TIE IN PLAN

25/06/2019
ACTIVITIES PREDECESSOR RESOURCES 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

1 BI-WEEKLY PIGGING OPERATIONS DOESN'T IMPACT TIE-IN ACTIVITIES


ACTIVITIES ACTIVITIES

1 -TELEHANDLER
GRINDER
DISMANTLE THE 2 - SUPPORTING
2 STAIRS AND SCAFFOLD AND DOESN'T IMPACT TIE-IN ACTIVITIES
PLATFORM LADDER (CCCG)

1 - OPERATION
PUMP STATION - CERTIFICATION ACTIVITIES
3 SHUTDOWN WORKS OF TA-58 2 - CCCG (WELDER &
25 jun 2019 (09:00 am) - LOTOV FITTER) AND SOM
REPRESENTATIVES

4 CLOSE THE VALVES PUMP STATION OPERATION


AND DRAIN THE PIPE SHUTDOWN ACTIVITIES

DISMANTLE OLD PIG 1- TOOLS


5 LAUNCHER ITEM 04
2 - TELEHANDLER
(DISCONNECTION OF 3 - CLEANING TOOLS
PIPES ETC.) AND MATERIALS

1 - TOOLS
6 ASSEMBLE SLIP ITEM 04, 05 & 03 2 - TELEHANDLER
BLIND FLANGE
3 - SPILL
CONTAINMENT

1 - GRINDER
7 CUT THE PIPE 2 - TELEHANDLER
ITEM 05, 06
3 - TOOLS
4 - COLD CUT DEVICE

8 FITUP THE FLANGE 1 - GRINDER


ITEM 07
2 - TOOLS

9 WELDING (CRITICAL) ITEM 08 1 - WELD MACHINE

10 PERFORM RT ITEM 09
1 - QUALIFIED
(CRITICAL) INSPECTOR
1 - ASSEMBLE THE
NEW PIPE AND
INSERT SLIP BLIND
11 FLANGE SEPARATE ITEM 10 1 - TELEHANDLER
NEW HP LINE WITH 2 - TOOLS
EXISTING PUMP
STATION

REMOVE SLIP BLIND 1 -TOOLS


12 AND INSTALL NEW ITEM 10 2 - TELEHANDLER
GASKET 600# 3 - GASKET

RE-ASSEMBLE
13 STAIRS AND 1 -TOOLS DOESN'T IMPACT TIE-IN ACTIVITIES
ITEM 12
2 - TELEHANDLER
PLATFORMS

14 REPAIR
15 PERFORM RT
NOTES:
TIE IN PLAN
25/06/2019

3 – ASSEMBLE
THE SLIP BLIND
FLANGE