You are on page 1of 16

ResearchIT

Featuring research from

Switch N to Eaton.

Power Perspectives
and IT Analysis
Power through increased energy consumption.

Conserve energy and money


without compromising protection.
Dramatically reduce energy consumption, environmental impact
and power costs with Eaton’s Energy Saver System (ESS).
ESS technology enables large, three-phase uninterruptible power
systems (UPSs) to operate at the highest efficiency in the industry—
99%—even at low load levels down to 10%; dramatically reducing
energy consumption, environmental impact and power costs.
Your electric savings will pay for the UPS in 3-5 years!

Take your position on power management to


a new level and download our white paper
today to learn more. You’ll automatically be
entered for a chance to win a water bottle!

www.eaton.com/researchIT

Eaton is a registered trademark of Eaton Corporation. ©2010 Eaton Corporation. 11683_0610


2 researchit
ResearchIT

Powering Through the Economy


Q&A with Lennart Jonsson, Vice President & CTO
Electrical Sector, Eaton Corporation
their predecessors that they Q: There’s a lot of talk about
can quickly pay for themselves. “green IT” these days. How
In the 1990s, the average UPS
was generally about 85 to
can that help?
A: A typical data center
90 percent efficient. Today’s
consumes 10 to 30 times more
models routinely achieve 90
energy per square foot than the
to 94 percent efficiency, and
average office building. All of
UPSs equipped with Energy
that power usage harms both
Saver System deliver up to 99
the environment and corporate
percent efficiency. For most
balance sheets. Fortunately,
companies, that can quickly
there are lots of ways to reduce
translate into considerable
both your carbon footprint and
savings. For instance, a UPS
your energy spending through
that delivers 400 kW at 82
the use of environmentally-
percent efficiency requires an
responsible IT practices.
average of 4.3 million kW hours
Today’s lean, more tightly- up to the CIO while facilities per year. A newer, 95 percent
regulated economy and the reports into the COO or vice For example, most data centers
efficient, UPS reduces that are filled with underutilized
ever-increasing importance of president of corporate real to only 3.7 million kW hours
IT have many organizations estate. Unfortunately, that but energy-hungry servers.
annually. That’s a reduction of Virtualization technology
caught in a bind. On one hand, divided organizational structure more than 600,000 kW hours,
reliable access to power is can produce conflicting goals enables organizations to convert
which can easily save tens or underused physical servers
vital to keeping data centers around technology, energy even hundreds of thousands of
operational, and the costs spend and sustainability. For into virtual devices and then
dollars a year. consolidate them on shared
associated with loss of power example, while IT buys server
can be devastating. On the equipment, facilities often pays host machines. The end results
Q: What’s the best long-term are greater hardware utilization
other hand, IT departments are the energy bill. As a result,
being asked to get more done power efficiency is sometimes
strategy for ensuring power and significant energy savings.
with less money even as energy a bigger priority for facilities efficiency?
A: Use modular power system You can also add hot and cold
rates continue to rise. managers than it is for their IT
design principles. No business aisles to your data center.
counterparts.
Lennart Jonsson, vice president ever wants to get caught with Every server takes in cool air
and chief technology officer, Changing your organizational less power than it needs, but through one vent and expels
Electrical sector, at Eaton structure such that both the arming yourself with excess hot air through another. Simply
Corporation believes that any IT and facilities departments capacity just in case pointlessly positioning servers such that
organization can get past this report up to the same drives up capital outlays while only hot air exhausts or cool
predicament by tapping into a executive helps align everyone lowering overall efficiency. air intakes face each other in
different kind of power—the around common goals, metrics Taking a modular approach a given aisle can generate a
power of returns on smart, and objectives. That can drive to power system design, in continuous air flow in your data
strategic investments. He greater efficiencies by ensuring which you deploy only the center that lowers operating
recently shared his thoughts on that IT and facilities managers capacity you need in the short temperatures and reduces the
that topic with us. are equally motivated to term and gradually plug in burden on cooling systems.
improve performance and additional resources as your
business grows, allows you Relatively simple practices like
Q: What’s a good starting lower power bills.
these can make a big impact
to keep pace with expanding
point for companies look- on operational spending. In
Q: What’s the quickest way needs economically, rather
ing to “power through the than pay heavily in advance for fact, coupling ideas like those
economy”? to save money on power? above with deployment of more
capacity you may never even
A: Creating organizational A: Invest in new Uninterruptible efficient power and cooling
require. Plus, deploying multiple
alignment between your IT Power Supplies! That might technologies can enable a
modular components instead of
and facilities departments not seem like the most intuitive midsize data center with 1,500
a single big one also increases
is an excellent first step. At action when money is tight, but servers to save millions of dollars
redundancy, which leads to
most companies, IT reports the latest power systems are while dramatically shrinking its
better reliability.
so much more efficient than contribution to global warming.

