Professional Documents
Culture Documents
COURSE
218.763
ADVANCE CONSTRUCTION LAW,2019
BY
Suresh Govindaraj
STUDENT ID:19026136
COURSE COORDINATOR
DR. NASEEM AMEER ALI
RISK ALLOCATION IN
CONSTRUCTION CONTRACTS
Contents
1. Introduction
3. Risk management
a) How to deal with the risks
Transferring the risk
Accepting the risk
Avoiding the risk
insurance
4. Procurement Methods
a) Traditional
Lump-sum contract
Measurement Contract
Cost-Plus Contract
b) Integrated
Design and Build Contract
Package Deal Contract
c) Management Contracting
5. Conclusion
6. References
1. INTRODUCTION
The risks are broadly classified into three groups. The first type is the pure and
particular risk. It inscribes the risks that cause damage to people and property
such as explosion or any other natural calamity. These are generally covered by
the insurance and its mandatory have them under the contract obligations. The
second type is called as fundamental risks and they include government
policies, malicious damage, etc. and the insurance cover isn’t necessary as they
are all subject to statutory liabilities. The third category is referred to as
speculative risks. This category includes risks that can be apportioned during the
pre-contract stage. The common risks under this category are cost, schedule
and performance risks. In addition, there are other risks which are less common
yet equally significant. They are strategic risks, governance risks, market risks,
legal risks and operational risks.
The following sections will guide through the basic understanding of contracts,
how to deal with the contractual risks followed by the ideal risk allocation
recommendations for the common procurement types.
2. THE FUNDAMENTALS OF A CONTRACT
AGREEMENT
It is a negotiated arrangement among the parties that provides an
acceptable offer to each other to do particular work. The offer is
awarded by the client and the contractor acts as receiver and in return
the contractor develops the client’s vision.
INTENTION
It is defined as the purpose to enter into a contract by a party and is
expected to be genuine and unbiased and intentions are enforceable
by law
CONSIDERATION
It is the outcome that each of the parties benefit from entering into
contract and has to be valued reasonably. Considerations are preferred
to be kept in a balance between the benefit and burden between the
two parties.
LEGAL CAPACITY
The parties entering into a contract must be legally admissible to do so.
Some basic criteria are age, mental capacity, etc. Basically, the parties
entering the contract must be in a position to understand that they are
taking an ownership of responsibility enforceable by law.
All the contracts must have these four-criterion satisfied and that forms the basis
of a contract. These criteria are expressed as terms of contract which is broadly
classified into two groups, conditions and warranties.
Conditions are the fundamental parts of a contract that defines all the major
works. In the case of a construction contract, conditions include the clauses the
furnish the information on cost, quality, schedule, bills of quantities, specifications
and other major factors of the project. The conditions of a contract are legally
binding by default unless the contract says otherwise. Whereas, warranties are
supplemental terms in a contract that does not contribute any major
significance in making or breaking a contract. On the other hand, conditions, if
breached may even lead to termination of contract.
A contract is tailor made based on the inputs from the client/contractor to suit
best to their interests. Clients and the contractors can be grouped based on
their previous endeavors, nature and their business strategy. The client will be on
the deciding end to choose a particular type of procurement method and
eventually find a contractor who specializes in that procurement method.
There are various strategies that have been appreciated with regards to risk
management, but the most used strategy would be identifying the risk and
tagging a price for it.
Pricing the risk for is a universally accepted practice and its application is
adopted in almost all the risks that people take in their day-to-day life. For
instance, let’s consider the famous Chinese casino game ‘sic-boo’, where three
dice are rolled in an enclosed chamber and the players must guess the number
on the dies. The game works in such a way that, the least probable outcome
would bag the highest reward and the ones that can be easily guessed will get
the minimum reward.
The parties that enter into a contract, the contractor and the client have to
considerably allocate the risks among themselves based on the above
mentioned factors. To make the allocation more effective, there is another
factor called “frequency of risks” which would indicate who ought to take the
responsibility of the risks.
In some cases, such that the client an active builder it is good to take few risks
and retain the financial benefit for it. The one who builds repeatedly might have
a deeper understanding of the risks, therefore bearing the financial liability for a
particular risk (provided that its occurrence is very rare on the account of
projects taken) can be borne by the client himself.
It is essential to mention that, failing to have a contractual provision for the risk,
that is, if the contract is silent on who takes responsibility for it, the risk is sided on
either party eventually. Therefore, it is better to identify the risk on the pre-tender
stage and apportion it.
How to deal with the risks?
