Convevance of material by lorry

1 Rubble and brokenstone 36 Km 499.00

2 River sand 27 Km 400.00

3 Cement and steel 5 Km 234.00

4 Bitumen 50 Km 459.00

5 Brick 27 Km 518.00

6 Laterite 14 Km 257.00

7 Timber (Scantling) 46 Km 495.00

8 Earth for filling 14 Km 257.00

9 Lime 5Km 126.00


Part I
RATES FOR LABOUR
Sl No Name of Item Unit Rate
1 Blacksmith Each Per Day 325.00
2 Blaster or Quarryman ,, 270.00
Boy (=0.75 Man) ,, 180.00
8 Carpenter ,, 325.00
11 Cleaner Lift Irrigation ,, 270.00
15 Driver pump driver/Operator ,, 270.00
18 Fitter ,, 300.00
19 Hammerman for helping Blaster ,, 225.00
24 Mason - Brick or Laterite ,, 325.00
25 Mason - Rubble ,, 325.00
26 Mason - Stone Mason or Stone cutter ,, 325.00
27 Mazdoor - Man ,, 240.00
28 Mazdoor - Special mazdoor for Surveying ,, 255.00
29 Mazdoor - Heavy load mazdoor ,, 270.00
30 Mazdoor - Woman mazdoor ,, 240.00
38 Painter ,, 270.00
40 Plumber / Pipe fitter ,, 325.00
41 Sawyer ,, 300.00
42 Scavenger ,, 325.00
51,51a Welder - gas/arch welding ,, 325.00
HIRE CHARGES
68 Bulls (pair) with driver for grinding mortar per day 400.00
Road roller ,, 2060.00
Boiler ,, 35.65
Mini H M plant ,, 830.00
Wheel barrow ,, 5.75
Polishing machine ,, 60.00
Part II
RATES FOR MATERIALS
Bricks and tiles
1 Wire cut bricks Ist class 19cmX9cmX9cm 1000 Nos 4050.00
2 Do traditional bricks 22.9cmX11.2cmX7cm ,, 4500.00
4 Country burnt bricks Ist class 19cmX9cmX9cm ,, 2100.00
5 Do traditional bricks 22.9cmX11.2cmX7cm ,, 2400.00
8 Hollow Bricks 40cmX20cmX20cm 100 Nos 1200.00
9 M P Roofing tiles 340mm nominal size Ist class 1000 Nos 6100.00
10 do 320mm do ,, 5400.00
11 M P Hip and Ridge tiles ,, 13800.00
Stones including Road materials
20 Laterite stone 44X24X14cm roughly dressed 100 Nos 1100.00
24 Blasted Rubble at quarry (20 to 40 dm3 size) m3 270.00
Hard Broken Stone (Granite)
29 20mm nominal size as per I S S m3 600.00
31 40mm do ,, 420.00
Broken Stone (for road work)
28 15mm ,, 650.00
35 6mm m3 475.00
37 12mm ,, 675.00
43 36mm ,, 460.00
46 60mm ,, 370.00
52 River sand ,, 1750.00
52(a) Manufactured sand ,, 1750.00
53 Sea sand ,, 210.00
55 Shell lime quick ,, 2200.00
59 Red earth for blinding ,, 105.00
61 Quarry dust ,, 85.00
62 Cement (Portland) packed or bags of 50kg Tonne 4700.00
63 White cement kg 14.00
Timber and Roofing materials
2 Anjili or Ayani m3 20800.00
8 Mavu or Mango ,, 6300.00
13~14 Teak wood ,, 65800.00
28 Vengai ,, 20720.00
30 Bamboo Ist class 9m long Each 95.00
31 Coconut trees 6m to 9m long ,, 525.00
33 Arecanut trees 9m long ,, 225.00
34 Arecanut trees 1/3 split m 17.00
35 Plaited coconut cadjan madals 100 Nos 660.00
37 Ettamats m2 35.00
39 Bamboo reepers m 4.50
40 Arecanut reepers ,, 4.50
Metal and Iron
1 M S Rounds and Squares Qtl 4670.00
2 M S Angles,Channels,Flats,Joists ,, 3291.00
3 Twisted bars (Tor steel) ,, 4750.00
4 M S Plate ,, 4447.50
5..17 Iron Bolts,Nuts kg 58.00
18 G I Hooks crank bolts and nuts metal fittings ,, 58.00
27 Butt Hinges 75 mm 10 Nos 38.00
28 do 100 mm ,, 76.00
34 Barrel tower bolt-Iron 100mm ,, 61.00
35 do 150 mm ,, 85.00
47 Iron Screws 25mm (8) ,, 3.80
92 100mm Aluminium Door Handle ,, 260.00
97 200mm Aluminium Aldrop 16 mm dia ,, 950.00
98 Spike nails kg 47.00
99 Wire nails ,, 42.00
101 Iron wire for tying grill (22 gauge) ,, 59.00
113 100mm Iron Hooks and Eyes 10 Nos 23.00
117 65mm Pad lock (7 lever) best quality Each 170.00
119 G I Fencing wire No 6 standard Qtl 3700.00
120 G I Barbed Wire ,, 3700.00
121 G I Staples ,, 4000.00
140 G I Corrugated sheets 0.63mm thick Tonne 46000.00
144 Copal Varnish Litre 105.00
145 Aluminium Paint ,, 150.00
146 Black Japan Paint ,, 57.00
148 Ready mixed paint colour best quality ,, 126.00
149 Plastic Emulsion paint ,, 180.00
150 Synthetic Enamel Paint ,, 162.00
151 Cement water proof paint kg 24.00
155 Iron primer Litre 85.00
157 Wood primer ,, 85.00
158 Epoxy coal tar Paint kg 150.00
162 Mansion Polish ,, 200.00
164 Cardinal polish red 400gm 90.00
166 Red oxide powder - Ist quality kg 81.00
167 Black oxide powder - Ist quality ,, 54.00
168 Water proofing compound ,, 28.00
Miscellaneous Items
2 Asbestos Cement Sheet Corrugated or trafford m2 125.00
3 Asbestos Cement Ridge Pair 125.00
5 Bitumen Washer 10 Nos 2.00
18 Charcoal Qtl 450.00
20 Glass Sheet Plain 3mm thick m2 205.00
25 Fiber glass corrugated or trafford ,, 945.00
29 Well Pulley Cast Iron No:8 Each 40.00
32a Empty cement bag ,, 1.50
34 Country blasting Powder kg 35.00
35 Country Fine Fuse m 11.00
40 Asphalt (Bitumen) Tonne 27583.00
41 Asphalt (Bitumen) with container ,, 30248.00
43 Diesel Oil Litre 33.50
44 Kerosene ,, 20.00
49 Fire wood split Tonne 2700.00
52 Carborandom stone course, medium, or fine Each 120.00
53 Oxalic acid powder kg 80.00
54 Marble white powder Ist quality 50 kg 90.00
59 Rolling shutter m2 1250.00
60 Top cover of shutter m 400.00
61 Collapsible gate m2 1250.00
62 Welding electrode 100 Nos 370.00
65 M S Rivets kg 60.00
Floor paving stones (20mm thick)
9 Pink marble (Adanga) m2 563.00
25 Ceramic floor tiles (I S O / 1st quality) ,, 322.00
30 Marble chips of various colours Qtl 200.00
41(a) mosaic tiles (ISI 237/1959) gray colour 10m2 1170.00
Part III
RATES FOR WATER SUPPLY AND SANITARY ITEMS
102 15 mm G M wheel walve Each 188.00
144 I W C with P or S trap 450mm ,, 383.00
145 I W C with P or S trap 500mm ,, 409.00
146 I W C with P or S trap 580mm ,, 484.00
147 Orissa pan W C 530X400mm (white) ,, 600.00
155 E W C with P or S trap 580mm (white) ,, 634.00
159 W H B without fittings 550X400mm ,, 480.00
167 Trap P or S ,, 98.00
168 15mm or nearest size C P pillar tap for W H B ,, 242.00
169 32mm C P waste with chain and plug ,, 6.00
171 Lipped urinal (430mmX230mmX50mm) ,, 368.00
172 Urinal flat - Large 510X400X380mm ,, 797.00
181 32mm dia lead trap ,, 165.00
184 450X450mm C I Manhole cover 15 kg ,, 495.00
188 G M ball valve with polythene float for 20mm ,, 203.00
193 Duro plastic seat and cover for E W C (black) ,, 232.00
228 white glazed tiles 200mmX200mm size 10 Nos 120.00
245 C I brackets for wash hand basine Pair 55.00
WATER SUPPLY FITTINGS P V C ITEMS
10 20mm PVC pipe (10kg/cm2) m 11.00
19 25mm PVC pipe (8kg/cm2) m 12.50
20 32mm PVC pipe (8kg/cm2) m 20.00
27 40mm PVC pipe (6kg/cm2) m 25.00
28 50mm PVC pipe (6kg/cm2) m 38.00
29 63mm PVC pipe (6kg/cm2) m 56.00
30 75mm PVC pipe (6kg/cm2) m 79.00
32 110mm PVC pipe (4kg/cm2) m 130.00
231 Automatic flush tank 5 Lr. Capacity Each 682.00
235 32mm P V C flush pipe ,, 62.00
236 15mm P V C connection (heavy) ,, 44.00
237 P V C low level flush tank ,, 791.00
238 P V C high level flush tank ,, 778.00
241 porcelain foot rest Pair 96.00
245 P V C storage water tank Litre 3.50
47040
DATA OF WORKS
IN PARAVOOR TALUK BASED ON 2009 Schedule Of Rates

Sl. Amount
Quantity Description of works Unit Rate
No.
Without CP With CP

CLEARING SITE

1 Clearing grass and over growth of vegitations


0.5 no man each 240.00 120.00 132.00
Say Rs. 120.00 /100m2 Rs. 132.00

2 Clearing light jungles including uprooting of thick


vegitations and small trees etc
1 no man each 240.00 240.00 264.00
Say Rs. 240.00 /100m2 Rs. 264.00

3 Clearing thick and throny jungles and small trees of


girth upto 30cm and rooting out including removal of
rubbish etc.compete
2 no man each 240.00 480.00 528.00
Say Rs. 480.00 /100m2 Rs. 528.00

4
Felling trees including cutting of trunks and
branches, removing the roots completely and
stacking serviceable materialds
groth 60 to120cms
0.3 No wood cuter each 300.00 90.00 99.00
0.5 No man each 240.00 120.00 132.00
sudries LS 3.75 3.75
213.75 234.75
Say Rs. 214.00 /Each Rs. 235.00
DISMANTLING

6 Dismantling clearing and carefully stacking reusable


materials for any thickness walls of brick, laterite,
or rubble in mud morter
0.7 no man each 240.00 168.00 184.80
Say Rs. 168.00 /m3 Rs. 185.00

7
Dismantling clearing and carefully stacking reusable
materials for any thickness of dry rubble masnory
0.7 no man each 240.00 168.00 184.80
Say Rs. 168.00 /m3 Rs. 185.00

8 Dismantling clearing and carefully stacking reusable


materials for any thickness walls of brick, laterite,
or rubble in lime morter
1.15 no man each 240.00 276.00 303.60
Say Rs. 276.00 /m3 Rs. 304.00

Page 8
9 Dismantling clearing and carefully stacking reusable
materials for any thickness walls of brick, laterite,
or rubble in cement morter
1.6 no man each 240.00 384.00 422.40
Say Rs. 384.00 /m3 Rs. 422

12 Chipping and removing portions of existing RCC


works and removing the debries with in a distance
of 150m.
0.05 no mason each 325.00 16.25
0.05 no man each 240.00 12.00
28.25 31.075
Say Rs. 28 /m3 Rs. 31

13
Lifting and removing tiles set in mortar in floors
including clearing and stacking materials and
removing the debries within a distance of 150m
0.25 no mason each 325.00 81.25
0.25 no man each 240.00 60.00
141.25 155.38
Say Rs. 141 /m3 Rs. 155

14 Dismantling removing and stacking MP tiles over


roof including ridge,hip and vally sheet
0.5 no man each 240.00 120.00 132.00
Say Rs. 120 /10m2 132.00

15
Dismantling removing and stacking pan or pot
tiles over roof
1.0 no man each 240.00 240.00 264.00
Say Rs. 240.00 /m3 Rs. 264.00

16 Dismantling removing and stacking wrought and


framed timbers in roof
0.014 no carpenter each 325.00 4.55
0.014 no man each 240.00 3.36
7.91 8.70
Say Rs. 7.91 /10dm3 Rs. 8.70

17
Dismantling removing and stacking doors with or
without ventilators including remoel of shutters,
hinges,hold fast and other fittings
0.2 no mason each 325.00 65.00
0.18 no carpenter each 325.00 58.50
0.3 no man each 240.00 72.00
195.50 215.05
Say Rs. 196.00 /m3 Rs. 215

18 Dismantling removing and stacking windows with


or without ventilators including remoel of shutters,
hinges,hold fast and other fittings

Page 9
0.15 no mason each 325.00 48.75
0.1 no carpenter each 325.00 32.50
0.2 no man each 240.00 48.00
129.25 142.175
Say Rs. 129 /Each Rs. 142

19 Dismantling removing and stacking ventilators


with or without ventilators including remoel of
shutters, hinges,hold fast and other fittings
0.1 no mason each 325.00 32.50
0.05 no carpenter each 325.00 16.25
0.1 no man each 240.00 24.00
72.75 80.03
Say Rs. 73 /Each Rs. 80

20 Dismantling, removing and stacking planked


sheeting,boarded floor, ceiling etc.
0.35 no carpenter each 325.00 113.75
0.35 no man each 240.00 84.00
197.75 217.525
Say Rs. 198.00 /m3 Rs. 218.00

21
Taking down and stacking shutters of doors with
or without ventilaorsincluding removel of all fittings
0.1 no carpenter each 325.00 32.50
0.1 no man each 240.00 24.00
56.50 62.15
Say Rs. 57.00 /m2 Rs. 62

22 Taking down and stacking shutters of windows


with or without ventilaorsincluding removel of all
fittings
0.1 no carpenter each 325.00 32.50
0.05 no man each 240.00 12.00
44.50 48.95
Say Rs. 45.00 /m2 Rs. 49.00

23 Taking down and stacking shutters of ventilators


with or without ventilaorsincluding removel of all
fittings
0.05 no carpenter each 325.00 16.25
0.02 no man each 240.00 4.80
21.05 23.16
Say Rs. 21 /m2 Rs. 23

28 Demolishing and clearing concete in cement


mortar or RCC including stacking reinforcement
3.0 no man each 240.00 720.00 792.00
Say Rs. 720.00 /m3 Rs. 792.00

30 Domolishing and removing old lime mortar plaster


0.3 no man each 240.00 72.00 79.20
Say Rs. 72 /10m2 79

Page 10
31 Domolishing and removing old cement mortar
plaster
0.5 no man each 240.00 120.00 132.00
Say Rs. 120 /10m2 132.00

EARTH WORK

51
Earth work excavation in ordinary soil and
depositing on the bank with initial leads and lift for
foundation
1.10 no. man each 240.00 264.00
3.00 no. boy each 180.00 540.00
Total 10m3 804.00 884.4
Say Rs. 804.00 /10m3 Rs. 884

52
Earth work excavation in hard soil and depositing
on the bank with initial leads and lift for foundation
4.00 no. man each 240.00 960.00
3.00 no. boy each 180.00 540.00
Total 10m3 1500.00 1650
Say Rs. 1,500 /10m3 Rs. 1,650

53
Earth work excavation in ordinary rock and
depositing on the bank with initial leads and lift for
foundation
10.00 no. man each 240.00 2400.00
2.30 no. boy each 180.00 414.00
Total 10m3 2814.00 3095.4
Say Rs. 2,814 /10m3 Rs. 3,095

54 Granite rock blasting , measured in solid,


including bailing out water collecting aqnd stacking
spoil for measurment within an initial lead of 50m
and lift of 1.5m
3.2 kg countey blasting powder kg 35.00 112.00
9 m country fuse m 11.00 99.00
10.6 no quarry man for boring each 270.00 2862.00
1.2 no quarry man for charging holes and firi each 270.00 324.00
1.2 no hammer man for braking bolders each 225.00 270.00
4.5 no man for conveying rubbles each 240.00 1080.00
2.62 no man for stacking each 240.00 628.80
5375.80 5913.38
Say Rs. 5,376 /10m3 Rs. 5,913
54a Boring holes in granite rock to place the
reinforcement at 45cm c/c, 45cm deep and 19 to
22mm dia
data for 10 nos (Observed Data)
2.12 no quarry man for boring holes each 270.00 572.40 629.64

Say Rs. 572 /10nos Rs. 630

Page 11
56
Earth work excavation in ordinary soil and
depositing with leads upto 50m and lift upto1.5m for
cutting and filling
0.90 no. man each 240.00 216.00
2.75 no. boy each 180.00 495.00
Total 10m3 711.00 782.10
Say Rs. 711 /10m3 Rs. 782

57 Earth work excavation in hard soil and depositing


with leads upto 50m and lift upto1.5m for cutting
and filling (contractor's own earth)
3.60 no. man each 240.00 864.00
2.5 no. boy each 180.00 450.00
Total 10m3 1314.00 1445.4
Say Rs. 1,314 /10m3 Rs. 1,445

60 Earth work excavation in or under water or liquid


mud for removing the stiff deposited in the channel
and dumping the same at the place directed by the
Deptl. Officers at site
0.9 no man for excavation in ordinary soil each 240.00 216.00
2.75 boy 180.00 495.00
711.00
Add 20%on the above 142.20
Total 10m3 853.20 938.52
Say Rs. 853 /10m3 Rs. 939

61 Earth consolidation by Power Roller


0.65 liter Diesel lit 36.00 23.40 25.74
0.04 day hire of roller day 2080.00 83.20 83.20
LS Sundries LS 2.25 2.25
108.85 111.19
Say 109.00 /10m3 112.00

65 Granite rock blasting in wells, measured in solid,


including bailing out water collecting aqnd stacking
spoil for measurment within an initial lead of 50m
and lift of 1.5m
for initial depth up. to 1.5m 5375.80 5913.38
Say 5376 /10m3 Rs. 5,913

65a Additional depth for each 1.5m


1 no man for lifting, conveying, stacking, et each 240.00 240.00
0.031 no quarry man each 270.00 8.44
1.5 m extra for fuse m 11.00 16.50
264.94 291.43
Say 265.00 /10m3 291.43
67 Consolidation by ramming in 15cm.layers
including watering
0.7 nos man each 240.00 168.00 184.8
Say 168.00 /10m3 185.00

Page 12
67a
Earth filling with ordinary soil including
consolidation by ramming in 150mm layers
including watering
10 m3 excavation of ordinary soil (vide item
no.56) 10m3 711.00 711.00
10 m3 conveyance m3 257.00 2570.00
Total 10m3 3281.00 3609.10
Say Rs. 3,281 /10m3 3610.00

67b Deduct extra one lead and lift over item No.67a 3281.00
2.1 no women each 240.00 504.00
2777.00 3054.70
Say Rs. 2,777 /10m3 3055.00

67c Earth filling with ordinary soil including


consolidation by Power Rolle in 150mm layers
including watering
10 m3 excavation of ordinary soil (vide item
no.56) 10m3 711.00 711.00
10 m3 consolidation by Power Roller (vide
item no.61) 10m3 108.85 108.85
10 m3 conveyance m3 257.00 2570.00
Total 10m3 3389.85 3728.84
Say Rs. 2,624 /10m3

67d Deduct extra one lead and lift over item No.67c 3389.85
2.1 no women each 240.00 504.00
2885.85 3174.44
Say Rs. 2,886 /10m3 3174

