Professional Documents
Culture Documents
A Thesis Presented to
Ohio University
In Partial Fulfillment
Master of Science
by
Dan Suriyamongkol
November 2002
THIS THESIS ENTITLED
“NON-TECHNICAL LOSSES IN
by Dan Suriyamongkol
___________________________________________________
Brian Manhire, Professor
___________________________________________________
Richard Dennis Irwin, Dean
College of Engineering and Technology
iii
ACKNOWLEDGMENTS
First, I would like to thank Dr. Brian Manhire, my advisor, for all of his support,
insight and invaluable help during the preparation and information collection for this
thesis.
There is a large amount of information in this thesis that would not be available
without the help from the following persons. Mrs. Prachumporn Bunnak, Acting Director
(PEA), authorized unprecedented access to PEA information and operations. Mr. Barvorn
information gathering effort at PEA excellently. Mr. Youngyuth Sonjaiyuth, Head of the
Three-Phase Meter Installation and Inspection Group at PEA, who provided me with
great insight into electricity theft and a priceless view from the field.
Randle, John H. Provanzana, and Jack E. Carr. The World Bank proved an invaluable
resource through the report [2] by the Energy Sector Unit, sent to me by Alfred B.
Gustone.
iv
TABLE OF CONTENTS
ACKNOWLEDGMENTS………..…………………………………...………………...iii
LIST OF FIGURES……………………………………………………..……………....vi
LIST OF TABLES………………………………………………………………...........vii
CHAPTER 1 INTRODUCTION 1
BIBLIOGRAPHY 58
APPENDIX A
Principles of Power Systems Analysis:
Basic Load Flow and Loss Calculations 59
APPENDIX B
Two-Bus Load Flow Analysis Programs in MATLAB 68
APPENDIX C
Transmission Line Specifications for PEA 79
ABSTRACT
vi
LIST OF FIGURES
2.4 Load Demands for the Two-Bus Power System from Figure 2.3 12
2.5 Profile of Load Power Factors for Test Power System in Figure 2.3 14
2.6 Energy Losses Calculated Using the Two-Bus Test System with
Bus 1 as the Slack Bus and then with Bus 2 as the Slack Bus 16
LIST OF TABLES
CHAPTER 1
INTRODUCTION
A news article estimated that electricity theft in the United States costs billions of
dollars a year1. Such estimates were the beginning of this research. Electricity theft is part
This research aims to investigate the nature of non-technical losses in power systems,
their sources, the measurement of non-technical losses, some measures taken by selected
In this introduction, a summary of the main parts of this thesis will be presented.
Chapter 2 deals with the simulation and calculation of losses in power systems and the
effects that NTL have on those losses. Various forms of NTL and the utilities’ measures
to counter them are presented and discussed in Chapter 4. Before that, special attention
will be given to the watt-hour meter and various ways to tamper with it in chapter 3. The
study of utilities’ handling and recording of NTL cases was made possible by the
information obtained in rural Thailand, while information on NTL and utilities’ reactions
in the United States was based on a series of e-mail correspondences with officials of
American Electric Power. Also, the World Bank provided some information on the
1
Bill Nesbit, "Thieves Lurk - The Sizable Problem of Electricity Theft", Electric World T&D,
www.platts.com/engineers/issues/ElectricalWorld/0009/, September/October 2000
2
effects of wide-scale occurrences of NTL in Eastern Europe and Former Soviet Union
(FSU) nations.
losses in electrical power systems, the logical first step is to understand the complete
picture of power systems losses. Power system losses can be divided into two categories:
Technical losses are naturally occurring losses (caused by actions internal to the
power system) and consist mainly of power dissipation in electrical system components
losses are possible to compute and control, provided the power system in question
consists of known quantities of loads. In this thesis, it will be argued that the distortion of
load quantities caused by NTL will distort the computations for technical losses caused
Non-technical losses (NTL), on the other hand, are caused by actions external to
the power system, or are caused by loads and conditions that the technical losses
computation failed to take into account. NTL are more difficult to measure because these
3
losses are often unaccounted for by the system operators and thus have no recorded
• Electricity theft
• Non-payment by customers
The most prominent forms of NTL are electricity theft and non-payment, which
are thought to account for most, if not all, of NTL in power systems. However, the other
two sources of NTL listed above are not analyzed thoroughly in this thesis, so their
The methods used to perpetrate electricity theft are discussed in Chapter 3. A few
Other forms of NTL may exist, such as unanticipated increases in system losses
due to equipment deterioration over time, but are usually ignored in any calculations.
System miscalculation on the part of the utilities, due to accounting errors, poor record
keeping, or other information errors may also contribute to NTL. These losses are
Technical losses in power systems are caused by the physical properties of the
components of power systems. The most obvious examples are the power dissipated in
transmission lines and transformers due to their internal electrical resistance. Technical
losses are easy to simulate and calculate; computation tools for calculating power flow,
losses, and equipment status in power systems have been developed for some time.
Improvements in information technology and data acquisition have also made the
In this thesis, a simple power flow calculation is used to study relevant aspects of
technical losses in a very simplified power system. The results of those simulations are
presented and discussed in chapter 2. The technical principles of power flow calculations
and loss analyses are briefly discussed in Appendix A, but more useful treatments of the
Also discussed in this thesis is the required information for successfully analyzing
power systems using load flow analysis, the practical availability of the said information,
and the effects of adding known non-technical losses to the simulated power system
analysis. Results from simulations in Chapter 2 suggest that the use of traditional
technical losses calculation tools would not be useful in NTL calculations. This is due to
5
the lack of information on NTL loads attached to power systems, as well as the lack of
All of the utilities and sources contacted by this author agreed that the dominant
component of NTL is electricity theft and non-payment [2], [5], [6], [7]. Electricity theft
money he or she will owe the utility for electric energy. This could range from tampering
with the meter to create false consumption information used in billings to making
unauthorized connections to the power grid. Common methods of electricity theft are
discussed in Chapter 3.
Non-payment, as the name implies, refers to cases where customers refuse or are
unable to pay for their electricity. Non-payment cases, magnitudes and some solutions are
presented in Chapter 4. All of the non-payment information provided here are courtesy of
the World Bank Energy Sector Unit [2]. Some solution approaches reported by various
organizations that contributed to the World Bank report [2] are also included.
6
Electricity theft is a problem that has long been known to utilities. Chapter 4
Energy Authority of Thailand, and American Electric Power, based in the United States
of America. The summaries include the impact of electricity theft on each company, their
procedures for dealing with electricity theft, and results of revenue recovery efforts by
The conclusions from Chapters 2, 3, and 4 are given in Chapter 5 and can be
• NTL are nearly impossible to measure using traditional power system analysis
tools. This is due to the lack of information on both NTL and the legitimate loads
in the system, which translates to insufficient inputs for any meaningful loss
calculations.
distort the billing information or direct connections to the power system. Each
• Utilities contacted for this thesis all agreed that electricity theft is the most
prominent form of NTL, while customer non-payment can also lead to significant
problems in areas that fail to handle the situation properly [2], [5], [6], [7].
7
• All of the personnel interviewed for this thesis (listed in the Acknowledgement
section) also stated that due to reasons given in Chapter 2, there have been no
Possible future work on this topic is also discussed in Chapter 5. The possible
possible cost-benefit analyses on the current measures favored by the utilities compared
with other possible measures, and more detailed examinations of the NTL causes listed
CHAPTER 2
losses and non-technical losses. Technical losses mean losses that happen because of the
physical nature of the equipment and infrastructure of the power systems, i.e., I2R loss–
or copper loss – in the conductor cables, transformers, switches, and generators. Loads
are not included in the losses because they are actually intended to receive as much
energy as possible. Technical losses can be calculated based on the natural properties of
components in the power system: resistance, reactance, capacitance, voltage, current, and
power are routinely calculated by utility companies as a way to specify what components
will be added to the systems. Though the data and tools needed for calculating losses in
power systems are available, current techniques have certain drawbacks regarding such
calculations. This issue will be addressed in the section “Technical Losses in Power
Systems” below. The effects of adding non-technical losses to a power system will be
examined in the section “Losses with Non-technical Losses Present” later in this chapter.
such losses is the power loss caused by resistance of transmission lines. The average
where Psource means the average power that the source is injecting into the transmission
line and Pload is the power consumed by the load at the other end of the transmission line.
This is a simple enough calculation, except that power and current are both time-
dependent functions and that energy – not power – is the quantity that gets translated into
b
Wloss = ∫ Ploss (t )dt (2.2)
a
with a and b as the starting and ending points of the time interval being evaluated,
time to make a reliable prediction of energy loss (Wloss). And power, in a single-phase
with P, V and I being the average power, rms voltage and rms current of the element in
question, respectively. The term cosθ is the power factor of the element in question,
while θ is the phase difference between the voltage and the current waveforms.
From the above it can be summarized that the information needed to calculate the
element in a power system has to be one of the following sets (all variables are single-
3.) Voltage, current and phase difference between the two, or P=IVcosθ
These sets of data and choices of calculations are the options that an engineer will
have for computing power losses in a load-flow analysis2. But in order to gain V or I,
both rms values, the voltage must be known at two ends of the element that is evaluated,
at all times or as averages. This means the terminals that feed consumer loads must be
appropriately monitored at all times using some of the more sophisticated meters that
could store and compute average and instantaneous values that the load-flow analyst is
interested in.
The information about the power sources and loads listed above are needed to
determine expected losses in the power system using load-flow analysis software. The
actual losses are the difference between outgoing energy recorded by the source (e.g., at a
substation) and energy consumed by the consumers, which is shown on the bills. The
discrepancy between expected losses and actual losses would yield the extent of non-
2
Load-Flow Analysis is a computational tool for calculating power flow in electrical power systems (more
details in [1]).
