Professional Documents
Culture Documents
PART - A - ELECTRICAL
A B C
5% successive Sundry
Sl. Unit Ex-
Work Items hike for 3 yrs Charge
No. works Price
(A x 1.053) (5% of B)
PART - B - CIVIL
1 All Civil works 81.51 94.36 4.72
Page 1 of 50
D
Total Price
(B+C)
8,229,142.62
254,488.11
107,207.65
1,641,876.67
4,197,267.06
781,038.04
125,349.08
185,675.87
41,783.03
1,023,187.64
147,319.36
167,132.11
16,901,467.24
169.01
16.90
185.92
185.92
99.08
10.00
10.00
20.00
304.99
Page 2 of 50
POWER FINANCE CORPORATION LTD.
Detail Project Report - Part B
Cost Data of 33/11 kV Sub-station
A1 A2 B C D E F G H
Cost of Foundation
Cost of Supporting
(Cost Data: 2009-10)
Erection Charges
1.053 x (A2+B+C)]
5% hike for each
[D = 1.05 x A1 +
Sundry Charge
(E = 5% of D)
year
Work Items Unit
No.
TRANSFORMERS
33/11 kV, 10.0 MVA Power Transformer No. 8,427,216.00 - 42,000.00 8,897,197.05 444,859.85 9,342,056.90 934,205.69 102.763
33/11 kV, 6.3 MVA Power Transformer No. 4,379,431.00 - 42,000.00 4,647,022.80 232,351.14 4,879,373.94 487,937.39 53.673
33/11 kV, 3.15 MVA Power Transformer No. 2,394,727.00 - 42,000.00 2,563,083.60 128,154.18 2,691,237.78 269,123.78 29.604
33/0.433 kV, 100 kVA Station Transformer No. 218,718.00 - 15,000.00 247,018.28 12,350.91 259,369.19 25,936.92 2.853
CT, PT
33 kV CT (400 - 200 / 1 - 1 - 1 A) No. 23,317.00 4,950.00 5,000.00 36,001.22 1,800.06 37,801.28 3,780.13 0.416
33 kV CT (400 - 200 / 1 - 1 A) No. 20,173.00 4,950.00 5,000.00 32,700.02 1,635.00 34,335.02 3,433.50 0.378
33 kV CT (400 - 200 / 5 - 5 A) No. 21,129.00 4,950.00 5,000.00 33,703.82 1,685.19 35,389.01 3,538.90 0.389
33 kV CT (200 - 100 / 1 - 1 A) No. 22,018.00 4,950.00 5,000.00 34,637.27 1,731.86 36,369.13 3,636.91 0.400
33 kV CT (200 - 100 / 5 - 5 A) No. 21,759.00 4,950.00 5,000.00 34,365.32 1,718.27 36,083.58 3,608.36 0.397
33 kV CT (100 - 50 / 5 - 5 A) No. 20,493.00 4,950.00 5,000.00 33,036.02 1,651.80 34,687.82 3,468.78 0.382
33 kV PT
33 kV / 110V No. 18,571.00 4,950.00 5,000.00 31,017.92 1,550.90 32,568.81 3,256.88 0.358
√3 √3
11 kV CT (400 - 200 / 1 - 1 A)
11 kV CT (300 - 150 / 1 - 1 A) No. 14,438.00 16,713.79 835.69 17,549.48 1,754.95 0.193
11 kV CT (200 - 100 / 1 - 1 A)
Page 3 of 50
A1 A2 B C D E F G H
Cost of Foundation
Cost of Supporting
(Cost Data: 2009-10)
Erection Charges
1.053 x (A2+B+C)]
5% hike for each
[D = 1.05 x A1 +
Sundry Charge
(E = 5% of D)
year
Work Items Unit
No.