67e
Earth filling with hard soil including consolidation
by ramming in 150mm layers including watering
10 m3 excavation of ordinary soil (vide item
no.57) 10m3 1314.00 1314.00
10 m3 conveyance m3 257.00 2570.00
Total 10m3 3884.00 4272.4
Say Rs. 3,884 /10m3 4272

67f Deduct extra one lead and lift over item No.67c 3884.00
2.1 no women each 240.00 504.00
3380.00 3718.00
Say Rs. 3,380 /10m3 3718

67g
Bailing out water with 5 HP engine and pump set
1.000 Hire of 5 Hp engine and pump set day 70.00 70.00 70.00
10.000 diesel lit 36.00 360.00 396
LS lubricrating oil 5.00 5.00
1.000 driver 270.00 270.00 297
1.000 cleaner 225.00 225.00 247.5
LS installation charge 6.25 6.25

Page 13
Total 936.25 1021.75
Hence per hour =701.25/8 117.03 127.72
Say Rs. 117 /10m3 128

67h Sand filling in trenches including watering and


consolidation
1 m3 sea sand m3 450.00 450.00
0.7 no. man for consolidatioin each 240.00 168.00
1 m3 conveyance m3 257.00 257.00
Total m3 875.00 962.50
Say Rs. 875 /m3 Rs. 963

Earth work excavation in hard soil extra addition lift


1.5m or part thereof over initial lift

0.4 no woman each 240.00 96.00 105.60

Say Rs. 67 /10m3 Rs 74.00

A 67i
Putting up ring bunds of top width 2.5m and
bottom width 3.5m and height 2.5m using 1/2 split
coconut post and driving down 60cm c/c and 1.0m
below the ground level and 1/3 split coconut cross
ties 2.0m apart and wailing piceses 5 rows on either
side and screening double coconut cadgan madals
plated and 1/6 split aracanut reepers 50cm c/c
laying etc complete and including dismantling after
use
Sub data

a) supplying 1/2 split coconut post used


for 2 times
Material
cost of 6m to 9m coconut post round m 525.00 525.00
conveyance Ls 50.00
575.00
hence for 1m 575/2/7.5 38.33 /m
Labour for 1/2 split
1 no Sawyer each 300.00 300.00
1 no man each 240.00 240.00
540.00
hence labour for 1m 540/2/7.5 36.00 /m

Hence rate for 1.0m, used for 2 times (36+25.20)/2 37.17 /m

b) supplying 1/3 split coconut post for 2


times
cost of 1/3 split coconut post for 1m 540/3/7.5 25.56
Labour for 1/3 split
1.5 no Sawyer each 210.00 315.00
1.5 no man each 168.00 252.00
567.00
hence labour for 1m 567/3/7.5 25.20 /m

Page 14
Hence rate for 1.0m, used for 2 times (25.56+25.20/2 25.38 /m

c) Clay soil
10 m3 cutting charge (vide Sl. No.56) 10m3 711.00 711.00
0.2 20% extra for liquid 142.20
853.20

d)
Driving down the coconut post(vide Sl. No.712) ,
Details for 8 m and used for two times
3 no heavy load mazdoor each 270.00 810.00 891
3 no pile driver each 300.00 900.00 990
0.12 no carpenter each 325.00 39.00 42.9
plat form LS 62.5 62.50
rope , chain LS 62.5 62.50
wooden scffolding LS 25.00 25.00
1899.00 2073.90
Hence for 1.0m used for 2 times 1899/8/2 118.69 129.62

Main Data

1/2 split of cocunut post at 60cm c/c for 10m length


171 m 1/2split coconut post for
(45no.x3.5+0.3m=171m) vide sub
data (a) used 2 times m 37.17 6355.50 6991.05
1/3 split of cocunut horizontal at
50cm c/c for 10m length
1/3split for (2x5x10=100m)
tie 5x3=15m
115 m vide sub data (b) used 2 times m 25.38 2918.44 3210.29
7.26 kg 6mm MS bar strap (6x5.5x.22kg/m=7. kg 29.00 210.54 231.59
100 m Araconut reepers (2x5x10=100m) m 4.00 400.00 440.00
45 m Driving down 1/2 split coconut post
vide sub data (d) m 118.69 5340.94 5875.03
75 m3 Earth clay vide sub data (c) 10m3 853.20 6399.00 7038.90
5 kg coir yarn kg 42.00 210.00 231.00
10 no special man mazdoor for laying and fix each 180.00 1800.00 1980.00
5 no man mozdoor for dismantling each 168.00 840.00 924.00

screening with double new coconut


cadjas area 1/6 split bamboo reepers
27 no cadjas 100no 580.00 156.60 172.26
31.5 m bamboo reeper m 4.00 126.00 138.60
1 no green cadjas each 5.00 5.00 5.50
0.3 no special man mazdoor each 180.00 54.00 59.40
50 m2 screening 10m2 266.75 1333.75 1467.13
Dismantling thebnund after use
5 no spical man mazdoor each 180.00 900.00 990.00
5 no man mozdoor each 168.00 840.00 924.00
5 no women each 168.00 840.00 924.00
45 m Drawing out piles half rate of driving m 59.34 2670.47 2937.52
Total for 10m 31400.24 34540.26
Hence for 1.0m 3140.02 3454.03
Say Rs. 3,141 /m Rs. 3,455

Page 15
Putting up ring bunds of top width 1m and
bottom width 1.5m and height 1.0m using 1/3 split
coconut post and driving down 60cm c/c and 1.0m
below the ground level and 1/3 split coconut cross
ties 2.0m apart and wailing piceses at 50cm c to c
B
and tide with coir yarn cross ties to all vertical posts
with 1/3 split coconut wood , screening double
coconut cadgan leaves, filling the inside with stiff
clay &consolidated includingmaintaining the bund fill
the work is over and dismantling thesame of for use.
a

cost of 6m to 9m coconut post round m 525.00 525.00


for cuttingcharges Ls 100.00
conveyance Ls 100.00
725.00 /7.5m
Hence for 1/3 split Rs.690/7.5x3 32.22 /m
Hire charges for 1/3split coconut post using two times 16.11 m

b
Driving down the coconut post(vide Sl. No.712) ,
Details for 8 m and used for two times
3 no heavy load mazdoor each 270.00 810.00
3 no pile driver each 300.00 900.00
0.12 no carpenter each 325.00 39.00
1749.00
Hence for 1.0m length 1/3 split
1215.36/8/3 72.88 /m

c screening with double new coconut


cadjas and tying with coiryarn to
horizontal and vertical posts
43 no cadjas 100no 580.00 249.40
conveyance LS 50.00
conveyance for coir &other sundries LS 10.00
0.5 no spical man mazdoor each 255.00 127.50
436.90 /10m2

Pumping kayal clay inside the fund &


d consolidation etc.complete

1 m3 clay m3 90.00 90.00


1 m3 conveyance m3 65.00 65.00
0.35 no man for consolidation each 240.00 84.00
239.00 /m3

Driving out piles of any description


allowing half rate driving Rs.72.88/2
e m 36.44 /m

Dismantling and clearing awaythe


clay & other materials (10m3
f excavation chargesvide S.I.151

1.1 no man each 240.00 264.00


2.25 no man each 240.00 540.00

Page 16
Add 20% for under water 160.80
964.80 /m3

Main data for 5m length of bund.

a Hire charges for 1/3split coconut post


2x9x2m 36 m
Horizontal 30 m
crossties2x9x1.50 27 m
93 m
Total (Rs.15.33/m) 1498.33

b
Driving down 1/3 split the coconut post(vide Sl.
No.712) , Details for 8 m and used for two times
2x9x1.00 18 m

Total (Rs.72.88/m) 1311.75

c
screening with double new coconut
cadjas and tying with coiryarn to
horizontal and vertical posts

side of bund 2x5x1.00 10 m2


Total (Rs.436.9/10m2) 436.90

d G.I.Wire for tying LS 2kg @44/kg 88.00

e Rate for coiryarn for tying LS 5kg@Rs.40/kg 200.00

f 0.50 man.mazdoor for cutting


anjoining the horizontal@Rs.240/E 120.00

g Dumping the kayal clay inside the


bund
1x5x1x(1.50+1.00)x1.00=12.50m3 @
Rs.239/m3 2987.50

h
Driving down 1/3 split the coconut post(vide Sl.
No.712) , Details for 9 m and used for two times 327.94
@Rs.36.44/m

i Dismantling and clearing awaythe


clay & other materials (10m3
excavation chargesvide S.I.151
@964.8/10m3 1206
Total for 5No. Length 8176.42
For 1m length 1635.28 1798.81

Page 17
Say Rs. 1,635 /m Say 1799.00

Putting up ring bund 1/2(1.50+1.00) 1.00m size


using earth filled cement bags, packing tightly and
removing after completion of work.

Details for 10.00m. No. of cement


bags - 2x17x7=238 Nos.

Quantity of earth filling -


10.00x1/2(1.50+1.00)1.00=12.50m3
238.00 No Empty cement bags 3.00 /each 714.00
12.50 m3 E W in Ordinary Soil 711.00 /10m3 888.75
10.00 No man for filling 240.00 /each 2400.00
3.00 No man for packing 240.00 /each 720.00
4.00 No woman for assisting 240.00 /each 960.00
4.00 No man demolishing 240.00 /each 960.00
Total 6642.75 7307.025
Say Rs. 6,643 /10m Say 7308.00

Packing with mutty stone in slushly portion of


the road

1 m3 cost of mutty stone m3 110.00 110.00


1 m3 conveyance m3 386.75 386.75
spreading gravel SI 656
0.35 no man each 168 58.80
Total 555.55
Say Rs 556 /m3

CONCRETE

110
Cement concrete 1:3:6 using 40mm broken stone
including cost& conveyance of all materials labour
charges etc. complete
0.95 m3 40mm broken stones m3 490.00 465.50
0.48 m3 sand m3 1750.00 840.00
228 kg cement t 4700.00 1071.60
0.1 no mason each 325.00 32.50
1 no man each 240.00 240.00
1.4 no women c 240.00 336.00
0.95 m3 conveyance for 40mm broken stones m3 499.00 474.05
0.48 m3 do sand m 3
400.00 192.00
228 kg do cement t 234.00 53.35
Total m 3
3705.00
Say Rs. 3,705 /m3

111
Cement concrete 1:4:8 using 40mm broken stone
including cost& conveyance of all materials labour
charges etc. complete
0.95 m3 40mm broken stones m3 490.00 465.50

Page 18
0.48 m3 sand m3 1750.00 840.00
171 kg cement t 4700.00 803.70
0.1 no mason each 325.00 32.50
1 no man each 240.00 240.00
1.4 no women each 240.00 336.00
0.95 m3 conveyance for 40mm broken stones m3 499.00 474.05
0.48 m3 do sand m3 400.00 192.00
171 kg do cement t 234.00 40.01
Total m3 3423.76
Say Rs. 3,424 /m3

122
Cement concrete 1:2:4 using 20mm broken stone
including cost& conveyance of all materials labour
charges etc. complete
0.009 m3 20mm broken stones m3 700.00 6.30
0.0045 m3 sand m3 1750.00 7.88
3.3 kg cement t 4700.00 15.51
0.002 no mason each 325.00 0.65
0.01 no man each 240.00 2.40
0.035 no women each 240.00 8.40
0.009 m3 conveyance for 20mm broken stones m3 499.00 4.49
0.0045 m3 do sand m3 400.00 1.80
3.3 kg do cement t 234.00 0.77
Total 10dm3 48.20
Say Rs. 48 /10dm3

122
a Cement concrete 1:(1.5):3 using 20mm broken
stone including cost& conveyance of all materials
labour charges etc. complete
0.009 m3 20mm broken stones m3 700.00 6.30
0.0045 m3 sand m3 1750.00 7.88
4.32 kg cement t 4700.00 20.30
0.002 no mason each 325.00 0.65
0.01 no man each 240.00 2.40
0.035 no women each 240.00 8.40
0.009 m3 conveyance for 20mm broken stones m3 499.00 4.49
0.0045 m3 do sand m3 400.00 1.80
4.32 kg do cement t 234.00 1.01
Total 10dm3 53.23
Say Rs. 53 /10dm3

123
Cement concrete 1:3:6 using 20mm broken stone
0.009 m3 20mm broken stones m3 700.00 6.30
0.0045 m3 sand m3 1750.00 7.88
2.16 kg cement t 4700.00 10.15
0.002 no mason each 325.00 0.65
0.01 no man each 240.00 2.40
0.035 no women each 240.00 8.40
0.009 m3 conveyance for 20mm broken stones m3 499.00 4.49
0.0045 m3 do sand m3 400.00 1.80
2.16 kg do cement t 234.00 0.51

Page 19
Total 10dm3 42.57
Say Rs. 42.50 /10dm3

123 Cement concrete 1:3:6 using graded matel (60%of


a 40mm and 40% of 20mm)for foundation including
cost and conveyance of all materials , curring etc
complete
0.57 m3 40mm broken stone m3 490.00 279.30
0.36 m3 20mm broken stone m3 700.00 252.00
0.468 m3 sand m3 1750.00 819.00
223.2 kg Cement t 4700.00 1049.04
0.14 no mason each 325.00 45.50
1.0 no man each 240.00 240.00
2.24 no women each 240.00 537.60
0.93 m3 conveyance of broken stone m3 499.00 464.07
0.468 m3 do for sand m3 400.00 187.20
223.0 kg do for cement t 234.00 52.18
3925.89 4318.48
Say Rs. 3,926 /m3 Rs. 4,318

drain

1 m3 C.C 1:3:6 graded m3 3925.89 3925.89


5.71 m2 formwork 25% of slab 10m2 901.32 514.65
4440.55 4884.60
Say Rs. 4,441 /m3 Rs. 4,885

123
Cement concrete 1:3:6 using graded matel in the
b
ratio of 50% 40mm and 50%,20mm including the
cost and conveyance of all materials labour charges
curing etc, complete
0.475 m3 40mm broken stone m3 490.00 232.75
0.45 m3 20mm broken stone m3 700.00 315.00
0.465 m3 sand m3 1750.00 813.75
222.0 kg Cement t 4700.00 1043.40
0.14 no mason each 325.00 45.50
1.0 no man each 240.00 240.00
2.45 no women each 240.00 588.00
0.925 m3 conveyance of broken stone m3 499.00 461.58
0.465 m3 do for sand m3 400.00 186.00
222.0 kg do for cement t 234.00 51.95
3977.92 4375.72
Say Rs. 3,978 /m3 Rs. 4,376

130 Reinforcement for RCC works bent, tied and


placed in positiion using tore steel
1 q Tore steel q 4472.00 4472.00
0.45 kg iron wire kg 59.00 26.55
1 no. blacksmith each 325.00 325.00
1.48 no. man each 240.00 355.20
1 q conveyance for MS rods q 234.000 234.00
Total qtl 5412.75 5954.03

Page 20
Say 5413 /Qtl Rs. 5,954

FORM WORK

132 Form work for RCC works in slabs 10m2


Sub data for scanteling 10dm3
14.4 dm3 mango wood log dm3 7200.00 103.68
0.02 no. man each 240.00 4.80
0.33 sawing (4.3 sawer/10m2) m2 300.00 42.57
3.8 deduct cost of outer slab(25%of log) dm3 1800.00 6.84
Total 144.21

320/4 dm3 mango wood scanteling 10dm3 144.21 1153.68


190/8 dm3 junglewood joist & cleats 10dm3 144.21 342.50
9./6 bamboos each 105.00 157.50
1 spike and wire nails kg 48.50 48.50
2.5 man each 240.00 600.00
4 carpenter each 325.00 1300.00
LS coir LS 3.10
Total 10m2 3605.28 3965.81
Say 3605 /10m2 3966

132
a Form work for RCC works in ,beam
1.1 add 10% over the rate of slab 10m2 3605.28 3965.81 4362.39
Say 3966 /10m2 4362

132 Form work for RCC works in


c columns
1.2 add 20% over the rate of slab 10m2 3605.28 4326.33 4758.97
Say 4326 /10m2 4759

RCC WORKS

133
Reinforced cement concrete 1:2:4 using 20mm b.s
for slabs including form work, watering curring
etc.complete.butexcluding reinforcement.
10 cement concrete 1:2:4 using 20mm
dm3 metal (vide item no.122) 10dm3 48.20 48.20
0.1 m2 form work 10m2 3605.28 36.05
Total 10dm3 84.25 92.68
Say Rs. 84.50 /10dm3 Rs. 92.50

133
a Reinforcemed Cement concrete 1:(1.5):3 using
20mm broken stone for slab including form work,
watering , curing etc, complete,but excluding the
cost of reinforcement
10 dm3 cement concrete 1:1.5:3 using 20mm
metal (vide item no.122.a) 10dm3 53.23 53.23
0.1 m2 form work 10m2 3605.28 36.05
Total 10dm3 89.28 98.21

Page 21
Say Rs. 89.50 /10dm3 Rs. 98.00

134
b
Reinforced cement concrete 1:2:4 using 20mm b.s
for lintel (23x15cm) including form work, watering
curring etc.complete.but excluding reinforcement.
10 dm3 cement concrete 1:2:4 using 20mm
metal (vide item no.122) 10dm3 48.20 48.20
0.086 m2 form work 10m2 3015.93 25.94
74.14 81.55
Say Rs. 74.00 /10dm3 Rs. 81.50

134
b Reinforced cement concrete 1:11/2:3 using 20mm
b.s for lintel (23x15cm) including form work,
watering curring etc.complete.but excluding
reinforcement.
10 dm3 cement concrete 1:2:4 using 20mm
metal (vide item no.122) 10dm3 53.23 53.23
0.086 m2 form work 10m2 3015.93 25.94
79.17 87.08
Say Rs. 79 /10dm3 Rs. 87

134
Reinforced cement concrete 1:2:4 using 20mm b.s
c
for sun shade(60x7.5cm) including form work,
watering curring etc.complete .but excluding
reinforcement.
10 dm3 cement concrete 1:2:4 using 20mm
metal (vide item no.122) 10dm3 48.20 48.20
0.144 m2 form work 10m2 3015.93 43.43
Total 10dm3 91.63 100.79
Say Rs. 91.50 /10dm3 Rs. 101

134 Reinforced cement concrete 1:11/2:3 using 20mm


c b.s for sun shade(60x7.5cm) including form
work, watering curring etc.complete .but excluding
reinforcement.
10 dm3
cement concrete 1:11/2:3 using
20mm metal (vide item no.122) 10dm3 53.23 53.23
0.144 m2 form work 10m2 3015.93 43.43
Total 10dm3 96.66 106.33
Say Rs. 96.50 /10dm3 Rs. 106.50

134
d Cement concrete 1:2:4 using 20mm b.s for belt
(45x10),on top of ruble masonry including form
work, watering curring etc.complete.
10 dm3
cement concrete 1:2:4 using 20mm
metal (vide item no.122) 10dm3 48.20 48.20
form work 10m2 1.00
Total 10dm3 49.20 54.12
Say Rs. 49 /10dm3 Rs. 54

Page 22
134
Cement concrete 1:2:4 using 20mm b.s for
e
precast slab including form work, watering
curring etc.complete.
10 dm3 cement concrete 1:2:4 using 20mm
metal (vide item no.122) 10dm3 48.20 48.20
form work 10m2 1.00
Total 10dm3 49.20 54.12
Say Rs. 49 /10dm3 Rs. 54

134 Cement concrete 1:2:4 using 20mm b.s for


f column footing (120x120cm) including form work,
watering curring etc.complete.
10 dm3 cement concrete 1:2:4 using 20mm
metal (vide item no.122) 10dm3 48.20 48.20
0.014 m2 form work @ 50% of slab 10m2 1370.88 0.96
Total 10dm3 49.16 54.07
Say Rs. 49 /10dm3 Rs. 54

