You are on page 1of 22

Type MBCI Relay

Translay ‘S’ Differential Feeder


and Transformer Feeder Protection

T&D
Energy Automation & Information
Type MBCI Relay
Translay ‘S’ Differential Feeder
and Transformer Feeder Protection

Trip Trip
T2 Rpp Rpp T2
T1 Tr Tr T1
Rs Tt øc øc Rs
To To
Pilot wires

Ts RVD Ro Ro RVD
V V

T1 - Summation transformer To - Operating winding Rpp - Pilots padding resistor


T2 - Auxiliary transformer Tr - Restraining winding øc - Phase comparator
Figure 1: Basic circuit arrangement RVD - Non linear resistor Tr - Tertiary winding
Ts - Secondary winding Ro - Linear resistor

Features Models Available MCRI Instantaneous


overcurrent and start/check
MBCI Pilot wire differential • MBCI 01
relay
protection relay • MBCI 02
• High speed operation
• High stability for through faults • Not slowed by dc transients
Optional Extras
• High speed operation for in-zone • Wide setting range
faults
MRTP Supervision relay for ac • Two phase and earth fault relay
• Simultaneous tripping of relays at each pilot circuits
line end MCTH Transformer inrush
• Alarm and indication of pilot
• Low current transformer requirements failure and supervision supply current detector
• Low earth fault settings failure • Allows MBCI to be applied to
• Designed for the unit protection of • Suitable for pilot circuits insulated transformer feeders
overhead and underground feeders for 5kV or 15kV with pilot • Blocks operation of the MBCI
• Suitable for pilots up to 1kW or isolation transformers relay during transformer inrush
2.5kW with pilot isolation transformers conditions
MVTW Destabilising and • Blocking does not occur for zero,
• Four electrically separate contacts
intertripping relay normal load, or genuine fault
• Can be used as definite time
• For use with pilot wire relays current
overcurrent relay in the event of pilot
failure • Destabilises the feeder protection
so that tripping occurs
• Intertripping: injects ac voltage
into the pilot circuit so that
tripping occurs

2
Application The addition of pilot supervision will Emergency use for
not prevent tripping for pilot faults overcurrent protection
The Translay S differential schemes
but will indicate the cause. It will In the event of a pilot failure which
have been designed for the unit
also detect short circuit and cross- cannot quickly be rectified, the
protection of overhead and
connected pilot conditions which Translay S scheme may be adapted
underground feeders and
would not otherwise be detected. for use as a definite time
transformer feeders.
Indication is also provided for loss overcurrent relay as follows:
of the supervision supply.
Plain Feeders
If overcurrent relay is fitted
Differential protection Destabilising/intertripping
• disconnect pilot wires and leave
Differential feeder protection requires a When the protected line is terminals open circuited
comparison of the currents entering and connected to a busbar system, a
leaving the protected zone. For faults fault on the busbars will in general • set Kt to 3(300ms)
occurring within the protected feeder it be cleared by the busbar protection • check that overcurrent elements
is desirable to trip the circuit breakers at by opening some or all of the local are on the required setting above
each end to isolate the fault. Two MBCI circuit breakers. Although such maximum anticipated load
relays are therefore required, one for faults will usually appear to the current.
each end of the feeder. A pair of feeder protection as through faults,
pilot wires is used to transmit with resultant stability of the feeder If overcurrent relay is not
information between the two relays protection, it may be desirable to fitted
so that each may be able to compare open the remote line circuit breaker • disconnect pilot wires and
the current flowing at its respective also, to clear the line completely. connect a 1kΩ resistor across
end with the current at the other. The remote unit of the differential pilot terminals of relay
feeder protection can be caused to
The relays at both line ends operate • set padding resistors Rpp to
operate, provided sufficient line
simultaneously, providing rapid fault maximum (600Ω)
current is flowing, by open
clearance irrespective of whether
circuiting the pilots. If line current is • set Kt to 3 (300ms)
the fault current is fed from both line
not flowing, the remote unit can be
ends or only one line end. • set Ks to required open circuit
operated (intertripped) by injecting
When applying this protection to a current into the pilots. setting: Ks = 1 gives three phase
overhead lines the limiting factor is equal to rated load In.
generally the length of the pilot Overcurrent check/starting Note: Other fault settings will
circuits: for cable feeders the Although the supervision scheme depend upon the summation
limiting factors are more likely to be provides indication of pilot failure it ratio.
the level of line charging current does not prevent the protection
and the method of system earthing. operating if primary current above
setting is flowing. Where this hazard
Pilot supervision is unacceptable it is necessary to add
Correct interchange of information an overcurrent check feature.
over the pilot circuit is essential for
The current transformer requirements
the proper functioning of any
are not modified by the addition of
differential feeder protection. Pilots
overcurrent elements since they
may be exposed to hazards and
present a very low burden.
some risk of damage and failure
always exists. The most common When the starting feature is used the
pilot failure is to the open circuit overall operation time of the scheme is
state, caused by the accidental increased by 3–5ms. However, there
excavation of buried pilots or storm is no increase in the overall operation
damage to overhead pilots. With the time when the overcurrent protection
pilots open circuited the differential performs a check function only.
protection will be unstable and will When overcurrent relays are used the
trip the feeder if sufficient through protection cannot be intertripped by
current is flowing. For this reason the ac injection into the pilots, and
circulating current system is often destabilising the protection will result
preferred as such schemes will fail in tripping only if an overcurrent
safe and trip so that attention is condition exists simultaneously.
immediately drawn to the fault.

