 Sills of Access Openings
from the forward perpendicular. Except as otherwise provided in this Guide, the height
of the sills of access openings in bulkheads at the
3/18.5 Hatchway Coamings, Companionway ends of enclosed superstructures is to be at least 380
Sills and Access Sills mm (15 in.) above the deck. See Table 3/18.1 for
required sill heights.
3/18.5.1 Coaming and Sill Heights
The heights above deck of the coamings, the sills of 3/18.7.3 Means of Access
companionways and access openings, are to be not Superstructures are not to be regarded as enclosed
less than given in Table 3/18.1. Where hatch covers unless access is provided for the crew to reach
are made of steel or other equivalent material and machinery and other working spaces inside these
made tight by means of gaskets and clamping devices, superstructures by alternate means which are
these heights may be reduced, or the coamings available at all times when bulkhead openings are
omitted entirely, provided that the safety of the craft closed.
is not thereby impaired in any sea conditions. Sealing
arrangements are to be weathertight if coaming is 3/18.9 Hatchways Closed by Covers of Steel and
fitted, and watertight for flush covers. Fitted with Gaskets and Clamping
Devices
3/18.7 Enclosed Superstructures
Superstructures are to meet the following 3/18.9.1 Strength of Covers
requirements to be considered enclosed. The maximum allowable stress and deflection under
Superstructures with openings which do not fully design load, w, and the minimum top plate thickness
comply with these requirements are to be considered are as follows:
as open superstructures. See also 3/20.3.4 maximum allowable stress = 0.235σu
maximum allowable deflection = 0.0028s
3/18.7.1 Closing Appliances top plate thickness = 0.01s; but not less than
All openings in the bulkheads of enclosed 6.0mm (0.24in.)
superstructures are to be provided with efficient
means of closing, so that in any sea conditions water
will not penetrate the craft. Opening and closing
appliances are to be framed and stiffened so that the

PART 3 SECTION 18|1 Protection of Deck Openings


Position 1 SM = 7.8hsl2 cm3 SM = 0.0041hsl2 in.3
w= 0.097L + 7.45 kN/m2
w= 0.0099L + 0.76 tf/m2 h = 'tween-deck height in m or ft
w= 0.61L + 158.0 lbf/ft2 s = spacing of the stiffeners in m or ft
l = length of the stiffener in m or ft
Position 2
w= 0.0709L + 5.65 kN/m2 3/18.11.4 Wheel Loading
w= 0.00725L + 0.576 tf/m2 Where provision is to be made for the operation and
w= 0.450L + 118.5 lbf/ft2 stowage of vehicles having rubber tires, the thickness
of the hatch cover plating is to be in accordance with
w = design load in kN/m2 (tf/m2, lbf/ft2) the Rules for Building and Classing Steel Vessels
L = length of craft in m or ft as defined in under 90m (295 ft) in Length, section 3/18.11.4
Section 3/1, but is not to be taken less than
24 m (79 ft). 3/18.13 Hatchways within Open Superstructures
s = stiffener spacing in mm or in.
σu = minimum ultimate tensile strength in N/mm2 Hatchways within open superstructures are to be
(kgf/mm2, psi) considered as exposed.

3/18.9.2 Means for Securing Weathertightness 3/18.15 Hatchways within Deckhouses


The means for securing and maintaining
weathertightness is to be such that the tightness can Hatchways within deckhouses are to have coamings
be maintained in any sea condition. The covers are to and closing arrangements as required in relation to
be hose tested in position under a water pressure of at the protection afforded by the deckhouse from the
least 2.1 bar (2.1 kgf/cm2, 30 psi) at the time of standpoint of its construction and the means provided
installation. for the closing of all openings into the house.

3/18.9.3 Flush Hatch Covers 3/18.17 Machinery Casings


Where flush hatch covers are fitted on the freeboard
deck within the forward one-fourth length, and the 3/18.17.1 Arrangement
craft is assigned a freeboard less than Type-B under Machinery-space openings in Position 1 or 2 are to be
the International Convention on Load Lines 1966, the framed and efficiently enclosed by casings of ample
assumed loads on flush hatch covers are to be strength, and wherever practicable, those in freeboard
increase 15% over that indicated in 3/18.9.1. decks are to be within superstructures or deckhouses.
Casings are to be of material similar to that of the
3/18.11 Hatchways Closed by Portable Covers in surrounding structure. Openings in exposed casings
Lower Decks or within Fully Enclosed are to be fitted with doors complying with the
Superstructures requirements of 3/18.7.1; the sills are to be in
accordance with 3/18.5.1 for companionways. Other
3/18.11.1 General openings in such casings are to be fitted with
The following scantlings are intended for equivalent covers, permanently attached. Stiffeners
conventional type covers. Those for covers of special are to be spaced at not more than 760 mm (30 in.)
types are to be specially considered.
3/18.17.3 Scantlings
3/18.11.3 Steel Covers
The thickness of the plating for steel covers is not to The scantlings of exposed casings are to be similar to
be less than required for lower decks as obtained those obtained for superstructures and deckhouses in
from 3/9.1. A stiffening bar is to be fitted around the accordance with the applicable requirements of
edges as required to provide the necessary rigidity to Sections 3/8, 3/9 and 3/10.
permit the covers being handled without deformation. The scantlings of casings within enclosed
The effective depth of the framework is normally to superstructures or deckhouses will be specially
be not less than 4% of its unsupported length. The considered.
stiffeners in association with the plating to which they
are attached are to have section modulus, SM, as
determined by the following equation.:

PART 3 SECTION 18|2 Protection of Deck Openings


3/18.19 Miscellaneous Openings in Freeboard and
Superstructure Decks
TABLE 3/18.1
3/18.19.1 Manholes and Scuttles Coaming and Sill Heights
Manholes and flush scuttles in Position 1 or 2 within
superstructures other than enclosed superstructures L equal to or over 24 meters (79 feet) in length
are to be closed by substantial covers capable of
Position 1 Position 2
being made watertight. Unless secured by closely
Hatch Coamings 600 mm (23.5 in.) 450 mm (17.5 in.)
spaced bolts, the covers are to be permanently
Companionway 600 mm (23.5 in.) 380 mm (15 in.)
attached.
Sills
Access Sills 380 mm (15 in.) 380 mm (15 in.)
3/18.19.2 Other Openings
Openings in freeboard decks other than hatchways,
L under 24 meters (79 feet) in length
machinery-space openings, manholes and flush
Position 1 Position 2
scuttles are to be protected by an enclosed
superstructure, or by a deckhouse or companionway Hatch Coamings
and 450 mm (17.5 in.) 300 mm (12 in.)
of equivalent strength and weathertightness. Any such
Companionways
opening in an exposed superstructure deck or in the
Access Sills 380 mm (15 in.) 300 mm (12 in.)
top of a deckhouse on the freeboard deck which gives
access to a space below the freeboard deck or a space Note:
within an enclosed superstructure is to be protected 1 Coaming and sill heights may be reduced on craft
by an efficient deckhouse or companionway. which have freeboard in excess of the minimum
Doorways in such deckhouses or companionways are geometric freeboard and/or a superstructure deck with
height of deck in excess of the standard height of a
to fitted with doors complying with the requirements
superstructure.
given in 3/18.7.1. 2 For craft with L<24m, the coaming/sill height should
be as indicated above, unless otherwise specifically
3/18.19.3 Escape Openings requested by Flag Administration.
The closing appliances of escape openings are to be
readily operable from each side.

PART 3 SECTION 18|3 Protection of Deck Openings


PART 3 SECTION 20

Bulwarks, Rails, Ports,


Portlights, Windows, and Ventilators
3/20.1 Bulwarks and Guard Rails well 20 m (66 ft) or less in length is to be obtained
from the following equation:
3/20.1.1 Location and Heights
Bulwarks or guard rails or a combination of both, are A = 0.7 + 0.035l m2 A = 7.6 + 0.115l ft2
in general to be provided on exposed decks, and on
exposed tops of superstructures and deckhouses. Where the bulwark length exceeds 20 m (66 ft):
The height of bulwarks and guard rails on
exposed freeboard and superstructure decks is to be at A = 0.07l m2 A = 0.23l ft2
least 1 m (39.5 in.) Where this height would interfere
with the normal service or operation of a craft, a A = freeing-port area in m2 or ft2
lesser height may be approved if adequate protection l = bulwark length in m or ft but need not
is provided. Where approval of a lesser height is exceed 0.7L.
requested, justifying information is to be submitted.
In exposed areas not traversed in the normal The minimum area for each well on superstructure
operation of the craft, where it is not practical to fit decks is to be one half of the area obtained from the
bulwarks or guard rails, hand or grab rails may be above equations.
considered.
If a bulwark is more than 1.2 m (3.9 ft) in height, the
3/20.1.2 Strength of Bulwarks freeing-port area is to be increased by 0.004 m2 per
Bulwarks are to be of ample strength for their height meter (0.04 ft2 per foot) of length of well for each 0.1
and location, suitably stiffened at the top, and if m (1 ft) difference in height. If a bulwark is less than
necessary at the bottom, and supported by efficient 0.9 m (3 ft) in height, the freeing-port area may be
stays or brackets. decreased by the same ratio. Craft receiving freeboard
Stays or brackets on the main weather deck are to assignment are to have freeing port area in
be spaced not more than 1.83 m (6.0 ft). accordance with the International Convention on
Openings in bulwarks are to be smooth-edged, Load Lines.
with well-rounded corners.
3/20.3.2 Trunks, Deckhouses, and Hatchway
3/20.1.3 Spacing of Guard Rails Coamings
a Fixed, removable or hinged stanchions are to Where a craft is fitted with a trunk on the freeboard
be fitted at approximately 1.5 m (5 ft) apart. deck, and open rails are not fitted in way of the trunk
b At least every third stanchions is to be for at least one-half its length, or where continuous or
supported by a bracket or stay. substantially continuous hatchway side coamings are
c The opening below the lowest course is not to fitted or long deckhouse exist between detached
exceed 230 mm (9 in.) The distance between the superstructures, the minimum area of freeing-port
remaining courses is not to be more than 380 mm (15 openings is to be obtained from the following table:
in.)
d For craft with rounded gunwales, stanchions Breadth of trunk, deckhouse Area of freeing ports
are to be placed on the flat of the deck. or hatchway in relation to in relation to total
breadth of craft area of bulwarks
3/20.3 Freeing Ports 40% or less 20%
75% or more 10%
3/20.3.1 Basic Area
Where bulwarks on freeboard decks form wells, The area of freeing ports at intermediate breadths is
ample provision is to be made for rapidly freeing the to be obtained by linear interpolation.
decks of water and for draining them. The minimum
freeing-port area on each side of the craft for each

PART 3 SECTION 20|1 Bulwarks, Rails, Ports, Portlights, Windows, and Ventilators
3/20.3.3 Superstructure Decks 3/20.6 Bow Doors and Inner Doors
Where bulwarks on superstructure decks form wells, Where steel bow doors of the visor or side-opening
the bulwarks are to comply with 3/20.3.1 except that type are fitted leading to complete or long forward
the minimum freeing-port area on each side of the enclosed superstructure, bow doors and inner doors
craft for each well is to be one-half of the area are to meet the requirements of this subsection. Hull
obtained in 3/20.3.1 and 3/20.3.2. supporting structure in way of the bow doors is to be
able to withstand the loads imposed by the bow doors
3/20.3.4 Open Superstructures securing and supporting devices without exceeding
In craft having superstructures that are open at either the allowable stresses for those devices, both given in
end or both ends, adequate provisions for freeing the this subsection. Special consideration will be given
spaces within such superstructures are to be provided; to bow doors constructed of materials other than
the arrangements will be subject to special approval. steel.

3/20.3.5 Details of Freeing Ports 3/20.6.1 Arrangement


The lower edges of the freeing ports are to be as near As far as practicable, bow doors and inner doors are
the deck as practicable. Two-thirds of the required to be arranged so as to preclude the possibility of the
freeing-port area is to be provided in the half of the bow door causing structural damage to the inner door
well nearest the lowest point of the sheer curve. or to the collision bulkhead in the case of damage to
Freeing-port openings are to be protected by rails or or detachment of the bow door.
bars in such a manner that the maximum clear vertical a Bow Doors Bow doors are to be situated
or horizontal space is 230 mm (9 in.). Where shutters above the freeboard deck except that where a
are fitted, ample clearance is to be provided to watertight recess fitted for arrangement of ramps or
prevent them from jamming. Hinges are to have pins other related mechanical devices is located forward of
and bearings of corrosion resistant material and in the collision bulkhead and above the deepest
general, the hinges are to be located at the top of the waterline, the bow doors may be situated above the
shutter. If the shutters are equipped with securing recess.
appliances, the appliances are to be of approved b Inner Doors An inner door is to be fitted in
construction. the extension of the collision bulkhead required by
3/12.1.2a. A vehicle ramp made watertight and
3/20.5 Cargo, Gangway, or Fueling Ports conforming to 3/12.1.2a in the closed position may be
accepted for this purpose.
3/20.5.1 Construction
Cargo, gangway, or fueling ports in the sides of craft 3/20.6.2 Securing, Locking and Supporting of
are to be strongly constructed and capable of being Doors
made thoroughly watertight. Where frames are cut in a Definitions
way of such ports, web frames are to be fitted on the 1 Securing device A device used to keep the
sides of the openings, and suitable arrangements are door closed by preventing it from rotating about
to be provided for the support of the beams over the its hinges or its pivoted attachments to the ship.
openings. Thick shell plates or doublers are to be 2 Supporting device A device used to transmit
fitted as required to compensate for the openings. The external or internal loads from the door to a
corners of the openings are to be well rounded. securing device and from the securing device to
Waterway angles and scuppers are to be provided on the ship’s structure, or a device other than a
the decks in way of ports in cargo spaces below the securing device, such as a hinge, stopper or
freeboard deck or in cargo spaces within enclosed other fixed device, that transmits loads from the
superstructures to prevent the spread of any leakage door to the ship’s structure.
water over the decks. 3 Locking device A device that locks a securing
Indicators showing whether the ports in the side device in the closed position.
shell below the freeboard or superstructure deck are b Securing and Supporting devices
secured closed or open are to be provided on the 1 Bow Doors Means are to be provided to
navigation bridge. prevent lateral or vertical movement of the bow
doors when closed. Means are also to be
3/20.5.2 Location provided for mechanically fixing the door in the
The lower edges of cargo, gangway, or fueling-port open position.
openings are not to be below a line parallel to the Means of securing and supporting the door
freeboard deck at side having as its lowest point the are to maintain equivalent strength and stiffness
designed load waterline or upper edge of the of the adjacent structure.
uppermost load line.

PART 3 SECTION 20|2 Bulwarks, Rails, Ports, Portlights, Windows, and Ventilators
a Clearance and packing The maximum to be supplemented by warning indicator
design clearance between the door and lights as indicated in 3/20.6.2c2a
securing/supporting devices is not to exceed 3 2 Indication/Monitoring
mm (0.12 in.). Where packing is fitted, it is to a Indicators The indicator system is to be
be of a comparatively soft type and the designed on the fail safe principle and in
supporting forces are to be carried by the steel accordance with the following:
structure only. 1 Location and Type Separate indicator
b Visor Door Arrangement The pivot lights are to be provided on the
arrangement is to be such that the visor is self navigation bridge to show that the bow
closing under external loads. The closing door and inner door are closed and that
moment, My, as defined in 3/20.6.6a3a is not their locking devices are properly
to be less than Myo as given by the following positioned.
equation. The indication panel on the
navigation bridge is to be equipped with
M yo = Wc + 01
. a 2 + b 2 Fx2 + Fz2 a mode selection function “harbor/sea
voyage”, arranged so that an audible and
Where W, a, b, c, Fx and Fz are as defined in visible alarm is given if in the sea voyage
3/20.6.6. condition, the bow door or inner door is
In addition, the arrangement of the door is not closed, or any of the securing devices
to be such that the reaction forces of pin or is not in the correct position.
wedge supports at the base of the door does Indication of the open/closed position
not act in the forward direction when the door of every door and every securing and
is loaded in accordance with 3/20.6.6a3d. locking device is to be provided at the
c Securing and Locking arrangement operating panels.
Securing devices are to be provided with a 2 Indicator lights Indicator lights are to
mechanical locking arrangement (self locking be designed so that they cannot be
or separate arrangement), or are to be of the manually turned off. The indication
gravity type. panel is to be provided with a lamp test
1 Operation Securing devices are to be function.
simple to operate and readily accessible. 3 Power Supply The power supply for the
The opening and closing systems as well as indicator system is to be independent of
the securing and locking devices are to be the power supply for operating and
interlocked in such a way that they can only closing the doors.
operate in the proper sequence. 4 Protection of Sensors Sensors are to be
a Hydraulic securing devices Where protected from water, ice formation and
hydraulic securing devices are applied, the mechanical damage.
system is to be mechanically lockable in b Water Leakage Protection A drainage
the closed position. In the event of a loss system is to be arranged in the area
of hydraulic fluid, the securing devices are between the bow door and ramp and in the
to remain locked. area between the ramp and inner door
The hydraulic system for securing and where fitted. The system is to be equipped
locking devices is to be isolated from other with an audible alarm function to the
hydraulic circuits when in the closed navigation bridge for water level in these
position. areas exceeding 0.5m (1.6 ft.) above the
b Remote Control Where bow doors and car deck level.
inner doors give access to a vehicle deck, A water leakage detection system with
an arrangement for remote control from a audible alarm and television surveillance
position above the freeboard deck is to be are to be arranged to provide an indication
provided allowing closing and opening of to the navigation bridge and to the engine
the doors and associated securing and control room of leakage through the inner
locking of the securing and locking door.
devices for every door. The operating c Door surveillance Between the bow door
panels for operation of doors are to be and the inner door a television surveillance
accessible to authorized persons only. A system is to be fitted with a monitor on the
notice plate giving instructions to the navigation bridge and in the engine control
effect that all securing devices are to be room. The system is to monitor the
closed and locked before leaving harbor is position of doors and a sufficient number
to be placed at each operating panel and is of their securing devices.

PART 3 SECTION 20|3 Bulwarks, Rails, Ports, Portlights, Windows, and Ventilators
3/20.6.3 Tightness packing material are not to be included in the
a Bow Doors Bow doors are to be so fitted as calculations.
to ensure tightness consistent with operational 1 Bearing Pressure The bearing pressure on
conditions and to give effective protection to the steel to steel bearings is to be calculated by
inner doors. dividing the design force by the projected
b Inner Doors Inner doors forming part of the bearing area, and is not to exceed the allowable
extension of the collision bulkhead are to be stress given in 3/20.6.7b.
weathertight over the full height of the cargo space 2 Redundancy In addition to the above
and arranged with fixed sealing supports on the aft requirements, the arrangement of the securing
side of the doors. and supporting devices is to be designed with
redundancy such that in the event of failure of
3/20.6.4 Bow Door Scantlings any single securing or supporting device, the
Bow doors are to be framed and stiffened so that the stresses in the remaining devices do not exceed
whole structure is equivalent to the unpierced the allowable stresses indicated in 3/20.6.7a by
bulkhead when closed. more than 20% under the above loads.
a Primary Structure Scantlings of primary 3 Visor Door Securing and Supporting Devices
members are to be designed so that the allowable Securing and supporting devices, excluding the
stresses indicated in 3/20.6.7a are not exceeded when hinges, are to be capable of resisting the vertical
the structure is subjected to the design loads indicated design force given in 3/20.6.6a3c without
in 3/20.6.6a1. stresses exceeding the allowable stresses in
b Secondary Stiffeners Secondary stiffeners are 3/20.6.7a.
to be supported by primary members constituting the Two securing devices are to be provided at
main stiffening of the door. The section modulus, the lower part of the door, each capable of
SM, of secondary stiffeners is to be as required by providing the full reaction force required to
3/10.1.2. In addition, stiffener webs are to have a net prevent opening of the door without stresses
sectional area not less than that obtained from the exceeding the allowable stresses indicated in
following equation: 3/20.6.7a. The opening moment, Mo, to be
balanced by this force is as given in
A = VQ/10 cm2 (A = VQ cm2, A = VQ/6.5 in2)
3/20.6.6a3b.
where 4 Side-opening Door Thrust Bearing A thrust
V = shear force in kN (tf, Ltf) in the stiffener bearing is to be provided in way of girder ends
calculated using the uniformly distributed at the closing of the two doors, and is to prevent
external pressure Peb given in 3/20.6.6a1 one door from shifting towards the other one
Q = as defined in 3/6.1.1a. under the effect of unsymmetrical pressure.
c Plating The thickness of bow door plating is Securing devices are to be fitted to secure
to be not less than that required for side shell plating sections thrust bearing to one another.
at the same location. e Visor Door Lifting Arms and Supports
d Securing and Supporting Devices Scantlings Where visor type bow doors are fitted, calculations
of securing and supporting devices are to be designed are to be submitted verifying that lifting arms and
so that the allowable stresses indicated in 3/20.6.7a their connections to the door and ship structure are
are not exceeded when the structure is subjected to adequate to withstand the static and dynamic forces
the design loads indicated in 3/20.6.6a2. All load applied during the lifting and lowering operations
transmitting elements in the design load path from the under a wind pressure of at least 1.5 kN/m2 (0.15
door through securing and supporting devices into the tf/m2, 0.014 Ltf/ft2)
ship structure, including welded connections, are to
meet the strength standards required for securing and 3/20.6.5 Inner Door Scantlings
supporting devices. Where fitted, threaded bolts are Scantlings of inner doors are to meet the requirements
not to carry support forces, and the maximum tensile of this paragraph. In addition, where inner doors are
stress in way of the threads is not to exceed the used as vehicle ramps, scantlings are not to be less
allowable stress given in 3/20.6.7c. than required for vehicle decks.
In determining the required scantlings, the door is a Primary Structure Scantlings of primary
to be assumed to be a rigid body. Only those active members are to be designed so that the allowable
supporting and securing devices having an effective stresses indicated in 3/20.6.7a are not exceeded when
stiffness in the relevant direction are to be included the structure is subjected to the design loads indicated
and considered when calculating the reaction forces in 3/20.6.6b1.
on the devices. Small or flexible devices such as
cleats intended to provide load compression of the

PART 3 SECTION 20|4 Bulwarks, Rails, Ports, Portlights, Windows, and Ventilators
b Securing and Supporting Devices Scantlings Fy = the design external force in the
of securing and supporting devices are to be designed horizontal direction in kN (tf, Ltf)
so that the allowable stresses indicated in 3/20.6.7a Fz = the design external force in the
are not exceeded when the structure is subjected to vertical direction in kN (tf, Ltf)
the design loads indicated in 3/20.6.6b. Where fitted, Ax = area in m2 (ft.2) of the transverse
threaded bolts are not to carry support forces, and the vertical projection of the door
maximum tensile stress in way of the threads is not to between the levels of the bottom of
exceed the allowable stress given in 3/20.6.7c. the door and the upper deck or
The bearing pressure on steel to steel bearings is between the bottom of the door and
to be calculated by dividing the design force by the the top of the door, whichever is less.
projected bearing area, and is not to exceed the Ay = area in m2 (ft.2) of the longitudinal
allowable stress given in 3/20.6.7b. vertical projection of the door
between the levels of the bottom of
3/20.6.6 Design Loads the door and the upper deck or
a Bow Doors between the bottom of the door and
1 External Pressure The design external the top of the door, whichever is less.
pressure, Peb, is to be taken as indicated by the Az = area in m2 (ft.2) of the horizontal
following equation. Peb for craft engaged in projection of the door between the
restricted service will be specially considered. levels of the bottom of the door and
the upper deck or between the bottom
Peb = nc(0.22 + 015 (
. tan β ) 0.4Vd sin α + 0.6 kL )
2
of the door and the top of the door,
whichever is less.
kN/m2 (tf/m2, Ltf/ft.2) Pem = bow door pressure, Peb, determined
where using αm and βm in place of α and β.
n = 2.75 (0.280, 0.0256) βm = flare angle measured at a point on the
c = 0.0125L for craft having L < 80 m (260 ft.) bow door l/2 aft of the stem line on a
= 1.0 for other craft plane h/2 above the bottom of the
L = length of craft as defined in 3/1.1 in m or door as shown in Figure 3/20.1b.
ft. αm = entry angle measured at the same
β = flare angle at the point to be considered, point as βm. See Figure 3/20.1b.
defined as the angle between a vertical line h = height in m (ft.) of the door between
and the tangent to the side shell plating the levels of the bottom of the door
measured in a vertical plane normal to the and the upper deck or between the
horizontal tangent to the shell plating. See bottom of the door and the top of the
Figure 3/20.1a. door, whichever is less.
α = entry angle at the point to be considered, l = length in m (ft.) of the door at a
defined as the angle between a longitudinal height h/2 above the bottom of the
line parallel to the centerline and the door.
tangent to the shell plating in a horizontal 3 Visor Door Load Cases
plane. See Figure 3/20.1a. a Closing Moment For visor doors, the
k = 1.0 (1.0, 0.305) closing moment, My is to be taken as
Vd = craft design speed as defined in 3/5.2.1 indicated by the following equation:
My = Fxa + Wc - Fzb kN-m (tf-m, Ltf-ft.)
2 External Forces The design external forces
considered in determining scantlings of where
securing and supporting devices of bow doors Fx and Fz are as defined in 3/20.6.6a2
are not to be taken less than those given by the W = weight of the visor door in kN (tf, Ltf)
following equations. a = vertical distance in m (ft.) from the
visor pivot to the centroid of the
Fx = PemAx transverse vertical projected area of the
Fy = PemAy visor door. See Figure 3/20.2.
b = horizontal distance in m (ft.) from
Fz = PemAz visor pivot to the centroid of the
where horizontal projected area of the visor
Fx = the design external force in the door. See Figure 3/20.2.
longitudinal direction in kN (tf, Ltf)

PART 3 SECTION 20|5 Bulwarks, Rails, Ports, Portlights, Windows, and Ventilators
c = horizontal distance in m (ft.) from the 3/20.6.7 Allowable Stresses
visor pivot to the center of gravity of the a Primary Structure and Securing and
visor. See Figure 3/20.2. Supporting Devices The following stresses are not
b Opening Moment The opening moment, to be exceeded under the loads indicated above.
Mo, is to be taken as indicated by the
following equation: Shear Stress: τ = 80/Q N/mm2
Mo = Wd + 5Axa kN-m (8.2/Q kgf/mm2,
11600/Q psi)
(Wd + 0.5Axa tf-m, Wd + 0.047Axa Ltf-ft.) Bending Stress: σ = 120/Q N/mm2
where (12.2/Q kgf/mm2,
d = vertical distance, in m (ft.), from the 17400/Q psi)
hinge axis to the center of gravity of the Equivalent Stress σe = 150/Q N/mm2
door.
s( σ + 3τ ):
2 2 (15.3/Q kgf/
W, Ax and a are as indicated above. mm2, 18000/Q psi)
c Vertical design Force The vertical design
force is to be taken as Fz-W where Fz is as where Q is as defined in 3/6.1.1a.
defined in 3/20.6.6a2 and W is as defined in b Steel Securing and Supporting Devices
3/20.6.6a3a. Bearing Stress For steel to steel bearings in securing
d Combined Load Case 1 The visor doors and supporting devices, the nominal bearing pressure
are to be evaluated under a load of Fx, Fz and is not to exceed 0.8σf, where σf is the yield stress of
W acting simultaneously with Fx and Fz the bearing material.
acting at the centroid of their respective c Tensile stress on threaded bolts The tensile
projected areas. stress in threaded bolts is not to exceed 125/Q N/mm2
e Combined Load Case 2 The visor doors (12.7/Q kgf/mm2, 18,000/Q psi).
are to be evaluated under a load of 0.7Fy
acting on each side separately together with 3/20.6.8 Operating and Maintenance Manual
0.7Fx, 0.7Fz and W. Fx, Fy and Fz are to be The following information is to be submitted for
taken as acting at the centroid of their review:
respective projected areas. a Manual An operating and maintenance manual
4 Side-Opening Door Load Cases for the bow door and inner door is to be provided on
a Combined Load Case 1 Side opening board and is to contain the following:
doors are to be evaluated under a load of Fx,
Fy, Fz and W acting simultaneously with Fx, main particulars and design drawings
Fy and Fz acting at the centroid of their service conditions, e.g. service area
respective projected areas. restrictions, acceptable clearances for
b Combined Load Case 2 Side opening supports
doors are to be evaluated under a load of maintenance and function testing
0.7Fx, 0.7Fz and W acting on both doors register of inspections and repairs
simultaneously and 0.7Fy acting on each b Operating Procedures Documented operating
door separately. procedures for closing and securing the bow door and
b Inner Doors inner door are to be kept on board and posted at an
1 External Pressure The design external appropriate location.
pressure is to be taken as the greater of Pei or
Ph as given by the following equations. 3/20.7 Portlights
2 2
Pei = 0.45L kN/m (0.046L1 tf/m ,
0.0042L1 Ltf/ft.2) 3/20.7.1 Construction
Portlights fitted below the main weather deck or in
Ph = 10h kN/m2 (1.0h tf/m2, superstructure and house side plating are to be of
0.029h Ltf/ft.2) substantial construction and provided with steel,
where aluminum or other approved material inside
L is as defined in 3/1.1. deadlights, permanently attached and arranged to be
h = the distance in m or ft. from the load capable of being closed and secured watertight.
point to the top of the cargo space. Except in way of the machinery space, portlights may
2 Internal Pressure The design internal be of the hinged opening type, with hinge pins of non-
pressure, Pi is to be taken as not less than 25 corrosive material. Where vessels are subject to
kN/m2 (2.5 tf/m2, 0.23 Ltf/ft2) damaged stability requirements of 3/3.3.2, portlights
found to be situated below a final damage equilibrium

PART 3 SECTION 20|6 Bulwarks, Rails, Ports, Portlights, Windows, and Ventilators
waterline are to be of the non opening type. Portlight 3/20.7.2 Testing
frames are to be of steel or other approved material All portlights are to be hose tested after installation.
and are to be attached to the hull by through bolts or
equivalent. Lower edges of portlights are not to be 3/20.8 Windows
below a line parallel to the main weather deck at side
having its lowest point at a distance above the design 3/20.8.1 Construction
waterline either 2.5% of the craft breadth or 500 mm Windows to spaces within enclosed superstructure
(19.5 in.) whichever is greater. and deckhouses are to be fitted with strong steel,
In craft limited in service range and weather aluminum or other approved material deadlight
conditions, consideration will be given to the covers. Windows should generally not be fitted in the
omission of deadlights depending on the type and end bulkheads of superstructures or deckhouses in
thickness of the portlight. Position 1. Window frames are to be of steel or other
The thickness of portlights of tempered or approved material and are to be attached by through
toughened monolithic safety glass is to be not less bolts or equivalent.
than given in Table 3/20.1. Consideration will also be Windows on the second tier above the freeboard
given to laminated glass, acrylic and polycarbonate deck may not require deadlight depending upon the
glazing materials based upon equivalent flexural arrangement of the craft. Window frames are to be
strength and stiffness. See Table 3/20.3 for glazing metal or other approval material, and effectively
mechanical properties. secured to the adjacent structure. Windows are to
have a minimum of a 1/4” radius at all corners. The
glazing is to be set into the frames in a suitable,
TABLE 3/20.1 approved packing or compound. Special
Thickness of Tempered or Toughened Monolithic consideration to be given to angled house fronts.
Glass Portlights The thickness of the window is not to be less than
that obtained from a, b, or c below, whichever is
a Rounded Portlights greater.
Location General Limited a.
Service
pk pk
Craft t=s (mm) t=s (in.)
Side shell below main weather 0.050d 0.040d 1000σ a σa
deck
Superstructure or deckhouse on 0.033d 0.033d b.
main weather deck
pk 1 pk1
Deckhouses above main weather 0.025d 0.025d t = s3 (mm) t = s3 (in.)
deck 20 E 0.02E
Notes: d is to be taken as the diameter between inner edges c. Minimum tempered monolithic glass
of the portlight frame in mm or in. thicknesses:
For calculation of required thickness on limited
service craft, d is not to be taken less than 250mm t = 9.5mm (0.37in.) for front windows
(10in.) t = 6.5mm (0.25in.) for side and end
windows.

b Rectangular Portlights t = required window thickness, in mm (in.)


s = lesser dimension of window in mm or in.
Location General Limited p = pressure head for window location as
Service
determined by 3/8.5
Craft
k = factor given in Table 3/20.2
Side shell below main weather 0 .0 9 1 s K 0 .0 7 3 s K k1 = factor given in Table 3/20.2
deck
σa = 0.30σf
Superstructures or deckhouses 0 . 0 6 0 s K 0 .0 6 0 s K σf = material flexural strength; see Table
on main weather deck
3/20.3
Deckhouses above main 0 .0 4 5 s K 0 .0 4 5 s K E = material flexural modulus; see Table
weather deck
3/20.3
Note: K is to be taken from Table 3/20.2; s is the short
panel dimension and l is the long window 3/20.8.2 Testing
dimension. All windows are to be hose tested after installation

PART 3 SECTION 20|7 Bulwarks, Rails, Ports, Portlights, Windows, and Ventilators
TABLE 3/20.2 The maximum steel coaming plate thickness required
is 10 mm (0.40 in.). The coamings are to be
l/s k k1 effectively secured to the deck. Coamings which are
>5 .750 .142 more than 900mm (35.5 in.) high and which are not
5 .748 .142 supported by adjacent structures are to have
4 .741 .140 additional strength and attachment. Ventilators
3 .713 .134 passing through superstructures other than enclosed
2 .610 .111 superstructures are to have substantially constructed
1.8 .569 .102
coamings of steel or equivalent material at the
freeboard deck. Coaming plate thickness of material
1.6 .517 .091
other than steel will be specially considered.
1.4 .435 .077
1.2 .376 .062
3/20.9.2 Coaming Height
1 .287 .044 Ventilators in Position 1 are to have coamings at least
l = greater dimension of window panel, in mm 900 mm (35.5 in.) high. Ventilators in Position 2 are
or in. to have coamings at least 760 mm (30 in.) high. For
s = lesser dimension of window panel, in mm or definitions of Position 1 and Position 2, see 3/18.3.
in. Coaming heights may be reduced on craft which have
freeboard in excess of the minimum geometric
TABLE 3/20.3 freeboard and/or a superstructure deck with height of
deck in excess of the standard height of a
superstructure.
Glazing Flexural Flexural Modulus
Strength 3/20.9.3 Means for Closing Ventilators
Except as provided below, ventilator openings are to
Tempered 119 MPa 73,000 MPa be provided with efficient, permanently attached
Monolithic (17,200 psi) (10,600,000 psi) closing appliances. In craft measuring 24 m (79 ft) or
more in length (as defined in the International
Laminated 69 Mpa 2,620 MPa Convention on Load Lines, 1966) ventilators in
Glass (10,000 psi) (380,000 psi) Position 1, the coamings of which extend to more
than 4.5 m (14.8 ft) above the deck and in Position 2,
Polycarbonate* 93 MPa 2,345 MPa the coamings of which extend to more than 2.3 m (7.5
(13,500 psi) (340,000 psi) ft) above the deck, need not be fitted with closing
arrangements.
Acrylic 110 Mpa 3,000 MPa These coaming height requirements may be
(PMMA) * (16,000 psi) (435,000 psi) modified in craft measuring less than 24 m (79 ft) in
length.
* Indicated values are for reference. Aging effects
are to be considered for design.

3/20.9 Ventilators

3/20.9.1 Coaming Construction


Ventilators on exposed freeboard decks,
superstructure decks, or deckhouses are to have
coamings of steel or equivalent material. Coaming
plate thicknesses for steel are to be obtained from the
following equation:

t = 0.01d + 5.5 mm t = 0.01d + 0.22 in.

t = thickness of coaming in mm or in.


d = diameter of ventilator in mm or in. but not
less than 200 mm (7.5in.)

PART 3 SECTION 20|8 Bulwarks, Rails, Ports, Portlights, Windows, and Ventilators
Figure 3/20.1a

Entry and Flare Angles

Figure 3/20.1b

Definition of αm and βm

PART 3 SECTION 20|9 Bulwarks, Rails, Ports, Portlights, Windows, and Ventilators
Figure 3/20.2

Visor Type Bow Door

PART 3 SECTION 20|10 Bulwarks, Rails, Ports, Portlights, Windows, and Ventilators
PART 3 SECTION 21

Protective Coatings
3/21.5 Protection of Steel 3/21.6.3 Faying Surfaces - Aluminum to
Aluminum
3/21.5.1 All Spaces Aluminum faying surfaces that will be exposed to
Unless otherwise approved, all steel work is to be weather, seawater, or other corrosive environment are
suitably coated with paint or equivalent. to be suitable coated to minimize crevice corrosion in
way of the faying surfaces.
3/21.5.2 Salt Water Ballast Space
Tanks or holds for salt water ballast are to have a 3/21.6.4 Faying Surface between Aluminum and
corrosion-resistant hard type coating such as epoxy or other Metals
zinc on all structural surfaces. Where a long retention a Hull Suitable means are to be taken to avoid
of salt water is expected due to the type of craft or direct contact of faying surfaces of aluminum to other
unit, special consideration for the use of inhibitors or metals. When such faying surfaces occur in hull
sacrificial anodes may be given. construction, suitable non-wicking and non-water
absorbing insulation tapes or coatings are to be used.
3/21.5.3 Oil Spaces Other types of joints between aluminum and other
Tanks intended for oil need not be coated. metals may be approved in certain applications.
b Piping Suitable means, such as special pipe
3/21.6 Protection of Aluminum hangers, are to be used to avoid conductive
connections between aluminum hulls and non-
3/21.6.1 General aluminum metal piping systems. Where
Aluminum alloys intended for hull construction are to watertightness is required, such as when piping passes
be used generally only under conditions that will not through bulkheads, decks, tanktops, and shell, special
induce excessive corrosion. Where exposure to fittings will be required to maintain isolation between
environment that would induce excessive corrosion is dissimilar metals.
expected, suitable coatings, tapes, sacrificial anodes, c Bearing Areas Bearing areas such as engine
impressed-current systems or other corrosion beds, pump foundations, propeller shafts, rudder and
prevention measures are to be used. When tapes are other appendages of metals other than aluminum are
used for corrosion protection, they are to be non- to be suitable isolated by such means as non-metallic
wicking and non-water absorbing. Grease containing bearing casing, non-conductive packing (not
graphite is not to be used with aluminum, instead, containing graphite or other conductors) or suitable
zinc or other suitable base grease is to be used. tapes and coatings. Alternative methods for
minimizing corrosion at these locations will be
3/21.6.2 Coatings specially considered. Wicking-type tapes or water-
Coatings are to be applied in accordance with the absorbing packing materials such as canvas should
manufacturer’s instructions, and are to be preceded not be used. The metals used for such applications
by appropriate cleaning and possibly chemical are to be selected to minimize galvanic effects;
conversion of surfaces as may be required in stainless steels are to be considered. The use of
accordance with the manufacturer’s copper-base alloys such as brass or bronze is
recommendations. Coatings are to be free from generally not recommended where galvanic corrosion
voids, scratches or other imperfections that are is of concern, and these materials may only be used
potential sites for localized corrosion. when specially approved. In those cases where the
The composition of coatings is to be compatible use of dissimilar metals cannot be avoided, or where
with aluminum. Coatings containing copper, lead, galvanic corrosion is of concern, such as in wet tanks,
mercury or other metals that can induce galvanic or a suitable sacrificial anode or impressed current
other forms of corrosion are not to be used. Zinc system should be installed.
chromate coatings may be used. Insulating coatings
intended to prevent galvanic corrosion are not to
contain graphite or other conducting materials.

PART 3 SECTION 21|1 Protective Coatings


3/21.6.5 Faying Surface between Aluminum and 3/21.6.10 Bi-material Joints
Non-metals Such joints, when used, may be required to be
Aluminum in contact with wood or insulating-type appropriately painted, coated, wrapped or protected
material is to be protected from the corrosive effects by other methods to prevent galvanic corrosion.
of the impurities in these materials by a suitable Where aluminum is to be joined to other materials,
coating or covering. Concrete used with aluminum is each faying surface is to be suitably coated to
to be free of additives for cold weather pouring. minimize corrosion. In addition, when one or both
Preformed glass insulation is recommended for sides of an aluminum or steel connection to dissimilar
piping insulation. Any adhesives which may be used metal joints are exposed to weather, sea water, or wet
to connect insulation to aluminum are to be free of spaces, a minimum of 0.5mm (0.02 in.) of suitable
agents that would be corrosive to aluminum. insulation is to be installed between faying surfaces
Foaming agents harmful to aluminum, such as freon, and extended beyond the edge of the joint. Non-
are not to be used for insulating foams. Areas where welded oil or water stops are to be of plastic
dirt or soot are likely to collect and remain for insulation tape or equivalent which would provide a
prolonged periods are to be protected from pitting suitably corrosion resistant system.
corrosion by the use of coatings or other suitable
means. 3/21.8 Protection of Fiber Reinforced Plastic

3/21.6.6 Corrosion of Wet Spaces 3/21.8.1 General


Suitable means are to be used to avoid arrangements Cured gel-coat resins and lay-up resin are to be highly
that could induce crevice corrosion in wet spaces. In resistant to water and other liquid absorption;
bilge spaces, chain lockers, and similar locations appropriate materials, lay-up, and lay-up procedures
where exfoliation corrosion may be of concern, are to be used and manufacturer’s recommendations
appropriate materials suitably heat treated for followed to attain this. Care is to be taken in the use
resistance to this form of corrosion are to be of laminates containing carbon fibers so that they are
employed. not close to or do not induce galvanic corrosion with
metal fittings.
3/21.6.7 Service at Elevated Temperatures
For service temperatures of 66°C (150°F) or above, 3/21.8.2 Tanks
only aluminum alloys and filler metals specially In water, fuel oil, or other approved tanks, the resins
designated for service at these temperatures are to be used are to be compatible with the contents of the
used. tanks; the contents of the tanks are not to affect the
cured properties of the tank laminate. The cured
3/21.6.8 Cathodic Protection for Corrosion laminate is to be highly resistant to absorption of the
Prevention liquid, and is not to have harmful, deleterious, or
For application where corrosion is of concern, undesirable effects on the contents of the tank. The
consideration is to be given to the use of sacrificial tank is generally to be gel-coated on the inside. See
anode or impressed current systems of corrosion also 3/12.3.1.
control. Details of sacrificial anodes and
arrangements are to be submitted for review. Anodes 3/21.8.3 Cathodic Protection
are to be in accordance with ASTM or other Cathodic protection is to be provided where shaft
recognized standard. When impressed current struts, propeller shafts, propellers, rudders, fittings,
systems are used, adequate precautions are to be etc. are constructed of manganese bronze, brass,
taken that the negative voltage is not excessive. stainless steel or mild steel. Details of the sacrificial
anodes and arrangements are to be submitted for
3/21.6.9 Stray Current Protection review. Anodes are to be in accordance with ASTM
Precautions are to be taken when in dock to prevent or other recognized standard.
stray currents from welding power or other sources
from adversely affecting the aluminum. Whenever
possible, the cathodic protection system of the craft
should be in place and operating when the craft is in
the water. A.C. power sources are to be insulated
from the hull. For battery and other D.C. power
sources, grounding is to be avoided if possible.
Where safety considerations require grounding to the
hull, the negative pole is to be connected to the hull.

PART 3 SECTION 21|2 Protective Coatings


PART 3 SECTION 22

Equipment
3/22.1 General load waterline which are within L (see 3/1.1).
Superstructures or deckhouses having a
All craft are to have a complete equipment of anchors breadth at any point no greater than 0.25B
and chains. The letter placed after the symbols of may be excluded. Screens and bulwarks more
classification in the Record, thus: !A1 , will than 1.5 m (4.9 ft) in height are to be regarded
signify that the equipment of the craft is in as parts of houses when calculating h and A.
compliance with the requirements of the Guide, or b Craft of Unrestricted Ocean Service Having
with requirements corresponding with the service EN of 205 and Above For craft of unrestricted ocean
limitation noted in the craft’s classification, which service having an EN of 205 or above in accordance
have been specially approved for the particular with 3/22.3.1, the calculated EN is to be used in
service. association with Table 3/22.1.
Cables which are intended to form part of the c Craft having EN less than 205 For craft of
equipment are not to be used as deck chains when the unrestricted ocean service having a basic EN less than
craft is launched. The inboard ends of the cables of 205 calculated in accordance with 3/22.3.1a, the EN
the bower anchors are to be secured by efficient for use with Table 3/22.1 may be calculated in
means. Anchors and their cables are to be connected accordance with the following equation.
and positioned, ready for use. Where three anchors
are given in Table 3/22.1, the third anchor is intended
Equipment Number = k∆
23
( )
+ m Ba + ∑ bh + nA
as a spare bower anchor and is listed for guidance Where k, m, n, ∆, B, a and A are as defined in
only; it is not required as a condition of classification. 3/22.3.1a above and;
Means are to be provided for stopping each cable as it b = breadth in m or ft of the widest superstructure
is paid out, and the windlass should be capable of or deckhouse on each tier.
heaving in either cable. Suitable arrangements are to h = the height in m or ft of each tier of deckhouse
be provided for securing the anchors and stowing the or superstructure having a width of B/4 or
cables. greater. In the calculation of h, sheer, camber
and trim may be neglected. See Figure 3/22.1.
3/22.3 Calculation of EN
3/22.3.2 Multi-Hulled Craft
3/22.3.1 Monohulls Anchors and chains are to be not less than given in
a Basic Equation The basic Equipment Number Table 3/22.1 and the numbers, weights and sizes of
(EN) is to be obtained from the following equation these are to be based on the equipment number
for use in determining required equipment. obtained from the following equation. Special
23 consideration will be given where anchoring and
EN = k∆ + mBh + nA
mooring conditions are specified.
k
m
=
=
1.0 (1.0, 1.012)
2 (2, 0.186) (
EN = k∆2 / 3 + m [2 Ba ] + B1 a1 + [ ∑ h]) + nA
n = 0.1 (0.1, 0.00929)
∆ = molded displacement in metric tons (long k, ∆, m, n and A are as defined in 3/22.3.1. B, B1, a,
tons) at the summer load waterline. a1, h1, h2, h3, Σh are shown in Figure 3/22.1b
B = molded breadth as defined in 3/1.3 in m or ft
h = a + h1 + h2 + h3 + . . . as shown in Figure
3/22.1. In the calculation of h, sheer, camber
and trim may be neglected.
a = freeboard, in m (ft), from the summer load
waterline amidships.
h1, h2, h3...= height in m (ft), on the centerline of
each tier of houses having a breadth greater
than B/4.
A = profile area in m2 (ft2) of the hull,
superstructure and houses above the summer

PART 3 SECTION 22|1 Equipment


FIGURE 3/22.1 - Effective Heights of Deckhouses
a Monohulls

b Multi-Hulled Craft

PART 3 SECTION 22|2 Equipment


3/22.5 Craft of Unrestricted Service 3/22.13 Windlass or Winch

The equipment, weight and size of all craft in 3/22.13.1 General


unrestricted service is to be in accordance with Table The windlass is to be of good and substantial make
3/22.1 in association with the EN calculated in 3/22.3 suitable for the size of intended anchor cable. The
winch is to be well bolted down to a substantial bed,
3/22.7 Restricted Service Craft and deck beams below the windlass are to be of extra
Craft intended for restricted service (see 1/1.3.4) and strength and additionally supported. Where wire
having their own moorage are to have one anchor of ropes are used in lieu of chain cables, winches
the tabular weight and one-half the tabulated length of capable of controlling the wire rope at all times are to
anchor chain in Table 3/22.1. Alternatively, two be fitted.
anchors of one-half the tabular weight with the total Construction and installation of all windlasses and
length of anchor chain listed in Table 3/22.1 may be winches used for anchoring are to be carried out in
fitted provided both anchors are positioned and ready accordance with the following requirements, to the
for use and the windlass is capable of heaving in satisfaction of the Surveyor. In general, the design is
either anchor. These craft are to have adequate to conform to an applicable standard or code of
towing arrangements so that the craft can be towed in practice. As a minimum, standards or practices are to
the worst intended conditions. In the areas of the indicate strength, performance and testing criteria.
towing arrangements where the towing cable is The manufacturer or builder is to submit in
susceptible to chafing there is to be sufficient radius accordance with 4/1.11, the following, as applicable:
to prevent the cable from being damaged when under a Plans
load. 1 Arrangement and details of the windlass or
winch, drums, brakes, shaft, gears,
3/22.9 Materials and Tests coupling bolts, wildcat, sheaves, pulleys
and foundation.
Material and testing for anchors and chains on craft 2 Electric one line diagram.
are to be in accordance with the requirements of 2/1 3 Piping system diagrams.
for the respective sizes of anchors and chains. See 4 Control arrangements.
2/1.11 through 2/1.13. Materials and tests for wire
rope are to be in accordance with a national or other Plans or data are to show complete details including
recognized standard. power ratings, working pressures, welding details,
material specifications, pipe and electric cable
3/22.11 Anchor Types specifications, etc.
b Calculations Detailed stress calculations for
3/22.11.1 General the applicable system components listed in a1 above.
Anchors are in general to be of the stockless type. The calculations are to be based on the breaking
The weight of the head of a stockless anchor, strength of the chain or wire rope; are to indicate
including pins and fittings, is not to be less than three- maximum torque or load to which the unit will be
fifths of the total weight of the anchor. subjected and also show compliance with either
applicable sections of the Rules such as 4/3.29 of the
3/22.11.2 High Holding Power Anchors (HHP) Rules for Building and Classing Steel Vessels for the
Where the anchor has a proven holding power of not gears and shafts, or to other recognized standard or
less than two times that of an ordinary stockless code of practice.
anchor and has been tested in accordance with 2/1.11
a weight reduction of 25% from the weight specified 3/22.13.2 Support Structure
in Table 3/22.1 will be given. For HHP anchors an The windlass or winch is to be well bolted down to a
appropriate notation will be made in the Record. substantial foundation. The stresses in the structures
supporting the windlass are not to be exceed the yield
3/22.11.3 Super High Holding Power Anchors point of the material under the following load applied
(SHHP) in the direction of the chain:
Where the anchor has a proven holding power of not
less than four times that of an ordinary stockless With cable stopper: 45% of B.S.
anchor and has been tested in accordance with 2/1.11 Without cable stopper: 80% of B.S.
a weight reduction of 50% from the weight specified
in Table 3/22.1 will be given. For SHHP anchors an B.S. = minimum breaking strength of the chain as
appropriate notation will be made in the Record. indicated in Tables 2/1.9 and 2/1.10.

PART 3 SECTION 22|3 Equipment


An independent cable stopper and its components are
to be adequate for the load imposed. The
arrangements and details of the cable stopper are to
be submitted for review.

3/22.15 Trial

See 1/2.3

3/22.17 Hawse Pipes

Hawse pipes are to be of ample size and strength;


they are to have full rounded flanges and the least
possible lead, in order to minimize the nip on the
cables; they are to be securely attached to thick
doubling or insert plates by continuous welds the size
of which are to be in accordance with Section 3/23
for the plating thickness and type of joint selected.
When in position they are to be thoroughly tested for
watertightness by means of a hose in which the water
pressure is not to be less than 2.06 bar (2.1 kgf/cm2,
30 psi). Hawse pipes for stockless anchors are to
provide ample clearances; the anchors are to be
shipped and unshipped so that the Surveyor may be
satisfied that there is no risk of the anchor jamming in
the hawse pipe. Care is to be taken to ensure a fair
lead for the chain from the windlass to the hawse
pipes and to the chain pipes.

PART 3 SECTION 22|4 Equipment


TABLE 3/22.1
Equipment for Self-propelled Ocean-going Craft
SI, Metric Units

The weight per anchor of bower anchors given in Table 3/22.1 is for anchors of equal weight. The weight of
individual anchors may vary 7% plus or minus from the tabular weight provided that the combined weight of all
anchors is not less than that required for anchors of equal weight. The total length of chain required to be carried on
board, as given in Table 3/22.1, is to be reasonably divided between the two bower anchors. Where three anchors
are given in Table 3/22.1, the third anchor is intended as a spare bower anchor and is listed for guidance only; it is
not required as a condition of classification.

Stockless Bower Chain Cable Stud Link Bower Chain


Anchors
Diameter
Equipment Equipment Number Mass per Length, m Normal-Strength High-Strength Extra High-
Numeral Number* Anchor, Steel (Grade 1), Steel (Grade 2), Strength Steel
kg mm mm (Grade 3), mm
UA1 30 2 75 192.5 12.5 - -
UA2 40 2 100 192.5 12.5 - -
UA3 50 2 120 192.5 12.5 - -
UA4 60 2 140 192.5 12.5 - -
UA5 70 2 160 220 14 12.5 -

UA6 80 2 180 220 14 12.5 -


UA7 90 2 210 220 16 14 -
UA8 100 2 240 220 16 14 -
UA9 110 2 270 247.5 17.5 16 -
UA10 120 2 300 247.5 17.5 16 -

UA11 130 2 340 275 19 16 -


UA12 140 2 390 275 20.5 17.5 -
U6 150 2 480 275 22 19 -
U7 175 2 570 302.5 24 20.5 -
U8 205 3 660 302.5 26 22 20.5
U9 240 3 780 330 28 24 22
U10 280 3 900 357.5 30 26 24

U11 320 3 1020 357.5 32 28 24


U12 360 3 1140 385 34 30 26
U13 400 3 1290 385 36 32 28
U14 450 3 1440 412.5 38 34 30
U15 500 3 1590 412.5 40 34 30

U16 550 3 1740 440 42 36 32


U17 600 3 1920 440 44 38 34
U18 660 3 2100 440 46 40 36
U19 720 3 2280 467.5 48 42 36
U20 780 3 2460 467.5 50 44 38

U21 840 3 2640 467.5 52 46 40


U22 910 3 2850 495 54 48 42
U23 980 3 3060 495 56 50 44
U24 1060 3 3300 495 58 50 46
U25 1140 3 3540 522.5 60 52 46

U26 1220 3 3780 522.5 62 54 48


U27 1300 3 4050 522.5 64 56 50
U28 1390 3 4320 550 66 58 50
U29 1480 3 4590 550 68 60 52
U30 1570 3 4890 550 70 62 54

PART 3 SECTION 22|5 Equipment


TABLE 3/22.1 (Continued)
SI, Metric Units

Stockless Bower Chain Cable Stud Link Bower Chain**


Anchors
Diameter
Equipment Equipment Number Mass per Length, m Normal-Strength High-Strength Extra High-
Numeral Number* Anchor, Steel (Grade 1), Steel (Grade 2), Strength Steel
kg mm mm (Grade 3), mm
U31 1670 3 5250 577.5 73 64 56
U32 1790 3 5610 577.5 76 66 58
U33 1930 3 6000 577.5 78 68 60
U34 2080 3 6450 605 81 70 62
U35 2230 3 6900 605 84 73 64

U36 2380 3 7350 605 87 76 66


U37 2530 3 7800 632.5 90 78 68
U38 2700 3 8300 632.5 92 8.1 70
U39 2870 3 8700 632.5 95 84 73
U40 3040 3 9300 660 97 84 76

U41 3210 3 9900 660 100 87 78


U42 3400 3 10500 660 102 90 78
U43 3600 3 11100 687.5 105 92 81
U44 3800 3 11700 687.5 107 95 84
U45 4000 3 12300 687.5 111 97 87

U46 4200 3 12900 715 114 100 87


U47 4400 3 13500 715 117 102 90
U48 4600 3 14100 715 120 105 92
U49 4800 3 14700 742.5 122 107 95
U50 5000 3 15400 742.5 124 111 97

U51 5200 3 16100 742.5 127 111 97


U52 5500 3 16900 742.5 130 114 100
U53 5800 3 17800 742.5 132 117 102
U54 6100 3 18800 742.5 120 107
U55 6500 3 20000 770 124 111

U56 6900 3 21500 770 127 114


U57 7400 3 23000 770 132 117
U58 7900 3 24500 770 137 122
U59 8400 3 26000 770 142 127
U60 8900 3 27500 770 147 132
U61 9400 3 29000 770 152 132

U62 10000 3 31000 770 137


U63 10700 3 33000 770 142
U64 11500 3 35500 770 147
U65 12400 3 38500 770 152
U66 13400 3 42000 770 157
U67 14600 3 46000 770 162
* For intermediate values of equipment number use equipment complement in sizes and weights given for the lower equipment number in the
table.
** Wire ropes may be used in lieu of chain cables for both anchors on craft having an Equipment Number less than 150.
The wire is to have a breaking strength not less than the grade 1 chain of required size and a length of at least 1.5 times the chain it is
replacing.
Between the wire rope and anchor, chain cable of the required size having a length of 12.5 m (41.0 ft), or the distance between anchor
in stored position and winch, whichever is less, is to be fitted.
For craft having a very small Equipment Number, nylon rope may be specially considered.

PART 3 SECTION 22|6 Equipment


TABLE 3/22.1
Equipment for Self-propelled Ocean-going Craft
US Units

The weight per anchor of bower anchors given in Table 3/22.1 is for anchors of equal weight. The weight of
individual anchors may vary 7% plus or minus from the tabular weight provided that the combined weight of all
anchors is not less than that required for anchors of equal weight. The total length of chain required to be carried on
board, as given in Table 3/22.1, is to be reasonably divided between the two bower anchors. Where three anchors
are given in Table 3/22.1, the third anchor is intended as a spare bower anchor and is listed for guidance only; it is
not required as a condition of classification.

Stockless Bower Chain Cable Stud Link Bower Chain**


Anchors
Diameter
Equipment Equipment Number Mass Length, fathoms Normal-Strength High-Strength Extra High-
Numeral Number* per Steel (Grade 1), Steel (Grade 2), Strength Steel
Anchor, inches inches (Grade 3),
pounds inches

UA1 30 2 165 105 1/2 - -


UA2 40 2 220 105 1/2 - -
UA3 50 2 265 105 1/2 - -
UA4 60 2 310 105 1/2 - -
UA5 70 2 350 120 9/16 1/2 -

UA6 80 2 400 120 9/16 1/2 -


UA7 90 2 460 120 5/8 9/16 -
UA8 100 2 530 120 5/8 9/16 -
UA9 110 2 595 135 11/16 5/8 -
UA10 120 2 670 135 11/16 5/8 -

UA11 130 2 750 150 3/4 11/16 -


UA12 140 2 860 150 13/16 11/16 -
U6 150 2 1060 150 7/8 3/4 -
U7 175 2 1255 165 15/16 13/16 -
U8 205 3 1455 165 1 7/8 13/16
U9 240 3 1720 180 1 1/8 15/16 7/8
U10 280 3 1985 195 1 3/16 1 15/16

U11 320 3 2250 195 1 1/4 1 1/8 15/16


U12 360 3 2510 210 1 5/16 1 3/16 1
U13 400 3 2840 210 1 7/16 1 1/4 1 1/8
U14 450 3 3170 225 1 1/2 1 5/16 1 3/16
U15 500 3 3500 225 1 9/16 1 5/16 1 3/16

U16 550 3 3830 240 1 5/8 1 7/16 1 1/4


U17 600 3 4230 240 1 3/4 1 1/2 1 5/16
U18 660 3 4630 240 1 13/16 1 9/16 1 7/16
U19 720 3 5020 255 1 7/8 1 5/8 1 7/16
U20 780 3 5420 255 2 1 3/4 1 1/2

U21 840 3 5820 255 2 1/16 1 13/16 1 9/16


U22 910 3 6280 270 2 1/8 1 7/8 1 5/8
U23 980 3 6740 270 2 3/16 1 15/16 1 3/4
U24 1060 3 7270 270 2 5/16 2 1 13/16
U25 1140 3 7800 285 2 3/8 2 1/16 1 13/16

U26 1220 3 8330 285 2 7/16 2 1/8 1 7/8


U27 1300 3 8930 285 2 1/2 2 3/16 2
U28 1390 3 9520 300 2 5/8 2 5/16 2
U29 1480 3 10120 300 2 11/16 2 3/8 2 1/16
U30 1570 3 10800 300 2 3/4 2 7/16 2 1/8

PART 3 SECTION 22|7 Equipment


TABLE 3/22.1 (Continued)
US Units

Stockless Bower Chain Cable Stud Link Bower Chain


Anchors
Diameter
Equipment Equipment Number Mass Length, fathoms Normal-Strength High-Strength Extra High-
Numeral Number* per Steel (Grade 1), Steel (Grade 2), Strength Steel
Anchor, inches inches (Grade 3),
pounds inches

U31 1670 3 11600 315 2 7/8 2 1/2 2 3/16


U32 1790 3 12400 315 3 2 5/8 2 5/16
U33 1930 3 13200 315 3 1/16 2 11/16 2 3/8
U34 2080 3 14200 330 3 3/16 2 3/4 2 7/16
U35 2230 3 15200 330 3 5/16 2 7/8 2 1/2

U36 2380 3 16200 330 3 7/16 3 2 5/8


U37 2530 3 17200 345 3 9/16 3 1/16 2 11/16
U38 2700 3 18300 345 3 5/8 3 3/16 2 3/4
U39 2870 3 19200 345 3 3/4 3 5/16 2 7/8
U40 3040 3 70500 360 3 7/8 3 5/16 3

U41 3210 3 21800 360 3 15/16 3 7/16 3 1/16


U42 3400 3 23100 360 4 3 9/16 3 1/16
U43 3600 3 24500 375 4 1/8 3 5/8 3 3/16
U44 3800 3 25800 375 4 1/4 3 3/4 3 5/16
U45 4000 3 27100 375 4 3/8 3 7/8 3 7/16

U46 4200 3 28400 390 4 1/2 3 15/16 3 7/16


U47 4400 3 29800 390 4 5/8 4 3 9/16
U48 4600 3 31100 390 4 3/4 4 1/8 3 5/8
U49 4800 3 32400 405 4 3/4 4 1/4 3 3/4
U50 5000 3 33900 405 4 7/8 4 3/8 3 7/8

U51 5200 3 35500 405 5 4 3/8 3 7/8


U52 5500 3 37200 405 5 1/8 4 1/2 3 15/16
U53 5800 3 39200 405 5 1/8 4 5/8 4
U54 6100 3 41400 405 4 3/4 4 1/4
U55 6500 3 44000 420 4 7/8 4 3/8

U56 6900 3 47400 420 5 4 1/2


U57 7400 3 50700 420 5 1/8 4 5/8
U58 7900 3 54000 420 5 3/8 4 3/4
U59 8400 3 57300 420 5 5/8 5
U60 8900 3 60600 420 5 3/4 5 1/8
U61 9400 3 63900 420 6 5 1/8

U62 10000 3 68000 420 5 3/8


U63 10700 3 72500 420 5 5/8
U64 11500 3 78000 420 5 3/4
U65 12400 3 85000 420 6
U66 13400 3 92500 420 6 1/8
U67 14600 3 101500 420 6 3/8
* For intermediate values of equipment number use equipment complement in sizes and weights given for the lower equipment number in the
table.
** Wire ropes may be used in lieu of chain cables for both anchors on craft having an Equipment Number less than 150.
The wire is to have a breaking strength not less than the grade 1 chain of required size and a length of at least 1.5 times the chain it is
replacing.
Between the wire rope and anchor, chain cable of the required size having a length of 12.5 m (41.0 ft), or the distance between anchor
in stored position and winch, whichever is less, is to be fitted.
For craft having very small Equipment Numbers, nylon rope may be specially considered.

PART 3 SECTION 22|8 Equipment


PART 3 SECTION 23

Welding, Forming, and Weld Design


3/23.1 Fillet Welds leg length or 0.7tp + 2.0mm (0.7tp + 0.08 in.)
whichever is less.
3/23.1.1 General Where it is intended to use continuous fillet
Fillet welds may be made by an approved manual, welding, the leg size of fillet welds is to be obtained
semi automatic or automatic process. The sizes of from the above equations taking s/l equal to 1.
fillet welds are subject to approval in each case, and For intermittent welding with plate thickness less
are to be indicated on detail drawings or on a separate than 7 mm (0.28 in.) welds are to be staggered.
welding schedule. When terminating an aluminum
weld, either continuous or intermittent, crater filling 3/23.1.4 Fillet Weld Arrangements
by back stepping is recommended to provide a sound a Intersections Where beams, stiffeners, frames,
ending for each fillet. etc, are intermittently welded and pass through slotted
girders, shelves or stringers, there is to be a pair of
3/23.1.2 Tee Connections matched 75mm (3 in.) intermittent welds on each side
In general, the required size and spacing of the fillets of each such intersection and the beams, stiffeners
is to be as given in 3/23.1.3. Special consideration and frames are to be efficiently attached to the
will be given where there is a substantial difference girders, shelves and stringers.
between the thickness of members being connected. b Unbracketed End Attachments Unbracketed
Where the opening between members exceeds 1.0 beams, frames, etc. and stiffeners of watertight and
mm (0.04 in.) and is not greater than 5mm (0.1875 tank bulkheads and superstructure and house fronts
in.), the size of the fillets is to be increased by the are to have double continuous welds for length at
amount of the opening. Spacing between plates each end equal to the depth of the member but not
forming tee joints is not to exceed 5 mm (0.1875 in.). less than 75mm (3 in.).
c Bracketed End Attachments Frames, beams,
3/23.1.3 Fillet Sizes and Spacing stiffeners etc. are to be lapped onto the bracket a
Tee connections are to be formed by continuous or length not less than 1.5 times the depth of the
intermittent fillet welds on each side, the leg size, w, member, and are to have continuous fillet welds all
of the fillet welds is to be obtained from the following around. Lapped end connections of longitudinal
equations: strength members are also to have a throat size, t,
such that the total effective area of the lap welding is
s
w = tp × C × + 15
. mm not less than the area of the member being attached.
l d Lapped Joints Lapped joints are generally to
have a width of overlap not less than twice the
s
w = tp × C × + 0.06 in thickness of thinner plate plus 25 mm (1 in.) with
l welds on both edges of the sizes required by 3/23.1.3.
e Plug Welds or Slot Welds Plug welds or slot
w = the size of the weld leg in mm or in. welds are to be specially approved for particular
l = the actual length of the weld fillet, clear of applications. When approved, an appropriate
crater, in mm or in. See Figure 3/23.1. demonstration that adequate weld penetration and
s = the distance between centers of weld fillets, soundness is achieved is to be made to the Surveyor’s
in mm or in. See Figure 3/23.1. satisfaction. When used in the attachment of doublers
tp = thickness of the thinner of the two members and similar applications, plug or slot welds may be
being joined in mm or in. spaced at 16 times the doubler thickness, but not
C = weld factor given in Table 3/23.1. more than 300 mm (12 in.) between centers in both
directions. In general, elongated slot welds are
w is not to be taken less than 0.3tp or 3.5 mm recommended. For closing plates on rudders, slots
(0.14in.), whichever is greater. are to be 75mm (3 in.) in length spaced at 150 mm (6
The throat thickness of the fillet is to be not less in.) between centers. The periphery of the plugs or
than 0.7w. slots are to be fillet welded, of fillet size, w, generally
In calculating weld factors, the leg length of not less than 0.70 times the plate thickness. Plugs
matched fillet weld is to be taken as the designated and slots are not to be filled with welded deposit.

PART 3 SECTION 23|1 Welding, Forming and Weld Design


3/23.3 Bi-material Joints
Techniques required for joining two different
materials will be subject to special consideration.
The use of explosion bonding may be considered
depending on the application and the mechanical and
corrosive properties of the joint.

3/23.7 Alternatives
The foregoing are considered minimum requirements
for welding in hull construction, but alternative
methods, arrangements and details will be considered
for approval.

FIGURE 3/23.1

PART 3 SECTION 23|2 Welding, Forming and Weld Design


TABLE 3/23.1
Weld Factor C
Aluminum Steel
Floors, Bottom Transverses, and Bottom Girders to Shell
At Bottom forward 3L/8, V> 25 knots 0.25 0.25
At Bottom forward L/4, V<= 25 knots 0.18 0.16
In way of propellers and shaft struts 0.25 0.25 DC
In machinery space 0.20 0.20
Elsewhere 0.16 0.14
Floors, Bottom Transverses and Bottom Girders to Inner Bottom or Face Bar
In machinery space 0.25 DC 0.25 DC
To Inner bottom elsewhere 0.14 0.12
To face plate elsewhere 0.14 0.12
Floors and Bottom Transverse to Bottom Girders 0.30 DC 0.30 DC
Bottom Girders to Bulkheads and Deep Transverses or Floors 0.30 DC 0.30 DC
End Attachments - single bottom construction 0.50 DC 0.50 DC
Frames to Shell
At Bottom forward 3L/8, V>25 knots 0.25 DC 0.25 DC
At Bottom forward L/4, V<=25 knots 0.18 0.16
In way of propellers and shaft struts 0.25 DC 0.25 DC
Elsewhere 0.14 0.12
End Attachments 0.50 DC 0.50 DC
Girders, Transverses and Stringers
To Shell (transverse) 0.16 0.14
To Deck and Bulkheads Clear of Tanks 0.16 0.14
To Deck and Bulkheads In way of Tanks 0.18 0.16
To Face Bar 0.14 0.12
End Attachments 0.50 DC 0.50 DC
Beams and Stiffeners
To Deck 0.14 0.12
To Tank Boundaries and House Fronts 0.14 0.12
To Watertight Bulkheads, House Side and Ends 0.14 0.12
End Attachments 0.50 DC 0.50 DC
Engine Foundations to Plating and Face Bar 0.50 DC 0.50 DC
Bulkheads and Tank Boundaries
Non-Tight, Internal 0.16 0.14
Weathertight, or exposed 0.38 DC 0.38 DC
Tank 0.40 DC 0.40 DC
Decks
Non-tight, Internal 0.25 0.25
Weathertight 0.38 DC1 0.38 DC1
Strength Deck 0.38 DC1 0.38 DC1
Rudders
Diaphragms to Side Plating 0.30 0.30
Vertical Diaphragms to Horizontal Diaphragms, clear of Mainpiece 0.50 DC 0.50 DC
Horizontal Diaphragm to Vertical 0.50DC 0.50 DC
Mainpiece Diaphragm 0.50 DC 0.50DC
Shaft Brackets to boss and doubler Full Penetration Full Penetration
Notes: DC = double continuous
1 = Where plate thickness is less than 12.5mm (0.50 in.), upper weld to be continuous, lower weld may
be intermittent as required by welding beams or stiffeners to tank boundaries.

PART 3 SECTION 23|3 Welding, Forming and Weld Design


PART 3 SECTION 24

Fire Safety
3/24.1 General craft is in accordance with the applicable criteria in
1974 SOLAS as amended.
3/24.1.1 SOLAS Application Where the Administration undertakes any part of
For classification purposes, the fire and safety the review and the Bureau is issuing above
measures contained in the International Convention Certificate, the acceptance by the Administration will
for the Safety of Life at Sea, 1974 (1974 SOLAS) as be required before the certificate is issued.
amended, are applicable to crafts of type, size and Compliance with the Rule requirements in
service coming under that Convention. This includes addition to those in 1974 SOLAS as amended is to be
the IMO International Code of Safety for High Speed verified by the Bureau.
Craft (HSC Code).
This section does not relax the requirements in 3/24.7.2 Bureau Review
other sections of the Rules. In all other cases, the required information and plans
Gross tonnage is to be taken as defined in 3/1.19. are to be submitted to the Bureau for review.

3/24.1.2 Regulation 3/24.9 The Review of Craft Constructed of Fiber


Regulation means the regulation contained in 1974 Reinforced Plastic (FRP)
SOLAS as amended. An abbreviated notation is FRP fire-restricting divisions may be considered
used, e.g. Regulation II-2/4.2 means Regulation 4.2 provided they meet the required tests for fire-
of Chapter II-2. restricting materials and fire-resisting divisions, or
comply with an acceptable fire risk assessment. FRP
3/24.3 Passenger Craft divisions may also be considered on the basis of
For passenger craft as defined in 1.1 through 1.4 of location with regard to diminished fire risk and
the HSC Code, the requirements in 7.1 through7.6 enhanced fire detection/extinguishing means.
HSC Code are applicable. See also Section 5/1 of
this Guide.
For all passenger craft subject to 1974 SOLAS as
amended, the requirements in Part B (Regulations 23
through 41) Chapter II-2 are applicable. See also
Section 5/5 of the Rules for Building and Classing
Steel Vessels.

3/24.5 Cargo Craft


For cargo craft as defined in 1.1 through 1.4 of the
HSC Code, the requirements in 7.1 through 7.6 HSC
Code are applicable.
For all cargo craft subject to 1974 SOLAS as
amended, the requirements in Part C (Regulations 42
through 54) Chapter II-2 are applicable.

3/24.7 Review Procedures

3/24.7.1 Administration Review


When the craft is issued a Passenger Ship Safety
Certificate, Cargo Ship Safety Equipment Certificate,
Cargo Ship Safety Construction Certificate, or High
Speed Craft Safety Construction Certificate by the
flag Administration or its agent other than the Bureau,
such Certificate will be accepted as evidence that the

PART 3 SECTION 24|1 Fire Safety Measures


PART 3 APPENDIX 3/A

Guidelines in Calculating Bending Moment


and Shear Force in Rudders and Rudder
Stocks
Bending moments, shear forces and reaction forces of rudders, stocks and bearings may be calculated according to
this Appendix for the types of rudders indicated. Moments and forces on rudders of different types or shapes than
those shown are to be calculated using alternative methods and will be specially considered.

3/A.1 Spade Rudders 3/A.1.2 Lower Stock


a Shear Force Lateral shear force at any section
3/A.1.1 Rudder of the lower stock between the top of the rudder and
a Shear Force Lateral shear force at a horizontal the neck bearing is given by the following equation.
section of the rudder z meters (feet) above the bottom
of lR is given by the following equation. Vl = C R kN (tf, Ltf)
Vl = transverse shear force in the lower stock.
CR = rudder force as defined in 3/A.1.1a
zC R  z 
V ( z) = cl + (cu − cl )  kN (tf, Ltf)
A  2l R  b Bending Moment at Neck Bearing The
bending moment in the rudder stock at the neck
V(z) = lateral shear force at the section of the bearing is given by the following equation.
rudder under consideration.
z = distance from the bottom of lR to the
 l ( 2 c + cu ) 
horizontal section under consideration in m M n = C R l l + R 1  kN-m (tf-m, Ltf-ft)
(ft)  3(cl + cu ) 
CR = rudder force as defined in 3/5.2.1 in kN (tf,
Ltf)
A = rudder blade area in m2 (ft2) Mn = bending moment at the neck bearing of the
cl, cu, and lR are dimensions as indicated in Figure rudder stock.
3/A.1 in m (ft). CR = rudder force as defined in 3/A.1.1a
cl, cu, ll and lR are dimensions as indicated in Figure
b Bending moment Bending at a horizontal 3/A.1 in m (ft).
section z meters (feet) above the baseline of the
rudder is given by the following equation. 3/A.1.3 Moment at Top of Upper Stock Taper
The bending moment in the upper rudder stock at the
top of the taper is given by the following equation.
z 2 CR  z 
M ( z) = cl + (cu − cl )  kN-m (tf-m,
2A  3l R   l ( 2 c + cu )   l u + l R + l l − z t 
Ltf-ft) M t = C R l l + R l × 
 3(cl + cu )   lu 
M(z) = bending moment at the horizontal section of kN-m (tf-m, Ltf-f)
the rudder under consideration.

z, CR, A, cl, cu and lR are as defined in 3/A.1.1a. Mt = bending moment at the top of the upper
rudder stock taper.
zt = distance from the rudder baseline to the top
of the upper rudder stock taper in m (ft)
CR = rudder force as defined in 3/A.1.1a

PART 3 APPENDIX 3/A|1 Guidelines in Calculating Bending Moment and Shear Force in Rudders and
Rudder Stocks
cl, cu, ll, lu and lR are dimensions as indicated in FIGURE 3/A.1
Figure 3/A.1 in m (ft). Spade Rudder

3/A.1.4 Bearing Reaction Forces


Reaction forces at the bearings are given by the
following equations.
Mn
Pu = − kN (tf, Ltf)
lu

Mn
Pn = C R + kN (tf, Ltf)
lu
Pu = reaction force at the upper bearing.
Pn = reaction force at the neck bearing.
Mn = bending moment at the neck bearing as
defined in 3/A.1.1b
CR = rudder force as defined in 3/A.1.1a
lu is as indicated in Figure 3/A.1 in m (ft).

PART 3 APPENDIX 3/A|2 Guidelines in Calculating Bending Moment and Shear Force in Rudders and
Rudder Stocks
PART 3 APPENDIX 3/B

Guidance on Torsional Analysis of the


Cross Deck Structure of a Multi-Hull Craft
This appendix gives guidance on the torsional analysis of a standard cross deck structure (constructed of aluminum
or steel similar to Figure 3/B.1) of a multi-hulled craft. The torsional analysis includes the determination of the
craft’s torsional moment of inertia and section modulus, and the maximum stress that is acting on each element. The
torsional analysis of cross decks that are of advanced design or material other than steel or aluminum will be
specially considered.

FIGURE 3/B.1
Typical Geometry of Centerline Section of Cross Deck

3/B.1 Torsional Moment of Inertia n

∑k x i i
The offered torsional moment of inertia of the cross i =1
Lc = center of torsional rotation, n
,
deck structure can be determined by the following
formula: ∑k i
i =1
n n in cm or in.
J t = (− ∑ k i × L2c ) + (∑ k i x i2 ) E = modulus of elasticity of the material, kN/m2
i =1 i =1 or psi.
Ii = moment of inertia of the element being
Jt = torsional moment of inertia. considered.
12 EI i Li = span of cross structure, in cm or in., see
ki = element stiffness, Figure 3/B.2
L3i
xi = longitudinal distance from forward
perpendicular in cm or in.
n = total number of elements in the cross deck
structure.

PART 3 APPENDIX 3/B|1 Guidance on Torsional Analysis of the Cross Deck Structure of a Multi-Hull Craft
FIGURE 3/B.2
Span of Cross Structure

3/B.2 Torsional Section Modulus


3/B.3.2 Bending Moment
The offered torsional section modulus of the cross The bending moment that is acting on each element is
structure is determined by the lesser of the following determined by the following formula:
equations:

Jt Jt Pi Li
Zt = Zt = BM i =
y (d cs − y ) 2
Zt = torsion section modulus in cm3 or in3 BMi = bending moment that is acting on the
ÿ = neutral axis of the cross deck structure. element under consideration in kN-cm, or in-
dcs = depth of cross deck, see figure 3/B.1 lbs.
Pi = δiki , force that is acting on the element in
3/B.3 Maximum Stress on Each Element kN or lbs.
Li = as defined in 3/B.1
3/B.3.1 Deflection δi = as defined in 3/B.3.1
The total amount that each element deflects can be ki = as defined in 3/B.10
determined by the following formula:

M tt x c2i 3/B.3.3 Maximum Stress


δi = n The maximum stress that is applied on each element
∑x 2
ci ki can be determined by the following formula:
i =1
BM i
δi = deflection of each member in cm or in. σi =
SM i
Mtt = design torsional moment acting upon the
transverse structure connecting the hulls as σi = maximum stress that is acting upon the
determined 3/6.13.2 in kN-m or ft-lbs. element in kN/m2 or psi.
xci = xi - Lc in cm or in. BMi = bending moment as defined in 3/B.3.2
xi, Lc, and ki are as defined in 3/B.1 SMi = section modulus of the element being
considered in cm3 or in3

PART 3 APPENDIX 3/B|2 Guidance on Torsional Analysis of the Cross Deck Structure of a Multi-Hull Craft
PART 3 APPENDIX 3/C

Guidance on First Ply Failure Analysis on


FRP Sandwich Panels
This appendix gives guidance on determining the offered section modulus of the inner and outer skins of an FRP
sandwich laminate using first-ply failure analysis. First-ply failure analysis is done by determining the critical strain
in which the first ply of the laminate will fail.

