You are on page 1of 30

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Calculating Earned Value and Estimate to Complete in


Primavera P6

Business Process Outsourcing

Presented By: Eric Costantino


Associate Consultant
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

• Introduction to Earned Value


• Calculate Planned Value Costs
• Calculate Actual Costs
• Calculate Earned Value Costs
• Estimate to Completion (ETC)
• Using CPI/SPI to calculate your ETC
• Questions?
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

What is Earned Value?

• Combines Measurements of
• Scope
• Your Original Plan
• Schedule
• Current Plan
• Cost
• Budget vs. Actual
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Primavera Variables

• Planned Value
• Cost & Schedule information comes from baseline
• Actual Value
• Actual cost
• Earned Value
• What has physically been built
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

A Simplified Example: (PV)


10 Day Project to build 10 Concrete Forms
• 1 Form Per Day
• $100 Per Day
Time

$100 $100 $100 $100 $100 $100 $100 $100 $100 $100
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

At the end of day 5


• 5 Forms Completed
• $500
• Planned Value – (PV) = 500
Time

$100 $100 $100 $100 $100 $100 $100 $100 $100 $100
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Let’s Just Say..


• Day 5
• Only 3 Forms Completed
• Our Earned Value – (EV) = 300
Time

$100 $100 $100 $100 $100 $100 $100 $100 $100 $100
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Let’s also say we have a cost over-run..


• Day 5
• Only 3 Forms Completed
• Each form cost $200 to build
• Actual Cost – (AC) - ($200 x 3 Days) = $600
Time

$200 $200 $200 $100 $100 $100 $100 $100 $100 $100
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

We now have our variables to compute Earned Value


• Day 5
• (PV) = 500
• (EV) = 300
• (AC) = 600
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

• Day 5
• (EV) – (PV) = Schedule Variance
• 300 - 500 = -200
• Behind Schedule
• (EV) – (AC) = Cost Variance
• $300 - $600 = $-300
• Over Budget
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Cost & Schedule Indices


• Schedule Index
• A ratio of what was earned vs. what was planned
• An index less than 1 is behind schedule
• An index greater than 1 is ahead of schedule
• EV/PV = SPI (Schedule Performance index)
• 300/500 = .6
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Cost & Schedule Indices


• Cost index
• A ratio of what we Earned vs. the Actual Cost
• An index less than 1 is over budget
• An index greater than 1 is under budget
• EV/AC = Cost Performance Index
• $300/$600 = .5
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Step 1. Add Activities, Tie Logic, Set % Complete to


Physical
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Step 2. Add Resource Assignments


Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Step 3: Maintain Baseline and Assign to Project

7
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Step 4: Customize Columns for analysis


Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Step 5: Update Physical % Complete


Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Step 6: Update Resource Actual Units (Or Expenses)

Step 7: Schedule Project, Advance Data Date


Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

On Day 5, We can now analyze our “Earned Value”

7
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Conclusions Based on Earned Value Analysis


• Schedule Performance
• The baseline indicates that 50% of the work should be complete.
With only 30% Performance % Complete (Actual Labor Units)
This shows the project is behind schedule.
• Cost Performance
• The baseline indicates that $500 worth of work should be complete
(Planned Value Cost)
As of the Data Date, (Actual cost) is $600 to achieve $300 worth of
work (Earned Value Cost).
This shows the project is over budget
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Using CPI/SPI to analyze project efficiency


• Cost Performance Index relates the amount of Physical
Work completed vs. the $ spent to accomplish the work
• CPI = (EV)/(AC)
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Using CPI/SPI to analyze project efficiency


• Schedule Performance Index relates to the Physical Work
completed vs. the amount of work planned
• SPI = (EV)/(PV)
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Using CPI/SPI to calculate your “Estimate to Complete”


• Set at the WBS Level
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

What is it going to cost to complete this project?


• ETC uses one of two formulas
• ETC = Remaining Cost of the activity

• ETC = Performance Factor*(Budget at Completion – Earned


Value Cost)
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Performance Factors
• 4 Optional Methods

• PF = 1 *Optimistic Result
• ETC = (PF * (Budget at Completion – Earned Value Cost
• PF = 1/CPI *Most likely Result
• ETC = (1/CPI)* Budget at Completion – Earned Value Cost
• PF = 1/CPI*SPI *Pessimistic Result
• ETC = [1/(CPI * SPI)] * Budget at Completion – Earned Value Cost
• PF = ____
• ETC = your custom PF * Budget at Completion – Earned Value Cost
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Using Remaining Costs for Activities to Calculate (ETC)


Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Using CPI to Calculate (ETC) – Yields an Optimistic Result

• PF = 1/CPI *Most likely Result


• ETC = (1/CPI)* Budget at Completion – Earned Value Cost
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Using CPI/SPI to calculate ETC – Worst Case Scenario

• PF = 1/CPI*SPI *Pessimistic Result


• ETC = [1/(CPI * SPI)] * Budget at Completion – Earned Value Cost
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Key Concepts:
• Perform Earned Value Analysis to compare the budgeted cost of the
work to the Actual Cost

• Calculate the Planned Value, Earned Value, and Actual Cost to


determine how much work should have been completed, How much
work was completed, and how much the completed work cost to build

• Use Estimate to Completion to calculate what the remaining cost of


the activity(s) in progress will be
Business Process Outsourcing

PROJECT MANAGEMENT SOLUTIONS THAT SIMPLY WORK.

Questions?
Eric Costantino
Associate Consultant
ecostantino@drmcnatty.com
T. (877) 367-7990 x7998
Web www.drmcnatty.com

You might also like