11
Bus 1 I Bus 2
Load
G
Transmission Line
Figure 2.1 above shows a simple power system with two buses (nodes), one a
generator, and the other a load. For the simulations undertaken for this research, the
voltage, current, power, and power factor of the generator have known values at the same
time intervals, and, consequently, the current going through the transmission line. The
loss in the transmission line is easily computed using the current and transmission line
resistance values. Information of the load’s power and power factor are unknown, but at
this point the information at the generator is sufficient to determine what’s happening to
Sload
I* = (2.4a)
Vload
With Sload, Vload, Ploss, I, and R are the load apparent power, load voltage, power
loss in the transmission line, current in the transmission line, and transmission line
resistance, respectively (all values are complex values), while I* is the complex conjugate
of the current. The same relationships hold when analyzing these quantities as phasors or
rms values. Any major calculations become unnecessary when I can be measured directly
12
and the transmission line properties are known, which is never true for practical power
systems. Companies that generate and distribute electricity usually measure currents that
enter and leave their facilities in order to measure the energy that is bought or sold. For
areas outside the companies’ facilities, i.e., residential or business consumer areas, only
However, the low voltage transmission systems (below 24,000 volts or 24 KV)
are not as thoroughly measured because of the costs of the added metering. This is the
reason power flow solutions are used to estimate the state the various points in the
system. Power flow analysis is generally used for specifying equipment ratings after
Finding the current in the one bus going out of a metered generator is simple, but
in reality there are often many interconnected buses and many more elements in the
system. Just expanding the two-bus characterization by one step would yield a three-bus
system shown in Figure 2.2 below. Using Kirchhoff’s Current Law to solve for the
I1 = I2 + I3 (2.5)
determine the current in Transmission Line 2 (I2), however, the current going into Load 1
must to be known. This means there has to be a meter at Load 1 with the same
Bus 1 Bus 2
I1 I3
G Load 1
Transmission Line 1
I2
Transmission Line 2
Load 2
Bus 3
More detailed analysis of technical losses and their calculations in practical power
with loads at both busses and one bus selected as a “slack bus”3 with constant voltage.
This configuration is chosen for simplicity. The bus with constant voltage is presumed, as
is the case with most systems, to be the one connected to the larger system that has a
relatively infinite supply of electrical energy with constant source characteristics. The
diagram for a two-bus system is shown in Figure 2.3 below where the electrical
3
The term “slack bus” refers to a reference bus (or node) in the system with known voltage and phase angle
necessary for analysis of the system. The slack bus is often treated as a source that can inject infinite
(relatively very large) power and energy into the system and maintain constant voltage and phase angle
throughout the analysis. In analyzing small power systems connected to larger systems, the slack bus would
be the point where the system is interconnected to the wider system that can inject large amount of power
and energy into the system of interest.
14
properties needed to complete a load-flow calculation for power loss in the transmission
line are provided below and in Appendix C. The load profiles for each of the two loads
Bus 1 Bus 2
Figure 2.3 – Single-Line Diagram of a Two-Bus, Two-Load Power System with Known
Load and Known Transmission Line Data (Each bus can be the Slack Bus)
500
450
400
Power Demand (KVA)
350
300
250
200
150
100
50
0
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
Time of day
Figure 2.4 – Load Demands for the Two-Bus Power System from Figure 2.3
From the system specifications discussed below, it can be seen that this test
system is a very simplified one numerically and conceptually. Each load has its own
profile, i.e., each load varies with time and has a different pattern over a period of 24
15
hours. To make the test loads more realistic they are represented as two sets of power
areas. The grey profile that peaks during the daytime and drops off at night represents an
The load peaks are at 500 KVA for load 1 and 350 KVA for load 2, which are
reasonable levels for loads connected through 750 KVA-rated and 500 KVA-rated
transformers, respectively. The average load demands are 291.67 KVA and 153.96 KVA
for load 1 and load 2, respectively. Load power factors are shown in Figure 2.5 below,
with average values of 0.83 and 0.78 for load 1 and load 2, respectively. Transformers are
omitted from the simulation program for simplicity’s sake. Transmission line resistance
and reactance values are taken from 22000-volt transmission line datasheets provided by
PEA (see Appendix C). The conductor size and line length were chosen arbitrarily from
the datasheet, with the maximum conductor size of 185 mm2 chosen to avoid overloading
the line. A line typical length of 2 kilometers (about 1.25 miles) was chosen arbitrarily.
Finally, the loads were assumed balanced between all three phases, to avoid
complex computing. This means that only the positive sequence impedance values need
1
0.9
0.8
0.7
Power Factor
0.6
0.5
0.4
0.3
0.2
0.1
0
10:00
12:00
14:00
16:00
18:00
20:00
22:00
0:00
2:00
4:00
6:00
8:00
Time of day
Figure 2.5 – Profile of Load Power Factors for Test Power System
in Figure 2.3
• Base Values4: 22000 Volts, 100 Ampere, 2.2 MVA, 220 Ohms
• Transmission Line:
4
The term “Base Value” is used in per-unit calculations; for more details, see [1].
17
The test system has been used to be a source for a simple load-flow calculation
program written in MATLAB to determine the losses for the transmission line (see
Appendices A and B). The results were later compared to those obtained using the Power
Education Toolbox© [10], and Power System Simulator© [11]. The specifications
provided about the loads are the following: power demands of the loads at various times
of the day over 24 hours; power factor values over the same time period; the averages of
power demands and power factors. The incurred transmission losses are shown in Figure
2.6 below. The trends suggest that load number 1 is an office or workplace with a peak
demand of 400 kilowatts and the load level being high during office hours. Load number
2 is presumed to be a residential area with a peak demand of 241.5 kilowatts and load
levels that rise around time for breakfast and dinner times.
In the case where bus 1 is used as the slack bus, the average power loss in the
transmission line is around 74.53 watts, while the power loss calculated using the average
As seen in Figures 2.4 and 2.5, the load profile changes according to the time of
the day and consumes a finite amount of energy. The load energy can also be represented
by a time invariant average demand value with the same amount of consumed energy
over the same amount of time. The point being made here is that since the utility bills
often only include energy, a number of vastly different chronological power profiles can
The MATLAB simulator was used to calculate the transmission losses for the
load demands and power factor for each hour, first using bus 1 as the slack bus, and then
with bus 2 as the slack bus. The results are shown in Figure 2.6 below. The losses based
on the average demand and power factor values were calculated only with bus 1 as the
slack bus, with results shown in Figure 2.7. The result is that the average of losses
calculated using the sum of data from individual times is not equal to the losses
calculated using the average values, as seen in Figure 2.7 below for the case where bus 1
is used as the slack bus. The reason for this inequality will be examined later in this
chapter.
2500
2000
Losses(KWh)
1500
1000
500
Time of day
Figure 2.6 – Energy Losses Calculated Using the Two-Bus Test System with
Bus 1 as the Slack Bus and then with Bus 2 as the Slack Bus
In the case where bus 1 is the slack bus, the total energy lost in the transmission
line each day is 6439.983 kilowatt-hours, while the energy computed using the average
power and power factor turns out to be 4466.707 kilowatt-hours. The difference is about
19
1973.276 kilowatt-hours a day (30.64 % of actual loss) or, at February 2002 prices in
25000
20000
15000
10000
5000
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
No. of Days With Identical Load Power Profiles (Days)
Figure 2.7 – Energy Losses in the Two-Bus Test System and a Comparison between the
Average Losses Computed Using the Detailed Load Schedule and Losses Computed
from Average Power. (Note: data shown as straight line to illustrate the different levels
when using different slack busses)
availability of information. And the information on the loads can be obtained either by
the customer monitoring the load or the utility monitoring the junction where the load is
because average values are shown to be inaccurate for calculating real losses. The
5
Energy rates are published by American Electric Power at www.aepcustomer.com/tariffs/default.htm
20
average values of power factor and voltages used to compute the losses in equation 2.4a
and 2.4b, for example, are meaningless because power factor and voltages may not peak
The nature of most loads means that the current values must be taken at intervals
small enough to make an accurate representation of the actual load characteristics. This is
where the measurement of loss in transmission lines gets complicated. The meters
required for useful measurements of current or power factor are significantly more
expensive than the simpler kind that only records consumption over time. Meters that can
record a load power profile are used mainly at substations, power plants, and by large
consumers that manage their consumption. Most locations with these meters give
accurate descriptions of losses in high-voltage power lines where there is very little, if
Transmission and distribution line sections that are most vulnerable to theft are
the medium- and low-voltage lines that connect to most of the consumers. These lines are
numerous and usually highly interconnected, which means that isolation of an area for
calculation is difficult. The two-bus calculations above are done with one of the buses
held constant, and there must always be a slack bus with constant known properties in
order to run load flow analyses. In medium- and low- voltage subsystems, however, the
bus voltages are often shifting along with consumer demand changes and even voltage
At this point, it is getting clear that making calculations for expected losses
accurately is nearly impossible in practice. This is because the data required – at least in
Thailand’s case – is very difficult to gather. Once again, refer to the list of possible ways
to calculate power above to see the data needed. The obstacle here is that meters installed
and used by Thailand’s utilities are all old models that only record peak power and
energy in kilowatt-hours for household loads. Even the industrial meters only record the
worst-case power factor, which has no bearing on an average – much less record a profile
of – power and power factor. Some meters record demands (power) at peak hours, which
again have no relationships with an average value or values that are usable in load flow
analyses.
The way to obtain a fairly accurate value of average load demand is to utilize the
information the utilities use to calculate the electric bills. The calculation requires energy
consumption accumulated up to the beginning of the time period (usually a month) and
the consumption accumulated at the end of the time period. The accumulated
consumption at the end of the period is subtracted by the accumulated consumption at the
beginning of the period. The result is the total consumption during the time period in
kilowatt-hours, and the portion of the bill for energy consumption is based on this
number.
