You are on page 1of 7

This Lecture….

Today we will give detailed consideration to the application


of the NPV valuation tools discussed last week and, in
doing so, discuss:
FINM2001 Corporate Finance / { How to estimate cash flows for the purpose of project evaluation;
{ Multiple approaches that can be employed in comparing
FINM8003 Applied Corporate Finance mutually exclusive projects with different lives;
{ How NPV analysis can be used in situations more complex than
simply deciding when to accept / reject a project, namely
Valuation Methods II deciding when to retire / replace existing projects;
{ The importance of undertaking sensitivity and break-even
analysis as part of the NPV evaluation; and,
{ The use of decision-tree analysis in NPV evaluation.

Estimation of Cash Flows Difference in Lives Adjustments I


As a reminder, when estimating cash flows, it is important As discussed briefly in FINM1001, companies will
to remember the following points: frequently have to compare mutually exclusive projects that
{ Focus on incremental cash flows and include taxes if have different economic lives. This is necessary because
relevant. Specifically, use after-corporate-tax cash flows in a
classical tax system and the after-effective-tax cash flows in such projects will often involve equipment of different
an imputation system. quality and therefore also of a different cost. However, the
{ Exclude sunk costs as they are already incurred and are better quality machines should last longer. Consider the
therefore irrelevant. following example for a furniture manufacturer:
{ Exclude financing charges: The required rate of return used { Machine A has a life of 3 years and Machine B has a life of 5
to discount cash flows incorporates the cost of equity and years;
debt, so including financing charges in the cash flows would { Both Machines can perform the required tasks satisfactorily;
be double counting; { Both Machines generate the same cash flows; and,
{ Include residual values; { The present value of post-tax cash outflows for Machine A is
{ Ensure consistency in the treatment of inflation; and, $18,000 and for Machine B is $21,000.
{ Recognise the timing of the cash flows.

Difference in Lives Adjustments II Difference in Lives Adjustments III


The fact that the present value of cash outlays for Given the preceding, the question arises as to how
Machine A are less than for Machine B, it doesn’t we actually compare Machines A and B
necessarily mean that the former should be appropriately. Two approaches could be
preferred. This is because: employed:
{If purchased, Machine A will need to be replaced two {Assume that the company will reinvest in a project
years earlier than B; and, identical to currently under consideration, or make
{Therefore, the alternatives are not directly comparable the constant chain of replacement assumption; or,
as the differences in lives means they involve different {Make assumptions about the reinvestment
future cash flows which have not been considered.
opportunities that will be available in the future.

1
Difference in Lives Adjustments IV Difference in Lives Adjustments V

Whilst the second approach is the most Under this assumption, each project is
realistic: assumed to be replaced with an identical
OIn practice, this approach would be impossible project at the end of its economic life. As
to implement given we are unable to see into valid comparison can only be made when
the future and therefore don’t know about the chains are of equal length, this can be
opportunities that will become available; and, achieved by employing:
OTherefore, the constant chain of replacement {The equivalent annual value (EAV) method;
approach is often used. {The constant chain of replacement in perpetuity
method; or,
{The lowest common multiple method.

Difference in Lives Adjustments VI Difference in Lives Adjustments VII


Recall from FINM1001 and last week that the EAV A variant of this approach, which will rank projects
method involves calculating the annual cash flow of identically, is the constant chain of replacement in
an annuity that has the same life as the project and perpetuity method. This method assumes that
whose present value equals the net present value of both chains continue indefinitely. Under this
the project, or: approach
{ The lengths of the chains are equal insofar as they are both
infinite;
NPV
EAV = { If the NPV of each replacement project is $N and the life of each
⎡1 − (1 + k )− n ⎤ project is n years, the constant chain of replacement is
⎢ ⎥ equivalent to receiving an inflow of $N at 0, n, 2n, etc; and,
⎣ k ⎦ { Therefore, the NPV of the chain comprises $N at 0 plus a
perpetuity of $N payable every n years, or….