Circuit Breakers
33 kV, 1250A Outdoor VCB No. 287,251.00 15,000.00 318,977.93 15,948.90 334,926.82 33,492.68 3.684
33 kV, 1250A Outdoor SF6 CB No. 319,731.44 15,000.00 387,493.48 19,374.67 406,868.16 40,686.82 4.476
11 kV, 800A Indoor VCB Panel - Incomer No. 484,288.00 560,623.90 28,031.19 588,655.09 58,865.51 6.475
11 kV, 800A Indoor VCB Panel - Outgoing No. 584,753.00 676,924.69 33,846.23 710,770.93 71,077.09 7.818
11 kV, 800A Indoor VCB Panel - Bus Coupler No. 422,081.00 488,611.52 24,430.58 513,042.09 51,304.21 5.643
12 KV, 350MVA, 1250 / 800A 16 PNL (4+3+9) VCB SET 4,942,084.00 5,189,188.20 259,459.41 5,448,647.61 544,864.76 59.935
12 KV, 350MVA, 1250 / 800A 14 PNL (3+3+8) VCB SET 4,349,056.00 4,566,508.80 228,325.44 4,794,834.24 479,483.42 52.743
12 KV, 350MVA, 1250 / 800A 14 PNL (4+3+7) VCB SET 4,412,198.00 4,632,807.90 231,640.40 4,864,448.30 486,444.83 53.509
12 KV, 350MVA, 1250 / 800A 14 PNL (3+2+9) VCB SET 4,351,499.00 4,569,073.95 228,453.70 4,797,527.65 479,752.76 52.773
12 KV, 350MVA, 1250 / 800A 13 PNL (4+3+6) VCB SET 4,046,094.00 4,248,398.70 212,419.94 4,460,818.64 446,081.86 49.069
12 KV, 350MVA, 1250 / 800A 11 PNL (2+1+8) VCB SET 3,381,356.00 3,550,423.80 177,521.19 3,727,944.99 372,794.50 41.007
12 KV, 350MVA, 1250 / 800A 10 PNL (2+1+7) VCB SET 2,212,623.00 2,323,254.15 116,162.71 2,439,416.86 243,941.69 26.834
12 KV, 350MVA, 1250 / 800A 10 PNL (3+2+5) VCB SET 2,239,925.00 2,351,921.25 117,596.06 2,469,517.31 246,951.73 27.165
12 KV, 350MVA, 1250 / 800A 9 PNL (2+1+6) VCB SET 1,997,842.00 2,097,734.10 104,886.71 2,202,620.81 220,262.08 24.229
12 KV, 350MVA, 1250 / 800A 7 PNL (2+1+4) VCB SET 1,568,279.00 1,646,692.95 82,334.65 1,729,027.60 172,902.76 19.019
12 KV, 350MVA, 1250 / 800A 10 PNL (2+2+6) VCB SET 3,054,043.00 3,206,745.15 160,337.26 3,367,082.41 336,708.24 37.038
12 KV, 350MVA, 1250 / 800A 9 PNL (2+1+6) VCB SET 2,827,271.00 2,968,634.55 148,431.73 3,117,066.28 311,706.63 34.288
12 KV, 350MVA, 1250 / 800A 8 PNL (2+1+5) VCB SET 2,523,938.00 2,650,134.90 132,506.75 2,782,641.65 278,264.16 30.609
12 KV, 350MVA, 1250 / 800A 8 PNL (2+2+4) VCB SET 2,494,927.00 2,619,673.35 130,983.67 2,750,657.02 275,065.70 30.257
12 KV, 350MVA, 1250 / 800A 7 PNL (2+1+4) VCB SET 2,220,605.00 2,331,635.25 116,581.76 2,448,217.01 244,821.70 26.930
Page 4 of 50
A1 A2 B C D E F G H
Cost of Foundation
Cost of Supporting
(Cost Data: 2009-10)
Erection Charges
1.053 x (A2+B+C)]
5% hike for each
[D = 1.05 x A1 +
Sundry Charge
(E = 5% of D)
year
Work Items Unit
No.
12 KV, 350MVA, 1250 / 800A 4 PNL (1+1+2) VCB SET 1,228,359.00 1,289,776.95 64,488.85 1,354,265.80 135,426.58 14.897
12 KV, 350MVA, 1250 / 800A 4 PNL (0+0+4) VCB SET 1,194,653.00 1,254,385.65 62,719.28 1,317,104.93 131,710.49 14.488
12 KV, 350MVA, 1250 / 800A 3 PNL (1+1+1) VCB SET 944,130.00 991,336.50 49,566.83 1,040,903.33 104,090.33 11.450
12 KV, 350MVA, 1250 / 800A 3 PNL (1+0+2) VCB SET 973,142.00 1,021,799.10 51,089.96 1,072,889.06 107,288.91 11.802
12 KV, 350MVA, 1250 / 800A 3 PNL (0+0+3) VCB SET 909,999.00 955,498.95 47,774.95 1,003,273.90 100,327.39 11.036
12 KV, 350MVA, 1250 / 800A 2 PNL (0+0+2) VCB SET 606,666.00 636,999.30 31,849.97 668,849.27 66,884.93 7.357
12 KV, 350MVA, 1250 / 800A 1 PNL (0+0+1) VCB SET 298,663.00 313,596.15 15,679.81 329,275.96 32,927.60 3.622
XLPE Cables
33/19 kV, 1c x 400 sq.mm. XLPE Cable Km 809,801.00 850,291.05 42,514.55 892,805.60 89,280.56 9.821
33/19 kV, 3c x 300 sq.mm. XLPE Cable Km 1,523,864.00 1,600,057.20 80,002.86 1,680,060.06 168,006.01 18.481
33/19 kV, 3c x 240 sq.mm. XLPE Cable Km 1,752,526.00 2,028,767.91 101,438.40 2,130,206.31 213,020.63 23.432
33/19 kV, 3c x 185 sq.mm. XLPE Cable Km 1,654,547.00 1,737,274.35 86,863.72 1,824,138.07 182,413.81 20.066