ResearchIT 3
ResearchIT

art data centers that are More broadly, Eaton is Leaf designation go well beyond
Q: What steps is Eaton designed from the ground up dedicated to making normal standards to provide
taking to help organizations to take maximum advantage sustainability an integral part exceptional environmental
power their way through of the strategies we’ve of everything we do. That’s benefit. It’s just one small
these turbulent times? been discussing. They use why we like to call Eaton the part of our commitment to
A: Most importantly, of course, only the latest and most business that’s “sustainable helping customers implement
we continue to develop efficient power quality and by design”. You can see that in sustainable materials and
leading-edge technologies distribution systems and our Green Leaf products. All of practices so they can realize
that equip organizations to employ modular power system our products and solutions are environmental benefits and
use power more efficiently, design principles, as well as a designed to meet or exceed financial savings.
effectively and safely. But we’re variety of technologies aimed government environmental
at conserving power and standards, but products and Source: Eaton
also setting new standards
for operational efficiency and shrinking our impact on the solutions that bear our Green
environmental stewardship in environment.
our own business practices.
For example, Eaton is currently
completing two state-of-the-

4 researchit
Switch N to Eaton.

Data Center Forum


Eaton's Global IT Newsletter

IT Perspective Customer Voice Data Center Interactive

Each quarterly publication


gives you access to:
IT Perspective: An Eaton editorial showcasing pertinent
technologies, trends, best practices in the IT industry
Customer Voice: A real-world application through
an in-depth customer case study
Data Center Interactive: A hands-on forum with
crossword puzzles, polls, contests, giveaways and
much more

Submit your data center


challenge story for a
chance to win a Gateway®
NetBook and subscribe
to Data Center Forum at:

www.eaton.com/dcf1

Eaton is a registered trademark of Eaton Corporation. ©2010 Eaton Corporation. 11633_0610

ResearchIT 5
ResearchIT

Newer Power and Cooling Technologies


Are Making Inroads in the Data Center, but
More Can Be Done
This research uses the electronic polling results from the 2009 Gartner Data Center Conference to examine some of the newer
power and cooling technologies used in today’s data centers. Infrastructure and operations (I&O) management can benefit from
knowing what other data centers are doing with newer power and cooling technologies.