The average demand for that same time period is the total energy consumption
divided by the length of the time period, in seconds. This information is always available
22
for metered loads, because it is what the utilities’ revenues are based on. For example, a
load that has the consumption information listed in Table 2.1 would have the average
Calculation results
Total time elapsed: 2,501,730 Seconds
Total energy consumed: 76,055 Kilowatt-hours
Average demand: 109,459 Watts
The average demand is not something difficult to find, as seen above, but the
problem for using this in load flow calculations is that the corresponding power factor
must be found. Power factor, as mentioned earlier, is not a quantity that is recorded by
most meters. The high-voltage or high-demand meters that record power factor exists
mainly in utilities’ installations or very large loads, while medium-sized loads often
record only the worst-case power factor for the purpose of billing, which is not useful
Non-technical losses are difficult to quantify. They refer to losses that occur
independently of technical losses in the power system. Two easy examples of sources of
such losses are component breakdowns that drastically increase losses before they are
replaced in time, and electricity theft. Losses incurred by equipment breakdown are quite
rare. These include losses from equipment struck by lightning, equipment damaged by
time, the elements and neglect. Most power companies do not allow equipment to
breakdown in such a way and virtually all companies maintain some form of maintenance
policies. Equipment failures due to natural abuses like snow and wind are also rare, for
equipment is selected and infrastructure designed with local weather and natural
phenomena considered.
Non-technical losses can also be viewed as undetected load; customers that the
utilities don’t know exist. When an undetected load is attached to the system, the actual
losses increase while the losses expected by the utilities will remain the same. The
increased losses will show on the utilities’ accounts, and the costs will be passed along to
an NTL load is added to the load at bus 2, the load that exhibits patterns similar to a
housing load, as implied by the hours that load activities increase and decrease. The
reason this load is chosen is that most NTL cases in reality are found in residential areas
From the technical loss analysis above, the effects of an undetected load attached
to one of the buses in the two-bus test system can be measured by adding extra demand
values to one of the loads and evaluating the changed losses. The extra load may be
simulated in a simplistic way by adding a profile of demands to the bus 2 load in the form
of adding VA values to the original demand and reducing the total power factors by
subtracting a power factor “contribution” for each value of added load. The pf
contributions chosen here were negative because the NTL load is assumed to be
inductive, i.e., motors or light fixtures. The profile of the added NTL and the total load
and the pf contribution to the load pf at bus 2 are shown in Figure 2.8 below. The
simulation is run with bus 2 as the slack bus. The NTL pf contribution is negative at all
After the simulation was completed and evaluated, some notable results were
evident. First, the increase in load demand and the increase in transmission losses were
not at the same levels. This is caused by the power factor contribution of the NTL load.
Indeed, the losses increased at a greater rate than the loads. On average, the load VA
increased by about 12.67 KVA, or about 7.9 per cent, while the losses had an average
increase of 23.39 per cent. The average loss here is computed by averaging the overall
It can be seen from Figure 2.9 below that the increase in demand caused by NTL
would also increase transmission line loss disproportionately. Even though the increase in
25
transmission loss places a greater burden on the transmission equipment, the greater
cause for concern would be the NTL load itself. During a 24-hour period, the increase in
transmission losses amounts to about 771 kilowatt-hours a day, or about $38.59. The
costs of the NTL itself during the same time period is much higher at 675,953 KW-h a
400000
350000
300000
Demand, VA
250000
200000
150000
100000
50000
0
10:00
12:00
14:00
16:00
18:00
20:00
22:00
0:00
2:00
4:00
6:00
8:00
Tim e, Hrs.
0:00 2:00 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00
0
Contributions
-0.005
Negative pf
-0.01
-0.015
-0.02
Time, Hrs.
Figure 2.8 – Demand and Power Factor Changes at Load 2 Caused by Non-Technical
Losses
26
50
45
40
35
Increase, %
30
25
20
15
10
5
0
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
Time, Hrs.
350
300
250
Losses, Watts
200
150
100
50
0
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
Time, Hrs.
The transmission line losses are very small compared to the loads themselves, but
the increased losses should not be ignored because they mean power dissipated in the
transmission lines as heat. When the lines get overheated, serious consequences can
follow, from loss of material strength to the weakening of insulation – possibly dangerous
The most noticeable effects of NTL, of course, are the monetary costs. In the
simulation results above, the load at bus 2 amounts to about $ 503,604 a day and the NTL
costs the utilities about $ 33,797 a day. The transmission costs due to the NTL, about $
38.59 a day, are just the transmission costs for the two kilometers of transmission lines
used in the simulation. In reality, the transmission costs would be similarly increased all
along the supply path back to the power plant, which could mean a very significant
increase depending on the distance. Table 2.2 below provides a summary of the results
obtained by the simulation of the two-bus system and the effects of NTL.
Note that once the NTL itself is taken into account, the discrepancy caused by
using average power to compute transmission losses becomes small, $4 out of nearly
$34,000. This is one of the reasons that the utility departments that work on electricity
theft interviewed for this research did not seem interested in using load-flow software.
28
Table 2.2 – Summary of Effects of Adding NTL to the Two-Bus Test System
Total daily losses Computed for each Computed using
hour in the load profile average demands & pf
Transmission losses without NTL, 6,439.98 4,466.70
KWH
Transmission losses with NTL, 7,211.57 5,169.48
KWH
Load demand at bus 2 without 10,061,280 10,061,280
NTL, KWH
Load demand at bus 2 with NTL, 10,737,230 10,737,230
KWH
Total increased losses, KWH 676,721.59 676,652.78
(increased load plus increased
transmission loss)
Total increased losses, $ 33,836 33,832
The last issue to be addressed in this section is who pays for the NTL costs. The
transmission and distribution costs in the United States are calculated as part of the
customers’ bills, while in Thailand the customers are usually charged a single flat energy
rate that includes all services. The US utilities have to “un-bundle” the charges because
widespread deregulation in various states has made the generation and distribution
This means that in the US, the transmission and distribution losses that increased
due to NTL would be charged either to the existing customer whose power lines are
illegally tapped, or the utility, depending on the method of theft (see Chapter 3 for
details). Who pays for the NTL loads depends on how the NTL loads are connected to the
power system. If the NTL loads are connected to the system’s transmission lines before
they reach the customers’ meters, the utilities will assume the costs of the NTL loads.
However, if the NTL loads are connected at a point beyond innocent customers’ meters,
29
the customers will be stuck with the transmission costs and, more seriously, the increased
loads. In Chapter 3, there are lists of various types of electricity theft that include both
systems as a whole using existing analytical tools would be possible only if information
about the NTL loads themselves is available to the analyst. The information would have
to include either the NTL loads’ power consumption profile comparable to the legitimate
loads being analyzed at the same time, as well as the NTL power factor, or power factor
that NTL cases cannot be directly measured because of the information gathering effort
required. After all, the people who make illegal connections to the power system are
unlikely to participate in any form of survey freely when their own illegal actions would
come to light.
30
CHAPTER 3
ELECTRICITY THEFT:
In some areas, the loads are not even metered or are metered communally [2], rendering
any loss calculations – technical or not – for that area useless. The approach used by both
utility companies contacted [2], [5], [6] involves primarily involves field staff monitoring
meters and access points in the system on a regular basis (see Chapter 4 for more details).
Sometimes this involves regular meter readers receiving special training for spotting
irregularities, and sometimes – when high voltage and large consumption is involved – it
involves meter technicians making dedicated meter and transformer inspection trips (see
Chapter 4).
The reason that meter inspection is the main method of NTL detection is because
the utilities consider electricity theft to be the major source of NTL and the majority of
electricity theft cases involves meter tampering or meter destruction [2], [5], [6]. The
term “meter” used in this and other chapters refers to the watt-hour recording meters used
in virtually every household to record and calculate electric bills by utility companies.
31
The principles of operation for watt-hour meters essentially have not changed
since the 1880s and the 1890s, when the watt-hour meter was invented [3]. The basic
principle for a single-phase energy measurement meter, first commercially used in 1894,
is as follows. First, there are two coils that produce electromagnetic fluxes: a coil,
connected across the two leads, that produces a flux proportional to the voltage and a coil
connected in series with one of the leads that produces a flux proportional to the current.
The dot product of those two fluxes creates a force proportional to the load power. An
illustration of the basic components of the watt-hour meter is shown in Figure 3.1 below.
which reflected the growing power industry in the late 19th century, is chronicled in detail
in [3].
In early designs, such as the ones shown in Figure 3.2 below, the meters were not
enclosed and all the parts and the meter installation were easily accessible to anyone.
However, as early as 1899, the minutes of meter committees of the Association of Edison
Illuminating Companies [meter paper] showed that electricity theft was a concern early
along with other efficiency and accuracy improvements – were added [3]:
This suggests that the problem of electricity theft has obviously been around almost as
long as power systems have been around. Modern meters, such as those in Figures 3.3
below, are relatively well enclosed and have seals that would reveal tampering. However,
theft can and does occur. Most utilities train their staff to spot tampering, but sometimes
the access to the inner mechanisms can be achieved with a very small hole, possibly
drilled using small tools and done at less obvious parts of the enclosure [7].
33
Figure 3.2 – Early recording meters: Sangamo Gutmann type A (c. 1899-1901) watt-hour
meter, left, and Westinghouse ampere-hour meter by Shallenberger (c. 1888-1897), right
(Source: David Dahle, www.watthourmeter.com, 2002)
Figure 3.3 – Modern recording meters: Schlumberger J5S (1984), and General Electric I-
70S (1968) (Source: David Dahle, www.watthourmeter.com, 2002)
34
There are two main categories for methods of electricity theft: directly connecting
an unregistered load to a power line, and tampering with a registered load’s meter in
order to reduce the size of the bill the utility charges that load. Once the meter seals are
broken, there are many things that can be done to the meter to slow or stop it. Below is a
list of various methods of electricity theft recorded by the Provincial Energy Authority of
High voltage three-phase watt-hour meters are installed throughout the PEA
system to monitor loads that consume high volumes of energy requiring high voltage.