3
Protected Zone Protected Zone
P1 P2 P2 P1
A
S1 S2 S2 S1
B
C

12
See
RS Note 5 RS
MBCI 13 + MBCI
Power
23 Supply VX
Circuits 14
IA –
See
Note 4
24
25
& Enable 11
See
23
24 IA
Squarer Kt 1
IB
RL1
2 Note 2 25
RL1–1 3
26
5 26 IB
27 Enable
A 27
IC 2
Level RL2 28 IC
I N 28 2 RL1–2 4
C B Detector 6 IN
Phase OP
Trip/
&
RL3
Rotation 1 Alarm
KS RES 7
RO Outputs
RL2–1 9
Squarer
Case Earth
See Note 3 8
Case earth
RL2–2
1 2
3 4
10
RPP 17
5 6
7 8
9 10 18 Pilot
11 12
Wires
13 14 19
15 16
17 18
Notes
19 20
1. (a) C.T. shorting links make before (b) & (c) disconnect. 3. Earthing connections are typical only.
21 22 Module
23 24 terminal block (b) Short terminals break before (c) 4. C.T. connections are typical only.
25 26
viewed from (c) Long terminal. 5. For overcurrent start schemes, terminal 12 must be
rear connected directly to D.C. +VE to provide a supply for
27 28
2. Link terminals 11 and 13 except when used with overcurrent the L.E.D. and reset circuits.
check replay type MCRI.

Figure 2: Application diagram: differential feeder protection relay type MBCI

17 17

MBCI Pilots MBCI

18 18
17 18 17 18
19

Case 20
Earth MRTP02

20
RL2 OP RL7
2 1 Supply
19 Reset
Fail
A.C. 27 OP
A.C. RL1 RL3 RL6 1
Auxiliary 2 2 1 Pilot
28 Power Reset RL4–1 3
Supply Supply S/C Output
13 OP RL8
5 Contacts
D.C. Reset 1 Pilot 2 Change
Case earth Vx 14 Power O/C RL4–2 4 state for
Supply
1 2 RL4 6 pilot fail
3 4 2
7
5 6
RL5–1 9 Output
7 8
9 10 11
Contacts
11 12
MRTP01 Change
8
13 14 +VE
RL5 state for
2 RL5–2 10
supply
15 16
RL1 RL2 RL3 RL1 RL2 RL3 12
17 18 Case fail
–1 –1 –1 Start –2 –2 –2
19 20
Earth t
21 22
23 24
25 26 Module terminal block Note 1.
27 28
viewed from rear (a) C.T. shorting links make before (b) & (c) disconnect.
(b) Short terminals break before (c).
(c) Long terminal.

Figure 3: Application diagram: pilot supervision relay and injection filter type MRTP 01

4
Pilot isolation Pilot isolation
transformer transformer
P6 S2 S1 P1
17 17
P5
P4 X2 X1
P3
P2
MBCI Pilots MBCI
P2
X2 P3
X1 P4
P1 S1 S2 P5
18 18
P6
S1 S2 Supervision
isolation
P1 P2 transformer

20 OP
RL2 RL7
2 1 Supply
19 Reset See
Fail
A.C. 27 OP Note 7
A.C. RL1 RL3 RL6 1
Auxiliary 2 2 1 Pilot
28 Power Reset RL4–1 3
Supply Supply S/C Output
13 OP RL8
5 Contacts
D.C. Reset 1 Pilot 2 Change
Vx 14 Power O/C RL4–2 4 state for
Case earth Supply
RL4 6 pilot fail
1 2 2
3 4
7
RL5–1 9
Output
5 6
Contacts
7 8 11
9 10 MRTP 03 Change
8
11 12 +VE
RL5 state for
13 14
2 RL5–2 10
supply
16
RL1 RL2 RL3 RL1 RL2 RL3 12 fail
15 Case –1 –1 –1 Start –2 –2 –2
17 18
Earth t
19 20
21 22
23 24 Note 1.
25 26
(a) C.T. shorting links make before (b) & (c) disconnect.
27 28
Module terminal block (b) Short terminals break before (c).
viewed from rear (c) Long terminal.

Figure 4: Application diagram: pilot supervision relay 15kV isolation type MRTP 03

P1 P2
A A
S1 S2
B
C C B +
D.C. _
See Phase
Note 4 Rs Rotation
See Note 2(B)

13 See Note
Power 23 11
2(A)
supply 24
14 13
circuits 25
23 I S (A) 26 14
27
Case earth 24 28
1 2
25
3 4 I S( ) RL1
5 6 2 5
26 RL1–1 1 MBCI
7 8
27 3
9 10
I S (C)
11 12 6
13 14 RL1–2 2
28
15 16 Case earth MCRI 4
17 18 See Note 3
19 20
Case earth
21 22
See Note 3
23 24 Notes
25 26
1. (a) C.T. shorting links make before (b) & (c) disconnect. 2. (A) Connection for overcurrent start
27 28
Module terminal block (b) Short terminals break before (c). (B) Connection for overcurrent check
viewed from rear (c) Long terminals. 3. Earthing connections are typical only
4. C.T. connections are typical only

Figure 5: Application diagram: overcurrent relay type MCRI 01

5
Transformer Feeders
Scheme Pilot Supervision O/C
(use of transformer Insulation Start/Check Arrangement of Equipment
inrush current detector) Level (kV) (Viewed from front)
In the case of transformer feeders
where there is no circuit breaker A 5kV — — 1 1

separating the transformer from the


B 15kV — — 1 1
feeder, the phenomenon of
transformer magnetising inrush must C 5kV • — 2 1 3 1
be considered. This is a transient
4 1 1
condition which may occur at the D 15kV • —
instant of transformer energisation,
or immediately following a system E 5kV — • 1 5 1 5

voltage drop due to a nearby heavy


fault condition. Magnetising inrush F 15kV — • 1 5 1 5

current is not a fault condition and


G 5kV • • 2 1 5 3 1 5
therefore does not necessitate the
operation of protection equipment H 15kV • • 4 1 5 1 5
which, on the contrary, must remain
stable during the inrush transient. Table 1. Typical scheme arragements for plain feeders. See key below.
The inclusion of a type MCTH relay,
designed to provide a blocking Scheme Pilot Supervision Transformer
signal in the presence of transformer Insulation Arrangement Arrangement of Equipment
inrush currents, enables a pilot wire Level (kV) (Viewed from front)
differential protection scheme to be Pilots
I 5kV — 1 8 9 7 1 8
applied to a transformer feeder.
Where line and therefore
J 15kV — 1 8 9 7 1 8
transformer energisation can occur
at one end only of the transformer K 5kV • 1 8 2 9 7 1 8 3
feeder, then a MCTH unit would be
required on that side only. L 15kV • 1 8 4 9 7 1 8

