Professional Documents
Culture Documents
On
Streetscaping of Mandir Marg Road in New Delhi
Submitted to The Institution of Engineers (India) in partial fulfillment of award of
AMIE degree of IEI (India)
Submitted by:
Amit Kumar
June 2012
(i)
OBJECTIVES OF THE STUDY
Streetscaping generally refers to urban roadways design and conditions as they impact street
users and nearby residents. Streetscaping programme are an important component of efforts to
redevelop urban areas and can being changes into the road sections, traffic management
system, sidewalk conditions, landscaping, street furniture, building fronts, improving signages
etc.
As per the contractual agreement of Delhi government with organizing committee of Common
Wealth Games – 2010, all roads with in 2 Km of games venue were to be Streetscaped by the
road owing agency. The main objectives behind Streetscaping of various roads was to provide
necessary facilities to both vehicular traffic and pedestrian movement for effective traffic
management on one hand & improve aesthetic look of the road on the other hand as a whole. The
roads were prepared up to the required international standard. It is envisaged that streetscaping
will make the visitors comfortable & happy while traveling on the Mandir Marg road.
The Mandir marg which had three main sections of length as follows namely From Talkatora
Roundabout to Kali Bari Road is 590 m, From Talkatora Roundabout to Kali Bari Road is 590 m & From Kali
Barricading was erected at all the working location on both sides of road.
(ii)
The existing parking area was shifted to other location at the time of execution.
The good coordination was made to other department like electrical & horticulture.
The trenches were excavated across the road at regular intervals for the identification of
existing utilities and then shifted/ diverted existing utilities for the proper functioning of
utilities.
It was proposed to make service duct in continuous lengths shall be provided on the
Mandir Marg in the footpath passage along the wall with duct chamber at each entry of
the building/crossing.
It was proposed to make cycle track on one side in continuous lengths shall be provided
It was proposed to provide granite & vitrified tiles will be provided on the footpath
passage.
EXPECTED CONTRIBUTION
residential areas.
To ensure a high level of amenity for residents, including adequate open space, privacy,
(iii)
LIST OF ACTIVITIES
Bar Chart showing the all major activities of project in April 2010 on page (vi) are as
under:-
1. Physical progress
(a) Construction of underground water tank irrigation line and boring etc.
(ii) CC 1:4:8
The tools used were Concrete mixer, Excavator, Chain pulley, Boring machine for borewell
(iv)
PROBLEMS ENVISAGED IN CARRYING OUT THE PROJECT
The shortage of skilled labour due to large scale construction activities were carried out in Delhi
There are two main old temple i.e. Laxmi Narayan Mandir( Birla Mandir ), Kali bari Mandir on the
road. At the time of execution there was big problem of movement of pilgrims on the temple.
The work was executed in a continuous business activities as well as vehicular movements.
Delayed in project execution due to heavy monsoon came in Delhi during construction of road.
(v)