Reference our discussion today regarding a possible project with yourself for packaging,
sourcing, supervising a installation/commissioning of a Turbine Generator in Punjab.
We have purchased a 7.83 MW Turbine Generator from Europe. Photo's attached. The
Turbine Generator was installed at a sugar plant which was liquidated 2 years ago.
The liquidator only saved the Turbine, Gear and Alternator. All auxilaries of the Turbine
Generator were destroyed by the plant liquidator and are missing.
Following is a list of components that are missing from the Turbine Generator:
All valves, fittings and instrumentation is available locally in Pakistan at very competitive
prices. All interconnecting piping for oil system would have to be done.
We will facilitate all support structure at site. We will provide lodging, food, tools and
necessary infra-structure during the project at the Site. An overhead crane is available in the
power house. The Turbine Generator is expected to arrive in Pakistan by July 30, 2010
We are sending the Turbine Generator Manual, drawings, photo's and all the relevant data
that may help you establish a commercial proposal for supply of missing components
and also commercial offer for services.