When the feeder transformer is


M 5kV — 1 8 1 8
energised any resulting inrush
current will be detected by the N 15kV — 1 8 1 8
MCTH relay, the output blocking
unit of which will pick-up causing O 5kV • 1 8 2 1 8 3
the pilot wires of the Translay S to
1 8 4 1 8
be short-circuited. This will stabilise P 15kV •
the differential relay and prevent it
from responding to what would Table 2. Typical scheme arragements for transformer feeders. See key below.
otherwise appear to be an in-zone
No. Type of relay
fault. The immunity to operation due
to inrush current is coupled with fast 1 MBCI 01/02 Differential
fault clearance times and the built-in 2 MRTP 01 Pilot supervision and injection filter
3 MRTP 02 Injection filter
overcurrent detectors of the MCTH
4 MRTP 03 Pilot supervision
relay ensure that the blocking
5 MCRI 01 Overcurrent start/check
feature is overridden if a fault is
6 MVTW 01 Destabilising
detected in one phase whilst inrush
7 MVTW 03 Destabilising and Intertripping
is present in another. Schemes A to D can be fitted with relay types 6 or 7.
Schemes E to H can be fitted with type 6 which will provide
Symbols: destabilising if the overcurrent start/check relays (MCRI 01) have
operated. Schemes I to L must use type 7 or 8.
8 MCTH 01 Transformer inrush current detector
15kV Isolating transformer 9 MFAC 14 High impedance earth fault relay
10 MMLG Test plug/block
It is advisable on all schemes to include the test unit to facilitate
15kV Isolating transformer commissioning and routine testing. The unit will be situated on the
with injection filter right–hand side of the scheme.

6
Description Taking into account the relative Telephone type pilots
values of winding ratios and circuit When the pilots to be used are of
Differential protection resistance values, it can be shown the telephone type, an alternative
The differential feeder protection that the quantities delivered for limiter based on a zener diode is
circuit is derived from the well comparison in phase are: available to ensure that the
known Merz-Price circulating current (IX + 2IY) and (2IX + IY) maximum voltage which can appear
system but employs phase on the pilot system is within
comparators as the measuring where IX and IY are the currents fed prescribed limits. Pilot isolating
elements. This novel combination into the line at each end (for through transformers can be used in this
provides high stability performance faults IX=IY). The expressions are of arrangement also, both to provide
for external faults with the minimum opposite sign for values of IY which insulation to 15kV and also
of bias (restraint) quantity thereby are negative relative to IX and are indirectly to enable pilots of
ensuring that the low earth fault between 0.5IX and 2IX in value. The relatively high resistance to be used.
settings are effectively retained even system is stable with this relative
when load current is flowing. Figure polarity and operates for all values Pilot supervision
1 shows the basic circuit of IY outside the limits.
Figure 3 shows the arrangement for
arrangement. A summation current The phase comparator has angular pilot supervision in a pilot circuit
transformer T1 at each line end limits of ± 90° giving a circular bias insulated for 5kV. In this instance the
produces a single phase current characteristic in the complex plane. If injection filters and the supervision
proportional to the summated three the pilots are open circuited, current unit are assembled with the relay
phase currents in the protected line. input will tend to operate the relay. case. (Types MRTP 01/02). Figure 4
The neutral section of the summation Conversely, short-circuited pilots will shows the similar arrangement for
winding is tapped to provide cause the relay to restrain, holding its pilot circuits insulated for 15kV (Type
alternative sensitivities for earth contacts open. MRTP 03). The injection filters are
faults. then assembled as part of the
Transformers T1 and T2 also
The secondary winding supplies isolation transformer and have to be
provide the necessary insulation
current to the relay and the pilot isolated from the supervision relay.
barriers for static circuitry. The input
circuit in parallel with a non-linear The supervision isolation transformer
circuits of the phase comparator are
resistor (RVD). The non-linear provides the necessary 15kV
tuned to the power frequency so
resistor can be considered to be isolation barrier. For further technical
that the threshold of operation
nonconducting at load current information see Publication R6026.
increases with frequency. This de-
levels. Under heavy fault conditions sensitises the relay to the transient
Destabilise and Intertrip
it conducts an increasing current high frequency charging current
Facilities
and thereby limits the maximum that flows into the line when it is
secondary voltage. At normal energised. A further advantage MVTW01
current levels the secondary current provided by the tuned input is that Refer to Figure 6.
flows through the operating winding the waveform of the derived signal,
To on transformer T2 and then which may be severely distorted by Operation of the destabilising relay
divides into two separate paths, current transformer saturation, is (UN) results in the summation current
one through Ro and the other improved, ensuring high speed transformer in the differential relay
through the restraint winding Tr of operation under adverse conditions. being short circuited and the local
T2, the pilot circuit and resistor Ro In order to maintain the bias relay prevented from tripping. The
of the remote relay. characteristic at the designed value remote relay then sees a single end
it is necessary to pad the pilot loop feed condition and trips, provided the
The resultant of the currents flowing
resistance to 1kΩ. through current exceeds the no-load
in Tr and To is delivered by the third
fault setting of the protection (see
winding on T2 to the phase A padding resistor Rpp is provided Table 5 page 18). Typical operating
comparator and is compared with in the relay for this purpose. times are shown in Figure 7.
the voltage across Tt of Transformer
T1. The emf developed across Tt is Pilot isolation transformers Terminals 17 and 20 should
in phase with that across the When pilot isolation transformers normally be linked together on the
secondary winding Ts which is in are used, the range of primary taps destabilising relay. However, the
turn substantially the voltage across enables pilots of loop resistance up operating level of the remote
Ro. to 2.5kΩ to be matched to the equipment can be reduced to one
relay. The pilot insulation level is half of the normal fault setting
also raised to 15kV by these (under destabilising operation only)
transformers. if this link is omitted.

