Professional Documents
Culture Documents
SLAB INSULATION
SLAB INSULATION TECHNIQUES MOISTURE AND AIR LEAKAGE CONTROL BUILD IN RADON RESISTANCE WHEN INSTALLING
Slab insulation can be installed following one of two basic 1. Keep all untreated wood materials away from the earth. SLAB-ON-GRADE FOUNDATIONS
techniques: installing rigid insulation directly against the R-VALUES AND RECOMMENDED DEPTH FOR Radon is a radioactive gas that occurs in some soils. It can
2. Install well-designed guttering and downspouts that are SLAB INSULATION
exterior of the slab and footing or building a “contained” or enter a home through the foundation and floor system. If it
connected to a drainage system diverting rainwater completely The IECC specifies both the R-value of the slab insula-
“floating” slab with interior insulation. Whichever design is occurs in significant concentrations (greater than 4 pico-curies
away from the house. tion and the minimum distance for the insulation from
followed, the keys to an effective slab foundation are: per liter), it may pose a severe health risk to the home
3. Slope the earth away from the house for at least 5 feet at a the top of the slab downward based on a locality’s occupants. To guard against radon problems in concrete slabs:
Moisture control—using a water-managed foundation system minimum 5% grade (3 inches in 5 feet). Establish drainage Heating Degree Days (HDDs):
to drain rainwater and groundwater away from the foundation. • Use a 4- to 6-inch gravel base and a continuous layer of 10-mil
swales as needed to direct rainwater around the house. Heating Feet Installed R-value of
polyethylene on top of the gravel.
Airtight construction—sealing interfaces between the slab 4. Add a sill gasket membrane between the slab and bottom plate Degree Days Vertically Slab Insulation
foundation and the exterior wall to reduce infiltration into 0 to 2,499 none required • Install a tee below the polyethylene that protrudes through the
to provide air sealing.
the house. 2,499 to 4,500 2 feet R-4 polyethylene and extends above the poured floor height.
5. Install a protective membrane (such as rubberized roofing
Complete insulation coverage—properly installing the correct 4,500 to 6,000 2 feet R-5 • Connect the tee to a 3-inch vertical plastic pipe that extends to
material or ice-dam protection membranes) to serve as a
insulation levels and making sure the insulation coverage is 6,000 to 7,200 4 feet R-6 the roof through an interior wall.
capillary break that reduces wicking of water up from the
continuous and complete. 7,200 to 8,700 4 feet R-7
foundation. This membrane can also serve as a termite shield. • Pour the slab and seal all slab joints with caulk.
8,700 to 10,000 4 feet R-8
6. Install a foundation drain directly beside the bottom of the • Have an electrician stub-in a junction box in the attic.
PERIMETER INSULATION— 10,000 to 12,400 4 feet R-9
SLAB-ON-GRADE CONSTRUCTION footing. The foundation drain assembly includes a filter 12,400 to 14,000 4 feet R-10 • Test the bottom-most conditioned room for radon with an
Provide good drainage away from the foundation and fabric, gravel, and a perforated plastic drain pipe typically EPA-listed radon test kit, or hire a qualified technician. If the
4 inches in diameter. Locate the drain beside the footing, not HDD=HEATING DEGREE DAYS house has a high radon concentration, install an active radon
capillary breaks for a durable foundation. Perimeter
on top, to avoid water flowing against the seam between the (Consult your local weather bureau for your city’s actual mitigation system by attaching a small blower to the plastic
insulation increases comfort in the living space.
footing and the foundation wall and prevent wicking from a annual Heating Degree Days.) Heating Degree Days is a pipe in the attic to expel the gasses to the outside.
Metal termite term used to help indicate the heating needed for any
yyyyy
;;;;; ;;;;;;
yyyyyy
flashing web footing through the stem wall.
Sill gasket • If radon levels are especially high (over 25 pico-curies per
Rigid insulation certain day. This method is commonly used to determine
;;;;;
yyyyy ;;;;;;
yyyyyy
encapsulated or 7. Install a capillary break and moisture barrier under the slab liter), consult with local radon experts.
covered with
;;;;;;;;
yyyyyyyy fuel consumption and/or the cost of heating during a
yyyyyyyy
;;;;;;;; floor, consisting of a layer of 10-mil polyethylene placed over
;;;;;
yyyyy ;;;;;;
yyyyyy
membrane to
season by using historical weather trends to calculate
;;;;;;;;
yyyyyyyy
protect from
at least 4 inches of gravel.
yyyyyyyy
;;;;;;;;
termites and
;;;;;
yyyyy ;;;;;;
yyyyyy
exterior average seasonal temperatures.
damage.