Key Findings • Use free cooling in your The presentation “A Look allow more compute capacity
• Only half the respondents’ data center to improve the at Data Center Power and to be installed in the same
data centers depend efficiency of your cooling Cooling Technologies Present power envelope. In-row cooling
on computer room air solution and to lower your and Future” was based on provides cooling or extra cooling
conditioning (CRAC) power demands if your the “Hype Cycle for Data directly to the cold aisle of a
units alone to cool their location will allow enough Center Power and Cooling row of servers. Cooling units
equipment. hours/days of sufficient Technologies, 2009.” We have may be interspersed within the
temperatures. compiled Q&A relevant to the row of servers, or an overhead
• Almost one-third (29%) of use of some of the newer cooling unit may be installed
the respondents say they • When looking to replace or power and cooling technologies directly over the cold aisle. In-
have plans to start using add UPS systems, expand in the data center, along with rack cooling moves the cooling
free cooling solutions your options by considering some general observations and closer to the server by providing
during the next two years. the benefits offered by analysis of the polling results. a cooling unit per rack to cool air
alternatives to battery Of the more than 200 attendees flowing in from the cold aisle,
• While most respondents’ backup power systems. at the session, approximately using a rear-door cooling unit
data centers use 150 responded to the polling to cool air flowing out of the
batteries as the backup ANALYSIS questions. server rack, or by a complete
power source for their This research examines the self-contained rack with internal
uninterruptible power results of polling questions Most data centers have only cooling and airflow. These direct
supply (UPS), a growing covering power in the data used room cooling with CRAC cooling systems can provide
number (11%) of center issues asked at the units placed around the edge supplemental cooling support
respondents are looking at Gartner Data Center Conference of the computer room, with an to room cooling, or provide the
battery alternatives. held in Las Vegas, 1 to 4 underfloor air plenum. As data total cooling solution with or
December 2009. More than centers install higher-density without a raised floor.
Recommendations 1,500 data center professionals, servers, there is a need to move
• When designing a new Gartner analysts and industry the cooling source closer to We asked: “What computer
data center or upgrade, experts discussed a host of the servers to increase cooling room cooling solutions have you
always include in-row and issues and challenges. As part efficiency. Air movement is adopted in your data centers?”
in-rack cooling as a cooling of the conference, electronic a power challenge for data See Figure 1 for the responses.
solution option. polling devices were made centers, as the power required
available during sessions, with to increase cooling through The results show that the higher
• To allow for liquid cooling selected questions inserted in increased air velocity follows a density servers, along with
flexibility, install drains, each presentation. Although we cube law. their requirement for greater
leak detectors and dams recognize that the respondents levels of cooling, are changing
that would allow for liquids may not necessarily represent The biggest cause of cooling the design of data centers.
to be placed anywhere in a statistically significant inefficiency in a data center is Only half the respondents’
the room, as needs arise distribution, we believe the inefficient air paths. Short air data centers depend on CRAC
and provide plenums or results of these polls will paths are more efficient than units alone. Forty-two percent
overhead hangers that will be of interest to our clients. long air paths that allow mixing of the respondents are using
support the installation of Polling results from previous of inlet and outlet air. Therefore, in-row cooling solutions, with or
pipes later on, allowing conferences have tracked very in a modern data center, the without other types of cooling,
you to delay committing close to observed and reported shortened air paths offered by and 15% have made use of
to specific pipe sizes and results. in-row and in-rack cooling can in-rack cooling solutions, with or
types. make a significant difference without other types of cooling
in energy consumption, and solutions.

6 researchit
ResearchIT

Figure 1. Computer Room Cooling Solutions Used in the Data Center to keep IT equipment
running through short power
disruptions.
None of the new technologies 45

Power management software 34 • Bridges the time needed to


CFD analysis 19
start backup generators for
longer power disruptions.
Thermal storage 12

In-chassis cooling 12 • Allows time for controlled


shutdown if no generators
Absorption/Adsorption chillers 6
are available.
Combined heat and power (CHP) 6
The UPS has also taken
On-site solar 4
over the role of providing
Fuel cells 3 conditioned power and isolating
On-site wind turbines 2 building power from noise and
waveform distortion caused by
0 5 10 15 20 25 30 35 40 45 50 the equipment. In older UPS
Percentage of Respondents systems, energy efficiency
curves fell off dramatically at low
Source: Gartner (March 2010) loads. Because of this, as well as
the growing interest in green IT,
many data centers are looking to
buy new, high-efficiency UPS to
During our one-on-one sessions • Air-side economizers use Two-thirds of the respondents replace older ones.
at conferences and inquiries outside air directly when do not use air-side or water-side
during the year there’s been that temperature is lower economizers to help cool the The newer class of UPS uses
a dramatic increase in the than the temperature of data center. The polling results a flywheel or ultracapacitor for
questions about in-row and air needed to cool the data show this will change during its backup power, rather than
in-rack cooling. Data center center. For best results, the 2010/2011 time frame. batteries:
management was reluctant to the air must be filtered Almost one-third (29%) of the
move liquid cooling closer to and have its humidity respondents have plans to start • Flywheel technology
the servers. CRAC units using adjusted (if necessary). using free cooling solutions has been around for
chilled water from the building Also, hot air expelled from during the next two years. Major decades, and is based on
cooling plant were not perceived the data center may be factors that will impact the use the acceleration of a rotor,
as liquid cooling, as they were needed to help regulate the of free cooling are: or flywheel, to a very high
on the periphery of the machine temperature of the outside speed, thereby maintaining
room. This attitude is changing, air entering the data center • Location of the data center energy in the system as
because of the increased cooling to prevent the temperature (hours/days available for free kinetic energy. The primary
needs, and the improved liquid from dropping too low. cooling) power source jump-starts
cooling technology and sensors the flywheel spinning. This
that have reduced the risk of • Water-side economizers • Temperature at which the builds kinetic energy based
leaks. use outside air to help cool data center is run on the mass of the flywheel
the liquid (water, glycol) and the speed at which it
Free cooling is another piped into the data center • Improvements in the rotates.
technology associated with to be used by cooling economizer technology
cooling efficiency. It is not free equipment. With water-side • Ultracapacitors use
of charge, but can reduce the economizers, there is no There has been a noticeable nanomaterials to store
cost of cooling significantly. need for filtration or extra uptick in inquires about free static charge on either side
Data center free cooling reduces humidity controls, because cooling solutions; but the 39% of a vast surface area of
the chiller burden, partially or the outside air is not being of respondent who said they insulating material. The
totally, to cool a data center by introduced into the data have no plans to use free cooling voltages are low, but the
using the temperature of outside center. Some data centers is higher than we expected, charge density is high. The
air or other naturally occurring are experimenting with given the improvements in technology continues to
cooling capability. Free cooling innovative approaches based the technology allowing many evolve, and ultracapacitors
is not a new concept. The use on favorable locations, such organizations to get some will continue to enter new
of a cooling water tower is an as deep-lake water cooling value from free cooling in most markets (such as UPS), as
example of using outside air to and ocean-water cooling. locations. capacity increases and costs
help cool water that is used in decrease.
We then asked: “Do you make Next, we looked at a major part
cooling large buildings and data
use of free cooling in your data of the power path: the UPS. The Some of the reasons people
centers.
center?” See Figure 2 for the modern UPS: are looking to replace batteries
Two types of economizers are responses. are that batteries take more
• Provides data centers with
being used today: space, need to be replaced
emergency backup power
every two to five years, are not

