India is the world's sixth largest energy consumer accounting for about 3.5% of the world's
total annual energy consumption. The thermal, hydro and nuclear energy are the major
sources of generation of electricity in India.

The Ministry has several undertakings/ organizations operating under it. They may be
classified as follows:-

Statutory bodies which include:-

 Central Electricity Authority- is an attached office of the Ministry and assists it in


all technical matters. CEA is responsible for overall planning and technical
coordination as well as supervision of standard programmes of entire electricity
sector of the country. It specifies the technical and safety requirements for
construction, operation and maintenance of electrical standards and electrical lines.
It is also involved in formulating the 'National Electricity Plan' in accordance with the
National Electricity policy', once in five years.

 Central Electricity Regulatory Commission - has been constituted in order to:-


(i) regulate the tariff of generating companies owned or controlled by the Central
Government; (ii) regulate the tariff of generating companies other than those owned
or controlled by the Central Government, if such generating companies enter into or
otherwise have a composite scheme for generation and sale of electricity in more
than one State; (iii) regulate the inter-State transmission of energy including tariff of
the transmission utilities; (iv) grant licences for inter-State transmission and trading;
and (v) advise the Central Government in formulation of National electricity policy
and tariff policy.

 State Electricity Regulatory Commission - have been constituted in order to:- (i)
determine the tariff for generation, supply, transmission and wheeling of electricity,
whole sale, bulk or retail sale within the State; (ii) issue licences for intra-State
transmission, distribution and trading; and (iii) promote generation of electricity from
renewal sources of energy etc.

 Appellate Tribunal for Electricity - has been constituted for the purpose of
hearing cases against the orders of the Regulatory Commissions and the
Adjudicating officer.

 Damodar valley corporation- is the first multi-purpose river valley project of the
Government, set up for the unified development of Damodar Valley region spread
over the States of West Bengal and Jharkhand. Its objectives are:- (i) flood control
and irrigation; (ii) water supply and drainage; (iii) generation, transmission and
distribution of electrical energy; (iv) afforestation and control of soil erosion; and (v)
promotion of industrial, economic and general well-being of the people.

 Bhakra Beas Management Board - has been constituted for the administration,
maintenance and operation of Bhakra Nangal Project. It manages the facilities
created for harnessing the waters impounded at Bhakra and Pong in addition to
those diverted at Pandoh through the BSL Water Conductor System. It has also been
assigned the responsibility of delivering water and power to the beneficiary States in
accordance with their due/ entitled shares.

Public Sector Undertakings, which include:-

 Power Grid Corporation of India Ltd. (POWERGRID) - is the Central


transmission utility of India which possesses one of the largest transmission network
in the world. It has been set up with the mandate 'to establish and operate Regional
and National Power Grids to facilitate transfer of power within and across the regions
with reliability, security and economy on sound commercial principles'. It is
responsible for all the existing and future transmission projects in the Central sector.

 National Thermal power corporation- is the largest thermal power generating


company of India and has been identified as one of the Navratnas. It has been set up
with the objective of planning, promoting and organizing an integrated development
of thermal power in the country.

 National Hydro-Electric Power Corporation - has been set up in order to


harness the vast hydro, tidal and wind potential of the country to produce cheap/
pollution-free and inexhaustible power. It covers all aspects such as investigation,
planning, designs, construction, operation and maintenance of hydroelectric, tidal
and wind power projects.

 North Eastern Electric Power Corporation limited - has been set up with the
objective of developing the large power potential of the North Eastern (NE) region of
the country by installing hydro and thermal power plants so as to ensure optimum
utilization of commissioned generation projects. It aims to plan, design, operate and
maintain power stations in the NE region.

 Rural Electrification Corporation - has been set up with the objective of financing
and promoting rural electrification projects all over the country. The projects cover
electrification of villages, including tribal villages and Dalit Bastis, energisation of
pump sets, provision of power for small, agro-based and rural industries, lighting of
rural households and street lighting. REC provides financial assistance to State
Electricity Boards, State Government Departments and Rural Electric Cooperatives.

 Power Finance Corporation (PFC) - function as the prime development financial


institution dedicated to the growth and overall development of the power sector. It
provides financial assistance/ services for power projects in the form of project term
loan, lease financing, direct discounting of bills, short term loan, consultancy
services, etc.

 Neyveli Lignite Corporation Limited: Neyveli Lignite Corporation Limited is


a Central Public Sector Undertaking engaged in lignite mining and power
generation
Autonomous Bodies, which include:-

 Central power research laboratory - serve as a National Laboratory for


undertaking applied research in electric power engineering, besides functioning as
an independent National Testing and Certification Authority for electrical equipment
and components so as to ensure reliability and develop new products.

 National power training Institute - functions as the National Apex body for the
human resource development of the power sector personnel in India. Its headquarter
is located in Faridabad (Haryana). It operates on all India basis through its five
Regional Power Training Institutes located at Neyveli (Tamil Nadu), Durgapur (West
Bengal), Badarpur (New Delhi), Nagpur (Maharashtra) and Guwahati (Assam). They
are fully equipped with the latest state-of-the-art training infrastructure and having
expert faculties with long years of professional and teaching background.

 Bureau of energy efficiency - has been set up to develop policies and strategies
within the overall framework of Energy Conservation Act 2001. It aims to promote
energy saving measures and in turn reduce energy intensity (i.e. energy consumed
per unit product/services, practice and procedure) of Indian economy.

Joint Venture Corporations, which include:-

 Satluj jal vidyut nigam limited - is a joint venture of the Government of India and
the Government of Himachal Pradesh, set up with the objective to plan, promote,
organize and execute hydro-electric power projects in the Satluj river basin in the
Himachal Pradesh.

 Tehri Hydro Development Corporation (THDC) - is a joint venture of


Government of India and Government of Uttar Pradesh, set up with the objective to
plan, promote, organize, execute, operate and maintain hydro power projects in
Bhagirathi- Bhilangna Valley in Uttar Pradesh.
Installed Capacity

Sector MW %age

State Sector 82,026.05 52.5

Central Sector 51,867.63 34.0

Private Sector 33,183.68 13.5

Total 1,67,077.36

Fuel Wise break up

Fuel MW %age

Total Thermal 108362.98 64.6

Coal 89,778.38 53.3

Gas 17,384.85 10.5

Oil 1,199.75 0.9

Hydro (Renewable) 37,367.40 24.7

Nuclear 4,560.00 2.9

RES** (MNRE) 16,786.98 7.7

Total 1,67,077.36
As on 30/11/12
**Renewable Energy Sources (RES) include SHP, BG, BP, U&I and Wind Energy
SHP= Small Hydro Project, BG= Biomass Gasifier, BP= Biomass Power,
U & I=Urban & Industrial Waste Power, RES=Renewable Energy Sources

The installed capacity figures as on 30.06.2010 in respect of RES is based on statement


dated 02.11.10 from Ministry of Renewable Energy (MNRE) where cumulative Grid
interactive power installed capacity has been indicated as 17174.60 MW. Reconciliation of
installed capacity of Hydro capacity resulted in transfer of 135 MW from conventional to
SHP-RES and retrieval of installed capacity of 67.20 from SHP-RES to conventional Hydro
has resulted in net addition of 67.8 MW to SHP under RES. Also 30 MW of capacity in the
nature of Waste Heat Recovery Power Plant at Goa Energy Private Limited under U&I
category of RES Out of this installed capacity due to wind - (374.636 MW) and small hydro
(110.79 MW) appearing in captive capacity has been deducted to arrive at installed
capacity of utilities in respect of RES.(17174.60-485.43+67.8+30=16786.98)

GENERATION INSTALLED CAPACITY (MW) OF POWER UTILITIES IN STATES/UTS

As on
30/11/12

State/UT MODE WISE BREAKUP


(Utilities) THERMAL NUCLEAR HYDRO RES TOTAL
COAL GAS DIESEL TOTAL (Renewable) (MNRE)