;;;;;;;;
yyyyyyyy
;;;;;;;;
yyyyyyyy
;;;;;
yyyyy
;;;;; yyyyyy
;;;;;
yyyyy
;;;;;;
;;;;;;;;
yyyyyyyy
Gravel INSULATION RADON-RESISTANT
yyyyy ;;;;;;;;
yyyyyyyy
base
;;;;;
yyyyy
;;;;; yyyyyy
;;;;; ;;;;;;
1. Review the plan for slab insulation with pest control and local CONSTRUCTION
;;;;;
yyyyy 4. If insulation is installed on the exterior of the slab:
yyyyy building officials to ensure code compliance. Passive
yyyyy
10-mil poly vapor Optional blower
• The insulation should be installed from the top of the slab (if required)
diffusion retarder is
2. Select insulation levels in accordance with the International radon-resistant
extented under Electrical
Perforated drainage pipe is embedded in gravel,
covered with filter fabric, and located at lower
footing.
Energy Conservation Code (IECC) or DOE Insulation Fact to the bottom of the frost line unless a termite inspection construction is an junction box
perimeter of foundation footing to provide drainage.
Sheet. The Insulation Fact Sheet (DOE/CE-0180) can be gap is required. inexpensive first
ordered from the Energy Efficiency and Renewable Energy • Encapsulate or cover the exterior face of the insulation cost. It can easily be
yyyy
;;;;
FLOATING SLAB-ON-GRADE CONSTRUCTION
Clearinghouse or accessed from the Internet at with a protective membrane to serve as a capillary break upgraded if active Plastic
;;;
yyy ;;;;
yyyy
vent stack
Sill gasket www.ornl.gov/roofs+walls. and to protect the insulation from termites. mitigation is later
Rigid insulation
;;;
yyy ;;;;
yyyy
required to cure a
;;
yy
3. Install rigid insulation using one of the two general designs
;;;;;;;;
yyyyyyyy • Cover the above-grade portion of the insulation exposed Sealed
radon problem.
;;;;;;;;
yyyyyyyy
polyethylene
;;;;;
yyyyy ;;
yy;;;;
yyyy
shown to achieve complete insulation coverage of the slab to outside air using a stucco coating, pressure-treated
;;;;;;;;
yyyyyyyy
Metal termite ;;;;;;;;;;;;;
@@@@@@@@@@@@@
ÀÀÀÀÀÀÀÀÀÀÀÀÀ
;;;;;;;;;;;;;;
@@@@@@@@@@@@@@
@;ÀÀÀÀÀÀÀÀÀÀÀÀÀÀÀ
;;;;;;;;;;;;;;
@@@@@@@@@@@@@@
;ÀÀÀÀÀÀÀÀÀÀÀÀÀÀ
@;;;
@@@
À
ÀÀÀ
;ÀÀÀÀ
@;;
@@
À
ÀÀ
; ÀÀÀÀ
@;;;;
@@@@
À
; ÀÀÀ
@;;;;
@@@@
À
; ÀÀÀ
@;;;
@@@
À
;
@;;;
@@@
À
;;;;;
yyyyy ;;
yy;;;;;;;;
yyyyyyyy
;;;;
yyyy
flashing perimeter. Use only insulation approved for below-grade use. wood, brick, or aluminum flashing. When covering
;;;;;;;;
yyyyyyyy
;;
yy
10-mil poly
;;;;;;;;
yyyyyyyy insulation, be conscious of how to detect termites in areas
;;;;;
yyyyy
;;;;; yyyy
;;;;; ;;;;
vapor diffusion Perforated "T" fitting
yyyyy
;;;;; retarder
;;;;;
yyyyy
;;;;; yyyy
;;;;; ;;;;
yyyyy
base
areas have addressed this issue by requiring a termite
yyyyy
;;;;;
yyyyy
yyyyy
;;;;
yyyy
Perforated drainage pipe is embedded in gravel,
covered with filter fabric, and located at lower perimeter
of foundation footing to provide drainage.
inspection gap near the top of the slab insulation.
