Professional Documents
Culture Documents
Computation :
6" D PINLIGHT WITH 18W 220 V CFL set 30.00 280.00 8,400.00
NONE
SUB-TOTAL (C) -
Computation :
Electrical Wire, THHN, 5.5mm², Stranded Wire metre 80.00 37.00 2,960.00
Electrical Wire, THHN, 3.5mm², Stranded Wire metre 280.00 24.00 6,720.00
Two(2) Gang Thumbler Switch, Flush Type pc 6.00 120.00 720.00
Rubberized Electrical Tape roll 10.00 30.00 300.00
NONE
SUB-TOTAL (C) -
Computation :
= 87 / 3
= 29 pcs
NONE
SUB-TOTAL (C) -
NONE
SUB-TOTAL (C) -
Computation : 1,764.81
NONE
SUB-TOTAL (C) -
Computation : 23.98
= 9.87 cu.m.
= 37.23 cu.m.
Concreting :
One Bagger Mix = 0.4763 x 12 personnel
U/H : 0.4763 m³/hr = 5.716 m³/hr
Number of Hours = 37.23 / 5.716 = 6.51 hr.
Placing of Concrete = 0.415 x 12 personnel
U/H : 0.415 m³/hr = 4.980 m³/hr
Number of Hours = 37.23 / 4.980 = 7.48 hr.
Computation :
Column (C1) = 0.45 x 0.30 x 5.70
= 0.77 x 12 columns
= 9.24 cu.m.
No. Of Bags (Cement) = 9.24 x 9.00 = 84 bag
No. Of Volume (Sand) = 9.24 x 0.50 = 5 cu.m.
No. Of Volume(Gravel) = 9.24 x 1.00 = 9 cu.m.
Concreting :
One Bagger Mix = 0.4763 x 12 personnel
U/H : 0.4763 m³/hr = 5.716 m³/hr
Number of Hours = 9.24 / 5.716 = 1.62 hr.
Placing of Concrete = 0.415 x 12 personnel
U/H : 0.415 m³/hr = 4.98 m³/hr
Number of Hours = 9.24 / 4.98 = 1.86 hr.
Computation : 23.98
RB1 (Roof Beams) = 109.64 x 0.20 x 0.30
Concreting = 6.58 cu.m.
Concreting :
One Bagger Mix = 0.4763 x 12 personnel
U/H : 0.4763 m³/hr = 5.716 m³/hr
Number of Hours = 6.58 / 5.716 = 1.15 hr.
Placing of Concrete = 0.415 x 12 personnel
U/H : 0.415 m³/hr = 4.980 m³/hr
Number of Hours = 6.58 / 4.980 = 1.32 hr.
Computation : 33.56
= 1.97 cu.m.
= 6.62 cu.m.
B.5 Project Billboard / Signboard 2.00 each 4,826.00 15% 10% 25% P 1,206.50
B.7 Occupational Safety and Health Program 1.00 month 5,560.00 0% 10% 10% P 556.00
B.9 Mobilization / Demobilization 1.00 L.S. 3,776.00 0% 0% 0% -
801 (1) Removal of Structures and Obstruction 1.00 L.S. 5,940.12 15% 10% 25% P 1,485.03
802(2) Surplus Common Excavation 53.08 m3 22,530.34 15% 10% 25% P 5,632.59
804(1)a Embankment (from structure excavation) 38.05 m3 2,928.49 15% 10% 25% P 732.12
804(4) Gravel Fill 6.62 m3 8,047.24 15% 10% 25% P 2,011.81
900 (1).c2 Structural Concrete (Footings and Slab on Fill) 37.23 m3 154,362.56 15% 10% 25% P 38,590.64
900(1)c4 Structural Concrete for Column (Class A, 28 days) 9.24 m3 38,299.52 15% 10% 25% P 9,574.88
900(1)c6 Structural Concrete for Beams (Class A, 28 days) 6.58 m3 28,442.30 15% 10% 25% P 7,110.58
Reinforcing Steel of Reinforced Concrete Structures,
902(1).a 2,861.62 kg 170,549.48 15% 10% 25% P 42,637.37
Grade 40
903(1) Forms and Falseworks 1.00 L.S. 33,132.97 15% 10% 25% P 8,283.24
1003(1).a1 Ceiling with Metal Frame 62.12 m2 42,580.46 15% 10% 25% P 10,645.12