3/C.1 Offered Section Modulus of the Inner and FMi = portion of the total failure moment that each
Outer Skins of an FRP Laminate ply is to carry in kN-cm or in-lbs.
εmin = the smallest critical strain that is acting on an
3/C.1.1 Critical Strain individual ply.
The critical strain of each ply can be determined by
the following equation: 3/C.1.3 Offered Section Modulus
The offered section modulus of the inner and outer
σ ai
ε criti = skins of the laminate can be determined by the
[
E ai y − yi + 1 t
2 i ] following equations:
n
εcriti = critical strain of ply under consideration.
σai = strength of ply under consideration in kN/m2
∑ FM i
i =1
(kgf/m2, psi);
SM o =
σ to
= σt for a ply in the outer skin.
= σc for a ply in the inner skin. n
Eai = modulus of ply under consideration in kN/m2
(kgf/m2, psi); ∑ FM
i =1
i

= Et for a ply in the outer skin. SM i =


= Ec for a ply in the inner skin. σ ci
ÿ = distance from bottom of panel to the neutral
SMo = offered section modulus of the outer skin in
axis in cm or in.
cm3 or in3
yi = distance from the bottom of the panel to the
SMi = offered section modulus of the inner skin in
ply under consideration in cm or in.
cm3 or in3
ti = thickness of ply under consideration in cm or
FMi = as defined in 3/C.1.2
in.
n = total number of plies in the laminate.
σt = tensile strength of ply being considered.
σto = tensile strength of outer skin, to be
σc = compressive strength of ply being
determined by mechanical testing. A
considered.
weighted average of the individual plies of
Et = tensile modulus of ply being considered.
the tensile strengths of the outer skin may be
Ec = compressive modulus of ply being
used for preliminary estimations.
considered.
σci = compressive strength of inner skin, to be
determined by mechanical testing. A
3/C.1.2 Failure Moment
weighted average of the individual plies of
The failure moment of each ply in the laminate can be
the compressive strengths of the inner skin
determined by the following equation:
may be used for preliminary estimations.
FM i = ε min E ai t i ( y − yi )
2

Eai, ti, ÿ, and yi are as defined in 3/C.1.1

PART 3 APPENDIX 3/C|1 Guidance on First Ply Failure Analysis on FRP Sandwich Panels
PART 4
Contents
Machinery Equipment and Systems

SECTION
1 Conditions of Classification of Machinery
3 Gas Turbines
4 Internal Combustion Engines and Reduction Gears
5 Electrical Installations
6 Pumps and Piping Systems
7 Propulsion Shafting, Propellers, Waterjets and Lift Devices
8 Steering
9 Fire Extinguishing Systems
11 Shipboard Control and Monitoring Systems
PART 4 SECTION 1

Conditions of Classification of Machinery

4/1.1 General Plans showing the location of control and


monitoring stations, controlled equipment and
The provisions of Section 1/1, Scope and Conditions of
piping/cable runs, etc.
Classification, are applicable to the classification of
Arrangements and details of the control consoles
machinery.
and panels including plan views and elevation
details, installation details and wiring data as
4/1.2 Certification on Basis of an Approved
listed in 4/11.1.4e
Quality Assurance Program
A list of all cables connecting equipment associated
Upon application, consideration will be given to the with the systems (see 4/11.1.4f)
acceptance of standardized mass-produced machinery A complete operational description of the automatic
and machinery components without test and inspection or remote control and monitoring systems (see
of individual units by the Surveyor subject to approval 4/11.1.4g)
of the manufacturer's quality assurance program. A simplified one-line diagram (electrical and piping)
of all power and automatic or remote control and
4/1.5 Shipboard Automatic or Remote Control monitoring systems (see 4/11.1.4h)
and Monitoring Systems A schematic diagram of all control, alarm, display
and safety systems.
Shipboard automation, remote control and monitoring
For computer-based systems, the following is to be
systems are to comply with Section 4/11, as applicable.
included:
Overall description and specification of the
4/1.11 Machinery Plans & Data
systems and equipment.
The following plans and data, as applicable for each Block diagrams for the computer hardware
craft to be built under survey, are to be submitted and showing interfacing between the work
approved before construction is commenced in stations, input/output (I/O) units, local
accordance with 1/1.9. The sizes, dimensions, welding controllers, traffic controllers, data
and other details, make and size of standard approved highways, etc.
appliances are to be shown on the plans as clearly and Logic flow chart or ladder diagrams.
fully as possible. Description of the alarm system indicating
the ways it is acknowledged, displayed
General
on the monitor or mimic display board,
Details of dead ship start arrangements (see 4/1.23)
etc.
Description of all automatic trips that may affect the
Description of the system redundancy and
craft’s propulsion system
back-up equipment, if any.
Automation and Remote Control Systems Description of the data communication
A list of electrical, pneumatic or hydraulic protocol including anticipated data
equipment associated with the particular systems process response delays.
including the data listed in 4/11.1.4a Description of the system' security protocol
A list of all major components installed within the to prevent unauthorized program
particular equipment (i.e., control console, etc.) changes which may compromise the
and the data as required in 4/11.1.4a. integrity of the automatic or remote
Certificates or test reports attesting to the suitability systems.
of the particular equipment in compliance with Description of the system with regard to the
the environmental criteria set forth in 4/11.3.7 degree of independence or redundancy
and 4/11.3.8, as applicable. For equipment that provided for the control systems
have been already certified by the Bureau and alarm/display systems and safety
provided their certification remains valid, the systems.
submission of a copy of pertinent certificate will Description of system's task priorities.
suffice. (see 4/11.3.8b)

PART 4 SECTION 1|1 Conditions of Classification of Machinery


Where applicable, description of UPS Fixed gas extinguishing system
(uninterruptable power supply) and their Fixed water spraying system
capacities including system's power Other fire extinguishing arrangements
consumption.
Gas Turbines
Equipment ratings and environmental
Plans and particulars as required by Section 4/3 of
parameters.
the Rules for Building and Classing Steel
Installation methods (electrical, pneumatic and
Vessels
hydraulic) (see 4/11.1.4k)
Additionally, details of the manufacturer’s proposed
A matrix chart for each of the systems indicating the
automatic safety devices in accordance with
information listed in 4/11.1.4l upon activation of
4/3.7.
a given alarm or safety action:
Internal Combustion Engines
Boilers, Pressure Vessels and Heat Exchangers
Plans and particulars as required by Section 4/4 of
Arrangements and details of boilers, pressure
the Rules for Building and Classing Steel
vessels and heat exchangers required by
Vessels
Section 4/2 of the Rules for Building and
Classing Steel Vessels Lift Devices
Plans and data for hydraulic and pneumatic power Details and material specifications of force
cylinders as required by 4/6.69.2b transmitting parts
Design basis stress calculations for the propellers,
Electrical Systems
impellers, shafting, gears, belt drives,
One line diagrams for the following electrical
couplings, keys, bearings, and control
systems containing the information specified in
mechanism (see 4/7.38)
4/5A1.1.2
Power supply and distribution Piping Systems
Lighting including navigating lights Diagrammatic plans of the following piping systems
Internal communication containing the information specified in 4/6.3.2
General emergency alarm Ballast system
Fire detection and alarm Bilge system
Steering gear control Compressed air systems (including starting
Intrinsically-safe equipment air systems and control systems)
Emergency generator starting Cooling water systems
Semiconductor converters for propulsion Deck drains and scuppers
Short-circuit data (see 4/5A1.3) Exhaust gas systems
Protective device coordination study (see 4/5A1.5) Essential Fresh water service systems
Electric-plant load analysis (see 4/5A1.7) Fuel oil filling, transfer and service systems
Booklet of standard wiring practices and details (see Hydraulic power piping systems
4/5B1.1) Lubricating oil systems
General arrangement plan of electrical equipment Potable water system
showing the location of the equipment listed in Sanitary system
4/5B1.3 Essential Sea water service systems
Location of splices and cable boxes together with Steam system
information of their services Vent, sounding and overflow piping
Hazardous area plan (see 4/5B1.5) Systems conveying toxic liquids, liquids with
List of all equipment in hazardous areas (see a flash point below 60C (140F), or
4/5B1.5) flammable gases
Details of electrical components as required by 4/5C All Group I piping systems not covered
above unless it is part of an
Fire Safety
independently manufactured unit (such
Arrangement and details of control station for
as air conditioning or refrigeration) that
emergency closing of openings and stopping
does not form part of a ship’s piping
machinery
system
Details and location of fireman’s outfits
A booklet of standard piping practices and details
Details of fire extinguishing appliances
(see 4/6.3.3)
Fire control plans (see 4/9.1.7)
Plans of molded or built-up flexible expansion joints
Plans of the following systems:
in seawater piping systems over 150 mm (6 in.),
Fire main system
including details of the reinforcement
Foam smothering system
arrangements (see 4/6.7.4)
Fire detection systems

PART 4 SECTION 1|2 Conditions of Classification of Machinery


Specifications for plastic pipes and components, Control system incorporating schematic electrical
including thermal and mechanical properties control logic diagram, instrumentation, alarm
and chemical resistance (see 4/6.15, 4/6.17.6 devices, etc. and including bill of materials
and 4/6.23.4)) Design calculations for torque-transmitting
Drawings of non-standard valves and fittings components such as tiller, tie rod, rudder
showing details of construction, materials and actuator, etc.
basis for pressure rating (see 4/6.19.1b and Details of electrical power supply to power units
4/6.21.3) and to steering gear control, including
Valve operating systems for all remote-controlled schematic diagram of motor controllers, feeder
valves cables, and feeder cable electrical protection
Rated torque of main steering gear
Propellers
Schematic hydraulic piping plan incorporating
For all propellers (air or water), a propeller plan
hydraulic logic diagram and including bill of
giving design data and characteristics of the
materials, typical pipe to pipe joint details, pipe
material
to valve joint details, pipe to equipment joint
For skewed propellers or propeller blades of unusual
details, pressure rating of valves and pipe
design, a detailed stress analysis as required by
fittings, and pressure relief valve settings
4/7.23.2 or 4/7.25.2
For controllable pitch propellers, plans of the Steering Vanes
propeller hub, propeller blade flange and bolts, Details and material specifications of force
internal mechanisms, hydraulic piping control transmitting parts
systems, and instrumentation and alarm Airfoil analysis including vane freestream
systems; also strength calculations for the characteristics (lift and drag characteristics)
internal mechanism Control system arrangements
Detailed stress calculations and fitting instructions
Thrusters (Steerable, Athwartship)
for keyless propeller connections
Drawings and data as per 2.4 of the Guide for
Reduction Gears Thrusters and Dynamic Positioning Systems
Arrangements, details and data as required by
Waterjets
Section 4/3 of the Rules for Building and
Details and material specifications of force
Classing Steel Vessels
transmitting parts
Shafting Design basis stress calculations for the impellers,
Detailed plans with material specifications of the shafting, steering mechanism and reversing
propulsion shafting, couplings, coupling bolts, mechanism (see 4/7.36.3)
propulsion shafting arrangement, tailshaft Calculations or test results to substantiate the
bearings and lubrication system, if oil- suitability and strength of the pressure and
lubricated, suction housing (see 4/7.36.5)
Calculations for flexible couplings and
Windlass or Winch
demountable couplings (see 4/4.19 and
Arrangements, details and stress calculations for the
4/7.10.7)
windlass or winch, drums, brakes, shaft, gears,
Shaft alignment and vibration calculations if
coupling bolts, wildcat, sheaves, pulleys and
required by 4/7.16
foundation
Detailed preloading and stress calculations and
Control arrangements
fitting instructions for non-fitted coupling bolts
Electric one-line diagram including power ratings
(see 4/7.10.3)
and cable specifications
Steering Gear Piping system diagram including working pressures,
General arrangements of the main and auxiliary welding details, material specifications and pipe
steering gears and steering compartment specifications
Assembly of upper rudder stock, tiller, tie rod,
rudder actuators, etc. 4/1.15 Machinery Space
Construction details of all torque-transmitting
Machinery spaces are to be arranged so as to provide
components such as tiller, tiller pin,
access to all machinery and controls as necessary for
tiller/rudder stock interference fit mechanism,
operation or maintenance.
tie rod, rudder actuator, etc., including bill of
materials, welding procedures, and non-
destructive testing, as applicable

PART 4 SECTION 1|3 Conditions of Classification of Machinery


4/1.17 Definitions their tanks for their own propulsion, into and from
which such vehicles can be driven, and to which
For the purpose of machinery installations, electrical
passengers have access, including spaces intended for
installations, periodically unattended machinery spaces,
the carriage of cargo vehicles.
fire protection, fire detection and fire extinction, the
following terms are defined:
4/1.17.9 Sources of Ignition
Sources of ignition are considered to include a flame,
4/1.17.1 Category A Machinery Spaces
arc, spark and electrical equipment, machinery and
Machinery spaces of Category A are those spaces and
other equipment having hot surfaces with the potential
trunks to such spaces that contain: internal combustion
of causing a non-intentional explosion or fire when
machinery used for main propulsion; internal
exposed to an explosive or flammable atmosphere or
combustion machinery used for purposes other than
material.
main propulsion where such machinery has an
aggregate total power output of not less than 375 kW
4/1.17.10 Vital Systems
(500 HP); oil fired equipment such as an incinerator,
Vital systems are those systems neccessary for the
waste disposal unit, etc.; or any oil fuel units.
craft’s survivability and safety including:
4/1.17.2 Machinery Spaces a Systems for fill, transfer, and service of fuel
Machinery spaces are Category A spaces and all other oil.
spaces containing propelling machinery, internal b Fire-main systems, including emergency fire
combustion engines, boilers, generators, major pump
electrical equipment, refrigerating, stabilizing, c Other required fire-extinguishing and detection
ventilation and air conditioning machinery, similar systems.
spaces and trunks to such spaces. d Bilge systems, including emergency bilge
suction
4/1.17.3 Oil Fuel Unit e Ballast systems.
An oil-fuel unit is any equipment, such as pumps, filters f Steering systems and steering control systems.
and heaters, used for the preparation and delivery of g Propulsion systems and their necessary
fuel oil to oil-fired boilers (including incinerators), auxiliaries (fuel oil, lube oil, cooling water,
internal combustion engines or gas turbines at a starting system, etc.) and control systems.
pressure of more than 1.8 bar (1.8 kgf/cm2, 26 psi). h Systems for transfer and control of cargo
i Ship’s service and emergency electrical
4/1.17.4 Accommodation Spaces generation systems and their auxiliaries (fuel
Accommodation spaces are those spaces used for public oil, lube oil, cooling water, starting system,
spaces, corridors, lavatories, cabins, offices, hospitals, etc.) and control systems.
cinemas, games and hobbies rooms, barber shops, j Venting and sounding systems
pantries containing no cooking appliances and similar k Engine room ventilation systems
spaces. l Other required ventilation systems
m Controllable pitch propeller systems including
4/1.17.5 Public Spaces controls
Public spaces are those portions of the accommodations n Electrical power and lighting systems
which are used for meeting halls, dining rooms, o Systems used for navigation
lounges, and similar permanently enclosed spaces. p Required communication and alarm systems
q Hydraulic systems for anchor windlass/winch
4/1.17.6 Service Spaces r Systems necessary due to special
Service spaces are those spaces used for galleys, characteristics or special service of a craft
pantries containing cooking appliances, lockers, mail s Any other system identified by the Bureau as
and specie rooms, storerooms, workshops other than crucial to the survival of the craft or to the
those forming part of the machinery spaces, similar protection of the personnel aboard.
spaces and trunks to such spaces.
4/1.17.11 Cargo Craft
4/1.17.7 Cargo Spaces Cargo craft is any craft which is not a passenger craft.
Cargo spaces are all spaces, other than special category
spaces, used for cargo and trunks to such spaces. 4/1.19 Astern Power

4/1.17.8 Special Category Spaces Astern power is to be provided in sufficient amount to


Special category spaces are those enclosed spaces secure proper control of the ship in all normal
intended for the carriage of motor vehicles with fuel in circumstances. The astern power of the main propelling

PART 4 SECTION 1|4 Conditions of Classification of Machinery


machinery is to provide for continuous operation astern 4/1.33 Thrusters
at 70% of the ahead rpm at rated speed. For main
Compliance with the Sections 2 and 4 of ABS's
propulsion systems with reversing gears, controllable
separately published, "Guide for Certification of
pitch propellers or electric propulsion drive, running
Thrusters and Dynamic Positioning Systems" is
astern is not to lead to overload of the propulsion
required as a condition for Class for main propulsion
machinery.
thrusters and is optional for propulsion-assist thrusters,
athwartship thrusters, and dynamic positioning
4/1.21 Inclinations
thrusters.
All main propulsion machinery and all auxiliary
machinery essential to the propulsion and safety of the 4/1.35 Boilers, Pressure Vessels and Turbines
craft, including the emergency source of power, is to be
When fitted, boilers and pressure vessels are to be
designed to operate when the craft is upright and when
designed and constructed in accordance with Section
inclined at any angle of list up to and including 15°
4/2 of the Rules for Building and Classing Steel
either way under static conditions and 22.5° under Vessels. Turbines are to comply with Section 4/3 of the
dynamic conditions (rolling) either way and Rules for Building and Classing Steel Vessels.
simultaneously inclined dynamically (pitching) 7.5° by
bow or stern. Lower angles may be specially accepted 4/1.37 Sea Trial
taking into consideration the type, size and service
conditions of the craft. 4/1.37.1 General
A final underway trial is to be made of all machinery,
4/1.23 Dead Craft Start including the steering gear, anchor windlass and ground
Means are to be provided to ensure that the machinery tackle. The entire installation is to be operated in the
can be brought into operation from a dead craft presence of the Surveyor to demonstrate its reliability
condition (e.g. a condition under which the main and capability to function satisfactorily under operating
propulsion plant, and auxiliaries are not in operation conditions and its freedom from harmful vibrations
due to an absence of power and normal starting energy within the operating range. The ability of the
sources are depleted) without external aid. machinery to reverse the direction of thrust of the
propeller from maximum ahead speed and bring the
4/1.25 Machinery Equations craft to rest is to be demonstrated on sea trials to the
satisfaction of the Surveyor.
The equations for rotating parts of the machinery in the All automatic controls, including trips which may
following sections are based upon strength affect the craft's propulsion system, are to be tested
considerations only. Their application does not relieve underway or alongside the pier, to the satisfaction of the
the manufacturer from responsibility for the presence of Surveyor.
dangerous vibrations in the installation at speeds within See also 4/4.23 and 4/8.8.2.
the operating range. See also 4/7.16.
4/1.37.2 Residual Fuel
4/1.27 Machinery Space Ventilation The viscosity of the fuel used on the sea trial will be
Machinery spaces are to be ventilated so as to ensure entered in the classification report.
that when machinery is operating at full power in all
weather conditions, including heavy weather, an 4/1.39 Units
adequate supply of air is maintained for operation of the These Rules are written in three systems of units, i.e., SI
machinery and safety of the personnel. units, MKS units and US customary units. Each system
is to be used independently of any other system. The
4/1.29 Engineers' Alarm format presentation in the Rules of the three systems of
Engineers’ alarms are required on craft of 500 gross units is as follows;
tons and over, which are intended for international SI units (MKS units, US customary units) unless
voyages. An engineers' alarm is to be operable from the indicated otherwise.
main propulsion control station. It is to be audible in
the engineers' accommodations. See 4/5A9.3.

4/1.31 Automatic Trips


A description of all automatic trips that may affect the
craft’s propulsion system is to be submitted for review.

PART 4 SECTION 1|5 Conditions of Classification of Machinery


PART 4 SECTION 3

Gas Turbines

4/3.1 General or other approved filter which is capable of being


cleaned without interrupting the oil supply. Where
All gas turbines of 100 kW (135 horsepower) and
strainers are fitted in parallel to enable cleaning
over and associated reduction gears are to be
without disrupting the oil supply, means are to be
constructed and installed in accordance with Section
provided to minimize the possibility of a strainer
4/3 of the Rules for Building and Classing Steel
under pressure being opened inadvertently. Strainers
Vessels.
are to be provided with suitable means for venting
Gas turbines of less than 100 kW (135
when being put into operation and being
horsepower) and associated reduction gears are to be
depressurized before being opened. Valves or cocks
constructed and equipped in accordance with good
with drain pipes led to a safe location are to be used
commercial practice, and will be accepted subject to a
for this purpose.
satisfactory performance test conducted to the
satisfaction of the Surveyor after installation.
4/3.9.2 Pressure Piping
All gas turbines are also to meet the requirements
Oil pressure piping between the service pumps and
in this Section.
the gas turbines is to be so located as to be readily
observable and is to have a relief valve fitted which
4/3.3 Piping Systems
will discharge into the suction line or back into the
Piping systems for gas turbines are to comply with the tank. Piping between the service pumps and the gas
applicable requirements in Section 4/6 in addition to turbine is to be of extra-heavy seamless or electric
this Section. resistance welded (ERW) steel, except that, if shut-off
valves are fitted between the pumps and the turbines,
4/3.5 Pressure Vessels and Heat Exchangers short flexible connections of appropriate material
may be used between the valves and the turbines.
Pressure Vessels and heat exchangers associated with
High pressure fuel oil piping is to be shielded or
gas turbine are to be in accordance with the
otherwise protected to avoid, as far as practicable, oil
applicable requirements of Section 4/2 of the Rules
spray or oil leakages onto hot surfaces with
for Building and Classing Steel Vessels.
temperatures in excess of 220C (428F), into
machinery air intakes or other sources of ignition.
4/3.7 Automatic Safety Devices
Details of the manufacturer’s proposed automatic 4/3.9.3 Drainage of Excess Fuel
safety devices to guard against hazardous conditions Provision is to be made to drain all excess fuel oil,
arising in the event of malfunction in the turbine particularly fuel which might reach the interior of the
installation are to be provided together with the jet pipe or exhaust system after a false start or after
failure mode and effect analysis. stopping, to a safe position so as to avoid a fire
hazard.
4/3.9 Fuel Oil Systems
4/3.9.4 Low Flash Point Fuel For Gas Turbines
In addition to 4/6.49, 4/6.51 and 4/6.55, fuel oil
Fuel with a flash point below 43C (109F), but not less
systems for gas turbines are to comply with the
than 35C (95F), may be permitted for gas turbine
following:
installations provided the arrangements for the
storage, distribution and utilization of the fuel are
4/3.9.1 Pumps, Heater and Strainers suitable with regard to the hazard of fire and
There are to be at least two independent fuel oil
explosion which the use of such fuel may entail, the
service pumps, each of sufficient capacity to supply
safety of the craft and persons on board is preserved.
turbines at full power and arranged that one may be
The arrangements are to comply with the following
overhauled while the other is in service.. Oil heaters
provisions:
are to be similarly installed in multiples.
Oil strainers are to be installed in the suction and
discharge lines and are to be either of the duplex type

PART 4 SECTION 3|1 Gas Turbines


a Tanks for the storage of such fuel are to be h Craft-to-shore fuel connections are to be of
located outside any machinery space and at a distance closed type and are to be provided with suitably
of not less than 760 mm (30 in.) inboard from the earthing arrangements to be used during bunkering
shell side and bottom plating and from decks and operations. ‘No Smoking’ and ‘No Naked Lights’
bulkheads. signs are to be posted in the vicinity of the bunkering
b Arrangements are to be provided to prevent station.
overpressure in any fuel tank or in any part of the oil i Each space containing a non-integral fuel tank is
fuel system, including the filling pipes. Any relief to be fitted with a fire-detection systems complying
valves and air or overflow pipes are to discharge to a with 4/9.23 and a fire extinguishing system
safe position and are to terminate with approved complying with 4/9.25.
flame arresters.
c The spaces in which fuel tanks are located are 4/3.11 Starting Arrangements
to be mechanically ventilated, using exhaust fans
Starting arrangements for gas turbine installations are
providing not less than six air changes per hour. The
to be capable of providing an equivalent number of
fans are to be such as to avoid the possibility of
starts as that required for diesel engines in 4/4.15.
ignition of flammable gas-air mixtures. Suitable wire
mesh guards are to be fitted over inlet and outlet
4/3.13 Exhaust Systems
ventilation openings. The outlets for such exhausts
are to be discharged to a safe position. ‘No Exhaust systems are to comply with 4/6.63. In
Smoking’ signs are to be posted at a the entrances to addition, gas turbine exhausts are to be located and
such spaces. arranged so that hot exhaust gases are directed away
d Earthed electrical distribution systems are not from walkways and other areas to which personnel
to be used, with the exception of earthed intrinsically have access.
safe circuits.
e Suitable certified safe type electrical equipment 4/3.15 Turbine Enclosures
is to be used in all spaces where fuel leakage could
Where an acoustic enclosure is fitted which
occur, including the ventilation system. Only
completely surrounds the gas turbine and the high-
electrical equipment and fittings essential for
pressure oil pipes, a fire detection and extinguishing
operational purposes are to be fitted in such spaces.
system is to be provided for the acoustic enclosure.
See 4/5B7.3.
f A fixed vapor detection system is to be installed
4/3.17 Turbines Driving Generators
in each space through which fuel lines pass, with
alarms provided at the continuously manned control Gas turbines driving generators are also to comply
station. with 4/5C2.15.
g Every fuel tank is, where necessary, to be
provided with “savealls” or gutters which would catch
any fuel which may leak from such tank.

PART 4 SECTION 3|2 Gas Turbines


PART 4 SECTION 4

Internal Combustion Engines


and Reduction Gears

4/4.1 General two or more engines may lead to a common oil mist
manifold.
4/1.1 Construction and Installation Where a common oil mist manifold is employed,
Internal combustion engines of 100 kW (135 the vent pipes from each engine are to be led
horsepower (hp)) and over and associated reduction independently to the manifold and fitted with a
gears are to be constructed in accordance with corrosion resistant flame screen within the manifold.
Section 4/4 the "Rules for Building and Classing The arrangement is not to violate the engine
Steel Vessels" and installed in accordance with the manufacturer’s recommendations for crankcase
following requirements, to the satisfaction of the ventilation. The common oil mist manifold is to be
Surveyor. Engines of less than 100 kW (135 hp) and accessible at all times under normal conditions and
associated reduction gears are to be constructed and effectively vented to the weather. Where venting of
equipped in accordance with good commercial the manifold to the weather is accomplished by means
practice, and will be accepted subject to satisfactory of a common vent pipe, the location of the manifold
performance test conducted to the satisfaction of the is to be as close as practicable to the weather such
Surveyor after installation. that the length of the common vent pipe is no greater
For engines driving generators, see also 4/5C2.17. than one deck height. The clear open area of the
common vent pipe is not to be less than the aggregate
4/4.1.3 Piping Systems cross-sectional area of the individual vent pipes
In addition to requirements for specific system in this entering the manifold, and the outlet to the weather is
section, piping systems are to comply with the to be fitted with a corrosion resistant flame screen.
applicable requirements in Section 4/6. The manifold is also to be fitted with an appropriate
draining arrangement.
4/4.1.5 Pressure Vessels and Heat Exchangers
Pressure vessels and heat exchangers are to be in 4/4.1.13 Warning Notices
accordance with the applicable requirements of Suitable warning notices are to be attached in a
Section 4/2 of the "Rules for Building and Classing conspicuous place on each engine and are to caution
Steel Vessels". against the opening of a hot crankcase for a specified
period of time after shutdown based upon the size of
4/4.1.7 Torsional Vibration Stresses the engine, but not less than 10 minutes in any case.
Refer to 4/7.16. Such notice is also to warn against restarting an
overheated engine until the cause of overheating has
4/4.1.11 Crankcase Ventilation been remedied.
a General Provision is to be made for
ventilation of an enclosed crankcase by means of a 4/4.1.15 Bedplate
small breather or by means of a slight suction not The bedplate or crankcase is to be of rigid
exceeding 25.4 mm (1 in.) of water. Crankcases are construction, oiltight, and provided with a sufficient
not to be ventilated by a blast of air. Otherwise, the number of bolts to secure the same to the ship's
general arrangements and installation are to be such structure. The structural arrangements for supporting
as to preclude the possibility of free entry of air to the and securing the main engines are to be submitted for
crankcase. approval. Refer to 3/7.11 for structural requirements.
b Piping Arrangement Crankcase ventilation For welded construction see also Section 2/3.
piping is not to be directly connected with any other
piping system. Crankcase ventilation pipes from each 4/4.1.17 Engine Air Intake Systems
engine are normally to be led independently to the Engine air intakes are to be provided with filters to
weather and fitted with corrosion resistant flame protect against damage from foreign matter.
screens; however, crankcase ventilation pipes from

PART 4 SECTION 4|1 Internal Combustion Engines and Reduction Gears


4/4.3 Fuel Oil Pumps and Oil Heaters standby unit can be accomplished without loss of
propulsion capability, will be acceptable for this
4/4.3.1 Transfer pumps purpose.
Refer to 4/6.51. Where strainers are fitted in parallel to enable
cleaning without disrupting the oil supply, means are
4/4.3.3 Booster pumps to be provided to minimize the possibility of a
A stand-by fuel-oil booster pump is to be provided strainer being opened inadvertently. Strainers are to
for main engines having independently driven booster be provided with suitable means for venting when
pumps. For main engines having attached fuel being put in operation and being depressurized before
pumps, a complete pump may be carried as a spare in being opened. trainers are to be so located that in the
lieu of the standby pump. For multiple engines using event of leakage oil cannot be sprayed on to the
identical attached fuel pumps, only one complete exhaust manifold or surfaces with temperatures in
pump needs to be carried as a spare. A spare fuel oil excess of 220C (428F).
booster pump will not be required where it can be The injection lines are to be of seamless drawn
proven through a FMEA that the vessel is capable of pipe. Fittings are to be extra heavy. The material
safely returning to a port of refuge under all used may be either steel or nonferrous as approved in
conditions. connection with the design. Also refer to 4/6.51.4.

4/4.3.5 Heaters 4/4.7.3 Shielding of High Pressure Fuel Oil


When fuel oil heaters are required for main engine Piping
operation, at least two heaters of approximately equal On all main and auxiliary engines having a cylinder
size are to be installed. The combined capacity of the bore of 250 mm (10 in.) and above, the high pressure
heaters is to be not less than required to supply the fuel oil injection piping is to be effectively shielded
main engine(s) at full power. and secured to prevent fuel or fuel mist from reaching
a source of ignition on the engine or its surroundings.
4/4.5 Fuel oil Pressure Piping Suitable arrangements are to be made for draining
any oil-fuel leakage and for preventing contamination
Pipes from booster pumps to injection systems are to
of lubrication oil by fuel oil. If flexible hoses are
be at least standard seamless steel. Pipes conveying
used for shielding purpose, these are to be of an
heated oil are to be at least standard seamless or
approved type. When the peak to peak pressure
electric-resistance-welded steel. ERW pipe is to be
pulsation in return piping exceeds 19.7 bar (20
straight seam and fabricated with no filler metal (e.g.,
kgf/cm2, 285 psi), shielding of this piping is also
ABS Grade 2 or 3 ERW). Valves and fittings may be
required.
screwed in sizes up to and including 60 mm O.D. (2
in. N.P.S.), but screwed unions are not to be used on
4/4.9 Lubricating Oil Systems
pressure lines in sizes 33 mm O.D. (1 in.) and over.
Valves are to be so constructed as to permit packing
4/4.9.1 General
under pressure.
The following requirements are applicable for main
and auxiliary diesel engines and for reduction gears
4/4.7 Fuel oil Injection System
associated with diesel propulsion. See also 4/1.21
and 4/6.59.
4/4.7.1 General
Strainers are to be provided in the fuel oil injection
4/4.9.3 Low Oil Pressure Alarms, Temperature
pump suction line.
and Level Indicators
For main propulsion engines, the arrangement is
An alarm device with audible and visual signals for
to be such that the strainers may be cleaned without
failure of the lubricating oil system is to be fitted.
interrupting the fuel supply to the engine. However,
Pressure and temperature indicators are to be installed
where multiple engines are provided, a dedicated
in lubricating oil systems indicating that the proper
simplex strainer may be fitted for each engine
circulation is being maintained.
provided the craft can maintain at least one-half of the
design speed or 7 knots, whichever is less, while
4/4.9.5 Drain Pipes
operating with one engine temporarily out of service
Lubricating oil drain pipes from the sump to the drain
until its strainer can by cleaned.
tank are to be submerged at their outlet ends.
For auxiliary engines the arrangement is to be
No interconnection is to be made between the
such that the strainers may be cleaned without undue
drain pipes from the crankcases of two or more
interruption of power necessary for propulsion.
engines.
Multiple auxiliary engines, each fitted with a separate
strainer and arranged such that change over to a

PART 4 SECTION 4|2 Internal Combustion Engines and Reduction Gears


4/4.9.7 Lubricating Oil Pumps Where a reduction gear is driven by more than
In cases where forced lubrication is used for one engine and any other case where a separate
propulsion engines, one independently driven standby lubricating-oil system is provided for the reduction
pump is to be provided in addition to the necessary gear, the following requirements are applicable.
pumps for normal operation. Where the size and a Pumps Two lubricating-oil pumps are to be
design of an engine is such that lubrication before provided, at least one of which is to be independently
starting is not necessary and an attached lubricating driven. The capacity of each pump is to be sufficient
pump is normally used, an independently driven for continuous operation of the main propulsion plant
standby pump is not required if a complete duplicate at its maximum rated power.
of the attached pump is carried as a spare. For b Coolers One or more lubricated-oil coolers
multiple engines using identical attached lubricating- with means for controlling the oil temperature is to be
oil pumps, only one complete pump needs to be provided together with two separate cooling water
carried as a spare. A spare lube oil pump will not be pumps, at least one of which is to be independently
required where it can be proven through a FMEA that driven. The coolers are to have sufficient capacity to
the vessel is capable of safely returning to a port of maintain the required oil temperature while the main
refuge under all conditions. propulsion plant is operating continuously at its
maximum rated power.
4/4.9.9 Filters c Indicators Indicators are to be fitted by which
Oil filters are to be provided. In the case of main the pressure and temperature of the water inlet and oil
propulsion engines which are equipped with full- outlet may be determined. Gravity tanks are to be
flow-type filters, the arrangement is to be such that fitted with a low level alarm and a sight glass is to be
the strainers may be cleaned without interrupting the fitted in the overflow line to the sump. Pressure
oil supply. However, where multiple engines are systems are to be fitted with a low pressure alarm.
provided, a dedicated simplex strainer may be fitted Sump and gravity tanks are to be provided with
for each engine provided the craft can maintain at suitable gauges for determining the level of oil within
least one-half of the design speed or 7 knots, the tank.
whichever is less, while operating with one engine d Filters A filter is to be provided in the
temporarily out of service until its filter can by lubricating-oil piping to each reduction gear. The
cleaned. requirements in 4/4.9.9 are applicable.
For auxiliary engines the arrangement is to be
such that the filters may be cleaned without undue 4/4.11 Cooling Water Systems
interruption of power necessary for propulsion.
Multiple auxiliary engines, each fitted with a separate 4/4.11.1 General
filter and arranged such that change over to a standby Means are to be provided to ascertain the temperature
unit can be accomplished without loss of propulsion of the circulating water at the return from each engine
capability, will be acceptable for this purpose. and to indicate that the proper circulation is being
The arrangement of the valving is to be such as to maintained. Drain cocks are to be provided at the
avoid release of debris into the lubricating-oil system lowest point of all jackets. For relief valves, see
upon activation of the relieving mechanism. 4/6.7.9.
Where filters are fitted in parallel to enable
cleaning without disrupting the oil supply, means are 4/4.11.3 Sea Suctions
to be provided to minimize the possibility of a filter At least two independent sea suctions are to be
under pressure being opened inadvertently. Filters provided for supplying water to the engine jackets or
are to be provided with suitable means for venting to the heat exchangers, except that for multihull craft
when being put in operation and being depressurized classed with restricted service, special consideration
before being opened. Filters are to be so located that may be given. The sea suctions are to be located as
in the event of leakage, oil cannot be sprayed onto to minimize the possibility of blanking off the cooling
surfaces with temperatures in excess of 220C (428F). water. For multiple engine installations fitted with
individual sea suctions for each engine, two means of
4/4.9.13 Lubricating-Oil Systems for Reduction supplying cooling water to each engine may be
Gears omitted where it can be proven through a FMEA that
Where a reduction gear is driven by a single engine the vessel is capable of safely returning to a port of
and a common lubricating-oil system is used for both refuge under all conditions.
the engine and gear, the requirements in 4/4.9.1
through 4/4.9.9 are applicable.

PART 4 SECTION 4|3 Internal Combustion Engines and Reduction Gears


4/4.11.5 Strainers 4/4.15.3 Starting Air Capacity
Where seawater is used for direct cooling of the Craft having main engines arranged for air starting
engines, unless other equivalent arrangements are are to be provided with at least two starting-air
specially approved, suitable strainers are to be fitted containers of approximately equal size. The total
between the sea valves and the pump suctions. The capacity of the starting-air containers is to be
strainers are to be either of the duplex type or sufficient to provide, without recharging the
otherwise arranged so they can be cleaned without containers, at least the number of starts stated below.
interrupting the cooling water supply. If other compressed air systems, such as control
air, are supplied from starting air containers, the
4/4.11.7 Circulating Water Pumps capacity of the containers is to be sufficient for
There are to be at least two means for supplying continued operation of these systems after the air
cooling water to main and auxiliary engines, necessary for the required number of consecutive
compressors, coolers, reduction gears, etc. One of starts has been used.
these means is to be independently driven and may a Diesel Propulsion The minimum number of
consist of a connection from a suitable pump of consecutive starts (total) required to be provided from
adequate size normally used for other purposes, such the starting-air containers is to be based upon the
as a general service pump, or in the case of fresh- arrangement of the engines and shafting systems as
water circulation one of the craft’s fresh-water indicated in the following table.
pumps. Where, due to the design of the engine, the
connection of an independent pump is impracticable, Single Screw Craft Multiple Screw Craft
the independently driven stand-by pump will not be One engine Two or more One engine Two or more
required if a complete duplicate of the attached pump coupled to engines coupled to engines
is carried as a spare. For multiple propulsion engines shaft coupled to each shaft coupled to
directly shaft thru directly each shaft
using identical attached pumps, only one complete or clutch and or thru clutch
pump needs to be carried as a spare. Multiple thru reduction thru and
auxiliary engine installations utilizing attached pumps reduction gear reduction reduction
need not be provided with spare pumps. A spare gear gear gear
Reversible 12 16 16 16
cooling water pump will not be required where it can Engines
be proven through a FMEA that the vessel is capable Non-
of safely returning to a port of refuge under all reversible 6 8 8 8
conditions. Engines

4/4.15 Starting Systems For arrangements of engine and shafting systems


which differ from those indicated in the table, the
4/4.15.1 Starting Air Systems capacity of the starting-air containers will be specially
The design and construction of all air receivers are to considered based on an equivalent number of starts.
be in accordance with the applicable requirements of b. Diesel-electric Propulsion The minimum
Section 4/2 of the Rules for Building and Classing number of consecutive starts required to be provided
Steel Vessels. The piping system is to be in from the starting-air containers is to be determined
accordance with the applicable requirements of from the following equation.
Section 4/6 of these Rules. The air receivers are to be S = 6 + G(G-1)
so installed as to make the drain connections effective
under extreme conditions of trim. Compressed air where
systems are to be fitted with relief valves and each S = total number of consecutive starts
container which can be isolated from a relief valve is G = number of engines driving the propulsion
to be provided with a suitable fusible plug to relieve generators but the value of G need not
the pressure in case of fire. Connections are also to exceed 3.
be provided for cleaning the air container and pipe
lines. 4/4.15.5 Starting Air Compressors
All discharge pipes from starting air compressors For craft having internal-combustion engines
are to be led directly to the starting air receivers, and arranged for air starting, there are to be two or more
all starting pipes from the air receivers to main or air compressors, at least one of which is to be driven
auxiliary engines are to be entirely separate from the independently of the main propulsion unit, and the
compressor discharge piping system. total capacity of air compressors driven
independently of the main propulsion unit is to be not
less that 50% of the total required.

PART 4 SECTION 4|4 Internal Combustion Engines and Reduction Gears


The total capacity of the air compressors is to be required number of starting capacity. Provisions are
sufficient to supply within one hour the quantity of to be made to maintain continuously the stored energy
the air need to satisfy 4/4.15.3 by charging the at all times. See also 4/5A3.17 and 4/5B2.7.
receivers from atmospheric pressure. The capacity is
to be approximately equally divided between the 4/4.15.11 Hydraulic Starting
number of compressors fitted, excluding an Hydraulic oil accumulators for starting the main
emergency compressor where fitted. propulsion engines are to have sufficient capacity
The arrangement for dead craft air starting is to be without recharging for starting the main engines as
such that the necessary air for the first charge can be required in 4/4.15.3.
produced on board without external aid. See 4/1.23.
4/4.17 Engine Exhaust Systems
4/4.15.7 Protective Devices for Starting-air Mains Engine exhaust systems are to comply with 4/6.63. In
In order to protect starting air mains against addition, propulsion engines with bores exceeding
explosions arising from improper functioning of 200 mm (7.87 in.) are to be fitted with a means to
starting valves, an isolation non-return valve or display the exhaust gas temperature of each cylinder.
equivalent is to be installed at the starting air supply
connection to each engine. Where engine bores 4/4.19 Couplings
exceed 230 mm (9 1/16 in.), a bursting disc or flame
arrester is to be fitted in way of the starting valve of 4/4.19.1 Flexible Shaft Couplings
each cylinder for direct reversing engines having a Details of the various components of flexible
main starting manifold or at the supply inlet to the couplings for main propulsion machinery and ship's
starting-air manifold for nonreversing engines. service generator sets are to be submitted for
The above requirement is applicable to engines approval. Flexible couplings with elastomer or spring
where the air is directly injected into the cylinder. It type flexible members and which represent the sole
is not intended to apply to engines utilizing air start source of transmitting propulsive power in a line shaft
motors. on a single screw craft are to be provided with
torsional limit capacity (coupling will lock beyond its
4/4.15.9 Electrical Starting limit) or positive means of locking the coupling.
a Main Engine Where the main engine is Operation of the craft with a locked coupling may be
arranged for electric starting, at least two separate at reduced power provided warning notices are posted
batteries ( or separate set of batteries) are to be fitted. at the control station.
The arrangement is to be such that the batteries (or set
of batteries) cannot be connected simultaneously in 4/4.19.3 Flanged Couplings and Coupling Bolts
parallel. Each battery (or set) is to be capable of Refer to 4/7.10.5, for flanged couplings.
starting the main engine when in cold and ready to Elongation for auxiliary machinery coupling bolts
start conditions. The combined capacity of the made of steel having an ultimate tensile strength over
batteries is to be sufficient without recharging to 690 N/mm2 (70 kgf/mm2, 100,000 psi) will be subject
provide within 30 minutes the number of starts of to special consideration. Also refer to 4/7.10.1 and
main engines as required for air starting in 4/4.15.3, 4/7.10.3.
and if arranged also to supply starting for auxiliary
engines the number of starts required in b. See also c. 4/4.21 Testing of Pumps Associated with Engine
b Auxiliary Engine Electric starting and Reduction Gear Operation
arrangements for auxiliary engines are to have at least
Pumps associated with engine and reduction gear
two separate batteries (or separate set of batteries) or
operation (oil, water, fuel) utilized with engines
may be supplied by separate circuits from the main
having bores exceeding 300 mm (11.8 in.) are to be
engine batteries when such are provided. Where one
provided with certificates issued by the Surveyor.
auxiliary engine is arranged for electric starting, one
The following tests are to be conducted to the
battery (or set) may be accepted in lieu of two
Surveyor's satisfaction:
separate batteries (or sets). The capacity of the
batteries for starting the auxiliary engines is to be
4/4.21.1 Pumps Hydrostatic Tests
sufficient for at least three starts for each engine.
Independently-driven pumps are to be hydrostatically
c Other Requirements The starting batteries (or
tested to 4 bar (4 kgf/cm2, 57 psi) but not less than
set of batteries) are to be used for starting and for
1.5P, where P is the maximum working pressure in
engine’s own control and monitoring purpose only,
the part concerned.
When the starting batteries are used for engine’s own
control and monitoring purpose, the aggregate
capacity of the batteries is to be sufficient for
continued operation of such system in addition to the

PART 4 SECTION 4|5 Internal Combustion Engines and Reduction Gears


4/4.21.3 Capacity Tests operating conditions and its freedom from harmful
Tests of pump capacities are to be conducted to the vibration at speeds within the operating range. See
satisfaction of the Surveyor with the pump operating also 4/1.37.
at design conditions. Capacity tests will not be For conventional propulsion gear units above
required for individual pumps produced on a 1120 kW (1500 HP) a record of gear-tooth contact is
production line basis, provided the Surveyor is to be made at the trials. To facilitate the survey of
satisfied from periodic inspections and the extent and uniformity of gear-tooth contact, selected
manufacturer's quality assurance procedures that the bands of pinion or gear teeth on each meshing are to
pump capacities are acceptable. be coated beforehand with copper or layout dye. See
1/3.9.1b.
4/4.23 Trial The gear-tooth examination for conventional gear
units 1120 kW (1500 HP) and below and all epicyclic
Before final acceptance, the entire installation is to be
gear units will be subject to special consideration.
operated in the presence of the Surveyor to
The gear manufacturer's recommendations will be
demonstrate its ability to function satisfactorily under
considered.

PART 4 SECTION 4|6 Internal Combustion Engines and Reduction Gears


PART 4 SECTION 5

Electrical Installations

This Section consists of the following parts:

General “General” for descriptions and requirements applicable to systems, installations, machinery and
equipment in general.
Part A “Systems” for specific requirements necessary for initial planning and basic design of electrical
systems.
Part B “ Installations” for specific requirements necessary for the subsequent outfitting, selection of the
machinery/equipment, etc.
Part C “Machinery and Equipment” for requirements for procured equipment.
Part D “Specialized Installations” for supplemental requirements for high voltage system, electric
propulsion system and system of less than 75 kW.
Part E “Specialized Vessels and Services” for supplemental requirements for installations in special-
category spaces.

General 4/5.3.2 Essential Services


Services essential for the navigation, steering and
maneuvering, or for special characteristics (e.g. special
4/5.1 Applications
services) of the craft, or for the safety of human life.
Electrical apparatus and wiring systems are to be
constructed and installed to the satisfaction of the 4/5.3.3 Explosion-proof (Flameproof) Equipment
Surveyor in accordance with this Section. The Explosion-proof equipment is an equipment:
following are minimum requirements for classification a Having an enclosure capable of:
purposes. Consideration will be given, however, to 1 Withstanding an explosion within it of a
arrangements or details which can be shown to comply specified flammable gas or vapor, and
with other recognized standards, provided they are not 2 Preventing the ignition of the specified
less effective. flammable gas or vapor in the atmosphere
For craft having an aggregate generator capacity not surrounding the enclosure by sparks, flashes
exceeding 75 kW, the requirements contained in 4/5D3 or explosions of the gas or vapor within, and
are to be complied with. Electrical installations in b Operates at such an external temperature that a
machinery spaces with gasoline engines will be surrounding flammable atmosphere will not be ignited.
specially considered. Where explosion-proof equipment is required by this
For passenger craft, see Section 5/1. Guide, equipment certified as being flameproof as
defined in IEC Publication 79 or other recognized
4/5.3 Definition standard may be accepted.

The following definitions apply for the purpose of this 4/5.3.4 Hazardous Area (Hazardous Location)
Section. An area where flammable or explosive vapor, gas, or
dust, or explosives may normally expected to
4/5.3.1 Earthed Distribution System accumulate.
A system in which one pole of a single phase system or
the neutral point of a three phase system is earthed but 4/5.3.5 Hull-return System
the earthing connection does not normally carry A system in which insulated conductors are provided
current. for connection to one pole or phase of the supply, the
hull of the craft or other permanently earthed structure
being used for effecting connections to the other pole
or phase.

PART 4 SECTION 5||1 Electrical Installations -- General


4/5.3.6 Intrinsically-safe 4/5.3.12 Pressurized Equipment
A circuit or part of a circuit is intrinsically-safe when Equipment having an enclosure in which positive
any spark or any thermal effect produced in the test pressure is maintained to prevent against the ingress of
conditions prescribed in a recognized standard (such as external atmosphere and complying with the
IEC Publication 79-11) is incapable of causing ignition requirements in 4/5B7.3.3.
of the prescribed explosive gas atmosphere.
a Category “ia” Apparatus which is incapable of 4/5.3.13 Semi-enclosed Space
causing ignition in normal operation, or with a single A space limited by decks and/or bulkheads in such a
fault, or with any combination of two faults applied, manner that the natural conditions of ventilation in the
with the following safety factors: space are notably different from those obtained on open
deck.
- in normal operation: 1.5
- with one fault: 1.5 4/5.3.14 Separate Circuit
- with two faults: 1.0 A circuit which is independently protected by a circuit
protection device at the final sub-circuit and is
Above safety factors are applied to the current, voltage, dedicated to a single load.
or their combination as specified in 10.4.1 of IEC
Publication 79-11. 4/5.3.15 Short Circuit
A short circuit is an abnormal connection through a
4/5.3.7 Increased Safety negligible impedance, whether made accidentally or
Type of protection applied to electrical apparatus that intentionally, between two points of different potential
does not produce arcs or sparks in normal service, in in a circuit.
which additional measures are applied so as to give
increased security against the possibility of excessive 4/5.3.16 Short-time Rating
temperatures and of the occurrence of arc and sparks. A rating at which the machine is operated for a limited
See IEC Publication 79-7. period which is less than that required to reach the
steady temperature condition, followed by a rest and
4/5.3.8 Non-Periodic Duty Rating de-energized period of sufficient duration to re-
A rating at which the machine is operated continuously establish the machine temperature within 2 oC (3.6 oF)
or intermittently with varying the load and speed within of the coolant.
the permissible operating range. The load and speed
variations include the overloads applied frequently, 4/5.5 Plans and Data to Be Submitted
which may be greatly exceed the full load rating of the
machine. See 4/5A1, 4/5B1, 4/5C1 and 4/5D2.3.

4/5.3.9 Non-sparking Fan 4/5.7 Standard Distribution System


A fan consisting of a combination of impeller and
housing which are unlikely to produce sparks by static The following are recognized as standard systems of
electricity or by entry of foreign objects in both normal distribution. The distribution systems differing from
and abnormal conditions. these will be specially considered.

4/5.3.10 Periodic Duty Rating - Two-wire direct current


A rating at which the machine is operated repeatedly on - Three-wire direct current
cycle of sequential loading with starting, electric - Two-wire single-phase alternating current
braking, no-load running, rest and de-energized periods - Three-wire three-phase alternating current*
where applicable. The time for the duration of - Four-wire three-phase alternating current
operating cycle (duty cycle) is to be 10 minutes and the
ratio (i.e., cyclic duration factor) between the period of * Three-wire single-phase A.C. may be used in
loading (including starting and electric braking) and the conjunction with this system for lighting.
duty cycle is to be one of the values of 15%, 25%,
40%, or 60%. However, the electrical distribution voltages
throughout the craft are not to exceed:
4/5.3.11 Portable Apparatus
Portable apparatus is any apparatus served by a flexible - 500 V for power, cooking, heating and other
cord. permanently connected equipment; and
- 250 V for lighting, internal communications and
receptacle outlets.

PART 4 SECTION 5||2 Electrical Installations -- General


Subject to the acceptance by the Administration, 4/5.13.4 Class F Insulation
high voltage systems as outlined in 4/5D1 may be Materials or combinations of materials such as mica,
acceptable for propulsion systems. glass fiber, etc., with suitable bonding substances.
Other materials or combinations of materials, not
4/5.9 Voltage and Frequency Variations necessarily inorganic, may be included in this class if,
by experience or accepted tests, they can be shown to
Electrical appliances supplied from the main or be capable of operation at 155 oC (311 oF).
emergency systems other than battery supplied are to
be so designed and manufactured that they are capable 4/5.13.5 Class H Insulation
of being operated satisfactorily under the normally Materials or combinations of materials such as silicone
occurring variations in voltage and frequency. Unless elastomer, mica, glass fiber, etc., with suitable bonding
otherwise stated, the variations from the rated value substances such as appropriate silicone resins. Other
may be taken from the Table 4/5.1. Any special system, materials or combinations of materials may be included
e.g. electronic circuits, which cannot operate in this class if, by experience or accepted tests, they can
satisfactorily within the limit shown in the Table is to be shown to be capable of operation at 180 oC (356 oF).
be supplied through a stabilized supply.
4/5.13.6 Insulation for Temperature Above 180 oC
4/5.11 Materials (356 oF)
Materials or combination of materials which by
All electrical equipment is to be constructed of durable experience or accepted tests can be shown to be
and flame-retardant materials. Materials are to be capable of satisfactory operation at temperature over
resistant to corrosion, moisture, high and low 180 oC (356 oF) will also be considered: supporting
temperatures, and are to have other qualities necessary background experience or report of tests conducted in
to prevent deterioration in the ambient conditions the accordance with a recognized standard ascertaining
equipment may be expected to encounter. their suitability for the intended application and
temperature operation are to be submitted for review.
4/5.13 Insulation Material
4/5.15 Degree of Protection for Enclosure
For the purpose of these requirements insulating
material is designated as follows. The designation to indicate the degree of protection
consists of the characteristic letters IP followed by two
4/5.13.1 Class A Insulation numerals (the "characteristic numerals") indicating
Materials or combinations of materials such as cotton, conformity with conditions stated in Tables 4/5.2 and
silk and paper when suitably impregnated or coated or 4/5.3. The test and inspection for determining the
when immersed in a dielectric liquid such as oil. Other degree of protection may be carried out in accordance
materials or combinations of materials may be included with IEC Publication 529 by the manufacturer whose
in this class if, by experience or accepted tests, they can certificate of tests will be acceptable and is to be
be shown to be capable of operation at 105 oC (221 oF). submitted upon request from the Bureau. Type of
enclosure required for protection of equipment is to be
4/5.13.2 Class B Insulation suitable for the intended location. See 4/5B2.1.1 for
Materials or combinations of materials such as mica, selection of protective enclosure for electrical
glass fiber, etc., with suitable bonding substances. equipment based on location condition. Equipment in
Other materials or combinations of materials, not compliance with recognized national standards will
necessarily inorganic, may be included in this class if, also be considered.
by experience or accepted tests, they can be shown to
be capable of operation at 130 oC (266 oF). 4/5.17 Temperature Ratings
With the exception of equipment associated with
4/5.13.3 Class E Insulation control and monitoring systems described in 4/11, in
Materials or combinations of materials which, by the following requirements an ambient temperature of
experience or accepted tests, can be shown to be 40 oC (104 oF) has been assumed for locations outside
capable of operation at 120 oC (248 oF) (materials of boiler and engine rooms while 45 oC (113 oF) has
possessing a degree of thermal stability allowing them been assumed as the ambient temperature for the latter
to be operated at a temperature 15 oC (27 oF) higher spaces; however, electric rotating machines in boiler
than Class A materials). and engine rooms are to be rated for an ambient
temperature of 50 oC (122 oF). Where the ambient
temperature is in excess of these values, the
equipment's total rated temperature is not to be
exceeded. Where equipment has been rated on ambient

PART 4 SECTION 5||3 Electrical Installations -- General


temperatures less than those contemplated, sufficient to show satisfactory operation, and parallel
consideration will be given to the use of such operation with all possible combinations is to be
equipment, provided the total temperature for which the demonstrated. Each auxiliary motor necessary to the
equipment is rated will not be exceeded. For equipment operation of the craft is to be run for a time sufficient to
associated with control and monitoring systems show satisfactory performance at such load as can
described in 4/11, refer to 4/11.3.7e2. readily be obtained. All main switches and circuit
breakers are to be operated but not necessarily at full
4/5.19 Clearances and Creepage Distances load. The operation of the lighting system, heaters, etc.,
is to be demonstrated satisfactorily. The entire
The distances between live parts of different potential installation is to operate to the satisfaction of the
and between live parts and the case or other earthed Surveyor and the drop in voltage on any part of the
metal, whether across surfaces or in air, are to be installation is not to exceed 6 %. See 4/5B3.1.3.
adequate for working voltage having regard to the
nature of the insulating material and the conditions of 4/5.21.2 Communication Facilities
service. See 4/5C4.11.6 and 4/5D1.1.4 for additional Satisfactory operation of the interior communications
requirements for switchboard and high voltage systems. system required by 4/5A8 is to be demonstrated to the
Surveyor during sea trials. Particular attention is to be
4/5.21 Service Trial given to demonstrating that the voice communication
systems required by 4/5A8 provide the capability of
4/5.21.1 Electrical Installation for Craft Services carrying on a conversation while the craft is being
All auxiliary apparatus is to be tried under working navigated.
conditions. Each generator is to be run for a time

PART 4 SECTION 5||4 Electrical Installations -- General


TABLE 4/5.1 Voltage & Frequency Variations
[See 4/5.9]

Quantity in Permanent
Operation Variation
Frequency ±5%
Voltage + 6 %, - 10 %

TABLE 4/5.2 Degree of Protection


- indicated by the first characteristic numeral
[See 4/5.15]

Degree of Protection
First Short Description Definition
Characteristic
Numeral
0 Non - protected No special protection

1 Protected against solid A large surface of the body, such as a hand (but no
objects greater than 50 mm (2 protection against deliberate access). Solid object
in.) exceeding 50 mm (2 in.) in diameter.

2 Protected against solid Fingers or similar objects not exceeding 80 mm (3.15 in.) in
objects greater than 12 mm length. Solid objects exceeding 12 mm (0.5 in.) in diameter.
(0.5 in.)
Tools, wires, etc. of diameter or thickness greater than 2.5
3 Protected against solid mm (0.1 in.). Solid objects exceeding 2.5 mm (0.1 in.) in
objects greater than 2.5 mm diameter
(0.1 in.)
Wires or strips of thickness greater than 1 mm (0.04 in.).
4 Protected against solid Solid objects exceeding 1 mm (0.04 in.) in diameter.
objects greater than 1 mm
(0.04 in.)
Ingress of dust is not totally prevented, but dust does not
Dust protected enter in sufficient quantity to interfere with satisfactory
5 operation of the equipment

No ingress of dust
6 Dust-tight

[Designation]
The degree of protection is designated as shown in the following examples:
When it is required to indicate the degree of protection by only one characteristic numeral which shows either degree of
protection against foreign bodies and electrical shock or against liquid, the omitted numeral is to be replaced by the letter X.
Examples:
(1) IP56 The first characteristic numeral of "5".
The second characteristic numeral of "6".

PART 4 SECTION 5||5 Electrical Installations -- General


TABLE 4/5.2 Degree of Protection
(continued) - indicated by the first characteristic numeral
[See 4/5.15]
(2) IPX5 Degree of protection against only liquid.
(3) IP2X Degree of protection against only foreign bodies and electrical shock.

TABLE 4/5.3 Degree of Protection


- indicated by the second characteristic numeral
[See 4/5.15]

Degree of Protection
Second Short Definition
Characteristic Description
Numeral
0 Non - protected No special protection.

1 Protected against dripping Dripping water (vertically falling drops) is to have no


water harmful effect.

2 Protected against dripping Vertically dripping water is to have no harmful effect when
water when tilted up to 15 the enclosure is tilted at any angle up to 15 deg. from its
deg. normal position.

3 Protected against spraying Water falling as spray at an angle up to 60 deg. from the
water vertical is to have no harmful effect.

4 Protected against splashing Water splashed against the enclosure from any direction is
water to have no harmful effect.

5 Protected against water jets Water projected by a nozzle against the enclosure from any
direction is to have no harmful effect.

6 Protected against heavy seas Water from heavy seas or water projected in powerful jets
is not to enter the enclosure in harmful quantities.

7 Protected against the effects Ingress of water in a harmful quantity is not to be possible
of immersion when the enclosure is immersed in water under defined
conditions of pressure and time.

8 Protected against submersion The equipment is suitable for continuous submersion in


water under conditions which are to be specified by the
manufacturer.

Note.- Normally this will mean that the equipment is


hermetically sealed. However, with certain types of
equipment, it can mean that water can enter but only in such
a manner that it produces no harmful effects.

See Designation & examples in Table 4/5.2.

PART 4 SECTION 5||6 Electrical Installations -- General


the maximum allowable breaking and making
Part A. Systems capacities of the protective device. Similar calculations
are to be made at other points in the distribution system
4/5A1 Plans and Data to be Submitted where necessary to determine the adequacy of the
interrupting capacities of protective devices.
4/5A1.1 Wiring
4/5A1.5 Protective Device Coordination
4/5A1.1.1 Systems
One line diagrams for the following electrical systems
A protective device coordination study is be submitted
are to be submitted for review.
for review. This protective device coordination study
is to consist of an organized time-current study of all
- Power Supply and Distribution
protective devices in series from the utilization
- Lighting including Navigation Light
equipment to the source for all circuit protection
- Internal Communication
devices having different setting or time-current
- General Emergency Alarm
characteristics for long-time delay tripping, short-time
- Fire Detection and Alarm
delay tripping, and instantaneous tripping, where
- Steering Gear Control
applicable. Where an overcurrent relay is provided in
- Intrinsically-safe Equipment
series and adjacent to the circuit protection device, the
- Emergency Generator Starting
operating and time-current characteristics of the relay
are to be considered for coordination. See 4/5A5.1.5.
4/5A1.1.2 Data for Wiring Systems
The one line diagrams are to show the circuit
4/5A1.7 Load Analysis
designation, type and size of cables, cable grouping and
banking, trip setting and rating of the circuit protection
An electric-plant load analysis is to be submitted for
devices, the location of electrical equipment
review. The electric-plant load analysis is to cover all
accompanied by list of components, complete feeder
operating conditions of the craft, such as normal sea
list, rated load current for each branch circuit. The one
going, harbor in/out, and emergency operations.
line diagram for power supply and distribution systems
is to indicate the following components details.

Note:
4/5A2 Craft Service Main Source of Power
For craft having a length of 61 m (200 ft) and over, a voltage
drop calculation for the longest run of each cable size is to be 4/5A2.1 Power Supply by Generator
included.
4/5A2.1.1 Number of Generators
Generator: kW or kVA rating, voltage, rated Craft using electricity for craft's service power or light
current, frequency, number of are to be provided with at least two electric generators
phases, power factor for the craft service electrical demand.
Batteries: type, voltage, capacity, conductor
protection (when required) 4/5A2.1.2 Capacity of Generators
Motors: kW rating, remote stops (when The capacity of the generating sets is to be such that in
required) the event of any one generating set being stopped it will
Transformers: kVA rating, rated voltage and still be possible without recourse to the emergency
current on primary and secondary source of power to supply those services necessary to
side, connection method provide normal operational conditions of propulsion
and safety, preservation of the cargo and minimum
The one line diagram for power supply and distribution comfortable conditions of habitability which are to
systems is also to include a list of sequential start of include at least adequate services for cooking, heating,
motors and equipment having emergency tripping or domestic refrigeration, mechanical ventilation, sanitary
preferential tripping features. and fresh water.

4/5A1.3 Short-circuit Data 4/5A2.1.3 Starting from Dead Craft Condition


The generating sets are to be such that with any one
In order to establish that the protective devices on the generator or its primary source of power out of
main and emergency switchboards have sufficient operation, the remaining generating sets are capable of
short-circuit breaking and making capacities, data are providing the electrical services necessary to start the
to be submitted giving the maximum calculated short- main propulsion plant from a dead craft condition. The
circuit current in symmetrical r.m.s. and asymmetrical emergency source of electrical power may be used for
peak values available at the main bus bars together with the purpose of starting from a dead craft condition if its

PART 4 SECTION 5|7 Electrical Installations -- Part A. Systems


capability either alone or combined with that of any starting current will not cause any already running
other source of electrical power is sufficient to provide motor to stall or control equipment to drop out.
at the same time those services required to be supplied
by 4/5A3.3.2 to 4/5A3.3.3.
4/5A3 Emergency Source of Power
4/5A2.1.4 Power Supplied by Propulsion Generator
For craft propelled by electric power and having two or 4/5A3.1 General
more constant voltage propulsion generators, the craft's
service electric power may be derived from this source A self-contained emergency source of electrical power
and additional craft's service generators need not be is to be provided.
fitted provided that with one propulsion generator out
of service, a speed of 7 knots or one-half of the design 4/5A3.1.1 Location
speed whichever is the lesser can be maintained. See The emergency source of electrical power, associated
4/5D2.17.4 to 4/5D2.17.6 for details of propulsion power transformer, if any, transitional source of
generator. emergency power, emergency switchboard, emergency
lighting switchboard, and the fuel oil tank for
4/5A2.1.5 Fuel Capacity for Generator Prime emergency generator prime mover are to be located
Mover above the waterline in the final condition of damage as
Where the fuel for any craft's service generator prime referred to in Section 3/3 (see also 4/1.21), outside the
mover differs from the fuel for the main propulsion machinery casing, and are to be readily accessible from
plant, adequate fuel capacity for that craft's service the open deck. They are not to be located forward of
generator prime mover with adequate margins is to be the collision bulkhead.
provided for the longest anticipated run of the craft
between fueling ports. 4/5A3.1.2 Separation
a Machinery Space of Category A The location of
4/5A2.3 Generator Driven by Propulsion Unit the emergency source of electrical power, associated
power transformer, if any, the transitional source of
4/5A2.3.1 Shaft Generator as a Main Source of emergency power, the emergency switchboard and the
Power emergency lighting switchboard in relation to the main
A generator driven by a main propulsion unit (shaft source of electrical power, associated transforming
generator) which is intended to operate at a constant equipment, if any, and the main switchboard is to be
speed, e.g. a system where craft speed and direction are such that a fire or other casualty in the space containing
controlled only by varying propeller pitch, may be the main source of electrical power, power transformer,
considered to be one of the generators required by if any, and the main switchboard, or in any machinery
4/5A2.1.1. space of category A will not interfere with the supply,
control and distribution of emergency electrical power.
4/5A2.3.2 Non-constant Speed Shaft Generator As far as practicable the space containing the
Shaft generator installations which do not comply with emergency source of electrical power, associated
the criteria in 4/5A2.3.1 may be fitted in addition to the transforming equipment, if any, the transitional source
above required generators provided that an alternative of emergency electrical power and the emergency
source of electrical power can be brought on line switchboard including trunks to such spaces are not to
automatically within 45 seconds whenever the voltage be contiguous to the boundaries of machinery spaces of
or frequency of the shaft generator deviates, for any category A or those spaces containing the main source
reason, beyond the prescribed limits. of electrical power, associated transforming equipment,
if any, and the main switchboard.
4/5A2.5 Sizing of A.C. Generator b Machinery Space Other Than Category A
Spaces containing emergency sources of power are to
In selecting the capacity of an alternating-current be separated from machinery spaces (as defined in
generating plant, particular attention is to be given to 4/1.17.2) other than Category A machinery spaces, by a
the starting current of motors forming part of the boundary insulated to a level of not less than A-15 for
system. Under normal sea going condition of the craft bulkheads and decks and A-0 for the overhead from
with one generator held in reserve as a standby, the any such space (including trunks to such spaces).
remaining generator sets operating in parallel and Where the emergency sources of power is a generator
initially carrying minimum load necessary for operating the above is not intended to preclude the location of the
the craft are to have sufficient capacity with respect to emergency generator in the same space as its prime
the largest idle motor on the craft so that the motor can mover regardless of size.
be started and the voltage drop occasioned by its

PART 4 SECTION 5|8 Electrical Installations -- Part A. Systems


c Alternative Arrangement Where it can be actual service to draw their rated loads. In the latter
shown that the arrangements of the spaces containing case supporting details are to be submitted. The
the emergency source of power in relation to machinery emergency source of electrical power is to be capable,
space of category A are in compliance with the having regard to starting currents and the transitory
requirements of the governmental authority of the nature of certain loads, of supplying simultaneously at
country whose flag the craft flies, either of the least the following services for the period specified in
following may be considered in lieu of 4/5A3.1.2a: 4/5A3.3.2 to 4/5A3.3.10, if they depend upon an
1 Contiguous boundaries insulated to A-60 with electrical source for their operation.
the insulation extending at least 450 mm (18
in.) beyond the boundary of the space 4/5A3.3.2 Lighting Systems and Navigation Light
containing the emergency source of power. a Emergency Lighting for 12 hours
2 Separation by a cofferdam having dimensions 1 At the stowage positions of life-saving
as required for ready access and extending at appliances;
least 150 mm (6 in.) beyond the boundaries of 2 At all escape routes such as alleyways,
the space containing the emergency source of stairways, exits from accommodation and
power. Except for cables feeding services service spaces, embarkation points, etc.;
located in the machinery space or those 3 In the public spaces, if any;
spaces containing main source of electrical 4 In the machinery spaces and main emergency
power, associated transformer or converter, if generating spaces, including their control
any, and main switchboard, emergency positions;
electric cables are not to be installed in such 5 In control stations;
cofferdams unless the cofferdam is insulated 6 At the stowage positions for fireman' s outfits,
to A-60. and
7 At the steering gear.
4/5A3.1.3 Alternative to Emergency Source of b For period of 12 hours:
Power Navigation lights and other lights required by
Where the main source of electrical power is located in the International Regulation for Preventing
two or more compartments which are not contiguous, Collisions at Sea in force.
each of which has its own self-contained systems,
including power distribution and control systems, 4/5A3.3.3 Communication System, Radio,
completely independent of each other and such that a Navigation Aid, and Fire Alarm Systems and Fire
fire or other casualty in any one of the spaces will not Extinguishing Remote Controls
affect the power distribution from the others, or to the For a period of 12 hours:
services required by 4/5A3.3, the requirements of a Electrical internal communication equipment for
4/5A3.1, 4/5A3.1.1 and 4/5A3.5.4 may be considered announcements during evacuation;
satisfied without an additional emergency source of b The navigational equipment as required by
electrical power, provided that: Chapter 13 of the IMO International Code of Safety for
a There is at least one generating set, meeting the High-speed Craft. Where such provision is
requirements of Table 4/1.1 and each of sufficient unreasonable or impracticable, the Administration may
capacity to meet the requirements of 4/5A3.3, in each waive this requirement for craft of less than 5,000 GT;
of at least two non-contiguous spaces; c Fire-detection and general alarm system and
b The arrangements required by a in each such manual fire alarms;
space are equivalent to those required by 4/5A3.5.2, d Remote control devices of fire-extinguishing
4/5A3.9 and 4/5A3.15 so that a source of electrical systems, if electrical, and
power is available at all times to the services required e Craft radio facilities and other loads as set out in
by 4/5A3, and 14.12.2 of the IMO International Code of Safety for
c The generator sets referred to in a and their self- High-speed Craft.
contained systems are installed in accordance with
4/5A3.1.1. 4/5A3.3.4 Emergency Fire Pump
For period of 12 hours, one of the fire pumps required
4/5A3.3 Emergency Services by 4/9.15.2 if dependent upon the emergency generator
for its source of power.
4/5A3.3.1 General
The electrical power available is to be sufficient to 4/5A3.3.5 Steering Gear
supply all those services that are essential for safety in Steering gear to comply with 4/5A6.5 if powered from
an emergency, due regard being paid to such services the emergency source , for a period of 10 minutes
as may have to be operated simultaneously and for continuous operation.
equipment which can be shown as not being required in

PART 4 SECTION 5|9 Electrical Installations -- Part A. Systems


4/5A3.3.6 Emergency Control and Monitoring 2) Provided with a transitional source of
Systems emergency electrical power as specified in
Emergency control monitoring systems as required by 4/5A3.7 unless an emergency generator is
4/11.3.6a2. provided capable both of supplying the
services referred to in 4/5A3.7 of being
4/5A3.3.7 Emergency Sprinkler and Drencher automatically started and supplying the
Pump required load as quickly as is safe and
For period of 12 hours, the sprinkler pump and practicable subject to a maximum of 45
drencher pump, if fitted. seconds, and
c An adequate fuel capacity for the emergency
4/5A3.3.8 Emergency Bilge Pump and Controls generator prime mover is to be provided.
For period of 12 hours, the emergency bilge pump and
all the equipment essential for the operation of 4/5A3.5.3 Accumulator Battery
electrically powered remote controlled bilge valves. Where the emergency source of electrical power is an
accumulator battery it is to be capable of:
4/5A3.3.9 Signaling Lamps and Whistle a Carrying the emergency electrical load without
For a period of 4 hours of intermittent operation: recharging while maintaining the voltage of the battery
a The daylight signaling lamps, if they have no throughout the discharge period within 12% above or
independent supply from their own accumulator below its nominal voltage;
battery, and b Automatically connecting to the emergency
b The craft's whistle, if electrically driven. switchboard in the event of failure of the main source
of electrical power, and
4/5A3.3.10 Craft on Short Duration Voyages c Immediately supplying at least those services
In a craft engaged regularly in voyages of short specified in 4/5A3.7.
duration, where an adequate standard of safety is
attained, a lesser period than the 18 hour period 4/5A3.5.4 Emergency Generator for Non-
specified in 4/5A3.3.2a, 4/5A3.3.2b, 4/5A3.3.3, and emergency Services
4/5A3.3.4 but not less than 5. Provided that suitable measures are taken for
safeguarding independent emergency operation under
4/5A3.5 Power Supply all circumstances, the emergency generator may be
used, exceptionally, and for short periods, to supply
4/5A3.5.1 General non-emergency circuits during blackout situation, dead
The emergency source of electrical power may be craft situation and routine use for testing. See also
either a generator or an accumulator battery in 4/5A3.9.5.
accordance with 4/5A3.5.2 or 4/5A3.5.3 below:
4/5A3.7 Transitional Source of Power
4/5A3.5.2 Generator
Where the emergency source of electrical power is a The transitional source of emergency electrical power
generator, it is to be: where required by 4/5A3.5.2.b2 is to consist of an
a Driven by a prime mover with an independent accumulator battery which is to operate without
supply of fuel, having a flashpoint (closed cup test) of recharging while maintaining the voltage of the battery
throughout the discharge period within 12% above or
not less than 43 oC (110 oF)*, and below its nominal voltage and be of sufficient capacity
and is to be so arranged as to supply automatically in
* Fuel with a lower flashpoint, but not lower than 35°C, may be
used in gas turbines only subject to compliance with the
the event of failure of either the main or the emergency
provisions specified in 4/3.9. source of electrical power at least the following
services if they depend upon an electrical source for
b 1) Started automatically upon failure of the main their operation:
source of electrical power supply and 1 For a period of half an hour, the lighting required
connected automatically to the emergency by 4/5A3.3.2. For this transitional phase, the required
switchboard - then, those services referred to emergency electric lighting, in respect of the machinery
in 4/5A3.7 are to be connected automatically space and accommodation and service spaces may be
to the emergency generator as quickly as is provided by permanently fixed, individual,
safe and practicable subject to a maximum of automatically charged, relay operated accumulator
45 seconds, or lamps, and
2 All services required by 4/5A3.3.3a through
4/5A3.3.3d and 4/5A3.3.9.

PART 4 SECTION 5|10 Electrical Installations -- Part A. Systems


3 With respect to the watertight doors: 4/5A3.11 Arrangements for Periodic Testing
a Power to operate the watertight doors, but not
necessarily simultaneously, unless an Provision is to be made to enable the periodic testing of
independent temporary source of stored the complete emergency system and is to include the
energy is provided. The power source testing of automatic starting arrangements.
should have sufficient capacity to operate
each door at least three times, i.e. closed - 4/5A3.13 Craft Intended to Carry Passengers
open - closed, against an adverse list of 15°,
and See 5/1.13.
b Power to the control, indication and alarm
circuits for the watertight doors for half an 4/5A3.15 Starting Arrangements for Emergency
hour. Generator Sets

4/5A3.9 Emergency Switchboard 4/5A3.15.1 Cold Conditions


Emergency generating sets are to be capable of being
4/5A3.9.1 General readily started in their cold condition at a temperature
The emergency switchboard is to be installed as near as of 0 oC (32 oF). If this is impracticable, or if lower
is practicable to the emergency source of electrical temperatures are likely to be encountered, heating
power. arrangements are to be provided for ready starting of
the generating sets.
4/5A3.9.2 Emergency Switchboard for Generator
Where the emergency source of electrical power is a 4/5A3.15.2 Number of Starts
generator, the emergency switchboard is to be located Each emergency generator that is arranged to be
in the same space unless the operation of the automatically started is to be equipped with approved
emergency switchboard would thereby be impaired. starting devices with a stored energy capability of at
least three consecutive starts. Unless a second
4/5A3.9.3 Accumulator Battery independent means of starting is provided, the source
No accumulator battery fitted in accordance with of stored energy is to be protected to preclude critical
4/5A3.5.3 or 4/5A3.7 is to be installed in the same depletion by automatic starting system, i.e., the
space as the emergency switchboard. An indicator is to automatic starting system is only allowable for
be mounted on the main switchboard or in the consumption of the stored energy source to a level that
machinery control room to indicate when these would still provide the capability for starting the
batteries are being discharged. emergency generator upon intervention by a personnel.
In addition, a second source of energy is to be provided
4/5A3.9.4 Interconnector Feeder Between for an additional three starts within 30 minutes unless
Emergency and Main Switchboards manual starting can be demonstrated to be effective to
The emergency switchboard is to be supplied during the Surveyor.
normal operation from the main switchboard by an
interconnector feeder which is to be protected at the 4/5A3.15.3 Charging of Stored Energy
main switchboard against overload and short circuit. The stored energy is to be maintained at all times, as
The interconnector feeder is to be disconnected follows:
automatically at the emergency switchboard upon a Electrical and hydraulic starting systems are to be
failure of the main source of electrical power. Where maintained from the emergency switchboard;
the system is arranged for feedback operation, the b Compressed air starting systems may be
interconnector feeder is also to be protected at the maintained by the main or auxiliary compressed air
emergency switchboard against short circuit. In receivers through a suitable non-return valve or by an
addition, the circuit protection device at the emergency emergency air compressor which, if electrically driven,
switchboard on the interconnector feeder is to trip to is supplied from the emergency switchboard;
prevent overloading of the emergency generator. c All of these starting, charging and energy storing
devices are to be located in the emergency generator
4/5A3.9.5 Disconnection of Non-emergency Circuits space; these devices are not to be used for any purpose
For ready availability of the emergency source of other than the operation of the emergency generating
electrical power, arrangements are to be made where set. This does not preclude the supply to the air
necessary to disconnect automatically non-emergency receiver of the emergency generating set from the main
circuits from the emergency switchboard so that or auxiliary compressed air system through the non-
electrical power is to be available automatically to the return valve fitted in the emergency generator space.
emergency circuits.