7
It should be noted that, with this link
omitted, if the destabilising relay Pilot isolation transformer P6 S2
17
UN is operated for longer than the Pilots
supervision time delay (6-10 P1 S1
seconds) an indication of pilot MBCI
failure will be given. This does not UN-1
17
apply if pilot isolating transformers
are used. 18
18 UN-2
19
When overcurrent elements are 19
UN-3
used to provide a starting or check
20
function there is no advantage in Case earth
removing this link since, for 1 2
11 UN
3 4 Vx(1)+
operation, the through current must 5 6
Vx(2)+
12 3

7 8 13
exceed the overcurrent setting. 9 10
Vx(3)+
14
11 12
13 14
MVTW 03 15 16 MVTW 01
17 18
A circuit diagram for the MVTW 03
19 20 Notes
type relay which depicts the 21 22 Case earth
1. (a) CT shorting links make
destabilising, intertrip and inverter 23 24 See note 2
before (b) & (c) disconnect
25 26
function is shown in Figure 8. On 27 28
Module terminal block
(b) Short terminals break before (c)
(c) Long terminals
energising the relay, a green LED viewed from rear
illuminates and the normally closed 2. Earthing connections are typical only

contacts of RL1 open to indicate the


supply is healthy and the inverter is Figure 6: Application diagram: destabilising relay type MVTW 01
operating.
The MVTW 03 incorporates a full however if the current level is lower A typical scheme for a delta–star
bridge inverter, which receives than the setting the remote MBCI power transformer is shown in
complementary square wave signals does not trip. To ensure intertripping Figure 9. The line current
from the oscillator circuit at a occurs the output relay (RL2) injects transformers are connected in star
frequency of 80Hz. This frequency a 20mA intertrip current into the on the delta side of the transformer.
was chosen because it lies pilots; the remote MBCI sees the Appropriate choice of CT ratios
sufficiently far from the pilot intertrip current as a differential ensures that for normal load and
frequency of 50 or 60Hz and current which causes it to trip. through fault conditions, equal
cancellation of the intertripping currents flow into the differential
For further technical information see
signal will not be caused by the beat tripping units (MBCI) at each end. A
Publication R6027.
frequency that may be produced. high impedance differential relay
The inverter is continually energised Transformer Inrush Current (type MFAC 14) is included in the
and supplies a transformer which Blocking neutral lead of the star-connected
isolates the pilots to 5kV from the line transformers to provide
Transformer inrush current B-N protection on the delta side of
input circuits. The transformer
detector feature the power transformer. The MFAC 14
supplies the intertripping current and
the power supply for the output Refer to Figure 9. high impedance differential relay
relay (RL2). may be used to initiate an
The principle of operation of the
intertrip unit (type MVTW 02).
Intertripping is initiated by applying transformer inrush current detector
a trip signal to terminal 11 which (MCTH) is based upon a unique
energises the output relay. feature of substantially zero for
significant periods in each cycle.
The signal is isolated from the pilots During load or fault conditions, the
to 5kV by the opto isolator. When current waveform remains at zero for
the output relay (RL2) is operated, negligible periods in each cycle. The
the local MBCI is made stable by relay detects these zero periods in
shorting terminal 18 to terminal 19. the inrush waveform and initiates a
This action destabilises the remote blocking relay, which causes the
MBCI. If the load current level is pilot wires of the Translay S relay to
greater than the differential current be short-circuited, preventing tripping
setting the remote MBCI trips; for transformer inrush current.
8
200

160

120.
Milliseconds

Kt = 6
80
Kt = 14
Kt = 20
40 Kt = 40

0
1 2 3 4 5 6 7 8 9 10 20 30 40 50 80
Current - Multiple of setting

Figure 7:Time characteristic for destabilised operation

Figure 8: Destabilising and intertripping relay type MVTW 03

Pilot isolation transformer P6 S2


17
Pilots
P1 S1
MBCI
17

18
18
19
19
11+VE
Trip send
Case earth RL2
2
1 2 RL2-2
3 4
5 6
7 8
9 10 RL2-1
11 12 13+VE
13 14 RL1-1 1
Power
15 16 Vx RL1
2 Supply fail
14–VE supply 1
17 18 MVTW 03
19 20
Supply
21 22
23 Case earth See note 2 healthy
24
25 26
27 28 Notes
1. (a) CT shorting links make 2. Earthing connections as shown is typical only
before (b) & (c) disconnect
Module terminal block
(b) Short terminals break before (c)
viewed from rear
(c) Long terminals

9
P2 P2 P1
A I i A
S1 S2 S2 S1
B II ii B

C III iii C
yn

N.E.R.

23 MCTH MCTH 23
24 24
17 17
25 25
26 26
19 19
27 27
28 28

23 MBCI 17 17 MBCI 23
24 24
25 Pilots 25
26 26
27 18 18 17 18 27
28 19 19 MVTW03 28

MFAC14 1
27
RVD3 3
28 11

Note1: It is essential that the current transformer connections are earthed at one point only.

Figure 9:Typical application diagram: overall protection of transformer feeders

N = 6 A–N
15 3
Voltage across summation current transformer primary – volts 1A relay

N = 6 C–N

N = 3 A–N Voltage across summation current transformer primary – volts

10 2

N = 3 B–N
5 1

A–C
Figure 10: Current circuit burden

A–B

1 2 1A relay
0
5 10 5A relay
Current in summation current transformer primary – Amps

10
200 Metrosil
Limiter

160

Pilot Voltage (V Peak)


120

Zener
80
Limiter
Figure 11: Pilot voltage characteristics

40

0 1 0 20 30
A-N fault current (x In)

2.0

1.8
Factor by which setting is increased

Without 15 kV pilot isolating trans.