ResearchIT 7
ResearchIT

Figure 2. Free Cooling in the Data Center We also wanted to get a sense
of how organizations were
exploring emerging technologies.
Air-side economizer 12
We asked: “Which of the
following power and cooling
Water-side economizer 14 technologies do you currently
use?” and presented the list
Air- and water-side shown in Figure 4. Participants
3 were asked to choose all that
economizers
applied.
No, but plan to use within 2
29
years Power management software
— software designed to provide
No. No plans to use 39 low-level monitoring of energy
consumption for all IT-related
equipment, including compute
Don't know 3
resources and infrastructure
components. These products
0 5 10 15 20 25 30 35 40 45 are beginning to be integrated
Percentage of Respondents with traditional inventory/
configuration and performance
Source: Gartner (March 2010) management systems. We
recommend that you investigate
these integrated, data center
Figure 3. UPS Systems in Use
infrastructure management
(DCIM) tools to gain insight and
Battery-backed UPS 88 drive performance throughout
the data center, including data
center assets and physical
Flywheel UPS 5
infrastructure.

Ultracapacitor UPS 1 Computational fluid dynamic


(CFD) analysis — uses
Combined battery and
4 numerical algorithms to analyze
flywheel UPS
and model the flow of air around
Combined battery and data center hardware surfaces
1
ultracapacitor UPS
such as servers and storage
0
systems. Organizations can also
Don't use a UPS
use CFD analysis to determine
the optimum layout of hardware
Don't know 1
in a data center. CFD analysis is
not as useful for newer cooling
0 10 20 30 40 50 60 70 80 90 100 technologies, such as in-row and
Percentage of Respondents
in-rack cooling, where air flow is
more concentrated.
Source: Gartner (March 2010)
Thermal storage — a
mechanism that enables
cooling power consumption
environmentally friendly (can give some movement to the use of started and come to full power. to be timeshifted, from peak
off gases and require special flywheel backup power (9%) and Although this isn’t an issue daytime hours to off-peak
disposal), and are difficult to just a trace of ultracapacitors with modern generators, some nighttime hours. Most utilities
monitor for possible failures. (2%). Ultracapacitors still have users feel the window provided offer discounted rates for off-
to improve capacity, cost and by flywheel (and ultracapacitor) peak electricity, because they
To determine if the use of maturity (combined with a data- systems is too small to provide can deliver it from their most-
nonbattery technology with UPS center-level UPS) to gain usage; extra time if a generator fails efficient power plants. Increasing
for power backup was growing, flywheel technology, however, to start on the first try. Some sensitivity to electricity rates will
we asked: “What type of UPS appears to be gaining traction. flywheel UPS systems integrate drive adoption of the technology.
systems do you use?” See a 24 volt, high-current output, The challenge is the installation
Figure 3 for the responses. There is one major inhibitor which is enough to bring a and maintenance of the thermal
to both options. Flywheel and generator to speed in a few storage tanks.
While most respondents’ data ultracapacitor systems provide seconds. We will continue to
centers use batteries as the only seconds of power (for monitor the growth and maturity In-chassis cooling — this refers
backup power source for their example, 15 seconds), leaving a of these alternatives to batteries. to emerging technologies that
UPS, we are starting to see short time for generators to be

