2-5th vertical beam

A1-A3

DEAD LOAD
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.25M) = 2.95KN/M
CHB = (16.5KN/M3)(.15)(1.6M)=3.96 KN/M
PLASTER ON CHB = (.24KN/M2)(1.6MX2) = .768 KN/M
TOTAL DEAD LOAD = 10.038 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)(1.25M) = 2.375
TOTAL LIVE LOAD = 2.375
FACTORED LOAD
WU = 1.2(10.038) + 1.6(2.375)
WU = 15.846 = 16 KN/M

A7-A9
DEAD LOAD
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.25M) = 2.95KN/M
CHB = (16.5KN/M3)(.15)(1.6M)=3.96 KN/M
PLASTER ON CHB = (.24KN/M2)(1.6MX2) = .768 KN/M
TOTAL DEAD LOAD = 10.038 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)(1.25M) = 2.375
TOTAL LIVE LOAD = 2.375
FACTORED LOAD
WU = 1.2(10.038) + 1.6(2.375)
WU = 15.846 = 16 KN/M

P1-P3
DEAD LOAD
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.25M) = 2.95KN/M
CHB = (16.5KN/M3)(.15)(1.6M)=3.96 KN/M
PLASTER ON CHB = (.24KN/M2)(1.6MX2) = .768 KN/M
TOTAL DEAD LOAD = 10.038 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)(1.25M) = 2.375
TOTAL LIVE LOAD = 2.375
FACTORED LOAD
WU = 1.2(10.038) + 1.6(2.375)
WU = 15.846 = 16 KN/M

P7-P9
DEAD LOAD
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.25M) = 2.95KN/M
CHB = (16.5KN/M3)(.15)(1.6M)=3.96 KN/M
PLASTER ON CHB = (.24KN/M2)(1.6MX2) = .768 KN/M
TOTAL DEAD LOAD = 10.038 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)(1.25M) = 2.375
TOTAL LIVE LOAD = 2.375
FACTORED LOAD
WU = 1.2(10.038) + 1.6(2.375)
WU = 15.846 = 16 KN/M

A3-A5
DEAD LOAD
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146M) = 14.50KN/M
CHB = (16.5KN/M3)(.15)( 6.146M)=15.21 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5) = 1.155 KN/M
TOTAL DEAD LOAD = 36.175 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146M) = 11.68 KN/M
TOTAL LIVE LOAD = 11.68 KN/M
FACTORED LOAD
WU = 1.2(36.175) + 1.6(11.68)
WU = 62.098 = 62 KN/M

A5-A7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146M) = 14.50KN/M
CHB = (16.5KN/M3)(.15)( 6.146M)=15.21 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5) = 1.155 KN/M
TOTAL DEAD LOAD = 36.175 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146M) = 11.68 KN/M
TOTAL LIVE LOAD = 11.68 KN/M
FACTORED LOAD
WU = 1.2(36.175) + 1.6(11.68)
WU = 62.098 = 62 KN/M

P3-P5
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146M) = 14.50KN/M
CHB = (16.5KN/M3)(.15)( 6.146M)=15.21 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5) = 1.155 KN/M
TOTAL DEAD LOAD = 36.175 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146M) = 11.68 KN/M
TOTAL LIVE LOAD = 11.68 KN/M
FACTORED LOAD
WU = 1.2(36.175) + 1.6(11.68)
WU = 62.098 = 62 KN/M

P5-P7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146M) = 14.50KN/M
CHB = (16.5KN/M3)(.15)( 6.146M)=15.21 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5) = 1.155 KN/M
TOTAL DEAD LOAD = 36.175 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146M) = 11.68 KN/M
TOTAL LIVE LOAD = 11.68 KN/M
FACTORED LOAD
WU = 1.2(36.175) + 1.6(11.68)
WU = 62.098 = 62 KN/M