PART 4 SECTION 5|11 Electrical Installations -- Part A. Systems


4/5A3.15.4 Manual Starting 4/5A3.19 Requirements by the Governmental
Where automatic starting is not required as per Authority
4/5A3.5.2b2, manual (hand) starting is permissible,
such as manual cranking, inertia starters, manually Attention is directed to the requirements of the
charged hydraulic accumulators, or power charge governmental authority of the country, whose flag the
cartridges, where they can be demonstrated as being craft flies, for the emergency services and the
effective to the Surveyor. accumulator batteries required in various types of
When manual (hand) starting is not practicable, the craft.
requirements of 4/5A3.15.2 and 4/5A3.15.3 are to be
complied with except that starting may be manually
initiated. 4/5A4 Distribution System

4/5A3.17 Cargo Craft Less Than 500 GT Having 4/5A4.1 Craft Service Distribution System
Electrical Plants of 75 kW and Above
4/5A4.1.1 General
4/5A3.17.1 General Current-carrying parts with potential to earth are to be
These requirements are intended for cargo craft less protected against accidental contact.
than 500 GT having electrical plants of an aggregate For recognized standard distribution systems, see 4/5.7.
capacity of 75 kW and above. The emergency source Separate feeders are to be provided for essential and
of electrical power is to be self-contained and readily emergency services.
available. 4/5A3.1.1, 4/5A3.1.2, 4/5A3.5 through During normal operation these consumers may be
4/5A3.13 and 4/5A3.19 are also applicable. Where the connected to the same power-bus directly or via
source of electrical power is a battery, see 4/5B2.7 for distribution boards or group starters, but should be
the installation. For emergency lighting, a relay- separated by removable links or other approved means.
controlled, battery-operated lanterns is acceptable. Each power-bus should be able to supply all equipment
necessary to maintain the control of propulsion,
4/5A3.17.2 Capacity steering control, navigation, lighting and ventilation,
The emergency source of electrical power is to be and allow starting of the largest essential electric motor
capable of supplying simultaneously at least the at any load. See 4/5C15.2.
following services for the period as specified herein: Where loss of a particular essential service would cause
a Emergency lighting for 6 hours for: serious risk to the craft, the service should be fed by at
1 At the stowage positions of life-saving least two independent circuits fed in such a way that no
appliances; single failure in the electrical supply or distribution
2 At all escape routes such as alleyways, systems would effect both supplies.
stairways, exits from accommodation and For cargo craft, in order to minimize the probability of
service spaces, embarkation points, etc.; compromising the craft’s safety due to failure of an
3 In the public spaces, if any; essential service, partial reduction in the capability
4 In the machinery spaces and main emergency from normal operation may be accepted; additionally,
generating spaces, including their control non-duplicated consumers of essential services
positions; connected to the emergency switchboard directly or via
5 In control stations; distribution boards may be accepted.
6 At the stowage positions for fireman' s outfits, Automatic load-dependent disconnection of non-
and essential consumers may be allowed.
7 At the steering gear;
b Navigation lights and other lights required by the 4/5A4.1.2 Method of Distribution
International Regulation for Preventing Collisions at The output of the craft's service generators may be
Sea in force. supplied to the current consumers by way of either
c For 6 hours, craft radio facilities and other loads branch system, meshed network system, or ring main
as set out in 14.12.2 of the IMO International Code of system. The cables of a ring-main or other looped
Safety for High-speed Craft. circuit (e.g. interconnecting section boards in a
d For 6 hours, electrical internal communication continuous circuit) are to be formed of conductors
equipment for announcements during evacuation. having sufficient current-carrying and short-circuit
capacity for any possible load and supply
configuration.

PART 4 SECTION 5|12 Electrical Installations -- Part A. Systems


Distribution systems should be so arranged that the 4/5A4.1.9 Circuits for Bunker or Cargo Space
feeders from the main and emergency sources are All lighting and power circuits terminating in a bunker
separated both vertically and horizontally as widely as or cargo space are to be provided with a multiple pole
practicable. switch outside the space for disconnecting such
circuits.
4/5A4.1.3 Through-feed Arrangements
The size of feeder conductors is to be uniform for the 4/5A4.3 Hull Return System
total length, but may be reduced beyond any
intermediate section board and distribution board, 4/5A4.3.1 General
provided that the reduced size section of the feeder is The hull return system is not to be used for power,
protected by an overload device. heating, or lighting except that the following systems
may be used:
4/5A4.1.4 Motor Control Center 1 impressed current cathodic protective systems;
Feeder cables from the main switchboard or any section 2 limited and locally earthed systems, provided
board to the motor control centers are to have a that any possible resulting current does not
continuous current-carrying capacity not less than flow directly through any hazardous areas, or
100% of the sum of the nameplate ratings of all the 3 insulation level monitoring devices, provided
motors supplied. The over-current protective device is the circulation current does not exceed 30 mA
to be in accordance with 4/5A5.1.3. under all possible conditions.
Current-carrying parts with potential to earth are to be
4/5A4.1.5 Motor Branch Circuit protected against accidental contact.
A separate circuit is to be provided for each fixed
motor having a full-load current rating of 6 amperes or 4/5A4.3.2 Final Subcircuits and Earth Wires
more and the conductors are to have a carrying capacity Where the hull return system is used, all final
of not less than 100% of the motor full-load current subcircuits, i.e., all circuits fitted after the last
rating. No branch circuit is to have conductors less than protective device, are to consist of two insulated wires,
1.5 mm2 wire. Circuit-disconnecting devices are to be the hull return being achieved by connecting to the hull
provided for each motor branch circuit and to be in one of the busbars of the distribution board from which
accordance with 4/5B2.13.2 and 4/5C4.17.2. they originate. The earth wires are to be in accessible
locations to permit their ready examination and to
4/5A4.1.6 Power Supply Through Transformers enable their disconnection for testing of insulation.
and Converters
4/5A4.5 Earthed Distribution Systems
a Continuity of Supply Where transformers or
converters are an essential part of the propulsion or System earthing is to be effected by means independent
craft service electrical supply system, the system is to of any earthing arrangements of the non-current-
be so arranged as to ensure at least the same continuity carrying parts. Means of disconnection is to be
of the supply as required by 4/5A2.1.2 for generators. provided in the neutral earthing connection of each
b Arrangements Each required transformer is to generator so that the generator may be disconnected for
be located as a separate unit with separate enclosure or maintenance. In distribution systems with neutral
equivalent, and is to be served by separate circuits on earthed or for generators intended to be run with
the primary and secondary sides. Each of the secondary neutrals interconnected, the machines are to be
circuits is to be provided with a multipole isolating designed to avoid circulating currents exceeding the
switch. A circuit breaker provided in the secondary prescribed value. Transformer neutral is not to be
circuit in accordance with 4/5A5.15.1 will be earthed unless all corresponding generator neutrals are
acceptable in lieu of multipole isolating switch. disconnected from the system (e.g. during shore
supply).
4/5A4.1.7 Ventilation System
Ventilation fans for cargo space are to have feeders 4/5A4.7 External or Shore Power Supply
separate from those for accommodations. Connection

4/5A4.1.8 Heating Appliances 4/5A4.7.1 General


Each heater is to be connected to a separate final Where arrangements are made for the supply of
subcircuit. However, a group of up to 10 heaters whose electricity from a source on shore or other external
total current does not exceed 16 A may be connected to source, a termination point is to be provided on the
a single final subcircuit. craft for the reception of the flexible cable from the
external source. Fixed cables of adequate rating are to
be provided between the termination point and the main

PART 4 SECTION 5|13 Electrical Installations -- Part A. Systems


or emergency switchboard. Means for disconnecting Additionally, when a protective device is a fuse, it is to
the external or shore power supply are to be provided be placed on the load side of the disconnect switch
at the receiving switchboard. See 4/5A5.11 for the serving the protected circuit.
protection of external or shore power supply circuit.
4/5A5.1.2 Protection Against Short-circuit
4/5A4.7.2 Earthing Terminal a Protective Devices Protection against short-
An earth terminal is to be provided for connecting the circuit is to be provided for each non-earthed conductor
hull to an external earth. by means of circuit breakers or fuses.
b Rated Short-circuit Breaking Capacity The
4/5A4.7.3 Indicators rated short-circuit breaking capacity of every protective
The external supply connection or shore connection is device is not to be less than the maximum available
to be provided with a pilot lamp and a voltmeter (and fault current at that point. For alternating current
frequency meter for A.C.) at main or emergency (A.C.), the rated short-circuit breaking capacity is not
switchboard to show energized status of the cable. to be less than the root mean square (r.m.s.) value of
the A.C. component of the prospective short-circuit
4/5A4.7.4 Polarity or Phase Sequence current at the point of application. The circuit breaker
Means are to be provided for checking the polarity (for is to be able to break any current having an A.C.
D.C.) or the phase sequence (for three-phase A.C.) of component not exceeding its rated breaking capacity,
the incoming supply in relation to the craft's system. whatever the inherent direct current (D.C.) component
may be at the beginning of the interruption.
4/5A4.7.5 Information Plate c Rated Short-circuit Making Capacity The rated
An information plate is to be provided at or near the short-circuit making capacity of every switching device
connection box giving full information on the system of is to be adequate for maximum peak value of the
supply and the nominal voltage (and frequency if A.C.) prospective short-circuit current at the point of
of the craft's system and the recommended procedure installation. The circuit breaker is to be able to make
for carrying out the connection. the current corresponding to its making capacity
without opening within a time corresponding to the
4/5A4.7.6 Securing of Trailing Cable maximum time delay required.
Provision is to be made for securing the trailing cable
to a framework to absorb stress on the electrical 4/5A5.1.3 Protection Against Overload
terminals by catenary tension of the cable. a Circuit Breakers Circuit breakers or other
mechanical switching devices for overload protection
are to have a tripping characteristics (overload-trip
4/5A5 Circuit Protection System time) adequate for the overload capacity of all elements
in the system to be protected and for any discrimination
4/5A5.1 System Design requirements.
b Fuses The fuse of greater than 320 amperes is
4/5A5.1.1 General not to be used for overload protection.
Electrical installations are to be protected against c Rating Fuse ratings and rating (or settings, if
accidental overload, including short circuit, by adjustable) of time-delay trip elements of circuit
automatic protective devices for : breakers are not to exceed the rated current capacity of
a Continued supply to remaining essential circuits the conductor to be protected as listed in Table 4/5C.10
in the event of a fault. except as otherwise permitted for generator, motor, and
b Minimizing the possibility of damage to the transformer circuit protection in 4/5A5.3, 4/5A5.13 and
system and fire. 4/5A5.15. If the standard ratings or settings of overload
Three-phase, three-wire alternating current circuits are devices do not correspond to the rating or the setting
to be protected by a triple-pole circuit breaker with allowed for conductors, the next higher standard rating
three overload trips or by a triple-pole switch with a or setting may be used provided it does not exceed
fuse in each phase. All branch circuits are to be 150% of the allowable current carrying capacity of the
protected at distribution boards only and any reduction conductor. Except as otherwise permitted for motor and
in conductor sizes is to be protected. Dual-voltage transformer branch-circuit protection, adjustable-trip
systems having a earthed neutral are not to have fuses circuit breakers of the time-delay or instantaneous type
in the neutral conductor, but a circuit breaker which are to be set to operate at not more than 150% of the
simultaneously opens all conductors may be installed rated capacity of the conductor to be protected.
when desired. In no case is the dual-voltage system to d Indication The rating or setting of the overload
extend beyond the last distribution board. protective device for each circuit is to be permanently
indicated at the location of the protective device.

PART 4 SECTION 5|14 Electrical Installations -- Part A. Systems


4/5A5.1.4 Cascade System (Back-up Protection) 4/5A5.3.2 Trip Setting for Coordination
a General Where a circuit breaker does not have a The instantaneous and short-time overcurrent trips of
short circuit breaking and/or making capacity at least the generators are to be set at the lowest values of
equal to the maximum prospective short-circuit current current and time which will coordinate with the trip
at the point where it is installed, it is to be backed-up settings of feeder circuit breakers. See also 4/5A5.1.5.
by fuse or by a circuit breaker on the generator side,
having at least the necessary short-circuit rating for the 4/5A5.3.3 Load-shedding Arrangements
available fault at the point of application. The In order to safeguard electrical power supply for
upstream circuit breaker or fuse is to be specifically essential services, load-shedding arrangements to
approved for back-up combinations with the disconnect non-essential services are to be provided in
downstream circuit breaker and maximum fault rating the following cases.
for the combinations is to be provided. Cascading a Where one generating set is normally used to
arrangements exclude generator circuit breakers. supply the required load, but where the possibility exits
b Application Downstream circuit breakers having that due to the switching on of additional loads,
short circuit ratings less than the short circuit current whether manually or automatically initiated, the total
available at the point of application, will be specially load exceeds the rated generator capacity.
considered for non-essential circuits and for essential b Where in case of failure of one of the parallel
circuits where automatic transfer to a duplicate circuit running generators, the total load exceeds the
is utilized. The same fuse or circuit breaker may back- connected capacity of the remaining generator(s).
up more than one circuit breaker when essential
services are not involved. 4/5A5.3.4 Emergency Generator
The emergency generator is also to comply with
4/5A5.1.5 Coordinated Tripping 4/5A5.1, 4/5A5.3, 4/5A5.5 and 4/5A5.7 where
Coordinated tripping is to be provided between applicable. See also 4/5A3.9.
generator, bus tie, bus feeder and feeder protective
devices. See also 4/5A5.3.2 and 4/5A5.7.1. Except for 4/5A5.5 Protection for Alternating-current (A.C.)
cascade system (backup protection) in 4/5A5.1.4, the Generators
coordinated tripping is also to be provided between
feeder and branch-circuit protective devices for 4/5A5.5.1 Short-time Delay Trip
essential services. Continuity of service to essential Short-time delay trip are to be provided with circuit
circuits under short-circuit conditions is to be achieved breakers for A.C. generator. For generators with a
by discrimination of the protective devices as follows: capacity of less than 200 kW having prime movers such
a The tripping characteristics of protective devices as diesel engines or gas turbines which operate
in series is to be coordinated. independently of the electrical system, consideration
b Only the protective device nearest to the fault is will be given to omission of short-time delay trips if
to open the circuit except for cascade system (back-up instantaneous and long time delay trips are provided.
protection) as specified in 4/5A5.1.4a.
c The protective devices are to be capable of 4/5A5.5.2 Parallel Operation
carrying, without opening, a current not less than the Where A.C. generators are arranged for parallel
short-circuit current at the point of application for a operation with other A.C. generators, the following
time corresponding to the opening of the breaker, protective devices are to be provided.
increased by the time delay required for discrimination. a Instantaneous Trip Instantaneous trips are to be
installed and set in excess of the maximum short-circuit
4/5A5.3 Protection for Generators contribution of the individual generator where three or
more generators are arranged for parallel operation.
4/5A5.3.1 General b Reverse Power Protection A time-delayed
Generators of less than 25 kW not arranged for parallel reverse active power protection or other devices which
operation may be protected by fuses. Any generators provide adequate protection is to be provided. The
arranged for parallel operation and all generators of 25 setting of protective devices is to be in the range 2% to
kW and over are to be protected by a trip-free circuit 6% of the rated power for turbines and in the range 8%
breaker whose trip settings are not to exceed the to 15% of the rated power for diesel engines. A fall of
thermal withstand capacity of the generator. The long- 50% in the applied voltage is not to render the reverse
time over-current protection is not to exceed 15% power protection inoperative, although it may alter the
above either the full-load rating of continuous-rated setting to open the breaker within the above range.
machines or the overload rating of special-rated c Undervoltage Protection Means are to be
machines. The shutting down of the prime mover is to provided to prevent the generator circuit breaker from
cause the tripping of the craft’s service generator closing if the generator is not generating, and to open
circuit breaker. the same when the generator voltage collapses.

PART 4 SECTION 5|15 Electrical Installations -- Part A. Systems


In the case of an undervoltage release provided for this 4/5A5.11 Protection for External or Shore Power
purpose, the operation is to be instantaneous when Supply
preventing closure of the breaker, but is to be delayed
for discrimination purposes when tripping a breaker. 4/5A5.11.1 General
Where arrangements are made for the supply of
4/5A5.7 Protection for Direct Current (D.C.) electricity from a source on shore or other external
Generators source, permanently fixed cables from the external
supply or shore connection box to the main or
4/5A5.7.1 Instantaneous Trip emergency switchboard are to be protected by fuses or
D.C. generator circuit breakers are to be provided with circuit breakers located at the connection box.
an instantaneous trip set below the generator maximum
short-circuit current and are to coordinate with the trip 4/5A5.11.2 Interlocking Arrangement
settings of feeder circuit breakers supplied by the Where the generator is not arranged for parallel
generator. operation with the external or shore power supply, an
interlocking arrangement is to be provided for the
4/5A5.7.2 Parallel Operation circuit breakers or disconnecting devices between
a Reverse Current Protection D.C. generators generator and the external or shore power supply in
arranged for parallel operation with other D.C. order to safeguard from connecting unlike power
generators or with an accumulator battery are to be sources to the same bus.
provided with instantaneous or short-time delayed
reverse current protection. The setting of the protection 4/5A5.13 Protection for Motor Branch Circuits
devices is to be within the power range specified by
4/5A5.5.2b. When the equalizer connection is 4/5A5.13.1 General
provided, the reverse current device is to be connected Trip elements of circuit breaker for starting and for
on the pole opposite to the equalizer connection where short-circuit protection are to be in accordance with
the series compound winding for the generator is 4/5A5.13.2 or 4/5A5.13.3 except that circuit breakers
connected. Reverse current protection is to be adequate having only instantaneous trips may be provided as part
to deal effectively with reverse current conditions of the motor control center. Where circuit breakers
emanating from the distribution system (e.g., electric having only instantaneous trips are provided, the motor
driven cargo winches). running protective device is to open all conductors, and
b Generator Ammeter Shunts Generator ammeter the motor controller is to be capable of opening the
shunts are to be so located that the ammeters indicate circuit without damage to itself resulting from a current
total generator current. up to the setting of the circuit breaker. Circuit-
c Undervoltage Protection Requirements for A.C. disconnecting devices are to be provided for each
generator in 4/5A5.5.2c are also applicable to D.C. motor branch circuit and to be in accordance with
generator. 4/5B2.13.2 and 4/5C4.17.2.

4/5A5.9 Protection for Accumulator Batteries 4/5A5.13.2 Direct-current Motor Branch Circuits
The maximum fuse rating or the setting of the time-
Accumulator (storage) batteries, other than engine delay trip element is to be 150% of the full-load rating
starting batteries, are to be protected against overload of the motor served. If that rating or setting is not
and short circuits by devices placed as near as available, the next higher available rating or setting
practicable to the batteries but outside of the battery may be used.
rooms, lockers or boxes, except that the emergency
batteries supplying essential services are to have short 4/5A5.13.3 Alternating-current Motor Branch
circuit protection only. Fuses may be used for the Circuits
protection of emergency lighting storage batteries The maximum fuse rating or setting of the trip element
instead of circuit breakers up to and including 320 is to be the value stated below. If that rating or setting
amperes rating. The charging equipment, except is not available, the next higher available rating or
converters, for all batteries with a voltage more than setting may be used.
20% of the line voltage is to be provided with reverse
current protection.

PART 4 SECTION 5|16 Electrical Installations -- Part A. Systems


can be fed into secondary windings, short-circuit
Rating or Setting protection (i.e., short-time delay trips) is to be provided
Type of Motor in % Motor Full- in the secondary connections.
load Current
4/5A5.17 Protection for Meters, Pilot Lamps, and
Squirrel-cage and Synchronous 250 Control Circuits
Full-voltage, Reactor or Resistor-
starting Indicating and measuring devices are to be protected by
Autotransformer Starting 200 means of fuses or current limiting devices. For devices
such as voltage regulators where interruption of the
Wound Rotor 150
circuit may have serious consequences, fuses are not to
be used. If fuses are not used, means are to be provided
When fuses are used to protect polyphase motor
to prevent fire in unprotected part of installation. Fuses
circuits, it is to be arranged to protect against single-
are to be placed as near as possible to the tapping from
phasing.
the supply.
The setting of magnetic instantaneous trips for short-
circuit protection only is to exceed the transient current
4/5A6 Systems for Steering Gear
inrush of the motor, and to be the standard value
nearest to, but not less than, 10 times full-load motor
4/5A6.1 Power Supply Feeder
current.
Each electric or electrohydraulic steering gear is to be
4/5A5.13.4 Motor Running Protection served by at least two exclusive circuits fed directly
Running protection is to be provided for all motors
from the main switchboard; however, one of the
having a power rating exceeding 0.5 kW except that
circuits may be supplied through the emergency
such protection is not to be provided for steering gear
switchboard. An auxiliary electric or electrohydraulic
motors (see 4/5A6.3). The running protection is to be
steering gear associated with a main electric or
set between 100% and 125% of the motor rated current.
electrohydraulic steering gear may be connected to one
of the circuits supplying this main steering gear. The
4/5A5.13.5 Protection for Undervoltage
circuits supplying an electric or electrohydraulic
The motor controller for motors having power rating
steering gear are to have adequate rating for supplying
exceeding 0.5 kW is to provide protection against low
all motors, control systems and instrumentation which
voltage. Undervoltage release is to be provided on
are normally connected to them and operated
controllers for auxiliaries which are essential to the
simultaneously. The circuits are to be separated
operation of the propulsion equipment where the
throughout their length as widely as is practicable.
automatic restart after a voltage failure is not
hazardous. Otherwise undervoltage protection is to be
4/5A6.3 Protection for Steering Gear Circuit
used. The use of controllers of the undervoltage release
type is to be limited to avoid excessive starting current
4/5A6.3.1 Short Circuit Protection
when a group of motors with undervoltage release Each steering gear feeder is to be provided with short-
controllers are restarted automatically upon regaining circuit protection which is to be located at the main or
the voltage. emergency switchboard. Long term overcurrent
protection is not to be provided for steering gear
4/5A5.15 Protection for Transformer Circuits motors.
a Direct Current (D.C.) Motors For D.C. motors,
4/5A5.15.1 Setting of Overcurrent Device
the feeder circuit breaker is to be set to trip
Each power and lighting transformer feeder is to be
instantaneously at not less than 300% and not more
protected by an overcurrent device rated or set at a
than 375% of the rated full-load current of the steering
value not more than 125% of rated primary current.
gear motor, except that the feeder circuit breaker on the
When a transformer is provided with an overcurrent
emergency switchboard may be set to trip at not less
device in the secondary circuit rated or set at not more
than 200%.
than 125% of rated secondary current, the feeder
b Alternating Current (A.C.) Motors For A.C.
overcurrent device may be rated or set at a value less
motors, the protection against excess current, including
than 250% of the rated primary current.
starting current, if provided, is to be for not less than
twice the full load current of the motor or circuit so
4/5A5.15.2 Parallel Operation
protected, and is to be arranged to permit the passage
When the transformers are arranged for parallel
of the appropriate starting currents.
operation, means are to be provided to disconnect the
transformer from the secondary circuit. Where power

PART 4 SECTION 5|17 Electrical Installations -- Part A. Systems


c Fuses as Motor-feeder Protection The use of emergency source of electrical power, associated
fuses instead of circuit breakers for steering gear motor transforming equipment, if any, the emergency
feeder short circuit protection is not permitted. switchboard and the emergency lighting switchboard
will not render the main electric lighting system
4/5A6.3.2 Undervoltage Release required by 4/5A7.1.1 inoperative.
Power unit motor controllers and other automatic motor
controllers are to be fitted with undervoltage release. 4/5A7.1.3 Lighting Circuits
a Machinery Space and Accommodation Space
4/5A6.5 Emergency Power Supply In spaces such as :

Where the rudder stock is required by 3/5.3.1 to be - public spaces;


over 230 mm (9 in.) diameter using Ks = 1.0 in way of - main machinery spaces;
the tiller, excluding strengthening for navigation in ice, - galleys;
an alternative power supply, sufficient at least to supply - corridors;
the steering gear power unit and also its associated - stairways leading to boat-decks;
control system and rudder angle indicator, is to be
provided automatically, within 45 seconds either from there are to be more than one final sub-circuit for
the emergency source of electrical power or from an lighting, one of which may be supplied from the
independent source of power located in the steering emergency switchboard, in such a way that failure of
gear compartment. The steering gear power unit under any one circuit does not leave these spaces in darkness.
alternative power supply is to be capable of moving the b Cargo Spaces Fixed lighting circuits in cargo
rudder from 15 degrees on one side to 15 degrees on spaces are to be controlled by multipole-linked
the other side in not more than 60 seconds with the switches situated outside the cargo spaces. Means are
craft at the design draft while running at one half the to be provided on the multipole linked switches to
maximum speed ahead or 7 knots whichever is the indicate the live status of circuits.
greater. This independent source of power is to be used
only for this purpose. The alternative power supply is 4/5A7.1.4 Protection for Lighting Circuits
to have a capacity for at least 10 minutes of continuous Lighting circuits are to be protected against overload
operation. See 4/5A3.3.5. and short circuit. Overload protective devices are to be
rated or set at not more than 30 amperes. The
4/5A6.7 Controls, Instrumentation, and Alarms connected load is not to exceed the lesser of the rated
current carrying capacity of the conductor or 80% of
See 4/8.6. the overload protective device rating or setting. The
control switches are to be rated for the load controlled.

4/5A7 Lighting and Navigation Light Systems 4/5A7.3 Navigation Light System

4/5A7.1 Lighting System 4/5A7.3.1 Feeders


The masthead, side and stern lights are to be separately
4/5A7.1.1 Main Lighting System connected to a distribution board reserved for
A main electric lighting system is to provide navigation light, placed in an accessible position on
illumination throughout those parts of the craft bridge, and is connected directly or through
normally accessible to and used by passengers or crew. transformers to the main or emergency switchboard.
It is to be supplied from the main source of electrical These lights are to be fitted with duplicate lamps or
power. other dual light sources and are to be controlled by an
indicator panel. Provision is to be made on the bridge
4/5A7.1.2 System Arrangement for the navigation lights to be transferred to an
a Main Lighting System The arrangement of the alternative supply. See 4/5A3.3.2b for power supply.
main electric lighting system is to be such that a fire or
other casualty in spaces containing the main source of 4/5A7.3.2 Navigation Light Indicator
electrical power, associated transforming equipment, if Each navigation light as listed in 4/5A7.3.1 is to be
any, the main switchboard and the main lighting provided with an indicator panel which gives audible
switchboard, will not render the emergency electric and/or visual warning automatically in the event of
lighting system required by 4/5A3.3.2 of this Section extinction of the light. If an audible device is used, it is
or 5/1.13.3a1 or 5/1.13.3b1 inoperative. to be connected to a separate source of supply, for
b Emergency Lighting System The arrangement example a primary or accumulator (storage) battery. If
of the emergency electric lighting system is to be such a visual signal is used which is connected in series with
that a fire or other casualty in spaces containing the the navigation light, means are to be provided to

PART 4 SECTION 5|18 Electrical Installations -- Part A. Systems


prevent the extinction of the navigation light due to survival craft. The system should be such that flooding
failure of the visual signal. A means for disconnection or fire in any compartment does not render other parts
of each navigation light circuit is to be provided at the of the system inoperable.
indicator panel.
4/5A8.7 Emergency and Interior-communication
4/5A7.3.3 Protection Switchboard
Each navigation light as listed in 4/5A7.3.1 is to be
protected by a fuse in each insulated pole and provided Emergency and interior-communication switchboards,
with a double-pole switch or alternatively by a double- when fitted, are to comply with the applicable parts of
pole circuit breaker fitted on the distribution board or 4/5C4 and attention is directed to the requirements of
the indicator panel referred to above. The rating of the the governmental authority whose flag the craft flies.
fuses is to be at least twice that of the largest branch
fuse and greater than the maximum panel load.
4/5A9 Manually Operated Alarms

4/5A8 Interior Communication Systems 4/5A9.1 General Emergency Alarm System

4/5A8.1 Operating Compartment Each craft over 100 GT is to be fitted with a general
emergency alarm. The general emergency alarm
At least two independent means are to be provided for system is to be capable of sounding the general
communicating orders from the operating compartment emergency alarm signal consisting of seven or more
to the position in the machinery space or in the control short blasts followed by one long blast on the craft's
room from which the speed and direction of thrust of whistle or siren and additionally on an electrically
the propellers are controlled. Appropriate means of operated bell or klaxon or other equivalent warning
communication are to be provided to any other system, which is to be powered from the craft's main
positions from which the main propulsion machinery supply and the emergency source of electrical power
may be controlled. See 4/5A3.3.3a for power supply. required by 4/5A3, as appropriate. The system is be
capable of operation from the operating compartment
4/5A8.3 Voice Communications and, except for the craft's whistle, also from other
strategic points. The system is to be audible throughout
4/5A8.3.1 Propulsion and Steering Gear Control all the accommodation and normal crew working
Stations spaces and open decks, and its sound pressure level is
A common talking means of voice communication and to be at least 10 dB(A) above ambient noise levels
calling is to be provided between the operating under way in normal cruise operation. The alarm is to
compartment, main propulsion control station (if continue to function after it has been triggered until it is
fitted), and the steering gear compartment so that the manually turned off or is temporarily interrupted by a
simultaneous talking among these spaces is possible at message on the public address system.
all times and the calling to these spaces is always
possible even if the line is busy 4/5A9.3 Engineers' Alarm

4/5A8.3.2 Elevator An engineer's alarm operable from the main propulsion


Where an elevator is installed, a telephone is to be control station is to be provided on craft of 500 GT
permanently installed in all cars and connected to a and over. It is to be audible in all the accommodations
continuously manned area. The telephone may be and if provided, in the engineers' accommodation. See
sound powered, battery operated or electrically 4/5A3.3.9 for power supply.
powered from the emergency source of power.
4/5A9.5 Refrigerated Space Alarm
4/5A8.3.3 Independence of Power Supply Circuit
Final subcircuit for power supply to these voice Fan and diffuser rooms serving subfreezing
communication systems is to be independent of other compartments are to be provided with a device capable
electrical systems and control, monitoring, and alarm of activating an audible and visual alarm in a manned
systems. See 4/5A3.3.3a for power supply. control center and operable from within the latter space
for the protection of personnel. See 4/5A3.3.9 for
4/5A8.5 Public Address System power supply.

A public address system is to be provided. This system


is to cover all areas where passengers and crew have
access, escape route, and places of embarkation into

PART 4 SECTION 5|19 Electrical Installations -- Part A. Systems


4/5A9.7 Elevator b Machinery Space Ventilation The main
machinery-space ventilation is to be provided with
A device which will activate an audible and visual means for stopping the ventilation fans, which is to be
alarm in a manned control center is to be provided in located in the passageway leading to, but outside of the
all cars. Such alarm system is to be independent of space, or in a centralized fire-fighting location.
power and control systems of the elevator. See c Ventilation Other Than Machinery Space A
4/5A3.3.9 for power supply. control station for all other ventilation systems is to be
located in a centralized fire-fighting location or
4/5A10 Fire Protection and Fire Detection Systems operating compartment, or in an accessible position
leading to, but outside of the space ventilated.
4/5A10.1 Emergency Stop
4/5A10.1.2 Fuel Oil Units
4/5A10.1.1 Ventilation System See 4/6.49.3 and 4/9.5.3 for emergency tripping and
a General All electrical ventilation systems are to emergency stop for fuel oil units.
be provided with means for stopping the motors in case
of fire or other emergency. These requirements do not 4/5A10.3 Fire Detection and Alarm System
apply to closed re-circulating systems within a single
space. For passenger craft, the ventilation fans of each See 7.7.1 through 7.7.3 and 7.8.3 of the IMO
zone in the accommodation spaces are to be capable of International Code of Safety for High-speed Craft and
being independently control from a continuously 4/11.3.18c.
manned control station. See also 4/9.5.1.

PART 4 SECTION 5|20 Electrical Installations -- Part A. Systems


When the selection of the equipment has been
Part B. Installation finalized, a list identifying all equipment in the
hazardous areas, their degree of protection, rating,
manufacturer's name, model number and evidence of
4/5B1 Plans and Data to be Submitted certification is to be submitted. An approved copy of
this list/booklet is to be maintained on board for future
4/5B1.1 Booklet of Standard Details reference. See 1/3.3.1k5 and 4/5B7.1.4.
A booklet of the standard wiring practices and details
including such items as cable supports, earthing details,
4/5B2 Equipment Installation and Arrangement
bulkhead and deck penetrations, cable joints and
sealing, cable splicing, watertight and explosion-proof 4/5B2.1 General Consideration
connections to equipment, earthing and bonding
connections, etc., as applicable, is to be submitted. 4/5B2.1.1 Equipment Location
Where cable penetration methods for A- or B-class Electrical equipment is to be so placed or protected as
decks or bulkheads are shown, an evidence of approval to minimize the probability of mechanical injury or
by an Administration signatory to 1974 SOLAS as damage from the accumulation of dust, oil vapors,
amended is also to be submitted. steam or dripping liquids. Equipment liable to generate
arc is to be ventilated or placed in a compartment
4/5B1.3 Arrangement of Electrical Equipment ventilated to avoid accumulation of flammable gases,
acid fumes and oil vapors. See Table 4/5B.1 for
A general arrangement plan showing the location of at required degree of protection for various locations.
least the following electrical equipment is to be
submitted for review. 4/5B2.1.2 Protection from Bilge Water
All generators, motors and electric couplings are to be
- Generator, Essential Motor, and Transformer so arranged that they cannot be damaged by bilge
- Battery water; and, if necessary, a watertight coaming is to be
- Switchboard, Battery Charger, and Motor provided to form a well around the base of such
Controller equipment with provision for removing water from the
- Emergency Lighting Fixture well.
- General Emergency Alarm Device and Alarm
Actuator 4/5B2.1.3 Accessibility
- Detector, Manual Call Point and Alarm Panel for The design and arrangement of electrical apparatus is
Fire Detection and Alarm System to provide accessibility to parts requiring inspection or
- Certified-safe Type Equipment adjustment. Armature and field coils, rotors and
revolving fields are to be removable and where air
Where cable splices or cable junction boxes are ducts are used, there are to be means of access.
provided, locations of the splices and cable junction
boxes together with the information of their services 4/5B2.1.4 Special Requirements for Non-metallic
are also to be submitted for review. Craft
The following is applicable to non-metallic craft.
4/5B1.5 Electrical Equipment in Hazardous Areas a In order to minimize the risk of fire, structural
damage, electrical shock and radio interference due to
A plan showing hazardous areas is to be submitted for lightning strike or electrostatic discharge, all metal
review together with the following: parts of the craft are to be bonded together, in so far as
possible in consideration of galvanic corrosion between
- A list of intended electrical equipment in the dissimilar metals, to form a continuous electrical
indicated hazardous areas, including a description system, suitable for the earth return of electrical
of the equipment, applicable degree of protection equipment and to connect the craft to the water when
and ratings. See 4/5B7.3. waterborne. The bonding of isolated components
- For intrinsically-safe systems, also wiring plans, inside the structure is not generally necessary, except in
installation instructions with any restrictions fuel tanks. A lightning protection system consisting of a
imposed by the certification agency. copper spike, a conductor of a minimum cross-section
- Detail of installation for echo sounder, speed log, per 4/5B2.1.4b and a grounding plate of not less than
and impressed current cathodic protection system 450 cm2 (1 ft2) is to be installed. The spike is to
where located in these areas. project at least 150 mm (6 in.) above the uppermost
part of the craft, the conductor is to run clear of metal
objects and as straight as practicable, and the

PART 4 SECTION 5|21 Electrical Installations -- Part B. Installations


grounding plate is to be located so that it is immersed 4/5B2.5.2 Pump Motors
under all conditions of heel. Metallic rudders may be Motors for operating plunger and close-coupled pumps
used as grounding plates. are to have the driving end entirely enclosed or
b Primary conductors provided for lightning designed to prevent leakage from entering the motor.
discharge currents are to have a minimum cross-section
of 50 mm2 in copper or equivalent surge-carrying 4/5B2.5.3 Motors on Weather Decks
capacity in aluminum. Motors for use on weather decks are to have an
c Metallic pipes capable of generating electrostatic enclosure of at least IP56 protection or are to be
discharges, due to the flow of liquids and gases are to enclosed in watertight housings.
be bonded so as to be electrically continuous
throughout their length and are to be adequately 4/5B2.5.4 Motors Below Decks
earthed. Motors below decks are to be installed at a location as
d Secondary conductors provided for the dry as practicable and away from steam, water, and oil
equalization of static discharges, bonding of piping.
equipment, etc., but not for carrying lightning
discharges are to have a minimum cross-section of 5 4/5B2.7 Accumulator Batteries
mm2 copper or equivalent surge current carrying
capacity in aluminum. 4/5B2.7.1 General
e The electrical resistance between bonded objects The following requirements are applicable to
and the basic structure is not to exceed 0.05 ohm permanently installed power, control and monitoring
except where it can be demonstrated that a higher storage batteries of acid or alkaline types. Batteries are
resistance will not cause a hazard. The bonding path is to be so arranged that the trays are accessible and
to have sufficient cross-sectional area to carry the provided with not less than 254 mm (10 in.) headroom.
maximum current likely to be imposed on it without Where a relief valve is provided for discharging
excessive voltage drop. excessive gas due to overcharge, arrangements are to
f Each pressure refueling point is to be provided be made for releasing the gas to the weather deck away
with a means of bonding the fueling equipment to the from any source of ignition.
craft. Accumulator batteries are not to be located in crew
accommodation.
4/5B2.3 Generators
4/5B2.7.2 Battery Installation and Arrangements
All generators are to be located with their shafts in a a Large Batteries Large storage batteries, those
fore-and-aft direction on the craft and are to operate connected to a charging device with an output of more
satisfactorily in accordance with the inclination than 2 kW, are to be installed in a room assigned to the
requirements of 4/1.21. Where it is not practicable to battery only, but may be installed in a deck locker if
mount the generators with the armature shafts in the such a room is not available. No electrical equipment is
fore-and-aft direction, their lubrication will require to be installed in the battery rooms unless essential for
special consideration. Provision is to be made to the operational purposes and certified safe for battery
prevent oil or oil vapor from passing into the machine room atmosphere (See 4/5B7.1).
windings. b Moderate-size Batteries Batteries of moderate
size, those connected to a charging device with a power
4/5B2.5 Craft Service Motors output of 0.2 kW up to and including 2 kW, may be
installed in the battery room or may be installed in
4/5B2.5.1 General battery lockers or deck boxes in the emergency
Motors for use in the machinery space above the floor generator room, machinery space or other suitable
plate or spaces where subject to mechanical injury, or location. Cranking batteries are to be located as closely
dripping of oil or water are to have an enclosure of at as possible to the engine or engines served.
least IP22 protection in accordance with Table 4/5B.1. c Small Batteries Small batteries are to be
However where they are protected by drip covers, they installed in a battery box and may be located as
may have an enclosure of the lower protection grade desired, except they are not to be located in sleeping
than IP22. The motors having a protection enclosure of quarters unless hermetically sealed.
IP22 or lower are to be installed at a location high d Battery Trays Trays for batteries are to be
enough to avoid bilge water. Motors below the level of chocked with wood strips or equivalent to prevent
the floor plates are to have an enclosure of at least IP44 movement and each tray is to be fitted with
protection. Where motors intended for service at sea nonabsorbent insulating supports on the bottom and
are not mounted with the rotor shafts in the fore-and-aft with similar spacer blocks at the sides or with
direction, the type of bearing and lubrication will equivalent provision to secure air-circulation space all
require special consideration. around each tray.

PART 4 SECTION 5|22 Electrical Installations -- Part B. Installations


e Identification of Battery Types Lead-acid 4/5B2.9 Switchboard
batteries and alkaline batteries, when placed in the
same battery compartment, are to be effectively Switchboards are to be so arranged as to give easy
identified as to type and segregated. access as may be needed to apparatus and equipment,
without danger to personnel. Switchboards are to be
4/5B2.7.3 Ventilation located in a dry place so as to provide a clear working
a Battery Rooms Battery rooms are to be space of at least 914 mm (36 in.) at the front of the
ventilated to avoid accumulation of flammable gas. switchboard and a clearance of at least 610 mm (24 in.)
at the rear which may be reduced to 457 mm (18 in.) in
Natural ventilation may be employed if ducts are run
way of stiffeners or frames except that, for
directly from the top of the battery room to the open air
switchboards which are enclosed at the rear and are
above. fully serviceable from the front, clearance at the rear
If natural ventilation is impractical, mechanical exhaust will not be required unless necessary for cooling.
ventilation is to be provided with fan intake at the top Switchboards are to be secured to a solid foundation.
of the room. Fans are to be of non-sparking They are to be self-supported, or be braced to the
construction in accordance with 4/5B7.7 and capable of bulkhead or the deck above. In case the last method is
completely changing the air in the battery room in not used, means of bracing is to be flexible to allow
more than two minutes. Alternatively, a lesser deflection of the deck without buckling the assembly
ventilation rate may be considered, provided that structure.
satisfactory calculations are submitted substantiating
that adequate ventilation is available to maintain the
4/5B2.11 Distribution boards
flammable gases within the battery room to a level
below the lower explosive limit (L.E.L.) at the
maximum battery charging current. Where the 4/5B2.11.1 Location and Protection
ventilation rate is based on low hydrogen emission Distribution boards are to be located in accessible
type batteries, a warning notice to this effect is to be positions and not in such spaces as bunkers,
provided in a visible place in the battery room. storerooms, cargo holds or compartments allotted
Openings for air inlet are to be provided near the floor. alternately to passengers or cargo. Distribution boards
b Battery Lockers Battery lockers are to be are to have approved non-combustible non-hygroscopic
ventilated, if practicable, similarly to battery rooms by enclosures. Metal enclosures and all exposed metal
a duct led from the top of the locker to the open air or parts in non-metallic enclosures are to be earthed to the
to an exhaust ventilation duct. Louvers or equivalent craft's structure. All cases are to be of adequate
are to be provided near the bottom for entrance of air. mechanical strength.
c Deck Boxes Deck boxes are to be provided with
a duct from the top of the box, terminating in a goose 4/5B2.11.2 Switchboard-type Distribution boards
neck, mushroom head or equivalent to prevent entrance Distribution boards of the switchboard type, unless
of water. Holes for air inlet are to be provided on at installed in machinery spaces or in compartments
least two opposite sides of the box. The entire deck assigned exclusively to electric equipment and
box, including openings for ventilation, is to be accessible only to authorized personnel, are to be
weathertight to prevent entrance of spray or rain. completely enclosed or protected against accidental
d Small Battery Boxes Boxes for small batteries contact and unauthorized operation.
require no ventilation other than openings near the top
to permit escape of gas. 4/5B2.11.3 Safety-type Panels
If the method of operation demands the handling of
switches by persons unfamiliar with electrical
4/5B2.7.4 Protection from Corrosion
equipment, the distribution board is to be of the safety
The interiors of battery rooms, including the structural
type; this type of distribution board is to be used for
parts and shelves therein, as well as ventilation inlets controlling branch lighting circuits. Dead front type
and outlets are to be painted with corrosion-resistant panels are to be used where voltage to earth is in excess
paint. Shelves in battery rooms or lockers for acid of 55 volts D.C. or 55 volts A.C. r.m.s. between
batteries are to have a watertight lining of sheet lead conductors.
not less than 1.6 mm (1/16 in.) on all sides. For alkaline
batteries the shelves are to be similarly lined with steel 4/5B2.13 Motor Controllers and Control Centers
not less than 0.8 mm (1/32 in.) thick. Alternatively, a
battery room may be fitted with a watertight lead pan, 4/5B2.13.1 Location and Installation
steel for alkaline batteries, over the entire deck, carried Motor control centers are to be located in a dry place.
up not less than 152 mm (6 in.) on all sides. Deck Clear working space is to be provided around motor
boxes are to be lined in accordance with the above control centers to enable doors to be fully opened and
alternative method. Boxes for small batteries are to be equipment removed for maintenance and replacement.
lined to a depth of 76 mm (3 in.) consistent with the Motor control centers are to be secured to a solid
methods described above. foundation, be self-supported, or be braced to the
bulkhead.

PART 4 SECTION 5|23 Electrical Installations -- Part B. Installations


4/5B2.13.2 Disconnecting Arrangements 4/5B2.19 Heating Equipment
a Device Means are to be provided for
disconnecting the motor and controller from all supply Electric radiators, if used, are to be fixed in position
conductors, except that a manually operated switch or and be so constructed as to reduce fire risks to a
circuit breaker may serve as both controller and minimum. Electric radiators of the exposed-element
disconnecting means (see 4/5C4.17.2). type are not to be used.
b Location The disconnecting device may be in
the same enclosure with the controller, or may be in a 4/5B2.21 Magnetic Compasses
separate enclosure, and is to be externally operated.
The branch-circuit switch or circuit breaker on the Precautions are to be taken in connection with
power-distribution board or switchboard may serve as apparatus and wiring in the vicinity of the magnetic
the disconnect device if in the same compartment with compass to prevent disturbance of the needle from
the controller. external magnetic fields.
c Locking Means If the disconnecting device is
not within sight of both motor and controller, or if it is 4/5B2.23 Portable Equipment and Outlets
more than 15.25 m (50 ft) from either, it is to be Portable equipment are not to be used in hazardous
arranged for locking in the open position. Where a areas nor are portable lights to be used for berth lights
remote control is required for a motor, this locking in passenger accommodations or crew’s quarters.
device is not to be provided for the local start or stop
switch at the machine side and is to be provided at the 4/5B2.25 Receptacles and Plugs of Different
feeder circuit breaker for such motor. Ratings
d Identification Plate The disconnect switch, if
not adjacent to the controller, is to be provided with an Receptacles and plugs of different electrical ratings are
identification plate. not to be interchangeable. In cases where it is necessary
e Open and Close Indications The disconnect to use 230 volts portable equipment, the receptacles for
device is to indicate by a position of the handle, or their attachment are to be of a type which will not
otherwise, whether it is open or closed. permit attaching 115 volts equipment.

4/5B2.13.3 Indicating-light Circuits


Where indicating-light circuits are employed, their 4/5B3 Cable Installation
potential is to be limited to 150 volts if the opening of
the foregoing disconnecting devices does not de- 4/5B3.1 General Considerations
energize the indicating circuit.
4/5B3.1.1 Continuity of Cabling
4/5B2.15 Resistors for Control Apparatus Electric cables are to be installed in continuous lengths
between terminations at equipment or in cable junction
The resistor is to be protected against corrosion either boxes. See 4/5B3.33. However, approved splices will
by rust-proofing or embedding in a protective material. be permitted at interfaces of new construction modules,
Resistors are to be located in well-ventilated when necessary to extend existing circuits for a craft
compartments and are to be mounted with ample undergoing repair or alteration, and in certain cases to
clearances, about 305 mm (12 in.) to prevent excessive provide for cables of exceptional length (See
heating of adjacent craft's structure or dangerous 4/5B3.29).
overheating of unprotected combustible material. The
arrangement of the electrical equipment and wiring 4/5B3.1.2 Choice of Cables
located within these spaces is to be such as to prevent The rated operating temperature of the insulating
their exposure to ambient temperatures in excess of that material is to be at least 10 oC (18 oF) higher than the
for which they have been designed. maximum ambient temperature likely to exist, or to be
produced, in the space where the cable is installed.
4/5B2.17 Lighting Fixtures
4/5B3.1.3 Cable Voltage Drop for New Installation
Lighting fixtures are be so arranged as to prevent The cross-sectional area of conductors are to be so
temperature rises which could damage the cables and determined that the drop in voltage from the main or
wiring, and to prevent surrounding material from emergency switchboard bus-bars to any and every point
becoming excessively hot. of the installation when the conductors are carrying the
maximum current under normal steady conditions of
service, will not exceed 6% of the nominal voltage. For
supplies from batteries with a voltage not exceeding 55
V this figure may be increased to 10%.

PART 4 SECTION 5|24 Electrical Installations -- Part B. Installations


The above values are applicable under normal steady 4/5B3.5.2 Single Conductor Cables
conditions. Under special conditions of short duration, Single conductor cables may be used for power
such as motor starting, higher voltage drops may be transmission provided the following arrangements are
accepted provided the installation is capable of complied with;
withstanding the effects of these higher voltage drops. a Cables are supported on non-fragile insulators;
b There are to be no magnetic materials between
4/5B3.1.4 Restricted Location of Cabling cables of a group; and
Cables and wiring are to be installed and supported in c Where single conductor cables are run in
such a manner as to avoid chafing or other damage. bunches, each group of cables is to comprise 360
Cables are to be located with a view to avoiding, as far electrical degrees, and where run for considerable
as practicable, spaces where excessive heat and gases length, individual cables are to be transposed
may be encountered, also spaces where they may be throughout the length in order to cancel out any
exposed to damage, such as exposed sides of possible effects of magnetic interference.
deckhouses. Cables are not to be installed in the bilge
area unless protected from bilge water. Additionally, single conductor cables may be used
when carrying negligible current (for control circuits,
4/5B3.1.5 Means of Drainage from Cable etc.). See 4/5C7.1.5 for armor.
Enclosures
Where cables are installed in a cable draw box and 4/5B3.5.3 Non-shielded Signal Cables
horizontal pipes or the equivalent used for cable Except for fiber optic cables, non-shielded signal
protection, means of drainage are to be provided. cables for automation and control systems essential for
the safe operation of the craft which may be affected
4/5B3.1.6 High Voltage Cables by electromagnetic interference are not to be run in the
Cables serving systems above 1 kV are not to be same bunch with power or lighting cables.
bunched with cables serving systems of 1 kV and
below. 4/5B3.7 Joints and Sealing

4/5B3.3 Insulation Resistance for New Installation Cables not having a moisture-resistant insulation are to
be sealed against the admission of moisture by methods
Each power and each light circuit is to have an such as taping in combination with insulating
insulation resistance between conductors and between compound or sealing devices. Cables are to be installed
each conductor and earth of not less than the following in such a manner that stresses on the cable are not
values. transmitted to the conductors. Terminations and joints
in all conductors are to be so made as to retain the
Up to 5 amperes load 2 meg ohms original electrical, flame retarding and, where
10 amperes load 1 meg ohm necessary, fire resisting properties of the cable.
25 amperes load 400,000 ohms Terminal boxes are to be secured in place and the
50 amperes load 250,000 ohms moisture-resistant jacket is to extend through the cable
100 amperes load 100,000 ohms clamp. Enclosures for outlets, switches, and similar
fittings are to be flame and moisture-resistant and of
200 amperes load 50,000 ohms
adequate mechanical strength and rigidity to protect the
Over 200 amperes load 25,000 ohms
contents and to prevent distortion under all likely
conditions of service. See also 4/5B3.17.1 and
If the above values are not obtained, any or all 4/5B3.29.
appliances connected to the circuit may be
disconnected for this test.
4/5B3.9 Support and Bending
4/5B3.5 Protection for Electric-magnetic Induction 4/5B3.9.1 Support
Where cables are run in groups, they are to be
4/5B3.5.1 Multiple Conductor Cables supported in metal hangers arranged as far as
All phase conductors of alternating-current cables are practicable to permit painting of the surrounding
to be contained within the same sheath in order to structure without undue disturbance to the installation.
avoid overheating due to induction by use of multiple Single-cable runs may be supported by metal clips
conductor cables. screwed directly to deck or bulkhead except on
watertight bulkheads. Power supply cables grouped in a
single hanger are to be limited preferably to two banks.
Supports for cables are to be spaced less than 610 mm
(24 in.) apart in both the horizontal and vertical

PART 4 SECTION 5|25 Electrical Installations -- Part B. Installations


directions. Cables supported by clips or straps on the mm (0.25 in.), the holes are to be fitted with bushings
under side of beams are to be run on backing plates, having rounded edges and a bearing surface for the
cable racks or the equivalent. Metal supports are to be cable of at least 6.4 mm (0.25 in.) in length. Where
designed to secure cables without damage to insulation cables pass through deck beams, or similar structural
or armor and are to be so arranged that the cable will parts, all burrs are to be removed in way of the holes
bear over a length of at least 12.7 mm (0.5 in.). Plastic and care is to be taken to eliminate sharp edges. Where
cable straps are not to be used for cable support but cable conduit pipe or equivalent is carried through
may be used with a combination of metallic cable decks or bulkheads, arrangements are to be made to
straps for retaining cables. maintain the integrity of the water or gas tightness of
the structure. Cables are not to pass through a collision
4/5B3.9.2 Bending Radius bulkhead.
For bending radius requirements, see Table 4/5B.2.
4/5B3.15 Mechanical Protection
4/5B3.11 Cable Run in Bunches
4/5B3.15.1 Metallic Armor
4/5B3.11.1 Reduction of Current Rating Electric cables installed in locations liable to damage
Where cables which may be expected to operate during normal operation of the craft are to be provided
simultaneously are laid close together in a cable bunch with braided metallic armor and otherwise suitably
in such a way that there is an absence of free air protected from mechanical injury as appropriate for the
circulation around them the following reduction factor location. See also 4/5B7.1.3 for cables in hazardous
is to be applied to the current rating obtained from areas.
Table 4/5C.10: 4/5B3.15.2 Conduit Pipe or Structural Shapes
Where cables are installed in locations in way of
Number of cables in one bunch Reduction factor hatches, tank tops, open decks subject to seas, and
one to six 1.0 where passing through decks, are to be protected by
seven to twelve 0.85 substantial metal shields, structural shapes, pipe or
other equivalent means. All such coverings are to be of
Bunches of more than twelve cables will be subject to sufficient strength to provide effective protection to the
special consideration based on the type and service of cables. When expansion bends are fitted they are to be
the various cables in the bunch. accessible for maintenance. Where cables are installed
in metal piping or in a metal conduit system, such
4/5B3.11.2 Clearance and Segregation piping and systems are to be earthed and are to be
A clearance is to be maintained between any two cable mechanically and electrically continuous across all
bunches of at least the diameter of the largest cable in joints.
either bunch. Otherwise, for the purpose of determining
the number of cables in the bunch the total number of 4/5B3.17 Emergency and Essential Feeders
cables on both sides of the clearance will be used.
4/5B3.17.1 Location
4/5B3.11.3 Cable of Lower Conductor Cables and wiring serving essential services or
Temperature emergency power, lighting, internal communications or
The current rating of each cable in a bunch is to be signals are to be so far as practicable be routed clear of
determined based on the lowest conductor temperature galleys, laundries, machinery spaces and their casing
rating of any cable in the bunch. and other high fire risk areas. Cables connecting fire
pumps to the emergency switchboard are to be of a fire
4/5B3.13 Deck and Bulkhead Penetrations resistant type where they pass through high fire risk
areas. Cables are to be run in such a manner as to
Where cables pass through watertight, firetight, or preclude damage by heating of the bulkheads that may
smoke-tight bulkheads or decks, the penetrations are to be caused by a fire in an adjacent space.
be made through the use of approved stuffing tubes,
transit devices, or pourable materials which will 4/5B3.17.2 Requirements by the Governmental
maintain the watertight, firetight, or smoke-tight Authority
integrity of the bulkheads or decks. Additionally, each Attention is directed to the requirements of the
such stuffing tube, transit device, or pourable material governmental authority of the country, whose flag the
is to be of a character so as not to damage the cable craft flies, for the installation of emergency circuits
physically or through chemical action or through heat required in various types of craft.
build-up. When cables pass through non-watertight
bulkheads where the bearing surface is less than 6.4

PART 4 SECTION 5|26 Electrical Installations -- Part B. Installations


4/5B3.19 Mineral Insulated Cables of the pipe and for bulkhead penetrations it is to be on
the uninsulated side of the bulkhead. For refrigerated-
At all points where mineral-insulated metal-sheathed space insulation the pipe is to be of phenolic or similar
cable terminates, an approval seal is to be provided heat-insulating material joined to the bulkhead stuffing
immediately after stripping to prevent entrance of tube or a section of such material is to be inserted
moisture into the mineral insulation. In addition, the between the bulkhead stuffing tube and the metallic
conductors extending beyond the sheath are to be pipe.
insulated with an approved insulating material. When
mineral-insulated cable is connected to boxes or 4/5B3.29 Splicing of Electrical Cables
equipment, the fittings are to be approved for the
conditions of service. The connections are to be in 4/5B3.29.1 Basis of Approval
accordance with the manufacturers installation Replacement insulation is to be fire resistant and is to
recommendation. be equivalent in electrical and thermal properties to the
original insulation. The replacement jacket is to be at
4/5B3.21 Fiber Optic Cables least equivalent to the original impervious sheath and is
to assure a watertight splice. Splices are to be made
The installation of fiber optic cables is to be in using an approved splice kit which contains the
accordance with the manufacturer's recommendations following:
to prevent sharp bends where the fiber optic cables
enter the equipment enclosure. Consideration is to be - Connector of correct size and number
given to the use of angled stuffing tubes. The cables are - Replacement insulation
to be installed so as to avoid abrading, crushing, - Replacement jacket
twisting, kinking or pulling around sharp edges. - Instructions for use

4/5B3.23 Battery Room In addition, prior to approval of a splicing kit, it will be


required that completed splices be tested for fire
Where cables enter battery rooms, the holes are to be resistance, watertightness, dielectric strength, etc. to the
bushed as required for watertight bulkheads in satisfaction of the Surveyor. This requirement may be
4/5B3.13. All connections within battery rooms are to modified for splice kits which have had such tests
be resistant to the electrolyte. Cables are to be sealed to conducted and reported on by an independent agency
resist the entrance of electrolyte by spray or creepage. acceptable to the Bureau.
The size of the connecting cable is to be based on 4/5B3.29.2 Installation
current-carrying capacities given in Table 4/5C.10 and All splices are to be made after the cable is in place and
the starting rate of charge or maximum discharge rate, are to be accessible for inspection. The conductor
whichever is the greater, is to be taken into splice is to be made using a pressure type butt
consideration in determining the cable size. connector by use of a one-cycle compression tool. See
4/5B7.1.3 for splices in hazardous area.
4/5B3.25 Paneling and Dome Fixtures
4/5B3.29.3 Protection
Cables may be installed behind paneling, provided all Splices may be located in protected enclosures or in
connections are accessible and the location of open wireways. Armored cables having splices will not
concealed connection boxes is indicated. Where a cable be required to have the armor replaced provided that
strip molding is used for cable installation on the the remaining armor has been earthed in compliance
incombustible paneling, it is to be of incombustible with 4/5B4.9 or provided the armor is made electrically
material. Dome fixtures are to be installed so that they continuous. Splices are to be so located such that
are vented or they are to be fitted with fire-resistant stresses (as from the weight of the cable) are not
material in such a manner as to protect the insulated carried by the splice.
wiring leading to the lamps and any exposed woodwork
from excessive temperature. 4/5B3.31 Splicing of Fiber Optic Cables

4/5B3.27 Sheathing and Structural Insulation Splicing of fiber optic cables is to be made by means of
approved mechanical or fusion methods.
Cables may be installed behind sheathing, but they are
not to be installed behind nor imbedded in structural 4/5B3.33 Cable Junction Box
insulation; they are to pass through such insulation at
right angles and are to be protected by a continuous Except for propulsion cables, junction boxes may be
pipe with a stuffing tube at one end. For deck used in the installation of electric cables aboard the
penetrations this stuffing tube is to be at the upper end craft provided the plans required by 4/5B1.3 for

PART 4 SECTION 5|27 Electrical Installations -- Part B. Installations


junction boxes are submitted and the following Alternatively, they are to be connected to the hull by a
requirements are complied with. separate conductor in accordance with 4/5B4.5. Where
outlets, switches and similar fittings are of non-metallic
1 The design and construction of the junction construction, all exposed metal parts is to be earthed.
boxes are to comply with 4/5C6.7 as well as
subparagraph 2. below. 4/5B4.5 Connections
2 The junction boxes are to be suitable for the
environment in which they are installed, i.e., explosion- 4/5B4.5.1 General
proof in hazardous areas, watertight or weathertight on All earthing conductors are to be of copper or other
deck, etc. corrosion resistant material and is to be protected
3 Separate junction boxes are to be used for against damage. The nominal cross-sectional area of
feeders and circuits of different rated voltage levels. every copper earthing conductor is to be not less than
Each junction box is to be appropriately identified as that required by Table 4/5B.3.
regards the rated voltage of the feeders and circuits it
contains. 4/5B4.5.2 Earthed Distribution System
4 The junction boxes for emergency feeders and Earthing conductors in earthed distribution system are
circuits are to be separate from those used for normal to comply with 4/5B4.5.1, except that the earthing
craft service feeders and circuits. conductor in line C4 of Table 4/5B.3 is to be A/2.
5 The junction boxes for control and alarm circuits
are to be separate from those for power circuits. Also, 4/5B4.5.3 Connection to Hull Structure.
where separate means of control is required (e.g. All connection of an earth-continuity conductor or
steering gear), the junction boxes for such circuits are earthing lead to the craft's structure is to be made in an
to be separated. accessible position and is secured by a screw of brass
6 Cables are to be supported, as necessary, within or other corrosion-resistant material having cross
junction boxes so as not to put stress (as from the sectional area equivalent to the earth-continuity
weight of the cable) on the cable contact mountings, conductor or earthing lead but not less than 4 mm (0.16
The connections are to be provided with locking type in.) in diameter. The earth connection screw is to be
connections. used for this purpose only. See 4/6.7.12 for control of
In addition to the above, the applicable requirements in static electricity.
4/5B3 and 4/5C7 regarding cable installation and
application details are to be complied with. 4/5B4.7 Portable Cords

Receptacle outlets operating at 55 volts D.C. or 55


4/5B4 Earthing volts A.C. r.m.s. or more are to have a earthing pole.

4/5B4.1 General 4/5B4.9 Cable Metallic Covering

Exposed metal parts of electrical machines or All metal sheaths, armor of cable and mineral-insulated
equipment which are not intended to be live but which metal-sheathed cable are to be electrically continuous
are liable under fault conditions to become live are to and are to be earthed to the metal hull at each end of
be earthed unless the machines or equipment are: the run except that final subcircuits may be earthed at
the supply end only. All metallic coverings of power
1 supplied at a voltage not exceeding 55 V D.C. or and lighting cables passing through hazardous area or
55 V A.C. r.m.s. between conductors; auto- connected to equipment in such an area are to be
transformers are not to be used for the purpose of earthed at least at each end. See also 4/11.3.7.e3.
achieving this voltage; or
2 supplied at a voltage not exceeding 250 V A.C. 4/5B4.11 Lightning Earth Conductors
r.m.s. by safety isolating transformers supplying only
one consuming device; or Each wooden mast or topmast is to be fitted with
3 constructed in accordance with the principle of lightning earth conductors. They need not be fitted to
double insulation, steel masts.

4/5B4.3 Permanent Equipment

The metal frames or cases of all permanently installed


generators, motors, controllers, instruments and similar
equipment are to be permanently earthed through a
metallic contact with the craft's structure.

PART 4 SECTION 5|28 Electrical Installations -- Part B. Installations


4/5B7 Equipment and Installation in Hazardous b Physical Barrier When intrinsically-safe
Area components are located by necessity within enclosures
that contain non-intrinsically-safe systems, such as
4/5B7.1 General Consideration control consoles and motor starters, such components
are to be effectively isolated in a sub-compartment by
4/5B7.1.1 General physical barriers having a cover or panel secured by
Electrical equipment and wiring are not to be installed bolts, locks, allen-screws, or other approved methods.
in hazardous area unless essential for operational The physical barrier is not intended to apply to the
purposes. source of power for the intrinsically-safe circuit
interface.
4/5B7.1.2 Lighting Circuits c Nameplate The sub-compartment is to have an
All switches and protective devices for lighting fixtures identifying nameplate indicating that the equipment
in hazardous area are to interrupt all poles or phases within is intrinsically-safe and that unauthorized
and are to be located in a non-hazardous area. The modification or repairs are prohibited.
switches and protective devices for lighting fixtures are d Replacement Unless specifically approved,
to be suitably labeled for identification purposes. replacement equipment for intrinsically-safe circuits is
to be identical to the original equipment.
4/5B7.1.3 Cables Installation
Cables in hazardous areas are to be armored or 4/5B7.3.3 Pressurized Equipment
mineral-insulated metal-sheathed. Where these cables Pressurized equipment is to consist of separately-
pass through boundaries of such locations, they are to ventilated enclosures supplied with positive-pressure
be run through gastight fittings. No splices are allowed ventilation from a closed-loop system or from a source
in hazardous areas except in intrinsically-safe circuits. outside the hazardous areas, and provision is to be
made such that the equipment cannot be energized until
4/5B7.1.4 Permanent Warning Plates the enclosure has been purged with a minimum of ten
Permanent warning plates are to be installed in the air changes and required pressure is obtained.
vicinity of hazardous areas in which electrical Ventilating pipes are to have a minimum wall thickness
equipment is installed, such as pump room, to advise of 3 mm (0.12 in. or 11 gage). In the case of loss of
personnel carrying out maintenance, repair or surveys pressurization, power is to be automatically removed
of availability of the booklet/list of equipment in from the equipment, unless this would result in a
hazardous areas referenced in 4/5B1.5, if required for condition more hazardous than the created by failure to
their use. de-energized the equipment. In this case, in lieu of
removal of power, an audible and visual alarm is to be
4/5B7.3 Certified-safe and Pressurized Type provided at a normally manned control station.
Equipment and Systems Pressurized equipment in compliance with IEC
Publication 79-2, NFPA 496 or other recognized
4/5B7.3.1 Installation Approval standard will also be acceptable.
Electrical equipment in hazardous areas is to be of a
type suitable for such locations. Where permitted by 4/5B7.5 Paint Stores
the Guide, electrical equipment of certified safe type,
such as explosion-proof type and intrinsically-safe 4/5B7.5.1 General
electrical instruments, circuitry and devices, will be Electrical equipment in paint stores and in ventilation
approved for installation provided such equipment has ducts serving such spaces where permitted by
been type-tested and certified by a competent 4/5B7.1.1 is to comply with the requirements for group
independent testing laboratory as explosion-proof or IIB class T3 in IEC Publication 79.
intrinsically-safe and provided that there is no The following type of equipment will be acceptable for
departure in the production equipment from the design such spaces.
so tested and approved. a intrinsically-safe defined by 4/5.3.6
b explosion-proof defined by 4/5.3.3
4/5B7.3.2 Intrinsically-safe System c pressurized defined by 4/5.3.12
a Separation Intrinsically-safe systems are to be d increased safety defined by 4/5.3.7
completely separated and independent of all other e other equipment with special protection
electric systems. Intrinsically-safe cables are to have recognized as safe for use in explosive gas atmospheres
shielded conductors or to be installed a minimum of 50 by a national or other appropriate authority
mm (2 in.) from other electric cables and are not to
occupy an enclosure (such as a junction box or terminal
cabinet) with non-intrinsically-safe circuits.

PART 4 SECTION 5|29 Electrical Installations -- Part B. Installations


4/5B7.5.2 Open Area Near Ventilation Openings c Acceptable Combination of Materials Tests
In the areas on open deck within 1 m (3.3 ft) of referred to in 4/5B7.7.2a above are not required for
ventilation inlet or within 1 m (3.3 ft) (if natural) or 3 fans having the following combinations:
m (10 ft) (if mechanical) of exhaust outlet, electrical 1 Impellers and/or housings of nonmetallic
equipment and cables where permitted by 4/5B7.1.1 material, due regard being paid to the
are to be in accordance with 4/5B7.1.2, 4/5B7.1.3 and elimination of static electricity;
4/5B7.3.1. 2 Impellers and housings of non-ferrous
materials;
4/5B7.5.3 Enclosed Access Spaces 3 impellers of aluminum alloys or magnesium
The enclosed spaces giving access to the paint store alloys and a ferrous (including austenitic
may be considered as non-hazardous, provided that: stainless steel) housing on which a ring of
a the door to the paint store is gastight with self- suitable thickness of non-ferrous materials is
closing devices without holding back arrangements, fitted in way of the impeller;
b the paint store is provided with an acceptable, 4 Any combination of ferrous (including
independent, natural ventilation system ventilated from austenitic stainless steel) impellers and
a safe area, and housings with not less than 13 mm (0.5 in.)
c warning notices are fitted adjacent to the paint tip design clearance.
store entrance stating that the store contains flammable d Unacceptable Combination of Materials The
liquids. following impellers and housings are considered as
sparking-producing and are not permitted:
4/5B7.7 Non-sparking Fans 1 Impellers of an aluminum alloy or magnesium
alloy and a ferrous housing, regardless of tip
4/5B7.7.1 Design Criteria clearance;
a Air Gap The air gap between the impeller and 2 Housing made of an aluminum alloy or a
the casing is to be not less than 10% of the shaft magnesium alloy and a ferrous impeller,
diameter in way of the impeller bearing but not less regardless of tip clearance;
than 2 mm (0.08 in.). It need not be more than 13 mm 3 Any combination of ferrous impeller and
(0.5 in.). housing with less than 13 mm (0.5 in.) design
b Protection Screen Protection screens of not tip clearance.
more than 13 mm (0.5 in.) square mesh are to be fitted
in the inlet and outlet of ventilation ducts to prevent the 4/5B7.7.3 Type Test
entrance of object into the fan casing. Type tests on the finished product are to be carried out
using an acceptable national or international standard.
4/5B7.7.2 Materials The tests need not to be witnessed by the Surveyor for
a Impeller and its Housing Except as indicated in individual fans produced on a production line basis,
4/5B7.7.2c below, the impeller and the housing in way provided the Surveyor is satisfied from periodic
of the impeller are to be made of alloys which are inspections and the manufacturer's quality assurance
recognized as being spark proof by appropriate test. procedures that the fans are being satisfactorily tested
b Electrostatic Charges Electrostatic charges both to appropriate standards. See also 4/1.3.
in the rotating body and the casing are to be prevented
by the use of antistatic materials. Furthermore, the
installation on board of the ventilation units is to be
such as to ensure the safe bonding to the hull of the
units themselves.

PART 4 SECTION 5|30 Electrical Installations -- Part B. Installations


Table 4/5B.1 Minimum Degree of Protection
[See 4/5B2.1.1]
(1) (2) (3) EQUIPMENT - : Not recommended to be installed
Switchboards, Distribution boards, Motor Control Center,
and Controller (See 4/5B2.9 to 4/5B2.13)
Generators (See 4/5B2.3)
Example Condition Motors (See 4/5B2.5)
of of Transformers, Converters
Location Location Lighting fixtures (See 4/5B2.17)
Heating appliances
(See 4/5B2.19)
Accessories (*2)
REMARKS
Dry Accommodation space Danger of touching live parts IP20 - IP20 IP20 IP20 IP20 IP20
Dry Control Rooms only IP20 - IP20 IP20 IP20 IP20 IP20
Control rooms (Operating Danger of dripping liquid IP22 - IP22 IP22 IP22 IP22 IP22
compartment) and/or moderate mechanical
damage
Machinery spaces above IP22 IP22 IP22 IP22 IP22 IP22 IP44
floor plates
Steering gear rooms IP22 IP22 IP22 IP22 IP22 IP22 IP44
Refrigerating machinery IP22 - IP22 IP22 IP22 IP22 IP44
rooms
Emergency machinery rooms IP22 IP22 IP22 IP22 IP22 IP22 IP44
General store rooms IP22 - IP22 IP22 IP22 IP22 IP22
Pantries IP22 - IP22 IP22 IP22 IP22 IP44
Provision rooms IP22 - IP22 IP22 IP22 IP22 IP22
Bathrooms & Showers Increased danger of - - - - IP34 IP44 IP55
Machinery spaces below liquid and/or mechanical - - IP44 - IP34 IP44 IP55
floor plates damage (*1)
Closed fuel oil or lubricating IP44 - IP44 - IP34 IP44 IP55
oil separator rooms (*1)
Ballast pump rooms Increased danger of IP44 - IP44 IP44 IP34 IP44 IP55
Refrigerated rooms liquid and mechanical - - IP44 - IP34 IP44 IP55
Galleys and Laundries damage IP44 - IP44 IP44 IP34 IP44 IP44
Open decks Exposure to heavy seas IP56 - IP56 - IP55 IP56 IP56
Bilge wells Exposure to submersion - - - - IPX8 - IPX8

Notes:
(*1) Socket outlets are not to be installed in machinery spaces below the floor plates, enclosed fuel and lubricating oil
separator rooms or spaces requiring certified safe type equipment
(*2) "Accessory" includes switches, detectors, junction boxes, etc. Accessories, which are acceptable for use in hazardous
areas, are limited by the condition of the areas. Specific requirements are given in the Guide. See 4/5B2.23.

PART 4 SECTION 5|31 Electrical Installations -- Part B. Installations


Table 4/5B.2 Minimum Bending Radii of Cables
[See 4/5B3.9.2]
Minimum internal
Cable Construction Overall diameter bending radius (times
of cable (D) overall diameter D)
Insulation Outer Covering
Metal-sheathed armored Any 6
Thermoplastic and or braided
elastomeric Other 25 mm (1 in.) and less 4
finish Exceeding 25 mm (1 in.) 6
Mineral Hard metal-sheathed Any 6

TABLE 4/5B.3 Size of Earth-continuity Conductors and


Earthing Connections
[See 4/5B4.5]
Cross-sectional area Minimum cross-sectional area of
Type of earthing connection of associated current copper earthing connection
carrying conductor
(A)
Earth-continuity conductor A1 A ≤ 16 mm2 A
in flexible cable or A2 16 mm2 < A ≤ 32 mm2 16 mm2
flexible cord A3 A > 32 mm2 A/2
For cables having an insulated earth-continuity conductor
B1a A ≤ 1.5 mm2 1.5 mm2
B1b 1.5 mm < A ≤ 16 mm
2 2
A
Earth-continuity conductor B1c 16 mm2 < A ≤ 32 mm2 16 mm2
incorporated in fixed cable B1d A > 32 mm2 A/2
For cables with bare earth wire in direct contact with the lead sheath
B2a A ≤ 2.5 mm2 1 mm2
B2b 2.5 mm < A ≤ 6 mm
2 2
1.5 mm2
C1a Stranded earthing connection :
A ≤ 2.5 mm2 1.5 mm2 for A ≤ 1.5 mm2
A for A > 1.5 mm2
Separate fixed earthing C1b Unstranded earthing connection: 2.5 mm2
conductor C2 2.5 mm2 < A ≤ 8 mm2 4 mm2
C3 8 mm2 < A ≤ 120 mm2 A/2
C4 A > 120 mm2 2
70 mm (See note 1)

[NOTE]
(1) For earthed distribution systems, the size of earthing conductor need not exceed A/2.
(2) Conversion Table for mm2 to circular mils:

mm2 circ. mils mm2 circ. mils mm2 circ. mils mm2 circ. mils
1 1,973 2.5 4,933 6 11,841 70 138,147
1.5 2,960 4 7,894 16 31,576 120 236,823

PART 4 SECTION 5|32 Electrical Installations -- Part B. Installations


4/5C2.1.2 Certification on Basis of an Approved
Part C. Machinery and Quality Assurance Program
Equipment See 4/1.3.