Three-phase watt-hour meters use the technique known as the “two watt-hour meters”
connection to measure consumption. Because the load is connected with high voltage and
consumes high current levels, the current and voltage sensing are achieved by using
current transformers (CT)6 and voltage taps, respectively. The schematic that illustrates
6
A current transformer is a device that outputs a current proportional to the load current being measured,
enabling the meter to measure the load without subjecting it to large current and power levels.
35
Current
Transformers
(CT)
3-phase
Load
Incoming
Connection
Voltage Taps
Tampering with terminal seals is by far the most common method of meter
violations, because the terminal seals are easy to reach, located immediately below the
meter itself. Once the terminals were broken, it is be simple to connect one of the control
wires or CT wires to ground, making it appear to the meter that at lease one phase does
not show voltage or current. The cases of seal tampering, both terminal and meter seals,
refer to cases where seals were broken but no visible tampering was done to the meters or
Breaking control wires Control wires refer to the secondary wires of the current
transformer (CT). Meters for large loads measure high currents and must use CTs to step
the current level down to make it compatible with the components in the meter. Once the
36
insulation of the control wire is broken, external taps could be connected to reduce the
current going into the meter, causing the meter to read less current than reality.
Tampering with meter seals is another common form of violation, tampering with
meter seals means the person now has access to the meter itself. There are many ways to
Shorting control wires Like breaking control wires, this would divert the current
reading in the meter. In this case the current going to the meter would be zero. The effect
on the meter is immediate and obvious: with zero-current, the power and energy readings
Breaking the voltage taps Voltage taps in the meter housing allows the meter to
read the voltage of the load. Once these are broken (or shorted to ground, or have another
line connected to it), the reading the meter gets is distorted from reality, reading a lower
voltage in cases of electricity theft. In the unlikely event that the person wants the meter
to read higher values, the voltage taps could be connected to a higher voltage level, and
result in higher consumption readings. Many meters would not work properly or would
be damaged by this type of action, because the internal equipment must operate within
is to bypass the meter altogether. The major obstacle to this is that most high voltage
loads are built and connected at the request of the customers, such as a new shopping
mall asking for 12-kV lines to run to the back of the property to keep the front clear.
Since the customers are the ones who ask for the connections, direct connections like this
would be fairly easy to discover. Also, not many electricians would like to subject
themselves to a “hot” high voltage line without the power company there to assist with
safety.
Tampering with the meter Once the meter seals are broken and there’s easy access
to the meter inside the housing, and there are several things that can be done to slow or
stop the meter readings. A common way is to mechanically obstruct the spinning disc and
the axis that does the recording. Another popular action is to turn back the dials that bill
collectors eventually read. Obviously this wouldn’t work for digital-display meters, but
all of the PEA-installed meters in Thailand are spinning disc type manufactured in the
1980s or before.
Switching CT wires This is a subtle and effective way to reduce electric bills.
Many models of three-phase meters use only two current transformers (CTs) to read
current data from phases A and B, and assume the load is balanced between all three
phases. In reality, large facilities like factories or offices have unbalanced loads.
Depending on the engineer who designed the load connections, this imbalance could vary
38
between 10 and 20 percent of the most heavily loaded phase. C phase is almost always
the phase with the least load and lowest power factor, which is why CTs are connected to
the A and B phases. By switching the CTs or the wires from their secondary windings,
the meter’s current reading is altered. Switching A and B phases would result in a
reversal of phase difference seen by the meter, affecting the power factor reading, and
power/energy reading. If the CT from one of the phases is removed and placed on phase
the beginning of the chapter. The parts of the meter where tampering often occur are
Voltage
Sensing
Element Tampering
with the
Neutral Line
Disrupting
Current
Spinning Disc
Sensing
Element
Figure 3.5 – Parts of a Single-phase Watt-hour Meter Where Tampering Often Occur.
(Source: Bud Russell, http://www.themeterguy.com/Theory/watthour_meter.htm, 2002)
39
Direct connection to the power grid Since the meters and equipment in this
section are in the 220-volt system, where customers are mostly houses and small
businesses, a direct connection to the power grid is much easier than the high-voltage
system. Well, at least safer; a pair of rubber gloves could be all the necessary protection
and a ladder and knife all the necessary tools, as opposed to climbing up HV lines five
stories up on steel masts and being careful not to get tangled in other cables below or
inadvertent electrocution. This is by far the most common method here, used a lot by
street vendors and shantytowns. In fact, some of this writer’s temporary neighbors on a
Using alternate neutral lines The single-phase system often has only one wire
going into a house, the “hot” line. Neutral is usually grounded (electrically connected to
the earth) and is sometimes provided by the foundation of the house (or “location”, to be
more generic). So if a person could manage to use a small transformer and use that as the
“neutral”, the meter that uses the very same neutral source would read the incoming
the system voltage becomes the phase-to-phase voltage, at 240 or 380 volts, depending
Meter tampering/breaking seal is basically the same thing that happens to the HV
meters, since PEA uses meters that are quite aged for the low-voltage consumers, too.
Other methods of electricity theft include: tapping off a nearby paying consumer,
damage done to meter enclosures, and using magnets to slow down the spinning discs in
There are also many other methods for stealing electricity that have been
circulated on the Internet recently. Some of the suggested methods are not feasible, while
others may require too much effort or are outright dangerous [7]. This author has found
some Internet message boards full of possible methods to distort billing information at
the consumer end, such as using a “Tron Box” – a circuit to change the phase of one of
Methods suggested in chat rooms even include some highly far flung ideas, such
as placing enormous coils around high voltage power lines to act as transformers with
ridiculously large air gaps [4]. Interestingly, these message boards were also used by
some utilities to detect electricity theft perpetrators and track them to see if any of the
individuals fall within their areas of coverage, in effect, operating an online sting
operation7.
7
International Utilities Revenue Protection Association (IURPA), www.iurpa.org, 2002.
41
42
CHAPTER 4
Cases of non-technical losses (NTL) are acknowledged and dealt with by all of
the local utilities officials and international institutions contacted for this research. These
(PEA and MEA, respectively); USA’s American Electric Power (AEP); and the World
Bank.
Utility companies with transmission and distribution (T&D) operations that were
contacted by the author were all engaged in some form of NTL reduction policy. PEA has
a set of guidelines to prevent and respond to electricity theft that will be discussed in
further detail. AEP has a Revenue Protection department dedicated to recovering lost
development in many countries, which bring them in direct contact with utilities and NTL
in local service areas. A summary of the World Bank’s experience with NTL in Eastern
European and former Soviet Union countries in the 1990s will be provided. Finally, an
NTL has been established with representatives from utilities around the world.
43
utility company that provides electricity to consumers in every area of Thailand except
for Bangkok and its suburbs, which are serviced by the Metropolitan Energy Authority
(MEA). Virtually all of PEA’s electricity is bought wholesale from the Energy
small amount of electricity is sold to PEA and other consumers by local generators
located in a few industrial complexes; their effects on the PEA power system is negligible
because these local generators distribute power over very short power lines that seldom
extend beyond the industrial parks that they occupy [5], [6].
Since the companies that handle virtually all the electricity generation and
distribution in the country are government-owned, the electricity industry can be easily
described as fully regulated. Electricity rates for various regions are determined by a
board of appointed directors for each of the distribution utilities (MEA and PEA). Their
prices, in turn, are almost exclusively influenced by the supply rates governed by EGAT.
With Thailand being a net importer of crude oil – the fuel of choice for starting most
generators, as well as the primary fuel for some generation – the prices of crude oil often
plays a big part in EGAT’s pricing policies. In contrast, the coal and natural gas mines
are operated by other government entities, and hydroelectric dams are controlled by
EGAT.
44
The various energy sources constitute the majority of factors that govern the price
of electricity, and all of the entities controlling the sources have political and economic
considerations unique to their own organizations. For example, the hydroelectric facilities
are constantly negotiating deals with the Department of Agriculture, which operate the
reservoirs, while refineries owned by other government and private entities can alter oil
and natural gas prices based on their own agendas and situations.
The PEA determines its prices at board-of-directors meetings, where the prices of
PEA’s suppliers are the chief concern. The prices are also partly based on reports from
the Power Economics Division, the primary source of information for this research. And
the Power Economics Division is also the collection center for all the statistical
In the period from October 1999 to September 2000, PEA had a total of
earned 120,811 million baht (about US$ 2,730 million, by today’s exchange rates)
[5],[6]. The price of electricity averaged around 5.15 cents per Kilowatt-hour, nearly the
same per-unit price as American Electric Power’s residential prices in Athens, Ohio, in
January 20028.
8
AEP prices can be found on monthly statements to consumers, or at www.aep.com.
45
sizes, houses, temporary loads such as construction, agricultural irrigation loads that
include special releases of water from the dams, governmental and subsidized loads and
breakdown of number of consumers and consumption levels is shown in Figures 4.1 and
4.2 on the next page. It is worth noting that, in October 2000, businesses and industries
constituted about 7 per cent of the individual consumers, but consumed nearly three-
PEA services include transmission and distribution [5] to all provinces and areas
in Thailand not including the area covered by the Metropolitan Energy Authority (MEA),
which is the province of Bangkok. This means PEA covers most of Thailand’s areas,
loads. Figures 4.1 and 4.2 below illustrate the breakdowns of PEA customers sorted by
Small Businesses
Large Businesses 8%
42%
Medium Businesses
19%
Small Businesses
5%
The Provincial Energy Authority of Thailand (PEA) is the state enterprise that is
responsible for providing electric utility services for end users of all sizes in provincial
Thailand. The area of service includes 72 provinces of Thailand, excluding Bangkok and
a few suburbs. Its customers include: low-voltage loads such as housing, small and
medium businesses, and small industrial sites; high-voltage loads such as large
businesses, office complexes, large industrial sites, industrial parks, large housing
key indicator of NTL – remains relatively low. Between October 2000 and June 2001, a
total of 130 violations were found on high-voltage meters, and 2167 cases were found on
low-voltage meters. This number is very small compared to 11,399,150 total registered
users. Of course, this is a misleading presentation; registered users would not include
people who tap directly to the grid without meters. Some cases of violations may have
The PEA has a set of targets and schedules for inspecting meters. An inspection
team for high-voltage meters was observed for this research twice in July 2001; the team
includes inspectors from the central offices in Bangkok and drivers and local officials of
the PEA who are familiar with local sites and consumers. The local officials usually are
48
selected from the group of people who conduct inspections for transformers installed for
customers, which are invariably located near the meters that are the targets of inspection.