With 15 kV pilot isolating trans. (Ks = 1.0 or 2.0)
With 15 kV pilot isolating trans. (Ks = 0.5)
(Note: Pilot isolating transformer ratio = 1:1)
1.6

1.4
Figure 12:
Effect of pilot capacitance and pilot
isolating transformers on setting
1.2

1.0
0 1 2 3 4 5
Pilot intercore capacitance -m F

%In %In A-N


Earth Fault Setting 70 Earth Fault Setting
Ks = 2.0 Ks = 1.0
N=3 N=6 N=3 N=6
60
C-N
A-N B-N
100 50
A-N
C-N
80 40
B-N
A-N B-N
60 30
Figure 13: C-N C-N
B-N
Minimum earth fault current for 40 20
operation with through load
20 10

0 0.5 1.0 1.5 2.0 0 0.5 1.0 1.5 2.0


Through Load (xIn) Through Load (xIn)

11
CTs
CTs

RL RL RL

Figure 14:
Mesh type switchgear arrangements CTs

End A End B
Pilots
Relay Relay

240

200
Operation time (Milliseconds)

160

120

Figure 15: 80
Time characteristics Kt = 6
for internal faults Kt = 14
40 Kt = 20
Kt = 40

0
1 2 3 4 5 6 10 20 30 40 50 60 80 100
Current (multiples of setting)

60
Induced pilot loop voltage to operate

40

Figure 16: 20
Response to spurious
induced loop voltage in pilots

0
0.5 1.0 1.5 2.0
Setting multiplier – Ks

12
Transformer (Dy 11)

Feeder

Delta Star
23 25 27 17 17 23 25 27
MFAC N.E.R.
MCTH MCTH
inrush A B C REF inrush A B C
detector detector
24 26 28 19 19 24 26 28

MBCI MBCI

23 23
25 1.25 17 17 1.25 25
27 1 1 27

24 6 6 24
18 Pilots 18
26 26
28 28

Figure 17: Overall protection of transformer feeders showing connections to MBCI relay

13
Technical Data Durability • High frequency disturbance
(MBCI Relay) • Loaded contact IEC 60255-22-1: 1988 Class III
10,000 operations minimum 2.5kV peak between independent
Current rating (In) • Unloaded contact circuits and case.
1A, 2A or 5A 100,000 operations minimum
1.0kV peak across terminals of the
Reset time same circuit.
Frequency rating
50Hz or 60Hz Less than 100ms • Fast transient disturbance
IEC 60255-22-4: 1992 Class IV
Current withstand ratings Indication
4.0kV, 2.5kHz applied directly to
Duration (s) Differential A non-volatile LED trip indicator is auxiliary supply.
Continuous 2In used. If the auxiliary supply is lost
the LED will return to the same state IEC 60801-4: 1988 Level 4
3 45In
when the supply is restored. 4.0kV, 2.5kHz applied to all inputs.
2 55In
1 80In • Surge immunity
Stability level
0.5 100In IEC 61000-4-5: 1995 Level 3
Table 2 The stability of the protection for
2.0kV peak, 1.2/50ms between all
through faults is greater than 50In
groups and case earth.
Current circuit burden
High voltage withstand 2.0kV peak, 1.2/5-ms between
Highest phase burden
(with three phase rated current) • Dielectric withstand terminals of each group.
6VA N=6 IEC 60255-5: 1977 • EMC compliance
3.5VA N = 3 2.0kV rms for 1 minute between all 89/336/EEC
At setting current 0.5VA terminals and case earth. Compliance to the European
Auxiliary supply 2.0kV rms for 1 minute between all Commission Directive on EMC is
terminals of independent circuits, claimed via the Technical
Rated Operative Current drain (mA)
with terminals on each independent Construction File route.
voltage (Vx) range (V) Quiescent Operated
circuit connected together. EN 50082-2: 1994
24/27 19.2–32.4 30 17.5
30/34 24–37.5 15 175 5.0kV rms for 1 minute between EN 50082-2: 1995
48/54 37.6–72 15 175 pilot terminals and all other Generic Standards were used to
110/125 87.5–150 15 90 terminals and case earth. establish conformity.
1.0kV rms for 1 minute across • Product safety
Contacts
normally open contacts. 73/23/EEC
Contact arrangements
2 make and 2 change-over • High voltage impulse Compliance with the European
(See Figure 2) Commission Low Voltage Directive.
IEC 60255-5: 1977
Three positive and three negative EN 61010-1: 1993/A2: 1995
Contact ratings impulses of 5.0kV peak, 1.2/50µs, EN 60950: 1992/A11: 1997
• Make and carry for 0.2s 0.5J between all terminals and all Compliance is demonstrated by
7500VA subject to maxima of terminals and case earth. reference to generic safety
30A and 300V ac or dc standards.
Electrical environment
• Carry continuously
• DC supply interruption Atmospheric environment
5A ac or dc
• Temperature
• Break IEC 60255-11: 1979
ac 1250VA The unit will withstand a 10ms IEC 60255-6: 1988
dc 50W resistive interruption in the auxiliary supply, Storage and transit –25°C to
25W inductive under normal operating conditions, +70°C
L/R = 0.045s without de-energising. Operating
subject to maxima of 5A and 300V –25°C to +55°C
• AC ripple on dc supply
IEC 60068-2-1: 1990 Cold
IEC 60255-11: 1979
The unit will withstand 12% ac IEC 60068-2-2: 1974 Dry heat
ripple on the dc supply.