11 kV (E), 3c x 300 sq.mm. XLPE Cable Km 1,377,545.00 1,446,422.25 72,321.11 1,518,743.36 151,874.34 16.706
11 kV (E), 3c x 185 sq.mm. XLPE Cable Km 969,668.00 1,018,151.40 50,907.57 1,069,058.97 106,905.90 11.760
11 kV (E), 3c x 95 sq.mm. XLPE Cable Km 671,102.00 704,657.10 35,232.86 739,889.96 73,989.00 8.139
1.1 kV, 3.5c x 120 sq.mm. XLPE Cable Km 345,831.00 400,342.61 20,017.13 420,359.74 42,035.97 4.624
1.1 kV, 1c x 300 sq.mm. XLPE Cable Km 246,676.00 259,009.80 12,950.49 271,960.29 27,196.03 2.992
1.1 kV, 1c x 240 sq.mm. XLPE Cable Km 194,327.00 204,043.35 10,202.17 214,245.52 21,424.55 2.357
1.1 kV, 1c x 185 sq.mm. XLPE Cable Km 156,164.00 163,972.20 8,198.61 172,170.81 17,217.08 1.894
1.1 kV, 1c x 150 sq.mm. XLPE Cable Km 119,698.00
1.1 kV, 1c x 120 sq.mm. XLPE Cable Km 95,679.00 100,462.95 5,023.15 105,486.10 10,548.61 1.160
1.1 kV, 1c x 95 sq.mm. XLPE Cable Km 76,887.00 80,731.35 4,036.57 84,767.92 8,476.79 0.932
1.1 kV, 1c x 70 sq.mm. XLPE Cable Km 74,890.00 78,634.50 3,931.73 82,566.23 8,256.62 0.908
1.1 kV, 1c x 50 sq.mm. XLPE Cable Km 46,652.00 48,984.60 2,449.23 51,433.83 5,143.38 0.566
1.1 kV, 1c x 25 sq.mm. XLPE Cable Km 26,928.00 28,274.40 1,413.72 29,688.12 2,968.81 0.327
Page 5 of 50
A1 A2 B C D E F G H
Cost of Foundation
Cost of Supporting
(Cost Data: 2009-10)
Erection Charges
1.053 x (A2+B+C)]
5% hike for each
[D = 1.05 x A1 +
Sundry Charge
(E = 5% of D)
year
Work Items Unit
No.
Page 6 of 50
A1 A2 B C D E F G H
Cost of Foundation
Cost of Supporting
(Cost Data: 2009-10)
Erection Charges
1.053 x (A2+B+C)]
5% hike for each
[D = 1.05 x A1 +
Sundry Charge
(E = 5% of D)
year
Work Items Unit
No.
PVC Cables
1.1 kV, 3.5c x 240 sq.mm. PVC Cable Km 806,747.00 847,084.35 42,354.22 889,438.57 88,943.86 9.784
1.1 kV, 3.5c x 185 sq.mm. PVC Cable Km 649,213.00 681,673.65 34,083.68 715,757.33 71,575.73 7.873
1.1 kV, 3.5c x 120 sq.mm. PVC Cable Km 345,831.00 363,122.55 18,156.13 381,278.68 38,127.87 4.194
1.1 kV, 3.5c x 95 sq.mm. PVC Cable Km 347,306.00 364,671.30 18,233.57 382,904.87 38,290.49 4.212
1.1 kV, 3.5c x 70 sq.mm. PVC Cable Km - - - - -
1.1 kV, 3.5c x 50 sq.mm. PVC Cable Km 214,925.00 225,671.25 11,283.56 236,954.81 23,695.48 2.607
1.1 kV, 3.5c x 35 sq.mm. PVC Cable Km 121,120.00 140,211.54 7,010.58 147,222.12 14,722.21 1.619
1.1 kV, 3.5c x 25 sq.mm. PVC Cable Km 102,526.00 107,652.30 5,382.62 113,034.92 11,303.49 1.243
1.1 kV, 4c x 16 sq.mm. PVC Cable Km 112,156.00 117,763.80 5,888.19 123,651.99 12,365.20 1.360
1.1 kV, 4c x 10 sq.mm. PVC Cable Km 56,657.00 59,489.85 2,974.49 62,464.34 6,246.43 0.69
1.1 kV, 4c x 6 sq.mm. PVC Cable Km 48,694.00 51,128.70 2,556.44 53,685.14 5,368.51 0.59
1.1 kV, 2c x 10 sq.mm. PVC Cable Km 34,392.00 39,813.04 1,990.65 41,803.69 4,180.37 0.46
1.1 kV, 2c x 6 sq.mm. PVC Cable Km 26,715.00 28,050.75 1,402.54 29,453.29 2,945.33 0.32
1.1 kV, 2c x 4 sq.mm. PVC Cable Km 5,002.00 5,252.10 262.61 5,514.71 551.47 0.06
1.1 kV, 2c x 2.5 sq.mm. PVC Cable Km 9,960.00 11,529.95 576.50 12,106.44 1,210.64 0.13
1.1 kV, 2c x 1.5 sq.mm. PVC Cable Km 6,600.00 7,640.33 382.02 8,022.34 802.23 0.09
LA
42 kV LA (1 Set = 3 nos.) Set 22,599.00 23,728.95 1,186.45 24,915.40 2,491.54 0.274
12 kV LA (1 Set = 3 nos.) Set 1,029.00 1,080.45 54.02 1,134.47 155.00 0.013
Isolators
33 kV, 400A L.L. CR type Isolator No. 36,993.00 15,840.00 57,179.43 2,858.97 60,038.40 6,003.84 0.660
33 kV, 400A H.L. CR type Isolator with E/I No. 54,440.00 15,180.00 74,734.75 3,736.74 78,471.48 7,847.15 0.863
33 kV, 1250A H.L. CR type Isolator with E/S & E/I No. 72,299.00 15,180.00 93,486.70 4,674.33 98,161.03 9,816.10 1.080
Page 7 of 50
A1 A2 B C D E F G H
Cost of Foundation
Cost of Supporting
(Cost Data: 2009-10)
Erection Charges
1.053 x (A2+B+C)]
5% hike for each
[D = 1.05 x A1 +
Sundry Charge
(E = 5% of D)
year
Work Items Unit
No.
