You are on page 1of 7

Construction Engineering of Phu My Cable-Stayed Bridge,

Vietnam
George Moir, Design Manager, Bilfinger Berger Civil; Ho Chi Minh City, Vietnam; Colin Edmonds, Principal, Cardno, Sydney,
Australia; Peter Walser, Project Manager and Martin Romberg, Structural Engineer; LAP, Stuttgart, Germany.
Contact: george.moir@bbbh.com.vn

Abstract further downstream within the next Substructure


10 years, generates a considerable
The Phu My Bridge spans the Saigon Each main bridge pylon is founded
amount of heavy-goods traffic. In
River between Districts 7 and 2 of Ho on two groups of 14 piles with 2,05 m
addition, a significant amount of goods
Chi Minh City (HCMC). The bridge diameter, and up to 80 m depth (Fig. 3).
from manufacturing industries in the
forms part of a new ring road currently The underlying geology is of alluvial
Mekong Delta also travel up through
under construction around HCMC. deposits of alternating clay and sand
HCMC. This traffic currently crosses
The ring road will be an important layers. The pile toe levels are within a
the Saigon River at the most southerly
transport link from the southern layer of dense sand.
bridge, the Saigon Bridge, located in
Mekong Delta region to the central the central district of HCMC. A reduc- Each pile cap is composed of two sec-
and northern parts of Vietnam. tion of the traffic congestion in the tions of reinforced mass concrete cap-
The Phu My Bridge contract includes centre of the city is necessary to ensure ping – each group of 14 piles. These are
the design and construction of a 705 m efficient transportation conditions and locked together by means of a two-cell
long cable-stayed main bridge with will be realized by the creation of an box girder.
a clear span of 380 m, as well as the inner ring road, including the large
The pile cap construction was carried
approach structures on either side Phu My Bridge over the Saigon River,
out in phases within a shell of precast
being approximately 758 m on District linking the Southeast quadrant to the
concrete permanent formwork ele-
7 and 638 m on District 2. rest of the city.
ments. These elements were fixed to
The main span deck is 27 m wide. An Engineering, Procurement and the steel pile casings and allowed con-
Clearance to river traffic is provided Construction (EPC) contract was let struction work to be carried out within
with a 45 m vertical clearance in a 250 m for the construction of the Phu My a dry working area. The lateral form-
wide zone. The pylons carrying the Bridge. The project involved the design work of the pile cap is made of precast
deck are designed as an H frame and and construction of a 2101 m long skirting panels, which extend below
are approximately 140 m high. viaduct including a 705 m long cable- water level.
stayed main bridge with a clear span
The bridge was constructed by a joint of 380 m, as well as approach viaduct Towers
venture between two companies and structures on either side of the river,
was completed in September 2009. The concrete pylons are H shaped.
being 758 m on District 7 and 638 m
This paper describes the construction Each leg is a box section, with outer
on District 2.
engineering used during the stage by dimension varying from 5,50 m × 7 m
stage analysis of the bridge and the on- Design of the permanent works was to 3 m × 5 m. The stay anchorages are
site role to control the cable forces and split into two packages, the main located inside the upper legs and are
bridge geometry during construction bridge design and that of the approach in a vertical plane. The legs are linked
of the bridge. structures. A separate design pack- by two cross-beams, the lower of which
age was then created for the design was precast before being lifted into its
Keywords: cable-stayed bridge; con- of the main bridge - temporary work final position (Fig. 4).
struction engineering analysis; pylon and construction engineering for the
construction; deck erection. main bridge. This paper focuses on Tie-Down Piers
the construction engineering aspects,
The tie-down piers are located at the
particularly the work carried out prior
Introduction end of each cable-stayed back span.
to construction and the ongoing role
They are twin rectangular concrete
of the construction engineer during
The Phu My Bridge is a newly com- columns – with vertical prestress,
construction.
pleted, cable-stayed bridge construc- supported on large-diameter bored
tion, in Ho Chi Minh City (HCMC), in piles. The last three stay cables on the
Vietnam. The bridge spans the Saigon Description of the Main Bridge back span are connected at the tie-
River between Districts 7 and 2 and down pier location. The deck slab is
The main bridge is a three span cable-
forms part of a new ring road currently of solid concrete and is prestressed in
stayed bridge. The spans are 380 m for
under construction around HCMC both the longitudinal and transverse
central span and 162,50 m for each
(Fig. 1). The ring road will be an impor- directions.
back span (Fig. 2). The total height
tant transport link from the southern
of the pylons is 134,50 m above pile
Mekong Delta region to the central Superstructure
caps’ levels and 93 m above deck level.
and northern parts of Vietnam.
Clearance to river traffic is provided The total width of the main span deck
The main port, which is located slightly with a minimum 45 m vertical clear- is 27 m; this incorporates three lanes
downstream (or south) of the city cen- ance at high tide, over a 250 m wide of traffic in each direction, two car and
tre and is forecasted to be relocated zone at the centre of the bridge. truck lanes, a separated motorcycle

