Professional Documents
Culture Documents
A. DIRECT COST
Material
Item Descreption Unit Unit Cost Total SUBTOTAL
Qty
I. MOBILIZATION
temporary structure, I.e LS 2% of total direct cost 18,306.29
warehouse, field office, Qfr
bunkhouse
II. EARTHWORKS
clearing, grading sq.m 182.8605
excavation (soil only) cu.m 23.597875
backfilling w/ compacting cu.m 13.34675
Filling materials cu.m 16.6834375 250 4170.859375
SOIL POISONING
Chlordane (1 lit mixtue / 4sq.m) lit 25 500 12500
MATERIAL COST
3.1 Footing
a.column V = cu.m 2.176 Class A
crushed gravel, 3/4 cu.m 2.176 500 1088
crushed sand cu.m 1.088 500 544
gravel beddings cu.m 1.088 400 435.2
porland cement bags 19.584 165 3231.36
IV. REBARS
4.1 Column footing
12 mm dia. deformed bars (10.5m length) pcs 14 125 1,752.62
Ga 16 GI Tie wire kg 2.5 32 80.00
4.2 Wall footing
10 mm deformed bars (13.5m length) pcs 4 140 560.00
10 mm deformed bars (12m length) pcs 12 72 864.00
Ga 16 GI Tie wire kg 1.5 32 48.00
4.3 Column
20 mm deformed main bars (7.5m length) pcs 68 160 10,880.00
10 mm deformed bars (12m length) pcs 18 150 2,700.00
Ga 16 GI Tie wire kg 9 32 288.00
4.4 Beam
16mm deformed main bars (9m length) pcs 48 165 7,920.00
12 mm deformed bars (7.5m length) pcs 41 135 5,535.00
Ga 16 GI Tie wire kg 8.5 32 272.00
V. MASONRY WORKS
4.1 CHB (exterior wall ) A = sq.m 178.45
6" CHB pcs 2230.625 9 20075.625
screened sand cu.m 15.06118 500 7530.59
portland cement bags 181.6621 165 29974.2465
SUMMARY
A. DIRECT COST
Item Description Material cost Labor Cost Equipment Cost Total
I. MOBILIZATION Lump sum 18,306.29
II. EARTHWORKS 16670.85938 8190 1000 25,860.86
IIII. CONCRETE WORKS 88,227.32 26,468.20 4,411.37 119,106.89
IV. REBARS 61,953.62 18,586.09 3,097.68 83,637.39
V. MASONRY WORKS 109,351.63 32,805.49 5,467.58 147,624.70
VI. CARPENTRY WORKS 195,123.02 58,536.91 9,756.15 263,416.08
VII FINISHING WORKS 101,785.82 30,535.75 5,089.29 137,410.86
VIII ROOFING WORKS 51,364.60 15,409.38 2,568.23 69,342.21
IX SANITARY WORKS 32,530 9759 1626.5 43,915.50
X ELECTRICAL WORKS Lump sum 25,000
XIII DEMOBILIZATION Lump sum 18,306.29
GRAND TOTAL PHP 951,927.06
B. INDIRECT COST
1 OCM (OVERHEAD, CONTINGENCIES, MISC. FEES) 13% OF TDC PHP 123,750.52
2 CONTRACTOR'S PROFIT 13% OF TDC PHP 123,750.52
3 VAT 10% OF TDC PHP 95,192.71
TOTAL INDIRECT COST PHP 342,693.74
GRAND TOTAL DIRECT COST 1,859,687
PREPARED BY:
________________________________
Engineer