134 Reinforced cement concrete 1:2:4 using 20mm b.s


g for beam (20x20cm), including form work,
watering curring etc.complete.but excluding
reinforcement.
10 dm3 cement concrete 1:2:4 using 20mm
metal (vide item no.122) 10dm3 48.20 48.20
0.15 m2 form work 10m2 3965.81 59.49
Total 10dm3 107.69 118.45
Say Rs. 107.50 /10dm3 Rs. 118.50

134 Reinforced cement concrete 1:11/2:3 using 20mm


g b.s for beam (20x20cm), including form work,
watering curring etc.complete.but excluding
reinforcement.
10 dm3 cement concrete 1:11/2:3 using
20mm metal (vide item no.122) 10dm3 53.23 53.23
0.15 m2 form work 10m2 3015.93 45.24
Total 10dm3 98.47 108.32
Say Rs. 98.50 /10dm3 Rs. 108.50

134
Reinforced cement concrete 1:2:4 using 20mm b.s
h
for beam (20x30cm), including form work,
watering curring etc.complete.but excluding
reinforcement.
10 dm3 cement concrete 1:2:4 using 20mm
metal (vide item no.122) 10dm3 48.20 48.20
0.133 m2 form work 10m2 3965.81 52.75
Total 10dm3 100.94 111.04
Say 101 /10dm3 Rs. 111

Page 23
134
h Reinforced cement concrete 1:11/2:3 using 20mm
b.s for beam (20x30cm), including form work,
watering curring etc.complete.but excluding
reinforcement.
10 dm3
cement concrete 1:11/2:3 using
20mm metal (vide item no.122) 10dm3 53.23 53.23
0.133 m2 form work 10m2 3015.93 40.11
Total 10dm3 93.34 102.68
Say 93.50 /10dm3 Rs. 102.50

134 Reinforced cement concrete 1:2:4 using 20mm b.s


i for beam (20x40cm), including form work,
watering curring etc.complete.but excluding
reinforcement.
10 dm3 cement concrete 1:2:4 using 20mm
metal (vide item no.122.a) 10dm3 48.20 48.20
0.125 m2 form work 10m2 3965.81 49.57
Total 10dm3 97.77 107.55
Say Rs. 98 /10dm3 Rs. 107.50

134
i Reinforced cement concrete 1:11/2:3 using 20mm
b.s for beam (20x40cm), including form work,
watering curring etc.complete.but excluding
reinforcement.
10 dm3 cement concrete 1:11/2:3 using
20mm metal (vide item no.122.a) 10dm3 53.23 53.23
0.125 m2 form work 10m2 3015.93 37.70
Total 10dm3 90.93 100.02
Say Rs. 91 /10dm3 Rs. 100

135
Reinforced cement concrete 1:2:4 using 20mm b.s
for column(20x20cm) including form work,
watering curring etc.complete.butexcluding
reinforcement.
10 dm3 cement concrete 1:2:4 using 20mm
metal (vide item no.122) 10dm3 48.20 48.20
0.20 m2 form work 10m2 3290.10 65.80
Total 10dm3 114.00 125.40
Say Rs. 114.00 /10dm3 Rs. 125.50

135
Reinforced cement concrete 1:11/2:3 using 20mm
b.s for column(20x20cm) including form work,
watering curring etc.complete.butexcluding
reinforcement.
10 dm3 cement concrete 1:11/2:3 using
20mm metal (vide item no.122) 10dm3 53.23 53.23
0.20 m2 form work 10m2 3290.10 65.80

Page 24
Total 10dm3 119.03 130.94
Say Rs. 119 /10dm3 Rs. 131

135
a Reinforced cement concrete 1:2:4 using 20mm b.s
for column(30x20cm) including form work,
watering curring etc.complete.butexcluding
reinforcement.
10 dm3 cement concrete 1:2:4 using 20mm
metal (vide item no.122) 10dm3 48.20 48.20
0.167 m2 form work 10m2 3290.10 54.94
Total 10dm3 103.14 113.46
Say Rs. 103 /10dm3 Rs. 113.50

135 Reinforced cement concrete 1:11/2:3 using 20mm


a b.s for column(30x20cm) including form work,
watering curring etc.complete.butexcluding
reinforcement.
10 dm3
cement concrete 1:11/2:3 using
20mm metal (vide item no.122) 10dm3 53.23 53.23
0.167 m2
form work 10m2 3290.10 54.94
Total 10dm3 108.18 118.99
Say Rs. 108 /10dm3 Rs. 119

135
Reinforced cement concrete 1:2:4 using 20mm b.s
b
for column(40x20cm) including form work,
watering curring etc.complete.butexcluding
reinforcement.
1 dm3 cement concrete 1:1.5:3 using 20mm
metal (vide item no.122.a) 10dm3 48.20 48.20
0.15 m2 form work 10m2 3290.10 49.35
Total 10dm3 97.55 107.30
Say Rs. 97.50 /10dm3 Rs. 107.50

135 Reinforced cement concrete 1:1.5:3 using 20mm


b b.s for column(40x20cm) including form work,
watering curring etc.complete.butexcluding
reinforcement.
1 dm3
cement concrete 1:1.5:3 using 20mm
metal (vide item no.122.a) 10dm3 53.23 53.23
0.15 m2 form work 10m2 3290.10 49.35
Total 10dm3 102.58 112.84
Say Rs. 102.50 /10dm3 Rs. 113

BRICK WORK

Page 25
158
Brick work in cement mortar 1:5 with country burned
bricks19x9x9cm for foundatioin and basement
500 no. brick 1000n 2500.00 1250.00
0.24 m3 sand m3 1750.00 420.00
69 kg cement t 4700.00 324.30
0.7 no. mason each 325.00 227.50
0.35 no. man each 240.00 84.00
0.7 no. women each 240.00 168.00
500 no. conveyance for bricks 1000 518.00 259.00
0.24 m3 do sand m3 400.00 96.00
69 kg do cement t 234.00 16.15
Total m3 2844.95 3129.44
Say Rs. 2,845 /m3 Rs. 3,129

163 Brick work in cement mortar 1:5 with country burned


bricks19x9x9cm for superstructure in Gfloor upto
5m ht.
1 m3 Brick work (vide item No.158) m3 2844.95 2844.95
0.07 no. mason each 325.00 22.75
0.035 no. man each 240.00 8.40
0.07 no. women each 240.00 16.80
LS hire for scaffolding LS 6.25
Total m3 2899.15 3189.06
Say Rs. 2,899 /m3 Rs. 3,189

158
a Brick work in cement mortar 1:5 with country burned
bricks 22.9x11.2x7cm for foundatioin and
basement
460 no. brick 1000n 2800.00 1288.00
0.24 m3 sand m3 1750.00 420.00
69 kg cement t 4700.00 324.30
0.7 no. mason each 325.00 227.50
0.35 no. man each 240.00 84.00
0.7 no. women each 240.00 168.00
460 no. conveyance for bricks 1000 518.00 238.28
0.24 m3 do sand m3 400.00 96.00
69 kg do cement t 234.00 16.15
Total m3 2862.23 3148.45
Say Rs. 2,862 /m3 Rs. 3,148

163 Brick work in cement mortar 1:5 with country burned


a bricks 22.9x11.2x7cm for superstructure in Gfloor
upto 5m ht.
1 m3 Brick work (vide item No.158a) m3 2862.23 2862.23
0.07 no. mason each 325.00 22.75
0.035 no. man each 240.00 8.40
0.07 no. women each 240.00 16.80
LS hire for scaffolding LS 6.25
Total m3 2916.43 3208.07
Say Rs. 2,916 /m3 Rs. 3,208

Page 26
159
Brick work in cement mortar 1:6 with country burned
bricks19x9x9cm for foundatioin and basement
500 no. brick 1000n 2500.00 1250.00
0.24 m3 sand m3 1750.00 420.00
58 kg cement t 4700.00 272.60
0.7 no. mason each 325.00 227.50
0.35 no. man each 240.00 84.00
0.7 no. women each 240.00 168.00
500 no. conveyance for bricks 1000 518.00 259.00
0.24 m3 do sand m3 400.00 96.00
58 kg do cement t 234.00 13.57
Total m3 2790.67 3069.74
Say Rs. 2,791 /m3 Rs. 3,070

163
Brick work in cement mortar 1:6 with country burned
b
bricks19x9x9cm for superstructure in Gfloor upto
5m ht.
1 m3 Brick work (vide item No.159) m3 2790.67 2790.67
0.07 no. mason each 325.00 22.75
0.035 no. man each 240.00 8.40
0.07 no. women each 240.00 16.80
LS hire for scaffolding LS 6.25
Total m3 2844.87 3129.36
Say Rs. 2,845 /m3 Rs. 3,129

159 Brick work in cement mortar 1:6 with country burned


a bricks 22.9x11.2x7cm for foundatioin and
basement
460 no. brick 1000n 2800.00 1288.00
0.24 m3 sand m3 1750.00 420.00
58 kg cement t 4700.00 272.60
0.7 no. mason each 325.00 227.50
0.35 no. man each 240.00 84.00
0.7 no. women each 240.00 168.00
460 no. conveyance for bricks 1000 518.00 238.28
0.24 m3 do sand m3 400.00 96.00
58 kg do cement t 234.00 13.57
Total m3 2807.95 3088.75
Say Rs. 2,808 /m3 Rs. 3,089

163
Brick work in cement mortar 1:6 with country burned
c
bricks 22.9x11.2x7cm for superstructure in Gfloor
upto 5m ht.
1 m3 Brick work (vide item No.159a) m3 2807.95 2807.95
0.07 no. mason each 325.00 22.75
0.035 no. man each 240.00 8.40
0.07 no. women each 240.00 16.80
LS hire for scaffolding LS 6.25
Total m3 2862.15 3148.37
Say Rs. 2,862 /m3 Rs. 3,148

CEMENT BRICK WORK

Page 27
163
d Hollow brick stone masonry of brick 40x20x20cm
in cement mortar 1:5 for foundation and basement
55 no Hollow brick stone 100No 1500.00 825.00
0.16 m3 sand m3 1750.00 280.00
46 kgs cement t 4700.00 216.20
1.5 no mason each 325.00 487.50
0.35 no man each 240.00 84.00
0.5 no women each 240.00 120.00
0.84 m3 conveyance of stone m3 257.00 215.88
0.16 m3 do sand m3 400.00 64.00
46 kgs cement t 234.00 10.76
2303.34 2533.68
Say Rs. 2,303 /m3 Rs. 2,534

163 Hollow brick masonry of brick 40x20x20cm in


e cement mortar 1:5 for superstructure
1 m3 Hollow Brick work for foundation m3 2303.34 2303.34
0.15 no mason each 325.00 48.75
0.035 no man each 240.00 8.40
0.05 no women each 240.00 12.00
LS hire for scaffolding LS 6.25
Total m3 2378.74 2616.62
Say Rs. 2,379 /m3 Rs. 2,617

163 Hollow brick masonry of brick 40x20x10cm in


f cement mortar 1:5 for foundation
105 no Hollow brick stone 100No 1250.00 1312.50
0.16 m3 sand m3 1750.00 280.00
46 kgs cement t 4700.00 216.20
1.7 no mason each 325.00 552.50
0.35 no man each 240.00 84.00
1 no women each 240.00 240.00
0.84 m3 conveyance of stone m3 257.00 215.88
0.16 m3 do sand m3 400.00 64.00
46 kgs cement t 234.00 10.76
2975.84 3273.43
Say Rs. 2,976 /m3 Rs. 3,273

Hollow brick masonry of brick 40x20x10cm in


cement mortar 1:5 for superstructure
1 m3 Hollow Brick work for foundation m3 2975.84 2975.84
0.15 no mason each 325.00 48.75
0.035 no man each 240.00 8.40
0.05 no women each 240.00 12.00
LS hire for scaffolding LS 6.25
Total m3 3051.24 3356.37
Say Rs. 3,051 /m3 Rs. 3,356

163 Cement Solid brick masonry of brick 40x20x15cm in


g cement mortar 1:6 for foundation and basement
70 no Cement solid brick 100Nos 2100.00 1470.00

Page 28
0.16 m3 sand m3 1750.00 280.00
38 kg cement t 4700.00 178.60
0.70 no. mason each 325.00 227.50
0.35 no. man each 240.00 84.00
0.70 no. women each 240.00 168.00
0.84 no conveyance for brick m3 257.00 215.88
0.16 m3 do sand m3 400.00 64.00
38 kg do cement kg 234.00 8.89
Total m3 2696.87 2966.56
Say Rs. 2,697 /m3 Rs. 2,967

163
h Cement Solid brick masonry of brick 40x20x15cm
in cement mortar 1:6 for superstructure
1 m3 solid brick work for foundation m3 2696.87 2696.87 3263.22
add 10% of labour
0.07 no mason each 325.00 22.75 25.03
0.035 no. man each 240.00 8.40 9.24
0.07 no women each 240.00 16.80 18.48
LS hire for scaffolding LS 6.25 6.88
Total m3 2751.07 3322.84
Say Rs. 2,751 /m3 Rs. 3,323

164 Cement Solid brick work for superstructure in


each sucessive floors add the extra labour to the
previous floor
add 10% of labour
0.07 no mason each 325.00 22.75 25.03
0.035 no. man each 240.00 8.40 9.24
0.07 no women each 240.00 16.80 18.48
LS hire for scaffolding LS 6.25 6.25
54.20 59.00
Say Rs. 54 /m3 Rs. 59

LATERITE MASONRY

206 Laterite neatly dressed stones of size 35x20x14cm


a in cement mortar 1:6 for foundatioin and
basement
60 no laterite stones 100n 1350.00 810.00
0.16 m3 sand m3 1750.00 280.00
38 kg cement t 4700.00 178.60
1.5 no. mason each 325.00 487.50
0.35 no. man each 240.00 84.00
0.5 no. women each 240.00 120.00
0.88 no conveyance for laterite m3 257.00 226.16
0.16 m3 do sand m3 400.00 64.00
38 kg do cement t 234.00 8.89
Total m3 2259.15 2485.07
Say Rs. 2,259 /m3 Rs. 2,485

207 Laterite work in cement mortar 1:6 for


a superstructure in Gfloor upto 5m ht.

Page 29
1 m3 laterite work (vide item no.206a) m3 2259.15 2259.15 2485.07
0.15 no mason each 325.00 48.75 53.63
0.035 no man each 240.00 8.40 9.24
0.05 no women each 240.00 12.00 12.00
LS hire for scaffolding LS 6.25 6.88
Total m3 2334.55 2566.81
Say Rs. 2,335 /m3 Rs. 2,567

206 Laterite neatly dressed stones of size 29x24x14cm


in cement mortar 1:5 for foundatioin and
basement
90 no laterite stones 100n 1250.00 1125.00
0.16 m3 sand m3 1750.00 280.00
46 kg cement ton 4700.00 216.20
1.5 no. mason each 325.00 487.50
0.35 no. man each 240.00 84.00
0.5 no. women each 240.00 120.00
0.88 no conveyance for laterite m3 257.00 226.16
0.16 m3 do sand m3 400.00 64.00
46 kg do cement ton 234.00 10.76
Total m3 2613.62 2874.99
Say Rs. 2,614 /m3 Rs. 2,875

207 Laterite work in cement mortar 1:5 for


superstructure in Gfloor upto 5m ht.
1 m3 laterite work (vide item no.206) m3 2613.62 2613.62 2874.99
0.15 no mason each 325.00 48.75 53.63
0.035 no man each 240.00 8.40 9.24
0.05 no women each 240.00 12.00 13.20
LS hire for scaffolding LS 6.25 6.25
Total m3 2689.02 2957.30
Say Rs. 2,689 /m3 Rs. 2,957

206 Laterite neatly dressed stones of size 29x24x14cm


a in cement mortar 1:6 for foundatioin and
basement
90 no laterite stones 100n 1250.00 1125.00
0.16 m3 sand m3 1750.00 280.00
38 kg cement ton 4700.00 178.60
1.5 no. mason each 325.00 487.50
0.35 no. man each 240.00 84.00
0.5 no. women each 240.00 120.00
0.88 no conveyance for laterite m3 257.00 226.16
0.16 m3 do sand m3 400.00 64.00
38 kg do cement ton 234.00 8.89
Total m3 2574.15 2831.57
Say Rs. 2,574 /m3 Rs. 2,832

207
Laterite work in cement mortar 1:6 for
a
superstructure in Gfloor upto 5m ht.
1 m3 laterite work (vide item no.206a) m3 2574.15 2574.15 2831.57
0.15 no mason each 325.00 48.75 53.63
0.035 no man each 240.00 8.40 9.24

Page 30
0.05 no women each 240.00 12.00 13.20
LS hire for scaffolding LS 6.25 6.25
Total m3 2649.55 2913.88
Say Rs. 2,650 /m3 Rs. 2,914

208 Laterite work for superstructure in each


sucessive floors add the extra labour to the
previous floor
0.15 no mason each 325.00 48.75 53.63
0.035 no man each 240.00 8.40 9.24
0.05 no women each 240.00 12.00 13.20
LS hire for scaffolding LS 6.25 6.25
Total m3 75.40 82.32
Say Rs. 75 /m3 Rs. 82

RR MASONRY

274 Random rubble masonry in cement mortar 1:6 for


foundation and basement
1 m3 blasted rubble m3 270.00 270.00
0.3 m3 sand m3 1750.00 525.00
72 kg cement tonne 4700.00 338.40
0.7 no mason each 325.00 227.50
0.35 no man each 240.00 84.00
0.7 no women each 240.00 168.00
1 m3 conveyance for blasted rubble m3 499.00 499.00
0.3 m3 do sand m3 400.00 120.00
72 kg do cement kg 234.00 16.85
Total m3 2248.75 2473.62
Say Rs. 2,249 /m3 Rs. 2,474.00

275
Random rubble masonry in cement mortar 1:8 for
foundation and basement
1 m3 blasted rubble m3 270.00 270.00
0.3 m3 sand m3 1750.00 525.00
54 kg cement t 4700.00 253.80
0.7 no mason each 325.00 227.50
0.35 no man each 240.00 84.00
0.7 no women each 240.00 168.00
1 m3 conveyance for blasted rubble m3 499.00 499.00
0.3 m3 do sand m3 400.00 120.00
54 kg do cement kg 234.00 12.64
Total m3 2159.94 2375.93
Say Rs. 2,160 /m3 Rs. 2,376.00

275
a Random rubble masonry wih Departmental stone
in cement mortar 1:6 for foundation and basement
0.3 m3 sand m3 270.00 81.00
72 kg cement t 1750.00 126.00
0.7 no mason each 4700.00 3290.00
0.35 no man each 325.00 113.75

Page 31
0.7 no women each 240.00 168.00
0.3 m3 conveyance of sand m3 240.00 72.00
72 kg do cement kg 499.00 35.93
Total m3 3886.68 4275.35
Say Rs. 3,887 /m3 Rs. 4,275

277 Dry stone masonry for retaining wall including the


cost and conveyance of all materials and labour etc,
complete
1.05 m3 blasted rubble m3 270.00 283.50
1.05 m3 conveyance of blasted rubble m3 499.00 523.95
0.8 no rubble mason each 325.00 260.00
0.7 no man each 240.00 168.00
Total m3 1235.45 1359.00
Say Rs. 1,235 /m3 Rs. 1,359.00

277
a Dry stone masonry with Departmental stone for
retaining wall including the cost and conveyance of
all materials and labour etc, complete
0.8 no rubble mason each 325.00 260.00
0.7 no man each 240.00 168.00
Total m3 428.00 470.80
Say Rs. 428.00 /m3 Rs. 471.00