Communication
Page 8 of 50
Sl.
No.
Work Items
Page 9 of 50
122,370.00
Cost of Supporting
B
Structure
(Cost Data: 2007-08)
Cost of Foundation
C
[D = 1.05 x A1 +
1.053 x (A2+B+C)]
243,101.25
Sundry Charge
E
(E = 5% of D)
12,155.06
(F = D+E)
255,256.31
Erection Charges
G
(10% on F)
25,525.63
Total Price
H
(H = F + G)
[in Rs. Lacs]
3.982
2.808
A1 A2 B C D E F G H
Cost of Foundation
Cost of Supporting
(Cost Data: 2009-10)
Erection Charges
1.053 x (A2+B+C)]
5% hike for each
[D = 1.05 x A1 +
Sundry Charge
(E = 5% of D)
year
Work Items Unit
No.
Civil Works
Development of Land (Incl.Labor Charge) LS 1,100,000.00 1,273,387.50 63,669.38 1,337,056.88 - 13.371
Boundary Wall (Incl. Labor Charge) LS 1,872,000.00 2,167,074.00 108,353.70 2,275,427.70 - 22.754
Switchyard Fencing (Incl. Labor Charges) LS 400,000.00 463,050.00 23,152.50 486,202.50 - 4.862
Control Room Building (Incl. Labor Charge) LS 2,600,000.00 3,009,825.00 150,491.25 3,160,316.25 - 31.603
Electrification of Control Room Building (Incl. Labor
LS 100,000.00 115,762.50 5,788.13 121,550.63 - 1.216
Charge)
Approach Road & Drainage (Incl. Labor Charge) LS 500,000.00 578,812.50 28,940.63 607,753.13 - 6.078
Cable Trench (Incl. Labor Charge) LS 200,000.00 231,525.00 11,576.25 243,101.25 - 2.431
Substation Earthing Complete LS 82,500.00 95,504.06 4,775.20 100,279.27 21,625.00 1.219
Substation Yard Lighting LS 103,125.00 119,380.08 5,969.00 125,349.08 12,534.91 1.379
Substation Shielding with 6 nos. Rail Pole & 50 sq.mm.
LS 147,200.00 12,800.00 185,220.00 9,261.00 194,481.00 19,448.10 2.139
Weasel conductor
Gravel Filling on Switchyard (Incl. Labor Charge) LS 350,000.00 405,168.75 20,258.44 425,427.19 - 4.254
91.306
Page 10 of 50
POWER FINANCE CORPORATION LTD.
Detail Project Report - Part B
Cost Data of 33 kV Lines
New 33 kV, 3-Ph Overhead Line on 12.8 mtr. Rail Pole by ACSR Dog Conductor
Erection
1 Survey of HT Overhead Line Ckt-Km 1 1,058.00 1,224.77
2 Erection of Single Pole (Rail Pole) No. 13 2,216.00 33,348.86
3 Erection of Double Pole (Rail Pole) No. 2 5,271.00 12,203.68
4 Fixing of Pin Insulator No. 45 31.00 1,614.89
5 Fixing of Disc Insulator No. 36 48.00 2,000.38
6 Earthing complete Set 17 119.00 2,341.88
7 HT Stay Set complete Set 9 251.00 2,615.07
Craddle Guard (upto 30 mtr per span on S.P) per
8 LS 1 725.00 839.28
km
Page 11 of 50
12 Strenging and Sagging LS 1 6,934.00 8,026.97
D Total Erection cost 64,887.20
E Total Cost (Supply + Erection) 939,119.56
Page 12 of 50
Renovation of 33 kV, 3-Ph Overhead Line on 12.8 mtr. Rail Pole by ACSR Dog Conductor
Erection
1 Dismantling of pole with all acessories LS 1 3,098.00 3,586.32
2 Erection of Single Pole (Rail Pole) No. 4 2,216.00 10,261.19
3 Fixing of Pin Insulator No. 12 31.00 430.64
4 Fixing of Disc Insulator No. 9 48.00 500.09
5 Earthing complete No. 4 119.00 551.03
6 HT Stay Set complete Set 4 251.00 1,162.26
Craddle Guard (upto 30 mtr per span on S.P) per
7 LS 1 725.00 839.28
km
Page 13 of 50
POWER FINANCE CORPORATION LTD.