STATE SECTOR
A & N ISLAND 0.00 0.00 40.05 40.05 0.00 0.00 5.25 45.30
ANDHRA PRADESH4382.50 0.00 0.00 4382.50 0.00 3695.53 190.83 8268.86
ARUNACHAL PRD.0.00 0.00 15.88 15.88 0.00 0.00 78.55 94.43
ASSAM 60.00 239.00 20.69 319.69 0.00 100.00 27.11 446.80
BIHAR 530.00 0.00 0.00 530.00 0.00 0.00 54.60 584.60
CHANDIGARH 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
CHHATISGARH 2060.00 0.00 0.00 2060.00 0.00 120.00 19.05 2199.05
D & N HAVELI 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
DAMAN & DIU 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
DELHI 385.00 800.40 0.00 1185.40 0.00 0.00 0.00 1185.40
GOA 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05
GUJARAT 4440.00 892.72 17.28 5350.00 0.00 772.00 29.90 6151.90
HARYANA 3410.00 25.00 3.92 3438.92 0.00 884.51 70.10 4393.53
HIMACHAL PRD. 0.00 0.00 0.13 0.13 0.00 393.60 337.82 731.55
JAMMU & KASHMI0.00 175.00 8.94 183.94 0.00 780.00 129.33 1093.27
JHARKHAND 1190.00 0.00 0.00 1190.00 0.00 130.00 4.05 1324.05
KARNATAKA 2220.00 0.00 127.92 2347.92 0.00 3599.80 594.55 6542.27
KERALA 0.00 0.00 234.60 234.60 0.00 1881.50 142.83 2258.93
LAKSHADWEEP 0.00 0.00 9.97 9.97 0.00 0.00 0.00 9.97
MADHYA PRADESH2807.50 0.00 0.00 2807.50 0.00 1703.66 11.76 4522.92
MAHARASHTRA 7295.00 672.00 0.00 7967.00 0.00 2884.84 257.73 11109.57
MANIPUR 0.00 0.00 45.41 45.41 0.00 0.00 5.45 50.86
MEGHALAYA 0.00 0.00 2.05 2.05 0.00 156.00 31.03 189.08
MIZORAM 0.00 0.00 51.86 51.86 0.00 0.00 36.47 88.33
NAGALAND 0.00 0.00 2.00 2.00 0.00 0.00 28.67 30.67
ORISSA 420.00 0.00 0.00 420.00 0.00 2061.92 64.30 2546.22
PONDICHERRY 0.00 32.50 0.00 32.50 0.00 0.00 0.00 32.50
PUNJAB 2630.00 25.00 0.00 2655.00 0.00 2230.23 222.55 5107.78
RAJASTHAN 3615.00 443.80 0.00 4058.80 0.00 987.96 30.25 5077.01
SIKKIM 0.00 0.00 5.00 5.00 0.00 0.00 47.11 52.11
TAMIL NADU 2970.00 523.20 0.00 3493.20 0.00 2122.20 85.55 5700.95
TRIPURA 0.00 148.50 4.85 153.35 0.00 0.00 16.01 169.36
UTTAR PRADESH 4072.00 0.00 0.00 4072.00 0.00 524.10 25.10 4621.20
UTTRAKHAND 0.00 0.00 0.00 0.00 0.00 1252.15 132.92 1385.07
WEST BENGAL 4780.00 100.00 12.06 4892.06 0.00 977.00 143.40 6012.46
47267.0 27257.0
Total State 0 4077.12 602.61 51946.730.00 0 2822.32 82026.05

MODE WISE BREAKUP


THERMAL NUCLEAR HYDRO RES TOTAL
State/UT(Utiliti (Renewable) (MNRE)
es COAL GAS DIESEL TOTAL
CENTRAL SECTOR

DVC 3700.00 90.00 0.00 3790.00 0.00 143.20 0.00 3933.20


HP / NJPC JV 0.00 0.00 0.00 0.00 0.00 1500.00 0.00 1500.00
NEEPCO 0.00 375.00 0.00 375.00 0.00 755.00 0.00 1130.00
NEVEYLY LIG. COR2615.00 0.00 0.00 2615.00 0.00 0.00 0.00 2615.00
NHDC 0.00 0.00 0.00 0.00 0.00 1520.00 0.00 1520.00
NHPC 0.00 0.00 0.00 0.00 0.00 3767.20 0.00 3767.20
NTPC 25605.00 4017.23 0.00 29622.23 0.00 0.00 0.00 29622.23
NUCLEAR P CORP0.00 0.00 0.00 0.00 4560.00 0.00 0.00 4560.00
NTPC+ONGC 0.00 2220.00 0.00 2220.00 0.00 0.00 0.00 2220.00
TEHRI HYD CORP.0.00 0.00 0.00 0.00 0.00 1000.00 0.00 1000.00
31920.0
Total Central 0 6702.23 0.00 38622.234560.00 8685.400.00 51867.63
PRIVATE SECTOR
A & N ISLAND 0.00 0.00 20.00 20.00 0.00 0.00 0.10 20.10
ANDHRA PRADESH0.00 2878.40 36.80 2915.20 0.00 0.00 530.76 3445.96
ARUNACHAL PRD.0.00 0.00 0.00 0.00 0.00 0.00 0.03 0.03
ASSAM 0.00 24.50 0.00 24.50 0.00 0.00 0.00 24.50
BIHAR 0.00 0.00 0.00 0.00 0.00 0.00 9.50 9.50
CHHATISGARH 1600.00 0.00 0.00 1600.00 0.00 0.00 199.90 1799.90
DELHI 0.00 0.00 0.00 0.00 0.00 0.00 1.05 1.05
GOA 0.00 48.00 0.00 48.00 0.00 0.00 30.00 78.00
SL. REGION THERMAL Nuclear HYDRO R.E.S.@ TOTAL
GUJARAT 1640.00 2577.50 0.20 4217.70 0.00 0.00 1821.14 6038.84
NO. COAL GAS DSL TOTAL (Renewable) (MNRE)
HARYANA 0.00 0.00 0.00 0.00 0.00 0.00 35.80 35.80
1 Northern 0.00
HIMACHAL PRD. 23620.003813.26
0.00 12.99
0.00 27446.25
0.00 1620.00
0.00 13622.75
578.00 2777.32
0.00 45466.32
578.00
2 Western
JAMMU 29290.507903.81
& KASHMI0.00 0.00 17.48
0.00 37211.79
0.00 1840.00
0.00 7447.50
0.00 4918.28
0.00 51417.57
0.00
3 Southern 19172.504690.78
JHARKHAND 360.00 0.00 939.32
0.00 24802.60
360.00 1100.00
0.00 11299.03
0.00 8517.55
0.00 45719.18
360.00
4 Eastern
KARNATAKA 17635.38190.00
1460.00 220.00 17.20
106.50 17842.58
1786.50 0.00
0.00 3882.12
0.00 344.41
1842.94 22069.11
3629.44
N.
KERALA 0.00 174.00 21.84 195.84 0.00 0.00 0.03 195.87
5 Eastern
LAKSHADWEEP 60.00
0.00 787.00
0.00 142.74
0.00 989.74
0.00 0.00
0.00 1116.00
0.00 223.32
0.75 2329.06
0.75
6 Islands 0.00
MADHYA PRADESH0.00 0.00
0.00 70.02
0.00 70.02
0.00 0.00
0.00 0.00
0.00 6.10
232.60 76.12
232.60
MAHARASHTRA 2470.00 17384.8
180.00 0.00 2650.00 0.00 447.00 2316.15 5413.15
7 All India 89778.38
MIZORAM 0.00 50.00 1199.75
0.00 108362.98
0.00 4560.00
0.00 37367.40
0.00 16786.98167077.36
0.00 0.00
ORISSA 600.00 0.00 0.00 600.00 0.00 0.00 4.30 604.30
PONDICHERRY 0.00 0.00 0.00 0.00 0.00 0.00 0.03 0.03
PUNJAB 0.00 0.00 0.00 0.00 0.00 0.00 73.08 73.08
RAJASTHAN 270.00 0.00 0.00 270.00 0.00 0.00 1132.20 1402.20
TAMIL NADU 250.00 503.10 411.66 1164.76 0.00 0.00 5130.04 6294.80
TRIPURA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
UTTAR PRADESH 600.00 0.00 0.00 600.00 0.00 0.00 587.08 1187.08
UTTRAKHAND 0.00 0.00 0.00 0.00 0.00 400.00 0.05 400.05
WEST BENGAL 1341.38 0.00 0.14 1341.52 0.00 0.00 17.15 1358.67
Total Pvt.10591.3 13964.6
Sector 8 6605.50 597.14 17794.020.00 1425.00 6 33183.68
89778.3 17384.8 1199.7 108362.9 37367.4 16786.9 167077.3
TOTAL 8 5 5 8 4560.00 0 8 6

Region wise break up

Capacity addition for the 11th Plan:

Type/Sector Central State Private Total


Thermal 24840 23301 11552 59693
Hydro 8654 3482 3491 15627
Nuclear 3380 0 0 3380
Total 36874 26783 15043 78700

3380

15627
5969

Thermal Hydro Nuclear

TOTAL CAPACITY COMMISSIONED DURING 2008-09 (MW)

SECTOR THERMAL HYDRO NUCLEAR TOTAL


CENTRAL 750 - - 750
STATE 852.2 969 - 1821.2
PRIVATE 882.5 - - 882.5
TOTAL 2484.7 969 - 3453.7
TOTAL CAPACITY COMMISSIONED DURING 2009-10
(MW)
SECTOR THERMAL HYDRO NUCLEAR TOTAL
CENTRAL 1740 440 2180
STATE 3079 39 3118
PRIVATE 4287 - - 4287
TOTAL 9106 39 440 9585
*COMMISSIONED- Unit achieved full load