Structural Engineering International 3/2010 Technical Report 331

x010.indd 331 1/12/70 2:06:02 AM


105°00'E 110°00'E
PEOPLE’S REPUBLIC
OF CHINA
HANOI

Haiphong
VIETNAM
20°00'N Gulf of
Tonkin
20°00'N Phu my bridge approach roads project
Vinh
LAO
PEOPLE’S
DEMOCRATIC
REPUBLIC
Da Nang NH 13
PR 16 NH 1A
NH 1A
Quy Nhon

CAMBODIA
NH 1K
PROJECT AREA
Nha Trang
Da Lat
Gulf of
Thailand Ho Chi Minh City

10°00'N Vung Tau 10°00'N

South China Sea


105°00'E 110°00'E

Tan Son Nhat


Airport

Rach Chiec District 9


Bridge
Ho Chi Minh City
PR 25

n R ive
District 2

NH 10

ig o
National capital E
City/Town
Se
Ring road no. 2 (missing sections)

r
ive
Ring road No. 2 (existing) Phu My Bridge
Hung Vuong

iR
Primary road Huynh Tan Phat

Na
Flyover (to be constructed)

ng
Flyover (existing)
Do
W Western approach road
District 7 PR 15
E Eastern approach road
Nguyen Van Lin

NH National highway
PR Provincial road PR 34
River PHU MY
0 1 BRIDGE
2 3 4 5

International boundary
NH 50 Kilometers
Boundaries are not necessarily NH 1A
authoritative.
h

Fig. 1: Phu My Bridge forms a critical element of the new ring road

lane and footways for pedestrians controlling load cases on the tower position. With the cross-beam in its
(Fig. 5). were caused by high-wind events and correct position, casting the in situ
the forces created by the inclined concrete stitch thereby securing the
There are two vertical planes of stay
geometry (Fig. 6): lower cross-beam to the tower leg.
cables. The structure of the deck is
– Once the lower cross-beam was con-
composed of two longitudinal con-
– Constructing a 56 m tower leg and nected, the pier table had to be cast.
crete girders linked by transverse
installing the temporary lower strut/ This was done in three 10 m stages
prestressed concrete cross girders at
lifting beam 48 m above the pile cap. to complete a 30 m section of deck.
5 m centres. The stay cables are con-
The lower strut was used to control Deck construction was started as
nected to the longitudinal edge beams
the forces and deflections in the early as possible in parallel with
by precast anchor pods located at 10 m
tower leg and also for heavy lifting ongoing tower construction.
intervals.
the lower cross-beam. – Continuation of building the tower
– Constructing the lower cross-beam legs and installing the temporary
Construction Method on the pile cap by attaching the pier intermediate strut 70 m above
table falsework. the pile cap. The lower strut was
Tower Construction – Lifting the lower cross-beam and removed. The intermediate strut is
The towers were built in 4 m lifts pier table falsework using the lower a needle beam used to control the
using an enclosed jump form and by strut. This heavy lift involved lift- forces in the tower legs. It is also
adopting the following sequence. The ing the 1200 t assembly 30 m into used to support a catch platform for

332 Technical Report Structural Engineering International 3/2010

x010.indd 332 1/12/70 2:06:03 AM


West tie - down pier

East tie - down pier


Tower 2
Tower 7
Western approach Eastern approach
structure structure
705,00
162,50 380,00 162,50
5,20 190,00 190,00 5,20
West bearing