Difference in Lives Adjustments VIII Difference in Lives Adjustments IX


To compare the two methods, consider the following example: Chocolate
N N
NPV = N + + + ... Heaven Ltd, producers of fine quality chocolates, need to replace a chocolate
(1 + k ) n (1 + k ) 2 n mixing machine. Two competing machines, A and B are available. Both
⎡ 1 1 ⎤ machines are considered adequate in terms of their ability to complete the
= N ⎢1 + + + ...⎥ required tasks. Forecasted cash flows for each machine are provided below.
⎣ (1 + k ) (1 + k )
n 2n
⎦ Given Chocolate Heaven operates in a classical tax system, where the tax
⎡ ⎤ rate is 40%, and has an after-tax required rate of return of 10% p.a., which
⎢ 1 ⎥ machine would you recommend Chocolate Heaven should purchase? In
=N⎢ ⎥ providing an answer, show which option is preferable using both the EAV
⎢1 − 1 ⎥ and NPV to infinity methods of adjusting for differences in lives.
⎣⎢ (1 + k ) ⎦⎥
n
A B
⎡ (1 + k ) n ⎤ Estimated life 3 years 6 years
=N⎢ ⎥
⎣ (1 + k ) − 1 ⎦
n Cost 13000 22000
Net Cash Inflows (pre tax) 10000 14000
More.generally :
Salvage Value 1000 4000
⎡ (1 + k ) n ⎤ Depreciation (p.a.) 4000 3000
NPV ∞ = NPV0 ⎢ ⎥
⎣ (1 + k ) − 1 ⎦
n

2
Difference in Lives Adjustments X Difference in Lives Adjustments XI
First, calculate cash flows for each project.
For project A: Using this information, we can calculate the
{ Year 0:
z Cost of new machine: $13,000. NPV for each project:
{ Years 1-3 inclusive:
z Yearly post-tax cash revenues less expenses equalling$10,000 x (1-0.40)=$6,000; ⎡1 − (1.10)−3 ⎤ $1, 000
z Yearly depreciation tax shield of $4,000x0.40=$1,600; NPVA = ($6, 000 + $1, 600) ⎢ ⎥+ 3
− $13, 000
z Salvage value of $1,000 received at the end of year 3; and, ⎣ 0.10 ⎦ (1.10)
z Gain / loss on sale of $0.
For project B:
= $6, 652
{ Year 0:
z Cost of new machine: $22,000.
{ Years 1-6 inclusive: ⎡1 − (1.10) −6 ⎤ $4, 000
z Yearly post-tax cash revenues less expenses equalling$14,000 x (1-0.40)=$8,400; NPVB = ($8, 400 + $1, 200) ⎢ ⎥+ 6
− $22, 000
z Yearly depreciation tax shield of $3,000x0.40=$1,200; ⎣ 0.10 ⎦ (1.10)
z
z
Salvage value of $4,000 received at the end of year 3; and,
Gain / loss on sale of $0.
= $22, 064

Difference in Lives Adjustments XII Difference in Lives Adjustments XIII


We can also use the NPV figures above to calculate the
Using this information, we can then calculate NPV to infinity for each project:
the EAV for each project: ⎡ (1.10)3 ⎤
NPV∞A = $6, 652 ⎢ ⎥
⎣ (1.10) − 1 ⎦
3
$6, 652
EAVA = = $26, 748.68
⎡1 − (1.10) −3 ⎤
⎢ 0.10 ⎥
⎣ ⎦
⎡ (1.10)6 ⎤
= $2, 674.87 NPV∞ B = $22, 064 ⎢ ⎥
⎣ (1.10) − 1 ⎦
6

= $50, 660.57
$22, 064
EAVB =
⎡1 − (1.10) −6 ⎤
⎢ 0.10 ⎥ Based on the preceding results, we can see that,
⎣ ⎦
= $5, 066.06
irrespective of the method employed to adjust for different
lives, Machine B is preferable to Machine A.

Difference in Lives Adjustments XIV Retirement and Replacement Decisions I


The final way of comparing projects with different lives is using the Projects are not always continued to the end of their
lowest common multiple (LCM) method. To illustrate how this estimated lives, a fact that is a result of management
approach works, imagine a situation where Project A has a life of 5
years and Project B has a life of 10 years. Here: undertaking periodic reviews of existing projects and often
{ If A is undertaken four times and B is undertaken two times, the making subsequent decisions to either retire (abandon) or
replacement changes will both be 20 years. Therefore, in this replace existing projects and their assets:
example, 18 is the lowest common multiple; { Retirement decisions is the term used to describe those
{ Based on the above, we would calculate the NPV of four As situations where assets are used for some time prior to being
undertaken successively and two Bs undertaken successively and sold without being replaced; and,
compare them (ie choose the one with the highest NPV); but,
{ Replacement decisions are those situations where, whilst the
{ While this approach will rank projects identically to the two methods
discussed previously, it can be laborious – imagine if Project A had a
operation is to continue indefinitely, the company is faced with a
life of 99 years and Project B had a live of 100 years – the LCM would decision about when to replace the operation’s existing assets:
be 9,900 years!!!!
Let’s now consider each of these decisions in detail.