CAPACITY ADDITION TARGET FOR THE YEAR 2010-11

SECTOR THERMAL HYDRO NUCLEAR TOTAL


CENTRAL 6015 649 1220 7884
STATE 6549.2 356 6905.2
PRIVATE 6191 461 6652
TOTAL 18755.2 1466 1220 21441.2

CAPACITY COMMISSIONED DURING 2010-11 as on 17 July 2010

SECTOR THERMAL HYDRO NUCLEAR TOTAL


CENTRAL 125 80 - 205
STATE 1250 50 - 1300
PRIVATE 735 - - 735
TOTAL 2110 130 0 2240

Public Sector Utilities:

1. National Thermal Power Corporation:

NO. OF PLANTS CAPACITY (MW)


NTPC Owned
Coal 15 25,375
Gas/Liquid Fuel 7 3,955
Total 22 29,330
Owned By JVs
Coal & Gas 5 3,364
Total 27 32,694

Regional Spread of Generating Facilities

REGION COAL GAS TOTAL


Northern 8,015 2,312 10,327
Western 6,360 1,293 7,653
Southern 3,600 350 3,950
Eastern 7,400 - 7,400
JVs 1,424 1,940 3,364
Total 26,799 5,895 32,694

NTPC has also formulated its business plan of capacity addition of about 1,000 MW thru
renewable resources by 2017. In addition, capacity addition of 301 MW through Solar PV
and Thermal by March 2014 has envisaged in line with National Solar Mission.

2. National Hydro-Electric Power Corporation:


Beyond XIth Plan
Updated On :-
27/07/2010
Total
S No. Project Country/State Capacity Status
Capacity
Arunachal
1 Dibang 12 * 250 3000 Awating clearances
Pradesh
2 Kotli Bhel Stage - I B Uttarakhand 4 * 80 320 Awating clearances
8 *
3 Kotli Bhel Stage - II Uttarakhand 530 Awating clearances
66.25
Jammu &
4 Pakal Dul* 4 * 250 1000 Awating clearances
Kashmir
5 Kotli Bhel Stage - I A Uttarakhand 3 * 65 195 Awating clearances
6 Teesta - IV Sikkim 4 * 130 520 Awating clearances

7 Jammu &
Kiru* 4 * 150 600 Awating clearances
Kashmir
Jammu &
8 Kwar* 4 * 130 520 Awating clearances
Kashmir

Arunachal
9 Tawang-I 3 * 200 600 Awating clearances
Pradesh
10 Loktak Downstream* Manipur 2 * 33 66 Awating clearances
Arunachal
11 Tawang-II 4 * 200 800 Awating clearances
Pradesh
12 Tipaimukh* Manipur 6 * 250 1500 Awating clearances
Jammu &
13 Kishenganga 3 * 110 330 Under Construction
Kashmir
Jammu & Under Survey and Investigation
14 Bursar 4 * 255 1020
Kashmir Stage
Under Survey and Investigation
15 Karmoli Lumti Tulli Uttarakhand 2 * 27.5 55
Stage
Under Survey and Investigation
16 Garba Tawaghat Uttarakhand 3 * 210 630
Stage
Under Survey and Investigation
17 Chungar Chal Uttarakhand 2 * 120 240
Stage
Under Survey and Investigation
18 Lachen Sikkim 3 * 70 210
Stage
Under Survey and Investigation
19 Goriganga-IIIA Uttarakhand 3 * 40 120
Stage
Dhauliganga Under Survey and Investigation
20 Uttarakhand 3 * 70 210
Intermediate Stage
Total 12466
* Under Joint Venture
Projects under category ‘Under Survey and Investigation Stage’ are for survey & investigation for
preparation of PFR/FR/DPR of the project for getting various statutory clearances. For preparation
of these reports, various hydrological, geological, meteorological, power potential studies etc are
carried out at the project site.
Projects under ‘Awaiting clearances’ category are awaiting various statutory clearances
from CWC / CEA / MOP / MOWR/PIB and investment sanction from Cabinet Committee on Economic
Affairs (CCEA) after preparation of DPRs.

3. Nuclear Power Corporation India Limited:

Project Capacit Expected Commercial


y (MWe) Operation
RAJASTHAN ATOMIC POWER 2 x 700 Unit 7 – Jun-2016
PROJECT Unit 8 – Dec-2016
KAKRAPAR ATOMIC POWER 2 x 700 Unit 3 – Jun-2015
PROJECT Unit 4 – Dec-2015

4. North Eastern Electric Power Corporation limited:

Ongoing:

1. TUIRIAL HYDRO ELECTRIC PROJECT ( 60 MW) Mizoram:


Lot – IV (Hydro-Mechanical works): NIB floated on 03.11.10, and the last date for
submission has been fixed on 07.01.2011. The bids shall be opened on the same
day. Lot-V (EM works)
2. KAMENG HYDRO ELECTRIC PROJECT (600 MW) Arunachal Pradesh:
Commissioning schedule May, 2013( Revised)
3. TRIPURA GAS BASED COMBINED CYCLIC POWER PROJECT, Tripura (101MW)
Years of Commissioning / Completion Schedule - 36 months from the date of award
(i.e. by July'2013) for Main Plant Work.

Future Projects:

Sl NAME OF THE PROJECT COMMISSIONING SCHEDULE


No.
1 Kameng-I H.E. Project (1120 6 Years from the Date of CCEA Clearnce.
MW), Ar. Pradesh
2 Mawphu H.E. Project (85 MW), 4.5 years from CCEA Clearnce.
Meghalaya
3 Projects in Mizoram :
a Lungreng H.E. Project ( 815MW) Necessary action has been initiated for
b Chhimtuipui H.E. Project ( 635 obtaining clearances of the Ministry of
MW) External Affairs, Ministry of Defense,
c Mat H.E. Project ( 76 MW) Home Ministry, Govt. of India.
4 Garo Hills Thermal Power 36 months from CCEA Clearnce.
Project (500 MW) Meghalaya
5 West Khasi Hills Thermal Power 32 months from CCEA Clearance.
Project (240 MW) Meghalaya
6 Agartala Gas Turbine Plant- 30 months from Investment approved.
Combined Cycle Conversion
Project (52 MW), Tripura
4. Tehri Hydro Development Corporation (THDC)

Future Projects:

THDC proposes to add 2804 MW during XIIth Plan (2012-2017) in the Capacity Addition
Programme of MOP with the planned commissioning of following Projects:
1. Tehri Pumped Storage Plant - 1000 MW
2. Vishnugad Pipalkoti HEP - 444 MW
3. Kishau Multi Purpose Project - 600 MW
4. Malari Jelam HEP - 114 MW
5. Jelam Tamak HEP - 126 MW
6. Karmoli HEP - 140 MW (*)
7. Jadhganga HEP - 50 MW (*)
8. Bokang Bailing HEP - 330 MW (*)
(*) Under Wildlife clearance

5. Satluj jal vidyut nigam limited

Future Projects:

Projects under Survey and Investigation and DPR Preparation

A. In the State of Himachal Pradesh

Sr. No. Project Installed Capacity


1. Luhri HEP 775 MW
2. Dhaulasidh 66 MW

B. In the State of Uttarakhand

Sr. No Project Installed Capacity


1. Devsari HEP 252 MW
2. Naitwar Mori HEP 60 MW
3. Jakhol Sankri HEP 51 MW

C. In the State of Manipur

Sr. No Project Installed Capacity


1. Tipaimukh HEP* 1500 MW

*This project will be developed by a joint venture company to be established in


which SJVN have agreed to take a 26% equity inerest, with NHPC Limited and State
of Manipur taking 69% and 5% equity interest respectively.
Future Plans
The SJVN proposes to add 5000 MW additional capacity by 2014-15. This would
require an additional investment of about Rs. 29,000 Crores which shall be met
mainly from internal accruals and loans from domestic /multi literal funding
agencies.

To achieve the target of setting up of additional 5000 MW SJVN is exploring the


possibilities of taking up new projects in Himachal Pradesh, Arunachal Pradesh,
Nepal and Bhutan.