PEA has set guidelines and policies for dealing with electricity theft, as shown in
Table 4.1 below. Table 4.2 below shows the inspection schedules for the group
responsible for inspecting high-voltage (HV: 115 KV, 69 KV, 24 KV, and 12 KV) and
low-voltage (LV: loads with 380 V line-to-line) meters. The number of 220 V meters is
too great to make a dedicated inspection effort, so the inspection workload for those
meters goes to the unit-readers who are also trained to detect improprieties (see Chapter
3). Table 4.3 shows the regular schedule for reporting and deadlines for analyzing the
Table 4.1 - PEA Policies for Billing Customers Who Perpetrated Electricity Theft
(Source: PEA internal memorandum, June 2001)
Table 4.2 - Meter Inspection Protocols and Schedules for PEA (Source: PEA internal
memorandum, June 2001)
Item Goal/Schedule
1.) Regular Inspections
1.1) 69 KV and 115 KV meters 1.1) All meters inspected twice a year
1.2) HV and LV meters with CTs 1.2) All meters inspected once a year
1.3) LV meters 1.3) Each year, at least 50% of all
meters in each district will be
inspected
2.) Inspections of large customers with 2.) PEA’s task forces will compile a list
violation records and customers in and inspect all meters in these groups once
“high risk” businesses such as ice a quarter.
factories, hotels, etc.
3.) Inspections for large customers that 3.) All cases will be inspected within 30
are recently installed/changed days of the installation/change
4.) Large customers with irregularities
4.1) The comptroller reviews consumption
4.1) Checking and isolating cases with and separate the irregularities within 15
irregular consumption or irregular days of meter readings
behaviors for future meter checks
4.2) – Consumers with irregularities and
usage over one million baht
($25,000) a month will be checked
immediately
4.2) Checking for irregular – Low voltage meters are to be
consumption checked within 15 days of the
request for checks
– High voltage meters are to be
checked within 30 days
5.) Checking small consumers with 0 5.) – A list of consumers with 3
unit readings consecutive months of 0 unit
readings is compiled each trimester
– Within the following trimester, the
meters will be checked and the
reasons for the 0 unit reading would
be reported
50
Table 4.3 - PEA Guidelines and Schedules for Reporting Meter Inspection Results
(Source: PEA, internal memorandum, June 2001)
According to PEA estimates [6], the 127 high-voltage meter violations found
between October 2000 and June 2001 resulted in the recovery of 4,904,021.45 units lost,
or about $245,000. The low-voltage meter violations in the same time period added up to
about $155,000 in lost revenues. These numbers reflect only the cost of producing the
stolen energy without taking into account the cost of equipment damage and payments
for the staff charged with detecting these thefts. These numbers also do not reflect energy
lost due to undetected theft. Details of electricity theft are shown in Tables 4.4 and 4.5
below.
Table 4.4 - Meter Tampering Found Among High Voltage Consumers in Thailand
Between October 2000 and June 2001.
(Source: PEA, internal memorandum, June 2001)
Table 4.5 - Meter Tampering Found Among Low Voltage Consumers in Thailand
Between October 2000 and June 2001.
(Source: PEA, internal memorandum, June 2001)
The total amount of estimated recovered loss due to electricity theft in the period
between October 2000 and June 2001, about 8 million units [6], is very small compared
to the total losses of the system. The total losses of the PEA system is characterized by
subtracting the energy generated and purchased (system input) with the energy sold and
provided to some consumers without charge (system output), and the total losses amounts
to about 2.5 billion units, approximately 5.69 per cents of the system input. This means
the electricity theft found only accounts for about 0.32 per cent of the system losses, or
proportion of the system or even the total system losses, interviews with members of the
PEA inspection team observed for this research revealed that there are undoubtedly some
undiscovered cases of electricity theft. The undiscovered cases may be more or less than
the recovered costs. Also, the recovered costs only include the stolen energy. Other
53
related costs that were not mentioned were maintenance costs, equipment damages, labor
costs, and the administrative costs for pursuing electricity theft cases.
AEP is a utility company that services a large area in the USA, covering nearly
200,000 square miles spanning eleven states. AEP is the largest investor owned utility in
the United States9. At AEP, the Revenue Protection department is directly responsible for
personnel training, receiving information on electricity theft from customers and staff,
analyze consumer load profiles for drastic changes compared to past trends, assessing
charges for electricity theft and equipment tampering, and – if necessary – prosecute
The main source of information AEP uses to detect and prevent electricity theft is
the meter reading staff, which is routinely trained by the Revenue Protection Department
to detect tampering with AEP equipment. According to Mr. Bill Daniel, manager of the
3.2 million annually. In the 2001 annual report available on the AEP website, AEP sold
over $41 billion worth of electricity – and bought over $37 billion – in the year ending
December 31, 2001. Interestingly, the same report lists $109 million under “allowance
9
American Electric Power, www.aep.com, 2002.
54
The charges that constitute these billings include lost energy, tampering fees,
investigation fees, and interest. Customers are prosecuted under the following
circumstances:
2) repeat offenders
or above)
6) the customer climbs or accesses a pole with the intent to steal electricity.
It should be noted again that the main sources of information regarding electricity
are field employees and trend analysis of customer load profiles. In his correspondence
with the author, Mr. Daniel stated that, regarding using power system analysis software
for detecting electricity theft, AEP has “a large number of unmetered (flat rate)
In addition to AEP, a search for the phrase “electricity theft” on any search engine
on the Internet would yield information sites posted by utilities companies all over the
world.
10
Quoted from an electronic mail correspondence with Mr. Daniel from AEP, May 2002.
55
developing countries, including countries in the former Soviet Union (FSU) and Eastern
Europe. The World Bank studied NTL in these areas in an effort to increase the
efficiency and profitability for local utilities. The results of the World Bank’s studies are
In a 1999 publication [2], the World Bank Energy Sector Unit reported on non-
payment in the electrical sector in various countries in Eastern Europe and the FSU
nations. The study covered various time spans for different countries ranging from 1992
to 1998. The main stated reason for the significant – in some places very large – amount
communism and the response of the governments and the public to those changes.
The extent of the non-payment problem varies from country to country, and the
cause of the problem also varies. For example, countries with large natural energy
resources such as Russia and Ukraine continue to have problems collecting from
consumers, while countries that are dependent on energy imports have greater incentives
to solve the problem of non-payment. Household consumers are the main area of concern
in Albania, Georgia, and Armenia, while industrial consumers are the bigger problem in
Russia and Ukraine. An interesting type of non-payment is the use of cash substitutes that
56
can’t be converted to liquid assets by the utilities, which is a problem seen in Russia,
Ukraine, Georgia, and Armenia. The dimensions of the non-payment problem in these
IMPACTS
the micro and macroeconomic level [2]. Payment default at the consumer end resulted in
companies, which in turn accumulate unpaid debts to energy suppliers, banks, and
employees. In some cases, the inability to pay for energy has led to rationing, such as
Georgia, which had only a few hours of electricity supply each day in 1995 [2], or
Armenia, which had supply for only two hours a day because its gas utility could not
Table 4.6 - Extent of the Electric Utility Non-Payment Problem in Eastern Europe and
Former Soviet Union Nations (Source: World Bank Energy Sector Unit, Non-Payment in
the Electricity Sector in Eastern Europe and the Former Soviet Union, 1999)
In Russia, the utilities owe the government significant sums in taxes, while it is
estimated that the government owed even more for energy supplies. This situation created
a vicious cycle that resulted in Russian utilities being unable to pay for fuel supplies and
maintenance. Many large consumers also bartered or provided other cash substitutes for
electricity, forcing the utilities to do the same for fuel, resulting in inflated fuel prices
paid by utilities. This coupled with a drop in demand, ultimately led to a steep drop in
capacity, in Russia as well as other FSU nations with similar problems, shown in Table
4.7 below.
CAUSAL FACTORS
Eastern Europe and FSU. The causes that were listed in [2] as the main causes of the
problems include: effects of stabilization measures after regime changes in most of the
unsustainable subsidies installed by governments; tax laws and their enforcement; poor
corporate governance; tensions between federal and local agencies; and the concept of
property rights.
The non-payment problem emerged and grew to serious proportions at the same
time as the region-wide governmental, political and economic changes took place. The
• government entities could no longer afford the same level of energy consumption
• industrial enterprises lost access to financial support and loans that would have
• declining incomes, high inflation, high unemployment and rising energy prices
severely eroded the ability of households to pay for energy and heat
Most utilities in the world have one standard remedy for accumulated unpaid
consumer debts: disconnection or reduction of the number of clients. This remedy was,
and probably still is, significantly restricted in the FSU [2], [9]. In Russia, Ukraine and
Georgia in particular, the traditional legal concepts relating to the provision of energy
appear to stand in the way of the utility trying to disconnect supplies for non-payment. In
by the government, and is naturally politicized and abused [2]. In an extreme example
[2], some customers in Albania had threatened to shoot utility officials for attempting to
disconnect power supplies. In most countries, the absence of adequate metering and poor
location of meters effectively prevented any action against theft and non-payment.
60
Energy companies in the FSU also started the practice of cancellation of mutual
debts and barter trades for energy bills with government and other industries. In many of
these countries, taxes were based on cash accounting, giving these energy companies to
accept non-cash payments. Non-cash payments also provides another way for officials to
personally profit, resulting in stagnant cash collection rates in Ukraine and Russia [2] (see
table 4.4).