278 Rough stone dry packing for Aprons and


revetments including the cost and conveyance of
all materials and labour etc, complete
1.05 m3 blasted rubble m3 270.00 283.50
1.05 m3 conveyance of blasted rubble m3 499.00 523.95
0.35 no mason each 325.00 113.75
0.70 no man each 240.00 168.00
0.70 no women each 240.00 168.00
Total m3 1257.20 1382.92
Say Rs. 1,257 /m3 Rs. 1,383.00

278 Rough stone dry packing for forming road


surface including the cost and conveyance of all
materials and labour etc, complete
1.00 m3 blasted rubble m3 270.00 270.00
1.00 m3 conveyance of blasted rubble m3 499.00 499.00
0.70 no man each 240.00 168.00
0.70 no women each 240.00 168.00
Total m3 1105.00 1215.50
Say Rs. 1,105 /m3 Rs. 1,216.00

Packing with mutty stone in slushly portion of the


road

1 m3 cost of mutty stone m3 135.00 135.00

Page 32
1 m3 conveyance m3 499.00 499.00
spreading gravel SI 656
0.35 no man each 240.00 84.00
Total 718.00 789.80
Say Rs. 718.00 /m3 Rs. 790.00

WOOD WORK

301
a Anjily wood scantling 10dm3
14.4 dm3 Anjily wood log m3 ### 360.00
0.02 no man each 240.00 4.80
0.1419 no 0.33m2 sawing(4.3 sawer for10m2) each 300.00 42.57
407.37
3.8 dm3 Deduct cost of outer slab(25%) m3 6250.00 23.75
383.62
14.4 dm3 conveyance of Anjily wood log m3 360.90 5.20
Total 10dm3 388.82 427.70
Say Rs. 389 /10dm3 Rs. 428

312 Anjily wood wrought and put up


10.5 dm3 Anjily wood scantling allowing 5% wa 10dm3 383.62 402.80
10.5 dm3 Conceyance of -do- m3 407.90 4.28
0.04 no carpenter each 325.00 13.00
0.04 no man each 240.00 9.60
Total 10dm3 429.68 472.65
Say Rs. 430 /10dm3 Rs. 473

DOORS AND WINDOWS

Supplying and fixing Aluminium slinding window


with plain glass
window size 150x150
hight of Aluminium plain section
2 ( 2x2x0.85) = 3.40 2 0.85 0.00
( 4 x 1.50 ) = 6.00 4 1.5 6.00
6.00
5% wastage 0.30
6.30
2 Area of glass(2x0.85x1.50) =2.55m2 0.85 1.50 2.55

Observed Data
9.87 m 2x1 plain section m 150.00 1480.50 1628.55
2 1.5 2x1.5 top and bottom channel m 300.00 900.00 990.00
2.55 m2 4mm glass m2 260.00 663.00 729.30
9.87 m rubber beading m 3.00 29.61 32.57
L.S conveyance 30.00 30.00
2 nos fitter each 210.00 420.00 462.00
2 nos man each 168.00 336.00 369.60
3859.11 4242.02
1.5 3687.21/(1.50x1.50) 1.5 3859.11 1715.16 1885.34
Say Rs. 1,715 /m2 Rs. 1,885

Page 33
313 Supplying and fixing Anjily wood planed and
framed work for frames of door window ventilator
etc
10.5 dm3 Anjily wood scanteling 10dm3 383.62 402.80
0.22 no carpenter each 325.00 71.50
0.1 no man each 240.00 24.00
10.5 dm3
conveyance of Anjily wood scanteling m3 495.00 5.20
Total 10dm3 503.50 553.85
Say Rs. 503 /10dm3 Rs. 554

Sub Data
(A) Fixing in position precast cement concrete Door /
Window
Labour charges
0.2 no mason each 325.00 65.00
0.3 no man each 240.00 72.00
LS conveyance and sundries 9.00
146.00 160.60
Hence fixing charge for door/ window Say Rs. 105 /Each Rs. 116

(B) Fixing in position cement concrete


Ventilator
Labour charges
0.1 no mason each 325.00 32.50 35.75
0.1 no man each 240.00 24.00 26.40
LS conveyance and sundries 7.50 7.50
64.00 69.65
Hence fixing charge for door/ window Say Rs. 47.00 /Each Rs. 51

313 Suplying and fixing in position Cement Concrete


a Door/ window/ ventilator at different size with
nominal reinforcement using 8mm tore steel etc.
complete.

Door

1 m3 Cost of door frame @ /m2(MR) m2


Conveyance& fixing charges LS
Total
Say Rs. /m2 Rs.

Window

Say Rs. /m2 Rs.

Ventilator

Say Rs. /10m2 Rs.

326 Ceiling with 12mm Anjily wood


planks, planed, lap joined, and wire
nailed to rafters and collors 10m 2
sub data

Page 34
304a Anjily wood ceiling planks 12mm
thick 10m2
183 dm3 Anjily wood log m3 ### 4575.00
0.55 no man each 240.00 132.00
4.644 no 10.8m2 sawing(4.3 sawer for10m2) each 300.00 1393.20
6100.20
45 dm3 Deduct cost of outer slab(25%) m3 6250.00 281.25
Total 5818.95
183 dm3 conveyance of Anjily wood planks m3 495.00 90.59
5909.54
Main Data
10.5 m2 ceiling with 12mm Anjily wood planks, 10m2 5909.54 6205.01 6825.51
0.25 kg wire nail kg 42.00 10.50 11.55
1.1 no carpenter for fitting each 325.00 357.50 393.25
2.15 no carpenter for planing each 325.00 698.75 768.63
1.1 no man each 240.00 264.00 290.40
Scaffolding LS 6.25 6.25
7542.01 8295.59
Say Rs. 7,542 /10m2 Rs. 8,296

351
Supplying and fixing Anjily wood fully panelled
shutters to suit the door frames already fixed in
position,inclusive of all labour charges of all iron
fittings,but excluding the cost of fittings
scanteling requires for 10dm2 is
(50.303/168.56)10=3.03dm3
3.03 dm3 Anjily wood scanteling 10dm3 383.62 116.24
3.03 dm3 conveyanve of scantling m3 495.00 1.50
0.386 no carpenter each 325.00 125.45
0.028 no man each 240.00 6.72
Total 10dm2 249.91 274.90
Say Rs. 250.00 /10dm2 Rs. 275.00

360
a Supplying and fixing fully glazed Anjily wood
shutters to suit the window frames already fixed,
including all labour charges for fixing iron fittings,
but excluding the cost of iron fittings
2.068 dm3
Anjily wood scanteling (37.78dm3 for
190.44dm2 ie,0.198dm3 for 10dm2) 10dm3 383.62 79.33 87.27
2.068 m3 conveyance of Anjily wood m3 495.00 1.02 1.13
0.086 m2 glass pan, 3mm thick m2 235.00 20.21 22.23
0.386 no carpenter each 325.00 125.45 138.00
0.028 no man each 240.00 6.72 7.39
LS nails, fillers, putty etc LS 1.25 1.38
Total 10dm2 233.99 257.38
Say Rs. 234 /10dm2 Rs. 257

368 Providing MS rods for windows and windows and


ventilators
1 qtl MS rods qtl 3250.00 3250.00
1 no blacksmith each 325.00 325.00

Page 35
2 no carpenter each 325.00 650.00
1 qtl conveyance of MS rods t 234.00 23.40
Total qtl 4248.40 4673.24
Say Rs. 4,248 /Qtl Rs. 4,673

369 Providing MS flat ion works for hold fast to doors


and windows
1.00 qtl MS flat qtl 3800.00 3800.00 4180.00
10.00 kg charcoal qtl 550.00 55.00 60.50
LS sundries LS LS 3.10 3.10
5.00 no blacksmith each 325.00 1625.00 1787.50
0.66 no man (bellow boy) each 240.00 158.40 174.24
1.00 qtl conveyance of MS flat t 234.00 23.40 25.74
Total qtl 5664.90 6231.08
Say Rs. 5,665 /Qtl Rs. 6,231

Supplying and fixing iron fittings to doors and


13 windows
a 100mm iron butt hinges 85.00 /10nos 93.50
b 75mm iron butt hinges 42.00 /10nos 46.20
c 100mm aluminium tower bolt 250.00 /10nos 275.00
d 150mm aluminium tower bolt 320.00 /10nos 352.00
e 200mm aluminium tower bolt 360.00 /10nos 396.00
f 200mm aluminium aldrop 1100.00 /10nos 1210.00
g 75mm iron hooks and eyes 20.00 /10nos 22.00
h 100mm iron hooks and eyes 26.00 /10nos 28.60
i 200mm iron hooks and eyes 50.00 /10nos 55.00
j 150mm aluminium door handle 250.00 /10nos 275.00
k 20*7mm steel screws 6.50 /10nos 7.15
l 25*8mm steel screws 7.50 /10nos 8.30
m 50mm pad lock-6 lever 120.00 /each 132.00
n 65mm pad lock-7 lever 185.00 /each 203.50

FLOORING
410
Flooring with cement concrete 1:4:8 75mmthick
using 40mm broken stone and plastyered over with
cement mortar 1:3,12mm thick floated hard and
trowelled smooth
0.75 m3 Cement concrete 1:4:8 using 40mm
broken stone (Sl.no.111) m3 3423.76 2567.82
10.0 m2
Plastering in cement mortar
1:3,12mm thick one coat(Sl.no.506) 10m2 1315.14 1315.14
Total 10m2 3882.97 4271.26
Say Rs 3883 /10m2 Rs. 4271

410
a Flooring with cement concrete 1:4:8 75mmthick
using 40mm broken stone and plastyered over with
cement mortar 1:3,12mm thick and neat cement
flushing coat

Page 36
0.75 m3 Cement concrete 1:4:8 using 40mm
broken stone(Sl.no.111) m3 3423.76 2567.82
10 m2
Plastering in cement mortar
1:3,12mm thick one coat(Sl.no.506) 10m2 1315.14 1315.14
10 m2
Cement flushing coat/second coat
over cement plaster items(Sl.no.514) 10m2 271.05 271.05
Total 10m2 4154.02 4569.42
Say Rs 4154 /10m2 Rs. 4569

409
a
Flooring with ISO/ Ist quality ceramic floor tiles
(30x30cm) laid in cement mortar 1:3,12mm thick in
line and level as per specifications and directions 10m2
10.5 m2 ceramic floor tiles(add 5% wastage) m2 320.00 3360.00 3696.00
0.01 m3 sand m3 1750.00 17.50 19.25
23 kg cement t 4700.00 108.10 118.91
0.01 conveyance of sand m3 400.00 4.00 4.40
23 conveyance of cement t 234.00 5.38 5.92
10 m2 cement plaster 1:3,12mm thick
(Sl.506) 10m2 1315.14 1315.14 1446.66
1.5 no mason each 325.00 487.50 536.25
0.9 no man each 240.00 216.00 237.60
117 no conveyance of tiles 1000no 518.00 60.43 66.48
LS sundries for colour, cutting machine
etc LS 31.00 31.00
5605.06 6162.47
Say Rs 5605 /10m2 Rs. 6162

409
b Flooring with ISO/best quality rectified tiles (joint
free of size 45x45cm) laid in cement mortar
1:3,12mm thick in line and level as per
specifications and directions 10m2
10.5 m2 rectified joint free tiles(add 5%
wastage) m2 350.00 3675.00 4042.50
10 m2 cement plaster 1:3,12mm thick
(Sl.506) 10m2 1315.14 1315.14 1446.66
1 no mason each 325.00 325.00 357.50
0.5 no man each 240.00 120.00 132.00
0.5 no boy each 180.00 90.00 99.00
52 no conveyance of tiles 1000no 518.00 26.94 29.63
LS sundries for cutting machine etc LS 6.25 6.25
5558.33 6113.54
Say Rs 5558 /10m2 Rs. 6114

409 Flooring with ISO/best quality Vitrified tiles


c ( 60x60cm) laid in cement mortar 1:3,12mm thick in
line and level as per specifications and directions 10m2
10.5 m2 victrified tiles(add 5% wastage) m2 570.00 5985.00 6583.50

Page 37
10 m2 cement plaster 1:3,12mm thick
(Sl.506) 10m2 1315.14 1315.14 1446.66
1 no mason each 325.00 325.00 357.50
0.5 no man each 240.00 120.00 132.00
0.5 no boy each 180.00 90.00 99.00
30 no conveyance of tiles 1000no 518.00 15.54 17.09
LS sundries for cutting machine etc LS 6.25 6.25
7856.93 8642.00
Say Rs 7857 /10m2 Rs. 8642

413
a Flooring with gray marble slab over a bed of
cement mortar 1:4,12mm thick including the cost of
polishing and all laour charges etc. complete
10.5 m2 gray marble slab m2 520.00 5460.00 6006.00
10 m2 cement mortar 1:4,12mm thick
(Sl.No,507) 10m2 1277.44 1277.44 1405.18
1 no carborandom stone each 120.00 120.00 132.00
2 no mason each 325.00 650.00 715.00
2 no man each 240.00 480.00 528.00
0.5 no boy each 180.00 90.00 99.00
4 no polisher each 198.00 792.00 871.20
2 no man each 240.00 480.00 528.00
1 day hire of cutting mechine day 50.00 50.00 50.00
2 day hire of polishing mechine day 50.00 100.00 100.00
sundries for wax,current charge etc LS 25.00 25.00
9524.44 10459.38
Say Rs 9524 /10m2 Rs. 10459

413 Flooring with polished granite tiles (cat eye red


b tiles of size 2x1 ft,10mm thick) over a bed of cement
mortar 1:4,12mm thick including all laour charges
etc. complete
10.5 m2 granite tiles (cat eye red tiles of size
2x1 ft,10mm thick) m2 645.00 6772.50 7449.75
10 m2 cement mortar 1:4,12mm thick
(Sl.No,507) 10m2 1277.44 1277.44 1405.18
1 no mason each 325.00 325.00 357.50
0.5 no man each 240.00 120.00 132.00
0.5 no boy each 180.00 90.00 99.00
57 no conveyance of tiles 1000no 518.00 29.53 32.48
sundries for cutting machine, colour
for pointing etc LS 20.00 20.00
8634.46 9495.91
Say Rs 8634 /10m2 Rs. 9496

536
Dadoing the walls with coloured glazed tiles of
size 20x20cm, 7.5mm thick,in 12mm cement mortar
1:3 and pointed with coloured cement
25nos/

25 nos coloured glazed tiles 10nos 125.00 312.50 343.75

Page 38
5% wastage 15.63 17.19
1 m2 Plastering CM 1:3,12mm
thick(Sl.506) 10m2 1315.14 131.51 144.67
0.001 m3 sand m3 1750.00 1.75 1.93
0.48 kg cement tonne 4700.00 2.26 2.48
0.001 m3 conveyance of sand m3 400.00 0.40 0.44
0.48 kg conveyance of cement tonne 234.00 0.11 0.12
0.90 no mason each 325.00 292.50 321.75
0.50 no man each 240.00 120.00 132.00
LS colour LS 3.10 3.10
25 nos conveyance of tiles 3000nos 518.00 4.32 4.75
Total m2 884.07 972.17
Say Rs 884 /m2 Rs. 972

ROOFING
305
Supplying and fixing Anjily wood reepers
50mmx25mm to 38mmx16mm 10dm2
15.00 dm3 Anjily wood log(33% log value) m3 8250.00 123.75
1.6426 m2 3.82m2 sawing(4.3 sawer for10m2) each 300.00 492.78
616.53 678.18
Say Rs 617 /10dm2 Rs. 678

318 Supplying and fixing Anjily wood reepers with wire


nails of sutable length 10dm3
10 dm3 Anily wood reepers 10dm3 429.68 429.68
0.05 kg Wire nails kg 42.00 2.10
0.1 no carpenter each 325.00 32.50
0.1 no man each 240.00 24.00
488.28 537.11
Say Rs 488 /10dm3 Rs. 537

328 Ceiling with 12mm thick Anjily wood planks in


necessary overlaps using wire nails
10.5 dm3 anjily wood planks including
conveyance m2 429.68 4511.68
0.25 kg wire nails kg 42.00 10.50
1.1 no carpenter each 325.00 357.50
2.15 no carpenter for plaining each 325.00 698.75
1.1 no man each 240.00 264.00
sundies for scaffolding LS 6.25
5848.68 6433.55
Say Rs 5849 /10m2 Rs. 6434

452 Supplying and roofing with Ist class MP tiles


340mm size
145 no MP tiles of 340mm size 1000no 7000.00 1015.00
0.35 no mason each 325.00 113.75
0.35 no man each 240.00 84.00

Page 39
145 no conceyance of tiles 1000no 518.00 75.11
1287.86 1416.65
Say Rs 1288 /10m2 Rs. 1417

452 Roofing with Departmental MP roof tiles 340mm


a size
0.35 no mason each 325.00 113.75
0.35 no man each 240.00 84.00
0.3 no women for clean each 240.00 72.00
269.75 296.73
Say Rs 270 /10m2 Rs. 297

458
Suplying and fixing MP hip and ridge tiles Ist class
set in cement mortar 1:3 including finishing edges
27 nos MP hip and ridge tiles 1000nos ### 432.00
0.1 m3 cement mortar 1:3 m3 1094.16 109.42
0.75 nos mason each 325.00 243.75
0.3 nos man each 240.00 72.00
0.3 nos boy each 180.00 54.00
27 nos conveyance of MP tiles 340mm size 1000nos 518.00 13.99
925.15 1017.67
Say Rs 925 /10m Rs. 1018

458
Fixing with Depatmental MP hip and ridge tiles
a
set in cement mortar 1:3 including finishing the
edges 10m
0.1 m3 cement mortar 1:3 m3 1094.16 109.42
0.75 nos mason each 325.00 243.75
0.3 nos man each 240.00 72.00
0.3 nos boy each 180.00 54.00
0.2 nos women for cleaning each 240.00 48.00
527.17 579.88
Say Rs 527 /10m Rs. 580

460
Valleying with GI sheet 0.8mm thick 900mm width
with over laps of 150mm at joints including nails etc.
Details for 30m
174 kg 1mm thick GI plainsheet Tonne 42000 7308.00
0.25 kg wire nails kg 42.00 10.50
1.5 no carpenter each 325.00 487.50
1.5 no man each 240.00 360.00
174 kg conveyance of GI sheet T 234.00 40.72
8206.72
Hence for 10m 2735.57 3009.13
Say Rs 2736 /10m Rs. 3009

453
Roofing with AC corrugated sheets with GI bolts
and nuts and bitumenus washers including
necessary ocer laps of 150 mm at ends etc
complete
11.5 m2 AC corrugated sheets m2 150.00 1725.00

Page 40
1.05 kg GI hooks and crank bolts and nuts
including GI plain washers, bitumen
washers
etc(14x0.15x0.62kg/m=1.30kg) kg 50.00 52.50
11.5 m2 conveyance of 11.50m2 AC
sheet(15kg/m2) Tonne 234.00 40.37
1.60 no carpenter each 325.00 520.00
1.60 no man each 240.00 384.00
Total 10m2 2721.87 2994.05
Say Rs 2722 /10m2 Rs. 2994

454 Providing and fitting AC ridge capping with GI nut


and bolts and bitumen washers etc complete.
Details for 30m
31 pair plain AC ridge pair 120.00 3720.00
1.5 no carpenter each 325.00 487.50
1.5 no man each 240.00 360.00
31 pair conveyance of plain AC ridge
31x0.3=9.3m2 (15kg/m2) Tonne 234.00 32.64
Total 4600.14
Hence 10m 1533.38 1686.72
Say Rs 1533 /10m Rs. 1687