4/5C2.1.3 References
4/5C1 Plans and Data to Be Submitted a Inclination For the requirements covering
inclination for design condition, see 4/1.21.
4/5C1.1 Generators and Motors of 100 kW and b Insulation Material For the requirements
Over covering insulation material, see 4/5.13.
c Capacity of Generators For requirements
Drawings showing assembly, seating arrangements, covering main generator capacity, see 4/5A2.1.2 and
terminal arrangements, shafts, coupling, coupling bolts, 4/5A2.5. For requirements covering emergency
stator and rotor details are to be submitted for review generator capacity, see 4/5A3.3.1.
together with data for complete rating, class of d Power Supply by Generators For requirements
insulation, designed ambient temperature, temperature covering power supply by main or emergency
rise, weights and speeds for rotating parts. Plans to be generator, see 4/5A2.1.2 and 4/5A3.5.2 respectively.
submitted for generator prime movers are given in e Protection for Generator Circuits For
4/3.17 and 4/4.3 of the “Rules for Building and requirements covering protection for generator, see
Classing Steel Vessels”. 4/5A5.3, 4/5A5.5 and 4/5A5.7.
f Protection for Motor Circuits For requirements
4/5C1.3 Generators and Motors Below 100 kW covering protection for motor branch circuit, see
4/5A5.13.
Complete rating, class of insulation, and degree of g Installation For requirements covering
enclosure. installation, see 4/5B2.3 for generators and 4/5B2.5 for
motors.
4/5C1.5 Switchboards, Distribution Boards, etc. for h Protection Enclosures and its Selection For
Essential or Emergency Services requirements covering degree of the protection and the
selection of equipment, see 4/5.15 and 4/5B2.1
For switchboards, distribution boards, battery chargers, respectively.
motor control centers, controllers for essential services
or emergency services, drawings showing arrangements 4/5C2.3 Testing and Inspection
and details, front view, and installation arrangements
are to be submitted for review together with data for 4/5C2.3.1 Applications
protective device rating and setting, type of internal a Machines of 100 kW and Over All rotating
wiring, and size and rated current carrying capacity machines of 100 kW and over are to be tested in
(together with short-circuit current data) of bus bars accordance with Table 4/5C.1 in the presence of and
and internal wiring for power circuit. In addition, a inspected by the Surveyor, preferably at the plant of the
schematic or logic diagram with a written description, manufacturer.
giving the sequence of events and system operating b Machines Below 100 kW For machines of less
procedures for electrical power supply management on than 100 kW, the tests may be carried out by the
switchboards, and sequential or automatic changeover manufacturer whose certificate of tests will be
of the motors are also to be submitted for review. acceptable and is to be submitted upon request from the
Bureau.
4/5C2 Rotating Machines 4/5C2.3.2 Special Testing Arrangements
In cases where all of the required tests are not carried
4/5C2.1 General out at the plant of the manufacturer, the Surveyor is to
be notified and arrangements are to be made so that the
4/5C2.1.1 Applications remaining tests will be witnessed.
All rotating electrical machines of 100 kW and over are
to be constructed and tested in accordance with the 4/5C2.5 Insulation Resistance Measurement
following requirements to the satisfaction of the
Surveyor. All rotating electrical machines below 100 The resistance is to be measured before the
kW are to be constructed and equipped in accordance commencement of the testing and after completion of
with good commercial practice, and will be accepted the testing for all circuits. Circuits or groups of circuits
subject to a satisfactory performance test conducted to of different voltages above earth are to be tested
the satisfaction of the Surveyor after installation. separately. This test is to be made with at least 500

PART 4 SECTION 5|33 Electrical Installations -- Part C. Machinery and Equipment


volts D.C. and the insulation resistance in megohms of 4/5C2.7.2 Standard Voltage Test
the circuits while at their operating temperatures is to The insulation of all rotating machines is to be tested
be normally at least equal to: with the parts completely assembled and not with the
Rated Voltage of the Machine individual parts. The dielectric strength of the
(Rating in kVA/100) + 1000 insulation is to be tested by the continuous application
for 60 seconds of an alternating voltage having a
The minimum insulation resistance of the fields of frequency of 25 to 60 Hz and voltage in Table 4/5C.2.
machines separately excited with voltage less than the
rated voltage of the machine is to be of the order of 4/5C2.7.3 Direct Current Test
one-half to one megohm. A standard voltage test using a direct current source
4/5C2.6 Overload and Overcurrent Capability equal to 1.7 times the required alternating-current
voltage will be acceptable.
4/5C2.6.1 A.C. Generators
A.C. generators are to be capable of withstanding a 4/5C2.9 Temperature Ratings
current equal to 1.5 times the rated current for not less
than 30 seconds. 4/5C2.9.1 Temperature Rises
a Continuous Rating Machines After the machine
4/5C2.6.2 A.C. Motors has been run continuously under a rated load until
a Overcurrent Capacity Three phase motors, steady temperature condition has been reached, the
except for commutator motors, having rated outputs not temperature rises are not to exceed those given in Table
exceeding 315 kW and rated voltages not exceeding 1 4/5C.3.
kV are to be capable of withstanding a current equal to b Short-time Rating Machines After the machine
1.5 times the rated current for not less than 2 minutes. has been run at a rated load during the rated time,
For three-phase and single phase motors having rated followed by a rest and de-energized period of sufficient
outputs above 315 kW the overcurrent capacity is to be duration to re-establish the machine temperatures
in accordance with the manufacturer’s specification. within 2 oC (3.6 oF) of the coolant, the temperature
b Overload Capacity Three-phase induction rises are not to exceed those given in Table 4/5C.3. At
motors are to be capable of withstanding for 15 the beginning of the temperature measurement,
seconds, without stalling or abrupt change in speed, an temperature of the machine is to be within 5 oC (8 oF)
excess torque of 60 % of their rated torque, the voltage of the temperature of the coolant.
and frequency being maintained at their rated values. c Periodic Duty Rating Machines The machine
c Overload Capacity for Synchronous Motors has been run at a rated load for the designed load cycle
Three phase synchronous motors are to be capable of to be applied and continued until obtaining the
withstanding an excess torque as specified below for 15 practically identical temperature cycle . At the middle
seconds without falling out of synchronism, the of the period causing the greatest heating in the last
excitation being maintained at the value corresponding cycle of the operation, the temperature rises are not to
to the rated load. exceed those given in Table 4/5C.3.
d Non-periodic Duty Rating Machines After the
Synchronous (wound rotor) 35% excess torque machine has been run continuously or intermittently
induction motors: under the designed variations of the load and speed
Synchronous (cylindrical 35% excess torque within the permissible operating range until reaching
rotor) motors: the steady temperature condition, the temperature rises
Synchronous (salient pole) 50% excess torque are not to exceed those given in Table 4/5C.3.
motors: e Insulation Material Above 180 oC (356 oF )
When automatic excitation is used, the limit of torque Temperature rises for insulation materials above 180 oC
values are to be the same as with the excitation (356 oF) will be considered in accordance with
equipment operating under normal conditions. 4/5.13.6.
4/5C2.7 Dielectric Strength of Insulation
4/5C2.9.2 Ambient Temperature
4/5C2.7.1 Application These final temperatures are based on an ambient
The dielectric test voltage is to be successively applied temperature of 50 oC (122 oF). Where provision is
between each electric circuit and all other electric made for insuring an ambient temperature being
circuits and metal parts earthed and for direct-current maintained at 40 oC (104 oF) or less, as by air cooling
(D.C.) rotating machines between brush rings of or by locating the machine outside of the boiler and
opposite polarity. Interconnected polyphase windings engine rooms, the temperature rises of the windings
are to be considered as one circuit. All windings except maybe 10 oC (18 oF) higher. The ambient temperature
that under test are to be connected to earth. is to be taken in at least two places within 1.83 m (6 ft)

PART 4 SECTION 5|34 Electrical Installations -- Part C. Machinery and Equipment


of the machine under test and by thermometers having 4/5C2.11.9 Nameplates
their bulbs immersed in oil contained in an open cup. Nameplates of corrosion-resistant material are to be
provided in an accessible position of the machine and
4/5C2.11 Construction and Assemblies are to indicate at least the information as listed in Table
4/5C.4a.
4/5C2.11.1 Enclosure, Frame and Pedestals
Magnet frames and pedestals may be separate but are to 4/5C2.13 Lubrication
be secured to a common foundation.
Rotating machines are to have continuous lubrication at
4/5C2.11.2 Shafts and Couplings all running speeds and all normal working bearing
Rotating shaft, hollow shaft, and coupling flange with temperatures, with the craft's inclinations specified in
bolts are to comply with 4/4.19, 4/7.4 and 4/7.10 of this 4/1.21. Unless otherwise approved, where forced
Guide. lubrication is employed, the machines are to be
provided with means to shut down their prime movers
4/5C2.11.3 Circulating Currents automatically upon failure of the lubricating system.
Means are to be provided to prevent circulating Each self-lubricating sleeve bearing is to be fitted with
currents from passing between the journals and the an inspection lid and means for visual indication of oil
bearings, where the design and arrangement of the level or an oil gauge.
machine is such that damaging current may be
expected. Where such protection is required, a warning 4/5C2.15 Gas Turbines for Generators
plate is to be provided in a visible place cautioning
against the removal of such protection. Gas-turbine prime movers driving generators are to
meet the applicable requirements in Section 4/3 of the
4/5C2.11.4 Rotating Exciters “Rules for Building and Classing Steel Vessels Rules”
Rotating exciters are to conform to all applicable and in addition are to comply with the following
requirements for generators. requirements.

4/5C2.11.5 Insulation of Windings 4/5C2.15.1 Operating Governor


Armature and field coils are to be treated to resist oil An effective operating governor is to be fitted on prime
and water. movers driving main or emergency electric generators
and is to be capable of automatically maintaining the
4/5C2.11.6 Protection Against Cooling Water speed within the following limits. Special consideration
Where water cooling is used, the cooler is to be so will be given when an installation requires different
arranged to avoid entry of water into the machine, characteristics.
whether through leakage or from condensation in the a Momentary Speed Variations The momentary
heat exchanger. speed variations, when running at full load (equal to
rated output), is to be within 10% of the rated speed
4/5C2.11.7 Moisture-condensation Prevention when:
When the weight of the rotating machine, excluding the 1 The full load of the generator is suddenly
shaft, is over 455 kg (1000 lb), it is to be provided with thrown off, and
means to prevent moisture condensation in the machine
2 50% of the full load of the generator is
when idle. Where steam-heating coils are installed for
this purpose, there are to be no pipe joints inside the suddenly thrown on followed by the remaining
casings. See item 7 in Table 4/5C.7 for space heater 50% load after an interval sufficient to restore
pilot lamp for alternating-current generators. the speed to steady state.
3 The speed is to return to within 1% of the final
4/5C2.11.8 Terminal Arrangements steady state speed in no more than 5 seconds.
Terminals are to be provided at an accessible position b Speed Variations in Steady State The steady
and protected against mechanical damage and state speed variation is to be within 5% of the rated
accidental contact for earthing, short-circuit or speed at any loads between no load and the full load.
touching. Terminal leads are to be secured to the frame
and the designation of each terminal lead are to be 4/5C2.15.2 Overspeed Governor
clearly marked. The ends of terminal leads are to be In addition to the normal operating governor an
fitted with connectors. Cable glands or similar are to be overspeed governor is to be fitted which will trip the
provided where cable penetrations may compromise the turbine throttle when the rated speed is exceeded by
protection property of terminal enclosures. more than 15%. Provision is to be made for hand
tripping. See 4/5C2.13 for pressure-lubricated
machines.

PART 4 SECTION 5|35 Electrical Installations -- Part C. Machinery and Equipment


4/5C2.15.3 Power Output of Gas Turbines 4/5C2.19.2 Voltage Regulation
To satisfy the requirements of 4/5A2.1. the required a Voltage Regulators A separate regulator is to be
power output of gas turbine prime movers for craft's supplied for each A.C. generator. When it is intended
service generator sets is to be based on the maximum that two or more generators will be operated in parallel,
expected inlet air temperature. reactive-droop compensating means are to be provided
to divide the reactive power properly between the
4/5C2.17 Diesel Engines for Generators generators.
b Steady Conditions Each A.C. generator for
Diesel-engine prime movers are to meet the applicable craft's service driven by its prime mover having
requirements in Section 4/4 and in addition are to governor characteristics complying with 4/5C2.15.1 or
comply with the following requirements. 4/5C2.17.1 is to be provided with an excitation system
capable of maintaining the voltage under steady
4/5C2.17.1 Operating Governor conditions within plus or minus 2.5% of the rated
An effective operating governor is to be fitted on prime voltage for all loads between zero and rated load at
movers driving main or emergency electric generators rated power factor. These limits may be increased to
and is to be capable of automatically maintaining the plus or minus 3.5% for emergency sets.
speed within the following limits. Special consideration c Short Circuit Conditions Under steady-state
will be given when an installation requires different short-circuit conditions, the generator together with its
characteristics. excitation system is to be capable of maintaining a
a Momentary Speed Variations The momentary current of not less than 3 times its rated full load
speed variations, when running at full load (equal to current for a period of 2 seconds or of such magnitude
rated output), is to be within 10% of the rated speed and duration as required to properly actuate the
when: associated electrical protective devices.
1 The full load of the generator is suddenly
thrown off, and 4/5C2.19.3 Parallel Operation
2 50% of the full load of the generator is For A.C. generating sets operating in parallel, the
suddenly thrown on followed by the remaining following requirements are to be complied with. See
50% load after an interval sufficient to restore also 4/5A.5.5.2 for protection of A.C. generators in
the speed to steady state. parallel operation.
3 The speed is to return to within 1% of the final a Reactive Load Sharing The reactive loads of the
steady state speed in no more than 5 seconds. individual generating sets are not to differ from their
4 Where the electrical power system is designed proportionate share of the combined reactive load by
with an associated load management system, more than 10% of the rated reactive output of the
the application of load in multiple steps of less largest generator, or 25% of the rated reactive output of
than 50% of full load will be given special the smallest generator, whichever is the less.
considerations. b Load Sharing For any load between 20% and
b Speed Variations in Steady State The steady 100% of the sum of the rated output (aggregate output)
state speed variation is to be within 5% of the rated of all generators, the load on any generator is not to
speed at any loads between no load and the full load. differ more than 15% of the rated output in kilowatt of
the largest generator or 25% of the rated output in
4/5C2.17.2 Overspeed Governor kilowatt of the individual generator in question,
In addition to the normal operating governor each whichever is the less, from its proportionate share of
auxiliary diesel engine having a maximum continuous the combined load for any steady state condition. The
output of 220 kW and over is to be fitted with a starting point for the determination of the foregoing
separate overspeed device so adjusted that the speed load-distribution requirements is to be at 75% of the
cannot exceed the maximum rated speed by more than aggregate output with each generator carrying its
15%. Provision is to be made for hand tripping. See proportionate share.
4/5C2.13 for pressure-lubricated machines. c Facilities for Load Adjustment Facilities are to
be provided to adjust the governor sufficiently fine to
4/5C2.19 Alternating-current (A.C.) Generators permit an adjustment of load not exceeding 5% of the
aggregate output at normal frequency.
4/5C2.19.1 Control and Excitation of Generators
Excitation current for generators is to be provided by
attached rotating exciters or by static exciters deriving
their source of power from the machine being excited.

PART 4 SECTION 5|36 Electrical Installations -- Part C. Machinery and Equipment


4/5C2.21 Direct-current (D.C.) Generators the largest generator or 25% of the rated output in
kilowatt of the individual generator in question,
4/5C2.21.1 Control and Excitation of Generators whichever is the less, from its proportionate share of
a Field Regulations Means are to be provided at the combined load for any steady state condition. The
the switchboard to enable the voltage of each generator starting point for the determination of the foregoing
to be adjusted separately. This equipment is to be load-distribution requirements is to be at 75% of the
capable of adjusting the voltage of the D.C. generator aggregate output with each generator carrying its
to within 0.5% of the rated voltage at all loads between proportionate share.
no-load and full-load. c Tripping of Circuit Breaker D.C. generators
b Polarity of Series Windings The series windings which operate in parallel are to be provided with a
of each generator for two wire D.C. system are to be switch which will trip the generator circuit breaker
connected to negative terminal of each machine. upon functioning of the overspeed device.
c Equalizer Connections See 4/5C4.15.3.

4/5C2.21.2 Voltage Regulation 4/5C3 Accumulator Batteries


a Shunt or Stabilized Shunt-wound Generator
When the voltage has been set at full-load to its rated 4/5C3.1 General
value, the removal of the load is not to cause a
permanent increase of the voltage greater than 15% of 4/5C3.1.1 Application
the rated voltage. When the voltage has been set either All accumulator batteries for engine starting, essential
at full-load or at no-load, the voltage obtained at any or emergency services are to be constructed and
value of the load is not to exceed the no-load voltage. installed in accordance with the following
b Compound-wound Generator Compound- requirements. Accumulator batteries for services other
wound generators are to be so designed in relation to than the above are to be constructed and equipped in
the governing characteristics of prime mover, that with accordance with good commercial practice. All
accumulator batteries will be accepted subject to a
the generator at full-load operating temperature and
satisfactory performance test conducted to the
starting at 20% load with voltage within 1% of rated
satisfaction of the Surveyor after installation.
voltage, it gives at full-load a voltage within 1.5% of
rated voltage. The average of ascending and
4/5C3.1.2 Sealed Type Batteries
descending voltage regulation curves between 20% Where arrangements are made for releasing gas
load and full-load is not to vary more than 3% from through a relief valve following an overcharge
rated voltage. condition, calculations demonstrating compliance with
c Automatic Voltage Regulators Craft's service the criteria in 4/5B2.7.3 under the expected rate of
generators which are of shunt type are to be provided hydrogen generation are to be submitted together with
with automatic voltage regulators. However, if the load the details of installation and mechanical ventilation
fluctuation does not interfere with the operation of arrangements.
essential auxiliaries, shunt-wound generators without
voltage regulators or stabilized shunt-wound machines 4/5C3.1.3 References
may be used. An automatic voltage regulators will not a Emergency Services For requirements covering
be required for the craft's service generators of emergency services and transitional source of power,
approximately flat-compounded type. Automatic see 4/5A3.5.3 and 4/5A3.7 respectively.
voltage regulators are to be provided for all service b Protection of Batteries For requirements
generators driven by variable speed engines used also covering protection of batteries, see 4/5A5.9.
for propulsion purposes, whether these generators are c Battery Installation For requirements covering
of the shunt , stabilized shunt or compound-wound battery installation, ventilation of the battery location
type. and protection from corrosion, see 4/5B2.7.
d Cable Installation For requirements covering
4/5C2.21.3 Parallel Operation cable installation in battery room, see 4/5B3.23.
For D.C. generating sets operating in parallel, the
following requirements are to be complied with. See 4/5C3.3 Construction and Assembly
also 4/5A.5.7.2 for protection of D.C. generators in
parallel operation. 4/5C3.3.1 Cells and Filling Plugs
a Stability The generating sets are to be stable in The cells are to be so constructed as to prevent spilling
operation at all loads from no-load to full-load. of electrolyte due to an inclination of 40 deg. from
b Load Sharing For any load between 20% and normal. The filling plugs are to be so constructed as to
100% of the sum of the rated output (aggregate output) prevent spilling of electrolyte due to craft's movements
of all generators, the load on any generator is not to such as rolling and pitching.
differ more than 12% of the rated output in kilowatt of

PART 4 SECTION 5|37 Electrical Installations -- Part C. Machinery and Equipment


4/5C3.3.2 Crates and Trays e Hull Return and Earthed Distribution Systems
The cells are to be grouped in crates or trays of rigid For requirements covering hull return system and
construction equipped with handles to facilitate earthed distribution system, see 4/5A4.3 and 4/5A4.5
handling. For protection from corrosion, see 4/5B2.7.4. respectively
The mass of crates or trays are not to exceed 100 kg f Earthing For requirements covering earthing
(220.5 lb). connections, see 4/5B4.
g Installation For requirements covering
4/5C3.3.3 Nameplate installation, see 4/5B2.9 for switchboard, 4/5B2.11 for
Nameplates of corrosion-resistant material are to be distribution boards, and 4/5B2.13 for motor controllers
provided in an accessible position of each crate or tray and control centers.
and are to indicate at least the information as listed in h Protection Enclosures and its Selection For
Table 4/5C.4b. requirements covering degree of the protection and the
selection of equipment, see 4/5.15 and 4/5B2.1
4/5C3.5 Engine-starting Battery respectively.

Battery systems for engine-starting purposes may be of 4/5C4.3 Testing and Inspection
the one-wire type and the earth lead is to be carried to
the engine frame. See also 4/4.15.9 and 4/5A3.15 for 4/5C4.3.1 Applications
main engine starting and starting arrangement of a For Essential or Emergency Services All
emergency generator, respectively. Switchboards and motor controllers, intended for
essential services or emergency services, are to be
tested in the presence of and inspected by the Surveyor,
4/5C4 Switchboards, Distribution Boards, preferably at the plant of the manufacturer. For
Chargers, and Controllers distribution boards, the tests may be carried out by the
manufacturer whose certificate of tests will be
4/5C4.1 General acceptable and is to be submitted upon request from the
Bureau.
4/5C4.1.1 Applications b For Non-essential or Non-emergency Services
Switchboards are to provide adequate control of the For switchboards, distribution boards, and motor
generation and distribution of electric power. The controllers of other than essential or emergency
following equipment are to be constructed and tested in services, the tests may be carried out by the
accordance with the following requirements to the manufacturer whose certificate of tests will be
satisfaction of the Surveyor. acceptable and is to be submitted upon request from the
- Switchboards and motor controllers for essential Bureau.
and emergency services. c Motor Control Centers All motor control
- Motor control centers whose total connected centers, whose total connected motor rating is 100 kW
motor rating is 100 kW or more regardless of their or more regardless of their services, are to be tested in
services, and the presence of and inspected by the Surveyor,
- Battery chargers and discharging boards for preferably at the plant of the manufacturer.
emergency or transitional source of power. d Battery Chargers and Discharging Board
Switchboard, distribution board, charger, and Where a battery charger and discharging board is used
controllers not covered by the above paragraph are for emergency source of power or transitional source of
to be constructed and equipped in accordance with power, it is to be tested in the presence of and inspected
good commercial practice, and will be accepted by the Surveyor, preferably at the plant of the
subject to a satisfactory performance test conducted manufacturer. For all other battery chargers and
to the satisfaction of the Surveyor after installation. discharging boards, the tests may be carried out by the
manufacturer whose certificate of tests will be
4/5C4.1.2 References acceptable and is to be submitted upon request from the
a Inclination For requirements covering Bureau.
inclination for design condition, see 4/1.21. e Test Items Tests are to be carried out in
b Emergency Switchboard For requirements accordance with the requirements in Table 4/5C.5.
covering emergency switchboard, see 4/5A3.9.
c Circuit Breakers For requirements covering 4/5C4.3.2 Special Testing Arrangements
generator circuit breakers, see 4/5C6.1. In cases where all of the required tests are not carried
d Feeder Protection For requirements covering out at the plant of the manufacturer, the Surveyor is to
feeder protection, see 4/5A5.3 to 4/5A5.17, 4/5A6.3, be notified and arrangements are to be made so that the
4/5A7.1.4, and 4/5A7.3.3. remaining tests may be witnessed.

PART 4 SECTION 5|38 Electrical Installations -- Part C. Machinery and Equipment


4/5C4.5 Insulation Resistance Measurement 4/5C4.9.3 Mechanical Strength
All levers, handles, hand wheels, interlocks and their
The insulation resistance between current-carrying connecting links, shafts and bearings for the operation
parts (connected together for this purpose of this test) of switches and contactors are to be of such proportions
and earth and between current-carrying parts of that they will not be broken or distorted by manual
opposite polarity is to be measured at a D.C. voltage of operation.
not less than 500 volts before and after the dielectric
strength tests. The insulation resistance measurement, 4/5C4.9.4 Mechanical Protection
after the dielectric strength tests, is to be carried out The sides and the rear and, where necessary, the front
before components which have been disconnected for of switchboards are to be suitably guarded. Exposed
the dielectric tests are reconnected and the insulation live parts having voltages to earth exceeding a voltage
resistance is not to be less than 1 megohm. of 55 volts D.C. or 55 volts A.C. r.m.s. between
conductors are not to be installed on the front of such
4/5C4.7 Dielectric Strength of Insulation switchboards. Non-conducting mats or gratings are to
be provided at the front and rear of the switchboard.
The dielectric strength of the insulation is to be tested Drip covers are to be provided over switchboards when
for 60 seconds by an alternating voltage applied in subject to damage by leaks or falling objects.
accordance with Table 4/5C.5 between:
a All live parts and the interconnected exposed 4/5C4.11 Bus Bars, Wiring and Contacts
conductive parts, and
b Each phase and all other phases connected for 4/5C4.11.1 Design
this test to the interconnected exposed conductive parts Copper bar is to be used for main and generator bus in
of the unit. the switchboard. Other materials and combination of
The test voltage at the moment of application is not to materials will be specially considered. Generator bus
exceed 50 % of the values given in Table 4/5C.5. It is bars are to be designed on a basis of maximum
to be increased steadily within a few seconds to the generator rating. All other bus bars and bus-bar
required test voltage and maintained for 60 seconds. connections are to be designed for at least 75% of the
Test voltage is to have a sinusoidal waveform and a combined full-load rated currents of all apparatus they
frequency between 45 Hz and 60 Hz. supply, except that when they supply one unit or any
4/5C4.7.1 Production-line Apparatus group of units in continuous operation, they are to be
Standard apparatus produced in large quantities for designed for full load.
which the standard test voltage is 2500 volts or less,
may be tested for one second with a test voltage 20% 4/5C4.11.2 Operating Temperature of Bus Bars
higher than the one-minute test voltage. Bus bars are to be proportioned to avoid temperature
which will affect the normal operation of electrical
4/5C4.7.2 Devices with Low Insulation Strength devices mounted on the board.
Certain devices such as potential transformers, having
inherently lower insulation strength are to be 4/5C4.11.3 Short Circuit Rating
disconnected during the test. Circuit breakers and bus bars are to be mounted, braced
and located so as to withstand the thermal effects and
4/5C4.9 Construction and Assembly mechanical forces resulting from the maximum
prospective short circuit current. Switchboard
4/5C4.9.1 Enclosures and Assemblies instruments, controls, etc., are to be located with
Enclosures and assemblies are to be constructed of respect to circuit breakers so as to minimize the thermal
steel or other suitable incombustible, moisture-resistant effects due to short circuit currents.
materials and reinforced as necessary to withstand the
mechanical, electrical (magnetic) and thermal stresses 4/5C4.11.4 Internal Wiring
likely to be encountered in service and are to be Instrument and control wiring is to be of the stranded
protected against corrosion. No wood is to be used, type and is to have heat-resisting and flame-retarding
except for hardwood for nonconducting hand rails. insulation. Wiring from hinged panels is to be of the
Insulating materials are to be flame retardant and extra-flexible type.
moisture resistant. The supporting framework is to be
of rigid construction. 4/5C4.11.5 Arrangement
a Accessibility The arrangement of bus bars and
4/5C4.9.2 Dead Front wiring on the back is to be such that all lugs are readily
The dead-front type is to be used. Live-front type is not accessible.
acceptable regardless of the voltage ratings.

PART 4 SECTION 5|39 Electrical Installations -- Part C. Machinery and Equipment


b Locking of Connections All nuts and accomplished, the rheostat or other device is to be
connections are to be fitted with locking devices to mounted separately from the switchboard.
prevent loosening due to vibration. d Accessibility to Fuses All fuses, except for
c Soldered Connections Soldered connections are instrument and control circuits, are to be mounted on or
not to be used for connecting or terminating any wire or be accessible from the front of the switchboard.
cable of nominal cross-sectional area of greater than e Protective Device for Instrumentation All
2.5 mm2 (4,933 circ. mils). Soldered connections, wiring on the boards for instrumentation is to be
where used, are to have a solder contact length at least protected by fuses or current limiting devices, see
1.5 times the diameter of the conductor. 4/5A5.17.
f Wearing Parts All wearing parts are to be
4/5C4.11.6 Clearances and Creepage Distances accessible for inspection and readily renewable.
Bare main bus bars, but not including the conductors
between the main bus bars and the supply side of 4/5C4.13.3 Markings
outgoing units, are to have minimum clearances (in air) Identification plates are to be provided for each piece
and creepage distances (across surfaces) in accordance of apparatus to indicate clearly its service.
with Table 4/5C.6. Identification plates for feeders and branch circuits are
to include the circuit designation and the rating of the
4/5C4.11.7 Terminals fuse or circuit-breaker trip setting required by the
Terminals or terminal rows for systems of different circuit.
voltage are to be clearly separated each other and the
rated voltage is to be clearly marked. Each terminal is 4/5C4.15 Switchboards
to have a nameplate indicating the circuit designation
or circuit number. In addition to 4/5C4.1 to 4/5C4.13 as applicable, the
switchboards for essential or emergency services are to
4/5C4.13 Control and Protective Devices comply with the following requirements.

4/5C4.13.1 Circuit-disconnecting Devices 4/5C4.15.1 Handrails


a Systems Exceeding 55 Volts Distribution Insulated handrail or insulated handles are to be
boards, chargers or controllers for distribution to provided on the front of the switchboard. Similarly,
motors, appliances, and lighting or other branch circuits where access to the rear is required, insulated handrail
are to be fitted with multipole circuit breakers or a or insulated handles are also to be fitted on the rear of
multipole switch-fuse combination in each unearthed the switchboard.
conductor.
b Systems of 55 Volts and Less For distribution 4/5C4.15.2 Main Bus Bar Sub-division
boards, chargers or controllers where voltage to earth Where the total installed electrical power of the main
or between poles does not exceed 55 volts D.C. or 55 generating sets is in excess of 3000 kW or the
volts A.C. r.m.s., the fuses may be provided without operation of the vessel is dependent electrical
switches. equipment which is duplicate, the main bus bars are to
c Disconnect Device The rating of the be subdivided into at least two parts which are to be
disconnecting device is to be coordinated with the connected by removable links or other approved
voltage and current requirements of the load. The means. As far as practicable, the connection of
disconnect device is to indicate by position of the generating sets and any other duplicated equipment is
handle, or otherwise, whether it is open or closed. to be equally divided between the parts.
See 4/5A4.1.1.
4/5C4.13.2 Arrangement of Equipment
a Air Circuit Breakers Air circuit breaker contacts 4/5C4.15.3 Equalizer Circuit for Direct-current
are to be kept at least 305 mm (12 in.) from the craft's (D.C.) Generators
structure unless insulation barriers are installed. a Equalizer Main Circuit The current rating of the
b Voltage Regulators Voltage regulator elements equalizer main circuit for direct-current (D.C.)
are to be provided with enclosing cases to protect them generators is not to be less than half of the rated full-
from damage. load current of the generator.
c Equipment Operated in High Temperature b Equalizer Bus Bars The current rating of the
Where rheostats or other devices that may operate at equalizer bus bars is not to be less than half of the rated
high temperatures are mounted on the switchboard, full-load current of the largest generator in the group.
they are to be naturally ventilated and so located or
isolated by barriers as to prevent excessive temperature 4/5C4.15.4 Equipment and Instrumentation
of adjacent devices. When this cannot be See Table 4/5C.7

PART 4 SECTION 5|40 Electrical Installations -- Part C. Machinery and Equipment


4/5C4.17 Motor Controllers and Control Centers 4/5C4.19.2 Equipment and Instrumentation
At least the following equipment and instrumentation
In addition to 4/5C4.1 to 4/5C4.13 as applicable, the are to be provided for chargers.
motor controllers and control centers for essential or a Power Supply Disconnecting Switch A switch
emergency services are to comply with the following for disconnecting the power supply to the charger.
requirements. b Pilot Lamp A pilot lamp connected at the
downstream side of the power supply disconnecting
4/5C4.17.1 Enclosures and Assemblies switch in the power supply circuit to the charger.
The following materials are acceptable for the c Charging Voltage Adjuster A means for
enclosures. adjusting the voltage for charging.
d Voltmeter A voltmeter for indicating the
- Cast metal, other than die-cast metal, at least 3 charging voltage to a battery. This voltmeter may also
mm (1/8 in.) thick at every point. be used for indicating the battery discharging voltage
- Nonmetallic materials which have ample strength, by using a selector switch.
are noncombustible and nonabsorptive, e.g. e Ammeter An ammeter for indicating charging
laminated phenolic material. current to a battery. This ammeter may also be used for
- Sheet metal of adequate strength. indicating the battery discharging current of batteries
by using a selector switch.
Motor control centers are to be constructed so that they f Discharge Protection An acceptable means, such
are secured to a solid foundation, be self-supported, or as reverse current protection, for preventing a failed
be braced to the bulkhead. battery charger component from discharging the battery
is to be provided.
4/5C4.17.2 Disconnect Switches and Circuit
Breakers
Circuit-disconnecting devices are to be provided for 4/5C5 Transformers
each motor branch circuit. For motors rated not more
than 1.5 kW and not more than 250 volts, the starting 4/5C5.1 General
switch may serve as a disconnect, provided it has an
ampere rating not less than twice the rated current of 4/5C5.1.1 Applications
the motor. For motors over 1.5 kW rating the All transformers which serve for essential or
disconnect means is to be a switch with a horsepower emergency electrical supply are to be constructed and
rating not less than the motor rating or a circuit breaker installed in accordance with the following
with an ampere rating at least 115% of motor rating. requirements. Transformers other than the above
Disconnect switches and circuit breakers are to be services, auto-transformers for starting motors or
capable of being operated without opening the isolation transformers are to be constructed and
enclosures in which they are installed. equipped in accordance with good commercial
practice. All transformers are to be of the dry and air
4/5C4.17.3 Auto-starters cooled type. The use of liquid immersed type
Alternating-current (A.C.) motor manual auto-starters transformers will be subject to special consideration.
with self-contained auto-transformers are to be All transformers will be accepted subject to a
provided with switches of the quick-make-and-break satisfactory performance test conducted to the
type, and the starter is to be arranged so that it will be satisfaction of the Surveyor after installation.
impossible to throw to the running position without
having first thrown to the starting position. Switches 4/5C5.1.2 References
are to be preferably of the contactor or air-break-type. a Power Supply Arrangement For requirements
covering arrangement of power supply through
4/5C4.19 Battery Chargers transformers to craft's service systems, see 4/5A4.1.6.
b Protection For requirements covering protection
In addition to 4/5C4.1 to 4/5C4.13 as applicable, the of transformers, see 4/5A5.15.
battery chargers for essential or emergency services are c Protection Enclosures and its Selection For
to comply with the following requirements. requirements covering selection of the protection
enclosures for location conditions, see 4/5B2.1.1.
4/5C4.19.1 Charging Capacity
Except when a different charging rate is necessary and 4/5C5.1.3 Forced Cooling Arrangement (Air or
is specified for a particular application, the charging Liquid) (1997)
facilities are to be such that the completely discharged Where forced cooling medium is used to preclude the
battery can be recharged to 80% capacity within a transformer from exceeding temperatures outside its
period of at least 10 hours. rated range, monitoring and alarm means are to be

PART 4 SECTION 5|41 Electrical Installations -- Part C. Machinery and Equipment


provided and arranged so that an alarm activates when 4/5C6.1.2 Mechanical Property
pre-set temperature conditions are exceeded. Manual Arc-rupturing and main contacts of all open frame
or automatic arrangements are to be made to reduce the circuit breakers are to be self-cleaning.
transformer load to a level corresponding to the cooling
available. 4/5C6.1.3 Isolation
The electrical system is to be arranged so that portions
4/5C5.3 Temperature Rise may be isolated to remove circuit breakers while
maintaining services necessary for propulsion and
The design temperature rise of insulated windings safety of the craft, or circuit breakers are to be
based on an ambient temperature of 40 oC (104 oF) is mounted or arranged in such a manner that the breaker
not to exceed the values listed in Table 4/5C.8. If the may be removed from the front without disconnecting
ambient temperature exceeds 40 oC (104 oF), the the copper or cable connections or without de-
transformer is to be derated so that the total energizing the supply to the breaker.
temperature based on the above temperature rises is not
exceeded. Temperatures are to be taken by the 4/5C6.3 Fuses
resistance method of temperature determination.
Temperature rises for insulation material above 180 oC Fuses are to be constructed and tested to comply with
(356 oF) will be considered in accordance with IEC Publication 269 or other recognized standard. The
4/5.13.6. tests may be carried out by the manufacturer whose
certificate of tests will be acceptable and is to be
4/5C5.5 Construction and Assembly submitted upon request from the Bureau. All
components of the fuse are to be resistant to heat,
4/5C5.5.1 Windings mechanical stresses and corrosive influences which
All transformer windings are to be treated to resist may occur in normal use.
moisture, sea atmosphere and oil vapors.
4/5C6.5 Semiconductor Converters
4/5C5.5.2 Terminals
Terminals are to be provided in an accessible position. 4/5C6.5.1 General
The circuit designation is to be clearly marked on each The requirements in this subsection are applicable to
terminal connection. The terminals are to be so spaced static converters for essential and emergency services
or shielded that they can not be accidentally earthed, using semiconductor rectifying elements such as
short-circuited or touched. diodes, reverse blocking triodes thyristors, etc. The
tests may be carried out by the manufacturer whose
4/5C5.5.3 Nameplate certificate of tests will be acceptable and is to be
Nameplates of corrosion-resistant material are to be submitted upon request from the Bureau. All
provided in an accessible position of the transformer semiconductor converters will be accepted subject to a
and are to indicate at least the information as listed in satisfactory performance test conducted to the
Table 4/5C.4c. satisfaction of the Surveyor after installation.

4/5C6.5.2 Cooling Arrangements


4/5C6 Other Electric and Electronics Devices Semiconductor converters are preferably to be of a dry
and air cooled type. Where semiconductor converters
4/5C6.1 Circuit Breakers are of a liquid-immersed type, a liquid over-
temperature alarm and gas over-pressure protection
4/5C6.1.1 General devices are to be provided. If provision is made for
Circuit breakers are to be constructed and tested to breathing, a dehydrator is to be provided. Where
comply with IEC Publication 157-1 or other recognized arrangement for the forced cooling is provided, the
standard. The tests may be carried out by the circuit is to be designed that power cannot be applied
manufacturer whose certificate of tests will be to, or retained, on converter stacks unless effective
acceptable and is to be submitted upon request from the cooling is maintained.
Bureau. Circuit breakers of the thermal type are to be
calibrated for an ambient-air temperature as provided 4/5C6.5.3 Accessibility
in 4/5.17. Semiconductor converter stacks or semiconductor
components are to be mounted in such a manner that
Note: Where thermal-type breakers are mounted within they can be removed from equipment without
enclosures, it is pointed out that the temperature within
dismantling the complete unit.
the enclosure may exceed the designated ambient-air
temperature.

PART 4 SECTION 5|42 Electrical Installations -- Part C. Machinery and Equipment


4/5C6.5.4 Nameplate 4/5C7.1.2 Flame Retardant Property
A nameplate or identification is to be provided on the a Standards All electric cables are to be at least of
semiconductor converter and is to indicate at least the a flame retardant type complying with the following:
information as listed in Table 4/5C.4d. - Cables constructed to IEC Publication 92
standards are to comply with the flammability
4/5C6.7 Cable Junction Boxes criteria of IEC Publication 332-3.
- Cables constructed to IEEE Std. 45 are to comply
4/5C6.7.1 General with the flammability criteria of that standard.
The design and construction of the junction boxes - Cables constructed to another recognized marine
are to be in compliance with 4/5C6.7.2 or other standard, where specially approved, are to comply
recognized standard. The tests may be carried out by with the flammability criteria of IEEE Std. 45 or
the manufacturer whose certificate of tests will be other acceptable standards.
acceptable and is to be submitted upon request from the Consideration will be given to the special types of
Bureau. cables such as radio frequency cable, which do not
4/5C6.7.2 Design and Construction comply with the above requirements.
Live parts are to be mounted on durable flame- b Alternative Arrangement Flame retardant
retardant moisture-resistant material, of permanently marine cables which have not passed the above-
high dielectric strength and high resistance. The live mentioned bunched cable flammability criteria maybe
parts are to be so arranged by suitable spacing or considered provided that the cable is treated with
shielding with flame-retardant insulating material, that approved flame retardant material or the installation is
short-circuit cannot readily occur between conductors provided with approved fire stop arrangements. The
of different polarity or between conductors and earthed flame retardancy of communications cables will be
metal. Junction boxes are to be made of flame-retardant specially considered. When specifically approved, bus
material, junction boxes are to be clearly identified duct may be used in lieu of cable.
defining their function and voltage.
4/5C7.1.3 Fire Resistant Property
When electric cables are required to be fire resistant,
4/5C7 Cables and Wires they are to comply with the requirements of IEC
Publication 331.
4/5C7.1 Cable Construction
4/5C7.1.4 Insulation Material
4/5C7.1.1 General All electrical cables for power, lighting,
Electric cables are to have conductors, insulation, and communication, control and electronic circuits are to
moisture-resistant jackets in accordance with IEC have insulation suitable for a conductor temperature of
Publication 92-353 or IEEE Std. 45. Other recognized not less than 60 oC (140 oF). See Table 4/5C.9 for types
marine standards will also be considered. The tests may of cable insulation.
be carried out by the manufacturer whose certificate of
tests will be acceptable and is to be submitted upon 4/5C7.1.5 Armor for Single-conductor Cables
request from the Bureau. Conductors are to be of The armor is to be nonmagnetic for single-conductor
copper and stranded in all sizes. Conductors are not to alternating-current cables.
be less than the following in cross sectional size:
4/5C7.1.6 Fiber Optic Cables
- 1.0 mm2 (1,973 circ. mils) for power, lighting and Fiber optic cables are to be constructed and tested to a
control cables, recognized fiber optic cable construction standard
- 0.5 mm2 (986.5 circ. mils) for essential or acceptable to the Bureau. The requirements of flame
emergency signaling and communications cables retardancy for the electrical cables is applicable to the
except for those assembled by the equipment fiber optic cables. The construction of the fiber optic
manufacturer, and cable which may pass through or enter a hazardous area
- 0.375 mm2 (739.9 circ. mils) for telephone cables is to be such that escape of gases to a safe area is not
for non-essential communication services except for possible through the cable.
those assembled by the equipment manufacturer.
4/5C7.3 (No text)
See Table 4/5C.10 for current carrying capacity for
insulated copper wires and cables.

PART 4 SECTION 5|43 Electrical Installations -- Part C. Machinery and Equipment


4/5C7.5 Portable and Flexing Electric Cables Mineral-insulated cable provided with approved fittings
for terminating and connecting to boxes, outlets and
Unless otherwise required in the Guide, cables for other equipment may be used for any service up to 600
portable equipment and cables subject to flexing volts and may be used for feeders and branch circuits in
service need not be armored. both exposed and concealed work, in dry or wet
locations. The moisture-resisting jacket (sheath) of
4/5C7.7 Mineral-insulated Metal-sheathed Cable mineral-insulated metal-sheathed cable exposed to
corrosive conditions is to be made of or protected by
materials suitable for those conditions.

PART 4 SECTION 5|44 Electrical Installations -- Part C. Machinery and Equipment


Table 4/5C.1 Factory Testing Schedule
for Rotating Machines of 100 kW and over
[See 4/5C2.3.1a]

First unit of Duplicate Units Spare Rotors


Test Design
A.C. D.C. A.C. D.C. A.C. or D.C.
Full-load Heat Run including Temperature Rise X (1) X
Measurement
Saturating Curve X (2) X
Running Light Current at Rated Volts X X(2) & X (3)
(3)
Regulation Test at Operating Temperature X
Cold Resistance Measurement of Insulated X X X X X
Windings
Insulated Resistance Measurement of Insulated X X X X X
Windings
Dielectric Strength Test in accordance with Table X X X X X
4/5C.2
End Play Setting (3) X X X X
Bearing Temperatures X X
Measurement of Air gap X X X X
Commutation Check X X
Running Balance at Rated Speed (4) X X X X X
Verification of steady short circuit conditions in X
accordance with 4/5C2.19.2c for A.C. Generator`
(5)
Overload/overcurrent test in accordance with X X
4/5C2.6

Notes
(1) On synchronous machine, zero power factor heat run may be taken in lieu of full-load run.
(2) On synchronous machine, a no-load V curve may be taken in lieu of this test.
(3) Applies only to machines supplied with complete set of bearings.
(4) Static balance (machine rated 500 rpm or less) or dynamic balance (over 500 rpm) will be accepted in lieu of the specified
test on engine-type machines supplied without shaft and/or bearings, or with incomplete set of bearings.
(5) Verification of steady short circuit condition applies to synchronous machines only.

PART 4 SECTION 5|45 Electrical Installations -- Part C. Machinery and Equipment


Table 4/5C.2 Dielectric Strength Test
for Rotating Machines
[See 4/5C2.7]
Item Machine or Part Test Voltage (A.C .r.m.s)
1 Insulated windings of rotating machines having 500 V + twice the rated voltage
rated output less than 1 kVA, and of rated voltage
less than 100 V with the exception of those in items
4 to 8.
2 Insulated windings of rotating machines having 1,000 V + twice the rated voltage with
rated output less than 10,000 kVA with the minimum of 1,500 V (See Note 1)
exception of those in items 1 and 4 to 8 (See Note
2).
3 Insulated windings of rotating machines having 1,000 V + twice the rated voltage
rated output 10,000 kVA or more, and of rated
voltage (see Note 1) up to 2,000 V with the
exception of those in items 4 to 8 (see Note 2).
4 Separately-excited field windings of D.C. 1,000 V + twice the maximum rated circuit
machines. voltage with minimum of 1,500 V (See Note
1).
5 Field windings of synchronous generators and
synchronous motors
a) Field windings of synchronous generators Ten times the rated excitation voltage with a
minimum of 1,500 V and a maximum of 3,500
V.
b) When the machine is intended to be started with the Ten times the rated excitation voltage with a
field winding short-circuited or connected across a minimum of 1,500 V and a maximum of 3,500
resistance of value less than ten times the resistance V.
of winding.
c) When the machine will be started either with: 1,000 V + twice the maximum value of the
- the field winding connected across resistance voltage with a minimum of 1,500 V
of more than ten times of the field winding - between the terminals of the field winding,
resistance, or or
- the field windings on open circuit or without - between the terminals of any section for
a field dividing switch. a sectionalized field winding,
which will be occurred under the specified
starting conditions (see Note 3).
6 Secondary (usually rotor) windings of induction
motors or synchronous induction motors if not
permanently short-circuited (e.g., if intended for
rheostatic starting)
a) For non-reversing motors or motors reversible from 1,000 V + twice the open-circuit standstill
standstill only. voltage as measured between slip-rings or
secondary terminals with rated voltage applied
to the primary windings
b) For motors to be reversed or braked by reversing 1,000 V + four times the open-circuit standstill
the primary supply while the motor is running. secondary voltage as defined in item 6.a
above.

PART 4 SECTION 5|46 Electrical Installations -- Part C. Machinery and Equipment


Table 4/5C.2 Dielectric Strength Test
(continued) for Rotating Machines
[See 4/5C2.7]

Item Machine or Part Test Voltage (A.C. r.m.s)


7 Exciters (except as listed below) As for windings to which they are connected.
Exception 1 - Exciters of synchronous motors 1,000 V + twice the rated exciter voltage with a
(including synchronous induction motors) if minimum of 1,500 V.
connected to earth or disconnected from the field
winding during starting
Exception 2 - Separately excited field windings of
exciters (see Item 4 above).
8 Assembled group of machines and apparatus. A repetition of the tests in items 1 to 7 above is
to be avoided if possible. But, if a test on an
assembled group of several pieces of new
apparatus, each one is made, the test voltage to
be applied to such assembled group is to be
80% of the lowest test voltage appropriate for
any part of the group (see Note 4).

Note:
(1) For two-phase windings having one terminal in common, the rated voltage for the purpose of calculating the test voltage
is to be taken as 1.4 times the voltage of each separate phase.
(2) High-voltage tests on machines having graded insulation is to be subject to special consideration.
(3) The voltage, which is occurred between the terminals of field windings or sections thereof under the specified starting
conditions, may be measured at any convenient reduced supply voltage. The voltage so measured is to be increased in the
ratio of the specified starting supply voltage to the test supply voltage.
(4) For windings of one or more machines connected together electrically, the voltage to be considered is the maximum
voltage that occurs in relation to earth.

PART 4 SECTION 5|47 Electrical Installations -- Part C. Machinery and Equipment


Table 4/5C.3 Limits of Temperature Rise for Air-Cooled
Rotating Machines
[See 4/5C2.9.1]
Ambient Temperature = 50 oC (122 oF)

Temperature Class of Insulation


Item Part of Machine Measuring A E B F H
o
No. Method (Limit of Temperature Rise in C)
1 A.C. windings of machines having Resistance 50 60 70 90 115
rated output of 5,000 kVA or more, or
having a core length of one meter or Embedded 50 60 70 90 115
more. 1) Temp. Detector.
2 a) A.C. windings of machines having
rated output less than 5,000 kVA or Thermometer 40 55 60 75 95
having a core length less than one Resistance 50 65 70 90 115
meter.
b) Field windings of A.C. and D.C. Thermometer 40 55 60 75 95
machines having excitation other than Resistance 50 65 70 90 115
those in items 3 & 4 below.
c) Windings of armatures having Thermometer 40 55 60 75 95
commutators. Resistance 50 65 70 90 115
3 Field windings of turbine type Resistance - - 80 100 -
machines having D.C. excitation.
4 a) Low-resistance field windings of more Thermometer 50 65 70 90 115
than one layer, and compensating Resistance 50 65 70 90 115
windings.
b) Single-layer windings with exposed Thermometer 55 70 80 100 125
bare or varnished metal surfaces. 2) Resistance 55 70 80 100 125
5 Permanently short-circuited insulated Thermometer 50 65 70 90 115
windings.
6 Permanently short-circuited The temperature rise of these parts is
uninsulated windings. not to reach such a value that there is
7 Magnetic core and other parts not in a risk of injury to any insulating or
contact with windings. other material on adjacent parts.
8 Magnetic core and other parts not in Thermometer 50 65 70 90 115
contact with windings.
9 Commutators and slip-rings, open or Thermometer 50 60 70 80 90 4)
enclosed. 3)
(1) The Embedded Temperature Detector method may be used in machines having outputs less than 5,000 kVA or having a
core length less than one meter, but the limits of temperature rise given in this item is to be applied.
(2) Also includes multiple-layer field windings provided that the underlayers are each in contact with the circulating
coolant.
(3) The temperature rises in item 9 are permissible provided that insulation appropriate to the temperature rise is used,
except when the commutator or slip-ring is adjacent to windings in which case the temperature rise is not to exceed
that for the winding insulation class. The values of temperature rises given apply only to measurements made by bulb
thermometers.
(4) Subject to special consideration in using temperature rises 90 oC (162 oF) in selection of brush grades.

See “Remark” in next page:

PART 4 SECTION 5|48 Electrical Installations -- Part C. Machinery and Equipment


Table 4/5C.3 Limits of Temperature Rise for Air-Cooled
(continued) Rotating Machines
[See 4/5C2.9.1]
[Remark for Table 4/5C.3]
(1) The limit of temperature rise in the above Table are based on an ambient temperature of 50 oC (122 oF). For 40 oC (104
o
F) ambient, the temperature rises may be increased 10 oC (18 oF).
(2) If air-to-water heat exchangers are used, the temperature rise will be specified with respect to the temperature of the
cooling water at inlet of the cooler. In this case, the temperature rise of the above Table is to be increased by 20 oC (36 oF),
but only if the specified inlet water temperature does not exceed 30 oC (86 oF). When commutators of these machines are
not in the enclosed air circuit cooled by water cooler, but are cooled by the ambient cooling air, the permissible temperature
rise above the ambient cooling air is to be the same as for ventilated machine.
(3) Where the machine is designed to operate with a coolant at temperature more (or less) then ambient temperature of 50
o
C (122 oF), the permissible temperature rises may be increased (or decreased) in accordance with the given ambient
temperature. The permissible temperature rises are to be taken to the nearest whole Celsius degrees.

[Conversion Table between Celsius (oC) and Fahrenheit (oF) for Temperature Rise]

Celsius (oC) 50 55 60 65 70 75 80 90 95 100 115 125


Fahrenheit (oF) 90 99 108 117 126 135 144 162 171 180 207 225

PART 4 SECTION 5|49 Electrical Installations -- Part C. Machinery and Equipment


Table 4/5C.4 Nameplates

a. Rotating Machines [See 4/5C2.11.9]


The manufacturer's Name
The manufacturer's serial number (or identification mark)
The year of manufacture
Type of Machine(Generator or motor, etc.)
Degree of protection enclosures (by IP code)
Class of rating or duty type
The rated output
The rated voltage
The rated current and type of current (A.C. or D.C.)
The rated speed (r.p.m.) or speed range
The class of insulation or permissible temperature rise
The ambient temperature

Number of phase (for A.C. machines)


The rated frequency (for A.C. machines)
Power factor (for A.C. machines)
Type of winding (for D.C. machines)

Exciter voltage (for synchronous machines or D.C. machines with separate excitation)
Exciter current at rating (for synchronous machines or D.C. machines with separate excitation)
Open-circuit voltage between slip-rings and the slip-ring current for rated conditions (for wounded-rotor
induction machines)

b. Accumulator Battery [See 4/5C3.3.3]


The manufacturer's name
The type designation
The rated voltage
The ampere-hour rating at a specific rate of discharge
The specific gravity of the electrolyte
(in the case of a lead-acid battery, the specific gravity when the battery is fully charged).

c. Transformer [See 4/5C5.5.3]


The manufacturer's name
The manufacturer's serial number (or identification mark)
The year of manufacture
The number of phases
The rated power
The rated frequency
The rated voltage in primary and secondary sides
The rated current in primary and secondary sides
The class of insulation or permissible temperature rise
The ambient temperature

d. Semiconductor Converter [See 4/5C6.5.4]


The manufacturer's name
The identification number of the equipment

PART 4 SECTION 5|50 Electrical Installations -- Part C. Machinery and Equipment


Table 4/5C.5 Factory Testing Schedule for Switchboards,
Chargers, Motor Control Centers,
and Controllers
[See 4/5C4.3.1]
(1) Insulation resistance measurements in accordance with 4/5C4.5
(2) Dielectric strength test in accordance with 4/5C4.7 and the Table below
(3) Protective device tripping test, such as overcurrent tripping, selective tripping, preferential tripping, etc.
(4) Inspection of the assembly including inspection of wiring and, if necessary, electrical operation test.

Standard Test Voltage for Dielectric Strength Test

Rated Insulation Voltage, Dielectric Test Voltage


A.C. - r.m.s
Up to and including 12 V 250 V
over 12 V to 60 V inclusive 500 V
over 60 V to 300 V inclusive 2000 V
over 300 V to 690 V inclusive 2500 V
over 690 V to 800 V inclusive 3000 V
over 800 V to 1000 V inclusive 3500 V
over 1000 V to 1500 V inclusive - * 3500 V
[Note] * : For Direct-current (D.C.) only

Table 4/5C.6 Clearance and Creepage Distance for


Switchboards, Distribution boards, Chargers,
Motor Control Centers and Controllers 1
[See 4/5C4.11.6]
Rated insulation voltage (V) Minimum clearances mm (in.) Minimum creepage distances mm
(in.)
Up to 250 15 (19/32) 20 (25/32)
From 251 to 660 20 (25/32) 30 (1 3/16)
Above 6602 25 (1) 35 (1 3/8)

[Note]
1 The values in this table apply to clearances and creepage distances between live parts as well as between live parts and
exposed conductive parts, including earthing.
2 For 1 kV to 11 kV systems, see 4/5D1.1.4.

PART 4 SECTION 5|51 Electrical Installations -- Part C. Machinery and Equipment


Table 4/5C.7 Equipment and Instrumentation
for Switchboard
[See 4/5C4.15.4]

Instrumentation and Alternating-current (A.C.) Switchboard Direct-current (D.C.) Switchboard


Equipment
1. Pilot Lamp A pilot lamp for each generator connected A pilot lamp for each generator connected
between generator and circuit breaker. between generator and circuit breaker.
See Note 3.
2. Generator A generator switch or disconnecting links A generator switch, or disconnecting
Disconnect in series with the generator circuit breaker links, in series with the circuit breaker
which is to disconnect completely all which will open positive, negative,
leads of the generator and the circuit neutral and equalizer leads, except that
breaker from the buses except the earth for 3-wire generators equalizer poles may
lead. See Note 1. be provided on the circuit breaker. For 3-
wire generators the circuit breakers are to
protect against a short circuit on the
equalizer buses. See Note 1.
3. Field Rheostat A field rheostat for each generator and A field rheostat for each generator. See
each exciter. See Note 2. Note 2.
4. Insulation A means for continuously monitoring the A means for continuously monitoring the
Monitor and electrical insulation level to earth, and an electrical insulation level to earth, and an
Alarm audible or visual alarm for abnormally audible or visual alarm for abnormally
low insulation values. See Note 3. low insulation values. See Note 3.
5. Ammeter An ammeter for each generator with a An ammeter for each 2-wire generator.
selector switch to read the current of each For each 3-wire generator an ammeter for
phase. See Note 3. each positive and negative lead and a
center-zero ammeter in the earth
connection at the generator switchboard.
Ammeters are to be so located in the
circuit as to indicate total generator
current.
6. Voltmeter A voltmeter for each generator, with a A voltmeter for each generator with
selector switch to each phase of the voltmeter switch for connecting the
generator and to one phase of the bus. See voltmeter to indicate generator voltage
Note 3. and bus voltage. For each 3-wire
generator, a voltmeter with voltmeter
switch for connecting the voltmeter to
indicate generator voltage, positive to
negative, and bus voltage positive to
negative, positive to neutral, and neutral
to negative. Where permanent provisions
for shore connections are fitted, one
voltmeter switch to provide also for
reading shore-connection voltage,
positive to negative
7. Space Heater Where electric heaters are provided for Where electric heaters are provided for
Pilot Lamp generators, a heater pilot lamp is to be generators, a heater pilot lamp is to be
fitted for each generator. fitted for each generator.

PART 4 SECTION 5|52 Electrical Installations -- Part C. Machinery and Equipment


Table 4/5C.7 Equipment and Instrumentation
(continued) for Switchboard
[See 4/5C4.15.4]
Instrumentation and Alternating-current (A.C.) Switchboard Direct-current (D.C.) Switchboard
Equipment
8. Synchroscope A synchroscope or synchronizing lamps Not applicable
or Lamps with selector switch for paralleling in any
combination. See Note 3.
9. Prime mover Control for prime mover speed for Not applicable
Speed Control paralleling. See Note 3.
10. Wattmeter Where generators are arranged for Not applicable
parallel operation, an indicating
wattmeter is to be fitted for each
generator. See Note 3.
11. Frequency A frequency meter with selector switch to Not applicable
Meter connect to any generator. See Note 3.
12. Field Switch A double-pole field switch with discharge Not applicable
clips and resistor for each generator. See
Note 2.
13. Voltage A voltage regulator. See Note 3.
Regulator
14. Stator Winding For alternating current generator above For direct current propulsion generator
Temperature 500 kW, a stator winding temperature above 500 kW, an interpole winding
Indicator indicator is to be fitted for each generator temperature indicator is to be fitted for
control panel. See Notes 3 and 4. each generator control panel. See Notes
3 and 4.

[Notes]
(1) The switch or links may be omitted when draw-out or plug-in mounted generator breakers are furnished.
(2) For generators with variable voltage exciters or rotary amplifier exciters, each controlled by voltage-regulator unit acting
on the exciter field, the field switch, the discharge resistor and generator field rheostat may be omitted.
(3) Where craft have centralized control systems in accordance with Section 4/11 and the generators can be paralleled from
the main control station, this equipment may be mounted on the control console.
(4) For high voltage systems, see also 4/5D1.11.1c.

Table 4/5C.8 Temperature Rise for Transformers1, 2


[See 4/5C5.3]

Insulation Class Copper Temperature Rise Hottest Spot


by Resistance Temperature Rise
Class A 55 oC(99 oF) 65 oC (117 oF)
Class B 80 oC (144 oF) 110 oC (198 oF)
Class F 115 oC (207 oF) 145 oC (261 oF)
Class H 150 oC (270 oF) 180 oC (324 oF)

[Note]
1 Metallic parts in contact with or adjacent to insulation are not to attain a temperature in excess of that allowed
for the hottest-spot copper temperature adjacent to that insulation.
2 Temperature rises are based on an ambient temperature of 40C. See 4/5C5.3.

PART 4 SECTION 5|53 Electrical Installations -- Part C. Machinery and Equipment


Table 4/5C.9 Types of Cable Insulation
[See 4/5C7.1.4]

Insulation Type Designation Insulation Materials Maximum Conductor


Temperature
V60, PVC/A Polyvinyl Chloride 60 oC (140 oF)
- General purpose
V75, PVC/A Polyvinyl Chloride 75 oC (167 oF)
- Heat resisting
R85, XLPE Cross-linked Polyethylene 85 oC (185 o F)
E85 Ethylene Propylene Rubber 85 oC (185 oF)
M95 Mineral (MI) 95 oC (203 oF) *
S95 Silicone Rubber 95 oC (203 oF)

* A maximum conductor temperature of 250 oC (482 oF) is permissible for special applications and standard end fittings may
be used provided the temperature does not exceed 85 oC(185 oF) at the end of fittings. However, when the temperature at the
end of fittings is higher than 85 oC (185 oF), special consideration will be given to an appropriate end fitting.

PART 4 SECTION 5|54 Electrical Installations -- Part C. Machinery and Equipment


Table 4/5C.10 Maximum Current Carrying Capacity for
Insulated Copper Wires and Cables
[See 4/5C7.1.1]
Values in amperes
45oC (113oF) Ambient
750V and Less (A.C. or D.C.)
Conductor Size 1/C TYPE 2/C TYPE 3-4/C TYPE

103 V60 V75, R85, M95, V60 V75, R85, M95, V60 V75, R85, M95,
circ PVC/A Heat XLPE, S95 PVC/A Heat XLPE, S95 PVC/A Heat XLPE, S95
mm2 mils 60oC Resist. E85 95oC 60oC Resist. E85 95oC(2 60oC Resist. E85 95oC(2
(140oF) PVC 85oC (203oF) (140oF) PVC 85oC 03oF) (140oF) PVC 85oC(1 03oF)
75oC (185oF) 75oC (185oF) 75oC 85oF)
(167oF) (167oF) (167oF)
625 755 894 1006 642 760 855 529 626 704
600 736 872 981 626 741 834 515 610 687
1000 662 784 882 563 666 750 463 549 617
500 656 778 875 558 661 744 459 545 613
950 641 760 854 545 646 726 449 532 598
900 620 734 826 527 624 702 434 514 578
850 598 709 797 508 603 677 419 496 558
800 576 682 767 490 580 652 403 477 540
400 571 677 761 485 575 647 400 474 533
750 553 655 737 470 557 626 387 459 516
700 529 628 706 450 534 600 370 440 494
650 506 599 674 430 509 573 354 419 472
600 481 570 641 409 485 545 337 399 449
300 335 477 565 636 285 405 480 541 235 334 396 445
550 455 540 607 387 459 516 319 378 425
500 429 509 572 365 433 486 300 356 400
240 290 415 492 553 247 353 418 470 203 291 344 387
450 402 476 536 342 405 456 281 333 375
400 373 442 498 317 376 423 261 309 349
185 250 353 418 470 213 300 355 400 175 247 293 329
350 343 407 458 292 346 389 240 285 321
300 312 370 416 265 315 354 218 259 291
150 220 309 367 412 187 263 312 350 154 216 257 288
250 278 330 371 236 281 315 195 231 260
120 190 269 319 359 162 229 271 305 133 188 223 251
212 251 297 335 213 252 285 176 208 235
95 165 232 276 310 140 197 235 264 116 162 193 217
168 217 257 289 184 218 246 152 180 202
70 135 192 228 256 115 163 194 218 95 134 160 179
133 188 222 250 160 189 213 132 155 175
106 163 193 217 139 164 184 114 135 152
50 105 156 184 208 89 133 156 177 74 109 129 146
83.7 140 166 187 119 141 159 98 116 131
35 87 125 148 166 74 106 126 141 61 88 104 116
66.4 121 144 162 103 122 138 85 101 113

PART 4 SECTION 5|55 Electrical Installations -- Part C. Machinery and Equipment


Table 4/5C.10 Maximum Current Carrying Capacity for
(continued) Insulated Copper Wires and Cables
[See 4/5C7.1.1]
Values in amperes
45oC (113oF) Ambient
750V and Less (A.C. or D.C.)
Conductor Size 1/C TYPE 2/C TYPE 3-4/C TYPE

103 V60 V75, R85, M95, V60 V75, R85, M95, V60 V75, R85, M95,
circ PVC/A Heat XLPE, S95 PVC/A Heat XLPE, S95 PVC/A Heat XLPE, S95
mm2 mils 60oC Resist. E85 95oC 60oC Resist. E85 95oC(2 60oC Resist. E85 95oC(2
(140oF) PVC 85oC (203oF) (140oF) PVC 85oC 03oF) (140oF) PVC 85oC(1 03oF)
75oC (185oF) 75oC (185oF) 75oC 85oF)
(167oF) (167oF) (167oF)
52.6 105 124 140 89 105 119 74 87 98
25 71 101 120 135 60 86 102 115 50 71 84 95
41.7 91 108 121 77 92 103 64 76 85
33.1 79 93 105 67 79 89 55 65 74
16 54 76 91 102 46 65 77 87 38 53 64 71
26.3 68 81 91 58 69 77 48 57 64
20.8 59 70 78 50 60 66 41 49 55
10 40 57 67 76 34 48 57 65 28 40 47 53
16.5 51 60 68 43 51 58 36 42 48
6 29 41 49 55 25 35 42 47 20 29 34 39
10.4 38 45 51 32 38 43 27 32 36
4 22 32 38 43 19 27 32 37 15 22 27 30
6.53 28 34 38 24 29 32 20 24 27
2.5 17 24 28 32 14 20 24 27 12 17 20 22
4.11 21 25 32 18 21 27 15 18 22
1.5 12 17 21 26 10 14 18 22 8 12 15 18
1.25 15 18 23 13 15 20 11 13 16
1.0 8 13 16 20 7 11 14 17 6 9 11 14

[Notes]
(1) The values give above have been calculated for an ambient of 45 oC (113 oF) and assume that a conductor temperature
equal to the maximum rated temperature of the insulation is reached and maintained continuously in the case of a group of
four cables bunched together and laid in free air.
(2) The current rating values give in Table 4/5.C10 (and those derived therefrom) may be considered applicable, without
correction factors, in cable conduits or cable pipes, except as noted in Note 3.
(3) For bunched cables, see 4/5B3.11.1
(4) These current ratings are applicable for both armored and unarmored cables.
(5) If ambient temperature differs from 45 oC (113 oF), the values in Table 4/5.C10 are to be multiplied by the following
factors.

Maximum
Conductor Ambient Correction Factor
Temperature
40oC (104oF) 50oC (122oF) 55oC (131oF) 60oC (140oF) 65oC (149oF) 70oC (158oF)
o o
60 C (140 F) 1.15 0.82 -- -- -- --
75oC (167oF) 1.08 0.91 0.82 0.71 0.58 ---

PART 4 SECTION 5|56 Electrical Installations -- Part C. Machinery and Equipment


Maximum
Conductor Ambient Correction Factor
Temperature
40oC (104oF) 50oC (122oF) 55oC (131oF) 60oC (140oF) 65oC (149oF) 70oC (158oF)
o o
80 C (176 F) 1.07 0.93 0.85 0.76 0.65 0.53
85oC (185oF) 1.06 0.94 0.87 0.79 0.71 0.61
95oC (203oF) 1.05 0.95 0.89 0.84 0.77 0.71

(6) Where the number of conductors in a cable exceeds 4,, as in control cables, the maximum current carrying capacity of
each conductor is to be reduced as in the following table.

No. of Conductors % of 3-4/C TYPE Values in Table 4/5.C10


5-6 80
7 - 24 70
25 - 42 60
43 and above 50

(7) When a mineral-insulated cable is installed in such a location that its copper sheath is liable to be touched when in
service, the current rating is to be multiplied by the correction factor 0.80 in order that the sheath temperature does not
exceed 70 oC (158 oF).
(8) Cables being accepted based on approved alternate standard may have current carrying capacity of that standard provided
the cables are in full compliance with that standard.

PART 4 SECTION 5|57 Electrical Installations -- Part C. Machinery and Equipment


b Creepage Distance Creepage distances
Part D. Specialized between live parts and between live parts and earthed
Installations metal parts are to be adequate for the nominal voltage
of the system, due regard being paid to the
comparative tracking index of insulating materials
4/5D1 High Voltage Systems under moist conditions according to the IEC
Publication 112 and to the transient overvoltage
4/5D1.1 General developed by switching and fault conditions.

4/5D1.1.1 Application 4/5D1.3 System Design


The following requirements in this sub-section are
applicable to systems with nominal voltage (phase to 4/5D1.3.1 Selective Coordination
phase) exceeding 1 kV and up to 11 kV. For systems Selective coordination is to be in accordance with
with nominal voltages exceeding 11 kV a recognized 4/5A5.1.5, regardless of the system neutral earthing
standard will be considered. Unless stated otherwise, arrangement.
high voltage equipment and systems are to comply
with the other parts in Section 4/5 for low voltage 4/5D1.3.2 Earthed Neutral Systems
equipment and systems as well. a Current Due to Earth Fault Whatever the
earthing method (resistor or other limiting device), in
4/5D1.1.2 Standard Voltages and Frequency case of an earth fault the current is not to be greater
The nominal standard voltages/frequencies than the full load current of the largest generator on
recommended are 3.0 kV, 3.3 kV, 6.0 kV, 6.6 kV, 10 the switchboard but not less than three times the
kV and 11 kV at 50 or 60 hertz. Other minimum current required to operate any device
voltage/frequencies in accordance with a recognized against an earth fault.
national standard will be considered provided that b Equipment Electrical equipment is to
the entire system is designed to that standard. withstand the earth fault current for the time
necessary to trip the protective device.
4/5D1.1.3 Distribution Systems c Other Standard or Code Special consideration
The following distribution systems can be used: will be given to directly earthed neutral or other
proposed earth neutral systems designed to other
- 3 phase 3 wire with insulated neutral, or recognized standards or code of practices.
- 3 phase 3 wire with earthed neutral.
4/5D1.3.3 Neutral Disconnection
Earthed neutral systems are permitted only outside Each generator neutral is to be provided with means
hazardous areas. for disconnection.

4/5D1.1.4 Air Clearance and Creepage Distance 4/5D1.3.4 Hull Connection of Earthing Resistors
a Air Clearance Phase-to-phase air clearances All earthing resistors are to be connected to the hull.
and phase-to-earth air clearances between non- Neutral earth resistors or devices are to be
insulated parts are to be not less than the minimum as individually connected to the hull and also bonded to
specified below. each other. Additionally, the earth resistors or devices
for connection of the neutrals to the hull are to be
provided for each section of the system.
Nominal Voltage in kV Minimum air
clearance in mm (in.) 4/5D1.3.5 Interconnection of Neutrals
Generators running in parallel may have a common
1 - 1.1 25 (1.0) neutral conductor to earth provided the third
3 - 3.3 55 (2.2) harmonic content of the wave form is 5% or less.
Otherwise, individual resistors are to be provided for
6 - 6.6 90 (3.6)
neutral connection to earth of each generator.
10 - 11 120 (4.8)
4/5D1.3.6 Earth Fault Detection
Where intermediate values of nominal voltages are An earth fault is to be indicated by visual and audible
accepted, the next higher air clearance is to be means. Rapid isolation is to be provided unless the
observed. Where necessary, these distances are to be system is designed to operate continuously with an
increased to allow for the electromagnetic forces earth fault.
involved. In the case of smaller distances,
appropriate voltage impulse test is to be applied.

PART 4 SECTION 5|59 Electrical Installations -- Part D. Specialized Installations


4/5D1.5 Auxiliary Systems 4/5D1.9 Equipment Installation and Arrangement

4/5D1.5.1 Source of Supply 4/5D1.9.1 Degree of Protection


Where electrical energy or mechanical energy is The degree of equipment protection is to be in
required for the operation of circuit breakers and accordance with Table 4/5B.1.
switches, a means of storing such energy is to be
provided with a capacity at least sufficient for two 4/5D1.9.2 Protective Arrangements
on/off operation cycles of all the components. a Interlocking Arrangements Where high-
However, the tripping due to overload or short- voltage equipment is not contained in an enclosure
circuit, and under-voltage is to be independent of any but a room forms the enclosure of the equipment, the
stored electrical energy sources. This does not access doors are to be so interlocked that they cannot
preclude shunt tripping be opened until the supply is isolated and the
equipment earthed down.
4/5D1.5.2 Number of Supply Sources b Warning Plate At the entrance of such spaces,
At least one independent source of supply for a suitable marking is to be placed which indicates
auxiliary circuits of each independent section of the danger of high-voltage and the maximum voltage
system is to be provided. inside the space. For high-voltage electrical
equipment installed outside these spaces, a similar
4/5D1.7 Protection marking is to be provided.

4/5D1.7.1 Generator 4/5D1.9.3 Cables


Protection against interwinding faults within the a Runs of Cables High voltage cables are not to
generator is to be provided. This is to trip the be run through accommodation spaces. If not
generator circuit breaker and de-excite the generator. practicable, special consideration will be given to
such installation.
4/5D1.7.2 Power Transformers b Segregation High voltage cables are to be
If the total connected load of all outgoing circuits of segregated from cables operating at lower voltages; in
the power transformer secondary side exceeds the particular, they are not to be run either in the same
rated load, an overload protection or an overload cable bunch, the same ducts or pipes, or, in the same
alarm is to be fitted. When transformers are box. Other suitable equivalent arrangement may be
connected in parallel, tripping of the protective accepted.
devices at the primary side is to automatically trip the Higher voltage equipment are not to be combined
switch or protective devices connected at the with lower voltage equipment in the same enclosure,
secondary side. unless segregation or other suitable measures are
taken to ensure safe access to lower voltage
4/5D1.7.3 Voltage Transformers for Control and equipment.
Instrumentation c Installation Arrangements High voltage
Voltage transformers are to be protected against cables, are to be installed on cable trays or equivalent
short-circuit by fuses on the primary and secondary when they are provided with a continuous metallic
sides. Special consideration will be given to omitting sheath or armor which is effectively bonded to earth;
fuses on the primary side or to fitting automatic otherwise they are to be installed for their entire
circuit breakers on the secondary side instead of length in metallic ducting or pipes effectively bonded
fuses. to earth.
d Termination and Splices Terminations in all
4/5D1.7.4 Fuses conductors of high voltage cables are to be, as far as
Fuses may be used for short-circuit protection but not practicable, effectively covered with suitable
for overload protection. insulating material. In terminal boxes, if conductors
are not insulated, phases are to be separated from
4/5D1.7.5 Low Voltage Systems earth and from each other by substantial barriers of
Lower voltage systems supplied through transformers suitable insulating materials. Precautions are to be
from high voltage systems are to be protected against taken to relieve the electrical stresses where cable
overvoltages due to loss of insulation between insulation is terminated. Terminations and splices are
primary and secondary windings. Direct earthing of to be of a type compatible with the insulation and
the lower voltage system or appropriate neutral jacket material of the cable and are to be provided
voltage limiters may be fitted. Special consideration with means to earth all metallic shielding components
will be given to the use of an earthed screen between (i.e. tapes, wires, etc.)
the primary and secondary windings of high voltage e Marking High voltage cables are to be readily
transformers. identifiable by suitable marking.

PART 4 SECTION 5|60 Electrical Installations -- Part D. Specialized Installations


f Test after Installation After installation, high e Circuit Breakers Circuit breakers are to be of
voltage cables are to be subjected to a voltage test the withdrawable type or fitted with equivalent means
with a D.C. voltage of 4 times the rated phase to earth or arrangements permitting safe disconnection whilst
voltage (Uo) applied for 15 minutes. the bus bars are live.
f Locking Facilities Withdrawable circuit
4/5D1.11 Machinery and Equipment breakers and switches are to be provided with
mechanical locking facilities in both service and
4/5D1.11.1 Rotating Machines disconnected positions. For maintenance purposes,
a Protection Rotating machines are to have a key locking of withdrawable circuit breakers,
degree of protection of at least IP23; for terminal box, switches and fixed disconnectors are to be possible.
IP44, and for motors accessible to unqualified Withdrawable circuit breakers when in the service
personnel, IP43. position are to have no relative motion between fixed
b Windings Generator stator windings should and moving parts.
have all phase ends brought out. g Shutters The fixed contacts of withdrawable
c Temperature Detectors Rotating machines are circuit breakers and switches are to be so arranged
to be provided with temperature detectors in their that in the withdrawable position the live contacts are
stator windings to actuate a visual and audible alarm automatically covered.
in a normally attended position whenever the h Earthing and Short-circuiting For
temperature exceeds the permissible limit. If maintenance purposes, an adequate number of
embedded temperature detectors are used, means are earthing and short-circuiting devices is to be provided
to be provided to protect the circuit against to enable circuits to be worked upon with safety.
overvoltage. i Tests A power frequency voltage test is to be
d Cooler Water-air heater exchangers of rotating carried out on high voltage switchgear and
machines are to be of the double tube type. In a controlgear assemblies using the following test
normally attended position a visual and audible alarm voltages in accordance with the procedures of IEC
is to be given to monitor water cooler leakage. Publication 298 or other equivalent standards.
e Space Heater Effective means are to be
provided to prevent the accumulation of moisture and Nominal Voltage (phase Test Voltage (kV)
condensation within the machines when they are idle. to phase) (kV)
f Tests A high voltage test is to be carried out 2.5 - 3.6 10
on the individual coils in order to demonstrate a 3.6 - 7.2 20
satisfactory withstand level of the interwinding turn 7.2 - 11 28
insulation to steep fronted switching surges. This test
applies to coils for rotating machines to be used for Nominal voltage exceeding 1 kV up to voltages
either earth or insulated systems. The peak test below 2.5 kV will be specially considered.
voltage is to be that calculated by: Vt = 2.45V, 4/5D1.11.3 Transformers
where V is the nominal voltage of the system. Each a Protection Transformers are to have a degree
coil is to be subject to at least five impulses. of protection of at least IP44. However, when
Alternative procedures recommended by the installed in spaces accessible to qualified personnel
manufacturer will be considered. only the degree of protection may be reduced to
4/5D1.11.2 Switchgear and Controlgear IP2X. For transformers not contained in enclosures,
Assemblies see 4/5D1.9.1.
Switchgear and controlgear assemblies are to be
b Condensation Effective means to prevent
constructed according to the IEC Publication 298 and
accumulation of moisture and condensation within the
the following additional requirements:
transformers (when de-energized) is to be provided.
a Protection Switchgear, controlgear assemblies
and converters are to have a degree of protection of at
4/5D1.11.4 Miscellaneous Equipment
least IP23. Equipment is to comply with the following IEC
b Mechanical Construction Switchgear should Publication or other recognized standards:
be of metal - enclosed type in accordance with IEC
Publication 298 or of the insulation - enclosed type in 1 Circuit Breakers IEC 56
accordance with IEC Publication 466.
2 Switches IEC 265
c Configuration The distribution switchboard is
3 Fuses IEC 282
to be divided in accordance with 4/5C4.15.2;
4 Contactors IEC 470
however, the main bus bars are to be connected by
5 Current Transformers IEC 185
circuit breakers, switches or switch disconnectors.
6 Voltage Transformers IEC 186
d Clearance and Creepage Distances For
7 Relay IEC 255
clearance and creepage distances, see 4/5D1.1.4.

PART 4 SECTION 5|61 Electrical Installations -- Part D. Specialized Installations


4/5D1.11.5 Cables b Single System If a propulsion system contains
a Standards Cables are to be constructed to IEC only one generator and one motor and cannot be
Publication 92-3, 92-354, or other equivalent connected to another propulsion system, more than
recognized standard. See also 4/5C7.1 one exciter set is to be provided for each machine.
b Rated Voltage In a system with insulated However, this is not necessary for self-exited
neutral, the rated phase to earth voltage (Uo) of the generators or for multi-propeller propulsion craft
cables is to be not less than the nominal voltage of the where any additional exciter set may be common for
system. For an earth neutral system, the rated phase the craft.
to phase voltage (Un) is to be not less than the c Multiple Systems Systems having two or more
nominal voltage of the system. See IEC Publication propulsion generators, two or more semiconductor
183. converters, or two or more motors on one propeller
shaft are to be so arranged that any unit may be taken
out of service and disconnected electrically without
4/5D2 Electric Propulsion System preventing the operation of the remaining units.
d Excitation Systems Arrangements for electric
4/5D2.1 Application propulsion generators are to be such that propulsion
can be maintained in case of failure of an excitation
The following requirements in this sub-section are system or failure of a power supply for an excitation
applicable to electric propulsion system. The electric system. Propulsion may be at reduced power under
propulsion system complying with other recognized such conditions where two or more propulsion
standard will be considered. Unless stated otherwise, generators are installed provided such reduced power
electric propulsion equipment and systems are to is sufficient to provide for a speed of not less than 7
comply with the applicable requirements in other knots or 1/2 of design speed whichever is the lesser.
parts of Section 4/5 as well. e Features for Other Services If the propulsion
generator is used for other purposes than for
4/5D2.3 Plans and Data to be Submitted propulsion, such as dredging, and other special
services, overload protection in the auxiliary circuit
In addition to the plans and data to be submitted in and means for making voltage adjustments are to be
accordance with 4/5A1, 4/5B1, and 4/5C1, the provided at the control board. When propulsion
following plans and data are to be submitted for alternating-current generators are used for other
review. services for operation in port, the port excitation
control is to be provided with a device that is to
- One line diagrams of propulsion control system operate just below normal idling speed of the
for power supply, circuit protection, alarm, generator to remove excitation automatically.
monitoring, safety and emergency shutdown
systems including list of alarm and monitoring 4/5D2.5.2 Propulsion Excitation
points. a Excitation Circuits Every exciter set is to be
- Plans showing the location of propulsion supplied by a separate feeder. Excitation circuits are
controls and its monitoring stations.
not to be fitted with overload circuit-interrupting
- Arrangements and details of the propulsion
control console or panel including schematic devices except those intended to function in
diagram of the system therein. connection with the protection for the propulsion
- Arrangements and details of electric coupling. generator. In such cases the field circuit breaker is to
- Arrangements and details of the semiconductor be provided with a discharge resistor unless a
converters enclosure for propulsion system permanent discharge resistor is provided.
including data for semiconductor converter, b Field Circuits Field circuits is to be provided
cooling system with its interlocking arrangement. with means for suppressing voltage rise when a field
switch is opened. Where fuses are used for excitation
4/5D2.5 Propulsion Power Supply Systems circuit protection it is essential that they do not
interrupt the field discharge resistor circuit upon
4/5D2.5.1 Propulsion Generators rupturing.
a Power Supply The power for the propulsion c Craft's Service Generator Connection Where
equipment may be derived from a single generator. If the excitation supply is obtained from the ship's
a craft service generator is also used for propulsion service generators, the connection is to be made to the
purposes, other than for boosting the propulsion generator side of the generator circuit breaker with
power, such generator and power supply circuits to the excitation supply passing through the overload
propulsion systems are also to comply with the current device of the breaker.
applicable requirements in this subsection. See also
4/5A2.1.4.