8 researchit
ResearchIT

use liquids, rather than air, to Figure 4. Which of the following power and cooling technologies do you currently use?
transfer heat from the processor
and other components to an
external cooling system. The None of the new technologies 45
benefits are: Power management software 34

• Significantly reduced airflow, CFD analysis 19


reducing energy costs and
Thermal storage 12
noise
In-chassis cooling 12
• Smaller heat sinks, reducing
Absorption/Adsorption chillers 6
weight and cost and
increasing reliability Combined heat and power (CHP) 6

• Higher processor operating On-site solar 4


power, enabling higher Fuel cells 3
performance in the same
form factor On-site wind turbines 2

Absorption/adsorption chillers 0 5 10 15 20 25 30 35 40 45 50
— use a different mechanism Percentage of Respondents
than normal chillers (driven
by electric compressors), and
are powered by heat from Source: Gartner (March 2010)
gas burners or other sources.
Absorption/adsorption chillers
have complex thermodynamics centers. Depending on local business case for use with However, the power output is
and working fluid paths, but electricity costs, utility bill an individual data center. variable, and other challenges
relatively few moving parts. rebates and tax incentives, it include maintenance costs, the
Therefore, acquisition costs are may be economically viable Fuel cells — most common impact on migratory birds and
higher, but maintenance costs today. forms of fuel cells take hydrogen noise pollution.
are lower. Overall efficiency and and oxygen, which, when
carbon footprints are comparable On-site solar — solar cells are combined in a fuel cell, produce While many of these
to gas-derived electric power mature as an on-site power electricity, heat and water. technologies are just maturing
cooling systems. Expect to see source. There are challenges Data centers are reasonable for data center use, data center
a growing use of these in CHP with using on-site solar: contenders for fuel cell operation management should explore
systems. because of their 24/7 operation their use. The fact that 45%
• IT is a 24-hour operation, and opportunity to use waste or those polled have not used
Combined heat and power and solar cells only provide heat for cooling systems. any of the above technologies,
(CHP) — aka cogeneration. CHP power during daylight hours. including power management
is an efficient, clean and reliable Therefore, the facility still On-site wind turbines — software and CFD analysis,
approach to generating power needs full power feeds. intermittent electricity generated shows that there are still many
and thermal energy from a single by wind forces on spinning things that can be done to
fuel source. A CHP system • Solar cells deliver only about turbines that generate up to 2.5 improve data center power and
uses fuel such as natural gas 11 watts per square foot megawatts of power per turbine. cooling.
to produce heat and electricity under optimal conditions. This provides the kind of capacity
simultaneously. The electricity This low number is required for data centers. Source: Gartner RAS Core
can be used for running a data incompatible with modern Therefore, adding wind turbines Research Note G00174480, John
center, and the heat can be data center power density. to a rural data center is an R. Phelps, 3 March 2010
used for water or space heating While viable, it will take occasionally proposed solution
or cooling the data center and a unique situation and to data center power issues.
elsewhere. Technically, CHP
is a viable technology for data

ResearchIT 9
Power through high-density applications.

Eaton offers ePDUs with monitored


and switched technologies to power
through high-density applications.
Our monitored and switched ePDUs offer:
• Remote power monitoring of both voltage and current
• State-of-the-art software, allowing the user to aggregate
information from multiple ePDUs in one location
• Read Digital LED Ammeter for easy startup and
provisioning of servers
• Environmental monitoring for temperature and humidity
• Multiple configurations for individual on/off/reboot
control of up to 36 receptacles
• Highly customizable control interface

Download Eaton’s white paper,


“Optimizing Power Distribution
for High-Density Computing,” and
you’ll automatically be entered for
a chance to WIN a laptop case!
www.eaton.com/researchIT

10 researchit Eaton and ePDU are registered trademarks of Eaton Corporation. ©2010 Eaton Corporation. 11657_0610
ResearchIT

Power for the Data Center Is More Than a


Facilities Department Concern
This research uses electronic polling data from the 2009 Gartner Data Center Conference (DCC) to examine the changing power
environment in the data center. We look at the age of data centers, funding for data center power, the measurement and monitoring
of data center power, and the growing use of distributed power for the data center.