SLAB INSULATION
SLAB INSULATION TECHNIQUES MOISTURE AND AIR LEAKAGE CONTROL BUILD IN RADON RESISTANCE WHEN INSTALLING
Slab insulation can be installed following one of two basic 1. Keep all untreated wood materials away from the earth. SLAB-ON-GRADE FOUNDATIONS
techniques: installing rigid insulation directly against the R-VALUES AND RECOMMENDED DEPTH FOR Radon is a radioactive gas that occurs in some soils. It can
2. Install well-designed guttering and downspouts that are SLAB INSULATION
exterior of the slab and footing or building a “contained” or enter a home through the foundation and floor system. If it
connected to a drainage system diverting rainwater completely The IECC specifies both the R-value of the slab insula-
“floating” slab with interior insulation. Whichever design is occurs in significant concentrations (greater than 4 pico-curies
away from the house. tion and the minimum distance for the insulation from
followed, the keys to an effective slab foundation are: per liter), it may pose a severe health risk to the home
3. Slope the earth away from the house for at least 5 feet at a the top of the slab downward based on a locality’s occupants. To guard against radon problems in concrete slabs:
Moisture control—using a water-managed foundation system minimum 5% grade (3 inches in 5 feet). Establish drainage Heating Degree Days (HDDs):
to drain rainwater and groundwater away from the foundation. • Use a 4- to 6-inch gravel base and a continuous layer of 10-mil
swales as needed to direct rainwater around the house. Heating Feet Installed R-value of
polyethylene on top of the gravel.
Airtight construction—sealing interfaces between the slab 4. Add a sill gasket membrane between the slab and bottom plate Degree Days Vertically Slab Insulation
foundation and the exterior wall to reduce infiltration into 0 to 2,499 none required • Install a tee below the polyethylene that protrudes through the
to provide air sealing.
the house. 2,499 to 4,500 2 feet R-4 polyethylene and extends above the poured floor height.
5. Install a protective membrane (such as rubberized roofing
Complete insulation coverage—properly installing the correct 4,500 to 6,000 2 feet R-5 • Connect the tee to a 3-inch vertical plastic pipe that extends to
material or ice-dam protection membranes) to serve as a
insulation levels and making sure the insulation coverage is 6,000 to 7,200 4 feet R-6 the roof through an interior wall.
capillary break that reduces wicking of water up from the
continuous and complete. 7,200 to 8,700 4 feet R-7
foundation. This membrane can also serve as a termite shield. • Pour the slab and seal all slab joints with caulk.
8,700 to 10,000 4 feet R-8
6. Install a foundation drain directly beside the bottom of the • Have an electrician stub-in a junction box in the attic.
PERIMETER INSULATION— 10,000 to 12,400 4 feet R-9
SLAB-ON-GRADE CONSTRUCTION footing. The foundation drain assembly includes a filter 12,400 to 14,000 4 feet R-10 • Test the bottom-most conditioned room for radon with an
Provide good drainage away from the foundation and fabric, gravel, and a perforated plastic drain pipe typically EPA-listed radon test kit, or hire a qualified technician. If the
4 inches in diameter. Locate the drain beside the footing, not HDD=HEATING DEGREE DAYS house has a high radon concentration, install an active radon
capillary breaks for a durable foundation. Perimeter
on top, to avoid water flowing against the seam between the (Consult your local weather bureau for your city’s actual mitigation system by attaching a small blower to the plastic
insulation increases comfort in the living space.
footing and the foundation wall and prevent wicking from a annual Heating Degree Days.) Heating Degree Days is a pipe in the attic to expel the gasses to the outside.
Metal termite term used to help indicate the heating needed for any
yyyyy
;;;;; ;;;;;;
yyyyyy
flashing web footing through the stem wall.
Sill gasket • If radon levels are especially high (over 25 pico-curies per
Rigid insulation certain day. This method is commonly used to determine
;;;;;
yyyyy ;;;;;;
yyyyyy
encapsulated or 7. Install a capillary break and moisture barrier under the slab liter), consult with local radon experts.
covered with
;;;;;;;;
yyyyyyyy fuel consumption and/or the cost of heating during a
yyyyyyyy
;;;;;;;; floor, consisting of a layer of 10-mil polyethylene placed over
;;;;;
yyyyy ;;;;;;
yyyyyy
membrane to
season by using historical weather trends to calculate
;;;;;;;;
yyyyyyyy
protect from
at least 4 inches of gravel.
yyyyyyyy
;;;;;;;;
termites and
;;;;;
yyyyy ;;;;;;
yyyyyy
exterior average seasonal temperatures.
damage.