Detail Project Report - Part B
Cost Data of 11 kV Lines
New 11 kV, 3-Ph Overhead Line on 12.8 mtr. Rail Pole by ACSR Dog Conductor
Erection
1 Survey of HT Overhead Line Ckt-Km 1 1,058.00 1,224.77
2 Erection of Single Pole (Rail Pole) No. 13 2,216.00 33,348.86
3 Erection of Double Pole (Rail Pole) No. 2 5,271.00 12,203.68
4 Fixing of Pin Insulator No. 45 25.00 1,302.33
5 Fixing of Disc Insulator No. 12 27.00 375.07
6 Earthing complete Set 17 119.00 2,341.88
7 HT Stay Set complete Set 9 251.00 2,615.07
Craddle Guard (upto 30 mtr per span on S.P) per
8 LS 1 725.00 839.28
km
Page 14 of 50
12 Stringing and Sagging LS 1 6,934.00 8,026.97
D Total Erection cost 62,949.33
E Total Cost (Supply + Erection) 892,743.07
Page 15 of 50
Renovation of 11 kV, 3-Ph Overhead Line on 12.8 mtr. Rail Pole by ACSR Dog Conductor
Erection
1 Dismantling of pole with all acessories LS 1 3,098.00 3,586.32
2 Erection of Single Pole (Rail Pole) No. 5 2,216.00 12,826.49
3 Fixing of Pin Insulator No. 15 25.00 434.11
4 Fixing of Disc Insulator No. 6 27.00 187.54
5 Earthing complete Set 5 119.00 688.79
6 HT Stay Set complete Set 5 251.00 1,452.82
7 Craddle Guard(upto 60 mtr on S.P) LS 1 725.00 839.28
Page 16 of 50
New 11 kV, 3-Ph Overhead Line on 12.8 mtr. Rail Pole by ACSR Rabbit Conductor
Erection
1 Survey of HT Overhead Line Ckt-Km 1 1,058.00 1,224.77
2 Erection of Single Pole (PCC Pole) No. 13 2,216.00 33,348.86
3 Erection of Double Pole (PCC Pole) No. 2 5,271.00 12,203.68
4 Fixing of Pin Insulator No. 45 25.00 1,302.33
5 Fixing of Disc Insulator No. 12 27.00 375.07
6 Earthing complete Set 17 119.00 2,341.88
7 HT Stay Set complete Set 9 251.00 2,615.07
Craddle Guard (upto 30 mtr per span on S.P) per
8 LS 1 689.00 797.60
km
Page 17 of 50
Renovation of 11 kV, 3-Ph Overhead Line on 12.8 mtr. Rail Pole by ACSR Rabbit Conductor
Erection
1 Dismantling of pole with all acessories LS 1 3,098.00 3,586.32
2 Erection of Single Pole (Rail Pole) with all fittings No. 5 2,216.00 12,826.49
Page 18 of 50
New 11 kV, 3-Ph Overhead Line on 9.0 mtr. PCC Pole by ACSR Rabbit Conductor
Erection
1 Survey of HT Overhead Line Ckt-Km 1 1,058.00 1,224.77
2 Erection of Single Pole (PCC Pole) No. 13 1,317.00 19,819.70
3 Erection of Double Pole (PCC Pole) No. 2 3,342.00 7,737.57
4 Fixing of Pin Insulator No. 45 25.00 1,302.33
5 Fixing of Disc Insulator No. 12 27.00 375.07
6 Earthing complete Set 17 119.00 2,341.88
7 HT Stay Set complete Set 9 251.00 2,615.07
Craddle Guard (upto 30 mtr per span on S.P) per
8 LS 1 689.00 797.60
km
Page 19 of 50
New 11 kV, 3-Ph Overhead Line on 9.0 mtr. PCC Pole by 3c x 120 sq.mm. ABC
Erection
1 Survey of HT Line Ckt-Km 1 1,058.00 1,224.77
2 Erection of Single Pole (PCC Pole) No. 30 1,317.00 45,737.76
Erection of 11 kV Aerial Bunched Conductor
including Hoisting, stringing, sagging, tensioning
3 Km 1.05 62,292.23 75,716.59
& route clearance with fixing of Clamps, Jointing
Kits complete
4 Fixing of LA No. 3 52.00 180.59
5 Earthing complete Set 30 119.00 4,132.72
6 HT Stay Set complete Set 15 251.00 4,358.46
7 Fixing of Caution Board No. 4 11.00 50.94
8 Numbering of Pole No. 30 9.00 312.56
D Total Erection cost 131,714.38
E Total Cost (Supply + Erection) 1,177,071.12
Page 20 of 50
Renovation of 11 kV, 3-Ph Overhead Line on 9.0 mtr. PCC Pole by 3c x 120 sq.mm. ABC
Erection
1 Dismantling of Pole with all accessories LS 1 3,098.00 3,586.32
Erection of 9 mtr. long PCC pole with associated
2 No. 16 1,317.00 24,393.47
foundation (with all fittings)
Page 21 of 50
New 11 kV, 3-Ph Overhead Line on 9.0 mtr. PCC Pole by 3c x 95 sq.mm. ABC
Erection
1 Survey of HT Line Ckt-Km 1 1,058.00 1,224.77
Erection of 9 mtr. long PCC pole with associated
2 No. 30 1,317.00 45,737.76
foundation (with all fittings)
Page 22 of 50
Renovation of 11 kV, 3-Ph Overhead Line on 9.0 mtr. PCC Pole by 3c x 95 sq.mm. ABC
