You are on page 1of 3

L&T Construction - B&F IC

Construction of permanent campus of IIT Hyderabad Phase-1


Doc. No
Doc.
: L&T/BNF/IITH/CH/RFMT
No : L&T/BNF/IITH/CH/RCC Revision No : 00
CHECKLIST FOR RCC(Conventional)
AREA/ BUILDING: BLOCK: DATE:

MEMBER: GRID NO:

S.no DRAWING REF: TIME:


PART-A
SAFETY
YES NO NA
Is Work Permit available for the specific activity (To be
1
attached)

2 Is JSA report available for this potential activity

3 Are all necessary PPEs provided to all the staff and labours

Has all workers been trained about the hazards on concrete


4
at depths and heights above 2.00 mtr

Is adequate illumination provided to work during night


5
(lighting fixtures should be provided at elevated heights)

Is the road for vehicle movement(TM,Pump) from BP & work


6
site free from undulations for concrete pouring
Are all equipments engaged for transporting concrete in
working condition having necessary Fitness
7
certificates/licences/Insurances/Statutory Clearances

Is the RCC area safe from underground utilities, overhead


8
power lines & construction vehicles

9 Are proper warning signages provided at site

Are walkways/Staging/Ladders provided in the pit undergoing


10
RCC

Are stoppers placed for stopping the Transit Mixers at safe


11
distance away from Pit edge

Whether Staircase access is provided for height works in


12
safe mode as per safety plan

Whether concrete pipe line is placed/running on chairs made


13
with reinforcement/steel

GRIHA

14 Is available water used efficiently

CHECKLIST - RCC - CONVENTIONAL - A Page 1 of 3


L&T Construction - B&F IC
Construction of permanent campus of IIT Hyderabad Phase-1
Doc. No
Doc.
: L&T/BNF/IITH/CH/RFMT
No : L&T/BNF/IITH/CH/RCC Revision No : 00
CHECKLIST FOR RCC(Conventional)
Is washing area provided for the construction vehicles/Transit
15 Mixers likely to ply on Bituminous/Concrete roads to avoid
dirtying

Is Solid Waste Programme implemented for


16 segregation,reduction and recycle of construction waste
materials during construction

17 Is water spinkled on roads moving transit mixers

Execution
A)Pre-Concreting
18 Whether check list for reinforcement is cleared

19 Whether check list for form work is cleared

Whether PCC surface is cleaned from strains and dust and


20
washed with water cleanly.

Whether any Water Proofing is apllicable in RCC as per


21
notings mentioned in drawing/provisions of Contract

Whether Water Proofing is done as per approved method


22
statement and check list

Whether the dimensions and depth of RCC is cross checked


23
with respective GFC drawings

24 Is the top level of pour marked over shuttering

Whether grade of concrete is as per approved drawing


25
Grade of Concrete ________

26 Whether pour card is signed

Whether pour plan is submitted for major concrete/special


27
concrete pour

Whether cloumn/beam joint concrete grades have poured as


28
per approved GFC drawings.

Whether adequate labour is avaialble at site for spreading


29
and masons for finishing

Whether plain Metallic platforms and placing arrangments


30
are provided as per requirement

Whether sufficient vibrators and needles are available with


stand bys.
31
Vibrators-----------------
Needles 60mm ------, 40mm-----,25mm-----

Whether all machinery(Static Pupms,Boom Placers, Tower


crane with Concrete Buckets,etc) and equipment are
32
adequate capacity and in good working condition for pouring
concrete

CHECKLIST - RCC - CONVENTIONAL - A Page 2 of 3


L&T Construction - B&F IC
Construction of permanent campus of IIT Hyderabad Phase-1
Doc. No
Doc.
: L&T/BNF/IITH/CH/RFMT
No : L&T/BNF/IITH/CH/RCC Revision No : 00
CHECKLIST FOR RCC(Conventional)

33 Whether construction joint is as per specified methodology

34 Whether Expansion Joints are as per specified methodoly

Whether filler matrial in Expansion Joints is as per BOQ


35
Item/Specification

Whether the specified methodology is adopted for vertical


36
and horizontal joints ,if work is resumed

Whether the specified methodology is adopted for concrete


37
under special conditions, if it arises.

Whether the concrete is levelled, compaction & finished


38
properly

Whether, there are adequate provisions for protecting the


39
RCC from rain.

Whether provisions have been made for Sleeve


40 insertions,Insert plate Embedding, MS angle/channel fixing,
etc, if they are required as per provisions

Whether stainless steel cramps, angle irons for holding


41 stones and any holding arrangement for Civil/ MEP/Other
Services have been seen and approved.

Whether conduits and conceal piping for various


42 electrical/mechanical/fire fighting/other services have been
seen and approved.

Whether all embedded parts of Civil/MEP/Other services are


43
adopted as per approved GFC

Whether curing arrangement is done properly and adequate


44 curing is ensured at site
Required days for curing as specified -----------

B) During Concrete Pour

Whether Slump is being measured and Concrete Cubes for


45
4sets( 12 Cubes) are taken as per pre-decided frequency

Note: Check if any existing underground services found should be protected from damage

Approved / Not approved for next stage


Remarks:

L&T TCE BSNL IITH

CHECKLIST - RCC - CONVENTIONAL - A Page 3 of 3