14
• Humidity Pilot voltage • 1.1 times the steady state line
The voltage applied across the charging current for solidly
IEC 60068-2-3: 1969
pilots varies with fault current as earthed systems
56 days at 93% RH and 40°C
shown in Figure 12. For normal • 3.2 times the steady state line
• Enclosure protection through load conditions the peak charging current for resistance
IEC 60529: 1989 pilot voltage will be in the order of earthed systems
IP50 (dust protected) 50V rising to a maximum of: 200V
for MBCI 01, 80V for MBCI 02 • 1.9 times the steady state line
• Mechanical environment charging current for resistance
under fault conditions.
Vibration earthed systems with one relay
When pilot isolation transformers per phase
IEC 60255-21-1: 1988
are used this value of voltage is
Response Class 1 In all cases, allowance should be
multiplied by √KM .
made for some system overvoltage.
Pilots Note: Types MBCI 01 and 02 are This requirement ensures stability
not compatible. Relays should during external ground faults which
Pilots isolation be of the same type at either will cause the three phase
end. capacitance currents to be unequal,
Pilot isolation transformers are
required when any longitudinally resulting in an increased output
Pilot current from the summation transformer.
induced voltage in the pilot circuit is
likely to exceed 5kV: in effect this The pilot current is typically 30mA
The high frequency line in-rush
means when protecting feeders for normal through load conditions
currents can be neglected because
operating at voltages in excess of and rises to a maximum of 300mA
the setting of the relay automatically
33kV, unless these are short in under through fault conditions.
increases at high frequencies by a
length. Line charging current factor:
The use of pilot isolation Inrush frequency
In applications pertaining to cables,
transformers also extends the Rated system frequency
with or without in zone shunt
acceptable range of pilots. This is reactors, and overhead lines, it is
achieved by the matching ratios Overcurrent starter/check
necessary for the most sensitive fault
available as shown in Table 4. element settings
setting to be increased to:
The maximum resetting value of the
Pilots overcurrent elements is not less than
90% of the operating value. Thus,
KM 0.8 1.0 1.2 1.5 2.5 Matching ratio to ensure that they will reset when
Loop resistance 800 1000 1200 1500 2500 Ω the current is restored to the full
load level, the setting should be at
Capacitance 6.25 5 4.2 3.3 2 µF
least 1.2 times the maximum
Terminals P1-P6 P1-P5 P1-P4 P1-P3 P1-P2 anticipated through load current.
Table 4 The setting of the earth fault
elements should be at least 1.2
Where KM = (turns rotation)2 for respective tap of pilot isolation times any standing zero sequence
transformers. current and not higher than 80% of
the minimum earth fault current.
When pilot isolation transformers are not used KM = 1.
The value chosen as an assessment
The optimum value for KM is the nearest value Rp/1000 in Table 4, where
of minimum earth fault current must
Rp is the measured pilot loop resistance.
be conservative, due allowance
There are two types of pilot isolation transformers: ZC0244-002 for schemes being made for all aspects of
without pilot supervision: HN0068-001 for schemes with pilot supervision. minimum system operating
The latter includes the injection filter for the pilot supervision circuit. conditions and fault impedance;
The pilot padding resistor (Rpp) at each end should be set to: alternatively, a larger tolerance
below the nominal minimum fault
1/2(1000 – Rp/KM) current value is advisable.

15
Unit Protection of Plain Minimum operation for earth Kt = the selected time-dependent
faults with through load constant (40, 20, 14, 6 or 3)
Feeders
Bias being a direct function of *Note; For all applications at or
Fault settings for plain through current, increases minimum above 220kV where X/R
feeders operating current with through load. ratios are large use:
The input transformer has a Figure 14 shows the minimum earth
fault current required for various VK ≥ N Kt In (RCT + XRL)
summation ratio of 1.25:1:N where
N = 3 for normal use. N = 6 is levels of through load. It is not necessary for the line
used where low earth fault settings The curves shown are for the first current transformers at the two ends
are needed. The minimum relay to trip. The second relay will of the protected system to have the
operating current will therefore be trip sequentially provided the same knee point voltage.
dependent on the phase or phases resulting in-feed at that end is above Differences of up to 4:1 can be
involved in the fault. The minimum the setting value. To ensure that tolerated provided both are above
earth fault current (If) should be simultaneous tripping will occur the the minimum value. However, the
greater than twice the least sensitive minimum fault current should be three line current transformers at
earth fault setting to ensure rapid greater than twice the minimum any one end should have similar
fault clearance. operating current given in Figure 14. magnetising characteristics.

The range setting of fault settings is • Magnetising current:


Line current transformer
shown in Table 5. In order that the minimum effective
requirements for plain feeders
The minimum operating current of operating current of the relay
Class X BS 3938
the relay will be increased by any remains low, it is necessary to
shunt impedance connected across * VK ≥ 0.5N Kt In (RCT + XRL) apply a limit to the value of the
the pilot wires, for example, pilot magnetising current demanded by
Where
capacitance and the magnetising the line current transformers:
path of the pilot isolation VK = knee point voltage of current
IM ≤ 0.05 In at 10 V
transformers. The effect of the pilot transformers for through In
capacitance is shown in Figure 12. fault stability
• Mesh type switchgear arrangements
Values of Ks from 0.5 to 1.0 are RCT = resistance of current
provided to achieve effective fault transformer secondary The relay may be fed by parallel
setting equal to the nominal value circuit (Ω) connected current transformers as
indicated in Table 5. This is shown in Figure 15. It is essential to
RL = lead resistance of single
achieved by single balance the lead resistance in the
lead from relay to current
circulating secondary current path
end injection tests during transformers (Ω)
to ensure stability for a through
commissioning. Values of Ks from X = 1 for 4 wire connections busbar fault. Connecting the current
1.0 to 2.0 are between the main current transformers as shown in Figure 15
used to increase the setting when transformers and the relay: will result in the required balance
the application demands. Refer to 2 for 6 wire connections being obtained. It is essential that
section: Line charging current. N = relative neutral turns on the current transformers at the same
summation transformer end should have similar
winding (3 or 6, as shown magnetising characteristics. The
under heading Current value of RCT to be used in
Settings) calculations should be the resistance
of one current transformer plus the
Differential Fault Settings resistance of one lead between the
(Summation ratio = 1.25/1/N) N=3 N=6 two parallel connected current
transformers. The value of RL should
Ks is a setting multiplier A–N 0.19Ks.In 0.12Ks.In be the resistance of a single lead
and may be varied B–N 0.25Ks.In 0.14Ks.In from the common connection of the
from 0.5-2.0 C–N 0.33Ks.In 0.17Ks.In current transformers to the relay.
In is the rated relay current A–B 0.8Ks.In
B–C 1.0Ks.In
C–A 0.44Ks.In
A–B–C 0.5Ks.In
Table 5