Neyveli Lignite Corporation Limited:

Neyveli Lignite Corporation Limited is a Central Public Sector Undertaking engaged in


lignite mining and power generation

Future Plans:

1. WIND POWER PROJECT IN TAMILNADU: NLC is in the process of setting up a 50MW


capacity wind based power project in Tirunelveli District of Tamilnadu.
2. Thermal Power Plant of 250 MW capacity with linked mine of 2.25 MTPA is proposed
to be set up at Bithnok in Bikaner District, Rajasthan.
3. BARSINGSAR EXTENSION POWER PROJECT (250 MW) AND HADLA & PALANA LIGNITE
MINE (2.5 MTPA), Rajasthan
4. 2 x 800 MW power plant with linked lignite mine of 13.5 MTPA at Jayamkondam in
the State of Tamil Nadu
5. COAL BASED THERMAL POWER PLANT IN ORISSA (4 X 500 MW)

List of Hydro projects under execution


(Excluding projects under Ministry of New & Renewable Energy)
*****

Sl. Name of Project Unit State/ Capacity Likely


No. No. Implem. Agency (MW) Commissioning
A. Projects as per 11th Plan Programme
Central Sector
1 Parbati St. II U-1 to Himachal Pradesh/ 800 1 2th P la n
4x200= 800 MW U-4 NHPC
2 Chamera-III U-1 to Himachal Pradesh/ 231 2011-12
3x77= 231 MW U-3 NHPC
3 Parabati-III U-1 to Himachal Pradesh/ 520 2011-12
4x130= 520 MW U-4 NHPC
4 Kol Dam U-1 to Himachal Pradesh/ 800 2011-12
4x200= 800 MW U-4 NTPC
5 Rampur U-1 to Himachal Pradesh/ 412 1 2th P la n
6x68.67= 412 MW U-6 SJVNL

6 Uri-II U-1 to Jamm u & Kashmir/ 240 2011-12


4x60= 240 MW U-4 NHPC
7 Chutak U-1 to Jamm u & Kashmir/ 44 2011-12
4x11=44 MW U-4 NHPC
8 Nimoo Bazgo U-1 to Jamm u & Kashmir/ 45 2011-12
3x15=45 MW U-3 NHPC
9 Koteshwar U-1 to Uttaranchal/ 400 2010-12
4x100= 400 MW U-4 THDC
10 Loharinagpala U-1 to Uttaranchal/ 600 1 2th P la n
4x150=600 MW U-4 NTPC
11 Tapovan Vishnugad U-1 to Uttaranchal/ 520 1 2th P la n
4x130=520 MW U-4 NTPC
12 Teesta Low Dam-III U-1 to West Bengal/ 132 2011-11
4x33= 132 MW U-4 NHPC
13 Teesta Low Dam-IV U-1 to West Bengal/ 160 2011-12
4x40= 160 MW U-4 NHPC
14 Subansiri Lower U-1 to Arunachal Pradesh/ 2000 1 2th P la n
8x250= 2000 MW U-8 NHPC
15 Kameng U-1 to Arunachal Pradesh/ 600 1 2th P la n
4x150= 600 MW U-4 NEEPCO
Sub- total (Central): 7504
State Sector
16 Uhl-III U-1 to Himachal Pradesh/ 100 1 2th P la n
3x33.33= 100 MW U-3 Beas Valley Power Corp.
Ltd. (BVPC)
17 Swara Kuddu U-1 to Himachal Pradesh/ 110 1 2th P la n
3x36.6= 110 MW U-3 HPPCL
18 Priyadarshni Jurala U-6 Andhra Pradesh/ 39 2010-11
6x39= 234 MW APGENCO
19 Nagarujana Sagar TR U-1 & Andhra Pradesh/ 50 2011-12
2x25= 50 MW U-2 APGENCO
20 Lower Jurala U-1 to Andhra Pradesh/ 240 1 2th P la n
6x40= 240 MW U-6 APGENCO
21 Pulichintala U-1 to Andhra Pradesh/ 120 2011-12
4x30= 120 MW U-4 APGENCO
22 Pallivasal U-1 to Kerala/ 60 1 2th P la n
2x30= 60 MW U-2 KSEB

23 Bhawani Barrage II U-1 & Tam il Nadu/ 30 2011-12


2x15= 30 MW U-2 TNEB
24 Bhawani Barrage III U-1 & Tam il Nadu/ 30 2011-12
2x15= 30 MW U-2 TNEB
25 Myntdu U-1& Meghalaya/ 84 2011-11
2x42= 84 MW U-2 MeSEB
26 New Umtru U-1& Meghalaya/ 40 2011-12
2x20= 40 MW U-2 MeSEB
Sub- total (State): 903
Private Sector

Sl. Name of Project Unit State/ Capacity Likely


No. No. Implem. Agency (MW) Commissioning
27 Karcham Wangtoo U-1 to Himachal Pradesh/ 1000 2011-12
4x250= 1000 MW U-4 JKHCL
28 Budhil U-1 & Himachal Pradesh/ 70 2010-11
2x35= 70 MW U-2 LANCO
29 Malana-II U-1 & Himachal Pradesh/ 100 2010-11
2x50= 100 MW U-2 Everest Power
30 Sorang U-1 & Himachal Pradesh/ 100 2011-12
2x50= 100 MW U-2 Himachal Sorang Power
31 Shrinagar U-1 to Uttarakhand/ 330 2011-12
4x82.5= 330 MW U- 4 M /s G VK Industries
32 Maheshwar U-1 to M adhya Pradesh/ 400 2011-12
10x40= 400 MW U-10 SMHPCL
33 Chujachen U-1& Sikkim/ 99 2010-11
2x49.5= 99 MW U-2 Gati
34 Teesta- III U-1 to Sikkim/ 1200 2011-12
6x200= 1200 MW U-6 T eesta U rja Ltd.
Sub- total (Private): 3299
Total ‘A’ (11th Plan): 11706
A-1 Additional Unit likely to commission in 11th Plan
25a Myntdu U-1 Meghalaya/ 42 2011-12
1x42= 42 MW MeSEB
B. Projects likely to give benefits beyond 11th Plan
Central Sector
35 Kishanganga U-1 to Jamm u & Kashm ir/ 330 1 2th P la n
3x110= 330 MW U-3 NHPC
36 Pare U-1 to Arunachal Pradesh/ 110 1 2th P la n
2x55= 110 MW U-2 NEEPCO
State Sector
37 Baglihar-II* U-1 to J&K/ 450 1 2th P la n
3x150= 450 MW U-3 JKPDC
38 Kashang-I Himachal Pradesh/ 65 1 2th P la n
65 MW HPPCL
39 Thottiyar Kerala/ 40 1 2th P la n
40 MW KSEB
Private Sector
40 Tidong-I U-1 to Himachal Pradesh/ 100 1 2th P la n
2x50= 100 MW U-2 M/s Nuziveedu Seeds
41 Phata Byung Uttarakhand/ 76 1 2th P la n
76 MW M/s Lanco
42 Singoli Bhatwari U-1 to Uttarakhand/ 99 1 2th P la n
3x33= 99 MW U-3 L& T U ttaranchal H ydro
power Limited

43 Teesta- VI U-1 to Sikkim/ 500 1 2th P la n


4x125= 500 MW U-4 LANCO
44 Rangit-IV U-1 to Sikkim/ 120 1 2th P la n
3x40= 120 MW U-3 Jal Pow er corp. L td.
45 Jorethang Loop Sikkim/ 96 1 2th P la n
2x48= 96 MW M/s DANS Energy
46 Bhasmey U-1 to Sikkim/ 51 1 2th P la n
3x17= 51 MW U-3 G ati Infrastructu re
Total ‘B’ (Beyond 11th Plan): 2037
Total- Under Execution: 13785