SOLUTION APPROACHES
Various solutions have been tried by local utilities and governments in Eastern
Europe and the FSU in response to high levels of non-payment in the energy sector.
Listed below are some of the approaches taken at the utility level and at the government
level [2].
payment at the utility level. Meters had been installed at substations, feeders, and
consumer blocks have finally been added to the system in Armenia, Albania and
Georgia.
meter reading, billing and collection, customer accounting, and follow up. These
61
functions have been separated to avoid collusion and to enable greater control [2].
just hading cash to the meter man – long taken for granted elsewhere – were only
utilities widely outsource the meter reading, billing, and collection through
resellers. These resellers are being phased out in most areas because of past
records of indiscipline.
• Incentive Mechanisms for Utility Staff: In some cases where the utility staff have
• Working with Large Consumers: As in the case with Bulgaria, the largest
longer supply durations or guaranteed supplies for customers who were willing to
pay in advance. A Russian utility has tried offering discounts for customers who
• Broader Focus for Stabilization: In this respect, the World Bank observed that
most of the FSU and Eastern Europe, at the time of the report, were still focusing
done to certain sectors such as energy [2]. The World Bank then went on to urge
• Legal Framework and Exit Policies and Practices: The World Bank pointed out in
[2] that most nations covered in the report seriously lacked legal frameworks and
rights, financial laws and regulations, and enterprise laws, as well as banking and
trade reforms. This financial chaos is cited as a major reason of the continuation
to be in the beginning stages of reforms by the World Bank, with some exceptions
[2].
settlements of debts, taxes, wages, and bills. This requires some law and political
reform to reduce the incentives for using non-cash transactions. Some nations
such as Russia and Armenia have banned non-cash transactions, but taxes based
63
on cash transactions rather than assets and accruals continue to provide incentives
were urged by the World Bank to manage their budgets and their energy
consumption, in order to reduce the strain placed on utilities and the power
systems. Lithuania, and to a lesser extent Bulgaria, Hungary, and Poland, were
• Enabling Disconnection of Supply for Default: Legal reform, more clarity in the
current laws for most countries, as well as the enforcement of the rule of law are
CHAPTER 5
Non-technical losses (NTL) in all forms are very real and significant problems for
utilities companies. The vast majority of detected cases of NTL are caused by electricity
theft. The affected utilities and authorities have developed methods to reduce NTL,
Despite the best efforts by utilities, the current results of NTL measurements are
often inaccurate at best, because the figures rely heavily on the records of detected cases,
rather than by actual measurement of the electrical power system. The reason that
measurement or monitoring the power system is not the preferred method of measuring
NTL is because the infrastructure of the system, specifically the metering of the system,
does not facilitate time-varying calculations of system losses, which makes accurate
determination of NTL impossible. In fact, any given power system would have some
loads that are not metered at all, which would affect the outcome in any calculations as
NTL.
65
The obvious solution to this is to install meters at every billed load and to use
meters that sample load power or voltage values at reasonable intervals. This solution is
nearly impossible to implement in medium or large service areas simply because of the
possibility because of the lower costs and the added application of real-time pricing.
Meters that can perform the required duties, which includes somehow sending
data to the computing facility, would be much more expensive than the regular kind of
meters currently in use. In some cases where people are already stealing electricity, the
new meters would simply be more valuable targets. The technical difficulties of acquiring
data from countless meters would also make a continuous NTL measurement effort a
In the end, the utility must decide whether the costs of accurately measuring NTL
be worth the returns in the form of recovering the NTL costs that were not recovered by
the processes already in place. The fact that the departments charged with revenue
recovery at both PEA and AEP do not use any power system loss analysis to aid their
Some important factors that affect the overall impact and magnitude of NTL are
the political and economic situations in the local areas. In poor and unstable areas, such
66
as Former Soviet Union nations, NTL cases are so widespread that the operations of
In the end, NTL is a recognized problem that creates costs for utilities in the form
of lost revenues and damaged equipment. In most areas where NTL has not reached
reasonable enforcement of property rights laws. Other areas where NTL, usually in the
form of non-payment, has reached a significant level, the impact on utilities services and
the overall economy is nontrivial. In such areas, NTL is usually a byproduct of larger
economic and social turbulence. The solutions taken at the utility and local levels are thus
FUTURE WORK
analyzing utility billing information. Specific issues could include the optimal methods
2.) Cost analysis for utilities’ theft detection and prevention efforts compared
to the recouped revenues, as well as cost analysis for efforts to measure NTL more
accurately. Costs for extra staff and resources were not addressed by the utilities
67
contacted for the research. A cost analysis study on NTL prevention and detection would
help explain the companies’ decisions regarding NTL, especially electricity theft.
For example, some meter manufacturers have developed meters that could be read
remotely by the utilities staff. Such meters could be fitted with diagnostics equipment to
detect meter tampering. Or a small section of the system could be used for an experiment
in reading power and energy values at regular intervals in order to provide sufficient
[1] Charles A. Gross, Power System Analysis (Second Edition). John Wiley & Sons,
New York, 1986; pp. 255 – 298, and pp. 304 – 322.
[2] Energy Sector Unit, Europe and Central Asia Region, Non-Payment in the
Electricity Sector in Eastern Europe and the Former Soviet Union, World
Bank Technical Paper No. 423. The World Bank, June 1999; pp. 3-33.
[4] A.E. Fitzgerald, Charles Kingsley, Jr., and Stephen D. Umans, Electric
Machinery (Fifth Edition), McGraw Hill, 1992; pp. 51 – 87.
[10] Izudin Dzafic, Mevludin Glavic and Fernando L. Alvarado, “Power System
Simulator 1.0”, http://www.untz.ba/idzafic/powersimulator.htm, University of
Tuzla (Bosnia and Herzegovina), 2002
Electrical power that flows through power systems consist of real (P) and reactive
(Q) power and the two components combine to make apparent power (S):
S = P2 + Q2 (A.1)
The apparent power S generated or consumed by a given element in the power system is
the product of the phasor voltage across it and the complex conjugate of the phasor
current through it. The real and reactive power, in turn, can be calculated using the
apparent power and the angle representing the phase difference between the current and
S = VI * (A.2)
P = S cos φ
Q = S sin φ (A.3)
S = P + jQ
The last equation is the complex cartesian number form where j is the imaginary number
The voltage and current have their own relationships based on Ohm’s Law:
V = IZ
(A.4)
Z = R + jX
It is worth noting that all the quantities represent steady state, single-phase
operation. Though all power systems that operate with more than 220 volts are three-
phase systems, the discussions and calculations here will treat the values as single-phase
i.e., all three phases have exactly the same amount of power flowing through each of
them. In reality, three-phase power systems are rarely, if ever, perfectly balanced. The
voltages and currents are all stated in root mean square (rms) values, while power values
are average powers. The electrical quantities discussed in this thesis are all assumed to be
smooth sinusoid waves, which means the rms values are equal to the peak values divided
In this section, the underlying principles involved with calculating the values of
the power that flow through elements of power systems will be briefly discussed. For
more in depth analysis and discussion of results and applications, see [1].
66
The first premise of the power flow (or load flow) calculation involves an
extension of Kirschoff’s Current Law, which states that the sum of currents that flow in
and out of a node is zero. The application to load flow problems is that the sum of
n n n
Ptotal , A = −∑ PG ,i + ∑ PL ,i + ∑ PTL ,i = 0 (A.4)
i =1 i =1 i =1
where Ptotal,A is the total power at node A, PG,i, PL,i and PTL,i are the various values of
generated power, load power and power flowing through the transmission lines,
respectively. The index i signifies the ith generator, load, or transmission line connected
to bus A. Equation A.4 only shows the steady state equilibrium for real power, but the
same would hold true for reactive power (Q) and complex power (S). A visualization of
G
• Transmission
•
• STL,A
Generators
G
SG,A •
•
•
• Loads
G • SL,A
•
Bus A
Figure A.1. A General Connection Situation at an Arbitrary Bus (denoted Bus A, where
G denotes a generator unit). (Source: C.A. Gross, Power System Analysis, John Wiley &
Sons, Inc., 1986, 2nd Edition, p. 257.
67
The next component that is necessary for load flow analysis is the system
admittance array (Ybus). The system array is a matrix that consists of admittance values
between buses in the system, which are the inverse values of system impedances. The
system array is based on applying Ohm’s Law to a vector of voltage and current values
V1 I T ,1
V I T ,2
2
M M
Vˆ = and IˆT = , with Vi and I T ,i representing the complex values of bus
V
i I T , i
M M
V
n I T , n
voltage and total transmission current at bus i, respectively. The voltage Vi is a complex
value with the magnitude Vi and the phase angle δi. The number n signifies the total
Iˆ = [Y] Vˆ (A.5)
where [Y] is an n×n matrix. Each element of [Y], vector Yi,j represents the admittance
between bus i and bus j, with the impedance size yi,j and the phase angle γi,j. The
With all the variables above in place, the total real and reactive transmission
n
PTLi = ∑ViV j cos(δ i − δ j − γ i , j )
j =1
n (A.6)
QTLi = ∑ViV j cos(δ i − δ j − γ i , j )
j =1
68
Virtually all power flow calculations are done using iterative numerical methods.
In this thesis, the MATLAB simulation that is used to find the solutions to the test system
power flow is based on the Newton-Raphson method [1]. For power flow applications,
the Newton-Raphson method is used for two n-dimension vector functions, P and Q, with
two n-dimension vector variables, V and δ. The method used to solve for the final values
First, an initial set of estimated values (“guesses”) for the values of V and δ are
entered with one bus voltage and angle kept constant – the slack bus. The initial estimates
are then used to compute the variation of the variables results from the initial iteration,
∆V and ∆δ. The variations ∆V and ∆δ are then used to make the next estimate.