B2-B3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.25+1.25M) = 14.50KN/M
TOTAL DEAD LOAD = 8.26 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.25+1.25M) = 4.75 KN/M
TOTAL LIVE LOAD = 4.75 KN/M
FACTORED LOAD
WU = 1.2(8.26) + 1.6(4.75)
WU = 17.512 = 18 KN/M
B7-B8
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.25+1.25M) = 14.50KN/M
TOTAL DEAD LOAD = 8.26 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.25+1.25M) = 4.75 KN/M
TOTAL LIVE LOAD = 4.75 KN/M
FACTORED LOAD
WU = 1.2(8.26) + 1.6(4.75)
WU = 17.512 = 18 KN/M

O2-O3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.25+1.25M) = 14.50KN/M
TOTAL DEAD LOAD = 8.26 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.25+1.25M) = 4.75 KN/M
TOTAL LIVE LOAD = 4.75 KN/M
FACTORED LOAD
WU = 1.2(8.26) + 1.6(4.75)
WU = 17.512 = 18 KN/M

O7-O8
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.25+1.25M) = 14.50KN/M
TOTAL DEAD LOAD = 8.26 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.25+1.25M) = 4.75 KN/M
TOTAL LIVE LOAD = 4.75 KN/M
FACTORED LOAD
WU = 1.2(8.26) + 1.6(4.75)
WU = 17.512 = 18 KN/M

B3-B5
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+4.646M) = 21.93KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
TOTAL DEAD LOAD = 37.38 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+4.646M) = 17.655 KN/M
TOTAL LIVE LOAD = 17.655 KN/M
FACTORED LOAD
WU = 1.2(37.38) + 1.6(17.655)
WU = 73.1 =73 KN/M

B5-B7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+4.646M) = 21.93KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
TOTAL DEAD LOAD = 37.38 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+4.646M) = 17.655 KN/M
TOTAL LIVE LOAD = 17.655 KN/M
FACTORED LOAD
WU = 1.2(37.38) + 1.6(17.655)
WU = 73.1 =73 KN/M

D3-D5
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+4.646M) = 21.93KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
TOTAL DEAD LOAD = 37.38 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+4.646M) = 17.655 KN/M
TOTAL LIVE LOAD = 17.655 KN/M
FACTORED LOAD
WU = 1.2(37.38) + 1.6(17.655)
WU = 73.1 =73 KN/M

D5-D7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+4.646M) = 21.93KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
TOTAL DEAD LOAD = 37.38 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+4.646M) = 17.655 KN/M
TOTAL LIVE LOAD = 17.655 KN/M
FACTORED LOAD
WU = 1.2(37.38) + 1.6(17.655)
WU = 73.1 =73 KN/M

F3-F5
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+4.646M) = 21.93KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
TOTAL DEAD LOAD = 37.38 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+4.646M) = 17.655 KN/M
TOTAL LIVE LOAD = 17.655 KN/M
FACTORED LOAD
WU = 1.2(37.38) + 1.6(17.655)
WU = 73.1 =73 KN/M

F5-F7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+4.646M) = 21.93KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
TOTAL DEAD LOAD = 37.38 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+4.646M) = 17.655 KN/M
TOTAL LIVE LOAD = 17.655 KN/M
FACTORED LOAD
WU = 1.2(37.38) + 1.6(17.655)
WU = 73.1 =73 KN/M

K3-K5
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+4.646M) = 21.93KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
TOTAL DEAD LOAD = 37.38 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+4.646M) = 17.655 KN/M
TOTAL LIVE LOAD = 17.655 KN/M
FACTORED LOAD
WU = 1.2(37.38) + 1.6(17.655)
WU = 73.1 =73 KN/M
K5-K7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+4.646M) = 21.93KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
TOTAL DEAD LOAD = 37.38 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+4.646M) = 17.655 KN/M
TOTAL LIVE LOAD = 17.655 KN/M
FACTORED LOAD
WU = 1.2(37.38) + 1.6(17.655)
WU = 73.1 =73 KN/M