;;;;;;;;
yyyyyyyy
;;;;;;;;
yyyyyyyy
;;;;;
yyyyy
;;;;; yyyyyy
;;;;;
yyyyy
;;;;;;
;;;;;;;;
yyyyyyyy
Gravel INSULATION RADON-RESISTANT
yyyyy ;;;;;;;;
yyyyyyyy
base
;;;;;
yyyyy
;;;;; yyyyyy
;;;;; ;;;;;;
1. Review the plan for slab insulation with pest control and local CONSTRUCTION
;;;;;
yyyyy 4. If insulation is installed on the exterior of the slab:
yyyyy building officials to ensure code compliance. Passive
yyyyy
10-mil poly vapor Optional blower
• The insulation should be installed from the top of the slab (if required)
diffusion retarder is
2. Select insulation levels in accordance with the International radon-resistant
extented under Electrical
Perforated drainage pipe is embedded in gravel,
covered with filter fabric, and located at lower
footing.
Energy Conservation Code (IECC) or DOE Insulation Fact to the bottom of the frost line unless a termite inspection construction is an junction box
perimeter of foundation footing to provide drainage.
Sheet. The Insulation Fact Sheet (DOE/CE-0180) can be gap is required. inexpensive first
ordered from the Energy Efficiency and Renewable Energy • Encapsulate or cover the exterior face of the insulation cost. It can easily be
yyyy
;;;;
FLOATING SLAB-ON-GRADE CONSTRUCTION
Clearinghouse or accessed from the Internet at with a protective membrane to serve as a capillary break upgraded if active Plastic
;;;
yyy ;;;;
yyyy
vent stack
Sill gasket www.ornl.gov/roofs+walls. and to protect the insulation from termites. mitigation is later
Rigid insulation
;;;
yyy ;;;;
yyyy
required to cure a
;;
yy
3. Install rigid insulation using one of the two general designs
;;;;;;;;
yyyyyyyy • Cover the above-grade portion of the insulation exposed Sealed
radon problem.
;;;;;;;;
yyyyyyyy
polyethylene
;;;;;
yyyyy ;;
yy;;;;
yyyy
shown to achieve complete insulation coverage of the slab to outside air using a stucco coating, pressure-treated
;;;;;;;;
yyyyyyyy
Metal termite ;;;;;;;;;;;;;
@@@@@@@@@@@@@
ÀÀÀÀÀÀÀÀÀÀÀÀÀ
;;;;;;;;;;;;;;
@@@@@@@@@@@@@@
@;ÀÀÀÀÀÀÀÀÀÀÀÀÀÀÀ
;;;;;;;;;;;;;;
@@@@@@@@@@@@@@
;ÀÀÀÀÀÀÀÀÀÀÀÀÀÀ
@;;;
@@@
À
ÀÀÀ
;ÀÀÀÀ
@;;
@@
À
ÀÀ
; ÀÀÀÀ
@;;;;
@@@@
À
; ÀÀÀ
@;;;;
@@@@
À
; ÀÀÀ
@;;;
@@@
À
;
@;;;
@@@
À
;;;;;
yyyyy ;;
yy;;;;;;;;
yyyyyyyy
;;;;
yyyy
flashing perimeter. Use only insulation approved for below-grade use. wood, brick, or aluminum flashing. When covering
;;;;;;;;
yyyyyyyy
;;
yy
10-mil poly
;;;;;;;;
yyyyyyyy insulation, be conscious of how to detect termites in areas
;;;;;
yyyyy
;;;;; yyyy
;;;;; ;;;;
vapor diffusion Perforated "T" fitting
yyyyy
;;;;; retarder
;;;;;
yyyyy
;;;;; yyyy
;;;;; ;;;;
yyyyy
base
areas have addressed this issue by requiring a termite
yyyyy
;;;;;
yyyyy
yyyyy
;;;;
yyyy
Perforated drainage pipe is embedded in gravel,
covered with filter fabric, and located at lower perimeter
of foundation footing to provide drainage.
inspection gap near the top of the slab insulation.
Technology Fact Sheet
SLAB INSULATION