16
• Methods of reducing the current Stabilising resistance Feeder 11kV 300A rating
transformer requirements: V
Rs = K Ω but not greater than 122 Ω Tee Transformer Fuse Ks Kt
In general the larger the current 40In In rating(kVA) rating (A)
transformer the better the overall 300 20 1 40
performance. However, when Note: This resistor is not required 400 25 1.7 40
current transformer size is critical for single phase protection or 400 25 1.5 6
the following notes should prove when Translay S is fed from 500 30 1.75 3
helpful. delta connected current Table 6
• The operation time varies with transformers.
The table above refers to individual
fault current as shown in Figure 16.
Additional requirements: teed loads. When smaller loads are
Stability is maintained with smaller
• It is a stability requirement that connected at separate locations, on
current transformers if the value of
the relays at both ends have the the basis that only one will be subject
Kt is reduced.
same value of N & Kt selected. to a fault at any instant, the
This will of course result in the aggregate load may be greater. For
operation time increasing, typical • It is preferred, although not example twelve 100kVA transformers
operation times being: absolutely essential, that the each protected by 10A fuses could
equipment at the twoline ends have be connected to the above line, with
Kt 40 20 14 6 3 the same rated current In. main protection settings Ks = 1 and
Time at
Kt = 40. Similarly for ten 300kVA
5x setting 30 50 65 90 300 (ms) Small in-zone teed loads
transformers each protected by 20A
• Kt= 20 will suit most current Small three phase loads may be fuses, relay settings Ks = 2.0 and Kt
transformers on distribution systems connected to the feeder within the = 20 would be suitable. In general
Kt = 40 is the preferred setting for protected zone; normally these will the aggregate tee-off load should not
EHV systems where high speed be supplied by a delta/star exceed 0.25Ks x current transformer
operation is required transformer connected to the line rating.
through HRC fuses. Substantial faults
• It should be noted that the knee
on this circuit will cause the fuses to Maximum induced pilot loop
point requirement increases with the
blow very quickly before the voltage
nominal current rating In.
differential relay can operate. Ideally the pilot cores should be
Advantage is therefore obtained by
using a low value of rated current The limiting condition is a value of wormed (twisted together) so that
eg. 1A or even 0.5A. fault current which will just produce the induced loop voltage is kept to
an A–C phase setting current in the a minimum. The required level of
• Wires may be connected in this voltage to cause operation
relay: this current must cause the fuse
parallel to reduce the lead resistant varies with the setting multiplier Ks
to operate quickly enough to
(RL) and hence the current as shown in Figure 17.
discriminate. Most fusing time curves
transformer requirements.
show pre-arcing time and some
• If the relay is fed from delta allowance must be made for the
connected line current transformer arcing period.
then N = 1.
To accommodate the largest teed
• If one relay is used per phase load, use may be made of the Ks
then assume N = 1 (setting multiplier) adjustment, and/or
selection of a value of Kt
corresponding to a lower operating
speed.
The particulars tabulated below for
teed loads connected to a fused
11kV feeder may be helpful as a
general example.

17
Unit Protection of Line Current Transformer
Transformer feeders Requirements for Transformer
Vs = If ( I3n + RCT + RL)
2

Feeders:
Fault Setting Operating times less than 80ms will Where

The relay internal summation is be achieved and through fault Vs = setting of MFAC (V)
identical to that used for plain stability assured provided the
following CT requirements are If = maximum through fault
feeders but the turns ratio used is current referred to CT
2.25:6. This is connected as shown satisfied (Kt = 14):
secondary for which
in Figure 18 and will result in For star connected CTs stability is required (A-rms)
secondary settings as given in the
Vk ≥ 50 In 2.22 + RCT + RL
( In ) In = rated currency of relay (A)
table below:
RCT = resistance of secondary
Relay setting in amps = Ks x In For delta connected CTs winding (W)
constant in table below
Vk > 50In 9.72 + RCT + RL
( ) RL = resistance of a single lead
A to N 0.44 √3 In
B to N ∞ from the CTs to the relay (Ω)
If longer operating times can be
C to N 0.17 The effective primary operating
tolerated CT requirements to the
A to B 0.44 circuit (Iop) of the MFAC 14 is
following formulae will give operating
B to C 0.17 given by:
times less than 160ms and assured
C to A 0.12
through fault stability (Kt = 14): Iop = n(IR + NIIu)
3 Phase 0.14
For star connected CTs Where
Table 7
Vk ≥ 35 In 2.22 + RCT + RL
( In ) IR = relay operating current and
Where
Ks = setting multiplier which may be metrosil current at setting
For delta connected CTs voltage (see MFAC
adjusted between 0.5 and 2.0
Vk > 35In 9.72 + RCT + RL publication)
In = relay rated current. √3 ( In )
Iu = current transformer
NB. The Figures quoted in this table Where magnetising current at
are those to be expected under Vk = kneepoint voltage (V) setting voltage (A)
conditions of secondary In = rated current of relay (A)
injection testing Nl = number of connected
RCT = resistance of CT secondary current transformers
Note 1: As shown in Figure 18 winding (Ω)
there is a restricted earth n = current transformer turns ratio
RL = resistance of a single lead
fault relay in the neutral of The following notes on this
from the CTs to the relay (Ω)
the star connected CTs on application are also important:
the delta side of the power Note 1: Operating times are quoted
• A setting of 14 is recommended
transformer. This provides at 5x rated current.
for Kt to ensure sufficient time for
protection against earth
Note 2: The above equations for inrush blocking. Tripping for internal
faults on the delta side of
through fault stability are faults will then occur (typically)
the power transformer
applicable for up to 20% within 60 – 80 ms.
when the infeed is into the
CT mismatch.
delta. It will provide • The N = 6 setting on the MBCI
settings lower than any of Note 3: In normal applications, to relay must be used to achieve
the phase to neutral ensure the fast operation of increased sensitivity.
settings given above. the MFAC, the knee point
• Where the CT lead resistance is a
voltage Vk must be greater
Note 2: The MBCI relay, when used predominant part of the CT burden
than twice the voltage
in the transformer feed at one, or both, line ends then the
setting Vs of the MFAC
application, does not use of 1A line CTs is recommended.
relay. However, when used
require a stabilising The selected rating of current
with the MBCI/MCTH relay
resistor. transformers must be the same as
combination, lower knee
the relays (MBCI and MCTH) which
point voltage, down to Vs,
they supply.
may be used provided
operating times up to the
scheme operating time of
80ms are accepted.

