Professional Documents
Culture Documents
SWITCHGEAR
1. Description:
This sequence describes a system with generator(s) feeding the common load bus, frequently used in
conjunction with downstream Automatic Transfer Switches to provide emergency standby power to critical loads,
with or without an emergency tie breaker between the generator sources and/or between sources and load.
2. Functional Sequence of Operation
A. The EPS Automation shall be provided with the following modes of operation:
1. Automatic/Standby Mode
a. The automatic transfer switches are in the normal position serving utility power to the loads.
b. The generator set main breakers are open.
c. The automation is standing by to act in response to a run request from associated automatic transfer
switches.
2. Emergency Mode
Entry
a. Automatic Transfer Switch Run Request is received
b. Where applicable, load shed sequence is executed.
c. All available generators are started.
d. The first generator up to voltage and frequency is closed to the bus.
e. Critical loads and load shed priority 1 loads are powered in less than 10 seconds.
f. The remaining generator sets are synchronized and paralleled to the bus as they come up to voltage and
frequency.
g. As additional generators are paralleled to the emergency bus, Load Shed Priority levels are added,
powering their associated loads.
h. [With Generator Bus Tie Breaker] The generator bus tie breaker is closed after the minimum # of gensets
required to perform transfer (user adjustable) are synchronized and paralleled to the bus, or the maximum
time to transfer expires. (User adjustable) The remaining generator sets are synchronized and paralleled to
the bus as they come up to voltage and frequency.
i. The system is now in emergency mode.
Exit
a. Automatic transfer switches sense the utility source is within acceptable operational tolerances for a time
duration set at the automatic transfer switch.
b. As each automatic transfer switch transfers back to utility power, it removes it’s run request from the
generator plant.
c. When the last automatic transfer switch has retransferred to the utility and all run requests have been
removed from the generator plant, the tie breaker (if present) and all generator set main circuit breakers
shall opened.
d. The generator sets are allowed to run for their programmed cool down period and shut down.
e. The system is returned to automatic/standby mode.
Page 1 of 2
SWITCHGEAR
SWITCHGEAR
www.cat.com/electricpower
©2018 Caterpillar
All rights reserved.
Materials and specifications are subject to change without notice.
CAT, CATERPILLAR, their respective logos, “Caterpillar Yellow”,
the “Power Edge” trade dress as well as corporate and product identity used
LEXE1407-01 (9/18)
herein, are trademarks of Caterpillar and may not be used without permission.