Key Findings ANALYSIS polls will be of interest to our centers are showing limitations
• One-third of respondents’ Gartner’s use of electronic polling clients, and, in the past, polling in space and their power and
data centers in the U.S. are in major conferences began results from the conference have cooling infrastructure. In a third
more than 20 years old, and with the 2001 Gartner DCC tracked close to observed and track session, “Getting Your Data
50% are more than 16 years and has grown since then. This reported results. Center in Shape for Green IT
old. research will examine the results Evaluation,” we asked attendees
of polling questions on data We have compiled the results the age of their primary data
• For more than 70% of center power asked at the U.S. of the questions relevant to center (see Figure 1).
poll respondents, budget DCC, held in Las Vegas from 1 power for the data center, along
responsibility for the data December to 4 December 2009. with general observations and The results show that most
center power bill resides in At this conference, more than analysis of the results. There data centers were built before
the facilities budget, but this 1,500 data center professionals, were more than 200 attendees the current higher-density
is starting to change. Gartner analysts and industry at “The Impact of Green on rack systems were a concern.
experts discussed a host of the Data Center” and “A Look One-third of the data centers
• Fewer than 50% of the issues and challenges. As part at Data Center Power and are more than 20 years old, and
respondents measure of the conference, electronic- Cooling Technologies Present 50% are more than 16 years
the power utilization polling devices were made and Future” sessions, with old. As another data point, a
efficiency (PUE)/data center available at track sessions, with more than 150 responding to separate kiosk survey conducted
infrastructure efficiency selected questions inserted in the polling questions in each at the conference, which was
(DCiE) of their data centers. each presentation. Although we session. open to all attendees at the
recognize that the respondents conference, indicated that, for
• Almost one-third of the do not represent a statistically A major concern facing many 70% of the audience, the oldest
respondents are sourcing significant distribution, we I&O managers is the age of their data center was more than
some of their data center believe the results of these data centers. Many older data
power from locally
generated power sources.

Recommendations
• Data center and facilities Figure 1. When was your current data center built?
managers must work closely
when designing new data
centers or data center During the past two years 13
upgrades to ensure that
the highest levels of power
3–5 years ago 16
and cooling efficiencies are
achieved.
6–10 years ago 13
• Data center managers
should plan on having the
cost of power included in 11–15 years ago 9
future budgets, if it’s not
already there.
16–20 years ago 17
• Even if PUE and DCiE
metrics aren’t perfect, you
Older than 20 Years 32
should begin to measure
your data center power
efficiency to get a feel for 0 5 10 15 20 25 30 35
how much improvement Percentage of Respondents
potential you have, because
you can’t manage what you Source: Gartner (February 2010)
don’t measure.