1008 (1).a Aluminum Glass Windows (Sliding Type) 25.84 m2 59,709.86 15% 10% 25% P 14,927.47
1010 (2).b Doors (Wooden Panel) 15.12 m2 74,404.62 15% 10% 25% P 18,601.16
1018(1) Glazed Tiles and Trims 6.60 m2 8,014.67 15% 10% 25% P 2,003.67
1027(1) Cement Plaster Finish 480.26 m2 50,270.84 15% 10% 25% P 12,567.71
1032(1).a Painting Works (Masonry/Concrete) 480.26 m2 49,008.04 15% 10% 25% P 12,252.01
1032(1).b Painting Works (Wood) 30.24 m2 7,255.51 15% 10% 25% P 1,813.88
1046(2).a1 CHB Non Load Bearing (Including Reinforcing Steel) 240.13 m2 156,468.20 15% 10% 25% P 39,117.05
1047(2)a Structural Steel, Trusses 1,702.20 kg 116,370.97 15% 10% 25% P 29,092.74
1047(2)b Structural Steel, Purlins 226.26 kg 21,795.34 15% 10% 25% P 5,448.84
1047(7)b Metal Structure Accessories, Sagrods 22.32 kg 2,206.44 15% 10% 25% P 551.61
1047(3)c Metal Structure Accessories, Turnbuckle 12.00 each 2,320.26 15% 10% 25% P 580.07
Republic of the Philippines
Department of Public Works and Highways
Cebu 2nd District Engineering Office
Lawaan I, Talisay City, Cebu
Contract ID :
Contract Name : Rehab/Completion of Multipurpose Building
Location of the Contract : Barangay Bae, Sibonga, Cebu
1047(4) Metal Structure Accessories, Cross Bracing 43.20 kg 3,654.40 15% 10% 25% P 913.60
1100 (10) Conduits, Boxes & Fittings 1.00 L.S. 39,615.92 15% 10% 25% P 9,903.98
1101 (33) Wires and Wiring Devices 1.00 L.S. 13,628.00 15% 10% 25% P 3,407.00
1103 (1) Lighting Fixtures and Lamps 1.00 L.S. 10,230.00 15% 10% 25% P 2,557.71
PREPARED BY: A P P R O V E D:
MENCHU B. MONTEMAYOR
OIC, Construction Section
Republic of the Philippines
tment of Public Works and Highways
Cebu 2nd District Engineering Office
Lawaan I, Talisay City, Cebu
Unit Cost
Total Indirect Cost
VAT (5+9) 5% Total Cost (5+11) (Adjusted)
(9+10)
( 12/ 3 )
.(10) .(11) .(12) .(13)
Unit Cost
Total Indirect Cost
VAT (5+9) 5% Total Cost (5+11) (Adjusted)
(9+10)
( 12/ 3 )
.(10) .(11) .(12) .(13)
Unit Cost
Total Indirect Cost
VAT (5+9) 5% Total Cost (5+11) (Adjusted)
(9+10)
( 12/ 3 )
.(10) .(11) .(12) .(13)
TOTAL:
RECOMMENDING APPROVAL: A P P R O V E D:
March 6, 2018
Upon approval
30
WORK/BUDGET COST
EQUIPMENT
REQUIRED
( PLEASE SEE DETAILED ESTIMATES)
P 1,190,562.63
P 1,190,562.63
P 370,183.74
P 1,560,746.37
UNIT RATE
ITEM NO. DESCRIPTION QUANTITY UNIT AMOUNT
MATERIALS
Fiber Cement Board 4' x 8' x 4.5mm 21.00 sheet P 540.00 P 11,340.00
1" x 3" Flat Bar for Canopy Support 2.00 pc P 2,278.10 P 4,556.20
Pre-Painted Metal Roofing, Gauge 26 Long Span 78.00 sq.m. P 450.00 P 35,100.00
(D-1) Tanguile Paneled Door on 50 x 150mm Thk 9.00 set P 7,728.00 P 69,552.00
Mahogany jamb complete with hardware and
accessories cylinder type lockset
PREPARED BY:
LEONARD B. ABAO
Licensed Civil Engineer
Republic of the Philippines
Department of Public Works and Highways
Cebu 2nd District Engineering Office