Erection
1 Dismantling of Pole with all accessories LS 1 3,098.00 3,586.32
Erection of 9 mtr. long PCC pole with associated
2 No. 16 1,317.00 24,393.47
foundation (with all fittings)
Page 23 of 50
New 11 kV, 3-Ph Overhead Line on 9.0 mtr. PCC Pole by 3c x 70 sq.mm. ABC
Erection
1 Survey of HT Line Ckt-Km 1 1,058.00 1,224.77
Erection of 9 mtr. long PCC pole with associated
2 No. 30 1,317.00 45,737.76
foundation (with all fittings)
Page 24 of 50
New 11 kV U.G. Cable Railway Crossing Terminating on 9.0 mtr PCC DP (Single Run)
Erection
1 Erection of Double Pole (PCC Pole) No. 2 3,342.00 7,737.57
2 Fixing of Disc Insulator No. 6 27.00 187.54
3 Fixing of Lightning Arrestor No. 6 52.00 361.18
4 Earthing complete Set 6 119.00 826.54
5 HT Stay Set complete Set 8 251.00 2,324.51
6 Stringing and Sagging LS 1 175.15 202.76
Page 25 of 50
New 11 kV U.G. Cable Railway Crossing Terminating on 9.0 mtr PCC Four Pole (Double Run)
Erection
1 Erection of Four Pole (PCC Pole) No. 2 7,651.00 17,713.98
2 Fixing of Disc Insulator No. 18 27.00 562.61
3 Fixing of Pin Insulator No. 6 25.00 173.64
4 Fixing of Lightning Arrestor No. 6 52.00 361.18
5 Earthing complete Set 10 119.00 1,377.57
6 HT Stay Set complete Set 12 251.00 3,486.77
7 Stringing and Sagging LS 1 175.15 202.76
Page 26 of 50
Renovation of 11 kV U.G. Cable (Single Run) Railway Crossing Terminating on 12.8 mtr Rail Four Pole by 11 kV
U.G. Cable (Double Run)
Erection
1 Erection of Four Pole (Rail Pole) No. 2 7,651.00 17,713.98
2 Fixing of Disc Insulator No. 18 27.00 562.61
3 Fixing of Pin Insulator No. 6 25.00 173.64
4 Fixing of Lightning Arrestor Set 2 52.00 120.39
5 Earthing complete Set 10 119.00 1,377.57
6 HT Stay Set complete Set 12 251.00 3,486.77
7 Stringing and Sagging LS 1 175.15 202.76
8 Dismantling of PILC Cable LS 1 5,498.02 6,364.64
Page 27 of 50
POWER FINANCE CORPORATION LTD.
Detail Project Report - Part B
Cost Data of Distribution Transformers
New 100 kVA, 11/0.433 kV Distribution Transformer on 12.8 mtr. Rail Pole
Erection
Erection of Substation structure with all fittings
1 LS 1 6,040.00 6,992.06
on 12.8 mtr. Rail Pole (DP)
2 Fixing of Pin Insulator No. 6 25.00 173.64
3 Fixing of Disc Insulator No. 3 27.00 93.77
4 Earthing complete Set 6 119.00 826.54
5 HT Stay Set complete Set 4 251.00 1,162.26
6 Erection of 100 kVA Distribution Transformer No. 1 1,274.00 1,474.81
7 Fixing of Lightning Arrestor No. 3 52.00 180.59
8 Fixing of TPGO Isolator No. 1 540.00 625.12
9 Fixing of LTDB & Capacitor Panel No. 1 8,695.86 10,066.54
Erection & termination of 1.1 kV grade 1c x 70
10 Mtr. 40 11.23 520.01
sq.mm XLPE cable as I/C
Erection & termination of 1.1 kV grade 1c x 50
11 Mtr. 120 8.75 1,215.51
sq.mm XLPE cable as O/G
12 Fixing of Anti-climbing Device No. 2 60.00 138.92
13 Fixing of Caution Board No. 1 11.00 12.73
D Total Erection cost 23,482.49
E Total Cost (Supply + Erection) 359,842.81
Renovation of 100 kVA, 11/0.433 kV Distribution Transformer on 12.8 mtr. Rail Pole
Erection
1 Pole, Steel Structure & other accessories LS 1 5,000.00
2 Earthing complete Set 6 119.00 826.54
3 HT Stay Set complete Set 4 251.00 1,162.26
4 Fixing of Lightning Arrestor No. 3 52.00 180.59
5 Fixing of TPGO Isolator No. 1 540.00 625.12
6 Fixing of LTDB & Capacitor Panel Set 1 8,695.86 10,066.54
Erection & termination of 1.1 kV grade 1c x 70 sq
7 Mtr. 40 11.23 520.01
mm. XLPE cable as I/C
Erection & termination of 1.1 kV grade 1c x 50 sq
8 Mtr. 120 8.75 1,215.51
mm. XLPE cable as O/G
9 Fixing of Anti-climbing Device No. 2 60.00 138.92
10 Fixing of Caution Board No. 1 11.00 12.73
D Total Erection cost 19,748.21
E Total Cost (Supply + Erection) 150,873.85
New 63 kVA, 11/0.433 kV Distribution Transformer on 12.8 mtr. Rail Pole
Erection
Erection of Substation structure with all fittings