District 7 District 2

Mid span
Z = +51,25
Z = +46,50 Z = +46,50 Z = +38,375
Z = +38,375

5% 5%

45,00
Navigational clearance
Refer. el +0,00 250,00
Sai gon river

−50,00
−65,00 −70,00
−80,00

Fig. 2: Main bridge profile (Units: m)

a survey was carried out, prior to D7 Side Span Closure


making a final adjustment to the
After 15 segments are cast, the 1,5 m
cable length.
long side span closure is cast. A survey
Deck Construction is carried out prior to the closure and
the deck is positioned by releasing the
The following overall construction temporary tie-down cables. The pour
sequence was used for the main bridge is carried out in the evening to limit
(Fig. 7). the effects of temperature on the new
concrete.
Build Deck Out from D7 Tower
The deck is constructed one segment at Move Travellers and Repeat for D2
a time starting on the river side, by fol- Deck
lowing the sequence described in the
After the side span closure is complete,
Fig. 3: Pile group layout and precast form- next section. The sequence between the
the three remaining river side segments
work two sides was partially offset to reduce
are cast and the travellers are moved
the out of balance moments and speed
to the D2 side to repeat the process.
up the construction, that is, the travel-
safety during the construction of the ler on the river side was launched to
upper cross-beam. Main Span Closure
the next segment prior to casting the
– Installation of the temporary upper land side segment. The 10 m main span closure is cast
strut. The upper strut acts as both using one of the travellers. A full sur-
a brace for the tower legs and as Install Buffeting Cables vey and adjustment of the stay cables
support for the formwork of the are carried out prior to casting. After
upper cross-beam. Construction of After seven segments are cast on both
sides the buffeting cables are installed. casting, the SDL loads are placed and
the upper cross-beam followed by any further stay adjustments if neces-
removal of the intermediate and Only the land side is tensioned. The
river side is kept slack unless high sary are carried out.
upper struts and completion of the
tower leg construction. winds occur (greater than 20 m/s gust
at 10 m elevation). This limits the Deck Segment Construction Cycle
– Installation and stressing the first
stays to the pier table section. bending moments in the tower at the The deck is constructed in bal-
Releasing and lowering the pier deck level. anced cantilever starting from each
table formwork then lifting of the tower. The 10 m long segments are
Install Temporary Tie-Down Cables
form travellers into position. At this cast using a form traveller (Fig. 8).
stage, the geometry of the deck is After 11 segments, the temporary tie- The typical erection sequence is as
controlled by the length of the stays down cables are installed on the land follows:
more than the force as the deck is side. The land side buffeting cables
free to pivot on the bearing. The are released and the river side is kept – Casting of new segment. On the
stays were installed up to 75% of under tension. This limits the bending morning after casting, carrying out
their installation force. At this stage moments in the whole tower. an “as-built” survey.

Structural Engineering International 3/2010 Technical Report 333

x010.indd 333 1/12/70 2:06:06 AM


CL of tower
26,300
3,000 20,300 3,000 5,000

Stay N-18 Stay N-18

(Tower heads)
37,400
Upper cross beam

Cables
(Upper legs)

Stay N-1 Stay N-1


61,715

Bridge deck

34,957 10,00 10,00 10,00 10,00 10,00 10,00


3,00 28,957 3,00
5%

7,000
Lower cross
(Lower legs)

beam
35,385

44,921
5,50 33,921 5,50

∇ Reference
level + 0,00

Fig. 4: Pylon layout and lower cross-beam heavy lift

11,65 11,65

2,15 3,00 0,55 7,50 0,30 0,30 7,50 0,55 3,00 2,15

2 Lanes at 3,75 2 Lanes at 3,75

Fig. 5: Deck cross section (Units: m)

– Moving the rolling beam and stress- of the traveller and adjusting align-
ing of front cross girder. Required ment if required.
concrete strength is 30 MPa. – Placing the precast cross girders and
– Destressing and removing stress edge beam reinforcement cages.
bars at anchor pods and restressing Required concrete strength is 40
the stay cable. Required concrete MPa.
strength is 30 MPa. – Starting installation of deck rein-
– Removing the longitudinal strut. forcement. Up to 25 t of rebar could
Lowering the traveller and stressing be placed before stay installation.
of the rear cross girder. Required – Installation of longitudinal struts
concrete strength is 35 MPa. between anchor pods and the previ- Fig. 6: Tower construction
– Launching the traveller halfway ous segment.
towards the new position. – Installation and stressing of stay
– Installation of precast anchor pods cable. The stay cable is attached to
during the launch. the anchor pod which is in turn con- the load is transferred to the pre-
– Completing the launch and raising nected to the traveller using stress vious segment via the longitudinal
the traveller. Surveying the position bars. The horizontal component of strut. The vertical load component