M3-M5
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+4.646M) = 21.93KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
TOTAL DEAD LOAD = 37.38 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+4.646M) = 17.655 KN/M
TOTAL LIVE LOAD = 17.655 KN/M
FACTORED LOAD
WU = 1.2(37.38) + 1.6(17.655)
WU = 73.1 =73 KN/M

M5-M7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+4.646M) = 21.93KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
TOTAL DEAD LOAD = 37.38 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+4.646M) = 17.655 KN/M
TOTAL LIVE LOAD = 17.655 KN/M
FACTORED LOAD
WU = 1.2(37.38) + 1.6(17.655)
WU = 73.1 =73 KN/M
O3-O5
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+4.646M) = 21.93KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
TOTAL DEAD LOAD = 37.38 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+4.646M) = 17.655 KN/M
TOTAL LIVE LOAD = 17.655 KN/M
FACTORED LOAD
WU = 1.2(37.38) + 1.6(17.655)
WU = 73.1 =73 KN/M

O5-O7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+4.646M) = 21.93KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
TOTAL DEAD LOAD = 37.38 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+4.646M) = 17.655 KN/M
TOTAL LIVE LOAD = 17.655 KN/M
FACTORED LOAD
WU = 1.2(37.38) + 1.6(17.655)
WU = 73.1 =73 KN/M

C3-C5
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146+6.146M) = 29KN/M
CHB = (16.5KN/M3)(.1M)( 6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5+1.5M) 2.31 KN/M
TOTAL DEAD LOAD = 46.76 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146+6.146M) = 23.35 KN/M
TOTAL LIVE LOAD = 23.35 KN/M
FACTORED LOAD
WU = 1.2(46.76) + 1.6(23.35)
WU = 93.47 = 93KN/M
C5-C7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146+6.146M) = 29KN/M
CHB = (16.5KN/M3)(.1M)( 6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5+1.5M) 2.31 KN/M
TOTAL DEAD LOAD = 46.76 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146+6.146M) = 23.35 KN/M
TOTAL LIVE LOAD = 23.35 KN/M
FACTORED LOAD
WU = 1.2(46.76) + 1.6(23.35)
WU = 93.47 = 93KN/M

E3-E5
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146+6.146M) = 29KN/M
CHB = (16.5KN/M3)(.1M)( 6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5+1.5M) 2.31 KN/M
TOTAL DEAD LOAD = 46.76 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146+6.146M) = 23.35 KN/M
TOTAL LIVE LOAD = 23.35 KN/M
FACTORED LOAD
WU = 1.2(46.76) + 1.6(23.35)
WU = 93.47 = 93KN/M

E5-E7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146+6.146M) = 29KN/M
CHB = (16.5KN/M3)(.1M)( 6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5+1.5M) 2.31 KN/M
TOTAL DEAD LOAD = 46.76 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146+6.146M) = 23.35 KN/M
TOTAL LIVE LOAD = 23.35 KN/M
FACTORED LOAD
WU = 1.2(46.76) + 1.6(23.35)
WU = 93.47 = 93KN/M
G3-G5
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146+6.146M) = 29KN/M
CHB = (16.5KN/M3)(.1M)( 6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5+1.5M) 2.31 KN/M
TOTAL DEAD LOAD = 46.76 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146+6.146M) = 23.35 KN/M
TOTAL LIVE LOAD = 23.35 KN/M
FACTORED LOAD
WU = 1.2(46.76) + 1.6(23.35)
WU = 93.47 = 93KN/M

G5-G7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146+6.146M) = 29KN/M
CHB = (16.5KN/M3)(.1M)( 6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5+1.5M) 2.31 KN/M
TOTAL DEAD LOAD = 46.76 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146+6.146M) = 23.35 KN/M
TOTAL LIVE LOAD = 23.35 KN/M
FACTORED LOAD
WU = 1.2(46.76) + 1.6(23.35)
WU = 93.47 = 93KN/M

