You are on page 1of 2

ID Task Name Duration Start Finish

Mar '19 Apr '19 May '19 Jun '19 Jul '19
24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21
1 PEKERJAAN PENYEHATAN RELICS AREA 150 days Thu 04/04/19 Sat 31/08/19
RFCC PT PERTAMINA RU IV CILACAP
2 Pre-Execution 6 days Thu 04/04/19 Tue 09/04/19
3 Kick-off Meeting 1 day Thu 04/04/19 Thu 04/04/19
4 Work Permit 5 days Fri 05/04/19 Tue 09/04/19
5 Preparation 9 days Sat 06/04/19 Sun 14/04/19
6 Survey 1 day Sat 06/04/19 Sat 06/04/19
7 Cable Installation 1 day Sat 06/04/19 Sat 06/04/19
8 Upload PLC Program 1 day Sat 06/04/19 Sat 06/04/19
9 Back-up HMI SCADA program 1 day Sat 06/04/19 Sat 06/04/19
10 HMI SCADA Request 1 day Sun 14/04/19 Sun 14/04/19
Modification Submit (by
Pertamina)
11 Engineering 65 days Mon 15/04/19 Tue 18/06/19
12 Eng. Document 65 days Mon 15/04/19 Tue 18/06/19
13 Functional Design 10 days Mon 15/04/19 Wed 24/04/19
Specification (Server)
14 Interconnection Diagram 15 days Mon 15/04/19 Mon 29/04/19
15 Commissioning 10 days Thu 30/05/19 Sat 08/06/19
16 Report 10 days Sun 09/06/19 Tue 18/06/19
17 PLC Programming 15 days Mon 15/04/19 Mon 29/04/19
18 HMI SCADA Programming 45 days Mon 15/04/19 Wed 29/05/19
19 Procurement 60 days Fri 05/04/19 Mon 03/06/19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project Schedule RELIC
Summary Manual Summary Rollup Progress
Date: Tue 02/04/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Name Duration Start Finish
Mar '19 Apr '19 May '19 Jun '19 Jul '19
24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21
20 Delivery Material 3 days Wed 05/06/19 Fri 07/06/19
21 Site Installation 7 days Thu 20/06/19 Wed 26/06/19
22 Pulling Cable 7 days Thu 20/06/19 Wed 26/06/19
23 Server Installation 7 days Thu 20/06/19 Wed 26/06/19
24 PLC Program Modification 7 days Thu 20/06/19 Wed 26/06/19
25 HMI Program Modification 7 days Thu 20/06/19 Wed 26/06/19
26 Pre-Commissioning 7 days Thu 27/06/19 Wed 03/07/19
27 Commissioning 7 days Mon 01/07/19 Sun 07/07/19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project Schedule RELIC
Summary Manual Summary Rollup Progress
Date: Tue 02/04/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2

You might also like