ResearchIT 11
ResearchIT

seven years old. This is in line compiled from the kiosk survey for data center power efficiency information about the potential
with the data shown in Figure — budget responsibility for the measurement in most data for improvement and a way to
1. Also, last year’s conference data center power bill has not centers is based on the work see the results of efficiency
results indicated that 80% of been the responsibility of the of the Green Grid with its PUE actions taken by the data
the respondents’ oldest data data center. With the increase and its reciprocal DCiE. These center. It is important to have a
centers were more than seven in power use, the rising cost of metrics measure the proportion power efficiency measurement
years old. The economic climate power and the growing concern of power consumed by the process in place because you
in 2009 caused many data center for greenhouse gas (GHG) IT load (some have called this can’t manage what you don’t
building projects to be deferred emissions, we are starting to “productive work,” but much of measure.
or canceled, worsening the see a shift toward data center it is nonproductive) versus total
problem. management becoming more power used, which includes Whether you measure PUE/
responsible for the cost and what’s used for non-IT load, DCiE — or something else, such
The age of most data centers efficiency of power usage in the such as cooling, or lost in as consumption trends — you
indicates that, during the next data center. The numbers show power distribution. We asked if need to measure it on a regularly
few years, companies may be that slightly more than one-fifth companies measured the PUE/ scheduled basis. Also, the more
building new data centers or of the respondents show the DCiE of their data centers, and, if often you measure, the better
renovating older data centers, data center power budget has they measured it, what was the you can manage consumption. In
because of the increase in recently shifted (6%) or will soon PUE/DCiE value they recorded the session “Getting Your Data
higher-density servers. If you’re shift (15%) to the data center (see Figure 3). Center in Shape for Green IT
running out of space, power or budget. With the data center Evaluation,” we asked how often
cooling capacity, things can be power cost moving from facilities The results show that fewer than the respondents measured and
done to avoid the need to build a to the data center budget, we 50% of respondents measure trended the energy consumption
new data center. However, if you expect to see greater emphasis the PUE/DCiE of their data of their data center (see Figure 4).
need to build a new data center, on data center design for power centers (44%). Twenty-seven
because of the new demands and cooling efficiencies. This will percent of the respondents who The above results show that
on power and cooling capacity also give I&O managers more measure it don’t know what the 25% of the respondents do
brought on by newer server, leverage in the design issues, ratings are, which would indicate not measure basic energy
storage, and communication because they’ll be paying the that, in their case, the results are consumption, much less PUE/
equipment, data center bills. Don’t underestimate how not widely distributed. Although DCiE. Of course, with the
management must work closely difficult this shift in budget the PUE/DCiE metrics are not results shown in Figure 2 that
with the data facilities group responsibility may be or how perfect measures of efficiency the budget responsibility for
to ensure that the data center dramatic the effects could be. (there is no component of power is more invested with the
design provides efficient power actual workload processed facilities department, this isn’t
and cooling capacity. Next, we looked at how data by the measured equipment), surprising. What is surprising is
centers measure their power they can provide valuable the low frequency with which
In the past, more than 80% efficiency. The standard used measurements are taken. The
of the IT departments weren’t largest, at 39%, is done monthly,
responsible for the power bill for
the data center. In most cases,
IT management was unaware Figure 2. In which budget does the cost for data center power reside?
of the magnitude of the cost
of power and its impact on the
data center. This, coupled with Facilities budget 64
not seeing the looming power
and cooling issues brought on Facilities, but moving to IT 15
by new high-density racks and
the impact of blades, meant they
had not been as concerned with Just moved to IT budget 6
efficient power and cooling in
the data center. Having access
to (or responsibility for) the bill Always IT budget 8
would have highlighted the
issue sooner, but not solved it.
Although this lack of data center Other 4
responsibility for the power bill
appears to be changing, for most
Don't Know 3
companies, it is still a facilities
concern. We asked where the bill
for power resides (see Figure 2). 0 10 20 30 40 50 60 70
Percentage of Respondents
These results confirm what we
had been seeing during inquiries
and are similar to the results Source: Gartner (February 2010)

12 researchit
ResearchIT

Figure 3. Do you measure PUE/DCiE for your data center? with only 17% taken at least
daily. With the growing emphasis
PUE <1.3 on power efficiency and newer
0 technologies that are providing
DCiE >77%
PUE 1.3–1.5 monitoring points at the device
5 level, we are starting to see
DCiE 67–77%
PUE 1.5–1.75 power management software
7 that will enable workload shifting
DCiE 57–67%
PUE 1.75–2.0 to better control power usage
9 when the workload slackens.
DCiE 50–57%
PUE 2.0–2.5
With this technology and
10 software, expect to see the
DCiE 40%–50%
frequency of measurement
PUE >2.5
1 change dramatically. Expect
DCiE <40%
to see power management
Measure, but don't know what it is 12 dashboards available that
continuously monitor power
Do not measure
56 usage down to the device level.
PUE/DCiE

0 10 20 30 40 50 60 The next question examines a


Percentage of Respondents growing trend — increased use
of distributed power generation
for data centers. Here, we asked
Source: Gartner (February 2010) about the source of power for
major data centers (see Figure 5).

