Professional Documents
Culture Documents
1.1 General
1.1.1 Purpose / aim of the Method Statement submission:
Laying of Asphalt Cold-Mix recycling over remaining portion of old granular base as
shown in working drawings.
As per Tech. Specifications A – 6, MOST Cl. 519, BOQ item No. 4.06 and as per working
drawings.
1.3 Surveys
Asphalt cold recycling mix will be laid after completion of necessary survey checks on
remaining portion of old granular base surface by supervision staff.
1.4 Utilities
All identified utilities will be relocated before starting of the Asphalt cold recycling mix
processing.
Traffic will be diverted on another carriageway by providing traffic signals and safety
measures. More over necessary extra man power and display boards will be placed to
regulate the flow of traffic without causing any congestion or stagnation.
1.6 Access
Land access will be provided with the temporary diversion where necessary.
a) Prepare the sketch showing the overall layout of the length and width of road
intended for recycling during the day, broken into the number of parallel cuts
required to achieve the stated width, and the over lap dimensions at each joint
between cuts.
b) The sequence and length of each cut to be recycled before starting on the
adjacent or following cut.
c) Estimate the time required for milling, mixing and compacting each cut.
d) The location where samples were taken for determing in-situ moisture contents
and the results of the tests.
e) Proposed water addition for each cut, and the location at which any change is to
be made with in that sequence.
(i) Aggregate materials: The gradation of the aggregate separate from the
Asphalt and found by sieve analysis by ASTM C 136 and found the all physical
analysis like shape, AIV, stripping and water absorption.
(ii) Asphalt Content: The Asphalt is extracted and found the existing asphalt
content in the pavement by ASTM D 2172.
(i) Gradation of Recycled Mixture: Fix the gradation as per MOST – Table
– 500.4 (Gr.I) with combination of the reclaimed aggregates and new
aggregates (if any).
Pc = (0.035 a + 0.045 b + K c + F) / R
Where,
Where,
(i) Weather and seasonal limitations: Construction with cold mix must not
be under taken when temperature below 100C, during rain, in standing
water or generally when poor weather is predicted.
(ii) Preparation of Base: The base on which cold mix is to be laid shall be
prepared, shaped and leveled to the required profile as mentioned in Sl.
No. 1.7, and a prime coat, where specified shall be applied in accordance
with clause 502. A tack coat in accordance with clause 503 shall be
applied over the base on which the cold mix is to be laid, where specified
in the contract.
Mixing the Bitumen Emulsion uniformly with the sized asphalt pavement,
old granular base and new aggregate if used. When new aggregate is
added to In-place materials, a spreader box or windrow size should be
used to ensure the required quantity is evenly placed.
Cold mix prepare with proper proportioning of the asphalt and uniformly
by using blade mixing / rotary mixing / travel plant mixing. The entire
operation will be in a single pass.
Milling drum which rotates up wards into the direction of advance and
achieves at least 2.0 m of cut width in a single pass.
Mix the milled material with stabilizing agent, the recycling machine
shall have the following features.
The thickness of layer should not exceed 150 mm, when multiple lifts are
required, curing time must be allowed between 2 to 5 days under good
curing conditions.
Note: Emulsified asphalt mixes gain stability as the fluids (mainly water)
evaporate. It is important not to retard this process. Therefore, lift
thickness must be limited by the rate at which the mixture loses its fluids.
(vi) Open to Traffic: Traffic shall not be allowed to run on new work until the
water or volatile in the mixture have evaporated.