334 Technical Report Structural Engineering International 3/2010

x010.indd 334 1/12/70 2:06:06 AM


Phu my cable stayed bridge Phu my cable stayed bridge
deck construction sequence deck construction sequence

Late October 08′ Late November 08′

District 7 District 2 District 7 District 2

Sta
Stay

Sta
09

Sta
y7
7102
5

71

06

y7
20
10

y7
7202

71
y 9
y7

20
20
Sta
Stay

6
Sta

Sta
5

+1.49 +1.49

Completion of stage WM05 at 29 Oct. 08′ Completion of stage WM09 at 20 Nov. 08′
based on August 08′ programme based on August 08 programme

Phu my cable stayed bridge Phu my cable stayed bridge


deck construction sequence deck construction sequence

Mid December 08′ Late January 09′


District 7 District 2

District 7 District 2
Stay
Sta 7218

ST2201

Stay21
y 72
14

01
+1.49
Sta Sta
ST2201

y7 y7
ST2101

21 21
3 0 3
11 0
11
y7 y7
Sta Sta

+1.49

Completion of stage WM13 at 13 Dec. 08′ Completion of stage WM18 at 23 Jan. 09′
based on August 08′ programme based on August 08′ programme

Phu my cable stayed bridge Phu my cable stayed bridge


deck construction sequence deck construction sequence
Mid March 09′ Early July 09′
District 7 District 2 District 7 District 2
5
20

Stay

Sta
02
y2

ST22

y
Sta

21
2102

05

+1.49 +1.49

Completion of stage EM05 at 21 Mar. 09′ Completion of closure at 01 July. 09′


based on August 08′ programme based on August 08′ programme

Fig. 7: Deck sequence

of this first stay force is kept con- Construction Engineer Role – The best estimate of the time
stant at about 100 t for each stay, required for construction, as it was
which helps to support the travel- Construction Engineer Role—Design important to accurately determine
ler during casting of the concrete. Phase the time-dependant effects.
Required concrete strength was – When to install the stay cable.
45 MPa. The contractor engaged a design con- – When to install the temporary tie-
sultant to carry out the construction down cables and when and how
– Completion of deck reinforcement
engineering and the design of some of often to restress.
and carrying out pre-pour survey
the major temporary works. Prior to – When to dismantle the forms and
and casting new segment.
commencing on site construction, the supports at the pier tables for both
After the initial learning phase, this construction engineer and the contrac- the tower and the tie-down pier.
cycle was regularly achieved in five tor agreed on the following: – Exact local sequences, for typical
days with the side span cycle lag- segment construction as well as for
ging two days behind the main span – Weights and requirements for major side span and main span closure
cycle. temporary works items. procedures.

Structural Engineering International 3/2010 Technical Report 335

x010.indd 335 1/12/70 2:06:19 AM


– Adjust traveller alignment to create
the correct pre-camber.
– Adjust restress force to account for
deck loading, temperature and stay
forces.
– Advise contractor on possible
changes to construction sequence.
Following casting of a deck segment,
the following information was obtained
the next morning:

– A survey was carried out on the last


four segments—on the leading edge

Fi (ca
plus the tower.