J3-J5
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146+6.146M) = 29KN/M
CHB = (16.5KN/M3)(.1M)( 6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5+1.5M) 2.31 KN/M
TOTAL DEAD LOAD = 46.76 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146+6.146M) = 23.35 KN/M
TOTAL LIVE LOAD = 23.35 KN/M
FACTORED LOAD
WU = 1.2(46.76) + 1.6(23.35)
WU = 93.47 = 93KN/M
J5-J7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146+6.146M) = 29KN/M
CHB = (16.5KN/M3)(.1M)( 6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5+1.5M) 2.31 KN/M
TOTAL DEAD LOAD = 46.76 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146+6.146M) = 23.35 KN/M
TOTAL LIVE LOAD = 23.35 KN/M
FACTORED LOAD
WU = 1.2(46.76) + 1.6(23.35)
WU = 93.47 = 93KN/M

L3-L5
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146+6.146M) = 29KN/M
CHB = (16.5KN/M3)(.1M)( 6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5+1.5M) 2.31 KN/M
TOTAL DEAD LOAD = 46.76 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146+6.146M) = 23.35 KN/M
TOTAL LIVE LOAD = 23.35 KN/M
FACTORED LOAD
WU = 1.2(46.76) + 1.6(23.35)
WU = 93.47 = 93KN/M

L5-L7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146+6.146M) = 29KN/M
CHB = (16.5KN/M3)(.1M)( 6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5+1.5M) 2.31 KN/M
TOTAL DEAD LOAD = 46.76 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146+6.146M) = 23.35 KN/M
TOTAL LIVE LOAD = 23.35 KN/M
FACTORED LOAD
WU = 1.2(46.76) + 1.6(23.35)
WU = 93.47 = 93KN/M
N3-N5
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146+6.146M) = 29KN/M
CHB = (16.5KN/M3)(.1M)( 6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5+1.5M) 2.31 KN/M
TOTAL DEAD LOAD = 46.76 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146+6.146M) = 23.35 KN/M
TOTAL LIVE LOAD = 23.35 KN/M
FACTORED LOAD
WU = 1.2(46.76) + 1.6(23.35)
WU = 93.47 = 93KN/M

N5-N7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(6.146+6.146M) = 29KN/M
CHB = (16.5KN/M3)(.1M)( 6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)( 6.146M X2) = 2.95 KN/M
CERAMIC TILE = (.77 KN/M3)(1M)(1.5+1.5M) 2.31 KN/M
TOTAL DEAD LOAD = 46.76 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 6.146+6.146M) = 23.35 KN/M
TOTAL LIVE LOAD = 23.35 KN/M
FACTORED LOAD
WU = 1.2(46.76) + 1.6(23.35)
WU = 93.47 = 93KN/M

C2-C3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

C7-C8
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

D2-D3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

D7-D8
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

E2-E3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

E7-E8
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

F2-F3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

F7-F8
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

G2-G3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M
G7-G8
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

J2-J3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

J7-J8
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

K2-K3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

K7-K8
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

L2-L3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

L7-L8
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

M2-M3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

M7-M8
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

N2-N3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

N7-N8
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+1.6M) = 7.552KN/M
TOTAL DEAD LOAD = 9.912 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+1.6M) = 6.08KN/M
TOTAL LIVE LOAD = 6.08KN/M
FACTORED LOAD
WU = 1.2(9.912) + 1.6(6.08)
WU = 21.62 = 22 KN/M

H1-H3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+2M) = 8.496KN/M
TOTAL DEAD LOAD = 10.86 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+2M) = 6.84KN/M
TOTAL LIVE LOAD = 6.84KN/M
FACTORED LOAD
WU = 1.2(10.86) + 1.6(6.84)
WU = 23.98 = 24 KN/M