1 LS 1 6,040.00 6,992.06
12.8 mtr. Rail Pole (DP)
2 Fixing of Pin Insulator No. 6 25.00 173.64
3 Fixing of Disc Insulator No. 3 27.00 93.77
4 Earthing complete Set 6 119.00 826.54
5 HT Stay Set complete Set 4 251.00 1,162.26
6 Erection of 63 kVA Distribution Transformer No. 1 1,228.00 1,421.56
7 Fixing of Lightning Arrestor No. 3 52.00 180.59
8 Fixing of TPGO Isolator No. 1 540.00 625.12
9 Fixing of LTDB & Capacitor Panel No. 1 7,494.76 8,676.12
Erection & termination of 1.1 kV grade 1c x 50
10 Mtr. 40 8.74 404.71
sq.mm XLPE cable as I/C
Erection & termination of 1.1 kV grade 1c x 25
11 Mtr. 120 5.16 716.80
sq.mm XLPE cable as O/G
12 Fixing of Anti-climbing Device No. 2 60.00 138.92
13 Fixing of Caution Board No. 1 11.00 12.73
D Total Erection cost 21,424.81
E Total Cost (Supply + Erection) 299,955.08
Renovation of 63 kVA, 11/0.433 kV Distribution Transformer on 12.8 mtr. Rail Pole
Erection
1 Pole, Steel Structure & other accessories LS 1 5,000.00
2 Earthing complete Set 6 119.00 826.54
3 Staying complete Set 4 251.00 1,162.26
4 Fixing of Lightning Arrestor No. 1 52.00 60.20
5 Fixing of TPGO Isolator No. 1 540.00 625.12
6 Fixing of LTDB & Capacitor Bank Set 1 7,494.76 8,676.12
Erection & termination of 1.1 kV grade 1c x 50 sq
7 Mtr. 40 8.74 404.71
mm. XLPE cable as I/C
Erection & termination of 1.1 kV grade 1c x 25 sq
8 Mtr. 120 5.16 716.80
mm. XLPE cable as O/G
9 Fixing of Anti-climbing Device No. 2 60.00 138.92
10 Fixing of Caution Board No. 1 11.00 12.73
D Total Erection cost 17,623.39
E Total Cost (Supply + Erection) 135,624.81
New 25 kVA, 11/0.433 kV Distribution Transformer on 12.8 mtr. Rail Pole
Erection
Erection of Substation structure with all fittings
1 LS 1 6,040.00 6,992.06
12.8 mtr. Rail Pole (DP)
2 Fixing of Pin Insulator No. 6 25.00 173.64
3 Fixing of Disc Insulator No. 3 27.00 93.77
5 Earthing complete Set 6 119.00 826.54
4 HT Stay Set complete Set 4 251.00 1,162.26
7 Erection of 25 kVA Distribution Transformer No. 1 894.00 1,034.92
8 Fixing of Lightning Arrestor Set 1 52.00 60.20
9 Fixing of TPGO Isolator No. 1 540.00 625.12
11 Fixing of LTDB & Capacitor Panel No. 1 7,494.76 8,676.12
Erection & termination of 1.1 kV grade 1c x 50
12 Mtr. 40 8.74 404.71
sq.mm XLPE cable as I/C
Erection & termination of 1.1 kV grade 1c x 25
13 Mtr. 60 5.16 358.40
sq.mm XLPE cable as O/G
6 Fixing of Anti-climbing Device No. 2 60.00 138.92
10 Fixing of Caution Board No. 1 11.00 12.73
D Total Erection cost 20,559.37
E Total Cost (Supply + Erection) 235,692.99
Renovation of 25 kVA, 11/0.433 kV Distribution Transformer on 12.8 mtr. Rail Pole
Erection
1 Pole, Steel Structure & other accessories LS 1 2,000.00
2 Earthing complete Set 6 119.00 826.54
3 Staying complete Set 4 251.00 1,162.26
4 Fixing of Lightning Arrestor No. 1 52.00 60.20
5 Fixing of TPGO Isolator No. 1 540.00 625.12
6 Fixing of LTDB & Capacitor Bank Set 1 6,242.73 7,226.74
Erection & termination of 1.1 kV grade 1c x 50 sq
7 Mtr. 40 8.74 404.71
mm. XLPE cable as incomer
Erection & termination of 1.1 kV grade 1c x 25 sq
8 Mtr. 60 5.16 358.40
mm. XLPE cable as incomer
9 Fixing of Anti-climbing Device No. 2 60.00 138.92
10 Fixing of Caution Board No. 1 11.00 12.73
D Total Erection cost 12,815.61
E Total Cost (Supply + Erection) 98,982.97
Renovation of 315 kVA, 11/0.433 kV Distribution Transformer on 12.8 mtr. Rail Pole
Erection
1 Pole, Steel Structure & other accessories LS 1 8,000.00
2 Earthing complete Set 6 119.00 826.54
3 Staying complete Set 4 251.00 1,162.26
4 Fixing of Lightning Arrestor No. 1 52.00 60.20
5 Fixing of TPGO Isolator No. 1 540.00 625.12
6 Fixing of LTDB & Capacitor Panel LS 1 20,237.27 23,427.17
Erection & termination of 1.1 kV grade XLPE
7 Mtr. 40 35.91 1,662.78
Cable 2 x (1c x 150 sq.mm) as incomer
Erection & termination of 1.1 kV grade XLPE