PART 4 SECTION 5|62 Electrical Installations -- Part D. Specialized Installations


4/5D2.5.3 Semiconductor Converters b Overcurrent Protection Arrangements are to
Semiconductor converter circuits are to be able to be made so that the permissible current of
withstand the transient overcurrents to which the semiconductor elements cannot be exceeded during
system is subject during maneuvering. Where normal operation.
semiconductor converters are connected in parallel, c Short-circuit Protection Fuses are to be
the current for each semiconductor converters is to be provided for protection of short-circuit of
equally distributed as far as practicable. If several semiconductor converters. Visual and audible alarm
elements are connected in parallel and a separate fan are to be provided at the control station for tripping of
is fitted for each parallel branch, arrangements are to these semiconductor protective fuses. In case of
be made for disconnecting the circuit for which blown fuse, the respective part of the plants is to be
ventilation is not available. Where semiconductor taken out of operation.
converters are connected in series, the voltage d Filter Circuits Fuses are to be provided for
between the semiconductor devices are to be equally filter circuits. Visual and audible alarm are to be
distributed as far as practicable. In case of failure of provided at the control station for tripping of the fuse.
the cooling system, an alarm is to be given or the
current is to be reduced automatically. 4/5D2.9 Protection for Earth Leakage

4/5D2.7 Circuit Protection 4/5D2.9.1 Main Propulsion Circuits


Means for earth leakage detection are to be provided
4/5D2.7.1 Setting for the main propulsion circuit and be arranged to
Overcurrent protective devices, if any, in the main operate an alarm upon the occurrence of an earth
circuits are to be set sufficiently high so as not to fault. When the fault current flowing is liable to cause
operate on overcurrents caused by maneuvering or damage, arrangements for opening the main
normal operation in heavy seas or in floating broken propulsion circuit are also to be provided.
ice.
4/5D2.9.2 Excitation Circuits
4/5D2.7.2 Direct-current (D.C.) Propulsion Means are to be provided for earth leakage detection
Circuits in excitation circuits of propulsion machines but may
a Circuit Protection Direct-current propulsion be omitted in circuits of brushless excitation systems
circuits are not to have fuses. Each circuit is to be and of machines rated up to 500 kW.
protected by overload relays to open the field circuits
or by remote-controlled main-circuit interrupting 4/5D2.9.3 Alternating-current (A.C.) Systems
devices. Provision is to be made for closing circuit Alternating-current propulsion circuits are to be
breakers promptly after opening. provided with an earthing detector alarm or indicator.
b Protection for Reversal of the Rotation If the neutral is earthed for this purpose, it is to be
Where separately driven D.C. generators are through an arrangement which will limit the current at
connected electrically in series, means shall be full-rated voltage so that it will not exceed
provided to prevent reversal of the rotation of a approximately 20 amperes upon a fault to earth in the
generator upon failure of the driving power of its propulsion system. An unbalance relay is to be
prime mover. provided which is to open the generator and motor-
field circuits upon the occurrence of an appreciable
4/5D2.7.3 Excitation Circuits unbalanced fault.
An overload protection is not to be provided for
opening of the excitation circuit. 4/5D2.9.4 Direct-current (D.C.) Systems
The earthing detector may consist of a voltmeter or
4/5D2.7.4 Reduction of Magnetic Fluxes lights. Provision is to be made for protection against
Means are to be provided for selective tripping or severe overloads, excessive currents and electrical
rapid reduction of the magnetic fluxes of the faults likely to result in damage to the plant.
generators and motors so that overcurrents do not Protective equipment is to be capable of being so set
reach values which may endanger the plant. as not to operate on the overloads or overcurrents
experienced in a heavy seaway or when maneuvering.
4/5D2.7.5 Semiconductor Converters
a Overvoltage Protection Means are to be 4/5D2.11 Electric Propulsion Control
provided to prevent excessive overvoltages in a
supply system to which converters are connected. 4/5D2.11.1 General
Visual and audible alarm are to be provided at the Failure of a control signal is not to cause an excessive
control station for tripping of the protective fuses for increase in propeller speed. The reference value
these devices. transmitters in the control stations and the control

PART 4 SECTION 5|63 Electrical Installations -- Part D. Specialized Installations


equipment are to be so designed that any defect in the Interlocks are to be provided with the field lever to
desired value transmitters or in the cables between the prevent the opening of any main circuits without first
control station and the propulsion system will not reducing the field excitation to zero, except that when
cause a substantial increase in the propeller speed. the generators simultaneously supply power to an
auxiliary load apart from the propulsion, the field
4/5D2.11.2 Automatic and Remote Control excitation need only be reduced to a low value.
Systems
Where two or more control stations are provided 4/5D2.13 Instrumentation at the Control Station
outside the engine room, or where automatic control
of the propulsion machinery is provided, 4/11.1 4/5D2.13.1 Indication, Display and Alarms
through 4/11.7, as applicable, are to be complied The necessary instruments to indicate existing
with. See 4/11.1.2 for propulsion class symbols. conditions at all times are to be provided and
mounted on the control panel convenient to the
4/5D2.11.3 Testing and Inspection operating levers and switches. Instruments and other
Controls for electric propulsion equipment are to be devices mounted on the switchboard are to be labeled
inspected when finished and dielectric strength tests and the instruments provided with a distinguishing
and insulation resistance measurements made on the mark to indicate full-load conditions. Metallic cases
various circuits in the presence of the Surveyor, of all permanently installed instruments are to be
preferably at the plant of manufacture. The permanently earthed. The following instruments,
satisfactory tripping and operation of all relays, where applicable, are to be provided.
contactors and the various safety devices are also to a For A-C Systems Ammeter, voltmeter,
be demonstrated. indicating wattmeter and field ammeter(*) for each
propulsion generator and for each synchronous
4/5D2.11.4 Initiation of Control motor. See also Table 4/11.7.
The control of the propulsion system can be activated b For D-C Systems An ammeter for each main
only when the delegated control lever is in zero circuit and one or more voltmeters with selector
position and the system is ready for operation. switches for reading voltage on each propulsion
generator and motor. See also Table 4/11.7.
4/5D2.11.5 Emergency Stop c For Electric Slip Couplings An ammeter for
Each control station shall have an emergency stop the coupling excitation circuit.
device which is independent of the control lever.
* Field ammeter is not required for brushless generators.
4/5D2.11.6 Prime Mover Control
Where required by the system of control, means are 4/5D2.13.2 Indication of Propulsion System Status
to be provided at the control assembly for controlling The control stations of the propulsion systems are to
the prime mover speed and for mechanically tripping have at least the following indications for each
the throttle valve. propeller.
a "Ready for Operation" Power circuits and
4/5D2.11.7 Control Power Failure necessary auxiliaries are in operation.
If failure of the power supply occurs in systems with b "Faulty" Propeller is not controllable.
power-aided control (e.g. with electric, pneumatic or c "Power Limitation" In case of disturbance,
hydraulic aid), it is to be possible to restore control in for example, in the ventilators for propulsion motors,
a short time. in the converters, cooling water supply or load
limitation of the generators.
4/5D2.11.8 Protection
Arrangements are to be made so that opening of the 4/5D2.15 Equipment Installation and
control system assemblies or compartments will not Arrangement
cause inadvertent or automatic loss of propulsion.
Where steam and oil gauges are mounted on the 4/5D2.15.1 General
main-control assembly, provision is to be made so The arrangement of bus bars and wiring on the back
that the steam or oil will not come in contact with the of propulsion-control assemblies is to be such that all
energized parts in case of leakage. parts, including the connections, are accessible. All
nuts and connections are to be fitted with locking
4/5D2.11.9 Interlocks devices to prevent loosening due to vibration.
All levers for operating contactors, line switches, Clearance and creepage distance are to be provided
field switches and similar devices are to be between parts of opposite polarity and between live
interlocked to prevent their improper operation. parts and earth to prevent arcing. See 4/5.19,
4/5C4.11.6, and 4/5D1.11.2d.

PART 4 SECTION 5|64 Electrical Installations -- Part D. Specialized Installations


4/5D2.15.2 Accessibility and Facilities for Repairs 4/5D2.17.2 Temperature Rating
a Accessibility For purposes of inspection and When generators, motors or slip-couplings for
repair, provision is to be made for access to the stator electric propulsion are fitted with an integral fan and
and rotor coils, and for the withdrawal and will be operated at speeds below the rated speed with
replacement of field coils. Adequate access is to be full-load torque, full-load current, or full-load
provided to permit resurfacing of commutators and excitation temperature rise limits according to Table
slip-rings, as well as the renewal and bedding of 4/5C.3 are not to be exceeded.
brushes.
b Facility for Supporting Facilities shall be 4/5D2.17.3 Protection Against Moisture
provided for supporting the shaft to permit inspection Condensation
and withdrawal of bearings. 4/5C2.11.7 is applicable for rotating machines and
c Slip-couplings Slip-couplings are to be converters regardless of the weight of the machines.
designed to permit removal as a unit without axial
displacement of the driving and driven shaft, and 4/5D2.17.4 Prime Movers
without removing the poles. a Capability The prime mover rated output are
to have adequate overloading and build-up capacity
4/5D2.15.3 Semiconductor Converters for supplying the power which is necessary during
Converters are to be installed away from sources of transitional changes in operating conditions of the
radiant energy in locations where the circulation of electrical equipment. When maneuvering from full
air is not restricted to and from the converter and propeller speed ahead to full propeller speed astern
where the temperature of the inlet air to air-cooled with the craft making full way ahead, the prime
converters will not exceed that for which the mover is be capable of absorbing a proportion of the
converter is designed. Immersed-type converters are regenerated power without tripping due to overspeed.
to use a non-flammable liquid. Where forced cooling b Speed Control Prime movers of any type are
is utilized, the circuit is to be so designed that power to be provided with a governor capable of
cannot be applied to or retained on converters unless maintaining the pre-set steady speed within a range
effective cooling is maintained. Converter stacks are not exceeding 5% of the rated full-load speed for load
to have at least IP22 protection and mounted in such changes from full-load to no-load.
a manner that they may be removed without c Manual Controls Where the speed control of
dismantling the complete unit. the propeller requires speed variation of the prime
mover, the governor is to be provided with means for
4/5D2.15.4 Propulsion Cables local manual control as well as for remote control.
Propulsion cables are not to have splices or joints For turbines driving A.C. propulsion generators,
except terminal joints and all cable terminals are to be where required by the system of control, the governor
sealed against the admission of moisture or air. is to be provided with means for local hand control as
Similar precautions are to be taken during installation well as remote adjustment from the control station.
by sealing all cable ends until the terminals are d Parallel Operation In case of parallel
permanently attached. Cable supports are to be operation of generators, the governing system is to
designed to withstand short- circuited conditions. permit stable operation to be maintained over the
They are to be spaced less than 915 mm (36 in.) apart entire operational speed range of the prime movers.
and are to be arranged to prevent chafing of the cable. e Protection for Regenerated Power Braking
See 4/5B3.9.1. resistors or ballast consumers are to be provided to
absorb excess amounts of regenerated energy and to
reduce the speed of rotation of the propulsion motor.
4/5D2.17 Machinery and Equipment
These braking resistors or ballast consumers are to be
located external to the mechanical and electric
4/5D2.17.1 Material Tests rotating machines. Alternatively, the amount of
The following materials intended for main propulsion regenerated power may be limited by the action of the
installation are to be tested in accordance with the control system.
“ABS Requirements for Materials and Welding”:
thrust shafts, line shafts, propeller shafts, shafting for 4/5D2.17.5 Rotating Machines for Propulsion
propulsion generators and motors, coupling bolts, and The following requirements are applicable to
in the case of direct-connected turbine-driven propulsion generators and propulsion motors
propulsion generators, fan shrouds, centering and a Ventilation and Protection Electric rotating
retaining rings. Major castings or built-up parts such machines for propulsion are to be enclosed ventilated
as frames, spiders and end shields are to be surface or be provided with substantial wire or mesh screen to
inspected and the welding is to be in accordance with prevent personnel injury or entrance of foreign
the “ABS Requirements for Materials and Welding ”. matter. Dampers are to be provided in ventilating air
ducts except when recirculating systems are used.

PART 4 SECTION 5|65 Electrical Installations -- Part D. Specialized Installations


o
b Fire-extinguishing Systems Electric rotating C (356 oF) will be considered in accordance with
machines for propulsion which are enclosed or in 4/5.13.6.
which the air gap is not directly exposed are to be d Excitation Excitation is to be provided as
fitted with fire-extinguishing systems suitable for fires required for propulsion generators. See 4/5C2.19.1,
in electrical equipment. This will not be required 4/5C2.21.1d, and 4/5D2.17.6.
where it can be established that the machinery e Control Equipment Electric-coupling control
insulation is self-extinguishing. equipment is to be combined with the prime mover
c Air Coolers Air cooling systems for propulsion speed and reversing control and is to include a two-
generators are to be in accordance with 4/4.11.3 and pole disconnect switch, short-circuit protection only,
4/4.11.7. ammeter for reading coupling current, discharge
d Temperature Sensors Stator windings of A.C. resistor and interlocking to prevent energizing the
machines and interpole windings of D.C. machines, coupling when the prime mover control levers are in
rated above 500 kW, are to be provided with an inappropriate position.
temperature sensors. See Table 4/11.9. f Nameplates Nameplates of corrosion-resistant
material are to be provided in an accessible position
4/5D2.17.6 Propulsion Generators of the electric coupling and are to indicate at least the
Excitation current for propulsion generators may be information as listed in Table 4/5D.1a.
derived from attached rotating exciters, static
exciters, excitation motor-generator sets, or special 4/5D2.17.9 Semiconductor Converters for
purpose generating units. Power for these exciters Propulsion
may be derived from the machine being excited or a General Converter enclosures and other parts
from any craft service, emergency, or special purpose subject to corrosion are to be made of corrosion-
generating units. resistant material or of a material rendered corrosion
resistant. Ambient air temperature is to be in
4/5D2.17.7 Direct-current (D.C.) Propulsion accordance with 4/5.13. In the case of water-cooled
Motors converters, the inlet cooling water temperature is to
a Rotors The rotors of D.C. propulsion motors be considered at 30 oC (86 oF), unless otherwise
are to be capable of withstanding overspeeding up to approved. In all cases, the temperature rise under all
the limit reached in accordance with the conditions is to be limited to such a value as will
characteristics of the overspeed protection device at permit the converter to meet the specified
its normal operational setting. performance criteria. Schematic and one line
b Overspeed Protection An overspeed diagrams are to be submitted for review.
protection device is to be provided to prevent b Testing and Inspection Semiconductor
excessive overspeeding of the propulsion motors due converters for propulsion systems are to be tested in
to light loads, loss of propeller, etc. the presence of and inspected by the Surveyor,
preferably at the plant of the manufacturer. Duplicate
4/5D2.17.8 Electric Couplings units of previously tested semiconductor converters
a General Couplings are to be enclosed are to be tested only as deemed necessary by the
ventilated or be provided with wire or mesh screen to Surveyor to demonstrate successful operation.
prevent personnel injury or the entrance of foreign c Insulation Test The insulation of
material. All windings are to be specially treated to semiconductor converters is to be tested with all the
resist moisture, oil and salt air. parts completely assembled not withstanding previous
b Accessibility for Repairs The coupling is to be tests carried out by the manufacturer on individual
designed to permit removal as a unit without moving parts. The dielectric strength is to be tested by the
the engine. See also 4/5D2.15.2a. continuous application for 60 seconds of an
c Temperature Rating The limits of temperature alternating voltage having a crest value equal to the
rise are to be the same as for alternating-current sq. root of [2] times the specified test voltage and a
generators given in Tables 4/5C.2a and 4/5C.3, frequency of 20 to 60 Hz. The standard test voltage is
except that when a squirrel-cage element is used, the to be twice the normal voltage of the circuit to which
temperature of this element may reach such values as it is applied plus 1000 volts except that where the
are not injurious. Depending upon the cooling
secondary circuit operates below 60 volts, the test
arrangements, the maximum temperature rise may
voltage is to be 600 volts r.m.s. and where in the
occur at other than full-load rating so that heat runs
will require special consideration; for this purpose, range of 60 to 90 volts, the test voltage is to be 900
when an integral fan is fitted, the coupling volts r.m.s. The dielectric test voltage is to be applied
temperatures are not to exceed the limits in Tables between each circuit and earthed metal parts.
4/5C.2a and 4/5C.3 when operated continuously at Alternative test procedures will be considered where
70% of full-load rpm, full excitation and rated torque. the above requirement could result in damage to
Temperature rises for insulation materials above 180 sensitive components.

PART 4 SECTION 5|66 Electrical Installations -- Part D. Specialized Installations


d Design Data The following limiting repetitive by solenoids, or other means in addition to the
peak voltages are to be used as a base for the manual method which is to be provided unless
semiconductor device: otherwise approved.
b Generator and Motor Switches Switches for
- when connected to a supply specifically for generators and motors are preferably to be of the air-
propeller drives: URM = 1.5 UP; break type but for alternating-current systems, where
- when connected to a common main supply: they are to be designed to open full-load current at
URM = 1.8 UP full voltage, oil-break switches using nonflammable
(UP is the peak value of the rated voltage at the liquid may be used if provided with leak-proof,
input of the semiconductor converter). nonspilling tanks.
c Field Switches Where necessary, field switches
If the semiconductors are connected in series, the are to be arranged for discharge resistors unless
above values may be increased by 10 %. discharge resistors are permanently connected across
e Watertight Enclosures Converter units having the field. For alternating-current systems, means are
a watertight enclosure are to meet successfully the to be provided for de-energizing the excitation
insulation test specified in 4/5D2.17.9c after being circuits by the unbalance relay and ground relay.
subjected to a stream of water from a nozzle not less
than 25 mm (1 in.) in diameter under a head of 10.5 4/5D2.17.12 Propulsion Cables
m (35 ft), played on the enclosure for at least 15 a Conductors The conductors of cables external
minutes from a distance of 3 m (10 ft). to the components of the propulsion plant, other than
f Terminals The alternating current terminals cables and interconnecting wiring for computers, data
are to be marked with the letters A.C. The direct loggers or other automation equipment requiring
current terminals are to be marked with a plus (+) on currents of very small value, are to consist of not less
the positive terminal and a minus (-) on the negative than seven strands and have a cross-sectional area of
terminal. not less than 1.5 mm2 (2,960 circ. mils).
g Nameplates Nameplates of corrosion-resistant b Insulation Materials Ethylene-propylene
material are to be provided in an accessible position rubber, cross-linked polyethylene, or silicone rubber
of the semiconductor converter or its enclosure and insulated cables are to be used for propulsion power
are to indicate at least the information as listed in cables except that polyvinyl chloride insulated cables
Table 4/5D.1b. may be used where the normal ambient temperature
will not exceed 50 oC (122 oF).
4/5D2.17.10 Reactors and Transformers for c Sheath, Jacket and Armor All cables are to
Semiconductor Converters have suitable moisture-resistant jackets and braided
a General Interphase reactors and transformers metallic armor. Impervious metallic sheaths will be
used with semiconductor converters are to conform considered but are not to be used with single-
with the requirements of 4/5C5.1.1, 4/5C5.1.2c, conductor alternating-current cables.
4/5C5.3, 4/5C5.5.1 and 4/5C5.5.2, and the following. d Inner Wiring The insulation of internal wiring
b Voltage Regulation Means to regulate in main control gear, including switchboard wiring,
transformer output voltage are to be provided to take shall be of flame-retardant quality.
care of increase in converter forward resistance and in e Testing All propulsion cables, other than
addition to obtain the necessary performance internal wiring in control gears and switchboards, are
characteristics of the converter unit in which the to be subjected to dielectric and insulation tests in the
transformer is used. presence of the Surveyor.
c High Temperature Alarm Interphase reactors
and transformers used with the semiconductor 4/5D2.19 Dock and Sea Trials
converters for main and auxiliary propulsion systems
are to be provided with high temperature alarm at the Complete tests are to be carried out including
switchboard or the propulsion control station. The duration runs and maneuvering tests which should
setting value of the alarm is to be determined by their include a reversal of the craft from full speed ahead to
specific insulation class and is not to exceed the full speed astern, tests for operation of all protective
temperature corresponding to the limit listed in Table devices and stability tests for control. All tests
4/5C.8. necessary to demonstrate that each item of plant and
the system as a whole are satisfactory for duty are to
4/5D2.17.11 Switches be performed. Immediately prior to trials, the
a General Design All switches are to be insulation resistance is to be measured and recorded.
arranged for manual operation and so designed that
they will not open under ordinary shock or vibration;
contactors, however, may be operated pneumatically,

PART 4 SECTION 5|67 Electrical Installations -- Part D. Specialized Installations


4/5D3. Electrical Plants of Less Than 75 kW sets is to be sufficient to carry the necessary load
essential for the propulsion and safety of the craft and
4/5D3.1 General preservation of the cargo with any one generator set
Electrical plants having an aggregate capacity of less in reserve. Craft having only one generator are to be
than 75 kW are to comply with the following provided with a battery source to supply sufficient
requirements and the requirements in this Section 4/5, lighting for safety.
as applicable -- except 4/5.17, 4/5A1.3, 4/5A1.5,
4/5A2, 4/5A3, 4/5A4.1.6b, 4/5A5.1.5, 4/5A6.5, 4/5D3.13 Emergency Source of Power
4/5A6.7, 4/5A7.3, 4/5A8, 4/5A9.1, 4/5A9.3, 1 Capacity The emergency source of electrical
4/5A10.3, 4/5B1.1, 4/5B2.9, 4/5C2.15.4, power is to have adequate capacity to provide
4/5C4.19.2d and .2e, 4/5C7 and 4/5D1. emergency lighting for a period of at least 5 hours.
2 Sources The emergency power source may be
4/5D3.3 Standard Details any of the following:
Standard wiring practices and details including such a An automatically connected or manually
items as cable supports, earthing details, bulkhead controlled storage battery; or
and deck penetrations, cable joints and sealing, cable b An automatically or manually started generator,
splicing, watertight and explosion-proof connections or
to equipment, earthing and bonding connections, etc., c Relay-controlled, battery-operated lanterns.
as applicable, are to be indicated on the submitted 3 Battery Sources Where the source of electrical
plans or may be submitted in a booklet format. power is a battery connected to a charging device
with an output of more than 2 kW, the battery is to be
4/5D3.5 Calculations of Short-circuit Currents located as near as practicable to but not in the same
In the absence of precise data, the following short space as the emergency switchboard, distribution
circuit currents at the machine terminals are to be board or panel.
assumed: 4/5D3.15 Cable Construction
1 Direct Current Systems Ten times the full load Cables are to have copper conductors constructed in
current for generators normally connected (including accordance with a recognized standard and are to be
spare) for each generator capable of being of the stranded type, except sizes not exceeding 1.5
simultaneously connected. mm2 (16 AWG) may have solid conductors.
Six times full load current for motors
simultaneously in service 4/5D3.17 Switchboards, Distribution Boards and
2 Alternating Current Systems Ten times the full Panels
load current for generators normally connected 1 Installation Switchboards, distribution boxes
(including spare) for each generator capable of being panels and panels are to be installed in dry accessible,
simultaneously connected - symmetrical r.m.s. and well-ventilated areas. Not less than 610 mm (24
Three times full load current of motors in.) clearance is to be provided in front of
simultaneously in service. switchboards, distribution boxes panels and panels.
When located at the helm or other area adjacent to or
4/5D3.7 Lightning Protection part of an open cockpit or weather deck, they are to
For lightning protection systems, see 4/5B2.1.4a. be protected by a watertight enclosure.
2 Instrumentation A voltmeter, ammeter,
4/5D3.9 Temperature Ratings frequency meter, and voltage regulator are to be
In the requirements contained in 4/5D3, an ambient provided for each generator installed. Control
temperature of 40C (140F) has been assumed for all equipment and measuring instruments are to be
locations. Where the ambient temperature is in provided as necessary to insure satisfactory operation
excess of this value, the total temperature specified is of the generator or generators.
not to be exceeded. Where equipment has been rated
on ambient temperature less than that contemplated, 4/5D3.19 Navigating Running Lights
consideration will be given to the use of such
equipment provided the total temperature for which Mast head, port, starboard, and stern lights when
the equipment is rated will not be exceeded. required are to be controlled by a running light
indicator panel. A fused-feeder disconnect switch is
4/5D3.11 Generators to be provided; the rating of the fuses is to be at least
Craft using electricity for propulsion auxiliaries or twice that of the largest branch fuse and greater than
preservation of cargo are to be provided with at least the maximum panel load.
two generators. These generators are not to be driven
by the same engine. The capacity of the generating

PART 4 SECTION 5|68 Electrical Installations -- Part D. Specialized Installations


Table 4/5D.1 Nameplates

a. Electric Coupling [See 4/5D2.17.8e]

The manufacturer's name


The manufacturer's type and frame designation
The output
Kind of rating
The temperature rise at rated load and design
ambient temperature
The speed (r.p.m.) at rated load
The rated voltage
The exciter rated voltage
The Exciting current in amperes at rating

b. Semiconductor Converter [See 4/5D2.17.9g]

The manufacturer's name and address


The manufacturer's serial number
The type (silicon, copper oxide, etc.)
The rated A.C. volts
The rated A.C. amperes
Number of phases
Frequency
The rated D.C. volts
The rated D.C. amperes
The ambient temperature range
The cooling medium

PART 4 SECTION 5|69 Electrical Installations -- Part D. Specialized Installations


4/5E1.3.5 Exhaust Inlet and Outlet
Part E. Specialized Craft Inlet for exhaust ducts are to be located within 450
and Services mm (17.75 in.) above the vehicle deck. The outlet is
to be sited in a safe position, having regard to the
source of ignition near the outlet.
4/5E1 Installations in Special-category Spaces
4/5E1.3.6 Emergency Shutdown
4/5E1.1 Application Arrangements are to be provided to permit a rapid
shutdown and effective closure of ventilation system
In addition to the foregoing requirements in this in case of fire, taking into account the weather and
Section, the following requirements are applicable for sea conditions. See also 4/5E1.3.1.
installations in special-category spaces.
4/5E1.3.7 Operating Compartment Indication
4/5E1.3 Ventilation System Means are to be provided on the operating
compartment or other appropriate locations to
4/5E1.3.1 Arrangement indicate any loss of the ventilating capacity.
The ventilating system for special-category spaces is
to be independent from other ventilation systems and 4/5E1.5 Location and Type of Equipment
is to be capable of being controlled from a position
outside the space. 4/5E1.5.1 Certified Safe Type Equipment
Except as provided for in 4/5E1.5.2 below, electrical
4/5E1.3.2 Capacity equipment and wiring within the enclosed vehicle
An effective power ventilation system of sufficient spaces referred to in 4/5E1.3.1 are to be increased-
capacity to give at least 10 air changes per hour while safety, explosion-proof, or intrinsically-safe type.
navigating and 20 air changes per hour at the
quayside during vehicle loading and unloading 4/5E1.5.2 Arrangements
operations is to be provided. Except for a distance within 450 mm (17.75 in.)
above a platform that does not have openings of
4/5E1.3.3 Fans sufficient size permitting penetration of petroleum
Exhaust fans are to be of non-sparking construction in gases downward, electrical equipment of a type so
accordance with 4/5B7.7. enclosed and protected as to prevent the escape of
sparks, e.g. protection degree of IP55 or equivalent.
4/5E1.3.4 Material and Arrangement of Ducts
Ventilation ducts including dampers are to be of steel. 4/5E1.5.3 Equipment in Ducts from Vehicle Space
Ducts serving spaces capable of being sealed are to Electrical equipment and wiring installed within an
be separated for such space. exhaust duct are to be increased-safety, explosion-
proof, or intrinsically-safe type.

PART 4 SECTION 5|71 Electrical Installations -- Part E. Specialized Vessels and Services
PART 4 SECTION 6
Pumps and Piping Systems

4/6.1 Construction and Installation 4/6.3.3 Booklet of Standard Details


A booklet of standard piping practices and details
4/6.1.1 General Requirements including such items as bulkhead, deck and shell
All craft are to be provided with the necessary pumps penetrations, welding details including dimensions,
and piping systems for safe and efficient operation in pipe joining details, etc. is to be submitted. Pipe
the service for which they are intended. Materials welding details are to comply with Section 2/3.
and workmanship are to be in accordance with good
marine practice and to the satisfaction of the 4/6.4 Material Tests and Inspection
Surveyor. The arrangements and details are to
comply with the following requirements which are 4/6.4.1 Specifications and Purchase Orders
applicable to all oceangoing craft but which may be The appropriate material to be used for the various
modified for craft classed for limited service. pipes, valves and fittings is indicated in this section.
The material is to be made in accordance with the
4/6.1.2 Piping Groups requirements of Section 2/2, except that tests of
To distinguish between detail requirements for the material for valves, fittings, fluid power cylinders,
various systems the piping on shipboard is divided and Group II piping need not be witnessed by the
into two groups. Surveyor. Where electric resistance welding is used,
Group I in general includes all piping intended for the requirements of Section 2/3 are also applicable.
working pressures or temperatures in various services Copies in duplicate of the purchase orders for
as follows: material requiring test and inspection at the mills or
Service Pressure Temperature
place of manufacture are to be forwarded to the
bar (kgf/cm2, psi) C (F) Bureau for the information of the Surveyor.
Vapor and Gas over 10.3 (10.5, 150) over 343 (650)
Water over 15.5 (15.8, 225) over 177 (350) 4/6.4.2 Special Materials
Lubricating Oil over 15.5 (15.8, 225) over 204 (400) If it is desired to use special alloys or other materials
Fuel Oil over 10.3 (10.5, 150) over 66 (150)
not covered by the Rules, the use of such materials
Hydraulic Fluid over 15.5 (15.8, 225) over 204 (400)
will be specially considered for approval.
Group II includes all piping intended for working
pressures and temperatures below those stipulated 4/6.5 Definitions
under Group I. Group II also includes open-ended
lines such as drains, overflows, engine exhausts and 4/6.5.1 Piping/Piping Systems
vents. The terms piping and piping systems include the pipe,
fittings, system joints, method of joining and any
4/6.3 Plans and Data to Be Submitted internal or external liners, coverings and coatings
required to comply with the performance criteria. For
4/6.3.1 Plans example, if the basic material needs a fire protective
Before proceeding with the work, plans in accordance coating to comply with the fire endurance
with 4/1.11 are to be submitted, showing clearly the requirements, then the piping are to be manufactured
diagrammatic details or arrangement of the and tested with both the basic material and coating
equipment. attached and details are to be submitted to the Bureau
for approval.
4/6.3.2 All Piping Systems
The plans are to consist of a diagrammatic drawing of 4/6.5.2 Joints
each system accompanied by lists of material giving The term joint refers to the method of connecting
size, wall thickness, maximum working pressure and pipes by adhesive bonding, brazing, welding, bolted
material of all pipes and the type, size, pressure rating flanging, threading, etc.
and material of valves and fittings.

PART 4 SECTION 6|1 Pumps and Piping Systems


4/6.5.3 Fittings 4/6.7.4 Non-Metallic Expansion Joints
The term fittings refers to bends, elbows, fabricated Molded expansion fittings of reinforced rubber or
branch pieces, etc. other suitable materials may be used in circulating
water piping systems in machinery spaces. Such
4/6.5.4 Positive Closing Valves fittings are to be oil resistant. The maximum working
Positive closing valves are valves that are capable of pressure is not to be greater than 1/4 of the
maintaining a set position under all operating hydrostatic bursting pressure of the fitting as
conditions. determined by a prototype test. Manufacturer's name
and the month and year of manufacture are to be
4/6.5.5 Recognized Standard of Construction embossed or otherwise permanently marked on the
Recognized standards of construction are published outside edge of one of the flanges or other easily
construction standards from organizations, such as examined area of all flexible expansion joints
but not limited to the American Society of intended for use in sea water piping systems over 150
Mechanical Engineers (ASME), American Society of mm (6 in.). Plans of the molded or built-up flexible
Testing and Materials (ASTM), Department of expansion joints in sea water piping systems over 150
Transportation (DOT), Japanese Industrial Standard mm (6 in.), including details of the internal
(JIS), German Design Standard (DIN), British reinforcement arrangements, are to be submitted for
Standard Code of Practice (BSI), which are approval.
recognized by the Bureau as being acceptable
standards for a specific purpose or service. Each 4/6.7.5 Bulkhead, Deck or Tank Top
standard is to be used independently and in a Penetrations
consistent manner. Where pipes pass through bulkheads, decks or tank
tops, the penetrations are to be made by methods
4/6.5.6 Standard or Extra-Heavy Pipe which will maintain the watertight, fire-tight or
Pipe thickness referred to as Standard or Extra-Heavy smoke-tight integrity of the bulkhead, deck or tank
are the equivalent of American National Standards top. Bolted connections are to have the bolts
Institute Schedule 40 and Schedule 80 pipe up to a threaded through the plating and welded connections
maximum wall thickness of 9.5 mm (0.375 in.) and are to be welded on both sides or with full-strength
12.5 mm (0.5 in.), respectively. welds from one side.

4/6.7 General Installation Details 4/6.7.6 Collision-Bulkhead Penetrations


Pipes piercing the collision bulkhead are to be fitted
4/6.7.1 Protection with suitable valves operable from above the
Pipes, valves and operating rods are to be effectively bulkhead deck and secured to the bulkhead, generally
secured and adequately protected from mechanical inside the forepeak. Cast iron is not to be used for
damage. These protective arrangements are to be these valves. The use of nodular iron, also known as
fitted so that they may be removed to enable ductile iron or spheroidal-graphite iron will be
examination of the pipes, valves, and operating rods accepted, provided the material has an elongation not
protected. less than 12% in 50 mm (2 in.). Tanks forward of the
collision bulkhead are not to be arranged for the
4/6.7.2 Pipes Near Switchboards carriage of oil or other liquid substances that are
The leading of pipes in the vicinity of switchboards is flammable.
to be avoided as far as possible. When such leads are
necessary, care is to be taken to fit no flanges or 4/6.7.8 Sluice Valves and Cocks
joints over or near the switchboards unless provision No valve or cock for sluicing purposes is to be fitted
is made to prevent any leakage from damaging the on a collision bulkhead. Sluice valves or cocks may
equipment. be fitted only on other watertight bulkheads, when
they are at all times accessible for examination. The
4/6.7.3 Expansion or Contraction Stresses control rods are to be operable from the bulkhead
Provision is to be made to take care of expansion or deck and are to be provided with an indicator to show
contraction stresses in pipes due to temperature whether the valve or cock is open or closed. The
changes or working of the hull. Slip joints of an control rods are also to be properly protected from
approved type may be used in systems and locations injury and their weight is not to be supported by the
where possible leakage will not be hazardous. valve or cock.

PART 4 SECTION 6|2 Pumps and Piping Systems


4/6.7.9 Relief Valves c Fire-resistant Hoses In order for a non-
All systems which may be exposed to pressures metallic flexible hose to be considered fire-resistant, a
greater than that for which they are designed are to be prototype of the hose is to be subjected to a fire test
safeguarded by suitable relief valves or the for at least 30 minutes at a temperature of not less
equivalent, and pressure containers such as than 800C (1472F) while water at the maximum
evaporators, heaters, etc., which may be isolated from service pressure is circulated inside. The temperature
a protective device in the line are to have such of the water at the outlets is not to be less than 80C
devices either directly on the shell or between the (176F) during the test. The tested hose is to be
shell and the isolation valve. complete with end fittings and no leakage is to be
a Exceptions In pumping systems such as oil recorded during or after the test. As an alternative,
piping and fire main, where ordinarily relief valves the fire test may be conducted with the circulating
are required at the pump, such valves need not be water at a pressure of at least 5 bar (5.1 kgf/cm2, 72.5
fitted when the system is served only by centrifugal psi) and a subsequent pressure test to twice the design
pumps so designed that the pressure delivered cannot pressure.
exceed that for which the piping is designed. d Hose Fittings Each hose is to be complete
with factory assembled end fittings or factory
4/6.7.10 Instruments supplied end fittings installed in accordance with
a Temperature Thermometers and other manufacturer's procedures. The use of non-metallic
temperature sensing devices registering through hoses which are not provided with factory assembled
pressure boundaries are to be provided with end fittings will be considered for non-combustible
instrument wells to allow for instrument removal and non-toxic, Group II piping systems under 5.2 bar
without impairing the integrity of the pressurized (5.3 kgf/cm2, 75 psi) in pipe sizes up to 114.3 mm
system. O.D. (4 in. NPS). Such hoses are to be located in
b Pressure Pressure sensing devices are to be accessible locations and secured by means of at least
provided with valve arrangements to allow for two stainless-steel hose clamps at each end. Such
instrument isolation and removal without impairing clamps are to be at least 12 mm (0.5 in.) wide and are
the pressurized systems' integrity. not to be dependent on spring tension to remain
fastened.
4/6.7.11 Hose
a Hoses in Vital Systems Hose assemblies may 4/6.7.12 Control of Static Electricity
be installed between two points where flexibility is Piping systems that are routed through hazardous
required but are not to be subject to torsional areas are to be suitably grounded either by welding or
deflection (twisting) under normal operating bolting the pipes or their supports directly to the hull
conditions. In general, hose is to be limited to the of the ship or through the use of bonding straps. In
length necessary to provide for flexibility and for general, the resistance between ground points along
proper operation of machinery. Each hose is to be the length, across joints, and from pipe to ground is
visible at all times, easily accessible, and confined to not to exceed 1 megohm. Where bonding straps are
one watertight compartment. Burst pressure of the used, they are to be clearly visible, protected from
hose is not to be less than four times the relief valve mechanical damage and of a type not affected by
setting. corrosive product and paint. Bonding straps are
Where the use of non-metallic hose is permitted, required for piping systems which are not
the hose materials are to be suitable for the intended permanently connected to the hull, including piping
service. Hoses for oil service are to be fire resistant systems which are electrically separated from the hull
and reinforced with wire braid or other suitable and pipe connections arranged for removal of spool
material. pieces.
b Hoses in Non-vital Systems Flexible metallic
and non-metallic hose may be installed throughout in 4/6.7.13 Leakage Containment
systems such as sanitary drains, potable water, and For areas where leakage may be expected such as oil
fresh water cooling for non-vital equipment. Where burners, purifiers, oil drains, valves under day tanks,
hose passes through watertight bulkheads, it is to be etc., means of containing the leakage are to be
connected to a rigid sleeve of the same material as the provided. Where drain pipes are fitted for collected
bulkhead and the sleeve is to be fitted with either a leakage, they are to be led to a suitable oil drain tank
readily accessible valve at each side of the bulkhead not forming part of an overflow system.
or a single valve on one side of the bulkhead with a
remote operator capable of operation from above the
bulkhead deck.

PART 4 SECTION 6|3 Pumps and Piping Systems


4/6.7.14 Piping on Aluminum Craft 4/6.9 Pressure Tests
On a craft with an aluminum hull, the use of steel,
copper or other non-aluminum pipes, valves and 4/6.9.1 General
fittings will require special attention to avoid galvanic In addition to the testing and inspection of materials,
corrosion with dissimilar metals. Piping runs of as required in Section 2/2, the following tests on the
material not compatible with aluminum are to be fabricated piping are to be witnessed by the Surveyor
isolated from the hull by suitable isolating brackets or after bending and the attachment of flanges:
insulating material. Where non-aluminum pipes pass
through decks, bulkheads, tank tops, and shell plating, 4/6.9.2 Fuel Oil Service System
they are to be isolated from the vessel’s structure with Pressure lines are to be tested after installation to 1.5
suitable insulation. times the design pressure of the system but not less
than 3.4 bar (3.5 kgf/cm2, 50 psi).
4/6.8 Pumps
4/6.9.3 Fuel Oil Suction and Transfer Lines
4/6.8.1 General Fuel transfer systems are to be tested after installation
For self-propelled craft 500 gross tons and above, the to 3.4 bar (3.5 kgf/cm2, 50 psi). Fuel-oil gravity fed
following pumps are to meet the test requirements of suction lines are to be leak tested such that the testing
4/6.8.3 and 4/6.8.5: procedures reflect the static pressure working
conditions of the suction piping.
Fire pump
Bilge pump
4/6.9.4 Starting Air Piping
Ballast pump
Piping in starting-air systems is to be tested,
Hydraulic pumps for steering gear, anchor
preferably before installation, to 1.5 times the design
windlass and variable pitch propellers
pressure of the system.
The tests are to be carried out at the manufacturer's
plant in the presence of the Surveyor. The capacity 4/6.9.6 Hydraulic Power Piping
test will not be required nor will the hydrostatic test After fabrication, the hydraulic power piping system
need to be witnessed by the Surveyor for individual or each piping component is to be tested to 1.5 times
pumps assembled on a production line basis, the design pressure. For steering gear piping tests,
provided the Surveyor is satisfied from periodic see 4/8.8 and for controllable pitch propeller system
inspections and the manufacturer's quality assurance piping tests see 4/7.32.1c.1
procedures that the pump capacities are acceptable
and that hydrostatic testing is being performed. See 4/6.9.7 Fixed Oxygen-Acetylene Piping
4/1.2. For pumps associated with reciprocating The piping system is to be tested in the presence of
internal combustion engines and reduction gears, see the Surveyor to 1.5 times the maximum design
4/4.21 pressure and thoroughly purged with air before being
placed in service. The medium used for pressure
4/6.8.3 Hydrostatic Test testing of oxygen lines is to be oil-free and
All pumps are to be hydrostatically tested to 1.5P, but nonflammable. Material used externally for leak
not less than 3.9 bar (4 kgf/cm2, 57 psi), where P is testing oxygen lines is to be oil-free and, if
the maximum working pressure of the part concerned. combustible, is to be applied as a diluted water
When the suction and discharge sides of the pump are solution.
tested independently, the pump suction is to be tested
to 1.5 times Ps, but not less than 3.9 bar (4 kgf/cm2, 4/6.9.8 All Piping
57 psi), where Ps is the maximum pressure available After installation all piping is to be tested under
from the system at the suction inlet. For steering gear working conditions.
pumps, also see 4/8.5
4/6.13 Metallic Pipes
4/6.8.5 Capacity Test
Pump capacities are to be checked with the pump 4/6.13.1 Test and Inspection Group I Piping
operating at design conditions (rated speed and Pipes intended for use in Group I piping systems are
pressure head). For centrifugal pumps, the pump to be tested in the presence of and inspected by the
characteristic (head capacity) design curve is to be Surveyor in accordance with Section 2/2 or such
verified to the satisfaction of the Surveyor. other appropriate material specification as may be
approved in connection with a particular design. See
4/6.67.3 for pipe used in hydraulic systems.

PART 4 SECTION 6|4 Pumps and Piping Systems


4/6.13.2 Steel Pipe t = minimum thickness of pipe in mm or in
a Seamless Pipe Seamless-drawn steel pipe may See Note 5.
be used for all purposes. D = actual external diameter of pipe in mm or
b Welded Pipe Electric resistance welded steel in.
pipe may be used for temperatures up to 343C S = maximum allowable fiber stress in
(650F). Consideration will be given to the use of N/mm2, kgf/mm2 or psi from Table 4/6.1.
electric-resistance-welded (ERW) pipe for use above See Note 2.
343C (650F) where the material is shown to be M = factor from Table 4/6.1
suitable for the intended service (i.e. in a non- C = allowance for threading, grooving or
corrosive environment, where design temperature is mechanical strength
below the lowest graphitization temperature specified = 1.65 mm (0.065 in.) for plain-end steel
for the material, etc.). Furnace butt-welded pipe up to or wrought-iron pipe or tubing up to 115
and including 115 mm O.D. (4 in. NPS) may be mm O.D. (4 in. NPS). See Note 3.
used for Group II piping for temperatures up to 232C = 0.00 mm (0.000 in.) for plain-end steel
(450F) but is not to be used for flammable or or wrought-iron pipe or tubing up to 115
combustible fluids. mm O.D. (4 in. NPS) used for hydraulic
piping systems. See Note 3.
4/6.13.3 Copper Pipe = 0.00 mm (0.000 in.) for plain-end steel
Seamless-drawn and welded copper pipe, unless or wrought- iron pipe or tubing 115 mm
otherwise prohibited, may be used for all purposes O.D. (4 in. NPS) and larger. See Note
where the temperature does not exceed 208C (406F) 3.
and within the limitations specified in the material = 1.27 mm (0.05 in.) for all threaded pipe
specification. 17 mm O.D. ( 3/8 in.) and smaller
= depth of thread h for all threaded pipe
4/6.13.4 Brass Pipe over 17 mm O.D. ( 3/8 in.). See Note 4.
Seamless-drawn brass pipe, unless otherwise = depth of groove for grooved pipe
prohibited, may be used where the temperature does = 0.00 mm (0.000 in.) for plain-end
not exceed 208C (406F). In saltwater systems, only nonferrous pipe or tubing. See Note 3.
alloys with a zinc content of 15% or less which Notes:
contain dezincification inhibitors such as tin, 1 The value of W used in the equations is to be not
antimony or arsenic are to be used. less than 8.6 bar (8.8 kgf/cm2, 125 psi), except that
for suction and other low-pressure piping of
nonferrous material, the actual working pressure
4/6.13.5 Aluminum Pipe may be applied if a suitable addendum is provided
Aluminum pipe is not to be used for fuel oil, against erosion and outside damage. However, in
lubricating oil, hydraulic oil or other flammable or no case is the value of W to be less than 3.4 bar
combustible liquids. Aluminum pipe is also not to be (3.5 kgf/cm2, 50 psi) for use in the equations.
2 Values of S for other materials are not to exceed
used for bilge piping within the machinery space or the stress permitted by ASME B31.1 Code for
for fire fighting systems. Pressure Piping, Power Piping .
Aluminum pipe may be used for all other services 3 Plain-end pipe or tubing includes those joined by
on craft constructed of aluminum or fiber-reinforced any method in which the wall thickness is not
reduced.
plastic, including vents and sounding pipes from oil 4 The depth of thread h may be determined by the
tanks. equation h = 0.8/n where n is the number of
threads per inch, or in metric units by the equation
4/6.13.6 Maximum Allowable Working Pressure h = 0.8n where n is the number of mm per thread.
5 If pipe is ordered by its nominal wall thickness, the
and Minimum Thickness manufacturing tolerance on wall thickness is to be
The maximum allowable working pressure and the taken into account.
minimum thickness of pipes are to be determined by
the following equations, with due consideration being 4/6.13.7 Working Pressure and Thickness--
given to the reduction in thickness at the outer radius Alternative Consideration
of bent pipes: Consideration will be given to the maximum working
KS ( t − c)
pressure and the minimum thickness of piping
WD
W= t= +C determined from criteria of applicable recognized
D − M ( t − c) KS + MW standards.
K = 20 (200, 2)
W = maximum allowable working pressure in
bar, kgf/cm2 or psi. See Note 1.

PART 4 SECTION 6|5 Pumps and Piping Systems


4/6.15 Plastic Pipes testing and calculation methods, which are to be
submitted to the Bureau for approval.
4/6.15.1 General c Axial Strength
Pipes and piping components made of thermoplastic 1 The sum of the longitudinal stresses due
or thermosetting plastic materials, with or without to pressure, weight and other dynamic
reinforcement, may be used in piping systems and sustained loads is not to exceed the
referred to in Table 4/6.4 subject to compliance with allowable stress in the longitudinal
the following requirements. For the purpose of these direction. Forces due to thermal
requirements “plastic” means both thermoplastic and expansion, contraction and external
thermosetting plastic materials, with or without loads, where applicable, are to be
reinforcement, such as polyvinyl chloride (PVC) and considered when determining
fiber reinforced plastics (FRP). longitudinal stresses in the system.
2 In the case of fiber reinforced plastic
4/6.15.2 Specification pipes, the sum of the longitudinal
Rigid plastic pipes are to be in accordance with a stresses is not to exceed one-half of the
recognized national or international standard nominal circumferential stress derived
acceptable to the Bureau. Specification for the plastic from the maximum internal pressure
pipe, including thermal and mechanical properties determined according to 4/6.15.3a,
and chemical resistance, is to be submitted for review unless the allowable longitudinal stress
together with the spacing of the pipe supports. is verified experimentally or by a
combination of testing and calculation
4/6.15.3 Design methods.
a Internal Pressure A pipe is to be designed for d Temperature The maximum allowable
an internal pressure not less than the design pressure working temperature of a pipe is to be in accordance
of the system in which it will be used. The maximum with the manufacturer’s recommendations, but in
internal pressure, Pint, for a pipe is to be the lesser of each case it is to be at least 20C (36F) lower than the
the following: minimum heat distortion temperature of the pipe
material determined according to ISO 75 method A or
Psth Plth
Pint = or Pint = equivalent. The minimum heat distortion temperature
4 2.5 is not to be less than 80C (176F).
Where low temperature services are considered,
Psth = short-term hydrostatic test failure pressure special attention is to be given with respect to
Plth = long-term hydrostatic test failure pressure ( material properties.
> 100,000 hours) e Impact Resistance Plastic pipes and joints are
The hydrostatic tests are to be carried out under the to have a minimum resistance to impact in accordance
following standard conditions: with a recognized national or international standard
such as ASTM D2444 or equivalent. After the impact
atmospheric pressure = 1 bar (1 kgf/cm2, 14.5 psi) resistance is tested, the specimen is to be subjected to
relative humidity = 30% hydrostatic pressure equal to the 2.5 times the design
fluid temperature = 25C (77F) pressure for at least one hour.
The hydrostatic test failure pressure may be f Fire Endurance Table 4/6.4 specifies fire
verified experimentally or determined by a endurance requirements for pipes based upon system
combination of testing and calculation methods, and location. Pipes and their associated fittings
which are to be submitted to the Bureau for approval. whose functions or integrity are essential to the safety
b External Pressure External pressure is to be of the craft are to meet the indicated fire endurance
considered for any installation which may be subject requirements which are described below.
to vacuum conditions inside the pipe or a head of − Level 1 will ensure the integrity of the
liquid on the outside of the pipe. A pipe is to be system during a full scale hydrocarbon fire
designed for an external pressure not less than the and is particularly applicable to systems
sum of the pressure imposed by the maximum where loss of integrity may cause outflow of
potential head of liquid outside the pipe plus full flammable liquids and worsen the fire
vacuum, 1 bar (1 kgf/cm2, 14.5 psi), inside the pipe. situation. Piping having passed the fire
The maximum external pressure for a pipe is to be endurance test specified in 4/6.15.7 for a
determined by dividing the collapse test pressure by a duration of a minimum of one hour without
safety factor of 3. loss of integrity in the dry condition is
The collapse test pressure may be verified considered to meet Level 1 fire endurance
experimentally or determined by a combination of standard (L1).

PART 4 SECTION 6|6 Pumps and Piping Systems


− Level 2 intends to ensure the availability of Alternatively, flame spread testing in accordance
systems essential to the safe operation of the with ASTM D635 may be used in lieu of the IMO
ship, after a fire of short duration, allowing flame spread test provided such test is acceptable to
the system to be restored after the fire has the Administration.
been extinguished. Piping having passed the h Electrical Conductivity
fire endurance test specified in 4/6.15.7 for a 1 Piping conveying fluids with a
duration of a minimum of 30 minutes conductivity less than 1000 pico
without loss of integrity in the dry condition siemens per meter are to be electrically
is considered to meet Level 2 fire endurance conductive.
standard (L2). 2 Regardless of the fluid being conveyed,
− Level 3 is considered to provide the fire plastic pipes are to be electrically
endurance necessary for a water filled piping conductive if the piping passes through
system to survive a local fire of short a hazardous area.
duration. The system’s functions are 3 Where electrically conductive pipe is
capable of being restored after the fire has required, the resistance per unit length
been extinguished. Piping having passed the of the pipes and fittings is not to exceed
fire endurance test specified in 4/6.15.8 for a 1 × 105 Ohm/m (3 × 104 Ohm/ft). See
duration of a minimum of 30 minutes also 4/6.15.4d.
without loss of integrity in the wet condition 4 If the pipes and fittings are not
is considered to meet Level 3 fire endurance homogeneously conductive, the
standard (L3). conductive layers are to be protected
Where a fire protective coating of pipes and fittings is against the possibility of spark damage
necessary for achieving the fire endurance standards to the pipe wall..
required, the following requirements apply. i Marking Plastic pipes and other components
1 Pipes are generally to be delivered from are to be permanently marked with identification in
the manufacturer with the protective accordance with a recognized standard. Identification
coating applied, with on-site application is to include pressure ratings, the design standard that
limited to that necessary for installation the pipe or fitting is manufactured in accordance with,
purposes (i.e., joints). See 4/6.15.4g and the material with which the pipe or fitting is
regarding the application of the fire made.
protection coating on joints.
2 The fire protection properties of the 4/6.15.4 Installation of Plastic Pipes
coating are not to be diminished when a Supports
exposed to salt water, oil or bilge slops. 1 Selection and spacing of pipe supports
It is to be demonstrated that the coating in shipboard systems are to be
is resistant to products likely to come in determined as a function of allowable
contact with the piping. stresses and maximum deflection
3 In considering fire protection coatings, criteria. Support spacing is not to be
such characteristics as thermal greater than the pipe manufacturer’s
expansion, resistance against vibrations recommended spacing. The selection
and elasticity are to be taken into and spacing of pipe supports are to take
account. into account pipe dimensions,
4 The fire protection coatings are to have mechanical and physical properties of
sufficient resistance to impact to retain the pipe material, mass of pipe and
their integrity. contained fluid, external pressure,
g Flame Spread All pipes, except those fitted operating temperature, thermal
on open decks and within tanks, cofferdams, void expansion effects, loads due to external
spaces, pipe tunnels and ducts are to have low flame forces, thrust forces, water hammer and
spread characteristics. The test procedures in IMO vibrations to which the system may be
Resolution A.653(16), modified for pipes as indicated subjected. Combination of these loads
in 4/6.15.9, are to be used for determining the flame is to be checked.
spread characteristics. Piping materials giving 2 Each support is to evenly distribute the
average values for all of the surface flammability load of the pipe and its contents over the
criteria not exceeding the values listed in Resolution full width of the support. Measures are
A.653(16) (surface flammability criteria of bulkhead, to be taken to minimize wear of the
wall and ceiling linings) are considered to meet the pipes where they contact the supports.
requirements for low flame spread.

PART 4 SECTION 6|7 Pumps and Piping Systems


3 Heavy components in the piping system craft, the valves and the pipe connection to the shell
such as valves and expansion joints are are to be metallic. The side shell valves are to be
to be independently supported. arranged for remote control from outside the space in
4 The supports are to allow for relative which the valves are located. For further details of
movement between the pipes and the the shell valve installation, their connections and
ship’s structure, having due regard to material, refer to 4/6.25.
the difference in the coefficients of f Bulkhead and Deck Penetrations
thermal expansion and deformations of 1 The integrity of watertight bulkheads
the ship’s hull and its structure. and decks is to be maintained where
5 When calculating the thermal plastic pipes pass through them.
expansion, the system working 2 Where plastic pipes pass through fire-
temperature and the temperature at resisting divisions, arrangements are to
which assembling is performed are to be be made to ensure that the fire
taken into account. endurance is not impaired. These
b External Loads When installing the piping, arrangements are to be tested in
allowance is to be made for temporary point loads, accordance with IMO Resolution. A
where applicable. Such allowances are to include at 754 (18), Recommendation on Fire
least the force exerted by a load (person) of 980 N Resistance Tests for “A”, “B” and “F”
(100 kgf, 220 lbf) at mid-span on any pipe more than Class Divisions, as amended.
100 mm ( 4 in.) nominal diameter. 3 If the bulkhead or deck is a fire division
Pipes are to be protected from mechanical damage and destruction by fire of plastic pipes
where necessary. may cause inflow of liquid from tank, a
c Plastic Pipe Connections metallic shut-off valve operable from
1 The strength of fittings and joints is not above the bulkhead deck is to be fitted
to be less than that of the piping they at the bulkhead or deck.
connect. g Application of Fire Protection Coatings Fire
2 Pipes may be joined using adhesive- protection coatings are to be applied on the joints,
bonded, welded, flanged or other joints. where necessary for meeting the required fire
3 Tightening of flanged or mechanically endurance criteria in 4/6.15.3f, after performing
coupled joints is to be performed in hydrostatic pressure tests of the piping system (see
accordance with manufacturer’s 4/6.15.10). The fire protection coatings are to be
instructions. applied in accordance with the manufacturer’s
4 Adhesives, when used for joint recommendations, using a procedure approved in
assembly, are to be suitable for each particular case.
providing a permanent seal between the
pipes and fittings throughout the 4/6.15.5 Manufacturing of Plastic Pipes
temperature and pressure range of the Preferably, the manufacturer is to have a quality
intended application. system and be certified in accordance with 4/1.2 or
Joining techniques are to be in accordance with ISO 9001. The quality system is to consist of
manufacturer’s installation guidelines. Personnel elements necessary to ensure that pipes and
performing these tasks are to be qualified to the components are produce with consistent and uniform
satisfaction of the Bureau, and each bonding mechanical and physical properties in accordance
procedure is to be qualified before shipboard piping with recognized standards and is to include the
installation commences. Requirements for joint following tests.
bonding procedures are in 4/6.15.6. − Samples of pipe are to be tested to determine
d Electrical Conductivity Where electrically the short-term and long-term hydrostatic
conductive pipe is required by 4/6.15.3h, installation design strength. These samples are to be
of the pipe is to be in accordance with the following: selected randomly from the production
1 The resistance to earth (ground) from facilities.
any point in the system is not to exceed − For piping required to be electrically
1 megohm. The resistance is to be conductive, representative samples of pipe
checked in the presence of the Surveyor. are to be tested to determine electrical
2 Where used, earthing wires or bonding resistance per unit length.
straps are to be accessible for − Random samples of pipe are to be tested to
inspection. The Surveyor is to verify determine the adhesion qualities of the
that they are in visible locations. coating to the pipe.
e Shell Connections Where plastic pipes are
permitted in systems connected to the shell of the

PART 4 SECTION 6|8 Pumps and Piping Systems


Where the manufacturer does not have a certified assembly is to be either 200 mm (8 in.)
quality system, the tests listed above will be required or 25% of the largest piping size to be
using samples from each batch of pipes being joined, whichever is greater.
supplied for use aboard the craft. 3 When conducting performance
Regardless of whether the manufacturer has a qualifications, each bonder and each
certified quality system, each length of pipe is to be bonding operator are to make up test
tested at the manufacturer’s production facility to a assemblies, the size and number of
hydrostatic pressure not less than 1.5 times the which are to be as required above.
maximum allowable internal pressure of the pipe in
4/6.15.3a. 4/6.15.7 Tests by the Manufacturer - Fire
Endurance Testing of Plastic Piping in the
4/6.15.6 Plastic Pipe Bonding Procedure Dry Condition (For Level 1 and 2)
Qualification a Test Method
a Procedure Qualification Requirements 1 The specimen is to be subjected to a
1 To qualify joint bonding procedures, the furnace test with fast temperature
tests and examinations specified herein increase similar to that likely to occur in
are to be successfully completed. The a fully developed liquid hydrocarbon
procedure for making bonds is to fire. The time/temperature is to be as
include the following: follows:
− materials used at the end of 5 minutes 945C (1733F)
− tools and fixtures at the end of 10 1033C (1891F)
minutes
− environmental requirements at the end of 15 1071C (1960F)
− joint preparation requirements minutes
− cure temperature at the end of 30 1098C (2008F)
− dimensional requirements and minutes
at the end of 60 1100C (2012F)
tolerances minutes
− test acceptance criteria for the 2 The accuracy of the furnace control is to
completed assembly be as follows:
2 Any change in the bonding procedure − During the first 10 minutes of the test,
which will affect the physical and variation in the area under the curve of
mechanical properties of the joint will mean furnace temperature is to be
require the procedure to be requalified. within ±15% of the area under the
b Procedure Qualification Testing standard curve.
1 A test assembly is to be fabricated in − During the first 30 minutes of the test,
accordance with the procedure to be variation in the area under the curve of
qualified and it is to consist of at least mean furnace temperature is to be
one pipe-to-pipe joint and one pipe-to- within ±10% of the area under the
fitting joint. When the test assembly standard curve.
has been cured, it is to be subjected to a − For any period after the first 30 minutes
hydrostatic test pressure at a safety of the test, variation in the area under
factor of 2.5 times the design pressure the curve of mean furnace temperature
of the test assembly, for not less than
is to be within ±5% of the area under
one hour. No leakage or separation of
the standard curve.
joints is to be allowed. The test is to be
− At any time after the first 10 minutes of
conducted so that the joint is loaded in
the test, the difference in the mean
both longitudinal and circumferential
furnace temperature from the standard
direction.
curve is to be within ±100C (±180F).
2 Selection of the pipes used for test
3 The locations where the temperatures
assembly is to be in accordance with the
are measured, the number of
following:
temperature measurements and the
−When the largest size to be joined is
measurement techniques are to be
200 mm (8 in.) nominal outside
approved by the Bureau.
diameter or smaller, the test assembly is
b Test Specimen
to be the largest pipe size to be joined.
1 The test specimen is to be prepared with
−When the largest size to be joined is
the joints and fittings intended for use in
greater than 200 mm (8 in.) nominal
the proposed application.
outside diameter, the size of the test

PART 4 SECTION 6|9 Pumps and Piping Systems


2 The number of specimens is to be removed) so that any leakage will be
sufficient to test typical joints and apparent.
fittings including joints between non- 3 Alternative test methods and/or test
metal and metal pipes and metal fittings procedures considered to be at least
to be used. equivalent including open pit testing
3 The ends of the specimen are to be method, may be accepted in cases where
closed. One of the ends is to allow the pipes are too large for the test
pressurized nitrogen to be connected. furnace.
The pipe ends and closures may be
outside the furnace. 4/6.15.8 Test by Manufacturer - Fire Endurance
4 The general orientation of the specimen Testing of Water-Filled Plastic Piping
is to be horizontal and it is to be (For Level 3)
supported by one fixed support with the a Test Method
remaining supports allowing free 1 A propane multiple burner test with a
movement. The free length between fast temperature increase is to be used.
supports is not to be less than 8 times 2 For piping up to and including 152 mm
the pipe diameter. ( 6 in.) O. D., the fire source is to
5 Most materials will require a thermal consist of two rows of 5 burners as
insulation to pass this test. The test shown in Figure 4/6.1. A constant heat
procedure is to include the insulation flux averaging 113.6 kW/m2 ( 36,000
and its covering. BTU/hr-ft2) ± 10% is to be maintained
6 If the insulation contains, or is liable to 12.5 ± 1 cm (5 ± 0.4 in.) above the
absorb, moisture the specimen is not to centerline of the burner array. This flux
be tested until the insulation has reached corresponds to a pre-mix flame of
an air dry-condition, defined as propane with a fuel flow rate of 5 kg/hr
equilibrium with an ambient atmosphere (11 lb/hr) for a total heat release of 65
of 50% relative humidity at 20±5C kW (3700 BTU/min.). The gas
(68±9F). Accelerated conditioning is consumption is to be measured with an
permissible provided the method does accuracy of at least ± 3% in order to
not alter the properties of the maintain a constant heat flux. Propane
component material. Special samples with a minimum purity of 95% is to be
are to be used for moisture content used.
determination and conditioned with the 3 For piping greater than 152 mm (6 in.)
test specimen. These samples are to be O. D., one additional row of burners is
so constructed as to represent the loss of to be included for each 51 mm (2 in.)
water vapor from the specimen having increase in pipe diameter. A constant
similar thickness and exposed faces. heat flux averaging 113.6 kW/m2
c Test Condition A nitrogen pressure inside the (36,000 BTU/hr-ft2) ± 10% is still to be
test specimen is to be maintained automatically at 0.7 maintained at the 12.5 ± 1 cm (5 ± 0.4
± 0.1 bar (0.7 ± 0.1 kgf/cm2, 10 ± 1.5 psi) during the in.) height above the centerline of the
test. Means are to be provided to record the pressure burner array. The fuel flow is to be
inside the pipe and the nitrogen flow into and out of increased as required to maintain the
the specimen in order to indicate leakage. designated heat flux.
d Acceptance Criteria 4 The burners are to be type “Sievert No.
1 During the test, no nitrogen leakage 2942” or equivalent which produces an
from the sample is to occur. air mixed flame. The inner diameter of
2 After termination of the furnace test, the the burner heads is to be 29 mm (1.14
test specimen together with fire in.). See Figure 4/6.1. The burner
protective coating, if any, is to be heads are to be mounted in the same
allowed to cool in still air to ambient plane and supplied with gas from a
temperature and then tested to the manifold. If necessary, each burner is
maximum allowable pressure of the to be equipped with a valve in order to
pipes as defined in 4/6.15.3a and b . adjust the flame height.
The pressure is to be held for a 5 The height of the burner stand is also to
minimum of 15 minutes without be adjustable. It is to be mounted
leakage. Where practicable, the centrally below the test pipe with the
hydrostatic test is to be conducted on rows of burners parallel to the pipe’s
bare pipe (i.e., coverings and insulation

PART 4 SECTION 6|10 Pumps and Piping Systems


axis. The distance between the burner ± 0.5 kgf/cm2, 43.5 ± 7.25) during the
heads and the pipe is to be maintained at test.
12.5 ± 1 cm (5 ± 0.4 in.) during the test. d Acceptance Criteria
The free length of the pipe between its 1 During the test, no leakage from the
supports is to be 0.8 ±0.05 m (31.5 ± 2 sample(s) is to occur except that slight
in.). See Figure 4/6.2. weeping through the pipe wall may be
b Test Specimen accepted.
1 Each pipe is to have a length of 2 After termination of the burner test, the
approximately 1.5 m (5 ft). test specimen together with fire
2 The test pipe is to be prepared with protective coating, if any, is to be
permanent joints and fittings intended to allowed to cool to ambient temperature
be used. Only valves and straight joints and then tested to the maximum
versus elbows and bends are to be tested allowable pressure of the pipes as
as the adhesive in the joint is the defined in 4/6.15.3a and b . The
primary point of failure. pressure is to be held for a minimum of
3 The number of pipe specimens is to be 15 minutes without significant leakage
sufficient to test all typical joints and (i.e., not exceeding 0.2 l/min. (0.05
fittings. gpm)). Where practicable, the
4 The ends of each pipe specimen are to hydrostatic test is to be conducted on
be closed. One of the ends is to allow bare pipe (i.e., coverings and insulation
pressurized water to be connected. removed) so that any leakage will be
5 If the insulation contains, or is liable to apparent.
absorb, moisture the specimen is not to
be tested until the insulation has reached 4/6.15.9 Tests by Manufacturer - Flame Spread
an air dry-condition, defined as a Test Method Flame spread of plastic piping is
equilibrium with an ambient atmosphere to be determined by IMO Resolution A.653(16)
of 50% relative humidity at 20±5C entitled “Recommendation on Improved Fire Test
(68±9F). Accelerated conditioning is Procedures for Surface Flammability of Bulkhead,
permissible provided the method does Ceiling, and Deck Finish Materials” with the
not alter the properties of the following modifications.
component material. Special samples 1 Test are to be made for each pipe
are to be used for moisture content material and size.
determination and conditioned with the 2 The test sample is to be fabricated by
test specimen. These samples are to be cutting pipes lengthwise into individual
so constructed as to represent the loss of sections and then assembling the
water vapor from the specimen having sections into a test sample as
similar thickness and exposed faces. representative as possible of a flat
6 The pipe samples are to rest freely in a surface. A test sample is to consist of at
horizontal position on two V-shaped least two sections. The test sample is to
supports. The friction between pipe and be at least 800 ± 5 mm (31.5 ± 0.2 in.)
supports is to be minimized. The long. All cuts are to be made normal to
supports may consist of two stands, as the pipe wall.
shown in Figure 4/6.2. 3 The number of sections that must be
7 A relief valve is to be connected to one assembled together to form a test
of the end closures of each specimen sample is to be that which corresponds
c Test Conditions to the nearest integral number of
1 The test is to be carried out in a sections which makes up a test sample
sheltered test site in order to prevent any with an equivalent linearlized surface
draft influencing the test. width between 155 mm (6 in.) and 180
2 Each pipe specimen is to be completely mm (7 in.). The surface width is
filled with dearated water to exclude air defined as the measured sum of the
bubbles. outer circumference of the assembled
3 The water temperature is not to be less pipe sections that are exposed to the
than 15C (59F) at the start and is to be flux from the radiant panel.
measured continuously during the test. 4 The assembled test sample is to have no
The water is to be stagnant and the gaps between individual sections.
pressure maintained at 3 ± 0.5 bar (3.1

PART 4 SECTION 6|11 Pumps and Piping Systems


5 The assembled test sample is to be 4/6.17.3 Cast Iron
constructed in such a way that the edges For temperatures not exceeding 232C (450F), cast
of two adjacent sections coincide with iron of the physical characteristics specified in 2/2.17
the centerline of the test holder. may be used in the construction of valves and fittings,
6 The individual test sections are to be except in locations for which it is specifically
attached to the backing calcium silicate prohibited elsewhere in the Rules.
board using wire (No. 18
recommended) inserted at 50 mm (2 in.) 4/6.17.4 Ductile (Nodular) Iron
intervals through the board and Nodular-iron applications for valves will be specially
tightened by twisting at the back. considered when the material has an elongation of not
7 The individual pipe sections are to be less than 12% in 50 mm (2 in.) and where the
mounted so that the highest point of the temperature does not exceed 343C (650F). See
exposed surface is in the same plane as 2/2.15.
the exposed flat surface of a normal
surface. 4/6.17.5 Brass and Bronze
8 The space between the concave Brass or bronze having the physical characteristics as
unexposed surface of the test sample specified in Section 2/2 may be used in the
and the surface of the calcium silicate construction of valves and fittings intended for
backing board is to be left void. temperatures up to 208C (406F). For temperatures
9 The void space between the top of the greater than 208C (406F) but not in excess of 288C
exposed test surface and the bottom (550F) high-temperature bronze is to be used and the
edge of the sample holder frame is to be chemical and physical characteristics are to be
filled with a high temperature insulating submitted for approval. For use in salt water systems,
wool if the width of the pipe segments see also 4/6.13.4.
extend under the side edges of the Valves, fittings and flanges of nonferrous material
sample holding frame. may be attached to nonferrous pipe by an approved
soldering method. For pressures up to 6.9 bar (7
4/6.15.10 Testing On Board After Installation kgf/cm2, 100 psi) and temperatures not exceeding
Piping systems are to be subjected to a hydrostatic 93C (200F) ordinary solder may be used, but for
test pressure of not less than 1.5 times the design higher pressures and temperatures the method and the
pressure to the satisfaction of the Surveyor. quality of solder to be used will be considered for
For piping required to be electrically conductive, each case.
earthing is to be checked and random resistance
testing is to be conducted to the satisfaction of the 4/6.17.6 Plastic
Surveyor. Rigid plastic compounds for valves and fittings in
plastic piping systems will be considered for Group II
4/6.17 Material of Valves and Fittings piping systems. The design pressure and temperature
together with the physical characteristics of the
4/6.17.1 General material verifying compliance with the requirements
The physical characteristics of such material are to be of 4/6.15 are to be submitted in all cases.
in accordance with the applicable requirements of
Section 2/2 or other such appropriate material 4/6.19 Valves
specifications as may be approved in connection with
a particular design for the stresses and temperatures 4/6.19.1 General
to which they may be exposed. Manufacturers are to a Standard Valves Valves constructed and
make physical tests of each melt and, upon request, tested in accordance with a recognized standard may
are to submit the results of such tests to the Bureau. be used subject to compliance with 4/6.19.3.
b Non-Standard Valves All other valves not
4/6.17.2 Forged or Cast Steel certified by the manufacturer as being in accordance
In any system, forged or cast steel may be used in the with a recognized standard may be accepted based on
construction of valves and fittings for all pressures evidence verifying their suitability for the intended
and temperatures. Consideration is to be given to the service. Acceptable evidence includes testing or
possibility of graphite formation in the following analysis demonstrating adequacy including both
steels: Carbon steel above 425C (800F); carbon- structural and material capability aspects. Drawings
molybdenum steel above 468C (875F); chrome- of such valves showing details of construction and
molybdenum steel (with chromium under 0.60%) materials are to be submitted for review, as well as
above 524C (975F). basis for valve pressure rating, such as design
calculations or appropriate burst test data.

PART 4 SECTION 6|12 Pumps and Piping Systems


4/6.19.2 Construction 4/6.21 Pipe Fittings
All valves are to close with a right hand (clockwise)
motion of the handwheel when facing the end of the 4/6.21.1 General
stem and are to be either of the rising-stem type or All fittings in Group I piping are to have flanged or
fitted with an indicator to show whether the valve is welded ends in sizes over 89 mm O.D. (3 in. NPS).
open or closed. Screwed fittings may be used in Group I piping
All valves of Group I piping systems having systems provided the temperature does not exceed
nominal diameters exceeding 50 mm (2 in.) are to 496C (925F) and the pressure does the exceed the
have bolted, pressure seal, or breech lock bonnets and maximum pressure indicated below for the pipe size.
flanged or welding ends. Welding ends are to be the
butt weld type except that socket weld ends may be Pipe Size Maximum Pressure
used for valves having nominal diameters of 80 mm mm O. D. (in. NPS) bar (kgf/cm2, psi)
(3 in.) or less up to and including 39.2 bar (40.0 above 89 (3) not permitted in
kgf/cm2) pressure rating class (ASME 600 Class), and Group I piping service
for valves having nominal diameters of 65 mm (2.5 above 60 (2) through 89 (3) 27.6 (28.10, 400)
in.) or less up to and including 98.1 bar (100 kgf/cm2)
above 33 (1) 41.4 (42.2, 600)
pressure rating class (ASME 1500 Class). through 60 (2)
All cast iron valves are to have bolted bonnets or
above 27 (0.75) 82.8 (84.4, 1200)
are to be of the union bonnet type. For cast iron through 33 (1)
valves of union bonnet type, the bonnet ring is to be
of steel, bronze, or malleable iron. 27 (0.75) 103 (105.5, 1500)
and smaller
Stems, discs or disc faces, seats, and other
wearing parts of valves are to be of corrosion
Flared, flareless, and compression fittings may be
resistant materials suitable for intended service.
used for tube sizes not exceeding 60 mm O.D. (2 in.
Valves are to be designed for the maximum
NPS) in Group I piping. In Group II piping, screwed
pressure to which they will be subjected. The design
fittings, flared, flareless, and compression tube
pressure is to be at least 3.4 bar (3.5 kgf/cm2, 50 psi).
fittings will be accepted without size limitations.
Valves used in open systems, such as vent and drain
Flared fittings are to be used for flammable fluid
lines, (for example, level gauge and drain cocks) may
systems except that both flared and flareless fittings
be designed for a pressure below 3.4 bar (3.5 kg/cm2,
of the non-bite type may be used when the tubing
50 psi) subject to the requirements of 4/6.19.1. Large
system is of steel or nickel-copper or copper-nickel
fabricated ballast manifolds which connect lines
alloys. Only flared fittings are to be used when
exceeding 200 mm (8 in.) nominal pipe size may be
tubing for flammable fluid systems is of copper or
used when the maximum pressure to which they will
copper-zinc alloys. See 4/6.67.4 for hydraulic
be subjected does not exceed 1.7 bar (1.75 kgf/cm2,
systems.
25 psi).
All valves for Group I piping systems and valves
4/6.21.2 Hydrostatic Test and Identification
intended for use in oil lines are to be constructed so
All fittings are to be subjected by the manufacturer to
that the stem is positively restrained from being
a hydrostatic test at a pressure equal to that stipulated
screwed out of the body (bonnet). Plug valves,
by the American National Standards Institute or other
butterfly valves, and valves employing resilient
recognized standard. They are to bear the trademark
material will be subject to special consideration.
of the manufacturer legibly stamped or cast on the
Valve operating systems for all valves which cannot
exterior of the fitting and also the primary pressure
be manually operated are to be submitted for
rating at which the manufacturer guarantees the fitting
approval.
to meet the requirements of the standards.
4/6.19.3 Hydrostatic Test and Identification
4/6.21.3 Non-Standard Fittings
All valves are to be subjected by the manufacturer to
Fittings which are not certified by the manufacturer as
a hydrostatic test at a pressure equal to that stipulated
being in accordance with a recognized standard may
by the American National Standards Institute or other
be accepted based on evidence verifying their
recognized standard. They are to bear the trademark
suitability for the intended service. Acceptable
of the manufacturer legibly stamped or cast on the
evidence include testing or analysis demonstrating
exterior of the valve and the primary pressure rating
adequacy including both structural and material
at which the manufacturer identifies the valve as
capability aspects. Drawings of such fittings showing
meeting the requirements of the standards.
details of construction, material and design
calculations or test results are to be submitted for
review.

PART 4 SECTION 6|13 Pumps and Piping Systems


4/6.22 Welded Non-Standard Valves and 4/6.25 Sea Inlets and Overboard Discharges
Fittings
4/6.25.1 Installation
Non-Standard steel valves and fittings fabricated by
Piping connections bolted to the shell plating are to
means of fusion welding are to comply also with the
have the bolt heads countersunk on the outside and
requirements of Section 2/3. However, after a
the bolts threaded through the plating. Where a
manufacturer's procedure in the fabrication of
reinforcing ring of sufficient thickness is welded to
equipment of this kind has been demonstrated by tests
the inside of the shell, studs may be used.
to the satisfaction of a Surveyor to the Bureau,
subsequent tests on the product need not be
4/6.25.2 Valve Connections to Shell
witnessed, but the manufacturer's guarantee that the
Pipe connections fitted between the shell and the
Rules are complied with will be accepted as for other
valves are to be of substantial construction (i.e., pipe
valves and fittings which conform to standards of the
wall thickness is to be equal to the shell plating
American National Standards Institute or other
thickness but need not be greater than extra heavy)
recognized standards.
and as short as possible. Wafer type valves are not to
be used for any connections to the vessel's shell
4/6.23 Flanges
unless specially approved. Lug type butterfly valves
used as shell valves are to have a separate set of bolts
4/6.23.1 General
on each end of the valve so that the inboard end may
Flanges are to be designed and fabricated in
be disconnected with the valve closed to maintain its
accordance with a recognized standard. Slip-on
watertight integrity.
flanges from flat plate may be substituted for hubbed
slip-on flanges in Group II piping systems.
4/6.25.3 Materials
All shell fittings and valves required by 4/6.27 and
4/6.23.2 Group I Piping Flanges
4/6.29 are to be of steel, bronze or other approved
In Group I piping, flanges may be attached to the
ductile material. Valves of ordinary cast iron or
pipes by any of the following methods appropriate for
similar material are not acceptable. The use of
the material involved:
nodular iron, also known as ductile iron or
a Steel Pipe Over 60 mm O.D. (2 in. NPS)
spheroidal-graphite iron, will be accepted provided
steel pipes are to be expanded into steel flanges, or
the material has an elongation not less than 12% in 50
they may be screwed into the flanges and seal-
mm (2 in.). All pipes to which this subsection refers
welded. They may in all cases be attached by fusion
are to be of steel or other equivalent material, subject
welding in compliance with the requirements of
to special approval.
2/3B.9. Smaller pipes may be screwed without seal-
welding but oil lines are, in addition, to be expanded
4/6.25.4 Shell Reinforcement
into the flanges in order to insure uniformly tight
Overboard discharges are to have spigots extending
threads.
through the shell plate and doubling plate where fitted
b Nonferrous Pipe In Group I, nonferrous pipes
but need not project beyond the outside surface of the
are to be brazed to composition metallic or steel
vessel.
flanges, and in sizes of 60 mm O.D. (2 in. NPS) and
under they may be screwed.
4/6.25.5 Common Overboard Discharge
In general, various types of systems which discharge
4/6.23.3 Group II Piping Flanges
overboard are not to be interconnected without
Similar attachments are also to be used in Group II
special approval; that is closed pumping systems,
piping. However, modifications are permitted for
deck scuppers, gravity drains, etc. are not to have a
welded flanges as noted in 2/3B.9.3 and 2/3B.9.4 and
common overboard discharge
screwed flanges of suitable material may be used in
all sizes.
4/6.27 Machinery and Pumping Systems
4/6.23.4 Group II Plastic Piping Flanges
4/6.27.1 Valves Required
Rigid plastic compounds for flanges in plastic piping
Positive closing valves are to be fitted at the shell in
systems will be considered for Group II piping
inlet and discharge piping. The controls are to be
systems. The design pressure and temperature
readily accessible and are to be provided with
together with the physical characteristics of the
indicators showing whether the valves are open or
material are to be submitted in all cases.
closed.

