Professional Documents
Culture Documents
© Anil Sinha
Notice
Some of the diagrams and the text have
been taken from the World-wide-web, purely
for illustrative purposes. These remain the
copyright/ property of their respective owners
GENERAL
1
EMS Energy Management System
Process Supervision Stages
Energy • Instrumentation & Monitoring
• Automation
Management • Supervisory Control
•
System Process Rationalisation/
Optimisation
• Enterprise-wide Integration
2
EMS: Some Examples SCADA System Schematic
Load Management/ Energy Management
3
Energy Management Functions Power System Management
Load-Frequency Control
Power Factor Energy Storage
• Match Generation to Load & Load to Generation FACTS
correction Management
Availability based Tariff • Influence the • Regulate • Store power
transmission reactive power during lean
• Schedule Generation vs Demand
parameters to bring PF period, to use
Unscheduled Interchange such as closer to unity at peak
impedance,
• Meet demand under abnormal conditions voltage, and
phase
Load Shedding • Static VAR
• Meet shortage of power availability compensation,
etc.
Synchronisation
4
Other Important Functions
Multi-Tariff billing/ Time-of-Day Metering
Maintenance Management
• Improve the availability of assets
Asset Management
• Organising resources & Cost control POWER FLOW CALCULATION
Operator Training/ simulation
5
Power/ Load Flow Calculation Newton-Raphson Method
To start, one identifies the known and A popular method to solve the power balance
unknown variables equations is the Newton-Raphson method
Load/ Generator/ Slack busses are • Reduce the Grid to Nodes and Branches
identified • Assume initial values for each unknown at
each node
Power balance equations are written for • Solve the power balance equation using the
active and reactive power for each bus known values and get a new estimate for the
unknown
Newton-Raphson/ Gauss-Seidel • Repeat the solution with the new estimates
methods may be used to solve • Iterate till difference is acceptably small
6
ABT/ UI ABT Functions
Strategy to match Load to Generation in large
Grids
• Daily Schedules and
Balancing is deliberate and pre-decided, and in
steps of equal intervals (e.g., 15 minutes) ‘Availability tracking
• ABT Schedule Updation
Based
Short-term balancing is left to the very large Grid • Real Time Display
capacity Tariff’ • Alarms/ Events
Software • ABT Reports
It requires all participants to cooperate and
operate as per agreed plan System • Trends and short-term
estimation
The unforeseen is handled through the UI
The over-drawers are penalised This may be the only strategy available, in case of a
sudden major Grid disturbance
7
Load Shedding: The types Load Shedding: Keywords
Fast Load Shedding on Loss of Power Fast
Resources Exact
Load Shedding on Frequency Drop Flexible
Co-ordinated
Slow Load Shedding on Overload Deterministic
Security and Reliability
Slow Load Shedding for Peak Shaving
Accurate Event Logging
Synchronisation FACTS
Automatic Synchronisation after restart
FACTS is defined by the IEEE as
Automatic Synchronisation initiated by "a power electronic based system
operator and other static equipment that
provide control of one or more AC
Semi Automatic Synchronisation transmission system parameters to
enhance controllability and
Manual Synchronisation increase power transfer capability."
8
FACTS PF Correction
Shunt Capacitive Compensation The reactive power does not provide useful energy, but
causes copper losses
• To improve Power Factor
The consumer expects to receive only active power, for
maximum efficiency of his equipment
Shunt Inductive Compensation
• Normally used when charging the Transmission Hence, it is preferred to supply power at unity PF
Line
Capacitor banks are switched in or out, to shift the PF to
Series Compensation unity
To Shift the peak demand Start with the known value of every parameter
To save excess power for lean periods Iterate to estimate values not available in the data set
They differ in Storage capacity, charge-efficient operation, The method may be used to estimate system unknowns
and commercial viability which could not be measured
9
Power System Modeling/ Short-
circuit Analysis Contingency Planning
Use the Power Flow calculation to assess The basis is the Power System Model
multiple alternate scenario to:
• Study the effect of a system disturbance, so Various contingencies are created in the model
as to suggest a solution and result is observed
• Study the effect of possible network faults on • Circuit Fault/ Short circuit
the remaining grid, to arrive at an acceptable • Equipment down or mal-operation
fault-proof design • Unforeseen Over-/ Under-loads
• Recommend design of a high reliability • Protection malfunction
network • Line overload
• Train the network operator in Grid Operations • Combination events
• …..