V k +1 V k ∆V
k +1 = k + (A.8)
δ δ ∆δ
The vectors Vk+1 and δk+1 are values for the k+1th iteration, Vk and δk are results
from the previous kth iteration. The variations vectors ∆V and ∆δ are computed by using
∆V ˆk
k −1 P
∆δ = −[ J ] ˆk (A.9)
Q
Where P̂ k and Q̂ k are n-dimension vectors containing the total real and reactive power
values at each bus stacked on top of each other to make a 2n-dimension vector. The
matrix [Jk] is called the system Jacobian matrix, a 2n×2n matrix that can be divided into 4
quadrants as follows:
∂P ∂P
∂δ ∂V
[J ] = (A.10)
∂Q ∂Q
∂δ ∂V
∂P
a.) is an n×n matrix where the elements are calculated as follows:
∂δ
∂Pi n
= − ∑ViV j yi , j sin(δ i − δ j − γ i , j ) for diagonal elements, and
∂δ i j =1
j ≠i
∂Pi
= ViVk yi ,k sin(δ i − δ k − γ i ,k ) for i≠ k (A.11a)
∂δ k
∂P
b.) is an n×n matrix where the elements are calculated as follows:
∂V
∂Pi n
= Vi yi ,i cos γ i ,i + ∑V j yi , j cos(δ i − δ j − γ i , j ) for diagonal elements, and
∂Vi j =1
∂Pi
= Vi yi ,k cos(δ i − δ k − γ i ,k ) for i≠ k (A.11b)
∂Vk
70
∂Q
c.) is an n×n matrix where the elements are calculated as follows:
∂δ
∂Qi n
= ∑ViV j yi , j cos(δ i − δ j − γ i , j ) for diagonal elements, and
∂δ i j =1
j ≠i
∂Qi
= −ViVk y i ,k cos(δ i − δ k − γ i ,k ) for i≠ k (A.11c)
∂δ k
∂Q
d.) is an n×n matrix where the elements are calculated as follows:
∂V
∂Qi n
= −Vi yi ,i sin γ i ,i + ∑V j yi , j sin(δ i − δ j − γ i ,i ) for diagonal elements, and
∂Vi j =1
∂Qi
= Vi yi ,k sin(δ i − δ k − γ i ,k ) for i≠ k (A.11d)
∂Vk
Once the components described above are set in place, the iterative process is
V 0
started. The initial estimate of the solutions are entered as 0 and then used to
δ
∆V
calculate the first variation vector . The second iteration’s estimates are thus
∆δ
obtained and then used to calculate the next estimates. The process is repeated until the
solution converges. The solution is generally considered converged once the variation
vector becomes small enough to fall within a tolerance value set by the user. Also, the
71
initial values entered for the slack bus (see Chapter 2) is 1∠0o , or one per-unit in
Remarks
1.) There are several other established methods to formulate an iterative solution for
power flow analysis, most of which would yield the same results with less
2.) While writing the program for the two-bus test system, the author found that
Now that the concepts needed for calculating power flow in an electrical power
system has been developed, the next step is to use the information obtained above to
calculate for losses in the system. Power loss in the system is actually quite simple to
derive: the total power in the system must equal zero, i.e., input should equal output.
The losses would then equal the discrepancies between the total powers at the buses. In
11
Asif Selim, "An investigation of the use of Broyden's method of load flow analysis", Ohio University,
March 1994
72
n n n n
PLoss = Re[∑Vˆi ( ∑VˆiYi , j ) ∗] = ∑∑ViV j yi , j cos(δ i − δ j − γ i , j ) (A.12)
i =1 j =1 i =1 j =1
where Re[ ] represents the real part of the complex value inside the bracket in (A.12),
Vˆi and Yi,j are the vector form of the voltage and impedance, respectively.
Equation (A.12) yields the sum average power losses throughout the power
system. Other calculation methods are available for losses in subsections of large power
systems. However, (A.12) is sufficient for the purposes of this thesis because the test
power system used is a two-bus system with only one transmission line and no
transformers. In this case, the total power loss in the system and the loss in the
The loss calculations performed on the two-bus test system were carried out using
a MATLAB program using the principles discussed above. The program itself is shown
The following program was written with MATLAB Release 12 for the specific
purpose of calculating bus voltages, power flow, and ultimately power losses in the
hypothetical two-bus power system specified in Chapter 2: Loss Analysis and shown
in Figure B.1 below. The system specifications, also listed in Chapter 2, are as shown
below.
Bus 1 Bus 2
Figure B.1 – Single-line diagram of a two-bus, two-load power system with known
load and known transmission line data. Each bus can be the slack bus.
• Base Values: 22000 Volts, 100 Ampere, 2.2 MVA, 220 Ohms
• Transmission Line:
= 0.009121062 p.u.
74
The transmission line reactance and resistance values per unit length were
Authority of Thailand. The full datasheets, written in Thai and English, are shown in
Appendix C. The profiles of the loads at the two buses are shown in Figure 2.4 in
Chapter 2.
The calculation methods are those briefly explained in Appendix A. The block
diagram in Figure B.2 in the next page shows the information flow within the
MATLAB program. The ultimate results are the final voltages at the buses, the final
phase angles, the power flow between the buses, and the power losses. In the next
∆V ˆk
k −1 P
∆ δ = −[ J ] ˆ k
Q
Ptotal Î 0?
No
Yes
∂P ∂P
∂δ ∂V
RMS Voltages & Phase [J k ] =
∂Q ∂Q
angles (V, δ) found ∂δ ∂V
Figure B.2 – Information Flow Through the MATLAB Load Flow Analysis Program.
Two MATLAB programs are shown below: the first program calculates the
power losses in the transmission line under normal circumstances; the second
calculates the losses and then compares those losses to a scenario where non-technical
losses were inserted. In MATLAB codes, any line that begins with the “%” symbol
evaluated when the program is run. Lines that end with “…” are lines that contain
texts too long to fit the page and are continued on the lines immediately below them.
76
%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%
%
% TWO-BUS TEST SYSTEM LOAD FLOW CALCULATIONS
%
%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%
% The following program calculates the final voltage values at the
% two buses of the test system described in Chapter K, without
% technical losses.
% Once the system voltages are determined, the power losses are then
% calculated.
% The mathematical calculations are briefly discussed in Appendix A.
% The values for Z12 below represents the impedance (resistance plus
% reactance) of the transmission line in the system. The values are
% taken from actual datasheets shown in Appendix C, with specific
% calculations shown in Chapter K.
%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%
Z12 = 0.004792+0.009121j ; Y12 = 1/Z12;
% NOTE: All values above are per-unit with the following base
% values: Vbase = 2400 Ibase = 100
% Load schedule begins in the following format:
% Time(hrs) Power Reactive Power Reactive Power Factor
% Load 1 power Load 2 power 1 2
%
%
% Load schedule is arraged as [hour,Load1,pf1,Load2,pf2] for each
% row in row_sched.
Load_sched = [ 1, 0.045455, 0.9, 0.022727, 0.8;
2, 0.045455, 0.9, 0.022727, 0.8;
3, 0.045455, 0.9, 0.022727, 0.8;
4, 0.056818, 0.85, 0.025 , 0.85;
5, 0.068182, 0.88, 0.027273, 0.83;
6, 0.079545, 0.89, 0.034091, 0.75;
7, 0.113636, 0.85, 0.056818, 0.7;
8, 0.159091, 0.8, 0.090909, 0.72;
9, 0.227273, 0.75, 0.113636, 0.77;
10,0.227273, 0.75, 0.034091, 0.81;
11,0.227273, 0.75, 0.034091, 0.83;
12,0.227273, 0.75, 0.054545, 0.79;
13,0.227273, 0.75, 0.056818, 0.78;
14,0.227273, 0.75, 0.036364, 0.83;
15,0.227273, 0.75, 0.036364, 0.86;
16,0.227273, 0.8, 0.090909, 0.77;
17,0.227273, 0.8, 0.113636, 0.73;
18,0.159091, 0.82, 0.159091, 0.69;
19,0.113636, 0.85, 0.147727, 0.71;
20,0.068182, 0.88, 0.136364, 0.68;
21,0.045455, 0.89, 0.136364, 0.77;
22,0.045455, 0.9, 0.113636, 0.78;
23,0.045455, 0.89, 0.079545, 0.82;
24,0.045455, 0.89, 0.069981, 0.87];
% Average loads for Load1, Load2
Load_avg = [0.132576*0.83, 0.132576*sin(acos(0.83)),…
…acos(0.83),180*acos(0.83)/pi,0.069981*0.780833,…
…0.069981*sin(acos(0.780833)),acos(0.780833),180*acos(0.780833)/pi];
% The following loop is to create a power profile for the loads in
% this format:
77
tol = 0.0000001;
final_voltage_2=zeros(25,2);
for j2 = 1:25
V(1) = 1;delta(1)=0; %slack
V(2) = 1;delta(2)=0;
count= 0;
P2 = V(2)*V(2)*Y(2,2)*cos(-gamma(2,2)) + …
…V(2)*Y(2,1)*cos(delta(2)-gamma(2,1)) + Load_Powers(j2,5);
Q2 = V(2)*V(2)*Y(2,2)*sin(-gamma(2,2)) + …
…V(2)*Y(2,1)*sin(delta(2)-gamma(2,1)) + Load_Powers(j2,6);
while abs(Q2)>tol
P2 = V(2)*V(2)*Y(2,2)*cos(-gamma(2,2)) + …
…V(2)*Y(2,1)*cos(delta(2)-gamma(2,1)) + Load_Powers(j2,5);
Q2 = V(2)*V(2)*Y(2,2)*sin(-gamma(2,2)) + … \
…V(2)*Y(2,1)*sin(delta(2)-gamma(2,1)) + Load_Powers(j2,6);
Power(1,1) = P2;
Power(2,1) = Q2;
% Below is the calculation of the Jacobian Matrix (Appendix A)
J(1,1) = -V(2)*Y(2,1)*sin(delta(2)-gamma(2,1));
J(1,2) = 2*V(2)*Y(2,2)*cos(-gamma(2,2)) + …
…Y(2,1)*cos(delta(2)-gamma(2,1));
J(2,1) = V(2)*Y(2,1)*cos(delta(2)-gamma(2,1));
J(2,2) = 2*V(2)*Y(2,2)*sin(-gamma(2,2)) + …
…Y(2,1)*sin(delta(2)-gamma(2,1));
% Below, the Jacobian Matrix is used to calculate the voltage values
Power = [P2;Q2];
d = -inv(J)*Power;
dDelta = d(1);
dV = d(2);
V(2) = V(2) + dV;
delta(2)= delta(2) +dDelta;
count = count + 1;
end
final_voltage_2(j2,1) = V(2);
final_voltage_2(j2,2) = delta(2);
end
for j2=1:25
% Using equations stated in Power Systems Analysis (C A Gross,
% p 319) for calculating power losses, then converting to watts and
78
% vars.