THERMAL UNITS TARGETED FOR COMMISSIONING IN THE YEAR 2010-11


(Original Target and Actual Achieved) As On-31.10.10
State Project Name Impl Unit No Targeted Cap. (MW) Commd. Cap. (MW) Actual(A)/ Ant Comm.
Agency Date
A.CENTRAL SECTOR
Rajasthan Barsingsar NLC U-2 125 11/2010
Lignite
U-1 * 125 28.06.10(A)
Haryana Indira APCPL U-1 500 500 31.10.10(A)
Gandhi TPP
UP NCP Project NTPC U-6 490 490 30.07.10(A)
St-II,
WB Mejia TPS DVC U-1 500 500 30.09.10(A)
Extn
U-2 500 02/2011
Durgapur DVC U-1 500 03/2011
Steel TPS
U-2 500 05/2011
Farakka NTPC U-6 500 02/2011
STPS- III
Chhattisgarh Korba STPP NTPC U-7 500 11/2010
Jharkhand Kodarma TPP DVC U-1 500 '03/2011
TN Neyveli TPS- NLC U-1 250 02/2011
II Exp.
AP Simhadri NTPC U-3 500 01/2011
STPP Extn.
Jharkhand Maithon RB DVC U-1 525 02/2011
TPP
Sub Total(A) 5890 1615
B.STATE SECTOR
Delhi Pragati PPCL GT-1 250 250 24.10.10(A)
CCGT – III
GT2 250 12/2010
GT-3 250 04/2011
ST-1 250 06/2011
GT-4 250 02/2011
ST-2 250 05/2011
Gujarat Surat Lignite GIPCL U-3* * 125 12.04.10(A)
TPP Extn.
U-4 * * 125 23.04.10(A)
Hazira CCPP GSECL GT 223 03/2011
Extn.
ST 128 03/2011
Pipavav CCPP GSECL Block-1 351 04/2011
Haryana Rajiv Gandhi HPGCL U-2 600 600 01.10.10(A)
TPS,Hissar
Karnataka Raichur U-8 KPCL U-8 250 250 26.06.10(A)
Rajasthan Chhabra TPS RRVUNL U-2 * * 250 04.05.10(A)
AP Kakatiya APGENCO U-1 500 500 27.05.10(A)
TPP
Rayalseema APGENCO U-5 210 11/2010
TPP St-III
State Project Impl Agency Unit No Targeted Cap. Commd. Cap. Actual/ Ant Comm. Date
Name (MW) (MW)
UP Parichha Extn UPRVUNL U-5 250 06/2011
U-6 250 06/2012
Harduaganj UPRVUNL U-8 250 03/2011
Ext
U-9 250 04/2011
Maharashtra Khaperkheda MSPGCL U-1 500 02/2011
TPS Expn.
Bhusawal MSPGCL U-4 500 03/2011
TPS Expn.
WB Santaldih TPP WBPDCL U-6 250 12/2010
Extn Ph-II
Tripura Baramura TSECL GT* 21 03.08.10(A)
GT
Sub Total (B) 6012 2121
C.PRIVATE SECTOR
AP Konaseema Konaseema ST 165 165 30.06.10(A)
CCPP gas Power
Ltd.
Lanco Lanco ST 133 133 18.07.10(A)
Kondapalli Kondapalli
Ph-II (ST)
Delhi Rithala CCPP NDPL GT-1 35.75 11/2010
GT-2 35.75 11/2010
ST 36.5 12/2010
Gujarat Mundra TPP Adani Power U-3 330 330 02.08.10(A)
Ph-I(U-3&4) Ltd
U-4 330 11/2010
Maharashtra JSW JSW U-1 300 300 24.08.10(A)
Ratnagiri Energy(Ratn
TPP agiri) Ltd
U-2 300 11/2010
U-3 300 11/2010
U-4 300 04/2011
Wardha WPCL U-1 * 135 05.06.10(A)
Warora (KSK)
Wardha U-2 * 135 10.10.10(A)
Warora
Orissa Sterlite TPP Sterlite U-2(Ist 600 600 14.10.10(A)
Energy Ltd. Unit)
U-1 600 01/2011
Rajasthan Jallipa- Raj West U-2 135 135 08.07.10(A)
Kapurdi TPP Power
Ltd.(JSW)
U-3 135 01/2011
U-4 135 02/2011
U-5 135 04/2011
U-6 135 06/2011
U-8 135 09/2011
UP Anpara-C Lanco U-1 600 01/2011
Anpara
Power Pvt.
Ltd.
Rosa TPP Rosa Power U-2 * 300 28.06.10(A)
Ph-1 supply
Co.Ltd (
Reliance)
Karnataka Udupi TPP UPCL U-1 507.5 600 23.07.10(A)
U-2 507.5 01/2011
SubTotal (C ) 5891 2833

Grand Total (A+B+C) 17793 6569


State Generation Board

Northern Region:

1. Delhi:

2. Punjab:

Hydel project:

a) SHAHPUR KANDI HYDRO ELECTRIC PROJECT (168 MW) - This project is


likely to be completed during 12th plan.
b) SHAHPURKANDI EXTENSION (55.5 MW) - The Project is likely to be
commissioned during 12th Plan.

Thermal Project:

Goindwal Sahib - 2X270 MW Coal Based Thermal Power Project - the 1 st unit is
scheduled for commercial operation on 31.01.2013 and 2 nd unit on 30.04.2013.

3. Rajasthan:

Ongoing:

Sl.n Project Capacity Commission


o ing
Schedule
1 KALISINDH TPS UNIT-1 600 MW December
2011
2 KALISINDH TPS UNIT-2 600 MW March 2012
3 CHHABRA TPS PHASE 2 (UNIT-3) 250 MW November
2011
4 CHHABRA TPS PHASE 2 (UNIT-4) 250 MW December
2011
5 RAMGARH EXTN. PROJECT GT 110 MW NOV 2011
6 RAMGARH EXTN. PROJECT ST 50 MW FEB 2012

Future Projects:

Sl. Project Capacity Commission


no ing
Schedule
1 CHHABRA TPS STAGE II (UNIT-5) 660 MW 30.11.2013
2 CHHABRA TPS STAGE II (UNIT-6) 660 MW 30.05.2014
3 SURATGARH TPS STAGE V (UNIT- 7) 660 MW 30.11.2013
4 SURATGARH TPS STAGE V (UNIT- 8) 660 MW 30.05.2014

Gas based Power plant:

Sl. Project Capacity Commission


no ing
Schedule
1 Dholpuer Gas Thermal Power Station 330 MW 2013-14
Stage-II
2 KOTA Gas Power Project 330 MW 2013-14
3 Chabra Gas Power Project 330 MW 2013-14
4 Ramgarh Gas Power Station(Stage 160 MW 2015-16
-IV)

Coal based power plant:

Sl. Project Capacity Commission


no ing
Schedule
1 Suratgarh TPS unit 9-10(Super 1320 MW 2015-16
Critical)
2 Kalisindh TPS Unit 3-4 (Super Critical) 1320 MW 2015-16
3 Banswara TPS Unit I-II(Super Critical) 1320 MW 2016-17

4. Himanchal Pradesh:

Projects which have been alloted/under process of allotment and expected to yield
benefit during the 12th Plan period

A) CENTRAL /JOINT SECTOR

1. Khab-I – Satluj – 450mw - Allotted to SJVNL

2. Khab-II - 186.00mw - Allotted to SJVNL

3. Luhri - 750.00mw - Allotted to SJVNL

4. Parbati-I - Beas 750.00mw - Allotted to NHPC

B) PRIVATE SECTOR

S.no Project Basin Capacity Status


(MW)

1 Chanju-I Ravi 25 Allotted


2 Chanju-II Ravi 17 Allotted

3 Bara Banghal Ravi 20 Allotted

4 Bajoli-Holi Ravi 18 Allotted

5 Kuther Ravi Ravi 260 Allotted

6 Suil Ravi Ravi 13 Under process of


allotment

7 Sal-I Ravi Ravi 6.5 Allotted

8 Bardang Chenab 126 Under process of


allotment

9 Chattru Chenab 108 Allotted

10 Miyar Chenab 90 Under process of


allotment

11 Tinget Chenab 81 Under process of


allotment

12 Teling Chenab 69 Under process of


allotment

13 Tandi Chenab 104 Under process of


allotment

14 Rashil Chenab 102 Under process of


allotment

15 Gondhala Chenab 144 Under process of


allotment

16 Khoksar Chenab 90 Under process of


allotment

17 Ropa Satluj 60 Under process of


allotment

18 Mane Nadang Satluj 70 Under process of


allotment

19 Lara Satluj 60 Under process of


allotment

20 Bahairari Satluj 5.5 Allotted


21 Chango Yangthang Satluj 140 Allotted

22 Yangthang Khab Satluj 261 Under process of


allotment

23 Sumta Kathang Satluj 130 Under process of


allotment

24 Kut Satluj 24 Allotted

25 Tidong-II Satluj 60 Allotted

26 Jangi thopan Satluj 480 Allotted

27 Thopan Porari Satluj 480 Allotted

28 Kilhi-Balh Beas 7.5 Under process of


allotment

29 Dhaula-Sidh Beas 40 Allotted

30 Shalvi Yamuna 7 Under process of


allotment

31 Rupin Yamuna 39 Allotted

5. Haryana:

Ongoing:

• 1320 MW Mahatma Gandhi Thermal Power Project in Jhajjar Case-II -


Power likely to be available from Dec., 2011

Future Projects:

• 1500 MW Gas based Project at Faridabad.