10
Transmission Optimisation Minimum Loss
Assign the minimum & maximum generation value to
Given the availability of multiple power each plant
sources (including stored energy), with
varying cost structures, and the availability The Load at every node is as given (actual load), even
of alternate paths in the network, it is if ‘nill’
imperative to select an optimum set of
power sources and the optimum set of Power Flow calculation is applied to calculate the total
transmission paths, so as to: set of line losses
• Reduce the overall loss in transmission to a minimum Generation at each plant is adjusted as per given
• Achieve the lowest possible cost of power for a given criteria (within max & min, perhaps MoU) till a set with
load configuration the least possible loss is identified
The cost of each incremental unit Predicting the requirement of power over a time
period is a necessity
generated is available from the curve
The calculation is to optimise on the cost A Load Forecasting function does this function
of the transmission losses, rather than
on the loss itself
© Anil Sinha © Anil Sinha
11
Load Forecasting Load Forecasting
The function extrapolates from the actual Available algorithm may utilise for extrapolation data
consumption already recorded, as modified of
by some additional parameters • Past 3-7 days
• Past 1-2 months
The accuracy of this function is reasonably • Past few years
good over a short period of the next few
hours Some Supplementary data may come from:
• Weather Reports
With longer forecast periods, the reliability • Special Events, e.g., Public Holidays, etc.
does come down, but may still provide useful
data, depending on the algorithm in use Sophistication level of the algorithm varies
12
Energy Audit
The sum total of energy received over all the feeders at Commercial losses = Power flowing in –
one substation has to be ‘zero’
Power flowing out – Technical losses
On each line, power flowing in at one end has to be The remaining part is to find the physical
equal to the power flowing out the other end and the
line losses location of the commercial loss/ theft
© Anil Sinha © Anil Sinha
13
Multi-Tariff Billing/ ToD Metering Maintenance Management
Consumer Billing is an important revenue generation
activity There are multiple maintenance strategies
• Time since commissioning
Multi-tariff Billing/ Time-of-Day Metering is a tool to • Total operating time
manage demand
• Number of operations
• Preventive
The day is divided into high-demand & low-demand • Predictive
periods, with differing cost of power consumed • Condition-based
• ….
Along with consumption value, the time of
consumption is also required for calculating the bill Each equipment may use a different strategy
The function comes out with directives/ The Unit may be Online or Offline type
recommendations leading to maintenance activity
The Fault Locator injects a high frequency signal
The function may need to interface with: at one end-substation along the line (or cable)
• Part of the signal is reflected from the fault site
• Scheduling function; to allow the equipment to be safely
removed from operation, with possible replacement • The time-to-return, signal attenuation and a change in
phase angle are analysed, to predict the distance to fault
• Asset Management; to assign resources
and its nature
14
Fault Location, Isolation, Service
Restoration Asset Management
The information is used to isolate the faulty line This is a function keeping track of all possible
and/ or to bypass the faulty zone, else to resources of importance to the organisation
activate an alternate feeder, if available
• Spare parts & Consumables
The same information is also used to place the • Tools & Tackle
physical location of the fault and to device a • Instruments, probes
strategy to eliminate or overcome the fault • Temporary structures/ components
• Communication & IT equipment, Transport
If available, a Geographic Information System • Trained/ Expert Manpower
may aid in accurately identifying the fault
location and the assets needed • ….
• Assets available
A new person needs to be given the right theoretical
• Location and practical inputs
• Time-lines • The first comes though classroom training
• Limitations/ alternates • The later requires Hands-on experience
• Required calibrations/ retooling Since it would be too dangerous for the fresher to be
allowed to operate the real online power system,
• …. Simulation is a viable and practical alternate
15
Operator Training/ Simulation Related Systems
Customer Relations Management (CRM) system
The trainee is given a workstation which is visibly Staff Deployment System
the same as the operator’s console
Work Order Management System
• However, the allowed functionality is limited
• The full set of monitoring functions work Material Management System (MMS)
• The command function is disabled
Engineering & planning systems
To give a feel of the real system, a built-in simulation
function interacts with the trainee, to play out Communications Network Management Systems
different scenarios and to test his reaction
Automated Meter Reading System
• The simulation is controlled by a trainer
Data warehouse/ Data Mining
Thank you
16