Based on discussions with


Figure 4. How often do you measure and trend energy consumption of the data center? clients during the past two
years versus the poll results,
the results show there is
growing use of distributed
Every hour 10
(or locally generated) power
for data centers. Only 63%
Every day 7 of respondents use power
sourced from the utility power
grid only. Just 5% report using
Every month 39 just locally generated power,
and 26% of the respondents
use a combination of grid and
Every six months 10 distributed power. The use of
locally generated power stems
from several reasons. First,
Annually 9
some data center management
is becoming more concerned
Never 25 about the availability of power
from the standpoint of capacity
and from the standpoint of 24-
0 5 10 15 20 25 30 35 40 45
Percentage of Respondents
hour availability. We have also
talked with some companies
that have data centers in high
Source: Gartner (February 2010) power-cost areas, and have seen
multiple benefits from the use of
local combined heat and power
(CHP) systems. Also some data
centers are beginning to use
local, renewable energy sources,
such as solar, wind, geothermal
and tidal-generated power (see
Figure 6).

ResearchIT 13
ResearchIT

Figure 5. What is the source of power for your major data centers? We have seen growing
concern about green IT and
environmental issues, as
Use power grid only 63 evidenced by the increased
number of corporate social
responsibility (CSR) policies we
Grid augmented by locally have seen that have sections
21
generated on environmental sustainability.
Our final polling question
Locally generated concerned corporate initiatives to
5 use renewable energy sources
augmented by grid
for data center power, either
through locally generated power
Only locally generated
5 or programs to work with local
power
utilities to drive renewable
energy production.
Don't know 6
Fifty-two percent of respondents
have no renewable energy
0 10 20 30 40 50 60 70 initiatives (45%) or don’t know
Percentage of Respondents if they have one in place (7%).
Although only 21% have
renewable energy initiatives in
Source: Gartner (February 2010) place, 27% of the respondents
are actively looking at creating
such initiatives. Of those with
initiatives, 21% are working
toward sourcing more than 50%
Figure 6. Do you have an initiative to use renewable energy for the data center? of their data center power from
renewable sources.

No 45 The results of these electronic


polls show that power for the
No — but looking into 27 data center is moving into areas
that are well outside the normal
Yes — use at least 10% 7 facilities area. In the future, I&O
management will be taking a
Yes — use at least 20% 4 greater role in areas affecting
decisions about power for the
Yes — use at least 30% 1 data center.

Yes — use at least 40% 1


Gartner RAS Core Research Note
G00173986, John R. Phelps,
Yes — use 50% or more 8
5 February 2010

Don't know 7

0 5 10 15 20 25 30 35 40 45 50
Percentage of Respondents

Source: Gartner (February 2010)

14 researchit
Field service
you can trust.

Relax while we take care of your


UPS maintenance.
At Eaton®, our customers are the driving force behind everything
we do. We are committed to ensuring the ongoing health of every
Eaton UPS through our comprehensive service and maintenance
plans. Our team of rigorously trained field technicians strive
to keep your Eaton UPS in optimal health and
ensure that your business continues without
interruption.

Download Eaton’s white paper, “Maximize


your returns by choosing the best
service plan” and you’ll automatically be
entered for a chance to WIN a hammock!
www.eaton.com/researchIT
Eaton is a registered trademark of Eaton Corporation. ©2010 Eaton Corporation.
All rights reserved. #11632_0610_TN

ResearchIT 15
UNITED STATES
8609 Six Forks Road
Raleigh, NC 27615 U.S.A.
Toll Free: 1.800.356.5794

www.eaton.com/powerquality
©2010 Eaton Corporation
All Rights Reserved
Printed in USA
11713_ResearchIT
July 2010

Research IT is published by Eaton. Editorial supplied by Eaton. is independent of Gartner analysis. All Gartner research is © 2010 by Gartner, Inc. and/or its
Affiliates. All rights reserved. All Gartner materials are used with Gartner’s permission and in no way does the use or publication of Gartner research indicate
Gartner’s endorsement of Eaton’s products and/or strategies. Reproduction and distribution of this publication in any form without prior written permission is forbid-
den. The information contained herein has been obtained from sources believed to be reliable. Gartner disclaims all warranties as to the accuracy, completeness
or adequacy of such information. Gartner shall have no liability for errors, omissions or inadequacies in the information contained herein or for interpretations
thereof. The reader assumes sole responsibility for the selection of these materials to achieve its intended results. The opinions expressed herein are subject to
change without notice.

16

You might also like