Professional Documents
Culture Documents
net/publication/267506822
CITATIONS READS
0 215
3 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Laifa Cao on 14 April 2016.
ABSTRACT
This paper presents shoring supports for a deep excavation within soft to firm silty clay near a railway in Toronto. The
shoring system which consisted of caisson/soldier pile walls with tiebacks was monitored during excavation. The tieback
testing and field monitoring results were reviewed and discussed. Back-analysis using a finite element program was
carried out to evaluate the shoring wall performance. Recommendations for the design of shoring walls in the similar soil
conditions are provided.
RÉSUMÉ
Cet article présente les parois délocalization pour une excavation profonde dans la argile limoneux doux au solide à
proximité d'un chemin de fer à Toronto. Le système d'étaiement avec les murs embrasses de caissons/soldier ont été
surveillés pendant l'excavation. Les résultats des embrasses essais et les surveillances de terrain ont été examinés et
discutés. Rétro-analyse avec d'un programme d'éléments finis a été utilisé pour évaluer la performance du mur étayage.
Cet article va fournir des recommandations pour la conception des parois délocalisationdans les conditions de sol
similaires.
Movement
100
Alignment Load
Movement (mm)
80
60
40
20
0
0 200 400 600 800 1000 1200
Load (kN)
120
Free Length + 50% Bond Length
Photo 1. Outlook of caisson wall and soldier piles with 100
0
15 mm strand tendons. The tiebacks were generally post-
grouted the day after they were installed. Table 1
summarizes the tieback characteristics. 5
3 FIELD MONITORING
40
Prior to the excavation, the shoring walls were reviewed
and noted that they were marginally acceptable. Two
20 options were proposed: (1) add one more layer of
tiebacks; (2) monitor the movements of shoring walls and
nearby railway and retaining walls using field
0
instrumentation during excavation. The contractor
0 200 400 600 800
preferred the monitoring option. Thus extensive field
Load (kN)
monitoring during excavation was recommended. The
80 field monitoring included inclinometers and reflective
Elastic Movement targets installed at the top and middle parts of shoring
Elastic Movement (mm)
80% Free Length walls as well as on railway rail and retaining wall.
60 The caisson wall near the existing railway was
Free Length+50%Bond monitored using inclinometers and reflective targets.
Three inclinometers were installed behind the caisson
40 walls. The inclinometers were monitored during and after
the excavation. Figure 3 shows the monitoring results of
one inclinometer installed in the middle section of the
20
caisson wall including the readings taken after upper and
lower tieback installations, 1 day after the excavation to
0 bottom, and about 1 months after the excavation. The
0 200 400 600 800 lateral deflections measured by reflective targets installed
Load (kN) at the top of caissons are also shown in Figure 3. The
measurements of reflective targets are generally
Figure 2. A typical proof test for upper tieback consistent with the inclinometer measurements except
The average SPT N-value for soils in which tieback is 15 Very dense Excavation
bonded should be used in Eqs. (1) and (2). The proposed sandy silt till Level
correlations need to be verified by performance tests.
Based on the performance test results, the bond
length for the upper tiebacks installed in shallow compact
20
silt to sandy silt and/or firm to very stiff clayey silt till was
increased to 6.5m. Inclinometer after upper tieback installed
Proof tests were carried out for all production tiebacks. Reflective target after upper tieback installed
The proof test load was 133% of the design load and the Inclinometer after lower tieback installed
25 Reflective target after lower tieback installed
test load was generally maintained for 10 minutes for Inclinometer 1 d after excavation to bottom
each tieback. A typical result of tieback proof test is Reflective target 1 d after excavatio to bottom
shown in Figure 2, in which the elastic movement is Inclinometer 1 m after excavation to bottom
Reflective target 11 m after excavation to bottom
usually estimated based on a performance test. In the
case that the performance test cannot be compared with 30
the proof test, the elastic movement should be estimated
Figure 3. Lateral deflection of caisson wall
measurements taken after lower tieback installation, at
which inclinometer gave a lower lateral movement.
The railway located at about 15 m off the caisson wall
was monitored using sixteen reflective targets installed at
3 m spacing along rail. When the excavation reached 6m
below grade, the lateral movement of the railway was up
to 16mm with an average value of 12 mm and settlement
up to 9mm with an average value of 4 mm. Then railway
maintenance was carried out. When the excavation
continued from 6 to 7 m below grade, the railway lateral
movement was up to 12 mm and vertical movement up to
22 mm. One month after exaction to the bottom, no
increment in lateral movement was observed, whereas
increment in settlement was 2 mm.