3
Retirement and Replacement Decisions II Retirement and Replacement Decisions III
As the retirement of assets is another investment decision, Consider an example where a company owns a machine that is
the NPV approach is valid. Specifically: 4 years old and has an estimated remaining life not exceeding 2
years. Further, the post-tax net cash flows and residual value
{ The choice of an optional abandonment / retirement period can
estimates for the machine are as follows. If the company has
be treated as a situation of mutually exclusive alternatives as the
decision to retire the asset now precludes retiring it in another asked you to indicate when the machine should be replaced
year; given a post-tax required rate of return of 10% p.a…..
{ Although these mutually exclusive projects have different lives,
Year Post-Tax Residual Value ($)
NPV without an adjustment for difference in lives should be used
as the assumption of constant replacement is violated; and, Net Cash Flow ($)

{ Using the NPV rule, a project should be retired if the NPV of all 4 - 18,000
its future cash flows are less than zero. 5 12,000 9,000
6 7,500 0

Retirement and Replacement Decisions IV Retirement and Replacement Decisions V

We must start by calculating the net present value Given the resultant NPV is positive, the machine should be retained
for at least another year. However, the question then becomes
of forgoing the $18,000 residual value now to whether the machine should be retained for a period longer than 1
receive a post-tax net cash flow of $12,000 and a year (ie for 2 years). If this occurs, the company will forgo the
machine’s current residual value of $18,000 in exchange for the
residual value of $9,000 one year from now. This receipt of years 5 and 6 post-tax net cash flows (namely $12,000 and
calculation is as follows: $7,500) and a $0 residual value, or a net present value of -$892.56.
Given this, unless there is an upward revision of cash flow estimates
for Year 6, the machine should be retired at the end of Year 5:
($12, 000 + $9, 000)
NPV = −$18, 000 + $12, 000 $7,500
1.10 NPV = −$18, 000 + +
1.10 (1.10) 2
= $1, 090.91
= −$892.56

Retirement and Replacement Decisions VI Retirement and Replacement Decisions VII

When considering when to replace assets, we are If identical replacement is being considered,
effectively comparing projects with different lives. it is implicitly assumed that the current
Given this, we obviously need to make an project will be replaced by another project
adjustment for this difference, and we can do this that is identical in every respect. More
using the constant chain of replacement method specifically, it is assumed that the capital
discussed previously. In discussing how to make outlay, net cash flows, physical life and
replacement decisions in practice, we will consider residual value of the replacement project are
two possibilities, namely those involving identical the same as those of the current project.
replacement and those involving non-identical With this assumption in mind, consider the
replacement. following example ….

4
Retirement and Replacement Decisions VIII Retirement and Replacement Decisions IX
A machine costing $48,000 with an estimated useful life of 3 years In considering the optimal replacement time, remember that the
generates post-tax net cash flows of $24,000 in the first year. Post-tax decision rule is to select the replacement frequency that maximizes the
net cash flows in each subsequent year decrease by $2,000 per projects net present value in perpetuity or its equivalent annual value.
annum so that Years 2 and 3 post-tax net cash flows are $22,000 and With this in mind, the NPV of the machine if it were sold in each of
$20,000 respectively. Given a post-tax required rate of return of 10% years 1 to 3 are as follows:
p.a. and the post-tax residual values below, you have been asked to
indicate when the machine should be replaced. $24, 000 $32, 000
NPVYr1Re place = −$48, 000 + +
1.10 1.10
= $2,909.09
Year Residual Value $24, 000 $22, 000 $16, 000
($) NPVYr 2Re place = −$48, 000 + + +
1.10 (1.10) 2 (1.10) 2
1 32,000 = $5, 223.14
2 16,000 $24, 000 $22, 000 $20, 000
NPVYr 3Re place = −$48, 000 + + +
3 0 1.10 (1.10) 2 (1.10)3
= $7, 026.30

Retirement and Replacement Decisions X Retirement and Replacement Decisions XI


Next, as the previous present values are based on different lives, they
cannot be compared without adjustment. However, this can be
However, as mentioned previously, it is possible
overcome if a constant chain of replacement is assumed. Specifically, that existing machines will be replaced by non-
once the following adjustments have been made, the projects are identical alternatives. Such a scenario is possible
comparable and it is clear the machine should be replaced every year.
in situations where technological advances have
⎡ (1.10) ⎤
NPV1,∞ = $2,909.09 ⎢ ⎥ seen current machinery become obsolete, etc. If
⎣ (1.10) − 1 ⎦
= $32, 000
this occurs, the question may amount to when the
⎡ (1.10) 2 ⎤ old machinery should be replaced by the new. To
NPV2,∞ = $5, 223.14 ⎢ ⎥
⎣ (1.10) − 1⎦
2
answer such a question, consider the “ABC
= $30, 095.24
Company” example included on WebCT with the
⎡ (1.10)3 ⎤
NPV3,∞ = $7, 026.30 ⎢ ⎥ lecture notes for this week….
⎣ (1.10) − 1⎦
3