PART 4 SECTION 6|14 Pumps and Piping Systems


4/6.27.2 Sea Chests 4/6.29.3 Scuppers from Superstructures or
The location of sea chests is to be such as to minimize Deckhouses
the probability of blanking off the suction and a Enclosed Cargo Spaces Drainage of enclosed
arranged so that the valves may be operated from the cargo spaces situated on the bulkhead deck or the
floors or gratings. Power-operated sea valves are to freeboard deck is to be provided with the following:
be arranged for manual operation in the event of a 1 Where the summer freeboard is such
failure of the power supply. that the deck edge of the space being
Sea chests are to be fitted with strainer plates at drained is not immersed when the ship
the shell. The strainers are to have a clear area of at heels 5 degrees, the drainage is to be by
least 1.5 times the area of the sea valves. Efficient means of a sufficient number of
means are to be provided for clearing the strainers. scuppers of suitable size discharging
directly overboard in accordance with
4/6.29 Scuppers and Drains 4/6.29.1.
2 Where the summer freeboard is such
4/6.29.1 Discharges through the Shell that the deck edge of the space being
Discharges led through the shell either from spaces drained is immersed when the ship heels
below the freeboard deck or from within 5 degrees, the drainage of the enclosed
superstructures and deckhouses on the freeboard deck cargo spaces is to be led to a suitable
fitted with doors complying with the requirements of space, or spaces, of adequate capacity,
3/18.7.1 are to be fitted with efficient and accessible having a high water level alarm and
means for preventing water from passing inboard. provided with suitable arrangements for
Normally, each separate discharge is to have one discharge overboard. In addition the
automatic non-return valve with a positive means of system is to be designed such that;
closing it from a position above the freeboard deck a the number, size and disposition of
except as follows. the scuppers are to prevent
a Where the vertical distance from the summer unreasonable accumulation of free
loadline to the inboard end of the discharge pipe water;
exceeds 0.01L, the discharge may have two automatic b the pumping arrangements are to
non-return valves without positive means of closing, take into account the requirements
provided that the inboard valve is always accessible for any fixed, pressurized, water
for examination under service conditions. The spraying, fire extinguishing system;
inboard valve is to be above the tropical load c water contaminated with oil or
waterline. If this is not practicable, then, provided a other dangerous substances is not
locally controlled stop valve is interposed between drained to machinery spaces or
the two non-return valves, the inboard valve need not other spaces where sources of
be fitted above the tropical load waterline. ignition may be present; and
b Where the vertical distance exceeds 0.02L, a d where the enclosed cargo space is
single automatic non-return valve without positive protected by a carbon dioxide fire
means of closing may be accepted provided the valve extinguishing system the deck
and discharge outlet are located above the deepest scuppers are fitted with means to
load waterline. prevent the escape of the
L is defined in Section 3/1. smothering gas.
The means for operating the positive-action valve b Open Superstructures and Deckhouses
is to be readily accessible and provided with an Scuppers leading from superstructures or deckhouses
indicator showing whether the valve is open or not fitted with doors complying with the requirements
closed. of 3/18.7.1 are to be led overboard.

4/6.29.2 Scuppers and Discharges below the 4/6.29.4 Craft Receiving Subdivision Loadlines
Freeboard Deck For craft receiving subdivision loadlines, the
Scuppers and discharge pipes originating at any level bulkhead deck is to apply to provisions given in
and penetrating the shell either more than 450 mm 4/6.29.1 when it is higher than the freeboard deck.
(17.5 in.) below the freeboard deck or less than 600
mm (23.5 in.) above the summer load waterline are to
be provided with a non-return valve at the shell. This
valve, unless required by 4/6.29.1, may be omitted if
the piping has a wall thickness at least equal to the
thickness of the shell plating or extra-heavy pipe,
whichever is less.

PART 4 SECTION 6|15 Pumps and Piping Systems


4/6.31 Cooler Installations External to the Hull b Multihull Craft
1 20 m (65 ft) or Greater On multihull
4/6.31.1 General craft 20 m (65 ft) in length or greater,
The inlet and discharge connections of external each hull is to be provided with at least
cooler installations are to be in accordance with two power-driven bilge pumps, unless
4/6.25.1 through 4/6.25.3 and 4/6.27.1 except that a bilge pump in one hull is capable of
wafer type valves will be acceptable. pumping bilge in the other hull. At
least one bilge pump in each hull is to
4/6.31.2 Keel Cooler Installations be an independently-driven pump.
The positive closing valves required by 4/6.31.1 need 2 Under 20 m (65 ft) On multihull craft
not be provided if the keel (skin) cooler installation is under 20 m (65 ft) in length, each hull
integral with the hull. To be considered integral with is to be provided with at least one fixed
the hull, the installation is to be constructed such that power-driven bilge pump, which may
channels are welded to the hull with the hull structure be an attached unit, unless the system is
forming part of the channel, the channel material is to arranged such that a single fixed
be at least the same thickness and quality as that power-driven bilge pump is capable of
required for the hull and the forward end of the cooler taking suction from either hull. In
is to be faired to the hull with a slope of not greater either case, one portable hand pump is
than 4 to 1. also to be provided.
If positive closing valves are not required at the c Alternative Arrangement - Submersible
shell, all flexible hoses or joints are to be positioned Pumps As an alternative to a or b, an arrangement
above the deepest load waterline or be provided with utilizing submersible pumps may be utilized. See
an isolation valve. 4/6.41.
4/6.35.3 Capacity
4/6.31.3 Grid Cooler Installations
The capacity, Q, of each pump is to be in accordance
Where grid coolers are used, if the shell penetrations
with the following:
are not fully welded, the penetration is to be encased
in a watertight enclosure. Craft Length, L Minimum Capacity per Pump,
Q

4/6.33 General Arrangement of Bilge Systems Below 20 m (65 ft.) 5.5 m3/hr (25 gpm)
(hand pump 5 gpm, 1.13 m3/hr)
A pumping system is to be provided in all craft
20 m (65 ft.) or greater 11 m3/hr (50 gpm)
capable of pumping from and draining any but below 30.5 m (100 ft.)
compartment when the craft is on an even keel and
either upright or listed 5 degrees. For this purpose 30.5 m (100 ft.) or greater 14.33 m3/hr (66.6 gpm)
but below 45.7 m (150 ft.)
wing suctions will often be necessary, except in
narrow compartments at the ends of the craft. 45.7 m (150 ft.) and greater 5.66 d2/103 m3/hr
(16.1 d2 gpm)
Arrangements are to be made whereby water in the
compartment will drain to the suction pipes. Efficient where
means are to be provided for draining water from all d = required diameter of main bilge line suction,
tank tops and other watertight flats. Peak tanks, chain mm or in. See 4/6.39.5
lockers and decks over peak tanks may be drained by
ejectors or hand pumps. When more than two pumps are connected to the
bilge system, their arrangement and aggregate
4/6.35 Bilge Pumps capacity are not to be less effective.
4/6.35.1 Number of Pumps
a Monohull Craft 4/6.35.4 Centrifugal Pumps
1 20 m (65 ft) or Greater Each monohull Where centrifugal pumps are installed, suitable means
craft 20m (65 ft) in length or greater is for priming are to be provided.
to be provided with two power-driven
bilge pumps, one of which may be 4/6.35.5 Independent Power Bilge Pumps
attached to the propulsion unit. Sanitary, ballast and general service pumps may be
2 Under 20 m (65 ft) Each monohull accepted as independent power bilge pumps,
craft under 20 m (65 ft) in length is to provided they are of the required capacity and are
be provided with at least one fixed fitted with the necessary control valves required by
power-driven pump, which may be an 4/6.39.1 for pumping bilges. Pumps used for
attached unit, and one portable hand pumping oil or other flammable or combustible
pump. liquids are not to be used as bilge pumps.

PART 4 SECTION 6|16 Pumps and Piping Systems


4/6.39 Bilge and Ballast Piping lines in other compartments are to be fitted with
suitable strainers having an open area of not less than
4/6.39.1 General three times the area of the suction pipe. In addition
The arrangement of the bilge and ballast pumping strainers are to be fitted in accessible positions
systems is to be such as to prevent the possibility of between the bilge manifolds and the pumps.
water or oil passing into the cargo and machinery
spaces, or from one compartment to another, whether 4/6.39.5 Size of Bilge Suctions
from the sea, water ballast or oil tanks. The bilge and The least internal diameter of bilge suction pipes is to
ballast mains are to have separate control valves at be that of the nearest commercial size within 6 mm
the pumps. (0.25 in.) of the diameter determined by the following
equations.
4/6.39.2 Installation a Main Line For the diameter of main bilge line
Bilge or ballast pipes, where permitted to pass suctions and direct bilge suctions to the pumps:
through compartments intended for the carriage of
oil, are to be of either steel or wrought iron. d = 25 + 1.68 L( B + D) mm
Where bilge pipes in way of deep tanks are not
d = 1 + L ( B + D) 2500 in.
led through a watertight or oiltight tunnel, the bilge
lines are to be of steel and extra heavy. Similarly,
b Branch Lines For the equivalent diameter of
where ballast pipes in way of deep tanks, other than
the combined branch suctions to a compartment:
ballast tanks, are not led through a watertight or
oiltight tunnel, the ballast lines are to be of steel and d = 25 + 2.16 c( B + D) mm
extra heavy. For both bilge and ballast piping, the
number of joints is to be kept to a minimum and are d = 1 + c ( B + D) 1500 in.
to be welded or extra heavy flanged. The piping
within a deep tank is to be installed to take care of d = internal diameter of pipe in mm or in
expansion. A non-return valve is to be fitted at the L = length of craft as defined in Section 3/1
open end of bilge pipes. in m or ft
B = for monohull craft, breadth of craft as
4/6.39.3 Manifolds, Cocks and Valves defined in Section 3/1 in m or ft
a General All manifolds, cocks and valves in for multihull craft, the breadth of a hull
connection with the bilge pumping arrangement are to at or below the design waterline
be in positions which are accessible at all times under c = length of compartment in m or ft
ordinary circumstances. All valves in the machinery D = molded depth to bulkhead or freeboard
space controlling the bilge suctions from the various deck in m or ft except that, for the main
compartments are to be of the stop-check type. If line, in a craft having an enclosed cargo
valves are fitted at the open ends of pipes, they are to space on the bulkhead or freeboard deck
be of the non-return type. which is internally drained in accordance
b Controls for Ballast Tank Valves Ballast tank with 4/6.29.3a2 and which extends for
valves are to be arranged so they will remain closed the full length of the ship, D is to be
at all times except when ballasting. For this purpose, measured to the next deck above the
manual screw thread operated valves, positive bulkhead or freeboard deck. Where the
holding arrangements for butterfly type valves or enclosed cargo spaces cover a lesser
other equivalent arrangements may be used. Where length, D is to be taken as a molded
installed, remote controlled valves are to be arranged depth to the bulkhead or freeboard deck
so they will close and remain closed upon loss of plus lh/L where l and h are aggregate
control power, or will remain in their last position and length and height respectively of the
are provided with a readily accessible manual means enclosed cargo spaces.
of operation in case of loss of power to the valve c Main Line Reduction Where engine room
control system. Remote control of bilge and ballast bilge pumps are fitted primarily for drainage within
valves is to be clearly marked at the control station the engine room, L may be reduced by the combined
and means are to be provided to indicate whether the length of the cargo holds. In such cases, the cross
valve is open or closed. sectional area of the bilge main is not to be less than
twice the required cross sectional area of the engine
4/6.39.4 Strainers room branch lines.
Bilge lines in machinery spaces other than emergency
suctions are to be fitted with strainers easily
accessible from the floor plates and are to have
straight tail pipes to the bilges. The ends of bilge

PART 4 SECTION 6|17 Pumps and Piping Systems


d Alternate Size Requirements For craft below The total capacity, Qt, of the fixed submersible
45.7 m (150 ft.) in length the bilge main sizes may be bilge pumps for each hull is not to be less than 2.4
in accordance with the following in lieu of 4/6.39.5a. times the pump capacity, Q, determined in 4/6.35.3.
Craft Length Minimum Pipe Size (I.D.)
The capacity, Qn, of each submersible pump is not
to be less than:
Below 20 m (65 ft.) 25 mm (1 in.)
20 m (65 ft.) or greater but 32 mm (1.25 in)
Qn = Qt (N − 1) m3/hr (gpm), with a minimum of
below 30.5 m (100 ft.) 8 m3/hr (35 gpm)
30.5 m (100 ft) or greater but 38 mm (1.5 in.) N = number of submersible pumps
below 45.7 m (150 ft)
4/6.42 Bilge Alarms
e Size Limits For craft of 45.7 m (150 ft) in
length or greater, no main suction piping is to be less Any unattended space for which bilge pumping
than 63 mm (2.5 in.) internal diameter. For all craft, arrangements are required is to be provided with a
no branch piping need be more than 100 mm (4 in.) bilge alarm.
I.D., nor is it to be less than 25 mm (1 in.) I.D..
4/6.43 Vent Pipes
4/6.39.6 Gravity Drains
Gravity drains that penetrate the main machinery 4/6.43.1 General
space watertight bulkheads below the freeboard deck Except for comparatively small compartments that are
and terminate within the main machinery space are to not fitted with a fixed means of drainage, vent pipes
be fitted with a valve operable from above the are to be fitted to all tanks, cofferdams, voids, tunnels
freeboard deck or with quick-acting, self-closing and compartments which are not fitted with other
valves. The valve should preferably be located in the ventilation arrangements. In all craft the structural
main machinery space. When gravity drains from arrangement in double-bottom and other tanks is to be
other spaces are terminated in cargo holds, the cargo such as to permit the free passage of air and gases
hold bilge well is to be fitted with a high level alarm. from all parts of the tanks to the vent pipes. Each
Gravity drains which terminate in spaces which are tank is to be fitted with at least one vent pipe, which
protected by fixed gas extinguishing systems are to be is to be located at the highest part of the tank. Vent
fitted with means to prevent the escape of pipes are to be arranged to provide adequate drainage
extinguishing medium. under normal conditions.

4/6.40 Emergency Bilge Suctions 4/6.43.2 Height


Where air pipes extend above the freeboard or
An emergency bilge suction is to be fitted for each superstructure decks, the exposed parts of the pipes
machinery space containing a propulsion prime are to be of at least Standard thickness; the height
mover. This suction is to be provided from the from the deck to the point where water may have
largest suitable pump in the engine room except a access below is to be at least 760 mm (30 in.) on the
required bilge pump. The area of the direct bilge freeboard deck and 450 mm (17.5 in.) on the
suction pipe is to be equal to the full suction inlet of superstructure deck. Where these heights may
the pump selected. A suitable overboard discharge interfere with the working of the vessel, a lower
line is to be provided and the means of control of the height may be approved, provided that the closing
direct bilge suction is to be readily accessible and so arrangements and other circumstances justify a lower
located to provide rapid operation. The emergency height.
bilge suction is to be provided with suitable non- As an alternative, the vent pipes may be carried
return valves. out through the side of the vessel. The pipe is to
extend to a point close to the weather deck and a non-
4/6.41 Submersible Bilge Pumps return valve is to be located as close as practicable to
In bilge pumping arrangements where a bilge main is the shell. Other means will be considered provided
not provided, then, with the exception of the spaces they ensure equivalent protection against flooding.
forward of public spaces and crew accommodation, at
least one fixed submersible pumps is to be provided 4/6.43.3 Size
for each space. In addition, at least one portable Vent pipes are to have a minimum internal diameter
pump is to be provided and be supplied from the not less than 38 mm (1.5 in.) and not less than the
emergency supply, if electric, for use on individual internal diameter of the fill line. Where tanks are to
spaces. be filled by pump pressure, the aggregate area of the
vents in the tank is to be at least 125% of the effective
area of the filling line, except that when overflows are

PART 4 SECTION 6|18 Pumps and Piping Systems


fitted, the area of the overflow is to be at least 125% acceptable, provided there are suitable arrangements
of the effective area of the filling line and the vents to insure the valve not being closed by unauthorized
need not exceed the above minimum size. persons and provided a notice is posted in a
Notwithstanding the above, the pump capacity conspicuous place at the operating station to the
and pressure head are to be considered in the sizing effect that the valve is never to be closed except as
of vents, and overflows; when high capacity and/or may be required in an emergency.
high head pumps are used, calculations demonstrating Overflow pipes from combustible and flammable
the adequacy of the vent and overflows are to be liquid tanks are to be led to an overflow tank of
submitted. adequate capacity or to a storage tank having space
reserved for overflow purposes. An alarm device is
4/6.43.4 Location to be provided to give warning when the liquid
Vents for compartments required for subdivision reaches a predetermined level in the overflow tank.
(such as double bottom or wing spaces) are to be led The sight glasses are to be fitted only in vertical
to above the freeboard or bulkhead deck. In sections of overflow pipes.
addition, vents for ballast tanks, fuel oil tanks, and When overflows from the tanks in more than one
those cofferdams adjacent to fuel oil tanks are to be watertight subdivision are connected to a common
led to the weather. Vents for other tanks may header below the freeboard or bulkhead deck, the
terminate within the machinery space but are to be arrangement is to be such as to prevent fore-and-aft
located so as to preclude the possibility of flooding of one watertight bulkhead subdivision from
overflowing on electrical equipment, engines or another in the event of damage.
heated surfaces.
4/6.47 Sounding
4/6.43.5 Vent Outlets
All vent and overflow pipes on the open deck are to 4/6.47.1 General
terminate by way of return bends. All tanks are to be fitted with a suitable means of
a Fuel Oil Tank Vents Vent outlets from fuel determining the level of the liquid therein. Such
oil tanks are to be fitted with corrosion-resistant means may be sounding pipes, gauge glasses, or other
flame screens having a clear area through the mesh of approved level indicating systems or devices.
not less than the required area of the vent pipe. Compartments, including cofferdams and pipe
b Weathertight Closure Satisfactory means, tunnels, which are not readily accessible are to be
permanently attached, are to be provided for closing fitted with sounding pipes if the compartment is
the openings of the vent pipes. The means of closing adjacent to the sea or has pipes carrying liquids
vent pipes is to be weather tight. Closing devices are passing through it.
to be automatic if, while the craft is at its draught
corresponding to summer loadline, or timber summer 4/6.47.2 Sounding Pipes
load line where assigned, the openings of the air pipes Sounding pipes are not to be less than 38 mm (1.5 in.)
submerge at angles up to 40 degrees or up to a lesser inside diameter. They are to be led as straight as
angle which may be accepted on the basis of stability possible from the lowest part of the tank or
requirements. Automatic devices are also to be fitted compartment to the bulkhead deck or to a position
on vents for craft designed for the carriage of deck which is always accessible. If sounding pipes
cargoes which may prevent access to the vents. terminate below the freeboard deck, they are to be
provided with means for closing in the following
4/6.45 Overflow Pipes manner:
a Oil Tanks Quick-acting, self-closing gate
Overflow pipes discharging through the side of the
valves are required.
craft are to be located as far above the deepest
b Other Tanks A screw cap secured to the pipe
loadline as practicable and are to be provided with
with a chain or a gate valve is required.
non-return valves located on the craft's side. Where
the overflow does not extend above the freeboard Provision is to be made to prevent damaging the
deck, there is to be provided in addition an efficient craft's plating by the striking of the sounding rod. In
and accessible means for preventing water from general sounding pipes are not to pass through bilge
passing inboard. Such means may consist of a non- wells, but if this is not practicable, the pipe is to be at
return valve located in an accessible position above least extra-heavy in the bilge well. Sounding pipes
the deepest loadline. for combustible or flammable fluids are not to
Where it is impracticable to locate the valve in an terminate in accommodation spaces.
accessible position, one non-return valve with
positive means for closing from an accessible position
above the freeboard or bulkhead deck will be

PART 4 SECTION 6|19 Pumps and Piping Systems


c Ignition of Spillage Sounding pipes for fuel 4/6.47.4 Level Indicating Systems and Devices
oil tanks are not to terminate in any space where the Where a level indicating device or system is provided
risk of ignition of spillage may exist. In particular, for determining the level in a tank containing
they are not to not terminate in machinery spaces or flammable or combustible liquid, failure of the
in close proximity to internal combustion engines, device/system is not to result in the release of the
generators, electric equipment or surfaces with contents of the tank through the device. If an
temperatures in excess of 220C (428F) in other overflow is not fitted, means are also to be provided
spaces. Where it is impracticable to do otherwise, to prevent overfilling of the tank in the event of
sounding pipes from fuel oil tanks may terminate in malfuction of the indicating device/system.
machinery spaces provided the following are met:
1 The sounding pipes terminate in 4/6.49 Fuel Oil Piping Systems
locations remote from ignition hazards
or effective precautions such as 4/6.49.1 General Arrangement
shielding are taken to prevent fuel oil a Tanks As far as practicable, fuel oil tanks are
spillage from coming into contact with a to be part of the craft’s structure and located outside
source of ignition; and of Category A machinery spaces. Where fuel oil
2 The terminations of sounding pipes are tanks, other than double bottom tanks, are necessarily
fitted with quick-acting, self-closing located adjacent to or within a Category A machinery
gate valves and with a small diameter space, at least one of their vertical sides is to be
self-closing test cock or equivalent contiguous to the machinery space boundaries, and
located below the gate valve is to be preferably have a common boundary with the double
provided for the purpose of ascertaining bottom tanks, if fitted. The area of the tank boundary
that fuel oil is not present in the common with the machinery spaces is to be kept to a
sounding pipe before the gate valve is minimum. Where such tanks are situated within the
opened. Provisions are to be made so as boundaries of a Category A machinery space, they are
to prevent spillage of fuel oil through not to contain fuel oil having a flash point of 60C
the test cock from creating an ignition (140F) or less and they are to be made of steel or
hazard; and equivalent material.
3 An approved level gauge is provided. Tanks containing fuel oil are to be separated from
For oil tanks other than double bottoms, passenger, crew, and baggage compartments by
the oil level gauge may be omitted vapor-proof enclosures or cofferdams which are
provided an overflow system is fitted. suitably ventilated and drained. Fuel oil is not to be
The oil level gauge may also be omitted carried forward of public spaces and crew
for craft less than 500 gross tons. accommodation.
In general, the use of free standing fuel oil tanks is
4/6.47.3 Gauge Glasses to be avoided. Where permitted, they are to be
Tanks may be fitted with gauge glasses, provided the placed in an oil tight spill tray of ample size with
gauge glasses are fitted with a valve at each end and adequate means of drainage in accordance with
adequately protected from mechanical damage. 4/6.7.13.
Gauge glasses for tanks containing flammable or b Spillage No fuel oil tank is to be situated
combustible liquids are to be of the flat glass type where spillage or leakage therefrom can constitute a
having approved self-closing valves at each end. For hazard by falling on heated surfaces. Precautions are
hydraulic oil tanks located in spaces other than to be taken to prevent any oil that may escape under
category A machinery spaces, cylindrical gauge pressure during inspection or maintenance of any
glasses with approved self closing valves at each end pump, filter or heater from coming into contact with a
will be acceptable provided such spaces do not source of ignition as defined in 4/1.17.9.
contain internal combustion engines, generators,
major electrical equipment or piping having a surface 4/6.49.2 Piping, Valves and Fittings
temperature in excess of 220 C (428F). Gauge Fuel oil pipes, valves and fittings are to be of steel or
glasses are not to be used for fuel oil with a flash other approved materials.
point below 43C (109F).
Gauge glasses for tanks integral with the shell 4/6.49.3 Oil Heating Arrangements
which are located below the deepest load waterline a Oil Heaters Where heaters are provided in
are to be of the flat glass type and have approved fuel oil systems they are to be fitted with a
self-closing valves at each end. temperature control and either a high temperature
alarm or a low flow alarm, except where the
maximum temperature of the heating medium does
not exceed 220C (428F).

PART 4 SECTION 6|20 Pumps and Piping Systems


Where electric heaters are fitted they are to be directly over the gutterway in way of deep and
arranged to de-energize automatically when the oil settling tanks. Pumps, strainers, etc., requiring
level falls to a predetermined height to ensure that the occasional examination are to have drip pans.
heating elements are permanently submerged during
operation. In addition, a safety temperature switch 4/6.51.4 Valves on Oil Tanks
with a manual reset independent from the automatic Where pipe lines emanate from oil tanks at such a
control sensor is to be provided to cut off the electric level that they will be subjected to a static head of oil
power supply in order to avoid a surface temperature from the tank, they are to be fitted with positive
of 220C (428F) or above. closing valves located at the tank. Where the oil
b Tanks Unless specially approved otherwise, piping passes through adjacent tanks, the valve
fuel oil in storage tanks is not to be heated to required above may be located where the pipe run
temperatures within 10C (18F) below flash point of exits the adjacent tank(s) provided the piping in the
the fuel oil. adjacent tanks is extra-heavy and has all welded
Where heating arrangements are provided for connections.
settling and service tanks the control and alarm If the valves are installed on the outside of the
requirements of 4/6.49.3a are applicable. tank, they are not to be of cast iron. The use of
c Piping Arrangement As far as practicable, all nodular iron, also known as ductile iron or
parts of the oil fuel system containing heated oil spheroidal-graphite iron, may be used provided the
under pressure exceeding 1.8 bar (1.8 kgf/cm2, 26 material has an elongation not less than 12% in 50
psi) are not to be placed in a concealed position such mm (2 in.). Arrangements are to be provided for
that defects and leakage cannot readily be observed. closing them at the valve and for tanks having a
The machinery spaces in way of such parts of the oil capacity of 500 liters (132 US gal.) or greater, from a
fuel system are to be adequately illuminated. readily accessible and safe location outside of the
compartment in which the valve is located.
4/6.49.4 Fuel Oil Purifiers If the positive closing valve required above is
Fuel oil purifiers for heated oil are to be placed in a situated in a shaft tunnel or pipe tunnel or similar
separate room or rooms reserved for the purifiers and space, arrangements for closing may be effected by
their heaters. If it is impracticable to locate the means of an additional valve on the pipe or pipes
purifiers in a separate room, special consideration outside the tunnel or similar space. If such additional
will be given with regard to location, containment of valve is fitted in the machinery space, it is to be
possible leakage and shielding. operated from a position outside this space.
If the valves are located inside of the tank, they
4/6.51 Fuel-oil Transfer and Filling may be of cast iron and arranged for remote control
only, but additional valves for local control are to be
4/6.51.1 General located in the machinery space.
Where fuel oil transfer arrangements are furnished, Where independent filling lines are fitted, they are
two transfer pumps are to be provided and one of to enter at or near the top of the tank; but if this be
them is to be independent of the main engine. The impracticable, they are to be fitted with non-return
fuel oil pumping arrangements are to be distinct from valves at the tank.
the other pumping systems as far as practicable, and The valves required above may be remotely
the means provided for preventing dangerous operated by reach rods or by electric, hydraulic, or
interconnection in service are to be thoroughly pneumatic means. Other means may be specifically
effective. Where daily service fuel oil tanks are filled considered provided that they are not less effective.
automatically or by remote control, means are to be The source of power to operate these valves is to be
provided to prevent overflow spillage. located outside of the space in which the valves are
located. The positioning of the valve by either the
4/6.51.2 Pipes in Oil Tanks local or remote means is not to interfere with the
Oil pipes and other pipes, where passing through oil ability of the other means to close the valve.
tanks, are to be of wrought iron or steel, except that Materials readily rendered ineffective by heat are
other materials may be considered where it is not to be used within the space unless adequately
demonstrated that the material is suitable for the protected. If electric cables are utilized, they are to
intended service. All packing is to be of a be fire resistant meeting the requirements of IEC 331.
composition not affected by oil. Hydraulic systems are to be in accordance with 4/6.67
for both Class I and II piping systems. For a
4/6.51.3 Control Valves or Cocks pneumatic system, the air supply may be from a
Valves or cocks controlling the various suctions are source from within the space provided a separate
to be located close to the bulkhead where the suctions receiver complying with the following is located
enter the machinery spaces and wherever practicable outside the space:

PART 4 SECTION 6|21 Pumps and Piping Systems


a sufficient capacity to cycle all connected 4/6.59 Lubricating Oil Systems
loads
b fitted with low air pressure alarm 4/6.59.1 General
c air supply line is fitted with a non-return The lubricating systems are to be so arranged that
valve adjacent to the receiver. they will function satisfactorily under the conditions
specified in 4/1.21. The lubricating oil piping is to be
4/6.51.5 Remote Shutdown of Pumps entirely separated from other piping systems. In
Machinery driving fuel oil transfer pumps, oil fuel addition, the requirements of 4/6.49.1b, 4/6.49.2,
unit pumps and other similar fuel pumps are to be 4/6.49.3 and 4/6.51.4 are applicable.
fitted with remote shutdowns complying with 4/9.5.3.
4/6.59.2 Sight Flow Glasses
4/6.51.6 Oil Drain Tanks Sight flow glasses may be used in lubricating systems
Drain tanks, where fitted, for waste oil, fuel oil provided they are fire resistant.
overflows, drains, all oil drip pans, and fuel injection
piping, etc., are to have air and sounding pipes. Non- 4/6.59.3 Internal-Combustion Engines
return valves are to be fitted in drain lines entering For internal-combustion engines, see also 4/4.9.
the drain tanks except where backflow would not
present a hazard. Suitable means are to be provided 4/6.59.4 Reduction Gears
for pumping out these drain tanks. For reduction gears see also 4/4.9.13
Oil tanks not forming a part of the vessel's
structure, where permitted by 4/6.49.1a, are to have 4/6.59.5 Electrical Machinery
suitable drip pans with adequate means of drainage in For electrical machinery see also 4/5B2.3, 4/5B2.5
accordance with 4/6.7.13. and 4/5C2.13.

4/6.53 Fuel-Oil Service and Injection Systems 4/6.59.6 Hose Reels


Where hose reels are used for filling engine or
Fuel oil service and injection systems for internal-
reduction gear sumps with oil, a self-closing valve is
combustion engines are to be in accordance with
to be provided at the end of the filling hose to prevent
4/4.3, 4/4.5 and 4/4.7.
spillage. Suitable arrangements are to be provided to
properly drain and store the hose and reel when not in
4/6.55 Low-Flash Point Fuels
use. Hoses are to be approved for oil service and in
accordance with the requirements for burst pressure,
4/6.55.1 General
fire resistance, reinforcement, and end fittings in
Fuel oils with a flash point of 60C (140F) closed-cup
4/6.7.11
or below may be accepted for the following:
a ships classed for restrictive service within
4/6.59.7 Tank Location
areas having a climate ensuring that ambient
Lubricating oils are not to be carried forward of
temperatures of spaces where such fuel oil is
public spaces and crew accommodation.
stored will not rise within 10C (18F) below
its flash point, may use fuel oil with flash
4/6.61 Cooling Water System
point of 60C (140F) or below but not less
than 43C (110F). Cooling water systems for internal-combustion
b for emergency generators fuel oil with a engines are to comply with 4/4.11.
flash point of not less than 43C (110F) may
be used. See 4/5A3.5.2. 4/6.63 Exhaust Piping
c for gas turbines, subject to compliance with
the requirements in 4/3.9.4. 4/6.63.1 General
All engine exhaust systems are to be adequate to
4/6.55.2 Fuel Heating assure the correct functioning of the machinery and
For oil heating arrangements, see 4/6.49.3. that safe operation of the craft is not put at risk. The
exhaust pipes are to be water-jacketed or effectively
4/6.55.3 Fuel Oil Tank Vents insulated. Exhaust systems are to be so installed that
Vent pipes are to extend at least 2.4 m (8 ft.) above the vessel's structure cannot be damaged by heat from
the weather deck or other effective arrangements the systems. Exhaust pipes of several engines or gas
which have been approved are to be provided. Where turbines are not to be connected together but are to be
fuel oil with a flash point below 43C (109F) is run separately to the atmosphere unless arranged to
permitted in accordance with 4/6.55.1c, the vents are prevent the return of gases to an idle engine or
to terminate with approved flame arresters. turbine. Exhaust lines which are led overboard near

PART 4 SECTION 6|22 Pumps and Piping Systems


the waterline are to be protected against the 4/6.67.4 Pipe Fittings
possibility of the water finding its way inboard. Fittings and flanges are to meet the requirements of
Exhaust systems are to be so arranged as to minimize 4/6.17, 4/6.21, and 4/6.23, except as follows:
the intake of exhaust gases into manned spaces, air- a Split Flanges Split flanges are not to be used
conditioning systems, and engine intakes. Exhaust in steering gear systems nor in systems which are vital
systems are not to discharge into air-cushion intakes, to the propulsion or safety of the vessel. Split flanges
where provided. Also see 4/4.17 for internal- may be considered for use in other systems. Where
combustion engines and 4/3.13 for gas turbines. split flanges are permitted they are not to be used to
join sections of piping, but may be used for
4/6.63.2 Exhaust System Materials connections to machinery provided the materials and
Materials used in the exhaust system are to be construction are suitable for the system design
resistant to saltwater corrosion, galvanically pressure.
compatible to each other and resistant to exhaust b Straight-Thread "O"-Ring Connections
products. Plate flanges will be considered where the Straight-thread "O"-ring type connections may be
specified material is suitable for exhaust piping used for connections to equipment such as pumps,
pressures and temperatures. valves, cylinders, accumulators, gages, and hoses.
Such connections are not to be used for joining
4/6.65 Starting-Air Systems sections of pipe.
Starting-air systems for internal-combustion engines c Tapered Threaded Connections Tapered
are to comply with 4/4.15. threaded connections up to and including 89 mm
O.D. (3 in. NPS) may be used without limitation for
4/6.67 Hydraulic Systems connections to equipment such as pumps, valves,
cylinders, accumulators, gages, and hoses. Tapered
4/6.67.1 General threaded connections are not to be used in steering
The arrangements for Group I hydraulic piping gear systems, controllable pitch propeller systems,
systems are to be in accordance with the requirements and other systems associated with propulsion or
of this section, except that hydraulic systems which propulsion control, except where permitted by
form part of a unit which is independently 4/6.21.1. Such connections are not to be used for
manufactured and assembled and which does not joining sections of pipe except where permitted by
form part of the ship's piping system (such as a crane) 4/6.21.1.
are not covered by this section.
Plans showing clearly the arrangements and
4/6.67.7 Accumulators and Fluid Power Cylinders
details are to be submitted for review.
Accumulators are to meet the requirements of Section
Hydraulic pumps, actuators, motors and
accessories are to be suitable for the intended duty, 4/2 of the "Rules for Building and Classing Steel
compatible with the working fluid and are to be Vessels". Each accumulator which may be isolated is
designed to operate safely at full power conditions. to be protected by suitable relief valves. Where a gas
In general, the hydraulic fluid is to be non-flammable charging system is used, a relief valve is to be
or have a flash point above 157C (315F). provided on the gas side of the accumulator.
The requirements for fuel oil systems contained in Fluid Power Cylinders are to meet the
4/6.49.1b, 4/6.49.2 and 4/6.51.4 are applicable to requirements of 4/6.69.
tanks containing hydraulic fluid. See also 4/7.32 and
4/8.4. 4/6.67.8 Design Pressure
The pressure used for determining the strength and
4/6.67.2 Valves design of piping and components is not to be less than
a General In general, valves are to comply with the relief valve setting.
the requirements of 4/6.17 and 4/6.19.
b Relief Valves Relief valves are to be provided 4/6.67.9 Segregation of High Pressure Hydraulic
for the protection of the hydraulic system. Each relief Units
valve is to be capable of relieving not less than full Hydraulic units with working pressures above 15.5
pump flow with a maximum pressure rise of not more
bar (15.8 kgf/cm2, 225 psi) installed within a
than 10% of the relief valve setting.
machinery space are to be placed in separate room or
rooms or shielded as necessary to prevent any oil or
4/6.67.3 Piping
Piping is to meet the requirements of 4/6.4 and oil mist that may escape under pressure from coming
4/6.13, except that mill tests need not be witnessed by into contact with surfaces with temperatures in excess
the Surveyor. In such cases, mill certificates are to be of 220C (428F), electrical equipment or other sources
provided which verify the chemical and mechanical of ignition. For the purpose of this requirement, a
properties for the pipe. hydraulic unit includes the power pack and all
components of the hydraulic piping system.

PART 4 SECTION 6|23 Pumps and Piping Systems


4/6.69 Fluid Power Cylinders cylinders are to be in accordance with the applicable
requirements of Section 2/2 or other such appropriate
4/6.69.1 Application material specification as may be approved in
Hydraulic and pneumatic power cylinders are to be in connection with a particular design. Copies of
accordance with the requirements of this section. certified mill test reports are to be made available to
Hydraulic steering gear cylinders are to be in the Surveyor upon request. Ordinary cast iron or
accordance with the requirements of 4/8.3.6. similar materials (elongation less than 12% in 50 mm
Cylinders forming a part of an independently (2 in.) are not to be used for cylinders which may be
manufactured and assembled unit that do not form subjected to shock loading.
part of ship's piping system are not covered by this d Hydrostatic Tests
subsection. 1 General Cylinders are to be subjected
to a hydrostatic test. This test need not
4/6.69.2 Cylinders for Group I Piping Systems be witnessed by the Surveyor.
a Design The design of hydraulic and 2 Test Pressure The test pressure applied
pneumatic power cylinders is to meet the is to be not less than 1 ½ times the
requirements of 4/2.5.1 (for nodular cast iron, use y = maximum allowable working pressure
0.5), 4/2.9 and 4/2.11 of the "Rules for Building and for steel cylinders, and not less than
Classing Steel Vessels", as applicable, with S as twice the maximum allowable working
defined in this subparagraph. Welding is to be in pressure for cast iron and nodular iron
accordance with Section 2/3B. The maximum cylinders.
allowable stress S is not to exceed the following:
4/6.69.3 Cylinders for Group II Piping Systems
U Y Hydraulic and pneumatic power cylinders for use in
or
A B Group II piping systems may be accepted on the basis
of the manufacturer's data indicating pressure rating
where and suitability for the intended service.
U = minimum specified tensile strength of material
at room temperature 4/6.71 Fixed Oxygen--Acetylene Installations
Y = minimum specified yield point or yield
strength A & B are as follows: 4/6.71.1 Cylinder Storage
Rolled or Cast Nodular Where fixed installations consisting of two or more
Forged Steel Steel Cast Iron cylinders of each gas are located in enclosed spaces,
A 3.5 4 5 the cylinders are to be installed in dedicated storage
B 1.7 2 3 rooms, a separate room for each gas, on or above the
uppermost continuous deck. Storage rooms are to be
constructed of steel, ventilated and provided with
Alternatively, designs may be accepted on the basis
direct access from the open deck. Access doors are to
of certified burst test reports. Steel cylinders of other
open outwards, and bulkheads and decks forming
than cast construction are to be designed for a
boundaries between such rooms and other enclosed
bursting pressure not less than 4 times the maximum
spaces are to be gas tight. Ventilation arrangement
allowable working pressure. Cylinders of cast steel
for the storage rooms are to be independent of the
or ductile iron are to be designed for a bursting
ventilation systems of other spaces and are to be
pressure not less than 5 times the maximum allowable
capable of providing at least six air changes per hour
working pressure.
based on the gross volume of the space. The
b Plans and Data to be Submitted
Cylinder and head details termination of ventilation inlets and exhausts is to be
Cylinder rod and piston details at least 3 m (10 ft.) from any source of vapor ignition.
Thread standard and dimensions Where the cylinders are to be installed in open
Welding details and dimensions locations, they are to be effectively protected against
Lug attachments mechanical and heavy weather damage and excessive
Material specifications including minimum tensile, ambient temperatures. Suitable drainage of the
yield and elongation properties storage area is to be provided.
Design pressure and temperatures (minimum and Piping systems containing flammable or
maximum) combustible liquids are not to run through the storage
Test pressure rooms/area. Electrical arrangements within the
cylinder storage rooms or areas are to comply with
c Material The physical and chemical
4/5B7.
characteristics of materials entering into the
Cylinders are to be constructed to a recognized
construction of hydraulic and pneumatic power
standard acceptable to the Bureau.

PART 4 SECTION 6|24 Pumps and Piping Systems


4/6.71.2 Piping and Fittings pressure of the piping system to a location in the
The wall thickness of piping between cylinders and weather at least 3 m (10 ft.) from sources of vapor
pressure regulators is to be in accordance with ignition or openings to spaces or tanks. The pressure
4/6.13.6. Materials for piping on the high pressure relief devices may be either a relief valve or rupture
side of the regulators are to be steel for acetylene and disc.
steel or copper for oxygen. All piping is to be Outlet stations are to be provided with suitable
seamless. Copper or copper alloys containing more protective devices which will:
than 65% copper are not to be used in connection a Prevent back flow of gas into the supply
with acetylene. Where two or more cylinders are lines
connected to a manifold, the supply pipe between b Prevent the passage of flame into the supply
each cylinder and the manifold is to be fitted with a lines
non return valve. Shutoff valves are to be fitted at each outlet.
Piping and fittings on the low pressure side of the
regulators are to be in accordance with above 4/6.73 Liquefied Petroleum Gases
requirements except that seamless steel pipes of at
least standard wall thickness may be used. Except for 4/6.73.1 General
the cylinder manifolds, acetylene is not to be piped at Liquefied petroleum gas may be used for cooking and
a pressure in excess of 1.0 bar (1.0 kgf/cm2, 15 psi). heating on all craft except passenger vessels.
All piping on the low pressure side is to have all Liquefied petroleum gas systems are to be of the
joints welded. Branch lines are not to run through vapor withdrawal type only. Cylinders designed to
unventilated spaces or accommodation spaces. admit the liquid phase of the gas into any other part of
The system is to be tested in accordance with the system are prohibited. All component parts of the
4/6.9.7. system, except cylinders, appliances, and low
Note: Prior to installation of oxygen and acetylene pipe lines, pressure tubing, shall be designed to withstand a
all piping and fittings are to be thoroughly cleaned with pressure of 34 bar (35 kgf/cm2, 500 psi) without
a suitable solution, which will not react with oxygen, to rupture.
remove all grease, oil and dirt. Piping should be
thoroughly blown out after assembly to remove foreign
materials. For oxygen piping, oil-free air or oil-free 4/6.73.3 Storage Cylinders
nitrogen should be used. For acetylene, air or inert gas Cylinders for the storage of liquefied petroleum gases
may be used. are to be designed and constructed in accordance with
a recognized pressure vessel standard.
4/6.71.3 Pressure Relief and System Protective
Devices 4/6.73.5 Installation and Testing
Pressure relief devices are to be provided in the gas Where liquefied petroleum gases are used, the
piping if the maximum design pressure of the piping installation and testing is to comply with a recognized
system can be exceeded. These devices are to be set standard.
to discharge at not more than the maximum design

PART 4 SECTION 6|25 Pumps and Piping Systems


FIGURE 4/6.1 FIGURE 4/6.2
Fire Endurance Test
Burner Assembly Fire Endurance Test
Stand With Mounted Sample

TABLE 4/6.1
Allowable Stress Values S for Steel Piping N/mm2 (kgf/mm2, psi)
Service Temperature -- Degrees C (F)
Sec. 2/2 Par. & Grade -29C (-20F) to
Nominal Composition Tensile Strength 344C (650F) 372C (700F) 399C (750F) 427C (800F)
M = 0.8 M = 0.8 M = 0.8 M = 0.8
2/2.29.3-1 310 46.9 46.6
Elec. res. Carbon Steel (31.5, 45000) (4.78, 6800) (4.75, 6500)
2/2.29.3-2 330 70.3 68.3 62.8 53.1
Elec. res. Carbon Steel (33.7, 48000) (71.7, 10200) (6.96, 9900) (6.40, 9100) (5.41, 7700)
Seamless Carbon Steel 330 82.8 80.6 73.7 62.1
(33.7, 48000) (8.44, 12000) (8.22, 11700) (7.52, 10700) (6.33, 9000)
2/2.29.3-3 415 88.3 84.1 75.8 63.4
Elec. res. Carbon Steel (42, 60000) (9.0, 12800) (8.58, 12200) (7.73, 11000) (6.47, 9200)
Seamless Carbon Steel 415 103.5 99.2 89.6 74.4
(42, 60000) (0.55, 15000) (10.12, 14400) (9.14, 13000) (7.59, 10800)
2/2.29.3-4 330 82.8 80.7 73.7 62.1
Carbon Steel (33.7, 48000) (8.44, 12000) (8.23, 11700) (7.52, 10700) (6.33, 9000)
2/2.29.3-5 415 103.5 99.2 89.6 74.4
Carbon Steel (42, 60000) (10.55, 15000) (10.12, 14400) (9.14, 13000) (7.59, 10800)
Notes
1 Intermediate values of S may be determined by interpolation.
2 For grades of piping other than those given in Table 4/6.1, S values are not to exceed those permitted by ASME B31.1 Code for
Pressure Piping. See 4/6.13.7.
3 Consideration is to be given to the possibility of graphite formation in carbon steel at temperatures above 425C (800F)

PART 4 SECTION 6|26 Pumps and Piping Systems


TABLE 4/6.4
FIRE ENDURANCE REQUIREMENTS MATRIX

LOCATION
PIPING SYSTEMS A B C D E F G H I
FLAMMABLE LIQUIDS
1 Fuel oil flash point ≤ 60C (140F) X X X X 0 0 0 NA L1
2 Fuel oil flash point > 60C (140F) X X X X 0 0 0 L1 L1
3 Lubricating oil X X X X NA NA 0 L1 L1
4 Hydraulic oil X X X X 0 0 0 L1 L1
SEA WATER (See Note 1)
5 Bilge main and branches L14 L14 X X 0 0 0 NA L1
6 Fire main and water spray L1 L1 X NA NA 0 0 X L1
7 Foam system L1 L1 NA NA NA NA 0 L1 L1
8 Sprinkler system L1 L1 X NA NA 0 0 L3 L3
9 Ballast L3 L3 L3 X 0 0 0 L2 L2
10 Cooling water, essential services L3 L3 NA NA NA 0 0 NA L2
11 Non-essential systems 0 0 0 0 0 0 0 0 0
FRESH WATER
12 Cooling water, essential services L3 L3 NA NA 0 0 0 L3 L3
13 Condensate return L3 L3 0 0 NA NA 0 0 0
14 Non-essential systems 0 0 0 0 0 0 0 0 0
SANITARY/DRAINS/SCUPPERS
15 Deck drains (internal) L12 L12 L12 0 0 0 0 0 0
16 Sanitary drains (internal) 0 0 0 0 0 0 0 0 0
17 Scuppers and discharges (overboard) 01,5 01,5 01,5 01,5 0 0 0 01,5 0
VENTS/SOUNDING
18 Water tanks/dry spaces 0 0 0 0 0 0 0 0 0
19 Oil tanks (flashpoint > 60C (140F)) NA NA NA NA NA 0 0 NA X
20 Oil tanks (flashpoint > 60C (140F)) X X X X 0 0 0 X X
MISCELLANEOUS
21 Control air L13 L13 L13 L13 0 0 0 L13 L13
22 Service air (non-essential) 0 0 0 0 0 0 0 0 0
23 Brine 0 0 0 0 NA NA 0 0 0
24 Auxiliary low pressure steam (Pressure L2 L2 06 06 0 0 0 06 06
≤ 7 bar (7 kgf/cm2, 100 psi))

Locations Abbreviations
A Category A machinery spaces L1 Fire endurance test in dry conditions, 60 minutes, in
B Other machinery spaces accordance with 4/6.15.7
C Ro/Ro Spaces L2 Fire endurance test in dry conditions, 30 minutes, in
D Other dry cargo holds accordance with 4/6.15.7
E Fuel oil tanks L3 Fire endurance test in wet conditions, 30 minutes, in
F Ballast water tanks accordance with 4/6.15.8
G Cofferdams, void spaces, pipe tunnels and ducts 0 No fire endurance test required
H Accommodation, service and control spaces NA Not applicable
I Open decks X Metallic materials having a melting point greater than
925C (1700F).
Notes
1 Where non-metallic piping is used, remotely controlled valves are to be provided at the ship’s side. These valves are to be
controlled from outside the space.
2 For drains serving only the space concerned, “0” may replace “L1”.
3 When controlling functions are not required by statutory requirements, “0” may replace “L1”.
4 For passenger craft, “X” is to replace “L1”.
5 Scuppers serving open decks in positions 1 and 2, as defined in Regulation 13 of the International Convention on Load
Lines, 1966, are to be “X” throughout unless fitted at the upper end with the means of closing capable of being operated
from a position above the freeboard deck in order to prevent downflooding.
6 For essential services, such as fuel oil tank heating and ship’s whistle, “X” is to replace “0”.

PART 4 SECTION 6|27 Pumps and Piping Systems


PART 4 SECTION 7

Propulsion Shafting, Propellers, Waterjets


and Lift Devices

4/7.1 Propulsion Shafting and Propellers calculations are to be included for the internal
mechanism, see 4/7.30.
4/7.1.1 General
The construction of the propellers and propulsion Shafting
shafting is to be carried out in accordance with the
following requirements and to the satisfaction of the 4/7.2 Materials and Testing
Surveyor. Upon satisfactory compliance with the
requirements, a notation will be made in the Record 4/7.2.1 Material
indicating the type of propeller and the material of The material for shafting, couplings and coupling
which it is made. bolts is to be tested in the presence of the Surveyor, in
accordance with Section 2/2 or to other specifications
4/7.1.2 Small Conventional Propellers approved in association with the specific design. In
For planing and semi-planing craft, the propellers general, material with elongation of less than 16% in
need not to be designed and constructed in 50 mm (2 in.) is not to be used for shafting,
accordance with these requirements provided they do couplings, or coupling bolts, without specific
not exceed 1.5m (60 in.) in diameter and are part of a approval.
manufacturer’s standard product line. In such
instances, neither the Surveyor’s attendance for the 4/7.2.2 Alternative Test Requirements
material testing and inspection nor the design review Materials for shafting, couplings, and coupling bolts,
will be required. transmitting 373 kW (500 HP) or less, will be
accepted based on the manufacturer's certified mill
4/7.1.3 Plans and Data to be Submitted tests and hardness check witnessed by the Surveyor.
Plans and specifications are to be submitted in Bolts manufactured to a recognized standard and used
accordance with 1/1.9 as indicated in the following: as coupling bolts will not require material testing.
a Propulsion Shafting Detailed plans together
with material specifications of the propulsion 4/7.2.3 Inspection
shafting, couplings, coupling bolts, propulsion Shafting and couplings are to be surface examined at
shafting arrangement, tailshaft bearings and the manufacturer. Tailshafts in the finished machine
lubrication system, if oil-lubricated, are to be condition are to be subjected to a nondestructive
submitted. Calculations are to be included for examination such as magnetic particle, dye penetrant
flexible couplings and demountable couplings, see or other nondestructive methods and are to be free of
4/4.19 and 4/7.10.7. See also 4/7.16. linear discontinuities greater than 3.2 mm (1/8 in.)
b Fixed-Pitch Propellers Where the propeller except that in the following locations the shafts are to
blades are of conventional design, a propeller plan, be free of all linear discontinuities:
giving the design data and characteristics of the a Tapered Tailshafts The forward one-third
material, as required by 4/7.23.1, is to be submitted. length of the taper, including the forward end of any
For skewed propellers or propeller blades of unusual keyway and an equal length of the parallel part of the
design, a detailed stress analysis is also to be shaft immediately forward of the taper.
submitted as required by 4/7.23.2 or 4/7.25.2 For b Flanged Tailshafts The flange fillet area.
keyless propellers see 4/7.13. For air propellers
associated with air cushion vehicles, see 4/7.38.3. 4/7.2.4 Weldability
c Controllable-Pitch Propellers In addition to Steel used for tailshafts is to contain 0.35% or less
the plan and data required in 4/7.1.3b for the carbon content, unless specially approved. See
propeller blade; plans of the propeller hub, propeller 2/2.19.1b.
blade flange and bolts, internal mechanisms,
hydraulic piping control systems, and instrumentation
and alarm system are to be submitted. Strength

PART 4 SECTION 7|1 Propulsion Shafting, Propellers, Waterjets and Lift Devices
4/7.3 Shaft Diameters 4/7.5 Tailshaft Liners
The least diameter of propulsion shafting is to be
determined by the following equation: 4/7.5.1 Thickness at Bearings
D = 100 K ( (H
3 R )[c1 U + c2 ] ) a Bronze The thickness of bronze liners to be
shrink fitted to tailshafts or tube shafts of craft is not
C1 = 560 (41.95, 3.695) for single screw craft to be less in way of bearings than that given by the
45.7 m (150 ft) in length and over and following equation.
multiple screw craft 61m (200 ft) in length t = T/25 + 5.1 mm t = T/25 + 0.2 in.
and over
= 416.4 (31.22, 2.75) for single screw craft t = thickness of liner in mm or in.
below 45.7 m (150 ft) and multiple screw T = required diameter of tailshaft in mm or in.
craft below 61m (200 ft) b Stainless Steel Clad The post machining
C2 = 160 (16.3, 23180) thickness of stainless steel clad liners to be fitted to
D = required shaft diameter in mm or in. for all tailshafts or tube shafts for craft in saltwater service is
shafts except those covered in 4/7.4. not to be less than one-half that required for bronze
K = shaft design factor (see Table 4/7.1 and liners or 6.5 mm (0.25 inches) whichever is greater.
4/7.2) See 4/7.5.13.
H = power at rated speed, kW (PS, HP), [(MKS c The thickness of shrink-fitted liners other than
units: 1 PS = 0.735 kW), (US units: 1 HP = bronze will be subject to special consideration.
0.746 kW)]
R = rpm at rated speed 4/7.5.3 Thickness Between Bearings
U = minimum specified ultimate tensile strength The thickness of a continuous bronze liner between
of the material in N/mm2 (kgf/mm2, psi). bearings is to be not less than three-fourths of the
For calculation purposes, U is not to be thickness t determined by the foregoing equation.
taken as more than the following:
= 415 N/mm2 (42.2 kgf/mm2, 60,000 psi) for 4/7.5.5 Continuous Fitted Liners
carbon, and alloy steel tailshafts fitted with Continuous fitted liners are to be in one piece or, if
salt-water lubricated bearings and non- made of two or more lengths, the joining of the
continuous shaft liners. separate pieces is to be done by an approved method
= 600 N/mm2 (61.2 kgf/mm2, 87,000 psi) for of fusion through not less than two-thirds the
carbon, alloy and austenitic stainless steel thickness of the liner or by an approved rubber seal.
tailshafts fitted with oil lubricated bearings
or with continuous shaft liners or equivalent. 4/7.5.7 Fit between Bearings
= 930 N/mm2 (95.0 kgf/mm2, 135,000 psi) for If the liner does not fit the shaft tightly between the
other shaft sections and for tailshafts bearing portions, the space between the shaft and
manufactured of age-hardened martensitic liner is to be filled by pressure with an insoluble non-
stainless steels or other high strength alloy corrosive compound.
materials.
Note In general, the minimum specified ultimate tensile strength
4/7.5.9 Material and Fit
of steel used for propulsion shafting is to be between 400 Fitted liners are to be of a high-grade composition,
N/mm2 (40.7 kgf/mm2, 58,000 psi) and 930 N/mm2 (95.0 bronze or other approved alloy, free from porosity
kgf/mm2, 135,000 psi). See also 4/7.2.1. and other defects, and are to prove tight under
hydrostatic test of 1.0 bar (1 kgf/cm2, 15 psi). All
4/7.4 Hollow Shafts liners are to be carefully shrunk or forced upon the
For hollow shafts where the bore exceeds 40% of the shaft by pressure and they are not to be secured by
outside diameter, the minimum shaft diameter is not pins.
to be less than that given by the following equation.

Do = D 3 1 [1 − ( D i Do )4 ]
4/7.5.11 Glass Reinforced Plastic Coating
Glass reinforced plastic coatings may be fitted on
propulsion shafting when applied by an approved
Do = required outside diameter in mm or in.
procedure to the satisfaction of the Surveyor. Such
D = solid shaft diameter required by 4/7.3, as
coatings are to consist of at least four plies of cross-
applicable, in mm or in.
woven glass tape impregnated with resin, or an
Di = actual shaft bore in mm or in.
equivalent process. Prior to coating, the shaft is to be
cleaned with a suitable solvent and grit blasted. The
shaft is to be examined prior to coating and the first
layer is to be applied in the presence of the Surveyor.
Subsequent to coating, the finished shaft is to be

PART 4 SECTION 7|2 Propulsion Shafting, Propellers, Waterjets and Lift Devices
subjected to a spark test or equivalent to verify however, is not to be less than 1.5 times the actual
freedom from porosity to the satisfaction of the diameter. Where the material has demonstrated
Surveyor. In all cases where reinforced plastic satisfactory testing and operating experience,
coatings are employed, effective means are to be consideration may be given to increased bearing
provided to prevent water having access to the shaft. pressure.
Provisions are to be made for over-lapping and
adequately bonding the coating to fitted or clad liners. 4/7.8 Tailshaft Propeller-end Design
The end of the liner is to be stepped and tapered as Tailshafts are to be provided with an accurate taper fit
required to protect the end of the wrapping. in the propeller hub, particular attention being given
to the fit at the large end of the taper.
4/7.5.13 Stainless Steel Cladding a Keyed The key is to fit tightly in the keyway
Stainless steel cladding of shafts is to be carried out and be of sufficient size to transmit the full torque of
in accordance with an approved procedure. See latest the shaft, but it is not to extend into the liner
edition of the ABS Guide for Repair and Cladding of counterbore on the forward side of the propeller hub.
Shafts. The forward end of the keyway is to be so cut in the
shaft as to give a gradual rise from the bottom of the
4/7.7 Tailshaft Bearings keyway to the surface of the shaft. Ample fillets are
to be provided in the corners of the keyway and, in
4/7.7.1 Water Lubricated Bearings general, stress concentrations are to be reduced as far
a Wood Bearings (resinous, dense hardwoods) as practicable.
The length of the bearing, next to and supporting the b Keyless Where propellers are fitted without
propeller, is to be not less than four times the required keys, detailed stress calculations and fitting
tailshaft diameter. instructions are to be submitted for review. The
b Synthetic Bearings (rubber, reinforced resins, factor of safety against slip at 35C (95F) is to be at
plastic materials) The length of the bearing, next to least 2.8 under the action of maximum continuous
and supporting the propeller, is to be not less than ahead rating plus torque due to torsional vibrations.
four times the required tailshaft diameter. The astern operation is to be considered if the astern
For a bearing design substantiated by torque exceeds the ahead torque. For oil injection
experimental tests to the satisfaction of the Bureau, method of fit the coefficient of friction is to be taken
consideration may be given to a bearing length of less no greater than 0.13 for bronze/steel propeller bosses
than four times but not less than two times the on steel shafts. For dry method of fit using cast iron
required tailshaft diameter. on steel shafts the coefficient of friction is to be taken
no greater than 0.18. The maximum equivalent
4/7.7.3 Oil Lubricated Bearings uniaxial stress in the boss at 0C (32F) is not to exceed
a White Metal Lined The length of white-metal 70% of the minimum specified yield strength of the
lined, oil lubricated propeller-end bearings fitted with material at 0.2% offset (ASTM-E8). For cast iron,
an approved oil-seal gland is to be on the order of two this stress is not to exceed 30% of the minimum
times the required tailshaft diameter. The length of specified tensile strength.
the bearing may be less provided the nominal bearing
pressure is not more than 0.80 N/mm2 (0.0815 4/7.9 Flexible Couplings
kgf/mm2, 116 psi) as determined by static bearing See 4/4.19.1.
reaction calculation taking into account shaft and
propeller weight which is deemed to be exerted solely 4/7.10 Solid Couplings
on the aft bearing, divided by the projected area of
the shaft. The minimum length, however, is not to be 4/7.10.1 Fitted Bolts
less than 1.5 times the actual diameter. The minimum diameter of fitted shaft coupling bolts
b Synthetic Bearings (rubber, reinforced resins, is to be determined by the following equation:
plastic etc.) The length of synthetic rubber,
reinforced resin or plastic oil lubricated propeller end db = 0.65 D3 (U + c) NBU b mm (in.)
bearings fitted with an approved oil-seal gland is to
be on order of two time the required tailshaft c = 160 (16.3, 23180)
diameter. The length of bearing may be less provided db = diameter of bolts at joints in mm or in.
the nominal bearing pressure is not more than 0.60 D = required diameter of shaft as per 4/7.3.1 in
N/mm2 (0.0611 kgf/mm2, 87 psi) as determined by mm or in.
static bearing reaction calculation taking into account N = number of bolts fitted in one coupling
shaft and propeller weight which is deemed to be B = bolt circle diameter in mm or in.
exerted solely on the aft bearing, divided by the U = minimum specific tensile strength of shaft
projected area of the shaft. The minimum length, material in N/mm2, kgf/mm2 or psi

PART 4 SECTION 7|3 Propulsion Shafting, Propellers, Waterjets and Lift Devices
Ub = minimum specific tensile strength of bolt accurately fitted and effectively secured against axial
material in N/mm2, kgf/mm2 or psi. To be movement. The coupling is to be satisfactory for
not less than U. Ub is to be taken not more astern condition.
than 1.7 U or 1000 N/mm2 (102 kgf/mm2,
145,000 psi), whichever is less, for 4/7.10.5 Flanges
calculation purposes. The thickness of coupling flanges is not to be less
Notes:
than the minimum required diameter of the coupling
1 Coupling bolts are to be accurately fitted. bolts or 0.2 times D (as defined in 4/7.3), whichever
2 The material for coupling bolt is to be steel with an is greater. The fillet radius at the base of an integral
elongation of not less than 16% in 50 mm (2 in.). flange is not to be less than 0.08 times the actual shaft
3 The use of other materials will be subject to special
consideration based on submitted engineering analyses.
diameter. Consideration of a recognized shaft
coupling standard will be given to fillets of multiple
4/7.10.3 Non-fitted Bolts radii design. In general, the surface finish for fillet
The diameter of pre-stressed non-fitted coupling bolts radii is not to be rougher than 1.6 µ meters (63 µ in.)
will be considered upon the submittal of detailed RMS. For the fillet radius for tailshaft to propeller
preloading and stress calculations and fitting coupling flange, see Note 4 in Table 4/7.2.
instructions. The tensile stress on the bolt due to
prestressing and astern pull is not to exceed 90% of 4/7.10.7 Demountable Couplings
the minimum specified yield strength of the bolt Couplings are to be made of steel or other approved
material. In addition, the bearing stress on any ductile material. The strength of demountable
member such as the shaft, bolt, threads or nut is not to couplings and keys is to be equivalent to that of the
exceed 90% of the minimum specified yield strength shaft. Couplings are to be accurately fitted to the
of the material for that member. shaft. Where necessary, provisions for resisting
a Power Transmitted by Prestress Only Where thrust loading are to be provided.
bolts are under pure tension, the factor of safety Hydraulic and other shrink fit couplings will be
against slip under the worst of the operating specially considered upon submittal of detailed
conditions, including mean transmitted torque plus preloading and stress calculations and fitting
vibratory torque due to torsional loads, is to be at instructions. In general, the torsional holding
least as follows: capacity is to be at least 2.8 times the transmitted
1 Inaccessible couplings (external to the mean torque plus vibratory torque due to torsionals
hull or not readily accessible)--2.8 for inaccessible couplings (external to the hull or not
2 Accessible couplings (internal to the readily accessible) and at least 2.0 times for
hull)--2.0 accessible couplings (internal to the hull). The
b Power Transmitted by Combination Prestress preload stress is not to exceed 70% of the minimum
and Shear Where the power is transmitted by a specified yield strength.
combination of fitted bolts and prestressed non-fitted
bolts, the components are to meet the following 4/7.16 Propulsion Shaft Alignment and
criteria: Vibrations
1 Fitted Bolts: The shear stress under the
maximum torque corresponding to the 4/7.16.1 General
worst loaded condition, is to be not Propulsion shafting is to be aligned with the location
more than 50% of the minimum and spacing of the shaft bearings being such as to
specified tensile yield strength of the give acceptable bearing reactions and shaft bending
bolt material. moments and also acceptable amplitudes of vibration
2 Non-Fitted Bolts: The factor of safety for all conditions of ship loading and operation.
against slip, under the maximum torque The desiger or the builder is to evaluate the
corresponding to the worst loaded propulsion shafting system taking into consideration
condition and the specified bolt tension, any forces or factors which may affect the reliability
is to be at least 1.6 for inaccessible of the propulsion shafting system including weight of
couplings and 1.1 for accessible the propeller and shafts, hydrodynamic forces acting
couplings. on the propeller, number of propeller blades in
c Dowels Used for Transmitting Power Dowels relation to diesel engine cylinders, misalignment
connecting the tail shaft flange to the controllable forces, thermal expansion, flexibility of engine and
pitch propeller hub, utilized with non-fitted bolts to thrust bearing foundations, engine induced vibrations,
transmit power, are considered equivalent to fitted gear tooth loadings, flexible couplings, effect of
coupling bolts and are to comply with 4/7.10.1 and, if power take-off arrangements from the propulsion
applicable, 4/7.10.3b1. The dowels are to be shafting system driving auxiliaries, etc., as applicable,

PART 4 SECTION 7|4 Propulsion Shafting, Propellers, Waterjets and Lift Devices
as well as any limits for vibrations and loadings a Fixed-Pitch Propellers
specified by the equipment manufacturers.
 AH  C   BK  
t0.25 = S  K ±  s    mm (in.)
4/7.16.2 Craft 61 m (200 ft) in Length and Over  1 Cn CRN  Cn   4 C  
a Shaft Alignment Calculations The
requirements in 4/7.33.2 of the Rules for Building A = 1.0 + (6.0/P0.70) + 4.3P0.25
and Classing Steel Vessels are to be complied with. B = (4300wa/N) (R/100)2 (D/20)3
b Torsional Vibrations The requirements in C = (1 + 1.5P0.25) (Wf -B)
4/7.33.3 of the Rules for Building and Classing Steel
b Controllable-Pitch Propellers
Vessels are to be complied with.
c Axial Vibrations The requirements in 4/7.33.4 AH  C   BK 
of the Rules for Building and Classing Steel Vessels t0.35 = K2 ±  s   mm (in.)
Cn CRN  Cn   6.3C 
are to be complied with.
d Lateral (Whirling) Vibrations The A = 1.0 + (6.0/P0.7) + 3P0.35
requirements in 4/7.33.5 of the Rules for Building B = (4900wa/N) (R/100)2 (D/20)3
and Classing Steel Vessels are to be complied with. C = (1+0.6P0.35) (Wf - B)
4/7.16.3 Craft Below 61 m (200 ft) in Length c Nozzle Propellers (Wide Tip Blades)
a Torsional Vibration For craft fitted with
unusual propulsion arrangement or without vibration  AH   C s   BK 
t 0.35 = K 3   ±    mm (in.)
dampers, a torsional vibration analysis of the  C n CRN   Cn   5.6C 
propulsion system showing compliance with 4/7.33.3
of the Rules for Building and Classing Steel Vessels A = 1.0 + (6.0/P0.7) + 2.8P0.35
is to be submitted. This is not required for craft B = (4625wa/N) (R/100)2 (D/20)3
under 20 m (65 ft.) in length or where the installation C = (1+0.6P0.35) (Wf - B)
is essentially the same as previous designs which have S = 1.0. for all propellers with D ≤ 6.1 m (20 ft)
been proven satisfactory. = ( D + 24.0 30.1) SI, MKS units or
Propellers = ( D + 79 99) US units for solid propellers
with D > 6.1 m (20 ft) and weighing in
4/7.22 Materials and Testing excess of 20 tons. S is not to exceed 1.025.
t0.25 = required thickness at the one-quarter radius
4/7.22.1 Propeller Material in mm or in.
For propellers required to be of an approved design, t0.35 = required thickness at the 0.35 radius in mm
the material of the propeller is to be tested in the or in.
presence of and inspected by a Surveyor in K1 = 337 (289, 13)
accordance with the requirements of Section 2/2 or to K2 = 271 (232, 10.4)
other requirements which have been approved by the K3 = 288 (247, 11.1)
Committee. The finished and assembled propeller is H = power at rated speed, kW (hp, HP)
to be inspected by the Surveyor. hp = metric horsepower
HP = US horsepower
4/7.22.3 Stud Material R = rpm at rated speed
The material of the studs securing detachable blades N = number of blades
to the hub is to be of Grade 2 steel or equally P0.25 = pitch at one-quarter radius divided by
satisfactory material and is to be tested in the propeller diameter
presence of and inspected by the Surveyor in P0.35 = pitch at 0.35 radius divided by propeller
accordance with the requirements of 2/2.19.4. diameter, corresponding to the design ahead
conditions
4/7.23 Blade Design P0.7 = pitch at seven-tenths radius divided by
propeller diameter, corresponding to the
4/7.23.1 Blade Thickness design ahead conditions
Where the propeller blades are of conventional W = expanded width of a cylindrical section at
design, the thickness of the blades is not to be less the 0.25 or 0.35 radius in mm or in.
than determined by the following equations: a = expanded blade area divided by the disc area
D = propeller diameter, in m or ft

PART 4 SECTION 7|5 Propulsion Shafting, Propellers, Waterjets and Lift Devices
K = rake of propeller blade in mm/m or in./ft clearance of the spigot in its counterbore or the edge
multiplied by D/2 (with forward rake, use of the flange in the recess is to be kept to a minimum.
minus sign in equation; with aft rake, use
plus sign) 4/7.25 Skewed Propeller
Cs = as/WT (section area coefficient at the 0.25
or 0.35 radius). Also see below. 4/7.25.1 Definitions
Cn = Io/UfWT2 (section modulus coefficient at the a Maximum Skew Angle Maximum skew angle
o.25 or 0.35 radius). Also see below. (θ) is measured from ray A passing through the tip of
Io = moment of inertia of the expanded blade to ray B tangent to the mid-chord line of the
cylindrical section at 0.25 or 0.35 radius projected blade outline. See Figure 4/7.1a.
about a straight line through the center of b Rake Angle Rake angle (φ) for the purpose of
gravity parallel to the pitch line or to the this subsection is the angle measured from the plane
nose-tail line in mm4 or in.4 perpendicular to shaft centerline to the tangent to
as = area of expanded cylindrical section at the generating line at 0.6 radius. See Figure 4/7.1b.
0.25 or 0.35 radius, in mm2 or in.2
Uf = maximum normal distance from the moment 4/7.25.2 Application
of inertia axis to points on the face boundary a θ ≤ 25° The requirements in 4/7.23.1 are
(tension side) of the section, in mm or in. applicable where the maximum skew angle is 25
T = maximum thickness at the 0.25 or 0.35 degrees or less.
radius in mm or in. from propeller drawing b 25° < θ ≤ 50° The requirements in 4/7.25.3
The values of Cs and Cn computed as stipulated above may be used for fixed pitch propellers of ABS Type 4
are to be indicated on the propeller drawing. If the Cn material having skew angle over 25 degrees but not
value exceeds 0.10, the required thickness is to be exceeding 50 degrees. For other material/type
computed with Cn = 0.10. propellers, calculations as required in 4/7.25.2c are to
For craft below 61m (200 ft) in length, the be submitted.
required thickness may be computed with the c θ > 50° Propellers with the maximum skew
assumed values of Cn = 0.10 and Cs = 0.69. angle exceeding 50 degrees will be subject to special
f, w = material constants from the following table consideration upon submittal of detailed stress
calculations.
Representative SI and US Customary
Propeller Materials MKS Units Units
The maximum stress occurring during steady or
Type (See Section 2/2) f w f w transient astern operations is not to exceed seventy
2
Manganese bronze 2.10 8.3 68 0.30 per cent of the minimum specified yield strength of
3
Nickel-manganese 2.13 8.0 69 0.29 the propeller material.
bronze
4 Nickel-aluminum 2.62 7.5 85 0.27
4/7.25.3 Propellers Over 25 up to 50° Skew Angle
bronze
5 Mn-Ni-Al bronze 2.37 7.5 77 0.27 This paragraph applies to fixed pitch propellers of
Cast steel 2.10 8.30 68 0.30 ABS Type 4 material having a maximum skew angle
CF-3 Austenitic stainless 2.10 7.75 68 0.28 over 25 degrees but not exceeding 50 degrees.
steel a Blade Thickness at 0.25 Radius The
Note The f values of materials not covered will be specially maximum thickness at 0.25 radius is not to be less
considered upon submittal of complete material than the thickness required in 4/7.23.1a multiplied by
specifications including corrosion fatigue data to 108
the factor m as given below:
cycles.

m = 1 + 0.0065( θ − 25)
4/7.23.2 Blades of Unusual Design
Propellers of unusual design or application will be b Blade Thickness at 0.6 Radius The maximum
subject to special consideration upon submittal of thickness at 0.6 radius is to be not less than that
detailed stress calculations. obtained from the following equation:
4/7.23.3 Blade-root Fillets
(1 + C0.9 )(1 + 2 C0.9 [
C 0.6 ) ( HDΓ ) ( RP0.6 Y ) ]
0.5
t 0.6 = K
Fillets at the root of the blades are not to be
considered in the determination of blade thickness.
t0.6 = required thickness at the 0.6 radius in mm
4/7.23.4 Built-up Blades
(in.)
The required blade section is not to be reduced in
K3 = 12.6 (6.58, 1.19)
order to provide clearance for nuts. The face of the
C0.9 = expanding chord length at the 0.9 radius
flange is to bear on that of the hub in all cases, but the
divided by propeller diameter

PART 4 SECTION 7|6 Propulsion Shafting, Propellers, Waterjets and Lift Devices
C0.6 = expanded chord length at the 0.6 radius r = radius of pitch circle of the studs in mm or
divided by propeller diameter in.
H, D, R = as defined in 4/7.23.1
W, f and t are defined under 4/7.23.1.
Γ = [1+(θ - 25)/ θ][φ2 + 0.16φθP0.9 + 100]
θ = skew angle in degrees (see 4/7.25.1a and
4/7.28.3 Fit of Studs and Nuts
Figure 4/7.1a.) Studs are to be fitted tightly into the hub and provided
φ = rake angle in degrees (see 4/7.25.1b and with effective means for locking. The nuts are also to
Figure 4/7.1b), positive for rake aft have a tight-fitting thread and be secured by stop
P0.6 = pitch at the 0.6 radius divided by propeller screws or other effective locking devices.
diameter
P0.9 = pitch at the 0.9 radius divided by propeller 4/7.30 Blade Flange and Mechanisms
diameter
Y = minimum specified yield strength of ABS The strength of the propeller blade flange and internal
Type 4 propeller material in N/mm2 (kgf/m2, mechanisms of controllable-pitch propellers subjected
psi) to the forces from propulsion torque is to be at least
1.5 times that of the blade at design pitch conditions.
c Blade Thickness Between 0.6 and 0.9 Radius
1 Maximum Thickness The maximum 4/7.32 Controllable Pitch Propeller System
thickness between 0.6 and 0.9 radius is
not to be less than that obtained from 4/7.32.1 Piping Arrangement
the following equation. a General At least two hydraulic power pump
units are to be provided. Piping for the hydraulic
t x = 3.3D + 2.5(1 − x )( t 0.6 − 3.3D) mm system is to be arranged so that transfer between
pump units can be readily effected. The arrangement
t x = 0.04 D + 2.5(1 − x )( t 0.6 − 0.04 D) in. of piping is to be such that a single failure in one part
of the piping or pump unit will not impair the
tx = required maximum blade thickness at radius
integrity of the remaining parts of the system. For
x
multiple screw craft with controllable pitch propeller
t0.6 = blade thickness at 0.6 radius as required by
systems that are completely independent of each other
4/7.25.3b
such that a failure in one system will not affect the
x = ratio of the radius under consideration to
other systems, the above single failure criteria need
D/2, 0.6 < x ≤ 0.9
not be applied provided the ability to control and
propel the craft with the remaining propeller(s) can be
2 Trailing Edge Thickness at 0.9 Radius demonstrated to the satisfaction of the Surveyor.
The edge thickness measured at 5% of Where necessary, arrangements for bleeding air from
chord length from the trailing edge is to the hydraulic system are to be provided.
be not less than 30% of the maximum b Piping Piping is to meet the requirements of
blade thickness required by 1 above at 4/6.67.
that radius.
c Testing After installation in the craft, the
complete piping system is to be subjected to
4/7.28 Studs hydrostatic test equal to 1.5 times the design pressure,
including a check of the relief valve operation. These
4/7.28.1 Stud Area tests are to be performed in the presence of the
The sectional area of the studs at the bottom of the Surveyor.
thread is to be determined by the following equation:
s = 0.056kWt2f / rn mm2 4/7.32.3 Control of Pitch
Independent manual control of pitch is to be provided
s = 0.0018kWt2f / rn in.2 at or near the oil distribution box. For craft fitted
with shipboard automatic and remote control systems,
k = C/(U+C1) material correction factor refer to Section 4/11.
C = 621 (63.3, 90,000)
C1 = 207 (21.1, 30,000) 4/7.32.5 Instrumentation and Alarms
U = ultimate tensile strength of the stud material The following instruments and alarms are to be
kg/mm2 (psi) provided.
s = area of one stud at bottom of thread in mm2 a Pitch Indicators Each station capable of
or in2. controlling the propeller pitch is to be fitted with a
n = number of studs on driving side of blade pitch indicator. In addition, a pitch indicator is to be

PART 4 SECTION 7|7 Propulsion Shafting, Propellers, Waterjets and Lift Devices
fitted on the navigation bridge for craft 500 gross tons Waterjets
and above.
b Low Oil Pressure Visual and audible alarms 4/7.36 Waterjets
are to be provided in the engine room control station
to indicate low hydraulic oil pressure. 4/7.36.1 General
c High Oil Pressure Visual and audible alarms Full details are to be submitted for the force
are to be provided in the engine room control station transmitting parts of waterjet units including material
to indicate high hydraulic oil pressure. The alarm is specifications. For craft over 24 m (79 ft.) the units
to be set below relief valve pressure. are to be manufactured under Surveys. Mill
d High Temperature Visual and audible alarms certificates are to be provided for the components of
are to be provided in the engine room control station the steering section. The material tests for the
to indicate high hydraulic oil temperature. impellers shafts and couplings are to be witnessed by
the Surveyor. Hydraulic cylinders are to be
4/7.32.7 Electrical Components manufactured and inspected in accordance with the
Electrical components are to meet the applicable requirements of 4/6.69. The use of galvanically
requirements of Section 4/5. dissimilar metallic materials is to be considered in the
waterjet design.
4/7.34 Protection Against Corrosion
4/7.36.3 Design
4/7.34.1 Propeller Aft End Design basis stress calculations for the impellers,
The exposed steel of the shaft is to be protected from shafting, steering mechanism, and reversing
the action of the water by filling all spaces between mechanism are to be submitted to substantiate the
cap, hub and shaft with a suitable material. The suitability and strength of the components for the
propeller is to be fitted with a fairwater cap, acorn intended service. For the purpose of design review
nut, or other suitable after end sealing arrangements the stress calculations are to be cover the "worst case"
which prevents sea water from having contact with condition for each component. The factor of safety
the shaft taper area. See Figure 4/7.1 for typical for the above components is not to be less than 2.0
sealing arrangement. when determined by the following equation:
1 S S
4/7.34.3 Propeller Forward End = s+ a
The propeller assembly is to be sealed at the forward FS U E
end with a well-fitted soft-rubber packing ring. When nor less than 4.0 when determined by the following
the rubber ring is fitted in an external gland, the hub equation:
counterbore is to be filled with suitable material, and
clearances between shaft liner and hub counterbore U
FS =
are to be kept to a minimum. When the rubber ring is Ss
fitted internally, ample clearance is to be provided
between liner and hub and the ring is to be FS = factor of safety
sufficiently oversize to squeeze into the clearance Ss = steady stress of low cycle alternating stress
space when the propeller is driven up on the shaft; Sa = alternating stress
and, where necessary, a filler piece is to be fitted in U = ultimate tensile strength of material
the propeller hub keyway to provide a flat unbroken E = corrected fatigue strength of material (based
seating for the ring. on 108 cycles)
The recess formed at the small end of the taper by
the overhanging propeller hub is to be packed with a 4/7.36.5 Housings
rust preventive compound before the propeller nut is Calculations or test results to substantiate the
put on. suitability and strength of the pressure and suction
housing are to be submitted for review. The
4/7.34.5 Non-Corrosive, Non-Pitting Alloys condition with the inlet of the suction blocked is also
The sealing arrangements above are not required to be considered. A factor of safety of not less than 4
where the tailshaft is fabricated of corrosion-resistant, based on the ultimate tensile strength of the material
pitting-resistant alloy unless required by the (or 2 based on the yield strength) is to be maintained
manufacturer. at each point in the housing. Housing are to be
hydrostatically tested to 1.5 times the maximum
working pressure or to 3.4 bar (3.5 kgf/cm2, 50 psi)
whichever is greater.

