Professional Documents
Culture Documents
GENERAL
SECTION 1 - GENERAL
1.3.1 Notes
1.3.2 Abbreviations
S1-1
SECTION 1
GENERAL
If at any time it should appear to the E.R. that the actual progress
of the Works does not conform to the approved programme
referred to herein before the Sub-Contractor shall submit for
S1-2
SECTION 1
GENERAL
Should part of the site made use by the Sub-Contractor shall later
be required for the Works as a result of variation works and
amendments, the Sub-Contractor shall clear the Site and re-erect
their offices, stores, temporary workshops etc. entirely at his own
cost.
Any costs incurred under this Section shall be deducted from the
Contract Sum. No claim for loss of profit under the Conditions of
this Contract shall be deemed to have arisen. No action taken
under this Section shall in any way affect or modify the right of
the Employer to claim for damages in the event of the Sub-
Contractor’s failure to complete the Works by the agreed date.
S1-3
SECTION 1
GENERAL
S1-4
SECTION 1
GENERAL
Before the Works or any part thereof are commenced, the Sub-
Contractor shall verify the levels of the existing ground surface
within the area where earthworks are to be performed and the
locations and bed levels of water-courses.
These may differ from the locations and levels shown on the
Drawings owing to changes which could have taken place during
the interval between the original survey and construction.
From the commencement of the Works to the date the Works are
taken over by the Employer, the Sub-Contractor shall take full
responsibility for the care thereof together with all temporary
works and in case any damage loss or injury shall happen to the
Works or to any part thereof or to any temporary works from any
cause whatsoever the Sub-Contractor shall at his own cost repair
and make good the same so that on completion the Works shall be
in good order and condition and in conformity with every respect
with the requirements of the Contract and the E.R.’s instructions.
The Sub-Contractor shall also be liable for any damage to the
Works occasioned by him in the course of any operations carried
out during the Defects Liability Period.
S1-5
SECTION 1
GENERAL
If the Project Manager needs to be absent from Site for more than
three (3) consecutive days he shall give prior notice to the E.R.
who may require the Sub-Contractor to temporarily appoint
another Project Manager.
The E.R. or his representative may at any stage of the Works carry
out inspection, measurement and tests on any part of the Works to
ensure compliance with the requirements of this Specification and
of the Drawings. The Sub-Contractor shall provide the necessary
attendance whenever required by the E.R. or his representative.
Notwithstanding any tests which may have been carried out off the
Site the E.R. shall be empowered to order further tests of any
materials or goods to be made on the Site and to reject such
materials or goods should they fail to pass such tests on Site.
Before any part of the Works is permanently covered up, the Sub-
Contractor shall give due notice to the E.R. for the inspection and
S1-6
SECTION 1
GENERAL
The Sub-Contractor shall provide and maintain a site office for the
use of the E.R. and his supervisory staff, all in accordance with the
relevant Drawings inclusive of all furniture, fittings and equipment
as given in Appendix 1C of his charges for the construction of the
E.R.’s office and laboratory.
Where electricity and piped water are available from public utility
authorities the Sub-Contractor shall arrange for the site office to
be connected to the electricity and water supplies.
S1-7
SECTION 1
GENERAL
S1-8
SECTION 1
GENERAL
All vehicles shall be available for use within two (2) weeks from
the date of possession of Site. In the event that the Sub-Contractor
fails to make available any of the vehicles within the specified
time, the E.R. may hire a suitable vehicle outside the Contract and
debit any incurred costs from subsequent payments due to the Sub-
Contractor.
S1-9
SECTION 1
GENERAL
The Sub-Contractor shall provide for the sole use of the E.R. and
his staff all such instruments, equipment and chainmen as the E.R.
may require to enable him to check the accuracy of the Sub-
Contractor’s setting out and any measurements taken. The
chainmen shall have knowledge of Bahasa Malaysia or English
and as far as possible the same men shall be provided throughout
the Contract period.
S1-10
SECTION 1
GENERAL
S1-11
SECTION 1
GENERAL
S1-12
SECTION 1
GENERAL
To this end the Sub-Contractor shall erect and maintain on the Site
and at prescribed points on the approaches to the Site, all traffic
signs, signals and warning lights necessary for the direction and
control of traffic.
The sizes of all such signs and the lettering and wording thereon
shall be as shown on the Drawings and approved by the E.R.
before erection. Construction and excavation shall be sign posted
and, during periods of darkness shall be lit to the approval of the
E.R.
S1-13
SECTION 1
GENERAL
S1-14
SECTION 1
GENERAL
The Sub-Contractor shall provide at his own risk and cost all
water, lighting and electric power where required for use in the
Works and shall pay all costs, fees and charges and comply with
all safety regulations and statutes in connection therewith.
S1-15
SECTION 1
GENERAL
S1-16
SECTION 1
GENERAL
1.32 DRAWINGS
S1-17
SECTION 1
GENERAL
1.33.1 Compliance
S1-18
SECTION 1
GENERAL
No later than thirty (30) days after the commencement date, the
Sub-Contractor shall submit to the E.R. for approval a Site Safety
Plan. The Site Safety Plan shall be properly integrated with any
approved system safety plan prepared by or on the behalf of the
Employer and shall specify in detail the Sub-Contractor’s
approach to maintaining the safest possible work environment and
ensuring protection against accident and injury to the workers and
other persons and protection of the Works, Plant, Sub-Contractor’s
Equipment and other property from damage, loss or destruction.
The Site Safety Plan shall include but shall not be limited to the
following :-
S1-19
SECTION 1
GENERAL
The E.R. may direct the Sub-Contractor to suspend any part of the
Work if, in the E.R.’s opinion, an unsafe condition exists or is
likely to result, until the Sub-Contractor takes proper corrective
action. The Sub-Contractor shall not be entitled to any payment in
respect of any such suspension or to any extension of time in
respect thereof and any cost to the Employer of implementing
S1-20
SECTION 1
GENERAL
S1-21