Capital Improvement Program
Proposed Budget
2007 Facilities Capital Program
Browning Elementary School
Renovation 120
Budget Adjustments Total Original Program Budget 397 (397) 6 -
Summary for New Construction and Renovation
Project Data for New and Renovation Existing Building(s) Sq. Ft. New Sq. Ft. Demolition Sq. Ft. Proposed Total Sq. Ft. # of T-Buildings (2007) Student Enrollment (2007) New Construction and Renovation Cost Total Estimated New Construction Cost Total Estimated Renovation Co
Capital Improvement Program
Proposed Budget
2007 Facilities Capital Program
Browning Elementary School
Renovation 120
Budget Adjustments Total Original Program Budget 397 (397) 6 -
Summary for New Construction and Renovation
Project Data for New and Renovation Existing Building(s) Sq. Ft. New Sq. Ft. Demolition Sq. Ft. Proposed Total Sq. Ft. # of T-Buildings (2007) Student Enrollment (2007) New Construction and Renovation Cost Total Estimated New Construction Cost Total Estimated Renovation Co
Capital Improvement Program
Proposed Budget
2007 Facilities Capital Program
Browning Elementary School
Renovation 120
Budget Adjustments Total Original Program Budget 397 (397) 6 -
Summary for New Construction and Renovation
Project Data for New and Renovation Existing Building(s) Sq. Ft. New Sq. Ft. Demolition Sq. Ft. Proposed Total Sq. Ft. # of T-Buildings (2007) Student Enrollment (2007) New Construction and Renovation Cost Total Estimated New Construction Cost Total Estimated Renovation Co
Capital Improvement Program Browning Elementary School
Proposed Budget Renovation
2007 Facilities Capital Program 120 Budget Adjustments
Original Admin B C D F Total Original
Summary for New Construction and Renovation Adjustment Trustee Allot P1 HVAC Athletics Sci Equip Adj Program Budget Budget Project Data for New and Renovation Existing Building(s) Sq. Ft. 39,514 Proposed Classroom Capacity - - New Sq. Ft. 0 Current Classroom Capacity 397 397 Demolition Sq. Ft. 0 New Seats Gained (397) (397) Proposed Total Sq. Ft. 39,514 Proposed Core Capacity - - # of T-Buildings (2007) 9 Current Site Acres 6 6 Student Enrollment (2007) 530 Proposed Site Acres - -
New Construction and Renovation Cost
Total Estimated New Construction Cost - - - - - - - Total Estimated Renovation Cost 1,868,310 - - - - - 1,868,310 Total Estimated New Construction and Renovation Cost 1,868,310 - - - - - 1,868,310 Other Program Costs for New and Renovation Proposed Actual T-Building Costs - - - - - - - Contingency (Various% of Construction Costs) 93,416 9.20% 171,913 - - - - - 171,913 Design Fees (Various% of Construction Costs) 168,148 6.44% 120,339 - - - - - 120,339 Management Fee (Various% of Construction Costs) 74,732 8.37% 156,420 - - - - - 156,420 Soft Costs, Testing, Surveys, Printing, etc. (Various% of Constr. Costs) 0 13.42% 250,666 - - - - - 250,666 Project Reserves 224,778 - - - - - 224,778 Total Estimated Other Program Costs for New and Renovation 924,116 - - - - - 924,116 Furnishings/Equipment for New and Renovation Proposed Actual Furnishings and Equipment (Various% of Constr. Cost) 186,831 0.00% - - - - - - - Replacement Media Center Books & Materials - - - - - - - Media Center Books & Materials for Increased Capacity - - - - - - - Technology Equipment ($600,000 + $5.00 per sq ft) - - - - - - - Technology Cabling 51,574 - - - - - 51,574 Other Equipment - - - - - - - Science Equipment and Furnishings Upgrades - - - - - - - Total Estimated Furnishings and Equipment for New and Renovation 51,574 - - - - - 51,574 Land Purchase for New and Renovation Additional Site Area 0 acres x $1 per acre = - - - - - - - Total Estimated Land Purchase for New and Renovation - - - - - - -
Grand Total of New Construction and Renovation Cost 2,844,000 - - - - - 2,844,000
Anticipated Bid Date January-11 11/4/2010 TEA 120 Page 1 of 5 Proposed Budget v:9/2010 Capital Improvement Program Browning Elementary School Proposed Budget Renovation 2007 Facilities Capital Program 120 Estimate Date September-07 Grand Total with Inflation 2,844,000 - - - - - 2,844,000