= $28, 253.78

Retirement and Replacement Decisions XII Analysing Project Risk I


As discussed in previous lectures, the impact of risk on a
project is generally accounted for by using a required rate
Alternatively, a replacement decision may of return reflective of this risk to discount cash flows.
involve choosing between two replacement However, a calculated NPV figure is only an estimate that
relies on forecasted project cash flows. In practice:
alternatives, an example of which is given by { These forecasts will invariably turn out to be different to the
actual cash flows; and,
the “XYZ Company” case included with this { Therefore, projects will need to be analysed to consider what key
variables are likely to determine the success of the project and
week’s lecture notes…. how far can variables cash flows fall before the project loses
money. In practice, this analysis is performed using the below
approaches and, as with valuation, is undertaken using
spreadsheets (we will consider how to do this in Lecture 9):
z Sensitivity analysis;
z Break-even analysis; and / or,
z Simulation.

5
Analysing Project Risk II Analysing Project Risk III
Sensitivity analysis involves assessing the effect of A simple sensitivity analysis could be undertaken by:
{ Making pessimistic, expected and optimistic estimates of each
changes in the estimated variables on a project’s variable;
NPV. This is achieved by recalculating NPV { Calculating NPV using the pessimistic or optimistic value of one
variable and the expected value of others and re-performing this
figures using alternative estimates of variables. until a NPV has been calculated using an optimistic and
Such analysis is useful as it: pessimistic estimate for each specific variable in combination
with the expected values of all other variables; and,
{Provides management with knowledge of the sensitivity
{ Comparing the difference between the optimistic and pessimistic
of NPV to changes or errors in variables, allowing them NPVs for each variable. Small differences suggest NPV is
to decide whether the project is too risky to accept; and, largely insensitive to changes in that variable, and vice versa.
{Highlights variables that management should estimate
more thoroughly or collect more data in respect of to
reduce forecasting errors.

Analysing Project Risk IV Decision-Tree Analysis

Break-even analysis is a type of Next, in some cases, management needs to


sensitivity analysis. However, whilst evaluate alternatives which occur as a result of a
sensitivity analysis allows questions sequence of decisions over time. In this situation,
decision-tree analysis can be employed, as:
such as “what is the project’s NPV if
{It takes into account the probability of a given event
sales fall to $1 million per annum” to be taking place and the effect this event would have on
answered, break-even analysis allows a project’s NPV; and,
consideration of how far sales would {Uses the roll-back procedure, which means the
have to fall before the project loses most distant decision is evaluated first.
money.

Qualitative Factors and Project Selection Resource Constraints and Project Selection

Thus far, we have only considered the quantitative analysis In undertaking any of the preceding
associated with project selection. However, whilst the aim
is to maximise shareholder wealth, selection of projects analysis, it is important to remember that
may not necessarily be based solely on this analysis. This management is often unable to accept all
is because, in reality, management may also consider positive NPV independent projects or, in the
qualitative factors when selecting projects. An example
would be the need for greater managerial supervision being case of mutually exclusive projects, that
associated with a given project, the cost of which is difficult project with the highest NPV. This is
to quantify. Management may consider the existence of because management may have a shortage
these qualitative factors to be sufficiently important to
cause them to accept proposals with lower NPVS. of funds with which to undertake projects
and may therefore be forced to undertake
capital rationing.

6
Next Lecture….
After making decisions regarding which project/s to undertake,
management must decide how to finance them.
{ We will discuss the different financing options open to
companies in Lectures 5 and 6;
{ In deciding the sources of funding, managers must also consider
the appropriate mix of sources of finance, or make capital
structure decisions, an issue we will consider in Lecture 7;
{ The financing mix chosen will impact on the cost of capital used
in project evaluation (ie the discount rate). We will consider this
impact in detail in Lecture 8 and, in doing so, learn how to
calculate the cost of capital for use in project evaluation;
{ We will bring the materials from Lectures 2 to 8 together in
Lecture 9, when we will undertake a detailed project valuation,
including cost of capital calculation and sensitivity analysis, in
Excel.

You might also like