The soldier pile walls were monitored only using
reflective targets installed at two levels. When excavation
reached 5 m below grade at the north soldier pile wall,
loss of ground behind the wall as well as cracks in the
pavement adjacent the wall were observed.
Corresponding to these observations, a lateral deflection
up to 32 mm was measured by a reflection target installed
at that location. The lost soils were replaced by concrete
as shown in Photo 2. When excavation was to 7 m below
grade, the lateral movement of north soldier pile wall was
up to 70 mm with an average value of 25 mm and
settlement up to 23m m with an average value of 7 mm.
Although significant lateral deflections of the soldier pile
walls were observed locally, the excavation for the
building construction can be considered as successful
since the average lateral movement was limited to a
tolerable level, i.e. 25 mm . Photo 2. Cracks in pavement and concrete pouring to
replace soil
taken as 0.3 for sandy soils and 0.49 for clayey soils. The
4 FINITE ELEMENT BACK-ANALYSIS unit weight, γ was obtained from available laboratory
testing data. Mohr Coulomb failure criterion was used for
Finite element program Phase 2 (version 8.0) was used in soils. The soil properties used in the analysis are shown in
the back-analysis. The program can be used to simulate Table 2.
excavation in soil under plane strain condition. Six-node
triangle elements were used to model the soil media. The Table 2. Soil parameters used in the finite element
caisson wall and tiebacks were modelled by structural analysis
beam elements. The analysis modelled a half width of the
excavation where the right-hand boundary of the mesh
represented the line of symmetry at the centre line of Depth Soil Type γ E su φ Ko
(m) (kN/m3) (MPa) (kPa)
excavation. The finite mesh was 150 m long and 80 m
0 – 5.4 Silty sand 20 10 - 32 0.7
deep. The half width of the excavation was 30m. The fill
bottom boundary was strained from both vertical and Silty clay 19 17.5 35 - 1
5.4 –
horizontal movements. The left-hand and right-hand 13.3
boundaries were free to move in the vertical direction. Sandy silt 22 145 - 36 1
>13.3
The soil profiles used in the analysis were based on till
nearby borehole logs. The groundwater level was taken at Note: Ko is the coefficient of lateral earth pressure (total
3.6 m below existing ground surface prior to excavation. stress).
During the excavation, the groundwater level was
assumed to be drawn down to the excavation level at the The caisson wall was modelled as reinforced concrete
excavated side. with 2 nos. of W16x60 steel beams (equivalent to 2 nos.
For the sandy fill, a Young’s modulus, E of 10 MPa of W410x85) at spacing of 2.4 m. The equivalent
and a friction angle, φ of 32 were assumed. The residual
o
thickness of 40 MPa concrete was taken as 455 mm and
φ was taken as 30 . For the clayey soils, based on file
o
the Young’s modulus was 28 GPa. The concrete
vane shear tests, an average value of undrained shear compressive and tensile strengths were taken as 30 MPa
strength, su of 35 kPa was used in the analysis. The and 3 MPa, respectively. The compressive and tensile
residual su was taken as 50% of the initial su. The strengths of W16x60 were taken as 345 MPa. The
undrained E of clayey soil was estimated from 1000su for Poisson’s ratio for steel and concrete was taken as 0.2.
the low plasticity silty clay. The soil Poisson’s ratio was The equivalent bolt diameters for the upper and lower
tiebacks were taken as 80.8 mm and 98.8 mm, Lateral Deflection (mm)
respectively. The Young’s modulus of tiebacks was taken -40 -20 0 20 40
0
as 200 GPa. The bond shear stiffness was taken as 6000
kN/m/m based on the tieback proof test results. The bond
lengths of the upper and lower tiebacks were taken as 7.5
m and 12 m, respectively. The spacing of tiebacks was Loose to
5 compact
taken as 2.4 m. Based on tieback proof tests, the pre- fill
tensioning force for the upper and lower tiebacks were
taken as 500 and 860 kN, respectively in the analysis. Excavati
The E90 train load was simulated as 108 kPa uniform on Level
disturbed load on a strip width of 2.44 m. 10 Soft to
Figure 4 shows the deform meshes when the firm
silty T ieback
excavation reaches 7m below grade. The heaven of clay
Depth (m)
excavation base is up to 80 mm and the wall deflection up s
to 34 mm. The nearby train has a litter influence to the 15
lateral deflection of the caisson wall as expected. The
variation in the wall lateral deformation due to train load is Very dense
sandy silt
about 3 mm.
till
20