Professional Documents
Culture Documents
Vietnam
Dung Quat Economic Zone,
Binh Thuan, Binh Son, Quang Ngai,
Vietnam
T +84 55 5618 900
F +84 553 618 950
Owner :
Owner's Engineer :
Contractor :
Project : PC : T10206
MONG DUONG II 2 X 560MW (NET) COAL FIRED POWER PROJECT UAS : QE01
Unit : PO
KKS : ZEN
Title : T10206-QE01-POZEN__-040203 INSPECTION
AND TEST PLAN FOR Reg. No. 040203
CABLE TRAYS INSTALLATION Revision : A
Page 1
Doc. No. T10206-QE01-POZEN-040203 Rev. A
Detailed Legend
S : Surveillance Point / DOOSAN / Subcontractor does not send a notification to AES-VCM Mong Duong
except for the first or last operation on the basis of each process. AES-VCM Mong Duong
could check the operation, if he is present at the site during the inspection by Doosan.
W : Witness Point / DOOSAN / Subcontractor shall submit request for inspection to AES-VCM to
decide whether they will attend such inspection or not.
H : Hold Point / Downstream construction and other activities shall not proceed
without attendance or any written approval of AES-VCM Mong Duong.
NOTE : The Site ITP and all of the abovementioned reports will be kept available by
DOOSAN at anytime for control and or review by AES-VCM Mong Duong.
Page 2
Doc. No. T10206-QE01-POZEN-040203 Rev. A
Inspection & Test Plan for Cable Tray
Installation
AES-VCM
Contractor DOOSAN Page 3 of 4
Check the levelling and alignment of tray and rack and Approved Construction
B2 H W W Refer to attached Checklist N/A
expansion joints if any are specified are in place. Drawing T10206-YD04---
B. Cable Ensure the gap between parallel runs is quite enough Approved Construction
Tray B4 H W W Refer to attached Checklist N/A
to accommodate the layer of cables. Drawing T10206-YD04---
Installation
Ensure there are no sharp 90 degrees bends are Approved Construction
B5 H W W Refer to attached Checklist N/A
made. Drawing T10206-YD04---
Note : All inspection shall be performed in accordance with the approved Site Inspection and Test Plans/Project Specifications
Inspection Check List
Project : Cable Tray Installation Works Ref. No.
Drawing No. : Date :
Specific Location :
CHECK ITEM
Check the condition of cable Supports, Racks, Trays and Trunking while
1
receiving.
Check size and type of the Supports, Racks, Trays and Trunking with
2
respect to the requisitions.
Check the leveling & alignment of tray & rack and expansion joints if
4
any are specified are in place.
Ensure the gap between parallel runs is quite enough to accommodate the
6
layer of cables.
Earth jumper cable with crimp type terminals to be fitted to all cable
10
tray joints.
page 4