You are on page 1of 8

RIVERS STATE ELECTRIFICATION

PROJECT

60MVA 132KV/33KV TRANSMISSION STATION


AT AFAM POWER STATION

PROJECT WORKSCOPE PLAN

1
TABLE OF CONTENT

1.0 Purpose

1.1 Project Objective

2.0 Background

3.0 Summary Work scope

4.0 Detail work scope.

2
1.0 PURPOSE

The purpose of this document is to outline a strategy for the execution and installation of
the 60MVA 132KV/33KV Transformer, donated by RIVERS STATE GOVERNMENT
construction of switch yards and control buildings at Afam Power Station.
This will enable an integrated approach towards the execution of the project, so that the
Procurement, Construction, installation and commissioning phases of the Project will be
performed within the outline Project schedule, at the right quality and cost.

1.1 PROJECT OBJECTIVE

The main objective of this project is to provide electricity to some Rivers state
communities (Ogoni, Oyibo etc) by way of connecting the communities with High
Voltage (33KV) Transmission Line from Afam Power station facilities, thereby ensuring
power availability in the communities and also achieves interdependency between the
communities and Afam Power station Transmission facility.

2.0 BACKGROUND

The Rivers state Communities Electrification Project was borne out of the Sustainable
Community Development Policy & Objectives of the Government to supply electricity to
the citizenry.
The preliminary & detailed engineering design for the installation of the 60MVA
132KV/33KV Transformer and HV transmission line to the communities is on going.

3.0 SUMMARY WORKSCOPE

The project proposal is to install a 60MVA 132KV/33KV Transformer(to be


provided by the RVSG) , construct 132kv Switchyard, install 2nos 132kv Control
panels, construct a 33kv Switch yard(2nos bus bars circuits with 5nos 33kv
outdoors breakers), install 33kv control panels (Incomer, bus section and 3
outgoings and install Tripping units with Batteries in the existing 33kv Control
building.

3
4.0 DETAILD SCOPE OF WORK
The scope of work shall include, but not limited to the following.

4.1 PRELIMINARY WORKS

4.1.1 Removal of old and disused materials/ equipment


Identify the old and disused materials at site, such as the Transformer fins, Gantries,
burnt Circuit breaker, insulators etc and remove them from the area for the 132KV
Switch yard

4.1.2 Cable Excavation works


Excavate 120m of cable trench of the paved area from the 132kv Switch yard to the 33kv
Control room. The trenches shall be at least 850mm deep(for 600/1000volt cables) and
1m deep for H.V cables
Excavate 40m of cable trench of the paved area from the 132kv Switch yard to the 132kv
Control room The trenches shall be at least 850mm deep(for 600/1000volt cables) and
1m deep for H.V cables
Laying of cables on the excavated Trenches. Note that instrument systems and
Telecommunication cables shall not be laid in the same trenches used by H.V and/or L.V
power cables
The H.V cables may be laid in the same trench with the L.V cables, but shall be separated
, e.g. by a continues row of concrete cable tiles placed vertically between the two types of
cables. H.V. and L.V. cables must be separated by at least 250mm horizontally or
vertically.

4.1.3 Cable Tiles


Cable tiles made of pre-cast concrete shall be laid so as to protect the cable against
mechanical damage.

4.1.4 Back- filling and re-instatement


Back-filling of cable trenches shall be done with suitable approved earth material in well
compacted layers up to 150mm thick. The back-fill may be mounted up to 100mm above
grade level , to allow for future subsidence.

4.1.5 Cable installed above ground


All the cables which are not buried, installed in ducts or drawn into conduits shall be
installed on channels, racks or cable trays.

4.1.6 Cable fixing arrangement


All the cables shall be securely fixed to the cable trays and ladders by means of surface
type saddles secured with 6-mm screws and nuts

4.1.7 Cable segregation and Separation


Instrumentation and Telecommunication cable shall not be laid on the same trays as
power cables

4
4.1.8 Earthing
All metal parts of cable racks and trays shall be connected to the common earth grid

4.2 CIVIL ACTIVITIES

4.2.1 Civil Structural Activities


The civil /structural design element of the work shall be established before civil
construction activities commence on site. The elements are, but not limited to the
following,
• Soil conditions and foundation requirements shall be established
• Layout and support drawings shall be established
• Detail design of foundations, supports etc shall be prepared
• Civil/Structural specifications shall be prepared.
• Site preparation details shall be prepared
• Design of Substation drawings together with transformer and feeder plinths
shall be prepared.

4.2.2 Civil Construction Works(132kv and 33kv Switch yards)


Civil construction work shall be made up of but not limited to the following,
• Site clearing
• Modification of the existing Transformer foundation plinth.
• Modification of the existing stanchion gantries foundation plinths to realign
with the proposed new Gantry arrangement .
• Construction of new Earthing Transformer plinth
• Modification of the existing 33kv switchyard to accommodate two no bus bar
circuits with five outgoing feeders, by the construction of stanchion gantries
foundation plinths. (Available space 20x10m).