PART 4 SECTION 7|8 Propulsion Shafting, Propellers, Waterjets and Lift Devices
4/7.36.7 Reversing Mechanisms 4/7.38.3 Design
Astern thrust is to be provided in sufficient amounts Design basis stress calculations for the propulsion
to secure proper control of the craft in all normal and lift devices are to be submitted to substantiate the
circumstances. The reversing mechanism is to suitability and strength of the components for the
provide for reversing at full power. intended service and compliance with a recognized
standard or code of practice.
4/7.36.9 Impeller Bearings
Antifriction bearings are to have a B10 life of at least 4/7.38.5 Environment
80,000 hours. The design of propulsion and lift devices is to pay
due regard to the effects of allowable corrosion,
Propulsion and Lift Devices for Air electrolytic action between different metals, erosion
Cushion Vessels or cavitation which may result from operation in
environments in which they are subjected to spray,
4/7.38 Propulsion and lift devices debris, salt, sand, icing, etc.

4/7.38.1 General 4/7.38.7 Arrangement


Propulsion arrangements and lift arrangements may Appropriate arrangements are to be made to ensure
be provided by separate devices, or be integrated into that:
a single propulsion and lift device. Propulsion a Ingestion of debris or foreign matter is
devices are those which directly provide the minimized:
propulsive thrust and include machinery items and b The possibility of injury to personnel from
any associated air propellers, ducts, vanes, scoops shafting or rotating parts is minimized; and
and nozzles, the primary function of which is to c Where necessary, inspection and removal of
contribute to the propulsive thrust. The lift devices debris can be carried out safely in service.
are those items of machinery which directly raise the
pressure of the air and move it for the primary
purpose of providing lifting force for an air-cushion
vehicle.

PART 4 SECTION 7|9 Propulsion Shafting, Propellers, Waterjets and Lift Devices
Figure 4/7.1
Propeller Hub Details

1 Liberal Fillet 7 Soft rubber ring


2 Chamfer corners of key 8 Fill and vent holes. One to be
3 Break sharp corners centered on kewyway
4 Fill with suitable sealing 9 See 4/7.23.4
material 10 See typical hub seals
5 Locking device 11 Face (tension side)
6 Threaded holes for jack bolts 12 Back (compression side)

FIGURE 4/7.1a FIGURE 4/7.1b


Maximum Skew Angle Rake Angle at the 0.6 Radius,
Positive Aft

The rake angle φ, measured at


0.6 radius, is formed between
line D which is tangent to the
generating line, and the line C
which is perpendicular to the
propeller shaft centerline

PART 4 SECTION 7|10 Propulsion Shafting, Propellers, Waterjets and Lift Devices
TABLE 4/7.1
Shaft Design Factor K for Lineshafts, Thrust Shafts, and Oil Distribution Shafts
Design Features1
In way of
Radial On both axial
holes, sides of bearings
Propulsion Integral Shrink fit transverse Longitudinal thrust used as Straight
Type flange coupling Keyways2 holes3 slots4 collars thrust sections
bearings
Turbine Drives
Electric Drives
Diesel Drives
through slip
couplings 0.95 0.95 1.045 1.045 1.14 1.045 1.045 0.95
(electric or
hydraulic)
All Other Diesel 1.0 1.0 1.1 1.1 1.2 1.1 1.1 1.0
Drives
Notes
1 Geometric features other that those listed will be specially considered
2 After a length of not less than 0.2 x D from the end of the keyway, the shaft diameter may be reduced to the diameter calculated for straight
sections.
Fillet radii in the transverse section of the bottom of the keyway are to be not less than 0.0125 x D
3 Diameter of bore not more than 0.3 x D
4 Length of the slot not more than 1.4 x D, width of the slot not more than 0.2 x D, whereby D is calculated with k = 1.0

TABLE 4/7.2
Shaft Design Factor K for Tail Shafts and Stern Tube Shafts
Tail shafts may be reduced to stern tube shaft diameter forward of the bearing supporting the propeller. The inboard end of tailshafts or tube
shafts is to be designed the same as line shafts, with shaft design factors in accordance with Table 4/7.1.
Propeller attachment method1
Stern tube Keyless attachment Flanged4 Stern Tube Shafts5,6
Propulsion Type configuration Keyed2 by shrink fit3
All Oil lubricated 1.26 1.22 1.22 1.15
bearings
All Water lubricated 1.26 1.22 1.22 1.15
bearings with
continuous shaft
liners or equivalent
All Water lubricated 1.29 1.25 1.25 1.18
bearings with
noncontinuous shaft
liners
Notes
1 Other attachments are subject to special consideration.
2 Fillet radii in the transverse section at the bottom of the keyway are not to be less than 0.0125D.
3 See also 4/7.8.
4 The fillet radius in the base of the flange, for the tail shaft flange supporting the propeller, is to be at least 0.125D. Special consideration
will be given to fillets of multiple radii design. The fillet radius is to be accessible for non-destructive examination during tail shaft surveys.
See 2/3.13.3. For other fillet radii, see 4/7.10.5.
5 K factor applies to shafting between the forward edge of the propeller-end bearing and the inboard stern tube seal.
6 Where keyed couplings are fitted on stern tube shaft, the shaft diameters are to be increased by 10% in way of the coupling. See Note 2 of
Table 4/7.1.

PART 4 SECTION 7|11 Propulsion Shafting, Propellers, Waterjets and Lift Devices
PART 4 SECTION 8
Steering

4/8.1 General 2 in the case of electro-hydraulic steering


gear, an electric motor and its
4/8.1.1 Application associated electrical equipment and
Theses requirements apply to craft with a traditional connected pump(s), and
type steering gear which have a rule required upper 3 in the case of other hydraulic steering
rudder stock diameter less than 230 mm (9 in.). gear, a driving engine and connected
Where the rule required upper rudder stock diameter pump(s).
is 230 mm (9 in.) or above, the Rules for Building e Power Actuating System Power actuating
and Classing Steel Vessels are to be applied. system is the hydraulic equipment provided for
Where a rudder is not fitted and steering is supplying power to turn the rudder stock, comprising
achieved by change of setting of the propulsion units, a power unit or units, together with the associated
such as the use of cycloidal, azimuthing or similar pipes and fittings, and a rudder actuator. The power
type propulsion systems, Sections 2 and 4 of the ABS actuating systems may share common mechanical
“Guide for Thrusters and Dynamic Positioning components, i.e. tiller, quadrant, rudder stock or
Systems” are to be applied. components serving the same purpose.
Where a rudder is not fitted and steering is f Rudder Actuator Rudder actuator is the
achieved by waterjet nozzles, the material and design component which directly converts hydraulic pressure
requirements of 4/7.36 are applicable. Where the into mechanical action to move the rudder.
directional control system is power operated, the g Maximum Working Pressure Maximum
control and power systems are to meet the intent of working pressure is the expected pressure in the
4/8.4 and 4/8.6. system when the steering gear is operated to comply
with 4/8.1.5.
4/8.1.2 Definitions
a Main Steering Gear Main steering gear is the 4/8.1.3 Plans and Data
machinery, rudder actuators, power units, ancillary Plans and data of the steering gear system to be
equipment and the means of applying torque to the submitted are as follows:
rudder stock (e.g. tiller or quadrant) necessary for
effecting movement of the rudder for the purpose of Plans
steering the ship. a General arrangements of the main and
b Auxiliary Steering Gear Auxiliary steering auxiliary steering gears, and of the steering
gear is the equipment other than any part of the main gear compartment.
steering gear necessary to steer the ship in the event b Assembly of upper rudder stock, tiller, tie
of failure of the main steering gear but not including rod, rudder actuators, etc. as applicable.
the tiller, quadrant or components serving the same c Construction details of all torque-
purpose. transmitting components of steering gear,
c Control System Control system is the such as tiller, tiller pin, tiller/rudder stock
equipment by which orders are transmitted from the interference fit mechanism, tie rod, rudder
navigation bridge to the power units. Control systems actuator, etc, including bill of materials,
comprise transmitters, receivers, hydraulic control welding procedures, non-destructive testing,
pumps and their associated motors, motor controllers, as applicable.
piping and cables. For the purpose of the Rules, d Schematic hydraulic piping diagram,
steering wheels or steering levers are not considered incorporating hydraulic logic diagram, and
to be part of the control system. including bill of materials, typical pipe to
d Power Units A steering gear power unit is: pipe joint details, pipe to valve joint details,
1 in the case of electric steering gear, an pipe to equipment joint details, pressure
electric motor and its associated rating of valves and pipe fittings, and
electrical equipment, pressure relief valve settings.

PART 4 SECTION 8|1 Steering


e Steering gear control system incorporating 2 for cargo craft, the main steering gear is
schematic electrical control logic diagram, to be capable of operating the rudder as
instrumentation, alarm devices, etc, and required by 4/8.1.5 while all the power
including bill of materials. units are in operation.
f Electrical power supply to power units and b When the main steering gear is non-power
to steering gear control, including schematic operated such as an orbitrol system or consists solely
diagram of motor controllers, feeder cables, of mechanical components such as sheaves, blocks,
feeder cable electrical protection. wires, chains, etc.

Data 4/8.1.7 Steering Gear Compartment Unit


g Rated torque of main steering gear. Location
h Calculations of torque-transmitting The main and the auxiliary steering gears are to be
components such as tiller, tie rod, rudder protected from weather. The power units may be
actuator, etc. located either within or outside the compartment
containing the rudder actuators. In the event of loss
4/8.1.4 Power Operation of hydraulic fluid and of the need to restore the
The main steering gear is to be power operated, by operation of the main or the auxiliary steering gear,
one or more power units, if the rule required upper the steering gear compartment is to be provided with
rudder stock diameter is 120 mm (4.7 in.) or greater. handrails and gratings, or other non-slip surfaces, to
Notwithstanding the above, the performance ensure suitable working condition.
requirements stated in 4/8.1.5 and 4/8.1.6 are to be In the event of control system failure, or the need
used to determine if it is necessary for the main and to operate the main or the auxiliary steering gear from
auxiliary steering gears to be power operated. within the steering gear compartment or from
positions other than the navigating bridge, craft of
4/8.1.5 Main Steering Gear Capability 500 gross tons and above are to be provided with a
The main steering gear is to be capable of putting the means to indicate the position of the rudder at these
rudder from 35o on one side to 35o on the other side positions where emergency steering is to be
with the craft running ahead at maximum continuous conducted.
shaft rpm and at the design draft; and under the same
conditions, the travel time from 35o on either side to 4/8.2 Materials
30o on the other side is not to be more than 28
seconds. For controllable pitch propellers, the 4/8.2.1 General
propeller pitch is to be at the maximum design pitch All steering gear components transmitting a force to
approved for the above maximum continuous ahead the rudder and pressure retaining components of
rated RPM. hydraulic rudder actuator are to be of steel or other
approved ductile material. The use of gray cast iron
4/8.1.6 Auxiliary Steering Gear or other material having an elongation less than 12%
The auxiliary steering gear is to be capable of putting in 50 mm (2 in.) is not acceptable.
the rudder from 15o on one side to 15o on the other
side in not more than 60 seconds with the craft 4/8.2.2 Material Testing
running ahead at half speed, or seven knots, Except as modified below, materials for the parts and
whichever is greater. components mentioned in 4/8.2.1 are to be tested in
The auxiliary steering gear is to be so arranged the presence of the Surveyor in accordance with the
that the failure of the main steering gear will not requirements of 2/2.
render it inoperative. Likewise, failure of auxiliary Material tests for steering gear coupling bolts and
steering gear is not to affect the main steering gear. torque transmitting keys need not be witnessed by the
An auxiliary steering gear is not required under Surveyor.
the following conditions. Material tests for commercially supplied tie-rod
a When the main steering gear comprises two or nuts need not be witnessed by the Surveyor provided
more power units, and is so arranged that after a the nuts are in compliance with the approved steering
single failure in its piping system or in one of the gear drawings and are appropriately marked and
power units the defect can be isolated so that the identified in accordance with a recognized industry
steering capability can be maintained or regained; and standard. Mill test reports for the tie-rod nuts are to
provided that be made available to the Surveyor upon request. For
1 for passenger craft, the main steering all non-standard tie-rod nuts, material testing is
gear is capable of operating the rudder required to be performed in the presence of the
as required in 4/8.1.5 while any one of Surveyor.
the power units is out of operation; and

PART 4 SECTION 8|2 Steering


Material tests for forged, welded or seamless steel Other symbols are defined above.
parts (including the internal components) and all non-
5 Bearing stress of the tiller and rudder stock
ferrous parts of rudder actuators that are not more
keyways are not to be less than 0.9 times the
than 152.4 mm (6 in.) in internal diameter need not be
material yield stress.
carried out in the presence of the Surveyor. Such
6 If tiller is shrink fitted to the rudder stock,
parts are to comply with the requirements of 2/2 or
preloading and stress calculations and fitting
such other appropriate material specifications as may
instructions are to be submitted. The
be approved in connection with a particular design,
calculated torsional holding capacity is to be
and will be accepted on the basis of presentation of
at least 2.0 times the transmitted torque
mill certificates to the Surveyor for verification.
based on the steering gear relief valve
setting. Preload stress is not to exceed 70%
4/8.3 Design
of the minimum yield strength.
7 Section modulus of tiller arm at any point
4/8.3.1 Power Gear Stops
within it length is not to be less than:
Power operated steering gears are to be provided with
arrangements for stopping the steering gear before the 0.167S 3 ( L2 − L1 ) U R
rudder stops are reached. These arrangements are to ⋅
be synchronized with the rudder stock or position of L2 UT
the steering gear itself rather than with the steering-
where
gear control system.
L2 = distance from the point of application of the
force on the tiller to the center of rudder
4/8.3.2 Mechanical Components
stock
All steering gears parts transmitting force to or from
L1 = distance between the section of the tiller arm
the rudder, such as tillers, quadrants, rams, pins, tie
under consideration and the center of the
rods and keys are to be proportioned to have strength
rudder stock
equivalent to that of the rule required upper rudder
Other symbols are defined above
stock diameter.
8 Where tiller is of welded construction, weld
4/8.3.3 Tiller design and weld sizes are to be proportioned
Tillers are to comply with the following requirements. such that they are commensurate with the
All terms in the formulae are to have consistent units. strength of the tiller.
1 Depth of tiller hub is not to be less than rule
required upper rudder stock diameter. 4/8.3.4 Pin
2 Thickness of tiller hub is not to be less than Shear area of tiller pin is not to be less than:
one third of the rule required upper rudder
stock diameter. 0.196S 3 U R
3 Notwithstanding (2) above, polar section

L2 UP
modulus of the tiller hub is not to be less
than: where
UP = ultimate tensile strength of the pin
UR
. S3
0196 Other symbols are defined above.
UT
4/8.3.5 Tie Rod (Jockey Bar)
where The buckling strength of the tie rod is not to be less
S = rule required upper rudder stock diameter than:
UR = ultimate tensile strength of the rudder stock
UT = ultimate tensile strength of the tiller . S 3U R
0113
L2
4 The shear area of the tiller key is not to be
less than: Symbols are defined above.
0.196S 3 U R
⋅ 4/8.3.6 Rudder Actuators
r UK a General Rudder actuators are to meet the
requirements in 4/8.2 for materials and material tests
where and 2/3B.1 for welding. They are also to meet the
r = mean radius of the rudder stock in way of requirements for pressure vessels in the Rules for
the key Building and Classing Steel Vessels, specifically
UK = ultimate tensile strength of the key

PART 4 SECTION 8|3 Steering


4/2.5.1 (for malleable cast iron, use y = 0.5), 4/2.9 4/8.4 Hydraulic System
and 4/2.11 (in association with S as defined below)
for design and 4/2.39 for hydrostatic tests. The 4/8.4.1 Pipes, Valves & Fittings
maximum allowable stress S is not to exceed the Pipes, valves and fittings are to meet the requirements
lower of the following: of 4/6.67, as applicable. The design pressure of
piping components subject to internal hydraulic
U Y pressure is to be at least 1.25 times the maximum
or
A B working pressure of the system. Arrangements for
bleeding air from hydraulic system are to be
where provided, where necessary.
U = minimum specified tensile strength of
material at room temperature 4/8.4.2 Relief Valves
Y = minimum specified yield point or yield Relief valves are to be provided for the protection of
strength the hydraulic system. Each relief valve is to be
A & B = factors as given in the following table. capable of relieving not less than the full flow of all
the pumps which can discharge through it increased
Factor Rolled or Cast Nodular by 10%. With this flow condition, the maximum
Forged Steel Cast Iron pressure rise is not to exceed 10% of the relief valve
Steel setting. In this regard, consideration is to be given to
A 3.5 4 5 the extreme expected ambient conditions in respect to
B 1.7 2 3 oil viscosity. The relief valve setting is to be at least
1.25 times the maximum working pressure but is not
b Oil Seals Oil seals between non-moving parts to exceed the design pressure.
form the external boundary are to be of the pressure
seal type. Oil seals between moving parts forming 4/8.4.3 Filtration
the external pressure boundary are to be fitted in A means is to be provided to maintain cleanliness of
duplicate so that the failure of one seal does not the hydraulic fluid.
render the actuator inoperative. Alternative seal
arrangement may be acceptable provided equivalent 4/8.4.4 Single Failure
protection against leakage can be ensured. Where multiple power units are provided and an
auxiliary steering gear is not fitted, the steering gear
4/8.3.7 Mechanical Steering Gear hydraulic system is to be designed so that after a
Where mechanical steering system are permitted, the single failure in its piping system, one of the power
following are applicable. units, or mechanical connection to the power units,
a Steering Chains and Wire Ropes Steering the defect can be isolated so that the integrity of the
chains and wire rope are to be tested as required by remaining part of the system will not be impaired and
2/1.11 and 2/1.13 respectively. the steering capability can be maintained or regained.
b Sheaves Sheaves are to be of ample size and For this purpose, piping system associated with each
so placed as to provide a fair lead to the quadrant and power unit is to be independent of that of the other
avoid acute angles. Parts subjected to shock are not units as far as practicable and connections are made
to be of cast iron. Guards are to be placed around only where necessary. Isolation valves are to be
the sheaves to protect against injury. For sheaves fitted, as necessary, to allow any single failure in the
intended to use with ropes, the radius of the grooves piping system be isolated and the steering gear be
is to be equal to that of the rope plus 0.8 mm operated with the remaining intact part of the system.
(1/32in.), and the sheave diameter is to be determined Isolation valves are to be fitted at the pipe
on the basis of wire rope flexibility. For 6 X 37 wire connections to rudder actuators. Where non-
rope, the sheave diameter are to be not less than 18 duplicated rudder actuator is employed, the isolation
times that of the rope. For wire ropes of lesser valves are to be mounted directly on the actuator.
flexibility, the sheave diameter is to be increased Piping systems are to be so arranged that transfer
accordingly. Sheave diameters for chain are to be not between power units can be readily effected.
less than 30 times the chain diameter.
c Buffers Steering gears other than hydraulic 4/8.4.5 Reservoir and Storage Tank
type are to be designed with suitable buffer All open-loop hydraulic systems are to be provided
arrangement to relieve the gear from shocks to the with an oil reservoir of suitable capacity. In addition,
rudder. for craft of 500 gross tons and above, a fixed storage
tank having sufficient capacity to recharge at least
one hydraulic power system including the reservoir is
to be provided. The tank is to be permanently

PART 4 SECTION 8|4 Steering


connected by piping in such a manner that the system c Where duplicate (or more) power units are
can be readily recharged from a position within the provided and an auxiliary steering gear is not fitted,
steering gear compartment. two independent systems of control are to be
provided. Each of these systems is to meet the
4/8.5 Power Units requirements of the control system of the main
If the rule required upper rudder stock diameter is steering gear (See 4/8.6.1a). Where the control
120 mm (4.7 in.) or greater, power units are to be system consists of a hydraulic telemotor, a second
tested and certified in accordance with the following independent system need not be fitted.
requirements. If the rule required upper rudder stock d If steering gear is operated by manual means
diameter is less than 120 mm (4.7 in.), and if the craft only, such as by means of a steering wheel through a
is 500 gross tons or greater, power units are to be mechanical or a non-power operated hydraulic
tested and certified in accordance with 4/8.5.2 only. system, only the requirements of 4/8.6.4 and 4/8.6.5a
For craft less than 500 gross tons, power units may be are applicable.
accepted based on manufacturer’s guarantee for
suitability for the intended purpose and subject to 4/8.6.2 Control System Segregation
satisfactory functional tests after installation. a Control systems of the main and the auxiliary
steering gears are to be independent of each other in
4/8.5.1 Prototype Test all respects. The control wires are to be separated as
A prototype of each new design power unit pump is far as practicable throughout their length. Where
to be shop tested for a duration of not less than 100 found necessary, the wiring of the two systems may
hours. The testing is to be carried out in accordance share the same terminal box, provided a safety barrier
with an approved agenda and is to include the is fitted in the box to segregate the wiring.
following as a minimum. b If the main steering gear consists of duplicated
a The pump and stroke control (or directional (or more) power units and an auxiliary steering is not
control valve) is to be operated continuously from full
fitted, the two independent means of control are to
flow and relief valve pressure in one direction
comply with the segregation requirement of 4/8.6.2a.
through idle to full flow and relief valve pressure in
the opposite direction. However, this does not require duplication of steering
b Pump suction conditions are to simulate lever or other steering apparatus on the navigating
lowest anticipated suction head. The power unit is to bridge.
be checked for abnormal heating, excessive vibration, c If the main steering gear consists of a single
or other irregularities. Following the test, the power power unit and the auxiliary steering gear is not
unit pump is to be disassembled and inspected in the power operated, only one control system for the main
presence of a Surveyor. steering gear need be provided.

4/8.5.2 Production Unit Test 4/8.6.3 Control System Power Supply


Each power unit pump is to meet the hydrostatic and Electrical power for steering gear control system is to
capacity tests in accordance with 4/6.8, as applicable. be derived from the motor controller of the power
unit it is controlling, or from the main switchboard at
4/8.6 Steering Gear Control System a point adjacent to the supply to the power unit.

4/8.6.1 Locations of Control 4/8.6.4 Communication


a The main steering gear is to be provided with A means of communication is to be provided between
control both from the navigating bridge and from the navigating bridge and all other locations where
within the steering compartment. However, if the steering can be effected, such as the steering gear
power unit is located in a space other than the compartment, the space where the power units are
steering compartment, the control is to be provided in located and the space where auxiliary steering gear is
that space instead of the steering compartment. For to be operated, as applicable.
purpose of controlling from the steering gear
compartment (or the space containing the power
4/8.6.5 Instrumentation and Alarms
unit), a means is to be provided in the steering
compartment (or the space containing the power unit) The following instruments and alarms are to be
to disconnect any control system from the navigating provided. The audible and visual alarms are to have
bridge. provisions for testing.
b The auxiliary steering gear is to be operable a Rudder Position Indicator The angular
from a space in which the operation of the auxiliary position of the rudder is to be indicated on the
steering gear can be effectively carried out, or from navigating bridge and all other locations where
within the steering compartment. However, if power steering can be effected, such as the steering gear
operated, it is to be provided with control from the compartment, the space where the power units are
navigation bridge also. located and the space where auxiliary steering gear is

PART 4 SECTION 8|5 Steering


to be operated, as applicable. The rudder angle 4/8.8 Testing and Trials
indication is to be independent of the steering gear
control system. 4/8.8.1 Testing of Piping System
b Autopilot Where autopilot is fitted, a visual The following tests are to be performed in the
and audible alarm is to be provided on the navigating presence of the Surveyor.
bridge to indicate its failure. a Shop Tests After fabrication, each component
of the steering gear piping system, including the
Where power unit is provided and steering is
power units, hydraulic cylinders and piping is to be
controlled from navigating bridge, the following are
hydrostatically tested at the plant of manufacture to
applicable:
1.5 times the relief valve setting, except that for
c Motor Alarm A visual and audible alarm is to
steering gear cylinders of nodular iron, the test
be given on the navigating bridge and the engine
pressure is to be at least 2 times the relief valve
room control station to indicate an overload condition
setting.
of the steering gear power unit motor. Where three
b Installation Tests After installation in the
phase electrical power is used a visual audible alarm
craft, the complete piping system, including power
is to be installed which indicates failure of any one of
units, hydraulic cylinders and piping is to be
the supply phases. The operation of these alarms is
subjected to a hydrostatic test equal to 1.1 times the
not to interrupt the circuit.
relief valve setting, including a check of the relief
d Motor Running Indicators Indicators for
valve operation.
running indication of motors are to be installed on the
navigating bridge and the engine room control
4/8.8.2 Trials
station.
The steering gear is to be tried out on the trial trip in
e Power Failure A visual and audible alarm is order to demonstrate to the Surveyor’s satisfaction
to be given on the navigating bridge and engine room that the requirements of the Rules have been met.
control station to indicate a power failure to any one The trial is to include the operation of the following:
of the steering gear power units. a The main steering gear, including
f Control Power Failure A visual and audible demonstration of the performance requirements of
alarm is to be given on the navigating bridge and 4/8.1.5 or with the rudder fully submerged. Where
engine room control station to indicate an electrical full rudder submergence cannot be obtained in ballast
power failure in any steering gear control circuit or conditions, special consideration may be given to
remote control circuit. specified trials with less than full rudder
submergence.
In addition, hydraulic power operated steering gear is Trials are to be carried out with the craft running
to be provided with the following: ahead at maximum continuous rated shaft RPM. For
g Low Oil-level Alarm A visual and audible controllable pitch propellers, the propeller pitch is to
alarm is to be given on the navigating bridge and be at the maximum design pitch approved for the
engine room control station to indicate a low oil level above maximum continuous ahead RPM.
in any power unit reservoir. b The auxiliary steering gear, if required,
h Hydraulic Lock Where the arrangement is including demonstration to the performance
such that a single failure may cause hydraulic lock requirements of 4/8.1.6 and transfer between main
and loss of steering, an audible and visual alarm and auxiliary steering gear.
which identifies the failed system or component is to c The power units, including transfer between
be provided on the navigating bridge. The alarm is to power units.
be activated upon steering gear failure if: d The emergency power supply required by
- position of the variable displacement pump 4/5A3.3.5.
control system does not correspond to the e The steering gear controls, including transfer
given order, or of control, and local control.
- incorrect position of 3-way full flow valve or fThe means of communications as required by
similar in constant delivery pump system is 4/8.6.4
detected. g The alarms and indicators required by
4/8.6.5 (test may be done at dockside).
4/8.7 Electrical Power Supply h The storage and recharging system contained
Electrical power circuits are to meet the requirements in 4/8.4.5 (test may be done at dockside).
of 4/5A6 and 4/5A3.3.5. i The isolating of one power actuating system,
and checking for regaining steering capability are
required by 4/8.4.4 if applicable (test may be done at
dockside).
j Where steering gear is designed to avoid
hydraulic locking, this feature is to be demonstrated.

PART 4 SECTION 8|6 Steering


PART 4 SECTION 9

Fire Extinguishing Systems

4/9.1 General the ventilation system, fuel oil pumps and valves,
along with details of the means provided for the
4/9.1.1 Classification Requirements closing of openings, and locations of accesses to
The following are the minimum classification critical spaces (such as fire control stations, Category
requirements for high speed cargo craft which do not A machinery spaces, etc.). For craft where structural
proceed, in the course of their voyage, more than 8 fire protection is required by the Rules, locations and
hours, at operational speed, from a place of refuge. type of fire retarding bulkheads are to be specified on
(See 4/1.17.11 for definition of “cargo craft”). Cargo the plan.
craft which proceed more than 8 hours from a place b Plan Location The fire control plans are to be
of refuge are to comply with either Section 4/9 of the conspicuously posted on the craft for the guidance of
“Rules for Building and Classing Steel Vessels” or the crew.
Section 4/9 of the “Rules for Building and Classing
Steel Vessels Under 90 Meters (295 Ft) in Length”, 4/9.3 Fire Pumps, Fire Main, Hydrants and
as appropriate. Hoses

4/9.1.2 Governmental Authority 4/9.3.1 Materials


Attention is directed to the appropriate governmental Materials readily rendered ineffective by heat are not
authority. In each case there may be additional to be used for fire mains unless adequately protected.
requirements depending on the gross tonnage, length, In order to be considered not “readily rendered
type and intended service of the craft as well as other ineffective by heat”, a component is to be certified as
particulars and details. Consideration will be given to having passed an applicable recognized fire test, or
fire extinguishing systems which comply with the the material is to have a melting temperature higher
published requirements of the governmental authority than the test temperature specified in an applicable
of the country in which the craft is to be registered. fire test.

4/9.1.3 Automated Propulsion Machinery Spaces 4/9.3.2 Fire Pumps


Where automatic controls for propulsion machinery a Number of Pumps All craft are to have at
spaces are installed and it is intended that the least two fire pumps. For craft of 500 gross tons and
propulsion machinery spaces are either not above, the pumps are to be independently power-
continuously manned at sea or only one person is driven. For craft less than 500 gross tons, only one of
required on watch, the requirements of Section 4/11 the pumps need be independently power-driven and
are to be met. one of the pumps may be attached to the propulsion
unit. For craft less than 20m (65 ft.) in length, one
4/9.1.4 Fire Safety Measures power driven pump which may be an attached unit,
The applicable requirements of Section 3/24 are to be and one hand operated fire pump may be provided.
complied with. b Type of Pumps Sanitary, ballast, bilge or
general service pumps may be accepted as fire
4/9.1.5 Plans and Specifications pumps, provided that they are not normally used for
The plans together with supporting data and pumping oil. If the pumps are subject to occasional
particulars listed in 4/1.11 are to be submitted for duty for the transfer or pumping of fuel oil, change
review. over arrangements that prevent operation for fire
fighting when configured for fuel transfer are to be
4/9.1.7 Fire Control Plans fitted.
a Required Information Fire control plans are c Pump Capacity
to be general arrangement plans showing for each 1 Craft Of 500 Gross Tons And Above
deck the provision, location, controls and particulars, Each of the power-driven fire pumps
as applicable, of fixed fire detection, alarm and required by 4/9.3.2a is to have a
extinguishing systems, portable fire fighting capacity of not less than two-thirds of
appliances and equipment, controls for shutdowns of the quantity required under 4/6.35.3 to

PART 4 SECTION 9|1 Fire Extinguishing Systems


be dealt with by each of the independent 2 An air lock consisting of two gastight
bilge pumps but not less than 25 m3/hr steel doors. The doors are to be self-
(110 gpm) and in any event is to be closing without any hold back
capable of delivering at least the two arrangements.
required jets of water. These pumps are 3 In addition to the arrangements
to be capable of supplying the water specified in 1 or 2 above, a second
under the required conditions. Where protected means of access is to be
more pumps than required are installed, provided to the space containing the fire
their capacity will be subject to special pumps.
consideration. h Isolation For craft of 500 gross tons and
2 Craft Less Than 500 Gross Tons The above, isolating valves and other arrangements, as
capacity of each power driven fire pump necessary, are to be provided so that if a fire pump
is to be in accordance with item 1 above and its associated piping within its compartment are
or Table 4/9.3, whichever is less. Hand rendered inoperable, the fire main can be pressurized
pumps, where permitted, are to have a with a fire pump located in another compartment.
minimum capacity of 1.1 m3/hr (5 gpm).
d Pressure Power-driven fire pumps are to have 4/9.3.3 Fire Main
sufficient pressure to simultaneously operate the a Size The diameter of the fire main and water
adjacent hydrants as required by 4/9.3.4a. service pipes is to be sufficient for the effective
e Relief Valves In conjunction with all fire distribution of the maximum required discharge from
pumps, relief valves are to be provided if the pumps two fire pumps operating simultaneously except that
are capable of developing a pressure exceeding the the diameter need only be sufficient for the discharge
design pressure of the water service pipes, hydrants of 140 m3/hr (616 gpm).
and hoses. These valves are to be so placed and b Cocks or Valves A valve is to be fitted to
adjusted as to prevent excessive pressure in any part serve each fire hose so that any fire hose may be
of the fire main system. In general, the relief valve is removed while the fire pumps are at work.
to be set to relieve at no greater than 1.7 bar (1.75 c Cold Weather Protection Fire main systems
kgf/cm2, 25 psi) in excess of the pump pressure are to be provided with drains, circulation loops or
necessary to maintain the requirements of 4/9.3.2c. other means for cold weather protection.
f Arrangement For craft of 500 gross tons and
above, the two main fire pumps including their power 4/9.3.4 Hydrants
source, fuel supply, electric cables, and lighting and a Number and Position of Hydrants The
ventilation for the spaces in which they are located number and position of the hydrants are to be such
are to be in separate compartments so that a fire in that at least two jets of water not emanating from the
any one compartment will not render both main same hydrant, one of which is to be from a single
pumps inoperable. Only one common boundary is length of hose, may reach any part of the craft.
allowed between the compartments in which case the b Materials Materials readily rendered
single common boundary is to be at least to A-0 ineffective by heat are not be used for fire protection
standard. systems unless adequately protected. See 4/9.3.1.
No direct access is allowed between the c Installation The pipes and hydrants are to be
compartments except that where this is impracticable, so placed that the fire hoses may be easily coupled to
an access meeting the requirements in subparagraph g them. In craft where deck cargo may be carried, the
may be considered. positions of the hydrants are to be such that they are
g Alternative Arrangement Where it is always readily accessible and the pipes are to be
impracticable to do otherwise, a direct access arranged to avoid risk of damage by such cargo.
between the compartments containing the main fire
pumps may be considered provided: 4/9.3.5 Hoses
1 A watertight door capable of being a General Fire hoses are to be of a type
operated locally from both sides of the certified by a competent independent testing
bulkhead, and from a safe and laboratory as being constructed of non-perishable
accessible location outside of these material to a recognized standard. The hoses are to
spaces is provided. The means for the be sufficient in length to project a jet of water to any
latter operation is expected to be of the spaces in which they may be required to be
available in the event of fire in these used. The maximum length of hose is not to exceed
spaces; or 23 m (75 ft.). Each hose is to have a nozzle and the
necessary couplings. Fire hoses together with any
necessary fittings and tools are to be kept ready for
use in conspicuous positions near the hydrants.

PART 4 SECTION 9|2 Fire Extinguishing Systems


b Diameter Hoses are not to have a diameter be fitted with a valve capable of being closed from
greater than 38 mm (1.5 in.). Hoses for craft under outside the space where such tanks are located in the
20 m (65 ft.) in length may be of a good commercial event of a fire. In the special case of deep tanks
grade having a diameter of not less than 16 mm (5/8 situated in any shaft or pipe tunnel, control may be
in.) and are to be have a minimum test pressure of effected by means of an additional valve on the pipe
10.3 bar (10.5 kgf/cm2 , 150 psi) and a minimum burst line outside the tunnel. See 4/6.51.4 and 4/6.59.1.
pressure of 31.0 bar (31.6 kgf/cm2 , 450 psi).
c Number of Fire Hoses One fire hose with the 4/9.7 Portable Extinguishers
couplings and nozzle is to be provided for each
Portable extinguishers are to be provided in the
hydrant. Additionally, at least one spare hose is to be
quantities and locations indicated in Tables 4/9.1 and
kept on board.
4/9.2.
4/9.3.7 Nozzles
4/9.9 Fireman's Outfits
a Size Standard nozzle sizes are to be 12 mm
(0.5 in.), 16 mm (0.625 in.) and 19 mm (0.75 in.), or At least two complete fireman's outfits are to be
as near thereto as possible. Larger diameter nozzles carried on board each craft of 500 gross tons and
may be permitted subject to compliance with above. Each outfit is to consist of an approved
4/9.3.2c. For accommodation and service spaces, a breathing apparatus, a lifeline, a safety lamp, an axe,
nozzle size greater than 12 mm (0.5 in.) need not be non-conducting boots and gloves, a rigid helmet and
used. For machinery spaces and exterior locations, protective clothing complying with the following
the nozzle size is to be such as to obtain the requirements. The fireman’s outfits and equipment
maximum discharge possible from two jets at the are to be stored so as to be easily accessible and
pressure mentioned in 4/9.3.2c from the smallest ready for use and are to be stored in widely separate
pump; however, a nozzle size greater than 19 mm positions.
(0.75 in.) need not be used. a Breathing Apparatus The breathing apparatus
b Type All nozzles are to be of an approved is to be of an approved type and may be either of the
dual-purpose type (i.e. spray and jet type) following.
incorporating a shut-off. Fire hose nozzles of plastic 1 Smoke Helmet or Mask A smoke
type material such as polycarbonate may be accepted helmet or smoke mask with a suitable
subject to review of their capacity and serviceability air pump and a length of air hose
as marine use fire hose nozzles. sufficient to reach from the open deck,
well clear of hatch or doorway, to any
4/9.5 Means for Closing of Openings, Stopping part of the holds or machinery spaces.
of Machinery and Oil Containment If, in order to comply with this
requirement, an air hose exceeding 36 m
4/9.5.1 Ventilation Fans and Openings (120 ft) in length would be necessary, a
Means are to be provided for stopping ventilation self-contained breathing apparatus is to
fans serving machinery and cargo spaces and for be substituted or provided in addition.
closing all doorways, ventilators, and other openings 2 Self-contained Breathing Apparatus A
to such spaces. These means are to be capable of self-contained breathing apparatus,
being operated from outside such spaces and also which is to be capable of functioning for
from a continuously manned control station in case of a period of at least 30 minutes. Other
fire. See 4/5A10.1.1. periods of time will be specially
considered. At least one spare charge is
4/9.5.3 Other Auxiliaries to be carried for each required breathing
Machinery driving forced- and induced-draft fans, apparatus carried on board.
oil-fuel transfer pumps, oil-fuel unit pumps and other b Lifeline Each breathing apparatus is to have
similar fuel pumps are to be fitted with remote attached to its belt or harness, by means of a
shutdowns situated outside the spaces concerned and snaphook, a fire-proof lifeline of sufficient length and
also from a continuously manned control station so strength.
that they may be stopped in the event of a fire arising c Safety Lamp and Axe A safety lamp (hand
in the space. lantern) of an approved type and an axe are to be
provided. Such safety lamps are to be electric, and
4/9.5.5 Oil Tank Suction Valves are to have a minimum burning period of three hours.
Except for small independent tanks, having a capacity d Boots and Gloves The boots and gloves are to
less than 500 liters (132 gal.) every oil suction pipe be made of rubber or other electrically non-
from a storage, settling, daily service or lube oil tank conducting material.
situated above the double bottom, as applicable, is to

PART 4 SECTION 9|3 Fire Extinguishing Systems


e Helmet A rigid helmet is to be supplied which b For paint lockers and flammable liquid lockers
will provide effective protection against impact. of deck area less than 4 m2 (43 ft2), 6.3 kg (15 lb)
f Protective Clothing The protective clothing is CO2 or 4.5 kg (10 lb) dry-powder fire extinguisher(s)
to be made of material that will protect the skin from may be accepted unless subparagraph c below is
the heat of fire and burns from scalding steam or applicable.
gases. The outer surface is to be water resistant. c Portable fire extinguishing equipment of the
type and size indicated in b above stowed near the
4/9.11 Machinery Spaces entrance may be accepted for paint lockers of deck
area less than 10 m2 (108 ft2), located outside the
4/9.11.1 Fire Detection and Fire Alarm Systems main superstructure block and having no contiguous
Fire detection and fire alarm systems complying with boundaries with accommodation, Category A
4/9.23 are to be provided for any machinery space machinery spaces, or gas dangerous spaces.
containing an internal combustion engine, gas turbine,
oil filling station, or switchboards of aggregate 4/9.15 Tanks for Low Flash Point Fuel for Gas
capacity exceeding 800 kW. Turbines
Where fuel with a flash point below 43C (109F) is
4/9.11.2 Fixed Fire Extinguishing System
permitted by 4/3.9.4 for gas turbines, each space
For craft of 500 gross tons and above, Category A
containing a non-integral tank for the low flash point
machinery spaces are to be protected by a fixed fire
fuel is to be fitted with a fire detection system
extinguishing system. A fixed fire extinguishing
complying with 4/9.23 and a fire extinguishing
system is not required in a machinery space for craft
system complying with 4/9.25.
below 500 gross tons unless the space contains an oil
fuel unit. The fixed fire extinguishing system is to
4/9.17 Cargo Spaces
comply with 4/9.25 and be capable of local manual
control as well as remote control from a continuously For craft of 500 gross tons and above, cargo spaces,
manned control station. except deck areas or refrigerated holds, are to be
provided with an approved automatic smoke
4/9.13 Paint or Flammable Liquid Lockers detection system complying with 4/9.23 to indicate at
the control station the location of outbreak of a fire
4/9.13.1 Fire Detection and Fire Alarm System and are to be protected by an approved quick-acting
Paint lockers and flammable liquid lockers are to be fire extinguishing system complying with 4/9.25
provided with fire detection and alarm system operable from the control station.
complying with 4/9.23.
4/9.19 Spaces Containing Dangerous Goods
4/9.13.2 Fixed Fire Extinguishing Arrangements
Craft intending to carry dangerous goods are to
Paint lockers and flammable liquid lockers are to be
comply with the applicable requirements of Chapter
protected by an approved fire extinguishing
II-2, Part C, Regulations 53 and 54 of International
arrangement. Unless required otherwise by the flag
Convention for the Safety of Life at Sea (SOLAS)
Administration, the following arrangements will be
1974 and Amendments in force.
acceptable:
a Paint lockers and flammable liquid lockers of
4/9.21 Accommodation and Service Spaces
deck area 4 m2 (43 ft2) and more are to be provided
with a fire extinguishing system enabling the crew to A fire detection and fire alarm system complying with
extinguish a fire without entering the space. One of 4/9.23 is to be provided for accommodation and
the fixed arrangements specified below are to be services spaces.
provided unless subparagraph c is applicable.
1 CO2 system, designed for 40% of the 4/9.23 Fire Detection and Fire Alarm Systems
gross volume of the space. See
Where required, fire detection and fire alarm systems
4/9.25.2.
are to comply with Regulations 7.7.1, 7.7.2 and 7.7.3
2 Dry-powder system, designed for at
of the International Code of Safety for High Speed
least 0.5 kg/m3 (0.03 lb/ft3).
Craft, as applicable.
3 Water spraying system, designed for 5
l/m2-min (0.12 gpm/ft2). The water
spraying system may be connected to
the ship's main system.
4 Systems other than those mentioned
above may also be considered.

PART 4 SECTION 9|4 Fire Extinguishing Systems


4/9.25 Fixed Fire Extinguishing Systems automatically kept charged at all times
and is to be fitted with a low pressure
4/9.25.1 Gas Smothering alarm. The air supply may be taken
a Storage The cylinders for the gas smothering from the starting air receivers. Any stop
medium are to be stored outside the protected space valve fitted in the air supply line is to be
in a room which is situated in a safe and readily locked or sealed in the open position.
accessible location. The access doors to the storage Any electrical components associated
space are to open outwards. The storage room is to with the pneumatic system are to be
be gastight and effectively ventilated by a ventilation powered from the main and an
system independent of the spaces protected. Any emergency source of electrical power.
entrance to the storage room is to be independent of d Controls Except as otherwise permitted
the protected space, except that where this is herein two independent manual control arrangements
impracticable due to space limitations, access are to be provided, one of them being positioned at
between the storage location and the protected space the storage location, and the other in a readily
may be considered for craft under 500 gross tons accessible position outside the protected space.
subject to compliance with the following:
1 The door between the storage location 4/9.25.2 Carbon Dioxide Systems
and the protected space is to be self- In addition to the applicable requirements of the
closing with no hold-back arrangements. Rules, fixed carbon dioxide fire extinguishing
2 The space where cylinders are stored is systems are to be in accordance with Regulations
to be adequately ventilated by a system 7.7.6.1 and 7.7.6.2 of the International Code of Safety
which is independent of the protected for High Speed Craft. Fixed low pressure carbon-
space. dioxide systems are to be in accordance with the
3 Means are to be provided to prevent latest edition of the ABS Guide for the Use of
unauthorized release of gas, such as Refrigerated (Low Pressure) Carbon-Dioxide as a
containment behind a break glass. Fire Extinguishing Medium on Board Ship.
4 There is to be provision to vent the
bottles to the atmosphere in order to 4/9.25.3 Foam
prevent a hazard to personnel occupying a Fixed High Expansion Foam Systems In
the storage area. addition to the applicable requirements of the Rules,
5 An additional entrance to the storage fixed high expansion foam systems are to be in
location, independent of the protected accordance with Chapter II-2, Regulation 9 of the
space, is to be provided. International Convention for the Safety of Life at Sea
b Design Containers and associated pressure (SOLAS) 1974 and Amendments in force.
components are to be designed based upon an b Low Expansion Foam System Low
ambient temperature of 55C (131F). expansion foam systems may be fitted in machinery
c Alarm Means are to be provided for spaces in addition to the required fixed fire
automatically giving audible warning of the release of extinguishing system. In addition to the applicable
fire extinguishing gas into any space to which requirements of the Rules, fixed low expansion foam
personnel normally have access. The alarm is to systems are to be in accordance with Chapter II-2,
operate for at least a 20 second period before the gas Regulation 8 of the International Convention for the
is released. Alarms may be pneumatically (by the Safety of Life at Sea (SOLAS) 1974 and
extinguishing medium or by air) or electrically Amendments in force.
operated.
1 Electric If electrically operated, the 4/9.25.4 Fixed Water Spraying Systems
alarms are to be supplied with power In addition to the applicable requirements of the
from the main and an emergency source Rules, fixed water spraying systems are to be in
of electrical power. accordance with Chapter II-2, Part A, Regulation 10
2 Pneumatic If pneumatically operated of the International Convention for the Safety of Life
by air, the air supply is to be dry and at Sea (SOLAS) 1974 and Amendments in force.
clean and the supply reservoir is to be

PART 4 SECTION 9|5 Fire Extinguishing Systems


TABLE 4/9.1
Classification of Portable and Semiportable Extinguishers

Fire extinguishers are designated by type as follows: A, for fires in combustible materials such as wood; B, for fires
in flammable liquids and greases; C, for fires in electrical equipment.
Fire extinguishers are designated by size where size I is the smallest. Sizes I and II are hand portable extinguishers
and sizes III and V are semiportable.

Classification Water Foam Carbon Dry


liters liters Dioxide Chemical
Type Size (US gallons) (US gallons) kg (lb) kg (lb)

A II 9 (2.5) 9 (2.5) ---- 2.25 (5)1


B II ---- 9 (2.5) 6.8 (15) 4.5 (10)
B III ---- 45 (12) 15.8 (35) 9 (20)
B V ---- 152 (40) 45 (100)2 22.7 (50)2
C I ---- ---- 1.8 (4) 0.9 (2)
C II ---- ---- 6.8 (15) 4.5 (10)

Notes
1 Must be specifically approved as Type A, B, or C extinguisher
2 For outside use, double the amount to be carried.

PART 4 SECTION 9|6 Fire Extinguishing Systems


TABLE 4/9.2
Portable and Semiportable Extinguishers
Space Classification Quantity and Location
5
Safety Areas
Communicating corridors A-II 1 in each main corridor not more than 46m (150 ft.)
apart. (May be located in stairways.)
Pilothouse C-I 2 in vicinity of exit. See Note 4.
Radio room C-II 1 in vicinity of exit. See Note 4.
Accommodations5
Sleeping accommodations A-II 1 in each sleeping accommodation space. (Where
occupied by more than 4 persons.)
Service Spaces5
Galleys B-II or C-II 1 for each 230 m2 (2500 ft2) or fraction thereof for
hazards involved.
Storerooms A-II 1 for each 230 m2 (2500 ft2) or fraction thereof
located in vicinity of exits, either inside or
outside of spaces. See Note 4.
Workshops A-II 1 outside the space in vicinity of exit. See Note 4.
6
Machinery Spaces
Internal combustion or gas turbine- B-II 1 for each 746 kW (1000 hp), but not less than 2
engines and nor more than 6. See Note 1.
B-III 1 required. See Note 3.
Electric motors or generators of the open C-II 1 for each motor or generator unit. See Note 2.
type
Notes
1 When installation is on weather deck or open to atmosphere at all times, one B-II for every three engines is allowable.
2 Small electrical appliances, such as fans, etc., are not to be counted or used as basis for determining number of extinguishers
required.
3 Not required on craft of less than 500 gross tons.
4 Vicinity is intended to mean within 1 m (3 ft).
5 For craft of 500 gross tons and above, at least five extinguishers are to be provided for accommodation spaces, service spaces,
spaces where the ship's radio, main navigating equipment or emergency source of power is located, and locations where the fire
recording or fire control equipment is located.
6 At least one of the required extinguishers is to be located outside each main entrance to the machinery space and the remaining
required extinguishers distributed throughout the engine room located adjacent to high fire risk areas.

TABLE 4/9.3
Fire Pump Minimum Capacity for Craft Less Than 500 Gross Tons

Craft Length Minimum Capacity


Less than 20m (65 ft.) 5.50m3/hr (25 gpm)
20m (65 ft.) or greater but less than 11.0m3/hr (50 gpm)
30.5m (100 ft.)
30.5m (100 ft.) or greater but less 14.3m3/hr (66.6 gpm)
than 61m (200 ft.)
61 m (200 ft) or greater Capacity is to be in accordance
with 4/9.3.2c1

PART 4 SECTION 9|7 Fire Extinguishing Systems


PART 4 SECTION 11

Shipboard Control and Monitoring Systems

4/11.1 General installed under survey by the Surveyor. A symbol


without ! (Maltese cross) signifies that pertinent
4/11.1.1 Scope control and monitoring systems have not been
The installation of machinery and monitoring of the assembled and installed under survey but have
propulsion-machinery space in high speed craft is to be subsequently been surveyed and satisfactorily reported
so arranged that same permits the normal operation of upon by the Surveyor.
the craft with the propulsion-machinery space
a Craft ≥ 500 GT and ≤ 46 m (150 ft) in
unattended. However, as an alternative, consideration
Length
may be given to craft installations having minimum
1 ACCU Symbol Control and monitoring
manning levels from a centralized location in the
systems complying with 4/11.3 will be
propulsion- machinery space, see Note in 4/11.1.2.
distinguished in the Record by the symbol
The requirements contained in this Section are in
ACCU.
addition to those in other Sections of the Guide.
2 ABCU Symbol Control and monitoring
The following Table indicates the applicability of the
systems complying with 4/11.5 will be
relevant requirements:
distinguished in the Record by the symbol
ABCU.
Gross Tonnage (GT)
Note: ACCU or ABCU class symbol may be granted to
Craft’s Length (l) Under 500 500 or over craft of < 500 GT and a length of 20 m (65 ft)• l
• 46 m (150 ft), provided that the applicable
requirements in 4/11.1 through 4/11.5 of this
l < 20 m (65 ft) Will be specially Will be specially Section are met. Likewise, ACC class symbol may
considered considered be granted to craft provided the applicable
requirements in Section 4/11 of the “Rules for
Building and Classing Steel Vessels” are met.
20 m (65 ft)• l • 46 Use 4/11.7 Use 4/11.1 -
m (150 ft) 4/11.5
4/11.1.3 Definitions
The following definitions apply for the purpose of this
l > 46 m (150 ft) Use 4/11.7 Use Section 4/11 Section.
of the “Rules for a Machinery Space See 4/1.17.
Building and b Manned Space Means any space assigned at all
Classing Steel times with crew members needed to locally supervise
Vessels”, as the operation of the specific machinery or system
applicable installed in the space.
c Automatic Control Type of control which is
self-regulating in carrying out ordered instruction
Consideration will be given to craft of special without action by the operator.
design such as surface effect craft, air cushion craft, d Remote Control Control of a device by an
etc., upon submission of manufacturer's specification operator from a distance through mechanical, electrical,
and drawings. electronic, pneumatic, hydraulic, electromagnetic
(radio) or optical means or their combination.
4/11.1.2 Propulsion Class Symbols e Local Control Control by an operator of
Control and monitoring systems for propulsion and machinery through a device located on or adjacent to
monitoring systems of propulsion-machinery space that the controlled machinery.
comply with the relevant requirements, of this Section f Remote Station A permanent installation fitted
will be distinguished in the Record as follows. A with effective control and/or monitoring means and
certificate indicating the degree of automation, located at a distance from the specific machinery.
particulars and operating limitations, if any, will be
issued. A symbol preceded by ! (Maltese cross)
signifies that the installations have been assembled and

PART 4 SECTION 11|1 Shipboard Control and Monitoring Systems


g Centralized Control and Monitoring Station A comprise all required hardware, i.e., microprocessors,
remote station designated as the central location where monitor (video display unit), keyboard, etc., and data
the necessary instrumentation required to maintain the transmission path (data highways).
control and monitoring of the specific machinery is s Non-volatile Memory Memory which does not
fitted, and which is equivalent at least as if the require power to retain the stored data.
machinery were under local supervision. t Computer Monitor (Video Display Unit) A
h Operating Compartment Means the enclosed device where computer information or data is
area from which the navigation and control of the craft displayed.
is exercised. u ABS Type Approval Program Certification
i Instrumentation A monitoring device scheme whereby ABS certifies, at the request of the
including sensing and transmitting component. equipment manufacturer, that the specific equipment
j Monitoring The display and alarming of the conforms to cited standards and to cited ratings which
operational status of a specific machinery/system. ABS has verified by engineering analysis and that an
k Display Systems Display systems are those appropriate quality system is in place to manufacture a
which display operating machinery parameter values product of consistent quality.
such as pressure, temperature, liquid flow, motor v Integrated Propulsion Machinery A
running, etc., or the sequential operation of the system' propulsion machinery having its auxiliaries (fuel oil
process. pumps, cooling water pumps, etc.), necessary for
l Alarm A visual and audible signal of a normal operation driven by the engine, the reduction
predetermined out of limits parameter for the controlled gear or the propulsion shaft.
and/or monitored machinery or system.
m Summary-alarm A common alarm activated by 4/11.1.4 Required Plans and Data
any abnormal condition of the monitored machinery or Plans and data associated with control and monitoring
system. of machinery and systems are to be submitted for
n Safety Systems Systems which provide approval in accordance with 4/1.11 and are to include
automatic actions in response to faults that may the following:
develop too fast to be countered by manual a A list of electrical, pneumatic or hydraulic
intervention. The safety systems are intended to equipment associated with the particular systems. This
operate automatically in case of faults within the is to include manufacturer's name, model number,
machinery plant for the purpose of: material, ratings, degree of protection, permissible
1 Temporarily adjusting the operation of the angles of inclination and location of installation within
machinery to the prevailing conditions (by the craft.
reducing the output of the machinery), or b A list of all major components installed within
2 Restoring the normal operating conditions (by the particular equipment (i.e., control console, etc.) and
starting of standby units), or the data as required in 4/11.1.4a.
3 Protecting the machinery from critical c Certificates or test reports, as appropriate,
conditions by stopping the machinery attesting to the suitability of the particular equipment in
(shutdown). compliance with the environmental criteria set forth in
o Emergency Shutdown Systems Systems 4/11.3.7 and 4/11.3.8, as applicable. For equipment
intended for manual activation in an emergency to stop that have been already certified by the Bureau and
a particular system's function or machinery operation. provided their certification remains valid, the
submission of a copy of pertinent certificate will
p Fail-safe Fail-safe means that upon failure or
suffice. See 4/11.3.8b.
malfunction of a component, sub-system or system, the
output automatically reverts to a predetermined design d Plans showing the location of control and
state of least critical consequence. monitoring stations, controlled equipment and
piping/cable runs, etc.
q Independent As applied to two systems, means
that one system will operate with the failure of any part e Arrangements and details of the control
of the other system including power sources and its consoles and panels including plan views and elevation
supply connection. However, for electrical systems details, installation details and wiring data (rating,
which are not required to have an emergency source of construction standard, insulation type,
power as the standby power source, failure of the armored/unarmored/ shielded/non-shielded,
power source may be excluded from this criteria. temperature rating, flame-retardant properties, etc.).
r Computer-based System A computer-based f A list of all cables connecting equipment
system consists of one or more electronic or optical associated with the systems. This is to include
devices which together with their peripherals and using construction standard, electrical rating, insulation type,
fixed or programmable logic and memories, processes armored/unarmored/ shielded/non-shielded,
input data and output signals for purposes of display, temperature rating, size and connected load's power
alarm, control or storage. The system is understood to consumption requirements.

PART 4 SECTION 11|2 Shipboard Control and Monitoring Systems


g A complete operational description of the 3 Automatic tripping and other safety provisions
control and monitoring systems including a list of of controlled equipment.
alarms and displays and functional sketches or 4 Location of control stations where shutdown,
description of all special valves, actuator, sensors and and control and monitoring power supply
relays. transfer devices are fitted.
h A simplified one-line diagram (electrical and 5 Special remarks, if any.
piping) of all power and control and monitoring
systems. This is to include power supplies, circuit or 4/11.1.5 Tests and Surveys
piping protection ratings and settings, cable or pipe a Installation Tests Control and monitoring
sizes and materials, rating of connected loads, etc. systems are to be subjected to tests witnessed by the
i A schematic diagram of all control, alarm, Surveyor during and after installation onboard as
display and safety systems. outlined in this Section.
j For computer-based systems, the following is to b Periodical Surveys The continuance of
be included: certification is subject to periodic survey of the control
1 Overall description and specification of the and monitoring systems installation as outlined in
systems and equipment. 1/3.19.
2 Block diagrams for the computer hardware
showing interfacing between the work
stations, input/output (I/O) units, local Propulsion Control and Monitoring
controllers, traffic controllers, data highways, Systems and Monitoring Systems for
etc. Propulsion-machinery Space
3 Logic flow chart or ladder diagrams.
4 Description of the alarm system indicating the 4/11.3 Craft Classed with ACCU Symbol
ways it is acknowledged, displayed on the
monitor or mimic display board, etc. 4/11.3.1 General
5 Description of the system redundancy and The requirements in this sub-section are applicable to
back-up equipment, if any. craft fitted with 1) the means to control and monitor the
6 Description of the data communication craft’s propulsion, steering and trim related machinery
protocol including anticipated data process and the means to monitor a periodically unattended
response delays. propulsion-machinery space from the operating
7 Description of the system' security protocol to compartment, and 2) similar controlling an monitoring
prevent unauthorized program changes which
may compromise the integrity of the systems. means, as required in 4/11.3.10, at a suitably located
8 Description of the system with regard to the centralized control and monitoring station. See
degree of independence or redundancy 4/11.1.2a1.
provided for the control systems, The requirements in this sub-section cover the
alarm/display systems and safety systems. operation required for propulsion machinery start-up,
9 Description of system's task priorities. safe sailing during open sea and maneuvering
10 Where applicable, description of UPS conditions, and do not cover operations after anchoring
(uninterruptable power supply) and their or mooring.
capacities including system's power
consumption. 4/11.3.2 Propulsion Control Systems
11 Equipment ratings and environmental a Characteristics Propulsion control systems are
parameters. to be of the fail-safe type and designed to preclude
k Installation methods (electrical, pneumatic and detrimental mechanical or thermal overloads to the
hydraulic). This is to include details of cable or pipe controlled machinery.
runs, separation of cables of different voltage rating b Propulsion Control Capability Under all
and insulating rating, cable tray laying, deck or sailing conditions, including maneuvering, the speed,
bulkhead penetration, prevention of magnetic direction of thrust and, where applicable, the pitch of
interference, etc. See also 4/11.3.7e. the propeller, is to be fully controllable from the remote
l A matrix chart for each of the systems indicating propulsion control station. The remote control is to be
the following, as applicable, upon activation of a given performed, for each independent propeller, by a control
alarm or safety action: device so designed and constructed that its operation
1 Name, device designations and type, and does not require particular attention to the operational
location of alarms. details of the machinery. Additionally, where multiple
2 Preset parameter values, if any. propellers are designed to operate simultaneously, they
may be controlled by one control device.

PART 4 SECTION 11|3 Shipboard Control and Monitoring Systems


c Interlocks Controlled machinery or systems h Critical Speeds of Propulsion Drives
fitted with more than one remote propulsion control Adequate means are to be provided at the remote
station are to be provided with interlocking means to propulsion control station to alert the station operator
preclude simultaneous control or unauthorized transfer of prolonged operation of the propulsion drives within
to associated remote stations not in control. However, barred speed ranges.
propulsion control units interconnected with a specific i Automatic Propulsion Controls Automatic
associated remote control station and which are within propulsion control systems are to be designed to
sight of each other, may be accepted without interlocks. maintain the controlled machinery within pre-set
d Propulsion Starting parameters and to ensure the machinery operation in
1 An alarm is to be provided in the propulsion- the correct sequence and time intervals. Deviation
machinery space and at any propulsion control from these pre-set conditions is to force the sequential
station fitted outside the propulsion-machinery controls to a safe sequence stage that will not be
space to indicate a low level starting condition detrimental to the propulsion machinery and overall
which is to be set at a level to permit further safety of the craft. Additionally, the automatic
main engine starting operations. Where propulsion control system is to be designed and
automatic starting of the propulsion machinery arranged so that a failure in the system is not to
is fitted, the number of consecutive attempts to
compromise the integrity nor the manual operation of
automatically start an engine is to be limited in
order to safeguard sufficient capacity for local the propulsion machinery..
starting from the propulsion-machinery space. j Automatic Shutdown If the control system
See also 4/4.15. automatically shuts down the main propulsion
2 Propulsion machinery control system is to be machinery for any reason, this is to be alarmed at the
designed so that it will automatically inhibit remote propulsion control station(s).
the starting of the propulsion machinery where k Local Propulsion Controls Remotely operated
conditions exist which may damage the propulsion machinery or systems are to be provided
propulsion machinery, i.e., shaft turning gear with effective means of independent controls at or in
engaged, insufficient lubricating oil pressure, the proximity to the propulsion machinery or systems.
etc. Means are to be provided locally to disconnect or
e Transfer of Control Transfer of propulsion override other associated remote stations or disable
controls from a remote control station under operation automatic control, if any.
to other associated remote stations is to be possible by
a request from the receiving station and acceptance by
4/11.3.3 Alarm Systems
the station in operation, or vice versa. However, the
a Characteristics Alarm systems are to be of the
propulsion control station in the propulsion-machinery
space is to be capable of assuming control at all times self-monitoring type and designed so that a fault in the
and to block orders from other associated remote alarm system is to cause it to fail to the alarmed
control stations, if fitted. Considerations will be given condition. Additionally, they are not to react to normal
to cases where, due to the intended craft's service and transient conditions or spurious signals.
operational requirements, it may be necessary for other b Independence Alarm systems are to be
associated stations to have override controls over the independent of control and safety systems except that
remote propulsion control stations in the propulsion- common sensors will be acceptable as permitted in
machinery space. 4/11.3.4c.
All propulsion control stations are to have c Visual and Audible Alarms Alarms are to be
indicators showing which station is in control. both audible and visual and are to be provided at the
f Propulsion Control Orders Propulsion control stations, as required in this Section. Alarms are
machinery orders from the operating compartment to clearly identify the system and service of the faulted
are to be indicated in the centralized control station or machinery or machinery components. Visual alarms
maneuvering platform in the propulsion-machinery are to be displayed in a distinguishable manner such
space, as appropriate. that alarms for similar machinery or systems are
g Failure of Propulsion Control or Failure of grouped together and the colors representing a
Control Transfer In the event of failure of the particular function or condition remain uniform. Visual
propulsion control system or failure of control transfer, alarms are to flash when first activated. Audible alarms
the propulsion units are to continue to operate at the associated with machinery are to be of distinctive tone
last ordered speed and direction of thrust of the from other alarms such as fire-alarm, general alarm, gas
propellers until local control is in operation or control detection, etc. and they are to be of sufficient loudness
power is safely resumed. However, considerations will
to attract the attention of duty personnel; for spaces of
be given to special cases, where due to the intended
craft's propulsion design and operational requirements, unusual high noise levels, a beacon light or similar,
it may be necessary to automatically bring the craft to installed in a conspicuous place is to supplement any of
low speed without hazarding passengers or the craft. the audible alarms in such spaces; however, red light
beacons are only to be used for fire alarms.

PART 4 SECTION 11|4 Shipboard Control and Monitoring Systems


A fault in the visual alarm circuits is not to affect prevent the safety system from operating. However, for
the operation of the audible alarm circuits. For the functions specified in 4/11.1.3n1 and .3m2,
computer-based system, see 4/11.3.5. complete independence of the safety systems from the
d Acknowledgment of Alarms Alarms are to be control and alarm systems is not required.
acknowledged by manually changing the flashing d Activation Each safety action is to be alarmed
display of the incoming alarm to a steady display and at the associated remote station. When both an alarm
by silencing the audible signal; the steady state light and a safety action are required for a specific failure
display is to remain activated until the fault condition is condition, the alarm is to be activated first.
rectified. Alarming of other faults that may occur e Resumption of Operation Machinery that is
during the acknowledgment process is not to be stopped as a result of a safety action, is not to resume
suppressed by such action and is to be alarmed and operation unless it is reset manually.
displayed accordingly. The silencing of the audible f Override of Safety Provisions Remote override
alarm from an associated remote control station is not of safety provisions is not permitted for the following:
to lead automatically to the silencing of the original 1 Shutdown of propulsion gas turbines upon
alarm at the centralized control and monitoring station. failure or loss of the oil lubricating system.
e Disconnection and Resumption of Alarm See 4/3.13.3 of the “Rules for Building and
Functions Alarm circuits may be temporarily disabled Classing Steel Vessels”.
for maintenance purposes or during initial start-up of 2 Shutdown of prime-movers for propulsion and
machinery provided that such action is clearly indicated ship's service diesel-generators upon
at the associated station in control. . However, such activation of overspeed mechanism. See
alarm is to be automatically re-activated after a preset 4/5C2.17 of these Rules and 4/4.11.6 of the
time period. “Rules for Building and Classing Steel
f Summary-alarms In addition to required Vessels”. However, considerations will be
alarms to be fitted at the centralized control and given to specific cases where due to the craft's
monitoring station, visual alarms may be displayed and design and operational requirements, it may be
alarmed at other associated remote control stations as necessary to momentarily override the
summary-alarms. propulsion machinery over the overspeed
g Built-in Testing Alarm systems are to be automatic shutdown.
provided with effective means for testing all audible 3 Shutdown of prime-movers upon failure or
and visual alarms and indicating lamps without loss of oil lubricating system to forced-
disrupting the normal machinery or system operation. lubricated propulsion or ship's service diesel-
Such means are to be fitted in the associated remote generators. See 4/5C2.13.
stations. Remote overrides for other safety provisions as
specified in subject Section 4/11 are to be so arranged
4/11.3.4 Safety Systems that they cannot go unnoticed and their activation and
a General Safety systems are to be provided as condition are to be alarmed and indicated at the
required in this Section. Considerations will be given associated remote station. The override is to be
to the manual activation of safety systems provided that arranged to preclude inadvertent operation and is not to
measures are taken, by the inherent design of the deactivate alarms associated with safety provisions.
system or by suitable arrangements, to retard the The override mechanism to disconnect safety
escalation of the abnormal condition and to alert provisions is to be fitted at the associated remote
personnel to take the appropriate action prior to the station except that same may be fitted at the centralized
developing of a dangerous condition. control and monitoring station instead. Overrides fitted
b Characteristics Safety systems are to be of the at the operating compartment are to be operable only
fail-safe type and are to respond automatically to fault when in the operating compartment control mode.
conditions that may endanger the machinery or safety
of the crew. Unless otherwise required in this Section 4/11.3.5 Computer-based Systems
or specially approved, this automatic action is to cause a General Computer-based systems are to be
the machinery to take the least drastic action first, as designed so that failure of any of the system's
appropriate, by reducing its normal operating output or components will not cause unsafe operation of the
switching to a stand-by machinery and last, by stopping system. Hardware and software serving vital and non-
it, i.e., disrupting source of fuel or power supply, etc. vital systems are to be arranged to give priority to vital
c Independence Safety systems for different systems.
parts of the machinery plant are to be independent of b Independence Control, alarm and safety
each other. The safety system intended for the shutdown system functions are to be arranged such that
functions specified in 4/11.1.3n3 (shutdown) is to be a single failure or malfunction of the electronic
completely independent of the control and alarms computer equipment will not affect more than one of
systems so that a failure in these systems will not these system functions. This is to be achieved by

PART 4 SECTION 11|5 Shipboard Control and Monitoring Systems


dedicated equipment for each of these functions within g Parameters and Program Changes Alteration
a single system, or by the provision of back-up of parameters that may affect the system's performance
equipment, or by other suitable means considered not are to be limited to authorized personnel by means of
less effective. keyswitch, keycard, password or other approved
c Visual Display of Alarms methods. Similarly, computer program or system's
1 Incoming Signals In addition to the configuration changes are to be effected only by
requirements contained in 4/11.3.3, and when authorized personnel.
displayed by way of a computer monitor
(video display unit), alarms are to be 4/11.3.6 Supply, Arrangement and System
presented in an identifiable manner, and when Protection of Control and Monitoring Systems
displayed, alarms are to appear in the a Supply and Arrangement
sequence as the incoming signals are received. 1 General The power distribution to control
Alarming of incoming fault signals are to systems, alarm/display systems (considered as
automatically appear on the screen, to alert the one for the purpose of this requirement) and
on-duty personnel, regardless of whether the safety systems is to be provided with their
computer and monitor (video display unit) are individual circuits so that a fault in one of the
in a mode other than the monitoring mode, systems cannot cause loss of the other
i.e., computing or displaying other system's systems. Their supply status and failure
mimic or schematic diagrams. condition is to be displayed and alarmed at the
2 Unrectified Alarms Alarms associated with associated remote propulsion station.
faults which have not been rectified may be 2 Electrical
displayed in a summarized fashion until all the a Power Supply Two means of power
faults have been dealt with. supply for the circuits in 4/11.3.6a are to
3 Computer Monitor (Video Display Unit) be provided, one of which is to be
Displays on the computer monitor (video connected to the emergency switchboard
display unit) are to be clearly visible under (distribution board). The supply circuits in
ambient lighting conditions Computer 4/11.3.6a1 may be either connected
monitors on the operating compartment are to directly or supplied via a common supply
feeder connected to their respective
be provided with dimmers to control display
switchboards (distribution boards) and are
lighting. Data displayed on computer to be provided with short-circuit protection
monitors are to be readable by the operator at such boards. The power supply status
from the normal operating position. and failure condition of each of the circuits
4 Response Delay The time limit on response in 4/11.3.6a1 is to be monitored on the
delays for safety and alarm displays is not to load side of the feeder's protective device.
exceed 2 seconds. Additionally, control and monitoring
d Memory Capacity and Response Time systems that may require constant power
Computer system's memory is to be of sufficient supply are to be provided with an
capacity to handle the operation of all computer uninterruptable power supply (UPS)
programs (software) as configured in the computer system of sufficient capacity to cover the
system. The time response for processing and required main power transition period.
transmitting data is to be such that undesirable chain of See 4/11.3.5e.
events may not arise as a result of unacceptable data b Power Supply Transfer Transfer of power
delay or response time during the computer system's supply is to be effected automatically. The
power supply transfer device is to be
worst data overload operating condition (multi-tasking
arranged for manual operation.
mode).
c Continuity of Power Provision is to be
e Data Loss and Corruption To preclude the made for automatic starting and
possible loss or corruption of data as a result of power connecting to the main switchboard of a
disruption, program and associated memory data standby generator of sufficient capacity to
considered to be essential for the operation of the permit propulsion and steering and to
specific system is to be stored in non-volatile memory ensure the safety of the craft with
or a volatile memory with a secure uninterruptable automatic re-starting of the essential
power supply (UPS). auxiliaries including, where necessary,
f Power Supply Disruption The system's sequential operations. This standby
software and hardware is to be designed so that upon electric power is to be available in no more
restoration of power supply, after power failure, than 45 seconds. To satisfy the
control and monitoring capabilities can immediately be aforementioned requirement, the operation
available after the pre-established computer control of propulsion machinery and vital services
access (sign-in) procedure has been completed. may be at reduced power.

PART 4 SECTION 11|6 Shipboard Control and Monitoring Systems


3 Hydraulic The hydraulic pumps for control corrosive environments, etc., special consideration
and monitoring systems are to be fitted in corresponding to those of the operating environment
duplicate. The pump suctions are to be from a will be required.
reservoir of sufficient capacity to contain all b Electrical Equipment is to be constructed of
the fluid when drained from the system, robust, durable and flame-retardant material. It is to be
maintain the fluid level at an effective working designed to incorporate the degree of enclosure
height and allow air and foreign matter to protection as required in Table 4/5B.1. Wiring and
separate out. The pump suctions are to be cables are to meet the requirements contained in
sized and positioned to prevent cavitation or 4/5C4.11.4 and 4/5C7, respectively.
starvation of pump. The hydraulic fluid is to Non-current carrying metal parts are to be
be suitable for its intended operation. effectively earthed.
4 Pneumatic Compressed air for control and c Hydraulic Hydraulic pumps, actuators, motors
monitoring systems is to be available from at and accessories are to be suitable for the intended
least two air compressors. The starting air service, compatible with the working fluid and are to be
system may be used as a source of control air. designed to operate safely at full-power conditions. In
The air pressure to the pneumatic control or general, the hydraulic fluid is to be non-flammable or
display system is to be automatically have a flash point above 157C (315F).
maintained at a level required for the d Pneumatic Air compressors, actuators, motors
operation of the installation. Means to prevent and accessories are to be suitable for the intended
the accumulation of moisture is to be service and have working and other parts that will not
provided. Additionally, means are to be be damaged or rendered ineffective by corrosion.
provided to assure the supply, from a safe e Installations
area, of clean, dry and oil-free air to the 1 General The installation of equipment
pneumatic controls or displays. associated with control and monitoring
b System Protection systems is to be carried out taking into
1 Electrical Circuits are to be arranged so that a consideration adverse effects that may be
fault in one circuit will not cause maloperation introduced by their exposure to unintended
or failure on another circuit or system. It is to temperatures, weather, vibration conditions,
be possible to isolate the faulted circuit. falling objects or liquid, electromagnetic
Additionally, systems are to be protected interference, high voltage systems, electric
against accidental reversal of power supply noise, etc. Additionally, the installation is to
polarities, voltage spikes and harmonic facilitate the checking, adjustment and
interference, and in no case is the system's replacement of components, including filters
total harmonic distortion to exceed 5%. and sensing devices, without disrupting the
2 Hydraulic Pipe systems subject to pressure normal operation of the system, as far as
build-up that may exceed the rated pressure of practicable.
the pipe and associated components are to be 2 Ranges in Ambient Temperatures For the
provided with suitable pressure relief devices selection and installation of equipment
fitted on the pump’s discharge side. Each associated with control and monitoring
relief valve is to be capable of relieving not systems, a temperature range of 5C (41F) to
less than full pump flow with a maximum 55C (131F) is to be considered for machinery
pressure rise of not more than 10% of the space, control rooms, accommodations and
relief valve setting. operating compartment. When equipment is
3 Pneumatic The requirements in 4/11.3.6b2 located inside panels or cubicles,
are to be complied with, as applicable. consideration is to be given to the temperature
rise inside those panels due to the dissipation
4/11.3.7 Equipment Construction, Design and of heat from its own components. See also
Installation Note 1 of Table 4/11.1.
a General Equipment associated with remote or Where compliance with the above temperature
automatic control and monitoring systems is to meet ranges cannot be met, consideration will be
compliance with the requirements contained herein. given to the installation of equipment per
Deviation from the environmental requirements such as 4/11.3.7e7.
temperature, humidity and corrosion will be considered 3 Electromagnetic and Conducted Interference
for equipment intended for installation in ambient In general, the installation of equipment
controlled rooms or enclosures. See also 4/11.3.7e2 associated with control and monitoring
and 4/11.3.7e7. Similarly, where equipment is installed systems in areas of unusual electromagnetic
in environments having parameters other than those as sources is to be avoided. Where the values
specified in Table 4/11.1, i.e., cryogenic or highly per Table 4/11.1 may be exceeded,

PART 4 SECTION 11|7 Shipboard Control and Monitoring Systems


appropriate measures are to be implemented to a Testing of Equipment
reduce the effects of electromagnetic and 1 General Testing is to be carried out in
conducted interference. To avoid accordance with Tables 4/11.1 and 4/11.2.
electromagnetic noise caused by circulating Where environmental operating parameters
currents, the conductive shield and cable exceed those specified herein, special
armor is to be earthed only at one end of the arrangements will be considered. See
cable. Description of the preventive measures 4/11.3.7a.
to be followed is to be submitted for review. With the exception of field sensors, all
4 Shielded Cables To avoid possible signal required system's components are to be
interference, cables for control and subjected to these tests. For computer-based
monitoring systems occupying the same cable systems, the equipment to be tested includes
tray, trunk or conduit with power cables are to microprocessors, storage devices, power
be of the shielded type. supply units, signal conditioners,
analog/digital converters, computer monitors
5 Electrical Grounding Control and monitoring
(video display units), keyboards, etc. but it
systems are not to have common earth
excludes printers, data recording or logging
conductors with systems of higher voltage devices not required in this Section.
level. 2 Documentation The manufacturer or
6 Condensation Electrical equipment liable to assembler of the associated equipment is to
be exposed to ambient temperature provide documented evidence indicating that
fluctuations is to be provided with means to the equipment meets the criteria specified in
prevent accumulation of moisture inside the Tables 4/11.1 and 4/11.2. Additionally, for
component's enclosure, i.e., by the provisions computer-based systems, evidence is to be
of space heaters that automatically energizes included to indicate that semiconductor
upon shutdown or disconnection of the devices such as CPU, non-volatile memories,
electrical component. etc., have been subjected to a burn-in test for a
7 Cold Environment Electrical equipment period not less than 72 hours, at an operating
which may be adversely affected by the temperature of 70C (158F), with power
exposure to temperatures lower than those for connected to the device.
which they are designed for, is to be provided 3 Environmental Testing Environmental testing
with suitable heating arrangements so that they on the associated equipment is to be carried
may be readily operated when needed. See out in accordance with the criteria outlined in
4/11.3.7e2. Table 4/11.1. With the exception of the
8 Protection Against Falling Liquids or inclination and vibration tests, all
Leakage of Fluid Medium Electrical environmental tests are to be carried out and
equipment is not to be installed in the same satisfactorily reported upon by the
compartment or cabinet containing equipment manufacturer and/or assembler; such test
or pipes carrying water, oil or steam unless report is to be submitted for review.
effective measures are taken in order to Inclination and vibration tests are to be carried
protect the electrical equipment from possible out in the presence of the Surveyor at the
fluid leakage, i.e., welded connections, manufacturer's or assembler's plant, or at an
physical isolation together with suitable independent testing laboratory in accordance
draining arrangements, etc. with Table 4/11.1.
9 Measuring and Sensing Devices The 4 Performance Testing Performance testing in
installation of measuring and sensing elements accordance with Table 4/11.2 are to be carried
is to permit their easy access for functional out in the presence of the Surveyor at the
testing or replacement. testing plant or after installation of the
10 Marking All units, controllers, actuators, equipment onboard the vesselcraft. Where
displays, terminal strips, cable and test points, deemed necessary by the Surveyor, insulation
etc. are to be clearly and permanently marked. resistance and high voltage tests in accordance
Their systems and system's functions are to be with Table 4/11.1 may be required to be
included so that they can be easily identified carried out.
in associated drawings and instrument lists. b Type Approval of Automatic or Remote
Control and Monitoring Equipment Equipment that
meets the requirements contained in 4/11.3.8a is
4/11.3.8 Equipment/components Qualifications
Equipment associated with the automatic/remote eligible to be certified under the ABS Type Approval
control and monitoring of the propulsion machinery are Program upon formal request by the equipment
to comply with the following requirements: manufacturer. See also 4/11.1.4c.