Lawaan I, Talisay City, Cebu
B.7 Occupational Safety and Health Program 0.47% 1.00 month P 5,560.00
801 (1) Removal of Structures and Obstruction 0.50% 1.00 L.S. P 5,940.12
PART C EXCAVATION
PART D EMBANKMENT
900 (1).c2 Structural Concrete (Footings and Slab on Fill) 12.97% 37.23 m3 P 154,362.56
Structural Concrete for Column (Class A, 28
900(1)c4 3.22% 9.24 m3 P 38,299.52
days)
900(1)c6 Structural Concrete for Beams (Class A, 28 days) 2.39% 6.58 m3 P 28,442.30
T OF PROPOSED WORK
DIRECT COST ADJUSTED
UNIT COST UNIT COST
P 2,413.00 P 3,167.07
P 5,560.00 P 6,421.80
P 3,776.00 P 3,964.80
P 5,940.12 P 7,796.41
P 424.46 P 557.10
P 76.96 P 101.02
P 1,215.60 P 1,595.47
P 4,146.19 P 5,441.87
P 4,144.97 P 11,968.60
P 4,322.54 P 5,673.33
P 59.60 P 78.22
P 33,132.97 P 43,487.03
P 685.45 P 899.66
P 2,310.75 P 3,032.86
P 4,920.94 P 6,458.73
blic of the Philippines
Public Works and Highways
District Engineering Office
an I, Talisay City, Cebu
T OF PROPOSED WORK
DIRECT COST ADJUSTED
UNIT COST UNIT COST
P 265.90 P 348.99
P 575.19 P 754.94
P 528.83 P 694.09
P 1,214.34 P 1,593.83
P 104.67 P 137.38
P 102.04 P 133.93
P 239.93 P 314.91
P 651.60 P 855.22
P 68.37 P 89.73
P 96.33 P 126.43
P 98.85 P 129.75
P 193.36 P 253.78
P 84.59 P 111.03
P 39,615.92 P 51,995.90
P 13,628.00 P 17,886.75
P 10,230.00 P 13,426.88
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1003(1).a1 Ceiling with Metal Frame
COST SHEET I.D. : 1003(1).a1 PRODUCTION RATE: 0.62 sq.m./hr.
QUANTITY : 62.12 sq.m. NUMBER OF HOURS: 100.84 hr.
Computation : 259.49
Horizontal Ceiling = 12.30 x 5.05
(Including Eaves Area) = 62.12 / 2.9768
= 20.87 say 21 sheets - (4.5 mm thk Fiber Cement Board)
NONE
SUB-TOTAL (C) -
= 657.85 / 6
= 110 lengths of 16mmØ x 6.00 m Deformed Bars
= 732.00 x 0.30 / 53
# 16 Tie Wire G.I. = 5.00 kgs of G.I. Tie Wire
Computation : 114.01
Column Footing (F1) = 1.20 x 1.20 x 1.70
= 2.450 x 12 footings
= 29.40 cu.m.
NONE
SUB-TOTAL (A) -
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
NONE
SUB-TOTAL (C) -
Computation : 70.15
NONE
SUB-TOTAL (A) -
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
Unskilled 4 12.10 53.060 2,568.10
Computation : 128.275
Computation : 46.71
Installation = 0.2363 x 1 personnel
U/H : 0.2363 m²/hr = 0.2363 sq.m./hr.
Number of Hours = 15.12 / 0.2363
= 63.99 hr
NONE
SUB-TOTAL (C) -
NONE
SUB-TOTAL (C) -
NONE
SUB-TOTAL (C) -
Computation : 1,977.07
NONE
SUB-TOTAL (C) -
NONE
SUB-TOTAL (C) -
Computation : 6,075.72
Polycarbonate Sheet : 1 set
= 1.00 x 20
= 20.00 x 1 set
= 20.00 / 2.88
= 6.94 say 7 sheets
Computation : 46.71
Columns : 1.50 x 3 x 12
Paraphet 2.00 x 1.90 x 1
SUB-TOTAL (A)
QUANTITY
(B) LABOR COST Hourly Rate
No. Of Personnel Total Hours
SUB-TOTAL (B)
QUANTITY
(C) EQUIPMENT COST Hourly Rate
No. Of Equipment Total Hours
NONE
SUB-TOTAL (C)
UNIT COST
LED UNIT PRICE ANALYSIS
sq.m./hr.