P_loss(j2) = Y(1,1)*cos(-gamma(1,1)) +…
…(final_voltage_2(j2,1)^2)*Y(2,2)*cos(-gamma(2,2)) + …
…final_voltage_2(j2,1)*Y(2,1)*cos(final_voltage_2(j2,2) - …
…gamma(2,1)) + final_voltage_2(j2,1)*Y(1,2)*cos(-…
…final_voltage_2(j2,2)-gamma(1,2));
Q_loss(j2) = Y(1,1)*sin(-gamma(1,1)) +…
…(final_voltage_2(j2,1)^2)*Y(2,2)*sin(-gamma(2,2)) +…
…final_voltage_2(j2,1)*Y(2,1)*sin(final_voltage_2(j2,2) - …
…gamma(2,1)) + final_voltage_2(j2,1)*Y(1,2)*sin(-…
…final_voltage_2(j2,2)-gamma(1,2));
P_loss_watt(j2) = P_loss(j2)*2200000;
Q_loss_var(j2) = Q_loss(j2)*2200000;
LOSSES(j2,1) = P_loss_watt(j2);
LOSSES(j2,2) = Q_loss_var(j2);
end
Load_Powers(i,3) = acos(Load_sched(i,3));
Load_Powers(i,4) = 180*Load_Powers(i,3)/pi;
Load_Powers(i,5) = Load_sched(i,4)*Load_sched(i,5);
Load_Powers(i,6) = Load_sched(i,4)*sin(acos(Load_sched(i,5)));
Load_Powers(i,7) = acos(Load_sched(i,5));
Load_Powers(i,8) = 180*Load_Powers(i,7)/pi;
end
% establishing values for the transmission line admittances....
y(1,1) = Y12; Y(1,1)=abs(y(1,1)); gamma(1,1)=angle(y(1,1));
y(1,2) = -Y12; Y(1,2)=abs(y(1,2)); gamma(1,2)=angle(y(1,2));
y(2,2) = Y12; Y(2,2)=abs(y(2,2)); gamma(2,2)=angle(y(2,2));
y(2,1) = -Y12; Y(2,1)=abs(y(2,1)); gamma(2,1)=angle(y(2,1));
tol = 0.0000001;
final_voltage_2=zeros(25,2);
for j2 = 1:25
V(1) = 1;delta(1)=0; %slack
V(2) = 1;delta(2)=0;
count= 0;
P2 = V(2)*V(2)*Y(2,2)*cos(-gamma(2,2)) + …
…V(2)*Y(2,1)*cos(delta(2)-gamma(2,1)) + Load_Powers(j2,5);
Q2 = V(2)*V(2)*Y(2,2)*sin(-gamma(2,2)) + …
…V(2)*Y(2,1)*sin(delta(2)-gamma(2,1)) + Load_Powers(j2,6);
while abs(Q2)>tol
P2 = V(2)*V(2)*Y(2,2)*cos(-gamma(2,2)) + …
…V(2)*Y(2,1)*cos(delta(2)-gamma(2,1)) + Load_Powers(j2,5);
Q2 = V(2)*V(2)*Y(2,2)*sin(-gamma(2,2)) + …
…V(2)*Y(2,1)*sin(delta(2)-gamma(2,1)) + Load_Powers(j2,6);
Power(1,1) = P2;
Power(2,1) = Q2;
J(1,1) = -V(2)*Y(2,1)*sin(delta(2)-gamma(2,1));
J(1,2) = …
…2*V(2)*Y(2,2)*cos(-gamma(2,2))+Y(2,1)*cos(delta(2)-gamma(2,1));
J(2,1) = …
…V(2)*Y(2,1)*cos(delta(2)-gamma(2,1));
J(2,2) = 2*V(2)*Y(2,2)*sin(-gamma(2,2)) + …
…Y(2,1)*sin(delta(2)-gamma(2,1));
Power = [P2;Q2];
d = -inv(J)*Power;
dDelta = d(1);
dV = d(2);
V(2) = V(2) + dV;
delta(2)= delta(2) +dDelta;
count = count + 1;
end
final_voltage_2(j2,1) = V(2);
final_voltage_2(j2,2) = delta(2);
end
for j2=1:25
% Using equations stated in Power Systems Analysis (C A Gross, p
% 319) for calculating power losses, then converting to watts and
% vars.
P_loss(j2) = Y(1,1)*cos(-gamma(1,1)) + …
…(final_voltage_2(j2,1)^2)*Y(2,2)*cos(-gamma(2,2)) + …
…final_voltage_2(j2,1)*Y(2,1)*cos(final_voltage_2(j2,2) …
…- gamma(2,1)) + final_voltage_2(j2,1)*Y(1,2)*cos(…
…-final_voltage_2(j2,2)-gamma(1,2));
81
Q_loss(j2) = Y(1,1)*sin(-gamma(1,1)) + …
…(final_voltage_2(j2,1)^2)*Y(2,2)*sin(-gamma(2,2)) + …
…final_voltage_2(j2,1)*Y(2,1)*sin(final_voltage_2(j2,2) - …
…gamma(2,1)) + final_voltage_2(j2,1)*Y(1,2)*sin(-…
…final_voltage_2(j2,2)-gamma(1,2));
P_loss_watt(j2) = P_loss(j2)*2200000;
Q_loss_var(j2) = Q_loss(j2)*2200000;
LOSSES_reg(j2,1) = P_loss_watt(j2);
LOSSES_reg(j2,2) = Q_loss_var(j2);
end
%%% The NTL loads are then added to the regular load.
Load_sched2(:,1) = Load_sched(:,1);
Load_sched2(:,2) = Load_sched(:,2);
Load_sched2(:,3) = Load_sched(:,3);
Load_sched2(:,4) = Load_sched(:,4) + NTL_prof(:,2);
Load_sched2(:,5) = Load_sched(:,5) + NTL_prof(:,3);
%%%% Below is the calculation of losses with NTL introduced.
for i=1:25
Load_Powers2(i,1) = Load_sched2(i,2)*Load_sched2(i,3);
Load_Powers2(i,2) = Load_sched2(i,2)*sin(acos(Load_sched2(i,3)));
Load_Powers2(i,3) = acos(Load_sched2(i,3));
Load_Powers2(i,4) = 180*Load_Powers(i,3)/pi;
Load_Powers2(i,5) = Load_sched2(i,4)*Load_sched2(i,5);
Load_Powers2(i,6) = Load_sched2(i,4)*sin(acos(Load_sched2(i,5)));
Load_Powers2(i,7) = acos(Load_sched2(i,5));
Load_Powers2(i,8) = 180*Load_Powers(i,7)/pi;
end
% establishing values for the transmission line admittances....
J(1,1) = -V(2)*Y(2,1)*sin(delta(2)-gamma(2,1));
J(1,2) = 2*V(2)*Y(2,2)*cos(…
…-gamma(2,2))+Y(2,1)*cos(delta(2)-gamma(2,1));
J(2,1) = V(2)*Y(2,1)*cos(delta(2)-gamma(2,1));
J(2,2) = 2*V(2)*Y(2,2)*sin(-gamma(2,2)) + …
…Y(2,1)*sin(delta(2)-gamma(2,1));
Load_increase_W(i) = (Load_Powers2(i,5)-…
…Load_Powers(i,5))*2200000;
Losses_increase_pct(i) = …
…(Losses_increase(i)/LOSSES_reg(i,1))*100;
Losses_increase_W(i) = Losses_increase(i);
end
time = [1:24];
% The loop below computes the real power (watts) consumed
% by the NTL.
for i = 1:25
NTL_real_power_pu(i) = Load_Powers2(i,5)-Load_Powers(i,5);
NTL_real_power_W(i) = (Load_Powers2(i,5)-…
…Load_Powers(i,5))*2200000;
NTL_pct_of_load(i) = …
…(NTL_real_power_pu(i)/Load_Powers(i,5))*100;
end
% Total losses are sums of the real power consumed by the NTL
% and the loss increases that are caused by the addition of
% NTL.
Total_Losses = NTL_real_power_W+Losses_increase_W;
% In watts.
AVG_NTL = NTL_real_power_W(25)*ones(24);
AVG_TOT_LOS = Total_Losses(25)*ones(24);
APPENDIX C
technical losses in power systems. There are losses in power systems that cannot be
predicted or calculated beforehand: non-technical losses. The bulk of these losses are
likely caused by electricity theft, rather than the other possibilities such as poor
maintenance, and calculation and accounting mistakes, though some power systems
may suffer from both. This thesis will investigate the loss-related statistics of one
specific power system market: Thailand’s rural regions. Information presented here
would include the magnitude and characteristics of electricity theft, as well as the
utility company’s measures to curb such losses. Other topics that will be discussed
include a comparison with other nations’ systems and if – and how – can software
simulations of power systems account for non-technical losses. How popular load
flow analysis methods can or cannot account for non-technical losses would be the
Approved: _________________________
Brian Manhire, Professor