8 Mtr. 240 23.42 6,508.06
Cable 1 x (1c x 185 sq.mm) as Outgoing
9 Fixing of Expulsion type Fuse (1 set = 3 nos) Set 1 402.90 466.41
Erection
1 Pole, Steel Structure & other accessories LS 1 5,000.00
2 Earthing complete Set 6 119.00 826.54
1 Staying complete Set 4 251.00 1,162.26
4 Fixing of Lightning Arrestor No. 1 52.00 60.20
5 Fixing of TPGO Isolator No. 1 540.00 625.12
7 Fixing of LTDB & Capacitor Panel LS 1 14,168.20 16,401.46
Erection & termination of 1.1 kV grade XLPE
8 Mtr. 40 23.07 1,068.08
Cable 2 x (1c x 95 sq.mm) as I/C
Erection & termination of 1.1 kV grade XLPE
9 Mtr. 180 14.35 2,990.53
Cable 1 x (1c x 120 sq.mm) as O/G
7 Fixing of Expulsion type Fuse (1 set = 3 nos) Set 1 402.90 466.41
Erection
1 Survey of LT Line Ckt-Km 1 669.00 774.45
2 Erection of 8 mtr. long PCC pole (with fittings) No. 24 856.00 23,782.25
3 Fixing of 'D' iron clamp non RE rate No. 144 3.00 500.09
4 Fixing of C.I Reel No. 30 18.00 625.12
5 Fixing of shackle insulator No. 124 22.00 3,158.00
Fixing of shackle strap with nuts & bolts (non RE
6 No. 16 5.00 92.61
rate)
7 Staying complete Set 20 221.00 5,116.70
8 Earthing Complete Set 30 119.00 4,132.72
Fixing of safety Device with proper binding at
9 No. 50 13.00 752.46
both ends complete
Erection of 25 sq.mm AAC Conductor including
10 Hoisting, stringing, jointing, sagging, tensioning LS 1 963.00 1,148.24
& route clearance
Erection
1 Dismantling of pole with all accessories LS 1 3,000.00
3 Erection of 8 mtr. long PCC pole (with fittings) No. 5 856.00 4,954.64
4 Fixing of 'D' iron clamp non RE rate No. 36 3.00 125.02
5 Fixing of C.I Reel No. 30 18.00 625.12
6 Fixing of shackle insulator No. 32 22.00 814.97
Fixing of shackle strap with nuts & bolts (non RE
7 Pair 4 5.00 23.15
rate)
8 Staying complete Set 5 221.00 1,279.18
9 Earthing Complete No. 15 119.00 2,066.36
Fixing of safety Device with proper binding at
10 No. 50 13.00 752.46
both ends complete
Erection of 25 sq.mm AAC Conductor including
11 Hoisting, stringing, jointing, sagging, tensioning Km. 1 963.00 1,148.24
& route clearance
Erection
1 Survey of LT Line Ckt-Km 1 669.00 774.45
2 Erection of 8 mtr. long PCC pole (with fittings) No. 30 856.00 29,727.81
Erection
1 Dismantling of Pole with all acessories LS 1 3,000.00
2 Erection of 8 mtr. long PCC pole (with fittings) No. 15 856.00 14,863.91
Erection
1 Dismantling of pole with all accessories LS 1 3,000.00
2 Survey of LT Line Ckt-Km 1 669.00 774.45
3 Erection of 8 mtr. long PCC pole (with all fittings) No. 5 856.00 4,954.64
4 Fixing of 'D' iron clamp non RE rate No. 144 3.00 500.09
5 Fixing of C.I Reel No. 30 18.00 625.12
6 Fixing of shackle insulator No. 124 22.00 3,158.00
Fixing of shackle strap with nuts & bolts (non RE
7 No. 16 5.00 92.61
rate)
8 Staying complete Set 20 221.00 5,116.70
9 Earthing Complete Set 30 119.00 4,132.72
Fixing of safety Device with proper binding at
10 No. 50 13.00 752.46
both ends complete
Erection of 25 sq.mm AAC Conductor including
11 Hoisting, stringing, jointing, sagging, tensioning LS 1 963.00 1,148.24
& route clearance
Erection
1 Dismantling of Pole with all acessories LS 1 3,000.00
2 Survey of LT Line Ckt-Km 1 669.00 774.45
3 Erection of 8 mtr. long PCC pole (with fittings) No. 15 856.00 14,863.91
Erection
1 Fixing of 3-Ph Energy Meter No. 1 941.80 988.89
2 Fixing of Pilfer Proof box No. 1 120.09 126.09
D Total Erection cost 1,114.98
E Total Cost (Supply + Erection) 12,822.31
Erection
1 Fixing of 1-Ph Energy Meter with Pilfer Proof box No. 1 115.20 120.96
D Total Erection cost 120.96
E Total Cost (Supply + Erection) 1,391.04
Page 48 of 50
POWER FINANCE CORPORATION LTD.
Detail Project Report - Part B
Cost Data Summary of All Jobs
Page 49 of 50
Supply Erection Total
Sl. No. Description of Job Cost Cost Cost
(Rs. Lakhs) (Rs. Lakhs) (Rs. Lakhs)
Page 50 of 50