455
Roofing with galvanised iron corugatede sheets
1mm thick with overlape of 150mm at ends and GI
hooks or crank bolts and nuts including plain
washers and bitumen washers etc. complete
86 kg GI corrugated sheet 1mm thick t ### 3698.00
2.05 kg

GI hooks or crank bolts and nuts


including plain washers and bitumen
washers(22x0.15x0.62kg/m=2.05kg) kg 50.00 102.50
1.35 no carpenter each 325.00 438.75
1.35 no man each 240.00 324.00
86 kg conveyance of GI corrugated sheet t 234.00 20.12
4583.37 5041.71
Say Rs 4583 /10m2 Rs. 5042

455 Providing and fitting 0.8mm GI plane ridge capping


(a with GI nut and bolts and bitumen washers etc
complete.
Details for 30m
99.9 kg plain GI seet 0.8mm for
ridge(6.66Kg/m2) T ### 4195.80
11.44 kg GI hook or nut and bolts of 100mm
dia plain washers and bitumen
washers(123x0.15x0.62kg/m=11.44k
g) kg 50.00 572.00
1.35 no carpenter each 325.00 438.75

Page 41
1.35 no man each 240.00 324.00
99.9 kg conveyance of plain GI ridge t 234.00 23.38
Total 5553.93
Hence 10m 1851.31 2036.44
Say Rs 1851 /10m Rs. 2036

455
,b Roofing with fiber corugatede sheets 28gauge
with overlape of 150mm at ends and GI hooks or
crank bolts and nuts including plain washers and
bitumen washers etc. complete
10 m2 fiber corrugated sheet 1mm thick m2 1100.00 11000.00 12100.00
2.05 kg
GI hooks or crank bolts and nuts
including plain washers and bitumen
washers(22x0.15x0.62kg/m=2.05kg) kg 50.00 102.50 112.75
1.35 no fitter each 300.00 405.00 445.50
1.35 no man each 240.00 324.00 356.40
10 m2
conveyance of fiber corrugated sheet LS 30.00 30.00
11861.50 13044.65
Say Rs 11862 /10m2 Rs. 13045

455
,b
Roofing with alluminium corugatede sheets
26gauge 0.46mm thick with overlape of 150mm at
ends and GI hooks or crank bolts and nuts including
plain washers and bitumen washers etc. complete
11.5 m2
alluminium corrugated sheet 0.38mm
thick@1.47Kg/m2@Rs.230/Kg
GI hooks and crank bolts and nuts m2 230.00 3888.15 3888.15
1.65 kg including GI plain washers, bitumen
washers
etc(14x0.15x0.62kg/m=1.30kg) kg 50.00 82.50 90.75
1.35 no carpenter each 325.00 438.75 482.63
1.35 no man each 240.00 324.00 356.40
16.91 Kg Conveyance of Alluminium sheet tonne 234.00 3.96 4.35
Total 10m2 4737.36 4822.28
Say Rs 4737 /10m2 Rs. 4822

457 Providing and fitting 1mm thick alluminium plane


(a ridge capping with GI nut and bolts and bitumen
washers etc complete.
11.3 kg plain alluminium
sheet(10x0.225)@5.02Kg/m2@Rs.2
30/Kg kg 230.00 2599.00 2599.00
0.5 no carpenter each 325.00 162.50 178.75
0.5 no man each 240.00 120.00 132.00
11.30 Kg Conveyance of Alluminium sheet tonne 234.00 2.64 2.91
Total 2884.14 2912.66
Say Rs 2884 /10m Rs. 2913

Page 42
c)
Supplying and fixing 160mm dia PVC rain water
gutter semicircular section including fifing with
32x5mm MS flat supporters at 1m intervals
data for 6m
6 m PVC pipe,160mm dia (MR) m 130.00 780.00 858.00
7.8 kg 6x1m MS flat @1.3kg/m qtl 3800.00 296.40 326.04
sundries for conveyance,solvent etc LS 10.00 10.00
0.25 no plumber each 325.00 81.25 89.38
0.15 no man each 240.00 36.00 39.60
1203.65 1323.02
Hence for 1m 200.61 220.50
Say Rs 201 /m Rs. 221

d)
Supplying and laying 110mm dia PVC down water
pipe with fittings such as tees, elbows, bends,
checknuts, etc. complete

Details for 30m.


30 m 110mm PVC pipe (8kgf/cm2) m 204.00 6120.00 6732.00
add 10%for specials 612.00 673.20
LS clamp, cement ,paint etc LS 10.00 10.00
1.5 no. fitter each 300.00 450.00 495.00
1.5 no. man each 240.00 360.00 396.00
Total 7552.00 8306.20
Hence m 251.73 276.87
Say Rs 252 /m Rs. 277

PLASTERING

506 Plastering in cement mortar 1:3,12mm thick one


coat
0.14 m3 sand m3 1750.00 245.00
66 kg cement tonne 4700.00 310.20
0.9 no mason each 325.00 292.50
0.55 no man each 240.00 132.00
1.1 no women each 240.00 264.00
0.14 m3 conveyance of sand m3 400.00 56.00
66 kg do cement kg 234.00 15.44
Total 10m2 1315.14 1446.66
Say Rs 1315 /10m2 Rs. 1447

506 Plastering in cement mortar 1:3,9mm thick one


a coat floated hard and trowelled smooth etc.
complete
0.09 m3 sand m3 1750.00 157.50
43 kg cement kg 4700.00 202.10
0.9 no mason each 325.00 292.50
0.55 no man each 240.00 132.00
1.1 no women each 240.00 264.00
0.09 m3 conveyance of sand m3 400.00 36.00
43 kg do cement kg 234.00 10.06
Total 10m2 1094.16 1203.58

Page 43
Say Rs 1094 /10m2 Rs. 1204

507 Plastering in cement mortar 1:4,12mm thick one


coat
0.15 m3 sand m3 1750.00 262.50
54 kg cement tonne 4700.00 253.80
0.9 no mason each 325.00 292.50
0.55 no man each 240.00 132.00
1.1 no women each 240.00 264.00
0.15 m3 conveyance of sand m3 400.00 60.00
54 kg do cement kg 234.00 12.64
Total 10m2 1277.44 1405.18
Say Rs 1277 /10m2 Rs. 1405

511 Plastering in cement mortar 1:4,15mm thick one


coat
0.165 m3 sand m3 1750.00 288.75
59 kg cement tonne 4700.00 277.30
0.9 no mason each 325.00 292.50
0.55 no man each 240.00 132.00
1.1 no women each 240.00 264.00
0.165 m3 conveyance of sand m3 400.00 66.00
59 kg do cement kg 234.00 13.81
Total 10m2 1334.36 1467.79
Say Rs 1334 /10m2 Rs. 1468

514 Cement flushing coat / second coat over cement


plaster items
22 kg Cement tonne 4700.00 103.40
0.5 no mason each 325.00 162.50
22 kg conveyance of Cement t 234.00 5.15
Total 10m2 271.05 298.15
Say Rs 271 /10m2 Rs. 298

PAINTING

551 White washing two coats


0.003 m3 quick lime m3 2200.00 6.60 7.26
0.003 m3 conveyance of lime m3 126.00 0.38 0.42
LS glue and other sundries LS 1.85 1.85
0.12 no special man each 255.00 30.60 33.66
0.12 no boy rach 180.00 21.60 23.76
Total 10m2 61.03 66.95
Say Rs 61 /10m2 Rs. 67

551 Colour washing two coats


0.003 m3 quick lime m3 2200.00 6.60 7.26
0.003 m3 conveyance of lime m3 126.00 0.38 0.42
LS glue and other sundries LS 1.85 1.85
LS add rate fir colour LS 3.10 3.10
0.12 no special man each 255.00 30.60 33.66
0.12 no boy rach 180.00 21.60 23.76
Total 10m2 64.13 70.05

Page 44
Say Rs 64 /10m2 Rs. 70

555 White washing with white cement one coat to


a walls
1.48 kg white Cement kg 15.00 22.20
sundries LS 0.60
0.12 n o special man each 255.00 30.60
0.12 boy each 180.00 21.60
1.48 kg conveyance of cement t 234.00 0.35
75.35 82.88
Say Rs 75.50 /10m2 Rs. 83

555
b White washing with white cement two coat to walls
2.48 kg whiteCement kg 15.00 37.20
sundries LS 0.60
0.2 n o special man each 255.00 51.00
0.2 boy each 180.00 36.00
2.48 kg conveyance of cement t 234.00 0.58
125.38 137.92
Say Rs 125 /10m2 Rs. 138

557+558 Painting with oil bond distember two coat to new


wall
1.5 kg oil bond distember kg 68.00 102.00
sundries for breshes etc LS 3.7
0.5 no painter each 270.00 135.00
240.70 264.77
Say Rs 241 /10m2 Rs. 265

559 Painting with oil bond distember one coat to old


wall
0.6 kg oil bond distember kg 68.00 40.80
sundries for breshes etc LS 1.85
0.25 no painter each 270.00 67.50
110.15 121.17
Say Rs 110 /10m2 Rs. 121

560
Painting with water proof cement paint two coats
to the new walls
3.2 kg water proof cement paint kg 24.00 76.80
LS sundries LS 3.10
0.5 no painter each 270.00 135.00
0.7 no woman each 240.00 168.00
Total 10m2 382.90 421.19
Say Rs 383.00 /10m2 Rs. 421

561 Painting with water proof cement paint one coats


to the old walls
1.4 kg water proof cement paint kg 24.00 33.60
LS sundries LS 1.85
0.25 no painter each 270.00 67.50

Page 45
0.25 no woman each 240.00 60.00
Total 10m2 162.95 179.25
Say Rs 163.00 /10m2 Rs. 179

PAINTING

601 Scraping and cleaning old painted surface with


sand paper
1 no man each 240.00 240.00 264.00
sundries LS 1.85 1.85
241.85 265.85
Say Rs 242.00 /10m2 Rs. 266.00

603
Painting priming coat on new wood work after
rubbing with sand paper and cleaning the surface
0.85 ltr wood primer ltr 85.00 72.25 79.48
LS sundries-bresh,sand paper,soap,putty etc LS 1.85 1.85
0.4 no painter each 270.00 108.00 118.80
Total 10m2 182.10 200.13
Say Rs 183.00 /10m2 Rs. 201.00

604
Painting priming coat on new iron work after
rubbing with emery paper and cleaning the surface
0.75 ltr iron primer ltr 85.00 63.75 70.13
LS sundries-bresh,sand paper,soap,putty etc LS 2.50 2.50
0.4 no painter each 270.00 108.00 118.80
Total 10m2 174.25 191.43
Say Rs 175.00 /10m2 Rs. 191

607 Painting with ready mixed paint of approved colour


&60 and quality as specified, two coat(over apriming
6 coat already done) to new wood work
1.65 ltr ready mixed paint ltr 126.00 207.90 228.69
LS sundries-bresh,sand paper,soap,putty etc LS 1.25 1.25
0.45 no painter each 270.00 121.50 133.65
Total 10m2 330.65 363.59
Say Rs 331.00 /10m2 Rs. 364.00

607
Painting with ready mixed paint of approved colour
a
and quality as specified, two coat including a
priming coat to new wood work
10 m2 priming coat (603) 10m2 182.10 182.10
10 m2 Painting,two coat(607) 10m2 330.65 330.65
Total 10m2 512.75 564.03
Say Rs 513 /10m2 Rs. 564

608 Painting with ready mixed paint of approved colour


and quality as specified, for one coat to old wood
work
0.75 ltr ready mixed paint ltr 126.00 94.50 103.95
LS sundries-bresh,sand paper,soap,putty etc LS 1.85 1.85

Page 46
0.25 no painter each 270.00 67.50 74.25
Total 10m2 163.85 180.05
Say Rs 164.00 /10m2 Rs. 181.00

609 Painting with Aluminium paint of approved colour


&61 and quality as specified, two coat(over apriming
0 coat already done) to new iron work
1.75 ltr alumunium paint ltr 150.00 262.50 288.75
LS sundries-bresh,sand paper,soap,putty etc LS 1.85 1.85
0.45 no painter each 270.00 121.50 133.65
Total 10m2 385.85 424.25
Say Rs 386 /10m2 Rs. 425.00

611 Painting with Aluminium paint of approved colour


and quality as specified, for one coat to old iron
work
0.8 ltr alumunium paint ltr 150.00 120.00 132.00
LS sundries-bresh,sand paper,soap,putty etc LS 1.50 1.50
0.25 no painter each 270.00 67.50 74.25
Total 10m2 189.00 207.75
Say Rs 189 /10m2 Rs. 208.00

612
$61
Painting with synthetic enamal paint of approved
3
colour and quality as specified, two coat(over
apriming coat already done) to new wood work
1.15 ltr synthetic enamal paint ltr 162.00 186.30 204.93
LS sundries-bresh,sand paper,soap,putty etc LS 3.35 3.35
1.1 no painter each 270.00 297.00 326.70
Total 10m2 486.65 534.98
Say Rs 487 /10m2 Rs. 535

614 Painting with synyhetic enamal paint of approved


colour and quality as specified, for one coat to old
wood work
0.5 ltr synthetic enamal paint ltr 162.00 81.00 89.10
LS sundries-bresh,sand paper,soap,putty etc LS 1.85 1.85
0.5 no painter each 270.00 135.00 148.50
Total 10m2 217.85 239.45
Say Rs 218.00 /10m2 Rs. 239

612
a Painting with synthetic enamal paint of approved
colour and quality as specified, two coat including
a priming coat to new wood work
10 m2 priming coat (603) 10m2 182.10 182.10
10 m2 Painting,two coat(612) 10m2 486.65 486.65
Total 10m2 668.75 735.63
Say Rs 669.00 /10m2 Rs. 736

Page 47
612b
Painting with synthetic enamal paint of approved
colour and quality as specified, two coat(over
apriming coat already done) to new iron work
1.75 ltr synthetic enamal paint ltr 162.00 283.50 311.85
LS sundries-bresh,sand paper,soap,putty etc LS 1.85 1.85
0.45 no painter each 270.00 121.50 133.65
Total 10m2 406.85 447.35
Say Rs 407 /10m2 Rs. 448.00

612 Painting with synthetic enamal paint of approved


c colour and quality as specified, for one coat to old
iron work
0.8 ltr synthetic enamal paint ltr 162.00 129.60 142.56
LS sundries-bresh,sand paper,soap,putty etc LS 1.85 1.85
0.25 no painter each 270.00 67.50 74.25
Total 10m2 198.95 218.66
Say Rs 199.00 /10m2 Rs. 219.00

612
d Painting with synthetic enamal paint of approved
colour and quality as specified, two coat including
a priming coat to new iron work
10 m2 priming coat (604) 10m2 174.25 174.25
10 m2 Painting,two coat(612b) 10m2 406.85 406.85
Total 10m2 581.10 639.21
Say Rs 581 /10m2 Rs. 639.21

615
Painting with plastic emulsion paint of approved
colour and quality as specified, two coat including
a priming coat to new plastered surface
1.15 ltr plastic emulsion paint including primin ltr 180.00 207.00 227.70
LS sundries-bresh,sand paper,soap,putty etc LS 3.10 3.10
1.15 no painter each 270.00 310.50 341.55
Total 10m2 520.60 572.35
Say Rs 521 /10m2 Rs. 572

615 Painting with plastic emulsion paint of approved


a colour and quality as specified, one coat to old
surface
0.4 ltr plastic emulsion paint ltr 180.00 72.00 79.20
LS sundries-bresh,sand paper,soap,putty etc LS 1.85 1.85
0.4 no painter each 270.00 108.00 118.80
Total 10m2 181.85 199.85
Say Rs 182 /10m2 Rs. 200.00

619 Varnishing with Copal varnish two coat after


a rubbing with sand paper and cleaning the new wood
surface
0.8 ltr copal varnish ltr 105.00 84.00 92.40
LS sundries-bresh,sand paper,soap,putty etc LS 1.85 1.85
1 no painter each 270.00 270.00 297.00

Page 48
Total 10m2 355.85 391.25
Say Rs 356 /10m2 Rs. 392.00

621 Varnishing with Cpval varnish one coat after


rubbing with sand paper and cleaning the old wood
surface
0.35 ltr copal varnish ltr 105.00 36.75 40.43
LS sundries-bresh,sand paper,soap,putty etc LS 1.85 1.85
0.45 no painter each 270.00 121.50 133.65
Total 10m2 160.10 175.93
Say Rs 160 /10m2 Rs. 176

625 Painting with Black japan paint one coat to the


external surface
1.4 ltr black japan paint ltr 57.00 79.80 87.78
LS sundries-bresh,sand paper,soap,putty etc LS 1.25 1.25
0.5 no painter each 270.00 135.00 148.50
Total 10m2 216.05 237.53
Say Rs 216 /10m2 Rs. 238

628
Painting letters or figures 6.5, 8, 10cms height with
any kind of paints. Detailsof cost of 100 letters
0.45 ltr synthetic enamel paint of approved qualtr 162.00 72.9
Breshers LS 3.1
scaffolding LS 18.75
4.5 no painter each 270.00 1215
1.5 no man each 240.00 360
1669.75 1836.73
for average cost of each letters 16.6975 18.37
Say Rs 17 /each Rs. 18

629
Painting letters or figures 13, 15, 18cms height
with any kind of paints. Detailsof cost of 100 letters
0.6 ltr synthetic enamel paint of approved qualtr 162.00 97.2
Breshers LS 3.1
scaffolding LS 18.75
7 no painter each 270.00 1890
2 no man each 240.00 480
2489.05 2737.96
for average cost of each letters 24.8905 27.38
Say Rs 25 /each Rs. 27

630
Painting letters or figures 23, 25, 30cms height
with any kind of paints. Detailsof cost of 100 letters
synthetic enamel paint of approved
0.9 ltr quality ltr 162.00 145.8
Breshers LS 3.1
scaffolding LS 18.75
10 no painter each 270.00 2700
2 no man each 240.00 480
3347.65 3682.42

Page 49
for average cost of each letters 33.4765 36.82
Say Rs 33 /each Rs. 37

STEEL WORK

754
Steel work revetted or bolted in built up sections
trusses and framed work with MS angles, iron
plates, tees, etc. straightening, cutting, fabricating,
and hoisting including applying a coat of iron
priming
1.05 qtl cost of MS angles, plates, tees, channqtl 3800.00 3990.00
2 kg revets, nuts and bolts of sutable size
and length kg 60.00 120.00
3 m2 applying iron primer one coat 10m2 174.25 52.28
0.5 no blacksmith each 325.00 162.50
0.2 no heavy load mazdoor each 270.00 54.00
0.3 no fitter each 300.00 90.00
0.1 no heavy load mazdoor for cuttiung each 270.00 27.00
1.25 no blacksmith each 325.00 406.25
1.5 no heavy load mazdoor for punching holeeach 270.00 405.00
0.5 no blacksmith each 325.00 162.50
0.5 no heavy load mazdoor for revitting each 270.00 135.00
0.5 no blacksmith each 325.00 162.50
0.5 no heavy load mazdoor for revitting each 270.00 135.00
LS charcoal and hire for other appliances LS 5.00 15.00
LS hoisting and errecting in position LS 37.50 37.50
1.05 qtl conveyance of MS steel T 234.00 24.57
Total T 5979.10 6577.00
Say Rs 5979 /Qtl 6578.00

754
a Providing tubular truss with 65mm GI pipe (B
class) including cost and conveyance of all
materials , labour charges, scaffolding, errection
charges, hire of tools and plants etc complete,
including one coat of iron primer
63mm dia GI pipe for truss B class 1m
1 m 63mmGI pipe for truss m 230.00 230.00
L.S Labour for fabrication and errection L.S 40.00
L.s Hire of machinery & current charges L.S 20.00
0.2 m2 Iron primer 10m2 85.00 1.70
L.s Scaffolding & welding roads etc LS 10.00
301.70 331.87
Say Rs 302 /m Rs. 332