Dealing with is risks is not dealing with the uncertainty, which is usually
misinterpreted by most of professionals in the industry. It is the art of
maturely handling the identified risks. This art is the heart and soul of every
successful business person, whose strategy is viewing the risks from the
commercial point of view and it is often coined as “calculated risks” in the
business forums. As the earlier sections spoke about identifying and
analyzing the risks, this section will highlight the ways to ‘respond’ to these
risks.
Acceptance of risk
Certain risks have to be accepted by the client in and steal the
advantage of it. The occurrence of these risks such as war, earthquakes
and seizure, are very less. Its is unwise for the client to expect the
contractor to pay the premium for these risks as they clearly don’t hold
control over it. Avoidance of paying premium for these risks in short term is
not a brilliant decision considering the good probability of these risks on a
long term basis. Similarly, the contractor has to own the responsibilities for
certain risks such as health and safety of labors etc.
Avoidance of risk
When the results of the initial risk management process suggest that the
risk is unacceptable by either of the parties, then its good to just avoid it.
“Avoiding it” does not mean ignoring the risk. It means redefining the
process in such a way that the risk is not avoided. For instance, if there are
two ways to make a payment to purchase a product, one is online
payment and the other one paying buy cash in the nearby store. Assume
that there is a prolonged network issue in the neighborhood. Now, making
a payment online is risky business because if the transaction fails it gets 30
days to get a refund. So, the wise option is to manually walk to a store and
pay it. In this example it is a good alternative as the person is walking,
which is a physical exercise and also pays less tax.
Insurance
Insurance is a great way of dealing with the risks but unfortunately, there
are some situation’s that insurance fails to cover or it simply cannot be
insured at all. The design consultant of a design and build contractor is
very unlikely to get a professional indemnity insurance because the liability
owed by the design consultant is fitness of purpose and one with a very
minimum knowledge about how an insurance works can figure that out,
provided they are aware of the term “fitness of purpose”. Besides, most of
the construction works are insured by either of the parties in a contract.
Professionals shall cover them through a professional indemnity insurance
against the risk of failing to perform their duties aligning with the expected
level of skill and quality.
4. PROCUREMENT METHODS
TRADITIONAL
As the name suggests it’s the oldest procurement method. The other
name for traditional procurement is separated procurement method. This
method lets the client appoint an architect who will be presenting the
ideas of the client in a drawing format. Once the outline structure is
finalized the client or the architect himself outsources for a working
design and the cost estimation. These groups can be individual or
collaborative and are liable to client. Upon framing a brief scope of the
project, the client invites tenders from the contractors. The lowest bidding
contractor and the client enters into a contract. The terms of the
contract will be made according to the type of separated procurement
method. Separated procurement is classified as follows:
o MEASUREMENT CONTRACT
In this type of contract, the actual cost of the project cannot be
determined in the tendering stage, but a re-measurement of the
works done is finally calculated and the bill is settled. Let’s consider
an Eco-park project to understand this type of procurement. The
project brief states that an eco-park must be constructed on
barren land that features a man-made lake along with other
normal facilities of a park. The land has to be excavated in order
to build a man-made lake. Considering this situation, the land that
has to be excavated cannot be accurately determined in the
initial stage. Therefore, in these type of construction works, a
measurement contract is preferred. The contractor and the client
have to document the amount of land excavated for future
references and also to maintain a healthy relationship between
the parties. Measurement contract may lead to fraudulent
activities if the client fails to pay proper attention. So, this contract
expects that extra attention from the client. However, risks are still
high in the contractor end. The possible risk the contractor might
face in the above-mentioned project would be because of
natural calamities. Let’s assume that over 75% of excavation is
completed and now the site is experiencing heavy rainfall that
eventually leads to flood. The contractor is safe if the contract has
a provision for such calamities. Even though, it is very difficult to
anticipate the real time situation well in advance to extend the
provisions of contract to such uncertainties. It is suggested to have
a proper risk allocation considering these situations and also draft
a contract that clearly explains it.
INTEGRATED
o PACKAGE DEAL
Some of the basic ideas are similar to design/build type of contract
but the involvement of client is even more lesser compared to DB.
This method offers the client with a standardized set of buildings
that are functional type. Moreover, the contractor follows a
repetitive theme and minimize the scope for innovation in the
project. This will suit the clients who are willing to buy a property
that is completely based on the ideas of the contractor complying
to half baked satisfaction. Some examples of such constructions
are townships, retirement village, etc. These contracts
predominantly exist in highly populated countries and the target
clients are lower middle class to upper middle class people. The risk
allocation is entirely on the developer’s shoulders as he/she is solely
responsible for the entire package.