• 660 MW capacity additional super critical Thermal Unit at Yamuna
Nagar as an extension of 2x300 MW DCRTPP, Yamuna Nagar.
• 2800 MW (4x700 MW) Nuclear Power Plant in Distt. Fatehabad near
Village Gorakhpur – Site stands identified by Nuclear Power
Corporation of India. Govt. of India has approved the setting of this
Nuclear Power Project in Haryana during October 2009

6. Jammu and Kashmir:

Projects under construction: (State sector)


S.n Project Capacity
o (MW)
1 Baglihar Stage-II 450
2 Pahalgam(3rd Unit) 1.50
3 Matchil 0.35
4 Baderwah (3rd Unit) 0.5
5 Sanjak 1.26

7. Uttar Pradesh:

New Identified Projects

Schedule I – List of Tentative Small Hydro Projects (These details are


indicative. Capacity & Location of a particular SHP may change as per
assessment of Developer subject to approval of UPJVNL)

S
Capacity(
No Name of Project Distt Canal
M.W)
.
1 Khairi 3.75 Saharanpur Hathini Kund Link Canal
Sharda Canal Hardoi
2 Madho-I 3.75 Pilibhit
Branch
Shahjahanp Sharda Canal Hardoi
3 Madho-II 2.50
ur Branch
Shahjahanpur(Nahil Shahjahanp Sharda Canal Hardoi
4 2.50
) ur Branch
Ram Ganga Feeder
5 Ram Ganga 3.20 Bijnore
Canal
6 Bansagar-I 12.00 Mirzapur Adwa Meja Link Canal
7 Bansagar-II 10.00 Mirzapur Adwa Meja Link Canal
8 Ken Branch-I 3.00 Banda Ken Branch
9 Ken Branch-II 1.50 Banda Ken Branch
10 Bandran 10.50 Lalitpur Dam toe
11 Karmnasa 2.00 Chanduli Dam toe
12 Sharda Sagar 3.00 Pilibhit Dam toe
Sharda Canal Hardoi
13 Dunda 5.00 Pilibhit
branch
14 Malakpur Rehni 4.00 Saharanpur Eastern Yamuna Canal
15 Meja 9.50 Mirzapur Dam toe
76.20
Total
M.W.

8. Uttrankhand:

Future Plan:

S.no Project District Capacity Year of


(KW) Completion
1 Asiganga-III Uttarkashi 9000 2012-13
2 Dunao Pauri Garhwal 1500 2012-13
3 Suwarigad Uttarkashi 2000 2012-13
4 Tankul Pithoragarh 12000 2012-13
5 Sonegad Uttarkashi 3000 2012-13
6 Suringad II Pithoragarh 5000 2012-13
7 Urgam II Chamoli 3800 2012-13
8 Painagad Pithoragarh 9000 2012-13
9 Pilangad II Uttarkashi 4000 2012-13
10 Bhilangana-II- 2A Tehri 24000 2012-13
11 Bhilangana-II- 2B Tehri 24000 2012-13
12 Bhilangana-II- 2C Tehri 24000 2012-13

Greensite Project allocated to UJVNL

Estimated Completion
S.No. Name of Project Potential District River/Tributary Schedule
(MW)
1. Vyasi 120 Dehradun Yamuna May 2014
2. Lakhwar 300 Dehradun Yamuna 2016

3. Kishau 660 Dehradun Tons 2023

Work on hold
due to
4. Pala Maneri 480 Uttarkashi Bhagirathi environment
issues in river
Bhagirathi
5. Bharon Ghati 381 Uttarkashi Bhagirathi Same as above
6. Bowla Nandprayag 300 Chamoli Alaknanda 2016
7. Nand Pyayag Langasu 100 Chamoli Alaknanda 2017
8. Tamak lata * 280 Chamoli Dhauliganga 2016
9. Sirkari Bhyol Rupsiabagar 210 Pithoragarh Goriganga
10. Sela Urthing 230 Pithoragarh Dhauliganga
11. Taluka Sankri 140 Uttarkashi Tons
12. Rishiganga I 70 Chamoli Rishiganga
13. Rishiganga - II 35 Chamoli Rishiganga

PROJECTS UNDER DEVELOPMENT (Up to 25 MW)

S.No Name of project Capacity(MW)

2 Asiganga I 4.5

3 Asiganga II 3.0

4 Kaliganga I 4.0

5 Kaliganga II 6.0

6 Kalidigad 9.0

7 Madhyamaheshwar 15

8 Sobla-I 8

Total 53.0 MW

Western Region

1. Goa:

The Department does not have its own generation and purchases power from the
Central Sector Power Stations of the National Thermal Power Corporation. Besides
this, the department also purchases power of 16 Mw from Reliance Industries Ltd.,
Sancoale.

2. Daman and DIU:

The UT of Daman & Diu does not have its own power generation. The bulk power
supply is drawn from the Central Sector Power Stations in Western Region through
GETCO Grid.

3. Gujarat:

Following projects of GSECL are under implementation:


S.n Project Capacity (MW) Commissioning
o Date
1 Sikka TPS Extn 2*250 Unit 2 - 06/12
Unit 3 - 08/12
2 Pipavav Energy Private 2*600 Unit 1 - 08/13
Limited Unit 2 – 12/13

Following Projects are under various stages of Planning:

1 4X800 MW Coal Based Units at Kuchhadi, Dist. Porbandar


2 2X800 MW Coal Based Units at Sinor, Ta. Sinor, Dist. Vadodara
3 2X800 MW Coal Based Units at Dahej, Dist. Bharuch
4 2X1000 MW Gas Based Power Plants in North Gujarat

4. Madhya Pradesh:

Thermal projects in planning stage:


S.n Project Capacity
o
1 Banasagar TPP 2 X 800 MW
2 New Birsingpur TPS Distt: 2 X 500 MW or 1 X 500
Umaria MW or 2 X 250 MW
3 Amarkantak Extn Unit 6 1 X 250 MW
Distt : Annupur
4 Shahpura Project Distt - 1000 MW
Jabalpur
5 Shree Singaji TPP –I (Malwa TPP ) 2*600 MW

State Projects in Planning Stage - Hydel Projects

S.n Project Capacity


o
1 Sone HPS Distt Sidhi 5X20MW
2 Gandhi Sagar HEP Mandasaur 4X40MW
3 Kanhan HPS Distt Chindwara 2X45MW
4 Chambal Extn 270 MW
Stage-II
(i) Devipura (120 MW)
(ii) Jaitpura (40 MW)
(iii) Gujjapura (40 MW)
(iv) Barsala (70MW)

5. Maharashtra:
Ongoing:

• Chandrapur TPS Unit 8 & 9 (2 x 500 MW) - Trial operation of Unit 8 is


expected by Dec. 2012 followed by Unit 9 by March 2013.
• Parli TPS Unit 8 (1 x 250 MW - against existing 2 x 20 MW derated capacity
units, netcapacity addition : 210 MW). Trial operation is scheduled by Jan.
2012
• Koradi TPS Unit 8, 9 & 10 (3 x 660 MW - Unit 8 is against the existing 4 x 105
MWderated capacity units - Net capacity addition 1560 MW). The Trial
operation of Unit 8 is scheduled by Dec.2013 followed by Unit 9 by June
2014and Unit 10 by Dec. 2014.

Future Projects:

1. Uran Gas Based Combined Cycle Power Plant (1220 MW): (Block-I : 406
MW, Block-II:
814 MW).The trial operation of Block I (406 MW) is expected by June 2013
followed by Block II (814 MW) by September 2013.

2. Bhusawal TPS Unit 6 (1 x 660 MW against existing 55 MW capacity


units at Paras &
Bhusawal - Net capacity addition: 550 MW): Trial operation is expected by June
2015.

3. Nashik TPS Unit 6 (1 x 660 MW against existing 2 x 125 MW derated


capacity units – Net
capacity addition - 410 MW) :

Future Projects through Joint Venture – 9240 MW:

• Latur Coal Based Unit 1&2 (2 x 660 MW) or Gas based CCPP Block-
I & II (2 x 750
MW): the trial operation of the project is expected as under:
(i) Coal based: Unit 1 by June-2015 & Unit 2 by December- 2015 or
(ii) Gas based: Block-I by August 2013 and Block-II by November-2013.

Joint Venture through PPP (Public-Private Participation):

• Dhopawe TPS Project Unit – 1 to 3 (3 x 660 MW) :


• Dondaicha TPS Unit – 1, 2, 3, 4 & 5 (5 x 660 MW) :
• Coal based Thermal Power Project near Kanpa (Tal.Nagbhid, Dist.
Chandrapur) (2x660 MW) - Planning stage
• Coal based Thermal Power Project in Gondia District (2 x 660 MW) -
Planning stage
6. Chhattisgarh:

Ongoing:

• Korba tpp west extension 500MW – Commissioning schedule 06/12

• Marwa tpp – 2*500MW Janjgar - chamba - Commissioning schedule Unit


1 –sep 12, unit 2 – Nov 12

Future Projects:

Southern Region

1. Andhra Pradesh:

Future Projects:

• Rayalaseema TPP Unit-6 (600 MW) - commission by September,


2013.
• Gas based Station near Karimnagar (3x700 MW): 1st Block (700
MW) will be completed by March, 2013.
• IGCC Plant at Vijayawada TPS (182 MW): Unit is programmed to
commission by September, 2013.
• Sattupally TPS (600 MW): Unit is programmed to commission by
March, 2014.
• Vadarevu TPP Stage-I (1600 MW)
• Srikakulam TPS (2400 MW)
• Polavaram HEP (12x80 MW): First four units will be commissioned
by September, 2014 and the balance 8 units at an interval of 2 months
thereafter.
• Nuclear Power Plant in Kadapa District JV with Apgenco with Npcil

2. Karnataka:

Ongoing:
• Bidadi Combined Cycle Power Plant: 1400 MW – Unit is programmed to
commission by 2013