H7-H9
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+2M) = 8.496KN/M
TOTAL DEAD LOAD = 10.86 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+2M) = 6.84KN/M
TOTAL LIVE LOAD = 6.84KN/M
FACTORED LOAD
WU = 1.2(10.86) + 1.6(6.84)
WU = 23.98 = 24 KN/M

I1-I3
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+2M) = 8.496KN/M
TOTAL DEAD LOAD = 10.86 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+2M) = 6.84KN/M
TOTAL LIVE LOAD = 6.84KN/M
FACTORED LOAD
WU = 1.2(10.86) + 1.6(6.84)
WU = 23.98 = 24 KN/M

I7-I9
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(1.6+2M) = 8.496KN/M
TOTAL DEAD LOAD = 10.86 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 1.6+2M) = 6.84KN/M
TOTAL LIVE LOAD = 6.84KN/M
FACTORED LOAD
WU = 1.2(10.86) + 1.6(6.84)
WU = 23.98 = 24 KN/M
H3-H5
DEAD LOAD
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+6.146M) = 25.47KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)(6.146MX2) = 2.95 KN/M
TOTAL DEAD LOAD = 40.91 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+6.146M) = 20.50 KN/M
TOTAL LIVE LOAD = 20.50 KN/M
FACTORED LOAD
WU = 1.2(40.91) + 1.6(20.50)
WU = 81.89 = 81.89 KN/M

H5-H7
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+6.146M) = 25.47KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)(6.146MX2) = 2.95 KN/M
TOTAL DEAD LOAD = 40.91 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+6.146M) = 20.50 KN/M
TOTAL LIVE LOAD = 20.50 KN/M
FACTORED LOAD
WU = 1.2(40.91) + 1.6(20.50)
WU = 81.89 = 81.89 KN/M

I3-I5
DEAD LOAD
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+6.146M) = 25.47KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)(6.146MX2) = 2.95 KN/M
TOTAL DEAD LOAD = 40.91 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+6.146M) = 20.50 KN/M
TOTAL LIVE LOAD = 20.50 KN/M
FACTORED LOAD
WU = 1.2(40.91) + 1.6(20.50)
WU = 81.89 = 81.89 KN/M
I5-I7
DEAD LOAD
BEAM = (23.6KN/M3)(.2M)(.5M) = 2.36 KN/M
SLAB = (23.6KN/M3)(.1M)(4.646+6.146M) = 25.47KN/M
CHB = (16.5KN/M3)(.10M)(6.146M)=10.14 KN/M
PLASTER ON CHB = (.24KN/M2)(6.146MX2) = 2.95 KN/M
TOTAL DEAD LOAD = 40.91 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 4.646+6.146M) = 20.50 KN/M
TOTAL LIVE LOAD = 20.50 KN/M
FACTORED LOAD
WU = 1.2(40.91) + 1.6(20.50)
WU = 81.89 = 81.89 KN/M

AB4-AB6
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M

BC4-BC6
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M

CD4-CD6
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M

DE4-DE6
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M

EF4-EF6
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M

FG4-FG6
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M

GH4-GH6
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M

IJ4-IJ6
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M

JK4-JK6
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M

KL4-KL6
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M

LM4-LM6
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M

MN4-MN6
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M

NO4-NO4
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M

OP4-OP4
BEAM = (23.6KN/M3)(.2M)(.3M) = 1.42 KN/M
SLAB = (23.6KN/M3)(.1M)(3M) = 7.08KN/M
CHB = (16.5KN/M3)(.10M)(3M)= 4.95 KN/M
PLASTER ON CHB = (.24KN/M2)(3MX2) = 1.44 KN/M
TOTAL DEAD LOAD = 14.89 KN/M
LIVE LOAD
BASIC FLOOR AREA = (1.9 KN/M3)(1M)( 3M) = 5.7 KN/M
TOTAL LIVE LOAD = 5.7 KN/M
FACTORED LOAD
WU = 1.2(14.89) + 1.6(5.7)
WU = 26.99 = 27 KN/M