You are on page 1of 1

CASE studY

Using technology to map out the risks

Fire and gas detection systems aimed at protecting people and assets

S
afety and economy are high on Shell Global Solutions’ fire and gas detection Øystein Palmgren, Health, Safety and
the agenda throughout the oil and mapping technique, which has been developed Environment Adviser, A/S Norske Shell,
gas industry, and tried-and-tested over 15 years’ operational experience and says, “For the Ormen Lange project, more
technology can help deliver both peace of used on more than 100 Shell Group up- and than 200 mapping areas were evaluated,
mind and cost savings. downstream projects, was used during both making it one of the largest and most
Two major projects currently under projects. The method uses software to assess complex jobs of its type ever performed by
way in Norway are using proven fire and the placement and performance of detectors Shell Global Solutions.
gas detection mapping techniques in very by simulating idealised fire and gas-release “The verification process found that both
contractors had delivered robust designs.
The changes recommended were small, but
very valuable, and the whole process was
very reassuring.”
Production from the Draugen
monotower platform, which lies north­
west of Kristiansund, started in 1993, and
the safety system used consisted of early
versions of flame detectors and catalytic
gas detectors. Here, Shell Global Solutions’
mapping project involved redesigning the
fire and gas system so that it achieved the
required detection coverage.
The tool was used to investigate the
different ways. These projects are the huge scenarios throughout 3D models of the review original detection facilities. The results
Nyhamna gas processing plant serving sites. The output of the exercise is a coverage showed low coverage, especially for gas
the Ormen Lange field, and the Draugen map of each hazardous zone and a table giving detection. A new system, based on the
offshore oil facility. each individual detector’s contribution to the findings of the evaluation, was then
Ormen Lange is the second largest gas coverage achieved. The tool is therefore used to designed. Currently being installed, it uses
field on the Norwegian continental shelf. assess, optimise and design fire and gas detector 30 fewer flame detectors and hundreds
During construction of an onshore processing layouts that typically accommodate the latest fewer gas detectors to provide the required
plant at Nyhamna for gas from the field, safety legislation. level of coverage.
the engineering contractors required the At Ormen Lange, it was decided early in Palmgren says, “The coverage of the
newly designed fire and gas detector layout the installation’s design that the technique new system at Draugen uses fewer, but
to demonstrably provide mitigation of risk would be used as a verification tool, rather better, detectors with the aim of reducing
and an auditable assessment of the coverage than as an engineering tool. This enabled the the risks to both personnel and the asset.
provided by the detectors. plant’s engineering contractors, Aker Kværner The mapping exercise resulted in a major
At the offshore Draugen field oil platform, and Vetco Aibel, to recommend the best reduction in the number of detectors, from
a risk assessment review had recommended overall fire and gas detection system design approximately 500 point gas detectors to a
upgrading the fire and gas detection system and left the Shell Global Solutions team to combination of 51 line-of-sight detectors
as a risk-reducing measure. The layouts evaluate the effectiveness of the layout. The and 37 point gas detectors.”
recommended by Shell Global Solutions were timing of the engineering phase and the
tuned to the design intent for each module of verification process meant that recommended • Contact: Bob Nicol
Email: robert.nicol@shell.com
the facility. improvements could be made.

14 impact Issue 2, 2008 www.shell.com/globalsolutions

You might also like