3. Kerela:

ON GOING SCHEMES

(Undertaken by KSEB)
Sl. No. Name of Project Power in MW Energy in MU
1. PALLIVASAL EXTENSION SCHEME 60 153.9
2. THOTTIYAR HEP 40 99.0
3. POOZHITHODE SHEP 4.80 10.97
4. RANNI-PERUNAD SHEP 4.0 16.73
5. CHATHANKOTTUNADA-II SHEP 6.0 14.76
6. VILANGAD SHEP 7.5 22.63
7. PEECHI SHEP 1.25 3.315
8. SENGULAM AUGMENTATION 85.0
SCHEME
9. ADYANPARA SHEP 3.5 9.01

PROJECTS TENDERED FOR IMPLEMENTATION BY KSEB

Sl. No. Name of Project Power in MW Energy in MU


1 ATHIRAPILLY HEP 163 233
2 MANKULAM HEP 40 82
3 KARAPUZHA DAM TOE SHEP 0.5 2.054
4 ANAKKAYAM SHEP 7.5 22.83
5 PERUMTHENARUVI SHEP 6.0 25.77
6 BARAPOLE SHEP 15 36

PROJECTS IN PIPELINE
Sl. No. Name of Project Power in MW
1 Kakkayam Small HEP 3.0
2 Poringalkuthu SHEP 24.0
3 Chimmony Small HEP 2.5
4 Sengulam Tail Race Project 3.6
5 Pazhassi Sagar HE Project 20.0
6 Chembukkadavu Stage III 6.0
7 Peruvannamoozhy 7.0
8 Upper Kallar Project 2.0
9 Peechad Project 3.0
10 Thumboormuzhi 8.0
11 Western Kallar 5.0
12 Koodam 4.5
13 Chinnar 24.0
14 Sengulam Extn. Scheme 48.0
15 Olikkal 4.5
16 Poovaramthodu 2.7

4. Tamilnadu:

Ongoing:

NTPC-TNEB joint venture)

• Vallur Thermal Power Station: Unit III (500MW) - commission by Nov


2012

• Udangudi Thermal Power Station:


Unit I (800MW) - commission by Mar.2013
Unit II (800MW)- commission by Sep.2013

Future:

1. ETPS ANNEXE 1X 600 MW: commission by Jan 2014


• Establishment of Ennore SEZ project of 2x800MW coal based
supercritical thermal power plant in the ash dyke of North
Chennai (Kattupalli) :the project is scheduled to be completed by 2015-16.

5. Pondicherry:

The bulk power supply is drawn from the Central Sector Power Stations and
other state electricity board. PPCL had had invited bidders to build a 500MW coal
based project. The last date for the prequalification was July 2009.

Eastern Region

1. Bihar:

Ongoing:

2. Barauni TPS Extension Under Bihar SEB: (2x250 MW) the project is scheduled
to be completed by 2013-14
3. Muzaffarpur TPS Extension - Under Kanti Bijlee Utpadan Nigam Ltd.- JV of
Bihar SEB & NTPC Ltd.

2x195 MW extension at Muzaffarpur TPS (2013-14)

IPP Power-Stations under Case-2: Tariff based Bidding

S.no Project Capacity Expected Schedule

1 Buxar Bijlee 2x660 MW 2015-16


Company Pvt. Ltd. at
Chausa, Buxar Dist.
2 Lakhisarai Bijlee 2x660 MW 2015-16
Company Pvt. Ltd. at
Kajara, Lakhisarai.
3 Pirpainti Bijlee 2x660 MW 2015-16
Company Pvt. Ltd. at
Pirpainti, Bhagalpur
District
IPP Power Stations (MOU Signed with BSEB)

1 M/s Jas Infrastructure 2x660 MW 2014-15


Capital Pvt. Ltd., +
Nagpur at Banka 2x660 MW
(Bhagalpur)
2 M/s Vikas Metal & 500 MW Firm has postponed their
Power Ltd., Kolkata, project activities till the
at Begusarai. allotment of coal block and
suitable land by BIADA.

3 M/s Nalanda Power 4x500 MW in 2014-15


Company Ltd. two phases
Kolkata at Pirpainti
(Bhagalpur)
4 M/s Adhunik Power & 2x500 MW in 2014-15
Natural Resources two phases
Ltd., Kolkata, at
Lakhisarai/Bhagalpur
.

Other IPP projects approved by State Investment Planning Board (SIPB)

S.n Project Capacit Expected


o y Schedule
1 M/s Subhas Projects & 1200 M 13th Plan
Marketing Ltd., Kolkata, at W
Lakhisarai.
2 M/s IL&FS, New Delhi, at 500 MW 13th Plan
Motipur (Muzaffarpur)
3 M/s India Power Corporation 1650 M 13th Plan
Ltd., Kolkata W
4 M/s Cement Manufacturing 500 MW 13th Plan
Company Ltd., Kolkata, at
Kahalgaon (Bhagalpur)
5 M/s Essar Power, Ranchi 1800 M 13th Plan
W
6 M/s Usha-Martin, New Delhi, 1200- 13th Plan
at Kahalgaon (Bhagalpur) 1320
MW
7 M/s East-West Power 1000 M 13th Plan
Generation Co. Ltd., W
Maharashtra at Kahalgaon,
Bhagalpur
8 M/s Triton Energy Ltd., 1320 M 13th Plan
Gurgaon, Haryana, at Kochar, W
Aurangabad.
9 M/s Krishak Bharti Co- 1320 M 13th Plan
operative Ltd., New Delhi. W
10 NPCIL proposed for 4x700 M -
installation of 4x700 MW W
Nuclear Power Plant at
Rajauli, Nawada District.

2. Jharkhand:
New projects:

1. 1000 MW thermal power plant at Patratu


2. 1000 MW thermal power plant in Santhal Pargana region
3. 1000 MW thermal power plant linked with Maurya coal block (210 MT) to be
allocated to Jharkhand/JSEB under tariff based competitive bidding

Bihar State Hydroelectric Power Corporation Limited:

Ongoing Projects IN BIHAR:

S.n Project Capacity


o
1 Bathnaha Phase-I Small Hydel Project 8 MW
2 Nirmali Small Hydel Project 7 MW
3 Dhoba Small Hydel Project 2x1000 KW
4 Katanya Small Hydel Project 2x1000 KW
5 Mathauli Small Hydel Project 2x400 KW
6 Barwal Small Hydel Project 2x800 KW
7 Walidad Small Hydel Project 1x700 KW
8 Dehra Small Hydel Project 2x500 KW
9 Sipaha Small Hydel Project 2x500 KW

Projects in Jharkhand:

1. North Koel Hydroelectric Project (2x12 MW)


2. Chandil Dam H.E. Project (2x4 MW)
3. Tenu-Bokaro Link Canal H.E.P. (1x1 MW)
4. Sadani Hydroelectric Project (2x500 KW)
5. Lower Ghaghari Small Hydroelectric Project ( 2x200 KW)
6. Netarhat Small Hydroelectric Project ( 1x40 KW)
7. Nindighagh Demo Hydroelectric Project (1x200 KW)
8. Jalimghagh Demo Hydroelectric Project (1x200 KW)

Planned Project:

1. Kanhar Pumped – Storage Hydroelectric Project –


2. Sankh Hydroelectric Project

Proposed Big Projects


• Sinafdar PSS (3 x 115 MW)
• Panchgotia PSS (3x75 MW)
• Telharkund PSS (4 x 100 MW)
• Hathiahdah- Durgawati PSS (8 x 200 MW)
• Indrapuri Reservour Project (450 MW)
• Kohira Dam Pumped Storage (3x38 MW)
• Dagmara Hydroelectric Power Project

3. Orissa:

Hydel Project Under construction:

S.n Project Capacity


o
1 Potteru Small HE 2 x 3 MW
Project

Hydel project Identified for Future Implementation

S.n Project capacity


o
1 Sindhol Complex
a Deogaon 3 x 30 MW
b Kapasira 3 x 30 MW
c Godhaneswar 4 x 30 MW
2 Middle Kolab Hydro Electric 285 MW
Project
3 Tel Integrated Project To be assessed during DPR stage
4 Lower Vansadhara Project To be assessed during DPR stage
5 Balijori Hydro Electric Project 160 MW
6 Salki Hydro electric Project 96 MW
7 Khadago Project To be assessed during DPR stage
8 Uttel & Roul Integrated Project To be assessed during DPR stage
9 Mahanadi-Brahmani River Link 150 MW
10 Barmul Hydro Electric Project 60 MW

Private- Thermal projects:

S.n Project Company Capacity Commissioning


o Schedule
1 Kamalanga TPP GMR Kamalanga 3*350 Unit 1 - 04/12
Energy ltd Unit 2 – 06/12
Unit 3 – 08/12
2 Derang TPP JITPL 2*600 Unit 1 - 12/11
Unit 2 – 02/12
3 Ind.Bharat Energy Ind.Bharat 2*350 Unit 1 - 12/11
TPP Energy Unit 2 – 02/12

4. West Bengal:
The West Bengal Power Development Corporation Ltd. 2 Units of 500 MW each-Unit
No.3 & 4

North and Eastern region:

1. Assam, Arunachal Pradesh, Meghalaya and Nagaland :

The government has envisaged to establish a number of small Hydel projects

2. Tripura:

• Tripura CCPP Village :Palatana, Distt:Udaipur (Tripura) -OTPC (JV of ONGC,


Tripura State and IL&FS) –
 Unit 1 – (363.3MW) – To be commissioned during 09/12
 Unit 2 – (363.3MW) – To be commissioned during 02/13

Proposed Capacity Addition in Generation

 105 MW CCGT Project at Chakmaghat.


 104 MW TGBPP at Manarchwak by NEEPCO.
 740 MW CCGT at Palatana by OTPC.

3. Manipur:

New Proposals :

A). Proposed Micro Hydel Schemes to be implemented under Capital


Subsidy Programme.