18
• Additional conductors may be Cases Information Required
connected in parallel in order to
Relay type MBCI is provided in with Order
reduce the lead resistance (RL) and,
case size 6 as shown in Figure 18. Basic scheme reference
hence, the current transformer
requirements. (refer to Table 1)
Auxiliary Equipment
• The pilot resistance should not Type(s) of relay
exceed 700W. For outline drawings of pilot
Type of pilots (private or telephone)
isolation transformers, and
• With 15kV pilots, the MCTH stabilising resistor, see Figures 20, Pilot loop resistance and intercore
output contacts should be connected 21, 22 and 23. capacitance values.(This information
on the relay side of the isolating is required to determine whether pilot
transformer to terminate numbers isolating transformers are required for
Associated Publications
17 and 18 of the MBCI relay. matching purposes.)
R6001 Midos system
• The MCTH overcurrent settings for Pilot insulation level (5kV or 15kV). Is
each phase, set by 3 front-mounted R6026 MRTP supervision for ac pilot supervision equipment required?
potentiometers (one per phase), pilot circuits
should be set at least 50% above Is the overcurrent relay required?
R6027 MVTW destabilising and
the maximum possible load current. Is the destabilising facility or
intertripping relay
• The steady state magnetising destabilising/intertrip facility
R6028 MCRI instantaneous required?
current must not exceed the three
overcurrent relay
phase fault setting of the MCBI Pilot voltage: Metrosil (MBCI 01) or
relay. For a Ks = 1 setting, the three R6004 MMLG/B test block Zener limiting (MBCI 02).
phase fault setting is 14% of rated R6006 MSTZ power supply See Figure 11.
current. If the transformer is likely to
be subjected to overfluxing, with the R6007 MFAC high impedance Current rating
corresponding increase in steady differential relay Frequency rating
state magnetising current, then the R6066 MCTH transformer inrush Auxiliary dc supply rating
three phase setting must be current detector relay
permanently set above this higher Auxiliary ac supervision supply rating
magnetising current by increasing
AC intertrip supply rating
Ks.

103.6
149
4 holes ø 4.4 24

168 159

Push button 151


projection 10 max
Panel cut-out:
Flush mounting fixing details

32 212 25 min.

177 157 max.

Reset
Figure 18:
155 Flush mounting 11 Case outline size 6

All dimensions in mm

19
P1 2.5 1.5
1.2 1.0 0.9 S1 S2

Injections 172 mm
Inputs

X1 X2

340 mm

6 fixing holes, M6 clearance

64.5 mm

154 mm

30 mm 116 mm 9 mm
176 mm

Figure 19:
Pilot isolation transformer with filter.With insulation for 15kV

244 mm
176 mm 190 mm
45 mm

171.5 mm

8-M6 Terminals

9 mm
4 Fixing holes, M6 clearance

64.5 mm

Figure 18:
Pilot isolation transformer without filter.
With insulation for 15kV
30 mm 116 mm

20
19 mm 134 mm 19 mm 69 mm

S2

98 mm

S2

2 off M5 studs
2 off M5 studs

2 off fixing holes M5

52 mm 69 mm

8.5 mm 50 mm 52 mm

Figure 21:
Pilot supervision isolation transformer.With insulation for 15kV

2BA connection
screws

354 mm

48 mm

2 holes
6.5 mm 310 mm 48
mm
342 mm

Figure 21:
Stabilising resistor

21
© 2003 ALSTOM - 100300 - Electronic File
Publication: MBCI/EN BR/Ya

Transmission & Distribution Energy Automation & Information, Le Sextant, 3 avenue André Malraux, 92300 Levallois-Perret. France
Tel: +33 (0) 1 41 49 20 00 Fax: +33 (0) 1 41 49 24 85 energy-automation.information@tde.alstom.com www.tde.alstom.com
Contact Centre on line 24 hours a day : +44 (0) 1785 25 00 70

ALSTOM, the ALSTOM logo and any alternative version thereof are trademarks and service marks of ALSTOM.
MiCOM is a registered trademark of ALSTOM. Other names mentioned, registered or not, are the property of their respective companies.
Our policy is one of continuous development. Accordingly the design of our products may change at any time. Whilst every effort is made to produce up to date literature, this
brochure should only be regarded as a guide and is intended for information purposes only. Its contents do not constitute an offer for sale or advice on the application of any product
referred to in it. We cannot be held responsible for any reliance on any decisions taken on its contents without specific advice.

You might also like