754
b 50mm dia. GI pipe for purline B class 1m
1 m 50mm dia.GI pipe for truss m 185.00 185.00
L.S Labour for fabrication and errection L.S 30.00
L.s Hire of machinery & current charges L.S 15.00
0.157 m2 Iron primer 10m2 85.00 1.33
L.s Scaffolding & welding roads etc L.S 6.00
237.33 261.07

Page 50
Say Rs 237 /m Rs. 261

754
c 40 mm dia. GI pipe B class 1m
1 m 40 mm dia.GI pipe for truss m 154.00 154.00
L.S Labour for fabrication and errection L.S 25.00
L.s Hire of machinery & current charges L.S 12.00
0.125 m2 Iron primer 10m2 85.00 1.06
L.s Scaffolding & welding roads etc L.S 5.00
197.06 216.77
Say Rs 197 /m Rs. 217

754
d 25 mm dia. GI pipe B class 1m
1 m 25 mm dia.GI pipe for truss m 110.00 110.00
L.S Labour for fabrication and errection L.S 22.00
L.s Hire of machinery & current charges L.S 10.00
0.1 m2 Iron primer 10m2 85.00 0.85
L.s Scaffolding & welding roads etc L.S 4.00
146.85 161.54
Say Rs 147 /m Rs. 162
755
Providing MS grills for window and compound
gates including all labour, hire charges for
fabricating and cost of all materials and applying a
coat of iron primer
1.05 qtl cost of MS square or round, qtl 3250.00 3412.50
100 no welding rods,8g 100no 420.00 420.00
5 m2 applying iron primer one coat 10m2 174.25 87.13
2.5 no blacksmith for leveling each 325.00 812.50
1.25 no blacksmith for cutting each 325.00 406.25
1.0 no heavy load man mazdoor for helping each 270.00 270.00
1.0 no welder each 325.00 325.00
1.0 no heavy load man mazdoor for welding each 270.00 270.00
2.5 no blacksmith for grinding each 325.00 812.50
1.05 qtl conveyance of steel t 234.00 24.57
currient charge, hire for welding plant LS 37.50
sundries LS 50.00
grinding stones LS 25.00
6952.95 7648.24
Say Rs 6953 /m Rs. 7648

763

Supplying and fixing rolling shutters of appoved


make and painted with a priming coat of iron primer,
made of 80x1.25mm MS laths interlocking together
through their entire length and jointed together at
the end by end locks mounted on specially
designed pipe shaft with brackets, side guides and
arrangements for inside and outside locking with
push and pull operation etc complete.
10 dm2 rolling shutter m2 1400.00 140.00
0.03 no fitter each 300.00 9.00
0.03 no man each 240.00 7.20
0.03 no mason each 325.00 9.75

Page 51
Total 10dm2 165.95 182.55
Say Rs. 166 /10dm2 Rs. 183.00

763
a Supplying and fixing top cover to rolling shutter
1 m top cover m 450.00 450.00
LS for conveyance and fitting LS 10.00
Total m 460.00 506.00
Say 460.00 /m 506.00

763
b Supplying and fixing steel collapsible grill of
appoved make and painted with a priming coat of
iron primer, interlocking together through their
entire length and jointed together at the end by end
locks with brackets, side guides and arrangements
for inside and outside locking with push and pull
operation etc complete.
10 dm2 collapsible grill m2 1400.00 140.00
0.03 no fitter each 300.00 9.00
0.03 no man each 240.00 7.20
0.03 no mason each 325.00 9.75
Total 10dm2 165.95 182.55
Say Rs. 166 /10dm2 Rs. 183.00

Supplying and Fixing Fabricated sign board of size


90 X 60 triangle on the road way whereever necessary
with 16 gauge MS sheet in 75 x 75 x 6 mm frames and
post for supporting the board. Fixing the board with MS
Channel using bolt and nut and fixing the board in cement
concrete 1:4:8 (using 40mm broken stone) blocks of size
45 x 45, 40cm with bottom level of board at 180 cm above
ground level applying 2 coat of required paint over a coat
of iron primer including all labour and hire charges for
fabricating and cost of materil etc complete
I. Material
0.204 Qtl 75 x 75 x 6 mm Angle(3x6.8kg/m) Qtl 4087.00 833.75 917.12
Cutting Charges LS 20.00 20.00
0.134 Qtl MS Sheet(0.54m2x24.75kg/m2) Qtl 4087.00 547.66 602.42
Earth Work in ord. soil, 0.45 x 0.45 x
0.091 m3 45 10m3 562.80 5.12 5.63
0.091 m3 CC 1:4:8 m3 2625.32 238.90 262.79
1.600 m2 Priming Coat 10m2 140.65 22.50 24.75
1.600 m2 Synthetic Enamel paint 10m2 369.05 59.05 64.95
Conveyance of Board to site and
fixing position including 'U' Clamp LS 40.00 40.00
1766.98 1943.68
Say Rs 1767.00 /each Rs 1944.00

SANITARY

Page 52
855
a

Supplying and fixing 550x400mm or nearest size


wash hand basin of white glazed eartherenware,
Indian make, bst quality with CI brackets painted
white ,one central 15mm CP brass pillar tap, 1 no.
15mm PVC connection with brass union, 1 no.
15mm GM wheel valve, rubber plug and CP brass
chain 32mm, 32mm PVC waste pipe with access
cap, etc, complete including cutting and making
ghood the walls, painting the brackets and waste
connection with sutable paint two coats, etc comple
1.0 no. 550x400mm basin each 480.00 480.00
1.0 no. 15mmCP brass pillor tap each 242.00 242.00
1.0 no. 15mm GM wheel valve each 171.00 171.00
1.0 no. 15mm PVC connection with union(hea each 44.00 44.00
1.0 no. CP brass chain with 32mm rubber plug each 117.00 117.00
1.0 no. 32mm PVC waste each 58.00 58.00
1.0 pair CI brackets pair 55.00 55.00
sundies LS 11.25
2.0 kg cement t 4700.00 9.40
0.5 no. plumber each 325.00 162.50
1.0 man each 240.00 240.00
0.5 mason each 325.00 162.50
Total each 1752.65 1927.92
Say Rs. 1753 /Each Rs 1928.00

855
b Supplying and fixing Stainless steel sink (1mm
thick sheet) of over all size 510x432x165mm with
cuppling and stainer
1 no Stainless steel sink (1mm thick
sheet) of over all size
510x432x165mm each 1606.00 1606.00
1.5 kg cement t 4700.00 7.05
0.25 no. plumber each 325.00 81.25
0.25 no. mason each 325.00 81.25
1775.55 1953.11
Say Rs. 1776 /Each Rs 1953

860
Supplying and fixing Indian type white glazed
earthernware WC 580x400 mm or nearest siuze
with P ro S trap, embedding in brick jelly concrete,
with a pair of porcelane foot rest and forming
squattiung platform 900x700mm plastered with
cement mortar 1:3 with neat cement flushing coat ,
including cutting and making good the wall, floors,
etc complete
1 no. wihite glazed IWC with trap each 484.00 484.00
1 pair foot rest pair 96.00 96.00
LS birick jelly concrete, and other
sundries LS 30.00
7 kg cement T 4700.00 32.90

Page 53
0.6 no. mason each 325.00 195.00
0.6 no. man each 240.00 144.00
Total each 981.90 1080.09
Say Rs. 982 /Each Rs 1080

860
a
Supplying and fixing Indian type white glazed
earthernware WC orissa pan 530x400mm or
nearest siuze with P ro S trap, embedding in brick
jelly concrete and forming squattiung platform
900x700mm plastered with cement mortar 1:3 with
neat cement flushing coat , including cutting and
making good the wall, floors, etc complete
1 no. wihite glazed orissa pan IWC with trap each 600.00 600.00
LS birick jelly concrete, and other
sundries LS 30.00
7 kg cement T 4700.00 32.90
0.6 no. mason each 325.00 195.00
0.6 no. man each 240.00 144.00
Total each 1001.90 1102.09
Say Rs. 1002 /Each Rs 1102

861
Supplying and fixing European type white glazed
earthernware WC with P ro S trap, and plastic
seatcover with hinges and rubber bufer ,including
cutting and making good the wall, floors, etc
complete
1 no glazed EWC with trap each 634.00 634.00
1 no seat cover each 232.00 232.00
sundries for plug, screws etc, LS 7.50
2 kg cement kg 4.70 9.40
0.3 no mason each 325.00 97.50
0.3 no man each 240.00 72.00
1052.40 1157.64
Say Rs. 1052 /Each Rs 1158

862 Supplying and fixing high quality PVC automatic


a low level flush tank with necessary screws and
fittings, including 15mm GM wheel valve with 15mm
PVC connection etc complete
1 no 5ltr PVC low level flush tank each 791.00 791.00
1 no 15mm GM wheel valve each 171.00 171.00
1 no 15mm PVC connection each 44.00 44.00
0.25 no fitter/plumber each 325.00 81.25
0.2 no man each 240.00 48.00
1135.25 1248.78
Say Rs. 1136.00 /Each Rs 1249.00

Page 54
854
Supplying and fixing white glazed earthernware flat
back, lipped front, urinal of size 430x260x350mm ,
15mm GM wheel valve with 15mm PVC connection
and 32mm PVC wastage pipe with brass union,
including cutting and making good the wall
1 no flat back, lipped front urinal each 368.00 368.00
1 no 15mm GM wheel valve each 171.00 171.00
1 no 15mmPVC connection each 44.00 44.00
1 no 32mm PVC waste pipe each 58.00 58.00
sundries for conveyance,screws ,plugs etc. LS 7.50
2 kg cement kg 4.70 9.40
0.5 no mason each 228.00 114.00
0.5 no man each 168.00 84.00
855.90 941.49
Say Rs. 856.00 /Each Rs 941

WATER SUPPLY
883
Supplying threading and jointing 20mm dia PVC
pipe and specials such as tees, bends, elbows,
checknuts etc, with clamps including cutting and
making good the walls, painting with suitable paint
two coat, etc complete.(Internal)
Details for 30m.
30 m 20mm PVC threaded pipe (10kgf/cm2)m 11.00 330.00 363.00
add 15%for specials 49.50 54.45
LS clamp, cement ,paint etc LS 15.00 15.00
2 no. fitter each 210.00 420.00 462.00
2 no. man each 168.00 336.00 369.60
Total 1150.50 1264.05
Hence m 38.35 42.14
Say Rs. 38.50 /m Rs. 42.00

883
Supplying threading and jointing 25mm dia PVC
a
pipe and specials such as tees, bends, elbows,
checknuts etc, with clamps including cutting and
making good the walls, painting with sutable paint
two coat, etc complete.(Internal)
Details for 30m.
30 m 25mm PVC threaded pipe (10kgf/cm2)m 15.00 450.00 495.00
add 15%for specials 67.50 74.25
LS clamp, cement ,paint etc LS 15.00 15.00
2 no. fitter each 210.00 420.00 462.00
2 no. man each 168.00 336.00 369.60
Total 1288.50 1415.85
Hence m 42.95 47.20
Say Rs. 43 /m Rs. 47.00
884 30 m
Supplying and laying 40mm dia PVC pipe with
fittings such as tees, elbows, bends, checknuts,
etc.including trenching to a minimum depth of 0.5m.
And refilling etc, complete(External)

Page 55
30 m 40mm PVCpipe (8kgf/cm2) m 28.00 840.00 924.00
add 5% specials 42.00 46.20
0.5 no. fitter each 210.00 105.00 115.50
0.5 no. man each 168.00 84.00 92.40
3 no. man for tnching each 168.00 504.00 554.40
L.S 3.75 3.75
Total 1578.75 1736.25
hence for 1m m 52.63 57.88
Say Rs. 52.50 /m Rs. 58.00

884 30 m
a
Supplying and laying 110mm dia PVC pipe with
fittings such as tees, elbows, bends, checknuts,
etc.including trenching to a minimum depth of 0.5m.
And refilling etc, complete(External)
30 m 110mm PVCpipe (8kgf/cm2) m 204.00 6120.00
add 5% specials 306.00
0.5 no. fitter each 210.00 105.00
0.5 no. man each 168.00 84.00
3 no. man for tnching each 168.00 504.00
Total 7119.00
hence for 1m m 237.30 261.03
Say Rs. 237 /m Rs. 261

884 Supplying and fixing best quality 25mm


b unbreakable PVC ball valve
1 no. 25mm unbreakable PVC ball valve each 34.00 34.00 37.40
fitting charges, gum etc LS 7.50 7.50
41.50 44.90
Say Rs.41.50 /Each Rs.45

884 Supplying and fixing best quality CP shower rose,


b adjustable type
1 no. CP shower rose, adjustable type each 226.00 226.00 248.60
fitting charges, gum etc LS 10.00 10.00
236.00 258.60
Say Rs.236 /Each Rs.259

884 Supplying and fixing best quality Brass and gun


b metal 15mm SDB tap
1 no.
Brass and gun metal 15mm SDB tap each 148.00 148.00 162.80
fitting charges, gum etc LS 5.00 5.00
153.00 167.80
SayRs. 153.00 /Each Rs. 168

Supplying and fixing best quality Brass and gun


metal 20mm stop cock
1 no. Brass and gun metal 20mm stop
cock each 256.00 256.00 281.60
fitting charges, gum etc LS 5.00 5.00
261.00 286.60
Say Rs.261 /Each Rs.287

Page 56
Supplying and fixing best quality 110mm steel
grating to toilet floor
1 no. 110mm steel grating to toilet floor each 16.15 16.15 17.77
fitting charges, gum etc LS 3.00 3.00
19.15 20.77
Say Rs.19 /Each Rs.21

884 30 m
.c Supplying and fixing 40mm dia PVC pipe with
specials for septic tank ventilator(External)
1 m 40mm PVCpipe (8kgf/cm2) m 28.00 28.00 30.80
add 5% specials 1.40 1.54
fitting charges, gum etc LS 2.00 2.00
Total 31.40 34.34
Say Rs.31.50 /m Rs.34.50

ROAD WORK (IRC Specification)

651 Sectioning upto150mm and forming the surface for


new work
0.5 no. man each 240.00 120.00 132.00
Say Rs 120.00 /10m2 Rs. 132.00

652 Sectioning upto150mm and forming the surface for


old work
0.25 no. man each 240.00 60.00 66.00
Say Rs 60.00 /10m2 Rs. 66

653 Picking 50mm to 100mm old matelled surface and


sectioning
0.5 no. man each 240.00 120.00 132.00
Say Rs 120.00 /10m2 Rs. 132.00

659 Forming and consolidatioin sides of the road 1m


wide on either side of the road and gravelling to the
same sectioin
1.40 M3 earth in hard soil 10m3 1314.00 183.96
1.40 M3 consolidation by ramming (Vide item no.67) 74.16 10.38
194.34 213.78
Say Rs 194 /10m Rs. 214

Earth work
1.2 IRC Forming Embankment
Extra charges for compaction with Power Roller
10m3
0.027 Day Hire charges of roller day 2080.00 56.16
0.5 Liter Diesel oil lit 36.00 18
74.16 81.58
Say Rs 75.00 /10m2 Rs. 82

1.3 IRC Preparation of subgrade

Page 57
0.027 Day Hire charges of roller day 2080.00 56.16
0.5 Liter Diesel oil lit 36.00 18
74.16 81.58
Say Rs 75.00 /10m2 Rs. 82

a
Supplying and stacking 60mm( 70% of 60mm and
30%of 36mm) graded metal for measurements
0.7 m3 60mm broken stone m3 410.00 287.00
0.3 m3 36mm broken stone m3 510.00 153.00
1.0 m3 conveyance of metal m3 499.00 499.00
939.00 1032.90
Say Rs 939.00 /10m2 Rs. 1033

b Supplying and stacking 36mm metal for


measurements
1.0 m3 36mm broken stone m3 510.00 510.00
1.0 m3 conveyance of metal m3 499.00 499.00
1009.00 1109.90
Say Rs 1009.00 /10m2 Rs. 1110

c Supplying and stacking 12mm metal for


measurements
1.0 m3 12mm broken stone m3 740.00 740.00
1.0 m3 conveyance of metal m3 499.00 499.00
1239.00 1362.90
Say Rs 1239.00 /10m2 Rs. 1363

d Supplying and stacking 6mm metal for


measurements
1.0 m3 6mm broken stone m3 520.00 520.00
1.0 m3 conveyance of metal m3 499.00 499.00
1019.00 1120.90
Say Rs 1019.00 /10m2 Rs. 1121

e Supplying and stacking red earth blinding material


for measurements
1.0 m3 red earth m3 125.00 125.00
1.0 m3 conveyance of red earth m3 257.00 257.00
382.00 420.20
Say Rs 382.00 /10m2 Rs. 420

2.1.2
Sub base work:- Metalling the road way 100mm
spreaded thickness compacted to 75mm using
deptl. broken stones (graded in the ratio of 7:3 of
60mm and 36mm size)
0.67 no. man for spreading each 240.00 160.80 176.88
0.67 no. women for spreading each 240.00 160.80 176.88
0.67 no. boy for spreading each 180.00 120.60 132.66
0.012 day hire of roller day 2080.00 24.96 24.96
0.22 ltr diesel ltr 36.00 7.92 8.71
sundries LS 1.85 1.85
476.93 521.94
Say Rs 477 /10m2 Rs. 522

Page 58
2.2.2 Base course work:- Metalling the road way
100mm spreaded thickness compacted to 75mm
using 36mm deptl. broken stones
0.67 no. man for spreading each 240.00 160.80 176.88
0.67 no. women for spreading each 240.00 160.80 176.88
0.67 no. boy for spreading each 180.00 120.60 132.66
0.012 day hire of roller day 2080.00 24.96 24.96
0.22 ltr diesel ltr 36.00 7.92 8.71
sundries LS 1.85 1.85
476.93 521.94
Say Rs 477 /10m2 Rs. 522

2.3.2 Remetalling the road way with deptl broken stones


and blinding materials (new stones supplied at
0.5m3 for 10m2 and blinding material at 0.12m3 for
10m2)
0.5 no man for picking old matel each 240.00 120.00 132.00
0.35 no man for spreading matel each 240.00 84.00 92.40
0.35 no women for spreading matel each 240.00 84.00 92.40
0.35 no boy for spreading matel each 180.00 63.00 69.30
0.012 day hire of roller day 2080.00 24.96 24.96
0.22 ltr diesel ltr 36.00 7.92 8.71
sundries LS 1.85 1.85
385.73 421.62
Say Rs 386.00 /10m2 Rs. 422.00

3.1.1.2 Leveling undulatioins less than 20mm with 12mm


deptl broken stone, premixed with 48kg of bitumen
for 1m3 of matel including hire of all tools and plants
etc complete
0.03 day hire of boiler and sprayer day 100.00 3.00 3.00
0.03 day hire of mini hot mix plant day 830.00 24.90 24.90
0.09 day Hire for wheel barrows day 3.50 0.32 0.32
1 ltr diesel for HM plant ltr 36.00 36.00 39.60
2.7 ltr kerosene for heating aggregate ltr 26.00 70.20 77.22
2 ltr kerosene for heating bitumen ltr 26.00 52.00 57.20
sundries LS 1.35 1.35
48 kg bitumen kg 35.927 1724.50 1724.50
48 kg conveyance of bitumen T 459.00 22.03 24.24
1.8 no spical man each 255.00 459.00 504.90
0.75 no women each 240.00 180.00 198.00
sundries LS 1.35 1.35
2574.64 2656.57
Say Rs 2575 /m3 Rs. 2657
Except cost and conveyance of Bitumen
3.1.1.2
Leveling undulatioins less than 20mm with 12mm
deptl broken stone, premixed with 48kg of bitumen
for 1m3 of matel including hire of all tools and plants
etc complete
0.03 day hire of boiler and sprayer day 100.00 3.00 3.00
0.03 day hire of mini hot mix plant day 830.00 24.90 24.90
0.09 day Hire for wheel barrows day 3.50 0.32 0.32
1 ltr diesel for HM plant ltr 36.00 36.00 39.60