The State Government proposes to implement/ investigate the following hydel


projects with different funding agencies. Investigation schemes for medium sized
projects are funded by Govt. of India as an Additional Plan Assistance through NEC.
The micro hydel schemes are subsidised by the Ministry of Non-Conventional
Energy Sources, Government of India. The projects not covered by the above will be
taken up under State Plan.

Proposed Micro Hydel Schemes under Capital Subsidy Programme

Estimated
Sl. Name of Capacity(K
Cost(Rs. in Present status
No. Project W)
lakhs)
1. Gelnel - II 2 x 100 115.51 DPR prepared and submitted to
2. Tuipaki 2 x 250 256.59 Govt.
3. Haipi 2 x 50 91.80

Total : 800 463.90 Clearance from Forest and


Environment
angles awaited for submission to
MNES
B). Schemes proposed for survey and investigation

The following schemes are being taken up under the State Sector.

i) Medium/Small Hydro Electric Projects:

Estimated
Sl. Name of Capacity(K
Cost(Rs. in Present status
No. Project W)
lakhs)
Under Detail Survey and
1. Irang 4 x 15 MW 186.55 Investigation
(DSI) with NEC fund.
NEC fund is awaited for
completion of
2. Tuivai 3 x 17 MW 131.29*
survey and investigation work.
* Revision is in progress.
NEC fund is awaited for starting
Maklang-
3. 3 x 15 MW 243.00 survey
Tuyungbi
and investigation work.

ii). Mini/Micro Hydro Electric Projects:

Estimated
Sl. Name of Capacity
Cost (Rs. in Present status
No. Project (KW)
lakhs)
Chakpi/Phunch Pre-Feasibility Report (PFR)
1. 3 x 200 6.00
ang submitted to Govt. Detail
2. Chakpikarong 3 x 200 6.00 Survey and
3. Irang 3 x 100 4.00 Investigation (DSI) is being
taken up
4. Ijai 3 x 500 5.00 as soon as the financial health
5. Tupul 3 x 300 4.00 of the
Total : 3900 25.00 state permits.
LONG TERM FORECAST AT POWER STATION BUSBARS (UTILITIES)

State Electrical Energy Requirement (GWh) Peak Electric Load (MW)


2011 -2012 2016 - 2017 2021-2022 2011 -2012 2016 - 2017 2021-2022
Delhi 36292.545 52762.386 73481.328 6092.409 8728.832 12069.050
Haryana 38417.069 54304.879 73838.162 6839.158 9375.160 12557.464
Himachal Pradesh 9503.908 13135.520 17657.400 1611.109 2194.159 2906.958
Jammu & Kashmir 11202.446 15271.949 21282.743 2062.737 2789.568 3856.642
Punjab 60488.861 82571.657 107342.309 11000.469 14441.277 18351.770
Rajasthan 48915.759 67767.236 92376.811 8482.079 11404.490 15100.779
Uttar Pradesh 79267.680 110664.947 150157.415 13947.013 19622.530 26833.528
Uttarnanchal 8444.717 11667.894 16191.306 1533.337 2085.410 2849.272
Chandigarh 2308.347 3366.693 4440.158 419.542 602.307 782.095
Sub Total (NR) 294841.333 411513.161 556767.632 48136.901 66582.928 89912.790
Goa 4582.911 6879.880 9082.496 721.306 1082.827 1429.498
Gujarat 85445.226 119083.096 156841.512 14373.742 19670.034 25446.677
Chhattisgarh 21784.878 33076.392 45115.620 3565.388 5374.867 7279.413
Madhya Pradesh 49338.498 70444.570 98986.680 8461.912 11772.241 16128.817
Maharashtra 125661.409 167226.739 219910.417 21953.740 28347.752 35944.127
D. & N. Haveli 5041.957 8204.128 12242.813 777.792 1265.600 1888.623
Daman & Diu 3004.817 4890.242 7842.185 552.088 857.119 1323.701
Sub Total (WR) 294859.697 409805.046 550021.724 47108.381 64348.650 84778.064
Andhra Pradesh 89032.490 132118.210 175590.124 14721.210 21845.290 28215.843
Karnataka 53539.620 79995.770 107470.552 8826.000 13092.380 17463.812
Kerala 19229.540 26331.640 36134.030 3528.050 4573.790 5916.364
Tamil Nadu 87221.910 134754.730 182825.156 14224.060 21975.660 29814.931
Pondicherry 4419.430 6867.800 9639.046 682.500 1060.600 1488.566
Sub Total (SR) 253442.990 380068.150 511658.908 40367.135 60432.580 80484.967
Bihar 19904.770 32857.080 58248.405 3607.000 5598.220 9567.426
Jharkhand 23408.480 36274.000 51741.061 4296.130 6604.000 9129.079
Orissa 27149.150 39095.650 63098.108 4459.000 6330.460 10074.098
West Bengal 41019.893 60228.010 84498.993 7406.850 10742.720 15071.881
Sikkim 320.000 486.930 629.382 83.000 119.540 150.465
Sub Total (ER) 111802.293 168941.670 258215.949 19088.442 28400.908 42711.602
Assam 7584.620 13052.660 24433.491 1443.000 2292.350 3984.588
Manipur 931.890 1359.680 2336.809 203.000 269.940 444.598
Meghalaya 2101.000 2777.700 4015.131 428.290 542.030 751.391
Nagaland 698.000 1040.070 1505.358 152.000 222.340 318.821
Tripura 1229.000 1761.080 3180.264 282.000 386.610 666.135
Arunachal Pradesh 385.520 557.380 762.307 116.000 147.970 189.177
Mizoram 398.481 594.690 763.662 115.249 161.750 196.033
Sub Total (NER) 13328.511 21143.260 36997.022 2536.610 3759.804 6179.947
Andman & Nicobar 343.590 536.570 779.450 76.910 118.940 131.660
Lakshadweep 40.130 58.190 67.548 11.450 16.610 19.277
Total (All India) 968658.543 1392066.048 1914508.233 152746.097 218208.593 298253.241
Top 10 states in terms of additional energy requirement in 2021-2022
compared to 2011 – 2012 is given below

S.n State Energy Requirement


o (GWh)
1 Tamilnadu 95603.25
2 Maharashtra 94249.01
3 Andhra Pradesh 86557.63
4 Gujarat 71396.29
5 Uttar Pradesh 70889.74
6 Karnataka 53930.93
7 Madhya Pradesh 49648.18
8 Punjab 46853.45
9 West Bengal 43479.1
10 Rajasthan 43467.05
*based on 17th Electric Power supply by CEA

States With a potential to Harness Hydel projects in large numbers

1. Himachal Pradesh
2. Punjab
3. Uttarakhand
4. Andhra Pradesh
5. Kerala
6. Entire eastern region (Bihar, Jharkhand, West Bengal, Orissa and
Sikkim )
7. Entire North eastern region (Assam, Arunachal Pradesh,
Meghalaya, Tripura, Manipur, Nagaland and Mizoram)

Top 3 states in each region to come up with future projects

Northern region:

1. Rajasthan
2. Haryana
3. Uttrakhand

Western Region:

1. Maharashtra
2. Gujarat
3. Madhya Pradesh
Southern Region:

1. Andhra Pradesh
2. Tamil Nadu
3. Karnataka

Eastern Region

1. Bihar
2. Jharkhand
3. West Bengal and Orissa

North Eastern Region:

1. Tripura
2. Arunachal Pradesh and Manipur

*Based on data available on respective state electricity board

12TH PLAN AND BEYOND

The Working Group on Power has recommended a plan size of about 82,200 MW for
12th Plan also. This would comprise hydro projects totaling about 30,000 MW,
thermal projects totaling 42,200 MW and nuclear projects of about 10,000 MW
capacities.