rs bl
ts es
tr ag
– In addition, a load map was pre-

es )
sin
g
pared based on the major loading
P/T in place on the deck such as reinforcement
Rolling beam
stock, strand, mobile crane and so
Strength
45 MPa
Strut on (Fig. 9).
– A lift-off test was carried out on the
cable in the new segment to deter-
mine the actual stay force.
The survey was compared with the pre-
dicted position of the deck and tower
Fig. 8: Formwork traveller for that stage. An adjustment was made
for the actual loads on the deck, cable-
stayed force and temperature. From
Once this was done, the construc- The erection analysis was based on the this analysis, the construction engineer
tion engineer modelled the sequence results of the permanent works design determined the restress length of the
including consideration of the time- and took into account the most accu- stay cable and the appropriate align-
dependant effects. To do this, a sophis- rate actual parameters, dimensions and ment values for the next traveller posi-
ticated stage by stage analysis of the weights. While doing this, special care tion. This information was required
bridge was carried out. was taken to address the following: by the site team within a few hours in
The software program also featured an order to avoid delay in the construc-
efficient solution provider that deter- – dead weight, actual concrete density tion cycle.
mined the forces to be applied at each and reinforcement content;
Adjustments to the traveller alignment
stay installation such that the forces at – section properties;
shims affect the local curvature while
the end of construction were the same – P/T forces;
changes to the stay force have a greater
as those calculated by the permanent – shrinkage and creep values.
effect on the overall geometry of the
works designer. This was done by the The object of the analysis was to esti- bridge. During construction, the results
program by solving a set of simulta- mate as closely as possible both the from the survey were studied to check
neous equations with the constraints position of the bridge and the built- the accuracy of the analysis. Some of
being the final stay forces, tower forces in forces provided by the permanent the variables for which sensitivity anal-
and so on. The input variables were the works design, in order to be consist- ysis was carried out included:
stay stressing forces and other adjust- ent with the final design assumptions.
ments such as jacking forces prior to In addition, an erection stress analysis – Variation in traveller weight: The
the closure pours. was carried out to ensure that—the design had an assumed traveller
Once the stay forces were calculated, structural capacity of all the bridge ele- weight of 210 t. When it was lifted,
the camber curves and support reac- ments would not be exceeded at any of the weight of the traveller was found
tions could be calculated. The purpose the individual erection stages. to be 235 t. An update of the analysis
of the analysis was to achieve a clear was therefore carried out.
On the basis of their previous experi-
understanding of the following: – Deck stiffness: The deflections of
ence in cable-stayed bridges and work-
the deck depend on the modulus of
ing in Vietnam, the contractor had a
– Exact forces and deflections of all clear view of how to construct the bridge
parts during all erection stages. with speed and cost-effectiveness.
– Forces in the buffeting cables and
temporary tie-down cables. Construction Engineer Role—
– Forces in the temporary falsework Construction Phase
at the hold-down pier.
During construction, the role of the
The analysis also calculated adjustment construction engineer included the fol-
values to account for variations in: lowing responsibilities:
– temperature conditions; Fig. 9: Balanced cantilever deck
– construction live loads. – Monitor the survey results. construction

336 Technical Report Structural Engineering International 3/2010

x010.indd 336 1/12/70 2:06:19 AM


Fig. 10: Finished bridge

elasticity of the concrete used and During the erection of the bridge, the the bridge to be opened for traffic in
also the effective width of the deck stay forces were slightly increased to September 2009, (Fig. 10).
section. account for these deflections.
– Stay stiffness: The strand used was
provided with test certificates giving
the area and modulus of elasticity. Conclusion SEI Data Block
– Deck weight: The deck weight Owner:
included in the design allowed for In summary, this paper highlights some
of the features used for the speedy con- Phu My Bridge Corporation
an assumed reinforcement rate. A
comparison was carried out with the struction of a cable-stayed bridge. Contractor:
Bilfinger Berger Baulderstone
density of the actual concrete and The project required significant Hornibrook (BBBH Consortium)
reinforcement used and the original planning and design to agree with
assumption. and optimize the construction meth- Designers:
– Traveller stiffness: The traveller was Arcadis (Permanent Works Main
ods. This involved considerable col-
modelled separately using a three Bridge)
laboration between the contractor
Cardno/Golders (Permanent Works
dimensional (3D) program with all and the construction engineer and Approach Structures)
the members to calculate its stiff- resulted in relatively few issues Cardno/Leonhardt, Andrä und
ness. The computed stiffness of the occurring during the construction Partners (Temp. Works and Const.
traveller was compared with the process and a rapid achievement of Eng.)
true stiffness and analysed from the five day construction cycle with a
Employers representative:
measurements made on-site under short “learning process”. The role of
Maunsell (AECOM) Vietnam
actual loading conditions. the construction engineer both dur-
During the construction of the bridge ing the preconstruction and the con- Steel (t): 17 000
deck, it was noted that the deflections struction phase formed an important Concrete (m³): 100 000
of the bridge were greater than those part of this project.
Prestressing steel and stay
predicted by the model. As noted there A contract duration of 34 months was cables (t): 2000
are several possible reasons for this originally anticipated with the project Estimated cost (USD million):
occurance; however, one of the more scheduled to be opened to traffic by approx. 105
likely reason seemed to be an increase the end of 2009. Construction was how-
in the traveller and deck weights. Service date: 2 September 2009
ever completed in 30 months, allowing

Structural Engineering International 3/2010 Technical Report 337

x010.indd 337 1/12/70 2:06:24 AM

You might also like