Page 59
2.7 ltr kerosene for heating aggregate ltr 26.00 70.20 77.22
2 ltr kerosene for heating bitumen ltr 26.00 52.00 57.20
sundries LS 1.35 1.35
1.8 no spical man each 255.00 459.00 504.90
0.75 no women each 240.00 180.00 198.00
sundries LS 1.35 1.35
828.12 907.84
Say Rs 828 /m3 Rs. 908

3.1.3.2

Providing bitumens leveling course using 36mm


deptl. broken stone by spreading in line and levels
and rolling until the compacted course aggregate
has a firm surface and applying hot bitumen with
sprayer at the rate of 20kg/m3 including cost of
bitumen, all conveyance, heating, mixing, spreading
in approprite locations to proper levels, compacting
with power roller and all other sundries
0.022 day hire of roller day 2080.00 45.76 45.76
0.022 day hire of boiler and sprayer day 100.00 2.20 2.20
0.066 day Hire for wheel barrows day 3.50 0.23 0.23
0.4 ltr diesel for roller ltr 36.00 14.40 15.84
0.8 ltr kerosene ltr 26.00 20.80 22.88
1 no spical man each 255.00 255.00 280.50
0.5 no women each 240.00 120.00 132.00
20 kg bitumen kg 35.927 718.54 718.54
20 kg conveyance of bitumen T 459.00 9.18 10.10
sundries LS 1.35 1.35
1187.46 1229.40
Say Rs 1187 /m3 Rs. 1229

Except cost and conveyance of Bitumen


3.1.3.2

Providing bitumens leveling course using 36mm


deptl. broken stone by spreading in line and levels
and rolling until the compacted course aggregate
has a firm surface and applying hot bitumen with
sprayer at the rate of 20kg/m3 except cost of
bitumen, all conveyance, heating, mixing, spreading
in approprite locations to proper levels, compacting
with power roller and all other sundries
0.022 day hire of roller day 2080.00 45.76 45.76
0.022 day hire of boiler and sprayer day 100.00 2.20 2.20
0.066 day Hire for wheel barrows day 3.50 0.23 0.23
0.4 ltr diesel for roller ltr 36.00 14.40 15.84
0.8 ltr kerosene ltr 26.00 20.80 22.88
1 no spical man each 255.00 255.00 280.50
0.5 no women each 240.00 120.00 132.00
sundries LS 1.35 1.35

459.74 500.76
Say Rs 460 /m3 Rs. 501

Page 60
3.2.2 Providing 20mm premixed chipping carpet over
WBM surfacewith deptal. broken stone (Total usage
of bitumen is 29.1kg/10m2)
Data for 100m2
0.12 day hire of boiler and sprayer day 100.00 12.00 12.00
0.12 day hire of roller day 2080.00 249.60 249.60
0.12 day hire of hot mix plant day 830.00 99.60 99.60
0.36 day Hire for wheel barrows day 3.50 1.26 1.26
2.2 ltr diesel for roller ltr 36.00 79.20 87.12
4 ltr diesel for HM plant ltr 36.00 144.00 158.40
10.8 ltr kerosene for heating aggregate ltr 26.00 280.80 308.88
11.6 ltr kerosene for heating bitumen ltr 26.00 301.60 331.76
291 kg bitumen kg 35.927 10454.76 10454.76
291 kg conveyance of bitumen T 459.00 133.57 146.93
7.5 no spical man each 255.00 1912.50 2103.75
3 no women each 240.00 720.00 792.00
sundries LS 5.00 5.00
14393.89 14751.05
for 10m2 1439.39 1475.11
Say Rs 1440.00 /10m2 Rs. 1476.00

Except cost and conveyance of Bitumen


3.2.2 Providing 20mm premixed chipping carpet over
WBM surfacewith deptal. broken stone (Total usage
of bitumen is 29.1kg/10m2)
Data for 100m2
0.12 day hire of boiler and sprayer day 100.00 12.00 12.00
0.12 day hire of roller day 2080.00 249.60 249.60
0.12 day hire of hot mix plant day 830.00 99.60 99.60
0.36 day Hire for wheel barrows day 3.50 1.26 1.26
2.2 ltr diesel for roller ltr 36.00 79.20 87.12
4 ltr diesel for HM plant ltr 36.00 144.00 158.40
10.8 ltr kerosene for heating aggregate ltr 26.00 280.80 308.88
11.6 ltr kerosene for heating bitumen ltr 26.00 301.60 331.76
7.5 no spical man each 255.00 1912.50 2103.75
3 no women each 240.00 720.00 792.00
sundries LS 5.00 5.00
3805.56 4149.37
for 10m2 380.56 414.94
Say Rs 381 /10m2 Rs. 415

3.2.2.a Providing 20mm premixed chipping carpet over


BT surface with deptal. broken stone (Total usage
of bitumen is 26.6kg/10m2)
Data for 100m2
0.12 day hire of boiler and sprayer day 100.00 12.00 12.00
0.12 day hire of roller day 2080.00 249.60 249.60
0.12 day hire of hot mix plant day 830.00 99.60 99.60
0.36 day Hire for wheel barrows day 3.50 1.26 1.26
2.2 ltr diesel for roller ltr 36.00 79.20 87.12
4 ltr diesel for HM plant ltr 36.00 144.00 158.40

Page 61
10.8 ltr kerosene for heating aggregate ltr 26.00 280.80 308.88
10.6 ltr kerosene for heating bitumen ltr 26.00 275.60 303.16
266 kg bitumen kg 35.927 9556.58 9556.58
266 kg conveyance of bitumen T 459.00 122.09 134.30
7.5 no spical man each 255.00 1912.50 2103.75
3 no women each 240.00 720.00 792.00
sundries LS 5.00 5.00
13458.24 13811.66
for 10m2 1345.82 1381.17
Say Rs 1346 /10m2 Rs. 1381

Except cost and conveyance of Bitumen


3.2.2.a
Providing 20mm premixed chipping carpet over
BT surface with deptal. broken stone (Total usage
of bitumen is 26.6kg/10m2)
Data for 100m2
0.12 day hire of boiler and sprayer day 100.00 12.00 12.00
0.12 day hire of roller day 2080.00 249.60 249.60
0.12 day hire of hot mix plant day 830.00 99.60 99.60
0.36 day Hire for wheel barrows day 3.50 1.26 1.26
2.2 ltr diesel for roller ltr 36.00 79.20 87.12
4 ltr diesel for HM plant ltr 36.00 144.00 158.40
10.8 ltr kerosene for heating aggregate ltr 26.00 280.80 308.88
11.6 ltr kerosene for heating bitumen ltr 26.00 301.60 331.76
7.5 no spical man each 255.00 1912.50 2103.75
3 no women each 240.00 720.00 792.00
sundries LS 5.00 5.00
3805.56 4149.37
for 10m2 380.56 414.94
Say Rs 381 /10m2 Rs. 415

3.6.1.2
Filling up pot holes (cut and formed to regular
shapes And all loose and defective materials
removed) after applying a priming coat of hot
bitumen using 36mm deptl broken stone and
com,pacting with power roller to get a compact
surface and applying hot bitumen by sprayer
including cost, hire and conveyance of all materials,
hire of tools and plants (total usage of bitumen is
27.5kg/m3)
0.03 day hire of boiler and sprayer day 100.00 3.00 3.00
0.03 day hire of roller day 2080.00 62.40 62.40
0.09 day Hire for wheel barrows day 3.50 0.32 0.32
0.5 ltr diesel for roller ltr 36.00 18.00 19.80
27.5 kg bitumen kg 35.927 987.99 987.99
11 kg fire wood T 3400.00 37.40 41.14
27.5 kg conveyance of bitumen T 459.00 12.62 13.88
1.75 no special man each 255.00 446.25 490.88
0.75 no man each 240.00 180.00 198.00
0.75 no women each 240.00 180.00 198.00
sundries LS 0.40 0.40
1928.38 2015.81

Page 62
Say Rs 1928 /m3 Rs. 2016

3.6.1.2
Filling up pot holes (cut and formed to regular
shapes And all loose and defective materials
removed) after applying a priming coat of hot
bitumen using 36mm deptl broken stone and
com,pacting with power roller to get a compact
surface and applying hot bitumen by sprayer
including cost, hire and conveyance of all materials,
hire of tools and plants (total usage of bitumen is
27.5kg/m3)
0.03 day hire of boiler and sprayer day 100.00 3.00 3.00
0.03 day hire of roller day 2080.00 62.40 62.40
0.09 day Hire for wheel barrows day 3.50 0.32 0.32
0.5 ltr diesel for roller ltr 36.00 18.00 19.80
11 kg fire wood T 3400.00 37.40 41.14
1.75 no special man each 255.00 446.25 490.88
0.75 no man each 240.00 180.00 198.00
0.75 no women each 240.00 180.00 198.00
sundries LS 0.40 0.40
927.77 1013.93
Say Rs 928.00 /m3 Rs. 1014

3.6.2.2

Filling up pot holes (cut and formed to regular


shapes And all loose and defective materials
removed) after applying a priming coat of hot
bitumen using 12mm deptl broken stone premixed
with bitumen and compacting with power roller to
get a compact surface and including cost and
conveyance of all materials, hire of tools and plants
(total usage of bitumen is 60kg/m3)
0.06 day hire of boiler and sprayer day 100.00 6.00 6.00
0.06 day hire of roller day 2080.00 124.80 124.80
0.18 day Hire for wheel barrows day 3.50 0.63 0.63
1 ltr diesel for roller ltr 36.00 36.00 39.60
60 kg bitumen kg 35.927 2155.62 2371.18
24 kg fire wood T 3400.00 81.60 89.76
60 kg conveyance of bitumen T 459.00 27.54 30.29
5 no special man each 255.00 1275.00 1402.50
0.5 no man each 240.00 120.00 132.00
2 no women each 240.00 480.00 528.00
sundries LS 0.40 0.40
4307.59 4725.17
Say Rs 4308.00 /m3 Rs. 4725

Page 63
3.6.2.2

Filling up pot holes (cut and formed to regular


shapes And all loose and defective materials
removed) after applying a priming coat of hot
bitumen using 12mm deptl broken stone premixed
with bitumen and compacting with power roller to
get a compact surface and including cost and
conveyance of all materials, hire of tools and plants
(total usage of bitumen is 60kg/m3)
0.06 day hire of boiler and sprayer day 100.00 6.00 6.00
0.06 day hire of roller day 2080.00 124.80 124.80
0.18 day Hire for wheel barrows day 3.50 0.63 0.63
1 ltr diesel for roller ltr 36.00 36.00 39.60
24 kg fire wood T 35.93 0.86 0.95
5 no special man each 255.00 1275.00 1402.50
0.5 no man each 240.00 120.00 132.00
2 no women each 240.00 480.00 528.00
sundries LS 0.40 0.40
2043.69 2234.88
Say Rs 2044.00 /m3 Rs. 2235

Deepening of well
63

Earth work excavation in ordinary soil for deepening


the well upto 2.5m dia.and depositing on the bank
with initial leads and lift of 1.5m
1.10 no man each 168.00 184.80
3.00 no boy each 126.00 378.00
562.80 619.08
Say Rs. 563.00 /10m3 Rs. 620.00

a Ist depth of 1.5-3.0m add 25% to the rate of initial


1.25 m3 depth
10m3 562.80 703.50 773.85
Say Rs. 704.00 /10m3 Rs. 774.00

b 2nd depth of 3.0-4.5m add 25% to


1.25 m3 the rate of previus depth 10m3 703.50 879.38 967.31
Say Rs. 880.00 /10m3 Rs. 968.00

c 3rd depth of 4.5-6 m add 25% to the


1.25 m3 rate of previus depth 10m3 879.38 1099.22 1209.14
Say Rs. 1100.00 /10m3 Rs. 1210.00

d 4th depth of 6-7.5m add 25% to the


1.25 m3 rate of previus depth 10m3 1099.22 1374.02 1511.43
Say Rs. 1375.00 /10m3 Rs. 1512.00

e 5th depth of 7.5-9m add 25% to the


1.25 m3 rate of previus depth 10m3 1374.02 1717.53 1889.28
Say Rs. 1718.00 /10m3 Rs. 1890.00

Page 64
f 6th depth of 9m-10.5 add 10% to the
1.1 m3 rate of previus depth 10m3 1717.53 1889.28 2078.21
Say Rs. 1890.00 /10m3 Rs. 2079.00

Errcetion of RCC ring


2a
Providing and errceting in well RCC ring of 1.2m
dia, 0.05 thick and 0.3 height with 1:2:4 using
20mm broken stone
Data for each ring
0.054 m3 concrete 10dm3 38.88 209.95
2.17 m2 form work-@50% of slab 10m2 1370.88 297.48
0.5 no man for errecting each 168.00 84.00
Total 591.43 650.58
Say Rs. 591 /each 651.00

b
Providing and errceting in well RCC ring of 1.35m
dia, 0.05 thick and 0.3 height with 1:2:4 using
20mm broken stone

Data for each ring


0.061 m3 concrete 10dm3 38.88 237.17
2.44 m2 form work-@50% of slab 10m2 1370.88 334.49
0.5 no man for errecting each 168.00 84.00
Total 655.66 721.23
Say Rs. 656.00 /each 721

c
Providing and errceting in well RCC ring of 1.5m
dia, 0.05 thick and 0.3 height with 1:2:4 using
20mm broken stone
0.068 m3 concrete 10dm3 38.88 264.38
2.73 m2 form work-@50% of slab 10m2 1370.88 374.25
0.5 no man for errecting each 168.00 84.00
Total 722.63 794.90
Say Rs. 723.00 /each 795.00

d Providing and errceting in well RCC ring of 1.8m


dia, 0.05 thick and 0.3 height with 1:2:4 using
20mm broken stone

0.08 m3 concrete 10dm3 38.88 311.04


3.3 m2 form work-@50% of slab 10m2 1370.88 452.39
0.5 no man for errecting each 168.00 84.00
Total 847.43 932.17
Say Rs. 847 /each 932

e Providing and errceting in well RCC ring of 2.1m


dia, 0.075 thick and 0.3 height with 1:2:4 using
20mm broken stone in 11m height

0.15 m3 concrete 10dm3 38.88 583.20


3.72 m2 form work-@50% of slab 10m2 1370.88 509.97

Page 65
0.5 no man for errecting each 168.00 84.00
Total 1177.17 1294.88
Say Rs. 1177 /each 1295.00

e Providing and errceting in well RCC ring of 2.4m


dia, 0.075 thick and 0.3 height with 1:2:4 using
20mm broken stone

0.17 m3 concrete 10dm3 38.88 660.96


4.38 m2 form work-@50% of slab 10m2 1370.88 600.44
0.5 no man for errecting each 168.00 84.00
Total 1345.40 1479.94
Say Rs. 1345 /each 1480.00

Page 66
/100m2

/100m2

/100m2

/Each

/m3

/m3

/m3

Page 67
/m3

/m3

/m3

/10m2

/m3

/10dm3

/m3

Page 68
/Each

/Each

/m3

/m2

/m2

/m2

/m3

/10m2

Page 69
/10m2

/10m3

/10m3

/10m3

/10m3

/10nos

Page 70
/10m3

/10m3

/10m3

/10m3

/10m3

/10m3

/10m3

Page 71
/10m3

/10m3

/10m3

/10m3

/10m3

Page 72
/10m3

/m3

/10m3

Page 73
/m

Page 74
/m

/10m

Page 75
/m3

/m3

/m3

Page 76
/Qtl

/10m2

/10m2

/10m2

/10dm3

Page 77
/10dm3

/10dm3

/10dm3

/10dm3

/10dm3

/10dm3

Page 78
/10dm3

/10dm3

/10dm3

/10dm3

/10dm3

Page 79
/10dm3

/10dm3

/10dm3

/10dm3

Page 80
/10dm3

/10dm3

/10dm3

/10dm3

/10dm3

Page 81
/m3

/m3

/m3

/m3

Page 82
/m3

/m3

/m3

/m3

Page 83
/m3

/m3

/m3

/m3

Page 84
/m3

/m3

/m3

/m3

Page 85
/m3

/m3

/m3

/m3

Page 86
/m3

/m3

/m3

/m3

Page 87
/m3

/m3

/m3

/m3

/m3

Page 88
/m3

/10dm3

/10dm3

/m2

Page 89
/10dm3

/Each

/Each

/m2

/m2

/10m2

Page 90
/10m2

/10dm2

/10dm2

Page 91
/Qtl

/Qtl

/10nos
/10nos
/10nos
/10nos
/10nos
/10nos
/10nos
/10nos
/10nos
/10nos
/10nos
/10nos
/each
/each

/10m2

Page 92
/10m2

/10m2

941

225

#VALUE!