PART 4 SECTION 11|8 Shipboard Control and Monitoring Systems


4/11.3.9 Station in the Operating Compartment controls, alarms and displays to be fitted at such
Effective control of the propulsion machinery, from the station.
operating compartment, is to be performed with
automatic performance of all associated functions, 4/11.3.11 Automatic Transferring of Vital
including, where necessary, means of preventing Auxiliary Pumps
overload of the propulsion machinery. The required The means for the automatic starting and transferring of
automatic control means to operate the propulsion required standby vital auxiliary pumps associated with
machinery are to be capable of meeting load demands propulsion are to be provided. The automatic starting
from standby to full system rated load under all and transferring of vital auxiliary pumps is to be
operating conditions, without the need for manual alarmed at the centralized control and monitoring
adjustment or manipulation. station. The aforementioned is applicable to the
The operating compartment control station is to following machinery/systems:
include the controls, displays and alarms as required in a Propulsion Machinery
Table 4/11.3. In addition, the following controls b Electrical Power Generating Machinery
arranged for easy reach of the crew member for use in c Controllable Pitch Propellers (C.P.P)
an emergency are to be provided at the operating d Sea Water Main Circulating System
compartment: e Propulsion-machinery Space Bilge System
a Stopping the main propulsion and auxiliary f Fuel Oil Transfer or Service System This is
machinery. The stopping device for the main applicable to pumps associated with settling and daily
propulsion is to be independent of the navigating service tanks.
bridge control system.
b Disconnecting all electrical power sources 4/11.3.12 Propulsion Gas Turbines
from the normal power distribution system (the The centralized control and monitoring station is to be
operating control is be so arranged to preclude its provided with the alarms and displays as listed in
inadvertent or careless operation). Table 4/11.6.
c Stopping the machinery-space ventilation
blowers and closing of openings as per 4/9.5.1. 4/11.3.13 Propulsion Diesel Engines
d Stopping all fuel-oil pumps and forced-draft a Lubricating Oil In the event of loss of
blowers. lubricating oil, there is to be an automatic shutdown of
e If provided, closing machinery-space the main engine.
skylights. b Overspeed An overspeed condition is to cause
f Closing machinery-space watertight and fire- the automatic shutdown of the main engine.
resistant doors. c Controls and Instrumentation The centralized
g Closing propulsion-machinery space fuel oil control and monitoring station is to be provided with
tanks suction valves. (See 4/9.5.5). the safety provisions, alarms and displays as listed in
h Starting the emergency generator or Table 4/11.5 .
connecting a source of emergency power, unless
automatic operation is provided. 4/11.3.14 Electric Propulsion
i Means for starting any one of the fire pumps For electric propulsion driven craft, in order to prevent
(inclusive of the one located outside the propulsion- nuisance tripping of the main generator circuit
machinery space) including associated valves necessary breakers, a power management system is to be
to deliver required capacity to the fire main. provided and arranged so that when the power
j Releasing of the fire-fighting media for the requirement for the propulsion motors exceeds the on-
propulsion-machinery space This release is to be line generating capacity, the power management system
manual and not initiated automatically by signals from is to take, automatically, a corrective action, such as
the fire-detecting system. reduction of power, shedding of non-essential loads,
etc. The centralized control and monitoring station is
4/11.3.10 Centralized Control and Monitoring to be provided with the alarms and displays as listed in
Station Table 4/11.7.
The centralized control and monitoring station is to
include adequate controls, displays and alarms needed 4/11.3.15 Electrical Power Generating Machinery
to maintain normal and safe operation of the propulsion The centralized control and monitoring station is to be
machinery and monitor associated ship' service provided with the alarms and displays as listed in Table
systems, electrical power generating machinery, and 4/11.8.
propulsion-machinery space. The installed control and
monitoring system is to provide the same degree of
control as if the propulsion-machinery space was
manned. See Tables 4/11.4 through 4.11.8 for required

PART 4 SECTION 11|9 Shipboard Control and Monitoring Systems


4/11.3.16 Fuel Oil Settling and Daily Service 2 Drip trays for collecting oil as required in
Tanks 4/6.7.13 are to be of suitable height and
a General Low level conditions of fuel oil provided with suitable drainage to a collecting
settling and daily service tanks are to be alarmed at the tank incorporating a high level alarm audible
operating compartment and centralized control and at the centralized control and monitoring
monitoring station; additionally, adequate interlock station.
means to prevent tank over-pressurization or overflow 3 Where heaters are provided in fuel systems,
spillages are to be provided. the required alarms in 4/6.49.3 are to be
b Automatic Filling The fuel oil settling or daily located at the centralized control and
service tanks are to be of a capacity sufficient for at monitoring station.
least 8 hours operation at normal power. The 4 Fuel oil heaters, purifiers, pumps, and filters
arrangements are to include high level alarm together are to be shielded, or grouped in a special
with automatic filling-pump shutdown and automatic room or location ventilated by suction.
pump start-up at a predetermined low level, in addition c Fire Detection and Alarm The propulsion-
to the arrangements per 4/11.3.16a. machinery space is to be provided with a fixed fire
c Heating Arrangements See 4/11.3.18b3. detection and alarm system complying with 7.7.1
through 7.7.3 of the IMO International Code of Safety
4/11.3.17 Propulsion and Associated Machinery for High-Speed Craft. This fixed fire detection and
Start-up alarm system may be combined with other fire
Starting of the propulsion and associated machinery or detection and alarm system required on board the craft.
preparing the engines for sea may be performed d Fire Alarm Call Points Manually operated fire
manually, but if done automatically this is to be alarm call points are to be provided in, and in the
programmed that the propulsion machinery cannot be passageways leading to, the propulsion-machinery
started until all engine auxiliaries are functioning space.
correctly.
4/11.3.19 Monitoring Station in Engineer's
4/11.3.18 Arrangement and Monitoring of Accommodation
Machinery Space The following is applicable to craft fitted with
a Bilges engineer’s accommodations, if provided.
1 General The propulsion-machinery space is a General At least one alarm monitoring station
to be provided with a bilge water-level is to be provided in the engineer's public spaces. Each
system to detect excessive water influx or rise such station is to be provided with alarms for fire, high
in the propulsion-machinery space bilges, at bilge-water level in the propulsion-machinery space,
the various angles of craft's heel and trim; the and summary-alarms for the propulsion and its
bilge wells are to be large enough to associated machinery Any of the alarm conditions as
accommodate the normal drainage. Excessive listed in Tables 4/11.5 through 4/11.8, as applicable,
water influx or rise in the bilge wells is to be are to activate the specific machinery summary-alarm.
alarmed at the centralized control and Additionally, alarm monitoring stations through a
monitoring station. See also Tables 4/11.3 selector switch are to be provided in each individual
and 4/11.4 for alarms and displays. engineer's stateroom and arranged so that at least one
2 Excessive Automatic Starting of Bilge Pumps alarm monitoring station is active at all times.
Means are to be provided to indicate, at the Selective switching is not to be provided for the fire
centralized control and monitoring station, alarms. The fire alarm is to be separate and distinct
when the influx of liquid is greater than the from the alarms of any other systems. Fire, high bilge-
pump capacity or when the pump is operating water level and the specific machinery summary-alarms
more frequently than would normally be are to be audible in the engineer's public spaces and
expected. Additionally, special attention is to staterooms until manually silenced at the centralized
be given to oil pollution prevention control and monitoring station in the propulsion-
requirements. machinery space.
b Fire Prevention To minimize the outbreak of b Alternative Arrangement The arrangements in
fire, the following is to be provided: 4/11.3.19a may be modified to permit the audible
1 In high pressure fuel-oil piping (see 4/4.7.3 of machinery summary-alarm and high bilge water level
these Rules and 4/3.25.3 of the “Rules for alarm to be silenced locally at the alarm monitoring
Building and Classing Steel Vessels”), an oil stations in the engineer's public spaces and staterooms
leakage condition is to be alarmed at the provided the associated visual alarm is not
operating compartment and at the centralized extinguished. Also, the arrangements are to be such
control and monitoring station. that if the audible alarm is not also silenced manually at
the centralized control and monitoring station in a

PART 4 SECTION 11|10 Shipboard Control and Monitoring Systems


reasonable period of time, the system is to activate the electric power is to be simulated with the main engine
engineer's alarm audible in the engineer's running.
accommodations. The means for silencing locally at f Independent Manual Control Independent
the alarm monitoring stations is not to be provided for manual control of the propulsion machinery is to be
fire alarms. demonstrated. This is to include demonstration of
independent manual control through the full
4/11.3.20 Communications maneuvering range and transfer from automatic control.
For communication systems associated with propulsion
control stations, the requirements in 4/5A8.5.1 are 4/11.5 Craft Classed with ABCU Symbol
applicable and is to include the engineer's
4/11.5.1 General
accommodations area, if provided.
The requirements in this sub-section apply to craft
capable of operating as ACCU classed craft but
4/11.3.21 Sea Trials
because of their compact propulsion-machinery space
The ability to effectively control the propulsion from
design are not fitted with the means to control the
the remote propulsion control station is to be
propulsion and its associated machinery from a
demonstrated to the satisfaction of the Surveyor during
centralized location within the propulsion-machinery
sea trials or at dockside. These trials are to include
space. Except as noted herein, the requirements in
propulsion control transfer, propulsion starting,
4/11.1 through 4/11.3, as applicable, are to be
verification of propulsion control responses, propulsion
complied with.
control power failure and actuation of propulsion
emergency stop device. In addition, effective operation
4/11.5.2 Station in the Operating Compartment
of the following is to be demonstrated to the
Controls, alarms and displays as listed in 4/11.3.9 are
satisfaction of the Surveyor. With the exception of
to be provided on the station in the operating
4/11.3.21e, it is recommended that these
compartment. See Table 4/11.3. For craft having non-
demonstrations or tests be carried out before sea trials
integrated propulsion machinery, the means for
and are to include simulated failures so that proper
starting, stopping and transferring vital auxiliary pumps
corrective actions may be carried out and witnessed by
(see 4/11.3.11) are to be fitted at the station in the
the Surveyor.
operating compartment and may also be fitted in the
a Control and Monitoring System for Propulsion
centralized station. See 4/11.1.3v for definition of
Machinery and Electrical Power Generating
integrated propulsion machinery.
Machinery In addition to the verification of required
control responses, alarms and displays, this
4/11.5.3 Centralized Monitoring Station
demonstration is to include the automatic transferring
The requirements in 4/11.3.10 are applicable except
of the required standby vital auxiliary pumps
that the centralized station need not be provided with
b Local Control Local control of the propulsion
propulsion controls but is to include displays and
machinery is to be demonstrated.
alarms needed for the monitoring of the propulsion
c Fire Control and Alarm System In addition to
machinery and associated ship' service systems,
the verification of required detectors, displays and call
electrical power generating machinery, and monitoring
points and where the fire main is not maintained
of propulsion-machinery space. The monitoring system
pressurized, it is to be demonstrated that at least one of
is to provide the same degree of equivalency as if the
the main fire pumps can be started from the station in
propulsion-machinery space was manned. See Tables
the operating compartment.
4/11.4 through 4.11.8 for required alarms and displays
d Bilge Detection System Automatic starting of
to be fitted at this station.
the propulsion-machinery space bilge pumps is to be
demonstrated.
4/11.5.4 Communications
e Operational Test of Propulsion Machinery
Communications as required in 4/11.3.20 is also to
After the propulsion machinery has been running for at
include the centralized monitoring station in the
least 2 hours, the ability to control the machinery
propulsion-machinery space.
functions correctly for all loads and engine maneuvers
without any manual intervention in the propulsion-
4/11.5.5 Sea Trials
machinery space is to be demonstrated for an additional
In addition to the trials per 4/11.3.21, successful
period of 4 hours. Propulsion machinery or engine
operation of the propulsion machinery is to be
response to throttle control demands is to be tested
demonstrated with the propulsion-machinery space
during the trials and after final adjustments to
unattended for a period of at least 12 hours.
demonstrate that no part of the plant or engine is
jeopardized by the rate at which the throttle is moved
from one extreme position to the other. The loss of

PART 4 SECTION 11|11 Shipboard Control and Monitoring Systems


4/11.7 Craft Less Than 500 GT Having a Length 4/11.7.5 Alarms
Equal or Greater Than 20 m (65 ft) The alarm system is to be able to indicate more than
one fault at the same time and be so arranged that
4/11.7.1 General acceptance of one fault is not to inhibit another alarm.
The requirements contained in this sub-section are Audible alarms are to be maintained until they are
intended for craft less than 500 GT having a length acknowledged, and visual indication is to remain until
greater than 20 m (65 ft). The installation of machinery the fault is corrected.
and monitoring of the propulsion-machinery space in
such craft is to be so arranged that permits the normal 4/11.7.6 Safety System
operation of the craft with the propulsion-machinery Safety systems are to be of the fail-safe type and are to
space unattended. Craft having a length equal or less respond automatically to fault conditions that may
than 20 m (65 ft) will be specially considered. endanger the machinery or safety of the crew. This
automatic action is to cause the machinery to take the
Note: ACCU or ABCU class symbol may be granted to craft of <
least drastic action first, as appropriate, by reducing its
500 GT and a length of 20 m (65 ft)• l • 46 m (150 ft),
provided that the applicable requirements in 4/11.1 normal operating output or switching to a stand-by
through 4/11.5 of this Section are met. machinery and last, by stopping it, i.e., disrupting
source of fuel or power supply, etc. However, the
4/11.7.2 Definitions propulsion machinery is to automatically shutdown
See 4/11.1.3. upon a loss of lubricating oil or an overspeed
condition, and such conditions are to be alarmed.
4/11.7.3 Plans to be Submitted Where arrangements for overriding the shut-down of
Plans and specifications are to be submitted in the main propelling machinery are fitted, these are to be
accordance with 4/1.11 for approval and are to include such as to preclude inadvertent activation. Visual
the following information. means shall be provided to show whether or not it has
a Machinery arrangement plans showing been activated.
location of control stations in relation to controlled
units; 4/11.7.7 Propulsion
b Arrangements and details of control consoles The requirements in 4/11.3.2b, .2e, .2f, .2g and .2h are
including front views, installation arrangements applicable. Additionally, it is to be possible to control
together with schematic diagrams for all power, control the propelling machinery locally in the case of failure
and monitoring systems including their functions; and a in any part of the control systems.
list of alarms/displays as required in 4/11.7.8c.
c Type and size of all electrical cables and 4/11.7.8 Propulsion-machinery Spaces
wiring associated with the control systems including a Fire Protection
voltage rating, service voltage and currents together 1 Fire Prevention
with overload and short-circuit protection; a Piping for high pressure fuel injection and
d Description of all alarm and emergency return piping on main and auxiliary engines
tripping arrangements; functional sketches or is to be effectively shielded and secured to
description of all special valves, actuators, sensors and prevent fuel or fuel mist from reaching a
relays; source of ignition on the engine or its
e Schematic plans and supporting data of fire- surroundings. Leakages from such piping
protection and extinguishing systems, including fire- are to be collected in a suitable drain tank
detection and alarm systems and bilge high water provided with high level alarm audible at the
alarms, operating compartment.
f Schematic plans of hydraulic or pneumatic b Drip trays for collecting fuel and lubricating
control systems. oil are to be fitted below pumps, heaters,
burners, tanks not forming part of the craft’s
4/11.7.4 Electrical Cables and Console Wiring structure, etc., with connections to a suitable
drain tank with high level alarm audible at
In general, cables are to be used external to the
the operating compartment.
consoles and they are to be of the marine type in
c Where daily service fuel oil tanks are filled
accordance with the applicable parts of Section 4/5. automatically or by remote control, means
Cables in accordance with other standards which are are to be provided to prevent overflow
not less effective will be considered. Cables and spillages. Similar consideration is to be
console wiring for control and monitoring are to be of given to other equipment which treat
the flame-retarding type and are to be stranded except flammable liquids automatically (e.g., fuel
that solid conductors may be used in low-energy circuit oil purifiers), which whenever practicable
where they are properly supported and not subject to shall be installed in special space reserved
undue vibration or movements. for purifiers and their heaters.

PART 4 SECTION 11|12 Shipboard Control and Monitoring Systems


d Where fuel oil daily service tanks or settling detection system is to initiate an audible and visual
tanks are fitted with heating arrangements, a alarm on the operating compartment.
high temperature alarm, audible at the c Operating Compartment In addition to
operating compartment, is to be provided if other instrumentation which may be required for the
the flashpoint of the fuel oil can be satisfactory operation of the propulsion machinery and
exceeded. navigation of the craft, the following controls, alarms
2 Fire Detection A fire detection system is to and displays are to be provided at theoperating
be provided for the machinery spaces. compartment in accordance with Table 1.
b Protection Against Flooding Bilges in
machinery spaces are to be provided with a high level
alarm in such a way that the accumulation of liquids is
detected at normal angles of trim and heel. The

PART 4 SECTION 11|13 Shipboard Control and Monitoring Systems


TABLE 1
Displays and Alarms to be Fitted at the Operating Compartment
(Applicable to craft complying with 4/11.7)

Items Display Alarm

1 Propeller Speed RPM


2 Propeller Ahead
3 Direction or Astern
4 Pitch Pitch
5 Generator voltage Volt1
6 Generator current Amps1

The following alarms giving distinctive indication of conditions requiring immediate action and in full view of
the crew
7 Main engines Overspeed
8 Normal electrical supply Loss
9 Control power Available Failure
10 Any permanently installed nickel-cadmium battery associated with systems for Thermal
the control and monitor of the craft’s propulsion, steering and trim related runaway
machinery and propulsion-machinery space
11 Activation of a fire-detection system Light Fire
12 Bilge level High

With the exception of items 15 and 21, the following alarms are to be distinct from those referred in items
7 through 12 and are to indicate conditions requiring actions to prevent degradation to an unsafe condition
13 L.O. Pressure to main engine & reduction gear Pressure Low
14 Engine coolant Temperature High
15 Starting air (if applicable) pressure Low
16 Normal power supply to the powered directional or trim control devices Failure
17 Compass system Failure
18 Side, masthead or stern navigation lights Extinction
19 Fuel oil tank level Low
20 Oil collecting tank(see 4/11.7.8a1b) High or
Overflow
21 Fuel oil day tank heater temperature (see 4/11.7.8a1d) High
22 Level of contents of any fluid reservoir the contents of which are essential for Low
normal craft operation
23 High pressure fuel line (see 4/11.7.8a1a) Leakage
24 Any ventilation fan installed for ventilating spaces in which inflammable Failure
vapours may accumulate
25 Any automatic bilge pump Operation

Emergency Controls to be Fitted at the Operating Compartment and Arranged for Easy Reach of the Crew Members

Items Provision of
Device
26 Stops for main propulsion and auxiliary machinery x
26 Means to disconnect electrical power sources from the normal power distribution system x
27 Stops for the machinery-space ventilation blowers and means for closing of openings as per 4/9.5.1 x
29 Stops for all fuel-oil pumps and forced-draft blowers x
30 Means for starting any one of the fire pumps (inclusive of the one located outside the propulsion- x
machinery space) including associated valves necessary to deliver required capacity to the fire main
31 Releasing of the fire-fighting media for the propulsion-machinery space This release is to be manual x
and not initiated automatically by signals from the fire-detecting system.

Note:
1 As an alternative, these displays may be provided locally.

PART 4 SECTION 11|14 Shipboard Control and Monitoring Systems


TABLE 4/11.1
Environmental Tests for Propulsion Control and Monitoring Equipment

No TEST PROCEDURE ACCORDING TO TEST PARAMETERS OTHER INFORMATION


[See note 4]

1 Visual - - - Conformance to drawings, design data;


Inspection - quality of workmanship and construction.

The equipment specification - Standard atmosphere conditions. - Confirmation that operation is in


- Temperature: 25 C (77 F) ± 10 C (18 F) accordance with the requirements specified
- Relative humidity: 60% ± 30%. for particular automatic systems or
2 Conditional - Air pressure: .96 bar (.98 Kgf/cm 2., equipment;
13.92 Psi) ± .10 bar (.10 Kgf/ cm 2, 1.45 - checking of self-monitoring features;
Psi) - checking of specified protection against
an access to the memory and effects of
unerroneous use of control elements in the
case of computer systems.

IEC Publication 68-2-2 (1974), Temperature: 55 C (131 F) ± 2 C (3.6 F) - Equipment operating during conditioning
Amendment No. 1 (1993) and No. 2 (1994) Duration: 16 hours and testing;
- Test Bb - for non-heat dissipating or - functional test during the last hour of the
equipment. Temperature: 70 C (158 F) ± 2 C (3.6 F) test temperature;
Duration: 2 hours [See note 1] - functional test after recovery.
3 Dry heat

IEC Publication 68-2-2 (1974), Temperature: 55 C (131 F) ± 2 C (3.6 F) - Equipment operating during conditioning
Amendment No. 1 (1993) and No. 2 (1994) Duration: 16 hours [See note 1] and testing with cooling system on, if
- Test Bd - for heat dissipating equipment. or provided;
Temperature: 70 C (158 F) ± 2 C (3.6 F) - functional test during the last hour at the
Duration: 2 hours test temperature;
- functional test after recovery.

- Measurement of insulation resistance be


IEC Publication 68-2-30 (1980), Temperature: 55 C (131 F) fore test;
Amendment No. 1 (1985) - Test Db. Humidity: 95% - equipment operating during complete first
Duration: 2 cycles (12 + 12 hours cycle) cycle and switched off during second cycle
except for functional test;
- functional test during the first 2 hours of
4 Damp heat the first cycle at the test temperature and
during the last 2 hours of the second cycle
at the test temperature;
- recovery at standard atmosphere condit-
ions;
- insulation resistance measurements and
conditional test.

IEC Publication 68-2-1 (1990), Temperature: 5 C (41 F) ± 3 C (5.4 F) - Initial measurement of insulation
Amendment No. 1 (1993) and No. 2 (1994) Duration: 2 hours resistance;
- Test Ab - for non-heat dissipating or - equipment not operating during condition
equipment Temperature:-25 C (-13 F) ± 3 C (5.4 F) ing and testing except for functional test;
Duration: 2 hours [See note 2] - functional test during last hour at the test
temperature;
5 Cold - insulation resistance measurement and the
functional test after recovery.

IEC Publication 68-2-1 (1990), Temperature: 5 C (41 F) ± 3 C (5.4 F)


Amendment No. 1 (1993) and No. 2 (1994) Duration: 2 hours [See note 2]
- Test Ad - for heat dissipating equipment. or
Temperature:-25 C (-13 F) ± 3 C (5.4 F)
Duration: 2 hours

( Cont-)

PART 4 SECTION 11|15 Shipboard Control and Monitoring Systems


TABLE 4/11.1 )
Environmental Tests for Propulsion Control and Monitoring Equipment

No TEST PROCEDURE ACCORDING TO TEST PARAMETERS OTHER INFORMATION


[See note 4]

IEC Publication 68-2-52 (1984) Test Kb Four spraying periods with a storage of 7 - Initial measurement of insulation
days after each. resistance and initial functional test.
- equipment not operating during
conditioning of the test specimen;
6 Salt mist functional test on the 7th day of storage
period;
insulation resistance measurement and
operational; test after recovery.
[See note 3]

Rated Test Minimum - Insulation resistance is to be carried out


supply voltage insulation before and after: damp heat test , cold test
voltage resistance and salt mist test;
7 Insulation - Before After - between all circuits and earth;
resistance (V) (V) (M•) (M•) - on the supply terminals, where
Un •65 2*Un 10 1,0 appropriate.
(min. 24V) - Un is the rated (nominal) voltage.
Un >65 500 100 10

Rated voltage Un Test voltage - Separate circuits are to be tested against


(A.C. voltage each other and all circuits connected with
50 or 60 Hz) each other tested against earth;
8 High voltage - (V) (V) - printed circuits with electronic
up to 65 2* Un+500 components may be removed during the
66 to 250 1500 test;
251 to 500 2000 - period of application of the test voltage: 1
minute

IEC Publication 801-2 (1991). Test voltage: 8KV according to level 3 - To simulate electrostatic discharge as may
severity standard. occur when persons touch the appliance;
- the test is to be confined to the points and
surfaces that can normally be reached by
the operator;
9 Electrostatic - the equipment is to operate during testing;
discharge - as a result of the test neither permanent or
transient effects nor damage to the
equipment are allowed.

IEC Publication 801-3 (1984). Frequency range: 30 kHz to 500 MHz - To simulate electromagnetic fields
Field strength: 10 V/m radiated by different transmitter;
10 Radiated - according to severity level 3. - the test is to be confined to the appliance
electro- exposed to direct radiation by transmitters
magnetic field at their place of installation;
- as a result of the test neither permanent or
transient effects nor damage to the
equipment are allowed.

IEC Publication 801-4 (1988) Fast transient Test voltage (± 10%) : - To simulate interference by electric arcs
(burst) 2 kV on I/O signal data and control lines generated when actuating electrical
2kV on power supply contacts;
11 Conducted - interference effect occurring on the power
interference supply, as well as at the external wiring of
the test specimen.
- as a result of the test neither permanent or
transient effects nor damage to the
equipment are allowed.

( Cont-)

PART 4 SECTION 11|16 Shipboard Control and Monitoring Systems


TABLE 4/11.1
Environmental Tests for Propulsion Control and Monitoring Equipment
(Applicable to ACCU or ABCU Craft)

No TEST PROCEDURE ACCORDING TO TEST PARAMETERS OTHER INFORMATION


[See note 4]

- To simulate interference generated for


IEC Publication 801-5 (Draft 1990) Surge Test voltage: instance, by switching on or off high-
voltage immunity 1,0 kV differential mode; power inductive consumers;
2,0 kV common mode - the test is to be carried out at the power
Rise time: 1,2 µseconds supply;
Surge time (50 % value): 50 µseconds - as a result of the test neither permanent or
according to severity level 3. transient effects nor damage to the
Test duration: equipment are allowed.
not less than 3 min. positive pulse;
11 Conducted not less than 3 min. negative pulse;
interference Repetition rate: 6 pulses/min.

IEC Publication 1000-4-6 Conducted radio Testing signals: - To simulate electromagnetic fields
frequencies interference 1.0 Veff the range between 10 kHz and 50 coupled as high frequency into the test
kHz specimen via the connecting lines;
Modulation: 30% - as a result of the test neither permanent or
Modulation frequency: 1 kHz transient effects nor damage to the
(Provisional values applicable to equipment are allowed.
navigational instrument)

IEC Publication 68-2-6 (1995) Test Fc 2.0 (+3/-0) Hz to 13.2 Hz - amplitude ± 1 - Duration in case of no resonance
mm (.039 in). condition 90 minutes at 30 Hz;
13.2 Hz to 100 Hz- acceleration 0.7 g. - duration at each resonance frequency at
For severe vibration conditions such as, e.g. which Q•2 is recorded- 90 minutes;
12 Vibration on diesel engines, air compressors, etc.: - during the vibration test, operational
2.0 Hz to 25 Hz- amplitude ± 1.6 mm conditions are to be demonstrated;
(.0630 in). - test to be carried out in three mutually
25.0 Hz to 100 Hz- acceleration 4.0 g. perpendicular planes;
- it is recommended that Q does not exceed
5.

Static 22.5° a) Inclined at an angle of at least 22.5° to


the vertical
b) Inclined at least 22.5° on the other side
of the vertical and in the same plane as in
(a),
c) inclined at an angle of at least 22.5° to
the vertical and in a plane at right angle to
that used in (a),
d) Inclined to at least 22.5° on the other
side of the vertical and in the same plane as
13 Inclination in (c).
Note: The period of testing in each position
should be sufficient to fully evaluate the
behavior of the equipment.

Dynamic 22.5° Using the direction defined in a) to d)


above, the equipment is to be rolled to an
angle of 22.5° each side of the vertical with
a period of 10 seconds.
The test in each direction is to be carried
out for not less than 15 minutes.

Notes:

1) Dry heat at 70 C (158 F) is to be carried out for equipment located in a non-air conditioned space. See also 4/11.3.7e2.
2) For equipment installed in non-weather protected locations or cold locations test is to be carried out at-25 C (-13 F).See also 4/11.3.7e2 and
4/11.3.7e7.
3) Salt mist test is to be carried out for equipment installed in weather exposed areas.
4) Alternative equivalent testing procedures may be accepted provided the requirements in the other columns are complied with.
.

PART 4 SECTION 11|17 Shipboard Control and Monitoring Systems


TABLE 4/11.2
Performance Tests for Propulsion Control and Monitoring Equipment
(Applicable to ACCU or ABCU Craft)

No TEST PROCEDURE ACC. TO TEST PARAMETERS OTHER INFORMATION


[See note 1]

1 Visual - - - Conformance to drawings, design data,


inspection - quality of workmanship and
construction.

- 3 interruptions during 5 minutes; - Verification of the specified action of


2 Power - - switching-off time 30 seconds each case. the equipment on loss and restoration of
supply supply in accordance with the system
failure design.

Combination Voltage Frequency


variation variation
permanent permanent
(%) (%)

1 +10 +5
2 +10 -5
3 -10 -5
4 -10 +5
3 Power - -
supply Combination Voltage Frequency
(electric) transient transient
1.5s 5s
(%) (%)

5 +20 +10
6 -20 -10

Electric battery supply:


+30% to -25% for equipment connected
to battery during charging;
+20% to -25% for equipment not
connected to the battery during charging.

Power Pressure: ± 20%.


supply Duration: 15 minutes. -
(pneumatic
and
hydraulic)

Notes:
1) The conditional test parameters per Table 4/11.1 are applicable.

PART 4 SECTION 11|18 Shipboard Control and Monitoring Systems


TABLE 4/11.3
Control Station in the Operating Compartment
(Applicable to ACCU or ABCU Classed Craft) 8)

Provisions
Item Alarm Display of Device Remarks
1), 9) on Station
1)

A1 Failure or malfunctioning of system x 2), 10)


A2 Failure, supply x Main/Standby Automatic transfer 2), 10)
Control A3 Control station in operation Station
and A4 Control transfer switch x
Monitoring System A5 Alarm, disabled (override) Disabled 4)
A6 Safety, activation x 3),10)
A7 Safety disabled x Disabled 4), 10)
Main Power B1 Normal electrical supply, loss x
Source
Nickel-cadmium C1 Any permanently installed nickel-cadmium x Associated with systems for the control and
Battery battery, thermal runaway monitor of the craft’s propulsion, steering and
trim related machinery and propulsion-
machinery space
Supply to Steering D1 Normal power supply to the powered x 11)
& Trim System directional or trim control devices, failure
Compass E1 Compass system, failure x 11)
Navigation Lights F1 Side, masthead or stern navigation lights, x 11)
extinction
Controllable Pitch G1 Start/stop switch for CPP hydraulic motor x If provided
Propeller (CPP) G2 CPP hydraulic motor running Running If provided
G3 Automatic starting of required standby x If provided
pump
H1 Remote controls x For each propelling unit and all units, as
applicable
H2 Propeller shaft, speed Speed
Propulsion, H3 Propeller shaft, direction Direction
General H4 Propeller, pitch Pitch For controllable-pitch propeller
H5 Prime movers, prolonged operation within x Visual display may be acceptable
critical speed range
H6 Main engine, overspeed x
I1 Starting medium, pressure or level, low x Pressure or 5)
Propulsion Level
Starting I2 Hazardous condition present x See 4/11.3.2d2
I3 Start/stop switch for starting system x Not required for non-reversing engines
Electric Propulsion J1 Propulsion generator load-share overload x See 4/5C2.19.3 &.21.3 and 4/11.3.14
Summary-alarms K1 Propulsion and associated machinery, x 6), 7), 11)
failure
Vital Auxiliary L1 Start/stop and transfer switches x For ABCU craft having non-integrated
Pumps propulsion machinery; it may be combined
with item T1 below
M1 Level, tank, low x See 4/11.3.16a 11)
FO Settling
and M2 Level, tank, high x See 4/11.3.16b 11)
Daily Service Tanks M3 Fuel oil tank, heater temperature, high x See 4/11.3.18b3
FO & LO N1 Tank, level high or overflow x See 4/11.3.18b2 11)
Collect. Tank
High Pressure O1 Leakage x See 4/11.3.18b1 11)
FO System
Essential P1 Level of contents of any fluid reservoir the x 11)
Fluid contents of which are essential for normal
Reservoirs craft operation, low
( Cont-)

PART 4 SECTION 11|19 Shipboard Control and Monitoring Systems


TABLE 4/11.3
Control Station in the Operating Compartment
(Applicable to ACCU or ABCU Classed Craft) 8)

Provisions
Item Alarm Display of Device Remarks
1), 9) on Station
1)

Q1 Any ventilation fan installed for ventilating x 11)


Ventilation System spaces in which inflammable vapours may
accumulate, failure
Fire in Machinery R1 Fire control x Fire x See 4/11.3.18c 7)
Space
Bilges in Mach. S1 Any automatic bilge pump, operation x 11)
Space S1 Level, bilges, high x See 4/11.3.18a1 7)
Emergency T1 To be arranged for easy reach of the crew x See 4/11.3.9
Controls members

Notes:

1) Required actuation device or alarm is denoted by a (x).


2) For each system: control systems, alarm/display systems and safety systems. See 4/11.3.6a1 and 4/11.3.6a2.
3) Actuation of propulsion safeties is to either reduce output or shutdown the propulsion machinery as required. See also 4/11.3.4, 4/11.3.4f and
Tables 4/11.5 through 4/11.8.
4) Deactivation means are to be arranged so that such action cannot be done inadvertently. Alternative means to indicate disabling of safety actions or
alarms
will be considered.
5) This alarm is also to be provided in the machinery space.
6) This summary-alarm is to be activated by any of the alarm conditions as listed in Tables 4/11.5 through 4/11.8. 4/11.3.19.
7) These alarms are also to be alarmed at the engineer's accommodations, see 4/11.3.19.
8) Except for the controls prescribed in item T1 of this Table, the listed instrumentation is also applicable to other remote propulsion control stations
iinstalled outside the operating compartment.
9) Provided the audible alarms re-activate automatically after a preset time, audible alarms may be by-passed or de-activated during machinery start-up.
10) May be arranged as a summary-alarm (common).
11) These alarms are to be distinct from others listed in this Table and are to indicate conditions requiring actions to prevent degradation to an
unsafe condition.

PART 4 SECTION 11|20 Shipboard Control and Monitoring Systems


TABLE 4/11.4
Centralized Control and Monitoring Station
(Applicable to ACCU or ABCU Craft)

Item Alarm Display Provisions Remarks


1), 6) of Device
on Station
1)
A1 Failure or malfunctioning of system x 2), 5)
A2 Failure, supply x Main/Standby Automatic transfer to standby supply 2), 5)
A3 Control station in operation Station
A4 Control transfer switch x
Control and A5 Control power available, pressure or level Pressure/Level 5)
Monitoring System A6 Alarm, disabled (override) Disabled 4), 5)
A7 Safety, activation x 3), 5)
A8 Safety disabled x Disabled 4), 5)
A9 Safety, disabled (override) switch x See 4/11.3.4f 5)
Main Power B1 Normal electrical supply, loss x 5)
Source
Nickel-cadmium C1 Any permanently installed nickel-cadmium x Associated with systems for the control and
Battery battery, thermal runaway monitor of the craft’s propulsion, steering and
trim related machinery and propulsion-
machinery space 5)
Supply to Steering D1 Normal power supply to the powered x 5), 7)
& Trim System directional or trim control devices, failure
Compass E1 Compass system, failure x 5), 7)
Navigation Lights F1 Side, masthead or stern navigation lights, x 5), 7)
extinction
G1 Remote controls x
G2 Propeller shaft, speed Speed 5)
Propulsion, G3 Propeller shaft, direction Direction 5)
General G4 Propeller, pitch Pitch For controllable-pitch propeller 6)
G5 Prime movers, prolonged operation within x Visual display may be acceptable 6)
critical speed range
G6 Main engine, overspeed x 5)
Propulsion H1 Starting medium, pressure or level, low x Pressure or 5)
Level
Starting H2 Hazardous condition present x See 4/11.3.2d2 5)
Diesel Propulsion I1 Alarms and displays See Table 4/11.5
Gas turbine J1 Alarms and displays See Table 4/11.8
Propulsion
Electric K1 Alarms and displays See Table 4/11.7
Propulsion K1 Propulsion generator load-share overload x See 4/5C2.19.3 &.21.3 and 4/11.3.14
Elect. Gen. L1 Alarms and displays See Table 4/11.8
Machinery
FO Settling M1 Level, tank, low x See 4/11.3.16a 5), 7)
and M2 Level, tank, high x See 4/11.3.16b 5), 7)
Daily Service Tanks M3 Fuel oil tank, heater temperature, high x See 4/11.3.18b3 5)
FO & LO N1 Tank, level high or overflow x See 4/11.3.18b2 5), 7)
Collect.Tank
High Pressure O1 Leakage x See 4/11.3.18b1 5), 7)
FO System
LO Stern Tube P1 Level, oil, low x 5)
Tank
Q1 Level of contents of any fluid reservoir the x 5), 7)
Essential Fluid contents of which are essential for normal
Reservoirs craft operation, low
( Cont-)

PART 4 SECTION 11|21 Shipboard Control and Monitoring Systems


TABLE 4/11.4
Centralized Control and Monitoring Station
(Applicable to ACCU or ABCU Craft)

Item Alarm Display Provisions Remarks


1), 6) of Device
on Station
1)
R1 Any ventilation fan installed for ventilating x 5), 7)
Ventilation System spaces in which inflammable vapours may
accumulate, failure
S1 Level, bilges, high x See 4/11.3.18a1 5)
Bilges in S2 Any automatic bilge pump, operation x 5), 7)
Machinery Space S3 Excessive running of bilge pump motor x See 4/11.3.18a2 5)

Notes:

1) Required actuation device or alarm is denoted by a (x).


2) For each system: control systems, alarm/display systems and safety systems. See 4/11.3.6a1 and 4/11.3.6a2.
3) Actuation of propulsion safeties is to either reduce output or shutdown the propulsion machinery, as required. See 4/11.3.4f and Tables 4/11.5
through 4/11.8.
4) Deactivation means are to be arranged so that such action cannot be done inadvertently. Alternative means to indicate disabling of safety actions or
alarms
will be considered.
5) For ABCU craft, only these items and the alarms and displays per Tables 4/11.5 through 4/11.8, as applicable, need to be provided on such station.
6) Provided the audible alarms re-activate automatically after a preset time, audible alarms may be by-passed or de-activated during machinery start-up.
7) These alarms are to be distinct from others listed in this Table and are to indicate conditions requiring actions to prevent degradation to an unsafe
condition.

PART 4 SECTION 11|22 Shipboard Control and Monitoring Systems


TABLE 4/11.5
Monitoring of Propulsion Machinery - Medium/High (Trunk Piston) Speed Diesel Engines
(Applicable to ACCU or ABCU Craft. See also Table 4/11.4)

Automatic
Start of
Required
Standby
Item 11) Alarm Display Vital Remarks
1) Auxiliary
Pump
with
Alarm
1)
A1 Fuel oil after filter (engine inlet), pressure- x Pressure x 3)
low
A2 Fuel oil before injection pumps,
temperature or viscosity-low, and x 5)
Fuel Oil System Fuel oil before injection pumps,
temperature or viscosity, high
A3 Leakage from high pressure pipes x
A4 Fuel oil in daily service tank, level-low x See also 4/11.3.16a.
B1 Lube oil to main bearing and thrust x Pressure x 3), 4)
bearing, pressure-low
B2 Lube oil filter differential, pressure-high x Pressure x 3)
Lube Oil System B3 Lube oil inlet, temperature-high x Temp.
B4 Oil mist concentration in crankcase, mist- x Automatic engine shutdown 3), 6)
high
B5 Flow rate cylinder lubricator, flow-low. x Automatic engine slowdown 2), 10)
Each apparatus
Turbo-charger C1 Turbo-charger lube oil inlet, pressure-low x Pressure 7)
S. W. Cooling D1 Sea water cooling, pressure-low x Pressure x 3)
Cylinder Fresh E1 Water inlet, pressure-low or flow-low x Press. or flow x Automatic engine slowdown 2), 3)
Cooling
Water System E2 Water outlet (general), temperature-high x Temp. Automatic engine slowdown 8)
E3 Cooling water in expansion tank, level-low x
Air F1 Starting air before main shut-off valve, See item H1 in Table 4/11.4
pressure-low
System F2 Control air, pressure-low x Pressure
Scavenge Air G1 Scavenge air receiver, temperature-high x
System
Exhaust Gas H1 Exhaust gas after each cylinder, x Temp. Automatic engine slowdown 2), 9)
temperature-high
System H2 Exhaust gas after each cylinder, deviation x
from average, temperature-high 9)
Engine I1 Engine speed Speed
I2 Engine overspeed Automatic engine shutdown ; see also item
G6 in Table 4/11.4 3)
Power Supply J1 Control, alarm or safety system, power x
supply failure

Notes:

1) Required alarm or starting of standby pump is denoted by a (x).


2) A common sensor for alarm/display and automatic slowdown is acceptable.
3) Separate sensors are required for: a) alarm/automatic starting of required standby pump, and b) automatic engine shutdown.
4) Automatic engine shutdown is to be alarmed and effected upon loss of oil pressure. .
5) For heavy fuel oil burning engines only.
6) Only for medium speed engines having a power of more than 2250 kW (3000 hp) or a cylinder bore of more than 300 mm (11.8 in.).
7) If without integrated self-contained oil lubrication system.
8) Two separate sensors are required for alarm and slowdown.
9) For engine power > 500 kW/cyl.
10) If necessary for the safe operation of the engine.
11) For ABCU craft having integrated propulsion machinery, exemption from the listed instrumentation and safety provisions will be considered.

PART 4 SECTION 11|23 Shipboard Control and Monitoring Systems


TABLE 4/11.6
Monitoring of Propulsion Machinery - Gas Turbine
(Applicable to ACCU or ABCU Craft). See also Table 4/11.4)

Automatic
Starting
of
Item Alarm Display Required Remarks
1) Standby
Vital
Auxiliary
Pump
1), 4)

A1 Pressure, inlet, low x Pressure x Turbine automatic shutdown 3)


Lube Oil A2 Temperature, inlet, high x Temperature
2) A3 Differential pressure, filter, high x
A4 Level, tank, low x In gravity tank and sump
Bearings B1 Temperature, high x Main bearings
Cooling C1 Pressure or flow, low x Pressure, or
flow
Medium C2 Temperature, high x
D1 Pressure or flow, low x Pressure, or
flow
Fuel D2 Temperature or viscosity, low x Temperature, For heavy fuel
or
D3 Temperature or viscosity, high x viscosity For heavy fuel
E1 Temperature, high x
Exhaust Gas E2 Temperature, high-high x Turbine automatic shutdown
E3 Temperature deviation, high x
Turbine F1 Vibration level, high x
F2 Vibration level, high-high x Turbine automatic shutdown
Rotor G1 Axial displacement, high x
Overspeed H1 Device activated See also item G6 in Table 4/11.4

Notes:

1) Required alarm or starting of standby pump is denoted by a (x).


2) Individual alarms are required where separate systems (e.g., reduction gear, bearing, etc.) are installed.
3) The automatic shutdown is to be effected upon loss of lube oil pressure.
4) For ABCU craft having non-integrated propulsion machinery, starting of required standby pump is to be alarmed.

PART 4 SECTION 11|24 Shipboard Control and Monitoring Systems


TABLE 4/11.7
Monitoring of Propulsion Machinery Electric
(Applicable to ACCU or ABCU Craft. See also Table 4/11.4)

Item Alarm Display Remarks


1)

A1 Pressure, bearing, lube oil inlet, low x Pressure Prime mover automatic shutdown
A2 Voltage, off-limits x Voltage To read all phases and at least one bus 2)
Propulsion A3 Frequency, off-limits x Frequency
Generator A4 Current Current To read all phases 2)
A5 Temperature, stationary windings, high x Temperature To read all phases; for generators >500 kW
A6 Transfer of standby generator x
B1 Pressure, bearing, lube oil inlet, low x Pressure
B2 Voltage, armature, off-limits x Voltage To read all phases and at least one bus
B3 Voltage, field Voltage
B4 Frequency, off-limits x Frequency
Propulsion B5 Current, armature Current To read all phases
A.C. Motor B6 Current, field Current For synchronous motors
B7 Ground lights or similar Status
B8 Temperature, stationary windings, high x Temperature To read all phases; for motors >500 kW
B9 Motor running Running
B10 Transfer of standby motor x
B11 Motor cooling medium temperature, high x Temperature If required
C1 Pressure, bearing, lube oil inlet, low x Pressure Automatic shutdown
C2 Voltage, armature x Voltage
C3 Voltage, field Voltage
C4 Current, armature Current
Propulsion D.C. C5 Current, field Current
Motor C6 Ground lights or similar Status
C7 Motor running Running
C8 Failure of on-line motor x
C9 Transfer of standby motor x
C10 Motor cooling medium temperature, high x Temperature If required
D1 Voltage, SCR Voltage
Propulsion D2 Current, SCR Current
Semi-conductor D3 Overloading conditions, high current x Alarms before protective device is activated
Rectifier (SCR) D4 Open/close position for assignment switches Position
D5 SCR cooling medium temperature, high x Temperature If required

Notes:

1) Required alarm is denoted by a (x).


2) For D.C. generators. Additionally, field' voltmeters and ammeters are to be included.

PART 4 SECTION 11|25 Shipboard Control and Monitoring Systems


TABLE 4/11. 8
Monitoring of Auxiliary Prime-movers and Electrical Generators
(Applicable to ACCU or ABCU Craft. See also Table 4/11.4)

Item Alarm Display Remarks


1)
Lube Oil A1 Pressure, lube oil inlet, low x Pressure Automatic engine shutdown
A2 Temperature, inlet, high x Temperature
Cooling B1 Pressure or flow, low x Pressure, or
flow
Medium B2 Temperature, outlet, high x
B3 Level, expansion tank, low x If separate from main system
Diesel C1 Fuel oil leakage from pressure pipe x
Engine Fuel Oil C2 Level, in fuel oil daily service tank, low x See also 4/11.3.16a
Crankcase D1 Oil mist concentration, high x Automatic engine shutdown 2)
Starting E1 Pressure or level, low x Pressure, or
Medium level
Overspeed F1 Device activated x Automatic shutdown. See 4/5C2.17.2 and
4/4.11.6 of the “Rules for Building and
Classing Steel Vessels”
GE1 Pressure, bearing, lube oil inlet, low x Pressure Prime mover automatic shutdown
GE2 Voltage, off-limits x Voltage To read all phases and at least one bus 3)
Electrical GE3 Frequency, off-limits x Frequency
Generator GE4 Current, high x Current To read all phases 3)
GE5 Transfer of standby generator x

Notes:
1) Required alarm is denoted by a (x).
2) For engines having a power of more than 2250 kW (3000 Hp) or having a cylinder bore over 300 mm (11.8 in.).
3) For D.C. generation. Additionally, field' voltmeters and ammeters are to be included.

PART 4 SECTION 11|26 Shipboard Control and Monitoring Systems


PART 5
Contents
Specialized Craft and Services

SECTION
1 Craft Intended to Carry Passengers

Appendix
5/A Guidelines for Accommodation Design of Passenger Craft
PART 5 SECTION 1
Craft Intended to Carry Passengers
5/1.1 General
5/1.1.4 Safety Certificate for High-Speed
5/1.1.1 Classification Craft
In accordance with 1/1.3.2, either the Where authorized by the Administration of
classification of !A1 HSC Passenger Craft (A) country signatory to the International Convention
or !A1 HSC Passenger Craft (B) is to be for the Safety of Life at Sea, 1974 as amended,
assigned to craft designed and specifically fitted and upon request of the owners of a classed craft
for the carriage of passengers and built to the or one intended to be classed, the Bureau will
applicable requirements of this section and other review the plans, data, etc., and survey the craft
relevant sections of the Guide. In addition, the for compliance with the requirements of the
craft is to have a Safety Certificate for High- International Code for Safety for High-Speed
Speed Craft from the Administration of registry Craft and issue a Safety Certificate for High-
or its agent evidencing the craft compliance with Speed Craft, prescribed in the Convention on
the requirements of the International Code for behalf of the Administration.
Safety for High-Speed Craft (IMO HSC Code).
5/1.1.5 Independent Review
5/1.1.2 Application When the Safety Certificate for High-Speed Craft
These requirements are intended to apply to a is issued by an Administration or its agent other
craft of Category A or Category B of the than the Bureau, the Bureau when requested by
International Code for Safety for High-Speed the owner, shipyard, or designers, will conduct
Craft, carrying more than twelve passengers on an independent review of any of the following:
an international voyage.
Subdivisions and Stability
5/1.1.3 Scope Trim and Stability Booklet
This section is intended to cover the additional Inclining Experiment
hull construction, accommodation arrangement, Structural Fire Protection
machinery and safety equipment required to class Life-Saving Appliances and Arrangements
a craft as a passenger craft. These requirements
are applicable to those features that are Fees for such independent reviews will be
permanent in nature and can be verified by plan charged to the owner when the review is
review, calculation, physical survey or any other requested.
means. This Guide does not address the
requirements for Life Saving Appliances and
Arrangements (Chapter 8), Navigational 5/1.1.6 Administration Approval
Equipment (Chapter 13), Radio Communications In general, the approval of material for use in
(Chapter 14), and Operational Requirements accommodation, safety equipment, life-saving
(Chapter 18) found in the International Code for appliances, etc. is a function of the
Safety for High-Speed Craft, which are not a Administration. When the craft is issued a
condition for classification. Passenger Ship Safety Certificate by the
For a passenger craft intended for Administration or its agent other than the Bureau,
international voyage which is beyond the scope such certificate will be accepted as evidence that
of the International Code for Safety for High- the Administration has approved the material,
Speed Craft, the arrangements and scantlings are safety equipment, life-saving appliances, etc.
to comply with the requirements of Section 5/5 On other passenger craft, the designer or
of Rules for Building and Classing Steel Vessels. builder will submit evidence that the
For a passenger craft intended for service in Administration has approved the material, safety
domestic waters, the additional hull construction, equipment, life-saving appliances, etc. for
accommodation arrangement, machinery and Bureau acceptance on craft building to class.
safety equipment requirements in this section
may be replaced with the Regulations of the flag
Administration for a craft intended solely for
service in domestic waters.

PART 5 SECTION 1| 1 Craft Intended to Carry Passengers


When given specific instructions from the 5/1.3.7 Public Space
Administration, the Bureau may approve and Public spaces are those spaces allocated for the
accept the material, equipment, life-saving passengers and include bars, kiosks, smoke
appliances, etc. fitted on the craft. rooms, main seating areas, lounges, dining
rooms, recreation rooms, lobbies, lavatories and
5/1.3 Definitions similar permanently enclosed spaces allocated
for passengers.
5/1.3.1 General
For definitions of terms used in this section and 5/1.5 Intact Stability
not shown below, reference is to be made to the The intact stability for passenger craft, in the
definitions in the various Chapters in the displacement mode, in the transient mode and in
International Code of Safety for High-Speed the non-displacement mode are to comply with a
Craft. (Abbreviated: IMO HSC Code). recognized standard. The submission of
evidence showing approval by an Administration
5/1.3.2 Administration will be acceptable. Alternatively, upon request
Administration means the Government of the the review will be performed by the Bureau for
State whose flag the craft is entitled to fly. compliance with the applicable requirements of
IMO HSC Code.
5/1.3.3 Category A Craft
Any high-speed passenger craft carrying not 5/1.7 Subdivision and Damage Stability
more than 450 passengers and operating on a When the craft is issued a Safety Certificate for
route where it has been demonstrated to the High-Speed Craft by the Administration or its
satisfaction of the flag and port States that there agent other than the Bureau, such certificate will
is a high probability that, in the event of an be accepted as evidence of compliance with the
evacuation at any point of the route, all subdivision and stability requirements of
passengers and crew can be rescued safely within Chapter 2.6 of IMO HSC Code. On all other
the least of : a) the time to prevent persons in passenger craft, when authorized by an
survival craft from exposure causing Administration and requested by the Owner, the
hypothermia in the worst intended conditions, b) Bureau will review the data on the subdivision
the time appropriate with respect to and stability for compliance with IMO HSC
environmental conditions and geographical Code on behalf of the Administration. However,
features of the route, or c) 4 hours. also see 5/1.1.5.

5/1.3.4 Category B Craft 5/1.9 Inclining Experiment and Stability


Any high-speed passenger craft, other than a Information
category A craft, with machinery and safety When the craft is issued a Safety Certificate for
systems arranged such that, in the event of High-Speed Craft by the Administration or its
damage disabling any essential machinery and agent other than the Bureau, such certificate will
safety systems in one compartment, the craft be accepted as evidence of compliance with the
retains the capability to navigate safely. requirement for an inclining experiment and
stability information of Chapter 2.7 of IMO HSC
5/1.3.5 Crew Accommodation Code. On all other passenger craft, when
Crew accommodation are those spaces allocated authorized by an Administration and requested
for the use of the crew, and include cabins, sick by the Owner, the Bureau will review the
bays, offices, lavatories, lounges and similar inclining experiment and stability information for
spaces. compliance with IMO HSC Code on behalf of
the Administration. However, also see 5/1.1.5.
5/1.3.6 Passenger
A passenger is every person other than, a) the 5/1.11 Construction
master and members of the crew or other The scantlings and arrangements of the hull
persons employed or engaged in any capacity on structure are to be in accordance with the
board a craft on the business of that craft and b) a applicable requirements of Part 3.
child under one year of age.

PART 5 SECTION 1| 2 Craft Intended to Carry Passengers


5/1.13 Accommodation Space Design 5/1.15.3 Emergency Services
Passenger and crew accommodation spaces are a Category A Craft The emergency source of
to be designed and arranged so that the occupants power is to be capable of supplying
are protected from unfavorable environmental simultaneously the following services:
conditions, and the risk of injury to occupants 1 For a period of 5 h, emergency lighting:
during normal and emergency conditions is a At the stowage positions of life-saving
minimized. Spaces accessible to passengers are appliances;
not to contain controls, electrical equipment, b At all escape routes such as alleyways,
high-temperature parts and pipelines, rotating stairways, exits from accommodation and
assemblies, or other items from which injury to service spaces, embarkation points, etc;
passengers could result, unless such items are c In the public spaces;
adequately shielded, isolated, or otherwise d In the machinery spaces and main
protected. emergency generating spaces, including their
The design and location of public spaces and control positions;
crew accommodation may be in accordance with e In control stations;
the requirements in Appendix 5/A “Guidelines f At the stowage positions for fireman's
for Accommodation Design of Passenger Craft” outfits; and
unless the flag Administration has specific g At the steering gear;
requirements in this respect. 2 For a period of 5 h:
a Main navigation lights, except for "not
5/1.15 Emergency Source of Power under command" lights;
The emergency source of electrical power is to b Electrical internal communication
comply with 4/5A3 except as modified below. equipment for announcements for passengers
and crew required during evacuation;
5/1.15.1 Alternative to Emergency Source of c Fire-detection and general alarm system
Power and manual fire alarms; and
Where the main source of electrical power is d Remote control devices of fire-
located in two or more compartments which are extinguishing systems, if electrical;
not contiguous, each of which has its own self- 3 For a period of 4 h of intermittent
contained systems, including power distribution operation:
and control systems, completely independent of a The daylight signaling lamps, if they have
each other and such that a fire or other casualty no independent supply from their own
in any one of the spaces will not affect the power accumulator battery; and
distribution from the others, or to the services b The craft's whistle, if electrically driven;
required by 5/1.15.3a or 5/1.15.3b, the 4 For a period of 5 h:
requirements of 4/5A.3.1, 4/5A.3.1.1 and a Craft radio facilities and other loads as set
4/5A.3.5.4 may be considered satisfied without out in 14.12.2 of the IMO’s International
an additional emergency source of electrical Code of Safety for High-speed Craft; and
power, provided that: b Emergency control monitoring systems as
a There is at least one generating set, required by 4/11.3.6a2a
meeting the inclination requirements of 4/1.21 5 For a period of 12 h, the "not under
and of sufficient capacity to meet the command" lights; and
requirements of 5/1.15.3a or 5/1.15.3b in each of 6 For a period of 10 min continuous
at least two non-contiguous spaces; operation, steering gear to comply with
b The arrangements required by 5/1.15.1a in 4/5A6.5 if powered from the emergency
each such space are equivalent to those required source.
by 4/5A3.5.2, 4/5A3.9 and 4/5A3.15 so that a b Category B Craft The electrical power
source of electrical power is available at all times available is to be sufficient to supply all those
to the services required by 5/1.15.3a or services that are essential for safety in an
5/1.15.3b; and emergency, due regard being paid to such
c The generator sets referred to in 5/1.15.1a services as may have to be operated
simultaneously. The emergency source of
and their self-contained systems are installed
electrical power is to be capable, having regard
such that one of them remains operable after
to starting currents and the transitory nature of
damage or flooding in any one compartment.

PART 5 SECTION 1| 3 Craft Intended to Carry Passengers


certain loads, of supplying simultaneously at f Craft radio facilities and other loads as set
least the following services for the periods out in 14.12.2 of the IMO’s International
specified hereinafter, if they depend upon an Code of Safety for High-speed Craft;
electrical source for their operation: 5 For a period of 30 min, any watertight
1 For a period of 12 h, emergency lighting: doors, required by Section 3/3, to be power-
a At the stowage positions of life-saving operated, together with their indicators and
appliances; warning signals;
b At all escape routes, such as alleyways, 6 For a period of 10 min continuous
stairways, exits from accommodation and operation, steering gear to comply with
service spaces, embarkation points, etc.; 4/5A6.5 if powered from the emergency
c In the passenger compartments; source.
d In the machinery spaces and main
emergency generating spaces, including their 5/1.15.5 Transitional Source of Power
control positions; The transitional source of emergency electrical
e In control stations; power required by 4/5A3.5.2b2 may consist of an
f At the stowage positions for fireman's accumulator battery suitably located for use in an
outfits; and emergency which is to operate without
g At the steering gear; recharging while maintaining the voltage of the
2 For a period of 12 h: battery throughout the discharge period within
a The navigation lights and other lights 12% above or below its nominal voltage and be
required by the International Regulations for of sufficient capacity and so arranged as to
Preventing Collisions at Sea in force; supply automatically in the event of failure of
b Electrical internal communication either the main or emergency source of electrical
equipment for announcements for passengers power at least the following services, if the
and crew required during evacuation; depend upon an electrical source for their
c Fire-detection and general alarm system operation:
and manual fire alarms; and
d Remote control devices of fire- a For a period of 30 min, the load specified in
extinguishing systems, if electrical; 5/1.15.3a1 through .15.3a3 or in 5/1.15.3b1
3 For a period of 4 h of intermittent through .15.3b3; and
operation: b With respect to the watertight doors:
a The daylight signaling lamps, if they have 1 Power to operate the watertight doors, but
no independent supply from their own not necessarily simultaneously, unless an
accumulator battery; and independent temporary source of stored
b The craft's whistle, if electrically driven; energy is provided. The power source should
4 For a period of 12 h: have sufficient capacity to operate each door
a The navigational equipment as required at least three times, i.e. closed - open -
by Chapter 13 of the IMO’s International closed, against an adverse list of 15°; and
Code of Safety for High-speed Craft. Where 2 Power to the control, indication and alarm
such provision is unreasonable or circuits for the watertight doors for half an
impracticable, the Administration may waive hour.
this requirement for craft of less than 5,000
GT; The above requirements may be considered
b Essential electrically powered instruments satisfied without the installation of a transitional
and controls for propulsion machinery, if source of emergency electrical power if each of
alternate sources of power are not available the services required by that paragraph has
for such devices; independent supplies, for the period specified,
c One of the fire pumps required by 4/9.3; from accumulator batteries suitably located for
d The sprinkler pump and drencher pump, if use in an emergency. The supply of emergency
fitted; power to the instruments and controls of the
e The emergency bilge pump and all the propulsion and direction systems should be
equipment essential for the operation of uninterruptible.
electrically powered remote controlled bilge
valves as required by 5/1.21; and

PART 5 SECTION 1| 4 Craft Intended to Carry Passengers


5/1.15.7 Supplemental Emergency Lighting 5/1.17 Fire Safety Measures
for Craft Having Special-category The requirements specified in 3/24.3 are
Spaces applicable. In addition, the arrangement of
In addition to the emergency lighting required by spaces is to be as follows:
5/1.15.3a1, 5/1.15.3b1 and 5/1.15.5a on every a For category A craft, a single public space
craft with special-category spaces: is acceptable.
a All passenger public spaces* and alleyways b For category B craft, public spaces are to
are to be provided with supplementary electric be divided into zones according to the following:
lighting that can operate for at least 3 h when all 1 Passenger spaces are to be divided
other sources of electric power have failed and into at least two zones and the mean
under any condition of heel. The illumination length of each zone is to be less than
provided is to be such that the approach to the 40 m.
means of escape can be readily seen. The source 2 For the occupants of each zone there
of power for the supplementary lighting is to should be an alternative safe area to
consist of accumulator batteries located within which it is possible to escape in case
the lighting units that are continuously charged, of fire. The alternative safe area is to
where practicable, from the emergency be separated from other passenger
switchboard. Alternatively, any other means of zones by smoke-tight divisions of non-
lighting, which is at least as effective, may be combustible materials or fire-
accepted by the Administration. restricting materials extending from
The supplementary lighting is to be such that deck to deck. The alternative safe
any failure of the lamp will be immediately area can be another passenger zone
apparent. Any accumulator battery provided is provided the additional number of
to be replaced at intervals having regard to the passengers may be accommodated in
specified service life in the ambient condition an emergency.
that it is subject to in service; and 3 The alternative safe area is to be
b A portable rechargeable battery-operated located adjacent to the passenger zone
lamp is to be provided in every crew space it is intended to serve. There should
alleyway, recreational space and every working be at least two exits from each
space which is normally occupied unless passenger zone, located as far away
supplementary emergency lighting, as required from each other as possible, leading to
by 5/1.15.7a, is provided. the alternative safe area. Escape
* In category A craft having limited public spaces,
routes should be provided to enable
emergency lighting fittings of the type described in all passengers and crew to be safely
5/1.15.7a as meeting the requirements of 5/1.15.3a1 evacuated from the alternative safe
and 5/1.15.5a may be accepted, provided that an area.
adequate standard of safety is attained.
c Control stations, stowage positions of life-
saving appliances, escape routes and places of
5/1.15.9 Arrangements for Periodic Testing embarkation into survival craft are not to be
Provision is to be made for the periodic testing of located adjacent to any area of major or of
the complete emergency system, including the moderate fire hazard.
emergency consumers required by 5/1.15.3a or
5/1.15.3b and 5/1.15.5, and is to include the 5/1.19 Fire Fighting
testing of automatic starting arrangements.
5/1.19.1 General
5/1.15.11 Distribution The requirements in Section 4/9 applicable for
Distribution systems are to be so arranged that cargo craft of 500 gross tons and above are to be
fire in any main vertical zone will not interfere applied for all passenger craft, regardless of the
with services essential for safety in any other gross tonnage. The following requirements also
such zone. This requirement will be met if main apply.
and emergency feeders passing through any such
zone are separated both vertically and
horizontally as widely as is practicable.

PART 5 SECTION 1| 5 Craft Intended to Carry Passengers


5/1.19.2 Fixed Sprinkler System main. One of the pumps in either case may be
Public spaces, service spaces, storage rooms driven by the propulsion machinery.
other than those containing flammable liquids, b Multihull Craft On multihull craft, each
and similar spaces are to be protected by a fixed hull is to be provided with at least two bilge
sprinkler system. Manually operated sprinkler pumps.
systems are to be divided into sections of
appropriate size, and the valves for each section, 5/1.21.3 Arrangement of Fixed Bilge Pumps
the means to start the sprinkler pump(s) and The bilge system is to be arranged such that at
alarms are to be operable from two spaces least one power bilge pump will be available for
separated as widely as possible, one of which is use in all flooding conditions which the craft is
to be a continuously manned control station. In required to withstand as follows:
category B craft, no section of the system is to a One of the bilge pumps is to be an
serve more than one of the zones required in emergency pump of a reliable submersible type
5/1.17.1. connected to an emergency source of power; or
Plans of the system are to be displayed at b The bilge pumps and their sources of
each operating station. power are to be distributed throughout the length
Suitable alternatives may be accepted in lieu craft so that at least one pump in an undamaged
of a fixed sprinkler system provided the compartment will be available.
alternative is acceptable to the Administration.
5/1.21.4 Submersible Bilge Pumps
5/1.19.3 Fireman's Outfits As an alternative to 5/1.21.2 and 5/1.21.3, an
a Category A Craft The fireman’s outfits in arrangement utilizing submersible pumps may be
4/9.9 are not required for Category A Craft. utilized. See 4/6.41.
b Category B Craft In addition to the two
fireman's outfits required by 4/9.9, there are to be 5/1.21.5 Manifolds, Cocks and Valves
two more fireman’s outfits for every 80m (265 Manifolds, cocks and valves in connection with
ft), or part thereof, of the aggregate of the lengths the bilge pumping system are to be so arranged
of all passenger spaces and service spaces on the that, in the event of flooding, one of the bilge
deck which includes such spaces. If there is pumps may be operative in any compartment. In
more than one such deck, the deck which has the addition, damage to a pump or its pipe
largest aggregate of such lengths is to be used for connection to the bilge main is not to make the
determining the number of additional fireman’s bilge system inoperable. When, in addition to
outfits to be carried. Each fireman’s outfit is to the main bilge pumping system, an emergency
consist of the items in 4/9.9. Also, one water fog bilge pumping system is provided, it is to be
applicator is to be provided for each pair of independent of the main system and so arranged
breathing apparatus. The water fog applicator is that a pump is capable of operating in any
to be stored adjacent to the breathing compartment under the specified flooding
apparatuses. conditions. In that case, only the valves
necessary for the operation of the emergency
5/1.21 Bilge System system need be capable of being operated from
above the bulkhead deck.
5/1.21.1 General All cocks and valves referred to above which
The bilge system is to comply with 4/6.33 can be operated from above the bulkhead deck
through 4/6.42 except as modified below. are to have their controls at their place of
Suitable arrangements are to be provided for the operation clearly marked and are to be provided
drainage and discharge of water which may be with means to indicate whether they are open or
discharged by the fixed sprinkler system in closed.
5/1.19.2.
5/1.23 Ro/Ro Craft
5/1.21.2 Number of Fixed Bilge Pumps
Craft which are intended for carrying motor
a Monohull Craft Each category B
vehicles in addition to passengers are to comply
monohull craft is to be provided with three power
with the following requirements.
bilge pumps connected to the bilge main. Each
category A craft is to be provided with at least
two power bilge pumps connected to the bilge

PART 5 SECTION 1| 6 Craft Intended to Carry Passengers


5/1.23.1 Definition of Spaces test in conditions simulating a flowing petrol fire
Vehicles may be carried in open vehicle spaces in a special category space to be not less
or in special category spaces, which are defined effective in controlling fires likely to occur in
as follows: such a space.
a Open Vehicle Spaces Open vehicle
5/1.23.5 Fire Extinguishing Equipment
spaces are spaces intended for the carriage of
Each special category space is to be provided
motor vehicles with fuel in their tanks for their
with the following fire extinguishing equipment.
own propulsion, to which passengers have
a at least three water fog applicators.
access, that are either open at both ends or open
b one portable foam applicator unit
at one end and provided with adequate natural
consisting of an air-foam nozzle of an inductor
ventilation effective over their entire length
type capable of being connected to the fire main
through permanent openings in the side plating
by a fire hose, together with a portable tank
or deckhead or from above.
containing 20 liters (5 U.S. gallons) of foam-
b Special Category Spaces Special
making liquid and one spare tank. The nozzle is
category spaces are those enclosed spaces
to be capable of producing effective foam
intended for the carriage of motor vehicles with
suitable for extinguishing an oil fire at the rate of
fuel in their tanks for their own propulsion, into
at least 1.5 m3/min. (53 ft3/min.). Each craft
and from which such vehicles can be driven, and
having special category spaces is be provided
to which passengers have access, including
with at least two portable foam applicator units
spaces intended for the carriage of cargo
as a minimum.
vehicles.
c portable fire extinguishers located so that
no point in the space is more than 15 m (50 ft)
5/1.23.2 Electrical Equipment and Ventilation
from an extinguisher, provided that at least one
Electrical equipment and ventilation for special
portable extinguisher is located at each access to
category spaces are to be in accordance with
the space.
4/5E1.
5/1.23.6 Scuppers, Bilge Pumping and
5/1.23.3 Fire Detection and Fire Alarm
Drainage
Systems
In order to prevent a serious loss of stability
Open vehicle spaces and special category spaces
which could result due to large quantities of
are to be provided with fire detection and fire
water accumulating on the vehicle deck(s) from
alarms system complying with 4/9.23.
operation of the fixed water spraying system in
5/1.23.4 Fire Extinguishing System 5/1.23.5, scuppers are to be fitted to directly
Each special category space is to be fitted with discharge the water overboard. Alternatively,
an approved manually-operated fixed pressure pumping and drainage arrangements may be
water spraying system. Other types of fire provided additional to the requirements in
extinguishing systems may be considered 5/1.21.
provided that they have been shown by full-scale

PART 5 SECTION 1| 7 Craft Intended to Carry Passengers


PART 5 APPENDIX A

Guidelines for Accommodation Design of


Passenger Craft
Note:
This Appendix is prepared to give guidelines to users of the Guide to design, build and operate craft intended to
carry passengers on International voyages. It should be noted that any interpretations to the International Code
of Safety for High-Speed Craft in this respect issued by the flag Administration govern the guidelines in this
Appendix.

5/A.1 General k3 = 1 (1, 0.305)


For passenger craft, superimposed vertical M = 0.95 for mild steel
accelerations above 1.0g at the longitudinal center of = 1.3 for higher tensile steel
gravity should be avoided unless special precautions = 1.0 for aluminum alloy
are taken with respect to passenger safety. = 0.8 for fiber reinforced plastic
(165 + k 3 Lc ) +  k 3 Lc  0.4
5/A.2 Design Acceleration Levels CL =  
Passenger craft are to be designed for the collision 245  80 
k 3 d c + 2 + f (k 3 Dc 2)
load with respect to the safety in, and escape from,
the public spaces, crew accommodation and escape CH =
routes, including in way of life-saving appliances, and 2 k 3 Dc
emergency source of power. The size and type of Lc = overall length of the underwater watertight
craft together with speed, displacement and building envelope of the rigid hull, excluding
material are to be taken into consideration when the appendages, at or below the design waterline
collision load is determined. The collision design in the displacement mode with no lift or
condition is to be based on a head on collision at propulsion machinery active.
operational speed with a vertical rock with maximum Dc = depth of the craft measured at the middle of
2 m height above the waterline. Unless any specific L from the underside of the keel to the top of
data of collision energy are available in the process of the effective hull girder in meters (feet)
design, the following may be used for assessment of dc = bouyancy tank clearance to skirt tip (m, (ft),
collision deceleration. Where the deceleration of the (negative)) for air-cushion vehicles; lifted
craft is determined by carrying out a collision load clearance from keel to water surface (m, (ft)
analysis of the craft in accordance with these (negative)) for hydrofoils; and draft of the
assumptions, that value may be used as gcoll. craft measured at the middle of L from the
1 Monohulls underside of the keel to the design load
12
. kP waterline in m (ft) for all other craft.
gcoll =
∆ f = 0 when (dc + 2) < Dc SI or MKS units,
where [(dc + 6.6) < Dc U.S. units]
gcoll = collision deceleration in g’s = 1 when (dc + 2) ≥ Dc SI or MKS units,
k = 0.102 (1.0, 1.0) [(dc + 6.6) ≥ Dc U.S. units]
E = kinetic energy of the craft, 0.132∆V2 kN-m
k1 3 EC H ( MC L ) kN (tf, Ltf),
2
P = (0.0135∆V2 tf-m, 0.0442∆V2 Ltf-ft.)

k 2 MC L C H (k 3 d c + 2)
= average craft displacement taken as the mean
but not less than
of the lightweight and the maximum
kN (tf, Ltf) operational displacement in tonnes (long
k1 = 460 (100, 66.9) tons)
k2 = 9000 (918, 903) V = operational speed of the craft in knots.
g = 9.81 (1.0, 32.2)

PART 5 Appendix A|1 Guidelines for Accommodation Design of Passenger Craft


2 Catamarans and SES Craft Catamarans and k and ∆ are as defined in 5/A.2.1
SES craft may use the same equation as given in a for
gcoll with the following exceptions: 5/A. 3 Accommodation Design
f = 0 for T+2<Dc-HT SI or MKS units, 1 Location of Public Spaces Public spaces are
(T+6.6<Dc-HT U.S. units) 0.0132V
2
= 1 for Dc>(T+2)≥Dc-HT SI or MKS units, not to be located within a distance of
(Dc>(T+6.6)≥Dc-HT U.S. units) g coll
= 2 for T+2≥Dc SI or MKS units,  0.0434V 2 
(T+6.6≥Dc U.S. units) meters  ft of the extreme forward end
T = lifted clearance from the keel to the water  g coll 
surface in m (ft.), taken as negative
of the top of the effective hull girder of the craft,
HT = minimum height from tunnel or wet deck
where the terms V and gcoll are as defined in 5/A.2.
bottom to the top of the effective hull girder
For the purpose of this requirement, gcoll is not to be
in meters (feet)
taken as greater than 12, and need not be taken as less
3 Air Cushion Vehicles
than 3.
Air cushion vehicles may use the same equation as
2 Accommodation Requirements
given in a for gcoll with the following exceptions:
Accommodations are to be as required by Table
f = 1 for HT > 2 SI or MKS units,
5/A.1, and are to be designed to a recognized
(HT > 6.6 US units)
standard.
= 2 for HT ≤ 2 SI or MKS units,
3 Foundations Calculations are to be submitted
(HT ≤ 6.6 US units) indicating that foundations for large masses such as
HT is as defined in 5/A.2.2 main engines, auxiliary engines, lift fans,
4 Hydrofoils Hydrofoils may use the same transmissions and electrical equipment can withstand
equation as given in a for gcoll, however gcoll is not to the collision design acceleration, gcoll, as given in
kF 5/A.2 without fracturing.
be taken less than where

F = failure load of bow foil assembly applied at
the operational waterline in kN (tf, Ltf)

Table 5/A. 1 Accommodation Requirements


gcoll
<3 3 ≤ gcoll ≤ 12 > 12
Seat Seatback Low or high High seatback with protective High seatback with protective
Requirements seatback deformation and padding deformation and padding
Seating No restrictions Forward or backward Forward or backward
Direction
Sofas Sofas allowed Not allowed as seats Not allowed
Seat Belts Not required Lap belt required in seats Three point belt or belt with
with no protective structure shoulder harness in forward
forward facing seats
Tables No restrictions Protective features and Not allowed
dynamic testing required
Projecting Padding required Padding required Padding required and is to be
objects specially approved.
Kiosks, No restrictions Only on aft side of bulkheads Specially approved
bars, etc. or specially approved
Baggage No restrictions Protection required forward Protection required forward
and is to be specially
approved
Large To be restrained To be restrained and To be restrained and
masses and positioned positioned positioned and to be specially
approved

PART 5 Appendix A|2 Guidelines for Accommodation Design of Passenger Craft

You might also like