11/4/2010 TEA 120 Page 2 of 5 Proposed Budget v:9/2010
Capital Improvement Program Browning Elementary School Proposed Budget Renovation 2007 Facilities Capital Program 120
Original Admin B C D F Total Original
New Construction Adjustment Trustee Allot P1 HVAC Athletics Sci Equip Adj Program Budget Budget New Construction Costs Building Construction 0 s.f. x $0 per s.f. = - - Site Development 0 acres x $0 per acre = - - Site Utilities - - Demolition Costs - - Other Costs (Specify) - - Total Estimated New Construction Cost - - - - - - - Other Program Costs New Construction Proposed Actual T-Building Costs - - Contingency (5% of Construction Costs) 0 0.00% - - Design Fees (6.5% of Construction Costs) 0 0.00% - - Management Fee (3.5% of Construction Costs) 0 0.00% - - Soft Costs, Testing, Surveys, Printing, etc. (10% of Construction Costs) 0 0.00% - - Project Reserves - - Total Estimated New Construction, Soft Costs & Fees - - - - - - - Furnishings/Equipment for New construction Proposed Actual Furnishings and Equipment (10% of Construction Cost 0 0.00% - - Replacement Media Center Books & Materials - - Media Center Books & Materials for Increased Capacity - - Technology Equipment ($600,000 + $5.00 per sq ft) - - Technology Cabling - - Other Equipment - - Science Equipment and Furnishings Upgrades - - Total Estimate New Construction Furnishings and Equipment - - - - - - -
Land Purchase For New Construction
Additional Site Area 0 acres x $0 per acre = - - Total Estimated Land Purchase for New Construction - - - - - - -
Total Estimate New Construction Costs(Current $) - - - - - - -
11/4/2010 TEA 120 Page 3 of 5 Proposed Budget v:9/2010
Capital Improvement Program Browning Elementary School Proposed Budget Renovation 2007 Facilities Capital Program 120
Original Admin B C D F Total Original
Renovations to Existing Facility Adjustment Trustee Allot P1 HVAC Athletics Sci Equip Adj Program Budget Budget Construction Costs for Renovations to Existing Facility Site 73,766 73,766 Roofing - - Structural - - Exterior 49,553 49,553 Interior 362,243 362,243 Mechanical 437,007 437,007 Electrical 316,657 316,657 Plumbing 296,883 296,883 Fire/Life Safety 3,868 3,868 Technology Infrastructure 162,092 162,092 Conveyances 15,863 15,863 Specialties 150,378 150,378 Other Needs - - Science Infrastructure - - Rounding Adjustments - Total Estimated Renovation Cost 1,868,310 - - - - - 1,868,310 Other Program Costs Renovations to Existing Facility Proposed Actual T-Building Costs - - Contingency (5% of Construction Costs) 93,416 9.20% 171,913 171,913 Design Fees (9% of Construction Costs) 168,148 6.44% 120,339 120,339 Management Fee (4% of Construction Costs) 74,732 8.37% 156,420 156,420 Soft Costs, Testing, Surveys, Printing, etc. (10% of Construction Costs) 250,666 250,666 Project Reserves 224,778 224,778 Total Estimated Renovation, Soft Costs & Fees 924,116 - - - - - 924,116 Furnishings/Equipment for Renovations to Existing Facility Proposed Actual Furnishings and Equipment (10% of Construction Cost 186,831 0.00% - - Replacement Media Center Books & Materials - - Media Center Books & Materials for Increased Capacity - - Technology Equipment ($600,000 + $5.00 per sq ft) - - Technology Cabling 51,574 51,574 Other Equipment - - Science Equipment and Furnishings Upgrades - - Total Estimated Renovation Furnishings and Equipment 51,574 - - - - - 51,574
Land Purchase for Renovations to Existing Facility
Additional Site Area 0 acres x $0 per acre = - - Total Estimated Land Purchase for Renovation Construction - - - - - - - 11/4/2010 TEA 120 Page 4 of 5 Proposed Budget v:9/2010 Capital Improvement Program Browning Elementary School Proposed Budget Renovation 2007 Facilities Capital Program 120 Total Estimate Renovation Costs (Current $) 2,844,000 - - - - - 2,844,000
11/4/2010 TEA 120 Page 5 of 5 Proposed Budget v:9/2010