/10m2

Page 93
/10m2

/10m2

/10m2

Page 94
/m2

/10dm2

/10dm3

2541

/10m2

Page 95
/10m2

/10m2

/10m

/10m

/10m

Page 96
/10m2

/10m

/10m2

Page 97
/10m

/10m2

/10m2

/10m

Page 98
/m

/m

/10m2

Page 99
/10m2

/10m2

/10m2

/10m2

/10m2

Page 100
/10m2

/10m2

/10m2

/10m2

/10m2

/10m2

Page 101
/10m2

/10m2

/10m2

/10m2

/10m2

/10m2

Page 102
/10m2

/10m2

/10m2

/10m2

/10m2

/10m2

Page 103
/10m2

/10m2

/10m2

/10m2

/10m2

Page 104
/10m2

/10m2

/10m2

/each

/each

Page 105
/each

/Qtl

/m

Page 106
/m

/m

/m

/m

Page 107
/10dm2

/m

/10dm2

/each

Page 108
/Each

/Each

Page 109
/Each

/Each

/Each

/Each

Page 110
/Each

/m

/m

Page 111
/m

/m

/Each

/Each

/Each

/Each

Page 112
/Each

/m

/10m2

/10m2

/10m2

/10m

/10m2

Page 113
/10m2

/10m2

/10m2

/10m2

/10m2

/10m2

/10m2

Page 114
/10m2

/10m2

/m3

Page 115
/m3

100
5.75

/m3

Page 116
/10m2

/10m2

Page 117
/10m2

/10m2

Page 118
/m3

/m3

/m3

Page 119
/m3

/10m3

/10m3

/10m3

/10m3

/10m3

/10m3

Page 120
/10m3

/each

/each

/each

/each

Page 121
/each

/each

Page 122
Page 123
Page 124
Page 125
Page 126
0.00 /10m

Page 127
Page 128
Page 129
Conveyance of materials by lorry - Average lead (Paravoor
Taluk)

Alangad Block

Sl.No. Materials Avg.lead Amount

1 Rubble and broken stone 36 Km 386.75

2 River sand 27 km 311.15

3 Cement and Steel 5 km 187.20

4 Bitumen 50 km 377.90

5 Brick 27 km 420.90

6 Laterite 14 km 201.95

7 Lime 5km 100.40

8 Timber(scantling) 46 km 407.90

9 Earth for filling 14 km 201.95

Certified that the distance noted in the data for conveyance of materials
except cement/steel and earth are the average Taluk wise conveyance
approved by the Exe. Engineer, Building Division, Ernakulam and for cement /
steel and earth are the minimum lead required

Assistant Executive Engineer


Block Panchayath, Paravoor
ABSTRACT OF RATES
IN PARAVOOR TALUK BASED ON 2010 SCHEDULE OF RATES

Sl.
No. Description of works Rate with out C.P Rate with C.P
CLEARING SITE

1 Clearing grass and other growth of vegitations 120.00 /100m2 132.00 /100m2

2 Clearing light jungles 240.00 /100m2 264.00 /100m2

3 Clearing tick and throny jungles and small trees 480.00 /100m2 528.00 /100m2

4 Felling trees 60to120 girth 214.00 /Each 235.00 /Each

DESMANTLING

6 Dismantling brick, laterite,rubble masonry in mud 168.00 /m3 185.00 /m3

7 Do DR masonry 168.00 /m3 185.00 /m3

8 Do in lime mortar 276.00 /m3 304.00 /m3

9 Do in cement mortar 384.00 /m3 422 /m3

12 Dismantling or chipping RCC 28 /10dm3 31 /10dm3

13 Removing floor tiles 141 /10m2 155 /10m2

14 Do MP roof tiles 120.00 /10m2 132.00 /10m2

15 Do pan or pot roof tiles 240.00 /10m2 264.00 /10m2

16 Do wrought and framed timber from roof 7.91 /10dm3 8.70 /10dm3

17 Dismantling door with shutters 196.00 /Each 215 /Each

18 Do window with shutters 129 /Each 142 /Each

19 Do ventilator with shutters 73 /Each 80 /Each

20 Do ceiling 198.00 /10m2 218.00 /10m2

21 Taking down shutters of doors 57.00 /10m2 62.15 /10m2

22 Do shutters of windows 45.00 /10m2 49.00 /10m2

23 Do shutters of ventilator 21.05 /10m2 23.16 /10m2

28 Dismantling cement concrete/RCC 720.00 /m3 792.00 /m3

30 Do lime mortar 72.00 /10m2 79.20 /10m2

Page 132
31 Do cement mortar 120.00 /10m2 132.00 /10m2

EARTH WORK

51 Earth work excavation in ordinary soil for foundati Rs. 804 /10m3 884 /10m3

52 Do - in hard soil for foundation Rs. 1,500 /10m3 1650 /10m3

53 Do - in ordinary rock for foundatio Rs. 2,814 /10m3 3095 /10m3

54 Do - in granite rock blasting Rs. 5,376 /10m3 5913 /10m3

56 Do - in ordinary soil for cutting and f Rs. 711 /10m3 782 /10m3

57 Do - in hard soil for cutting and fil Rs. 1,314 /10m3 1445 /10m3

60 Do - in under water or liquid mud Rs. 853 /10m3 939 /10m3

61 Earth consolidation by Power Roller 109 /10m3 112 /10m3

65 Granite rock blasting in wells for initial deapth 5375.8 /10m3 5913 /10m3

65(a) Granite rock blasting in wells for additional deapth Rs. 265 /10m3 291 /10m3

67 Earth consolidation by ramming Rs. 168 /10m3 185 /10m3

67b Earth filling with ordinary soil,consolidation by ra Rs. 2,777 /10m3 3055 /10m3

Earth filling with ordinary soil, consolidation by


67d power roller Rs. 2,886 /10m3 3174 /10m3

67f Earth filling with hard soil,consolidation by rammin 3380 /10m3 3718 /10m3

67g Bailing out water Rs. 117 /Hr 128 /Hr

67h Sand filling with sea sand Rs. 875 /m3 963 /m3
Packing with mutty stone in slushly portion of the
road Rs 556 /m3 0 /m3

Earth work excavation in hard soil extra additional


lift 1.5m or part thereof over initial lift Rs. 67 /m3 Rs 74.00 /m3

67i Putting ring bunds Rs. 1,635 /m 1799 /m

67j Putting bunds with sand bags 6643 /10m 7308 /10m

CONCRETE

110 Cement Concrete 1:3:6,using 40mm matel Rs. 3,705 /m3 0 /m3

111 Do 1:4:8, 40mm Rs. 3,424 /m3 0 /m3

Page 133
122 Do 1:2:4,using 20mm matel 48 /10dm3 0 /10dm3

122a Do 1:(1.5):3,using 20mm matel 53 /10dm3 0.00 /10dm3

123 Do 1:3:6,using 20mm matel 42.50 /10dm3 0 /10dm3

123a Do 1:3:6,using graded(60:40 %,40mm,20mm) Rs. 3,926 /m3 4318 /m3


Do 1:3:6,using graded(60:40
%,40mm,20mm) matel including formwork for
b drains Rs. 4,441 /m4 4885 /m4

123b Do 1:3:6,using graded(50:50 %,40mm,20mm) Rs. 3,978 /m3 4376 /m3

130 Reinforcement for RCC works 5412.75 /Qtl 5954 /Qtl

FORM WORK

132 Form work for slab 3605 /10m2 3966 /10m2

132a Do for beam 3966 /10m2 4362 /10m2

132b Do for column 4326 /10m2 4759 /10m2

RCC WORK

133 Cement Concrete 1:2:4 for slab including form wor 84.50 /10dm3 92.50 /10dm3

133a Do 1:(1.5):3, for slab including form work 89.50 /10dm3 98.00 /10dm3

134b Do 1:2:4 for lintel including form work 74.00 /10dm3 81.50 /10dm3

134c Do for sun shade including form work 91.50 /10dm3 100.79 /10dm3

134d Do for belt 45x10 on rubble including 49 /10dm3 54 /10dm3

134e Do for pre cast slab including form wor 49 /10dm3 54 /10dm3

134f Do for column footing including form w 49 /10dm3 54 /10dm3

134g Do for beam (20x20) including form wo 107.50 /10dm3 118.50 /10dm3

134h Do for beam(20x30) including form wo 101 /10dm3 111 /10dm3

134i Do 1:2:4 for beam (20x40) including form wor 98 /10dm3 107.50 /10dm3

135 Do 1:2:4 for column(20x20) including form 114.00 /10dm3 125.50 /10dm3

135a Do 1:2:4 for column(30x20) including form 103 /10dm3 113.50 /10dm3

135b Do 1:2:4or column(40x20) including form wo 97.50 /10dm3 107.50 /10dm3

Page 134
BRICK WORK

158 Brick work in 1:5 using 19x9x9cm for foundation Rs. 2,845 /m3 3129 /m3

163 Do do super struc Rs. 2,899 /m3 3189 /m3

158a Do using 22.9x11.2x7cm for foundati Rs. 2,862 /m3 3148 /m3

163a Do do super struc Rs. 2,916 /m3 3208 /m3

159 Brick work in 1:6 using 19x9x9cm for foundation Rs. 2,791 /m3 3070 /m3

163b Do do super struc Rs. 2,845 /m3 3129 /m3

159a Do using 22.9x11.2x7cm for foundati Rs. 2,808 /m3 3089 /m3

163c Do do super struc Rs. 2,862 /m3 3148 /m3

CEMENT BRICK WORK

163d Hollow brick(40x20x20) work in 1:5 for foundation Rs. 2,303 /m3 2534 /m3

163e Do do super srructure Rs. 2,379 /m3 2617 /m3

163f Do (40x20x10) work in 1:5 for superstructu Rs. 3,051 /m3 3356 /m3

163g Solid brick(40x20x15) work in 1:6 for foundation Rs. 2,697 /m3 2967 /m3

163h Do do super srructure Rs. 2,751 /m3 3323 /m3

163j Do for additional floor 54 /m3 59.00 /m3

LATERITE WORK

206a Laterite work 1:6 for foundation (44x24x14cm) Rs. 2,259 /m3 2485 /m3

Do for superstructure Rs. 2,335 /m3 2567 /m3

206 Laterite work in 1:5 for foundation(29x24x14cm) Rs. 2,614 /m3 2875 /m3

207 Do for superstructure Rs. 2,689 /m3 2957 /m3

206a Do in 1:6 for foundation Rs. 2,574 /m3 2832 /m3

207a Do for superstructure Rs. 2,650 /m3 2914 /m3

208 Do for additional floor 75 /m3 82 /m3

STONE MASONRY
274 RR masonry in 1:6 Rs. 2,249 /m3 2474 /m3

275 RR masonry in 1:8 Rs. 2,160 /m3 2376 /m3

Page 135
274a RR masonry in 1:6 with Deptl. Stone Rs. 3,887 /m3 4275 /m3

277 DR masonry Rs. 1,235 /m3 1359 /m3

277a DR masonry with Deptl, stone Rs. 428 /m3 471 /m3

Packing with mutty stone 718 /m3 790 /m3

278 Rough stone dry packing for Aprons and revetmen 1257 /m3 1383 /m3

278 Rough stone dry packing for road formation 1105 /m3 1216 /m3

WOOD WORK

301a Anjily wood scanteling Rs. 389 /10dm3 428 /10dm3

312 Anjily wood wrought and put up Rs. 430 /10dm3 473 /10dm3

313 Do planed and framed work foir door/ wi Rs. 503 /10dm3 554 /10dm3

Ceiling with 12mm Anjily wood planks, planed,


326 lap joined, and wire nailed to rafters and collors Rs. 7,542 /10m2 8296 /10m2

A Fixing in position pre cast cement concrete door/ Rs. 105 /each 116 /each

B Do for ventilator 47.00 /each 51 /each

DOORS & WINDOWS


351 Anjily wood fully panelled shutters to doors Rs. 250 /10dm2 275 /10dm2

360 Anjily wood fully glazed shutters to windows Rs. 234 /10dm2 257 /10dm2

368 MS rods to windows Rs. 4,248 Qtl 4673 Qtl

369 MS flat iron work for windows or hold fast Rs. 5,665 Qtl 6231 Qtl

A S/F Alum. Sliding window with plain glass

B Supplying and fixing iron fittings to doors and windows

a 100mm iron butt hinges 85.00 /10nos 93.50 /10nos

b 75mm iron butt hinges 42.00 /10nos 46.20 /10nos

c 100mm aluminium tower bolt 250.00 /10nos 275.00 /10nos

d 150mm aluminium tower bolt 320.00 /10nos 352.00 /10nos

e 200mm aluminium tower bolt 360.00 /10nos 396.00 /10nos

f 200mm aluminium aldrop 1100.00 /10nos 1210.00 /10nos

Page 136
g 75mm iron hooks and eyes 20.00 /10nos 22.00 /10nos

h 100mm iron hooks and eyes 26.00 /10nos 28.60 /10nos

i 200mm iron hooks and eyes 50.00 /10nos 55.00 /10nos

j 150mm aluminium door handle 250.00 /10nos 275.00 /10nos

k 20*8mm steel screws 6.50 /10nos 7.15 /10nos

l 25*8mm steel screws 7.50 /10nos 8.30 /10nos

m 50mm pad lock-6 lever 120.00 /each 132.00 /each

B S/F Precast Cement Concrete door frame

S/F Precast Cement Concrete window/ventilator frame

FLOORING
410 CC 1:4:8-75mm thick, CM-1:3,12mm thick, one co 3883 /10m2 4271 /10m2

410a CC 1:4:8-75mm thick, CM-1:3,12mm thick, flushin 4154 /10m2 4569 /10m2

409a Flooring with ceramic tiles(30x30) 5605 /10m2 6162 /10m2

b Do with rectified joint free tiles(45x45) 5558 /10m2 6114 /10m2

c Do with Vitrified tiles(60x60) 7857 /10m2 8642 /10m2

413a Do with gray marble slab 9524 /10m2 10459 /10m2

b Granite tiles (polished) 2 ftx1 ft 8634 /10m2 9496 /10m2

Dadoing walls with glazed tiles20x30mm, CM-


536 1:3, 12mm thick 884 /m2 972 /m2

ROOFING

318 Supplying and fixing Anjily wood reepers 488 /10dm3 537 /10dm3

328 Ceiling with Anjily wood planks 5849 /10m2 6434 /10m2

452 Supplying and fixing MP tiles(340mm) 1288 /10m2 1417 /10m2

452a Fixing with Deptl.MP tiles(340mm) 270 /10m2 297 /10m2

Page 137
458 Supplying and fixing MP hip and ridge tiles 925 /10m 1018 /10m

458a Fixing with Deptl.MP hip and ridge tiles 527 /10m 580 /10m

460 Valleying with GI sheet 2736 /10m 3009 /10m

453 Roofing with AC corrugated sheet 2722 /10m2 2994 /10m2

454 Roofing with AC ridge capping 1533 /10m 1687 /10m

455 Roofing with GI corrugated sheet 4583 /10m2 5042 /10m2

455a Roofing with GI ridge capping 1851 /10m 2036 /10m

455b Roofing with fiber corrugated sheet 11862 /10m2 13045 /10m2

506 Plastering with cement mortar 1:3, 12mm thick 1315 /10m2 1447 /10m2

506a Do 1:3, 9mm thick 1094 /10m2 1204 /10m2

507 Do 1:4, 12mm thick 1277 /10m2 1405 /10m2

511 Do 1:4, 15mm thick 1334 /10m2 1468 /10m2

514 Cement flushing coat/ second coat 271.05 /10m2 298 /10m2

536 Dadoing with glazed tiles20x30mm, CM-1:3, 12mm 884 /m2 972 /m2

PAINTING WALLS

551 White washing two coats 61 /10m2 67 /10m2

555a White cement washing one coat 75.50 /10m2 83 /10m2

b Do two coats 125 /10m2 138 /10m2

558 Oil bond distember two coat to new wall 241 /10m2 265 /10m2

559 Do one coat to old wall 110 /10m2 121 /10m2

560 Water proof cement paint,2 coat,new wall 383.00 /10m2 421 /10m2

561 Do one coat, old wall 163.00 /10m2 179 /10m2

PAINTING WOOD /IRON

601 Cleaning old painted surface 242.00 /10m2 266.00 /10m2

603 Painting with wood primer 183.00 /10m2 201.00 /10m2

604 Iron primer 175.00 /10m2 191 /10m2

607 Ready mixed paint 2 coat, new wood 331.00 /10m2 364.00 /10m2

Page 138
608 Do 1 coat, old wood 164.00 /10m2 181.00 /10m2

607a Do 2 coat, new wood including primer 513 /10m2 564 /10m2

609 Aluminium paint 2 coat, new iron 386 /10m2 425.00 /10m2

610 Do 1 coat, old iron 189 /10m2 208.00 /10m2

612 Synthetic enamal paint-2 coat,to new wood 487 /10m2 535 /10m2

612a Do 2 coat,including primer,to new wood 669 /10m2 736 /10m2

614 Do one coat to old wood 218 /10m2 239 /10m2

612b Do- 2 coat,to new iron 407 /10m2 448.00 /10m2

612c Do one coat to old iron 199 /10m2 219.00 /10m2

612d Do -2 coat,including primer,to new iron 581 /10m2 639 /10m2

615 Plastic emulsion-two coat, to new wall 521 /10m2 572 /10m2

615a Do one coat to old wall 182 /10m2 200.00 /10m2

619a Varnishing, 2 coat to new wood 356 /10m2 392.00 /10m2

621 Do one coat to old wood 160 /10m2 176 /10m2

625 Black Japan coat to rubble surface 216 /10m2 238 /10m2

628 Painting letters 6,5,8,10cm Ht 17 /Each 18 /Each

629 Painting letters 13, 15,18cm Ht 25 /Each 27 /Each

630 Painting letters 23,25,30cm Ht 33 /Each 37 /Each

STEEL WORKS

Steel work in MS angles for,trusses or framed


754 work, including iron primer 5979 /Qtl 6578 /Qtl

754a GI pipe truses using 65mm dia. Pipe 302 /m 332 /m

c Do 50mm dia. 237 /m 261 /m

d Do 40mm dia. 197 /m 217 /m

e Do 25mm dia. 147 /m 162 /m

755 MS grill for windows and gate 6953 /Qtl 7648 /Qtl

Page 139
763 Rolling shutters 166 /10dm2 183 /10dm2

763a Top cover for Rolling shutters 460 /m 506 /m

b MS steel collapsible grill 166 /10dm2 183 /10dm2

c Welded mesh 50x50, 10g With out frame /m2 /m2

d Welded mesh 50x50, 10g With MS flat frame /m2 /m2

Supplying and Fixing Fabricated sign board


f of size 90 X 60 1767 /each 1944 /each
SANITARY

855 Wash hand basin 1753 /Each 1928 /Each

855b Stainless steel sink of size 510x432c165mm, 1mm 1776 /Each 1953 /Each

860 Indian type WC with foot rest 982 /Each 1080 /Each

860a Indian type WC orissa pan 1002 /Each 1102 /Each

861 Europian type WC 1052 /Each 1158 /Each

862a PVC low level flush tank 1136.00 /Each 1249 /Each

854 Urinal 856.00 /Each 941 /Each

WATER SUPPLY
883 Laying 20mm PVC pipe(10kgf/cm2) for internal wo Rs. 38.50 /m 42 /m

a Do 25mm(10kgf/cm2) Rs. 43 /m 47.00 /m

b Do 40mm (8kgf/cm2)for external wor Rs. 52.50 /m 58.00 /m

c Do 110mm(8kgf/cm2) for external wo Rs. 237 /m 261 /m

d supplying and fixing 25mm PVC ball valve Rs.41.50 /Each Rs.45 /Each

e Do - CP shower rose Rs.236 /Each Rs.259 /Each

f Do - 15mm SDB tap 153.00 /Each 168.00 /Each

g Do - brass and gun matel 20mm stop cock Rs.261 /Each Rs.287 /Each

h Do - 110mm steel grating for toilet Rs.19 /Each Rs.21 /Each

i Do - 40mm PVC ventilation pipe for septic tank Rs.31.50 /Each Rs.34.50 /Each

ROAD WORK
651 Sectioning new road 120.00 /10m2 132 /10m2

Page 140
652 Do old road 60.00 /10m2 66 /10m2

653 Picking up 50 to 100mm old matelled surface and 120.00 /10m2 132 /10m2

Formiong and consolidating sides of road after


659 completion 194 /10m 214 /10m

1 Supplying 60mm graded matel 939 /m3 1033 /m3

2 Do 36mm 1009 /m3 1110 /m3

3 Do 12mm 1239 /m3 1363 /m3

4 Do 6mm 1019 /m3 1121 /m3

5 Do red earth for blinding 382 /m3 420 /m3

6 Matelling Ist layer with 60mm graded matel 477 /10m2 522 /10m2

7 Do 2st layer with 36mm matel 477 /10m2 522 /10m2

8 Rematelling the road way 386.00 /10m2 422 /10m2

9 Filling pot holes with 12mm matel(bitumen-60kg/m 4308.00 /m3 4725 /m3

Except cost of Bitumen 2044.00 /m3 2235 /m3

10 Do 36mm matel(bitumen-27.5kg/ 1928.38 /m3 2016 /m3

Except cost of Bitumen 928.00 /m3 1014 /m3

11 Leveling course with 12mm matel(bitumen-40kg/m 2575 /m3 2657 /m3


Except cost of Bitumen 828 /10m2 908 /10m2

12 Do 36mm matel(bitumen-20kg/m3 1187 /m3 1229 /m3


Except cost of Bitumen 460 /10m2 501 /10m2

13 Chipping carpet-20mm thick with seal coat over


WBM surface(bitumen-29.1kg/10m2) 1440.00 /10m2 1476 /10m2

Except cost of Bitumen 381 /10m2 415 /10m2

14 Chipping carpet-20mm thick with seal coat over


BT surface(bitumen-29.1kg/10m2) 1346 /10m2 1381 /10m2

Except cost of Bitumen 381 /10m2 415 /10m2

Page 141