Westside Regional Treatment Plant News

Volume 1, Issue 1 Newsletter Date

Odour Control at the Plant


I Didn’t Know
Our staff, supported by the  Before summer the biofilter Inside this issue:
Stakeholder Committee (with media will be replaced, foul
That…
representatives from West Odour Control Focus 1
air ducting/piping below
Kelowna, Peachland and the media will be modified  The average daily flow into
What’s a Biofilter? 1
Westbank First Nation) are and steps will be taken to the plant during 2013 was
10,125 cubic meters of
continuing to follow up on eliminate any leakage of Interesting Facts 1 wastewater
recommendations from the four air.
2013 Odour Assessment 2014 Projects Update 2  Wastewater from 10,735
Report.  We will also install equip- residential, 869 commercial
ment to assist in monitor- Irrigation Pilot 2 and 643 institutional units in
Our goal is to cost-effectively West Kelowna flowed into
ing the performance of the the plant during 2013
reduce potential odour im- Managing Biosolids 2
biofilter.
pact from the plant.
 Approximately 2,957 resi-
Many of the recommenda-  We’ll continue this year dential, 347 commercial and
with ongoing odour moni- 163 institutional units within
tions are being implemented the Westbank First Nation
this year. Among them: toring in the neighbour- reserves are connected to
hoods around the treat- the sewage collection sys-

A detailed assessment of ment plant. The areas that tem that ends at the plant

the current plant biofilter will be focused on include


 In Peachland during 2013
was done during April. Canyon Ridge, the Pointe 1,356 residences, 162 com-
This work included a and locations along Whit- mercial businesses and 163
worth Road. Sampling and institutional units sent
smoke test – in which con-
wastewater to the plant for
centrated smoke is intro- analysis for this work will The open bed biofilter
treatment.
duced into the plant venti- be carried out through a system used at
lation pipe distribution program involving gradu- Wastewater Treatment  The Operational Certificate

system under the biofilter ate students of the Univer- Plant is similar to that from the Ministry of Environ-
ment authorizes the dis-
media to determine the sity of British Columbia— used at a majority of facil-
charge of reclaimed
condition of the biofilter. Okanagan campus. ities as an effective odour wastewater via a deep lake
reduction method. outfall into Okanagan Lake
approximately 475 meters
from shore at a depth of
between 46 and 68 meters

Biofilter 101—the Basics  The Maximum Daily Effluent


Discharge Rate authorized
Biofiltration is a very ef- throughout the treatment wood chips, soil and other by the Ministry for 2014 is
fective technology that’s plant through an isolated material that receives the 36,000 cubic meters of treat-
ed wastewater.
used to reduce odours. ventilation system and odourous gases.
using blowers are uniformly
A majority of operating Micro-organisms in this po- Source: 2013 Annual Report—
distributed through the view it at:
biofilters at plants across rous media, which is kept
biofilter media by way of a
the continent are open wet with irrigation, biologi-
lateral perforated pipe sys- w w w . r e g i o n a l d i s t r i c t . c om /
bed biofilters, like the one cally act with the odourous wastewater
tem that’s embedded in
in use at our plant. Odou- gases to ’scrub’ them out of
gravel. The biofilter media
rous gases are collected the gases before releasing
is a mixture of compost,
into the open air.
Biosolids Management— Disposal
of Post-treatment materials
While our facility discharges treat- than four decades across North Amercia
ed effluent, there’s more than wa- and Europe in agricultural and other land
Treatment Plant News ter in the material that initially uses.
enters the plant.
Treated biosolids from our plant have
Regional District of Central Okanagan The treatment process removes been used in the past to reclaim and re-
1450 KLO Road these solids from the water. This generate vegetation in gravel pits and has
Kelowna, BC stabilized sewage sludge is called most recently been hauled by specially
biosolids, a wet soil-like material. equipped trucks to a ranch near Clinton in
Phone: 250-763-4918 Approximately 90% of pathogens the Cariboo, as part of a land application.
Fax: 250-763-0606 are removed from the sludge dur-
E-mail: engineer@cord.bc.ca ing the treatment process. As As a result of the annual winter-spring
much of the water as possible is Provincial load restrictions which will likely
removed, leaving the biosolids, remain in effect through mid to late May,
containing mostly water, sand, during this time there may be more fre-
nutrients and organic matter quent movement of biosolids trailers from
(humus), which contains nutrients the plant. In order to accommodate the
that plants need to grow along plant’s current production of biosolids,
with microorganisms and trace trailers will be removed and replaced
elements. twice daily, while the load restrictions are
in effect.
As a result, biosolids are excellent
WE’RE ON THE WEB for land use fertilizer application. The Regional District is seeking a more
Such use is subject to Provincial cost-effective solution for ongoing man-
regulations which include setbacks agement of biosolids byproduct. It’s an-
WWW.REGIONALDISTRICT.COM/
from water bodies and water ticipated that before this summer, a Re-
WASTEWATER quest for Proposals will be issued, seeking
courses. Treated biosolid applica-
tion has been widely used for more responses from interested and qualified
parties.

Treated Effluent Pilot Project 2014 Plans


 Landscape Project
The Regional District has would be a great partnership
received a grant from the between local government and * A consultant is being hired to complete a
Okanagan Basin Water Board business and has the potential final landscape design around the
for a pilot project with a to reduce water consumption Wastewater Treatment Plant. Once we
neighbour of the Westside and treatment costs, as well have the design, planting will be done
Regional Wastewater Treat- as innovatively using treated during the remainder of this year and
ment Plant. effluent in a responsible man- into next. The project includes a new
ner. entrance sign and landscaping that’s low
The $18,000 grant helps fund
maintenance, cost effective and fits in
a project to assess and test The first phase would see a
with the surrounding natural landscape.
the feasibility of using treat- consultant researching wheth-
Our goal for this landscaping project is to
ed effluent from the plant as er treated effluent from the
provide a more natural visual buffer.
a source of irrigation water plant can be beneficially used
for the Bylands Nursery prop- on plants in the nursery.
erty right next door.
Then over the summer, the
The ultimate goal would be to second phase would see treat-
eliminate the need for By- ed effluent used to irrigate a
lands to pump water from test section in the nursery.
Okanagan Lake to irrigate its
Finally, if successful, the plant
property on Gellatly Road.  Air balancing of all HVAC systems to
could provide water to the
improve odorous air containment
The three stage project nursery for irrigation.
* The systems have been adjusted to pro-
vide negative pressure inside some main
process areas such as the sludge han-
dling building minimizing odourous air
escaping the system.