5
4.3 INSTALLATION OF ELECTRICAL EQUIPMENT

4.3.1. 132KV Transmission station works


Procurement of Electrical equipment & materials:
The following Electrical items shall be procure and install:

• Procure and install 1no 60MVA 132 KV/33KV Transformer.(RVSG


to procure)
• Procure and install 1no 132 KV outdoor SF6 Circuit breaker
• Procure and install a set of Voltage Transformers (132kv/√3/110/√3)
• Procure and install a set of Current Transformers(600/300/1A)
• Procure and install a set of 132kv Lightning Arresters
• Procure and install 2 sets of 132kv motorized gang Isolators
• Procure and install 2 sets of 132kv insulators with supports
• Procure and install station Earthing Transformer 500kva
33kv/0.415kv
• Procure and install 132kv Transformer incomer Control panels
(Indoor Transformer incomer and Protection/Metering panel)
• Procure and install 1no 110V Tripping unit
• Carry out station earthing

4.3.1.1. 132kv line entry Gantries


Procure and install 21nos steel lattice Transmission 3.0m stanchion
gantries, with ISO Metric black hexagonal bolts, screws and nuts to
BS4190

4.3.1.2. Conductors/Stringing
Procure and string 200metres of 240mm2 BAC conductors within the
switchyard

4.3.1.3 Power and Control Cables


Procure and install 1000m of 1c x 500mm2 power cable from the
60MVATransformer secondary to the 33kv Control panel, switch yard
etc.
Procure and install 1000m of 4cx4mm2 Control cable
Procure and install 1000m of 19cx2.5mm2 Control cable

4.3.2 33KV TRANSMISSION STATION WORKS


Procurement of Electrical equipment & materials:

6
The following Electrical items shall be procure and install:
• Procure and install 4no of 33 KV outdoor SF6 Circuit breakers
• Procure and install 4 set Voltage Transformers (33kv/√3/110/√3)
• Procure and install 3 set Current Transformers
• Procure and install 3 set of gang Isolators
• Procure and install 3 set of 33kv Lightning Arresters
• Procure and install 10 sets of 33kv Insulators
• 33kv Control panels (incomer, Bus section and 3nos outgoing) I/D
• Procure and string 200m of 240mm2 BAC
• Procure and intall 110V Tripping unit
• Carry out station earthing

4.3.2.1. 33kv line entry Gantries


Procure and install 45 nos steel lattice Transmission 3.0m stanchion
gantries, with ISO Metric black hexagonal bolts, screws and nuts to
BS4190

4.3.2.2 Conductors/Stringing
Procure and string 200metres of 240mm2 BAC conductors within the
switchyard

4.3.2.3 Power and Control Cables


Procure and install 120m of 3c x 240mm2 power cables to the 3no
outgoing feeders.
Procure and install 6no 33kv Raychem kits termination indoor 1-core
(300-500mm2)
Procure and install 6no 33kv Raychem kits termination outdoor 1-core
(300-500mm2)
Procure and install 3no 33kv Raychem kits termination indoor 3-core
(300-500mm2)
Procure and install 3no 33kv Raychem kits termination outdoor 3-core
(300-500mm2)
Procure and install 10nos 500mm2 compressible sockets.
Procure and install 10nos 300mm2 compressible sockets
Procure and install 100nos 4mm2 compressible sockets
Procure and install 100nos 2.5mm2 compressible sockets

4.3.3 Earthing Transformer 500kva, 33/0.415kv Substation

The following Electrical items shall be procure and install:

7
• Procure and install 1no 500kva, 33/0.415kv earthing Transformer,
• Procure and install a set of 33kv J& P fuse
• Procure and install a set of Lightning arrester
• Procure and install a set of gang Isolators
• Procure and install 9nos 33kv Channel iron (9 feet)
• Procure and install 100m of 150mm2x4c P.V.C Cable
• Procure and install 45m of 70mm2x3c XLPE Cable
• Procure and install Raychem kits(35-70mm), indoor and outdoor
• Procure and install 40m of 70mm2x1c copper cable
• Procure and install 4nos Earth rods

4.3.4 Other Materials


• 100 no of Galvanized nuts and bolt 5/8’’x7
• 100 no of Galvanized nuts and bolt 5/8’’x9
• 100 no of Galvanized nuts and bolt 5/8’’x11
• 30 no of Bimetal Line Tabs
• 3M Scotch Tapes
• P.V.C Tapes

4.4 EQUIPMENT

• Standard Tool boxs (Mechanical& Electrical)


• Electrical testing Instruments (AVO, IR, Hypotronics)
• Cable lifting devices/trolley
• Self loader truck
• Crane
• Cable terminating devices
• Oxy-acetylene kit
• Welding Machine
• Drilling Machines
• Concrete Mixer
• Generator
• Trailer
• Compressor

You might also like