hr.
pc/pcs
pc/pcs
TOTAL COST
11,205.00
11,205.00
TOTAL COST
2,336.88
2,336.88
TOTAL COST
13,541.88
2,031.28
1,354.19
846.37
4,231.84
17,773.72
2,141.41
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1047(2)a Structural Steel, Trusses
COST SHEET I.D. : 1047(2)a PRODUCTION RATE: 58.64
QUANTITY : 1,702.20 kg NUMBER OF HOURS: 29.03
Computation : 6,075.72
HT-1 : 6 set
SUB-TOTAL (A)
QUANTITY
(B) LABOR COST Hourly Rate
No. Of Personnel Total Hours
SUB-TOTAL (B)
QUANTITY
(C) EQUIPMENT COST Hourly Rate
No. Of Equipment Total Hours
SUB-TOTAL (C)
UNIT COST
ED UNIT PRICE ANALYSIS
kgs./hr.
hr.
wastages
TOTAL COST
71,073.00
16,205.28
2,938.32
2,280.00
7,054.83
240.00
135.00
99,926.43
TOTAL COST
4,002.66
3,080.66
7,083.32
TOTAL COST
9,361.22
9,361.22
116,370.97
17,455.65
11,637.10
7,273.19
36,365.94
152,736.91
89.73
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1047(2)b Structural Steel, Purlins
COST SHEET I.D. : 1047(2)b PRODUCTION RATE: 17.09 kgs./hr.
QUANTITY : 226.26 kg NUMBER OF HOURS: 13.24 hr.
Computation : 3,366.18 ### 4,071.69
Roof Purlins (HT-1)
1" x 1" x 1/4" = 0.075 x 54
Clip Angle = 4.05 / 6
= 0.68 say 1 lengths
NONE
SUB-TOTAL (C) -
SUB-TOTAL (B) -
QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours
NONE
SUB-TOTAL (C) -
NONE
SUB-TOTAL (A) -
QUANTITY
(B) LABOR COST Daily Rate TOTAL COST
No. Of Personnel Total Day
NONE
SUB-TOTAL (B) -
QUANTITY
(C) EQUIPMENT COST Daily Rate TOTAL COST
No. Of Equipment Total Day
Computation : 26.32
SUB-TOTAL (A) -
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
SUB-TOTAL (A)
QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours
SUB-TOTAL (B)
QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours
NONE
SUB-TOTAL (C)
Computation : 6,075.72
Landing : 3 set
3" x 3" x 1/4" = 4.00 x 1 no. of angle bar
Angle Bar = 4.00 x 3 set
= 12.00 / 6
= 2.00 say 2 lengths
=
Welding Rod = 423.92 / 1,000 x 30
= 12.72 say 13 kgs
Red Lead = 19.22 / 25 + 5%
= 1 gals
Fab/Erect/Install of Angle = 17.00 x 4 personnel
U/H : 17 kg/hr = 68.00 kg./hr.
Number of Hours = 423.92 / 68.00
= 6.23 hr
Painting of Angle = 4.25 x 4 personnel
U/H : 4.25 pcs./hr = 17.00 pcs./hr
Number of Hours = 15.00 / 17.000
= 0.88 hr
SUB-TOTAL (A)
QUANTITY
(B) LABOR COST Hourly Rate
No. Of Personnel Total Hours
SUB-TOTAL (B)
QUANTITY
(C) EQUIPMENT COST Hourly Rate
No. Of Equipment Total Hours
SUB-TOTAL (C)
UNIT COST
ED UNIT PRICE ANALYSIS
wastages
TOTAL COST
6,287.92
14,087.40
2,092.44
6,781.65
6,009.00
570.00
1,798.29
400.00
225.00
TOTAL COST
980.33
754.51
TOTAL COST
2,330.02
(0.18)
-
(0.01)
(0.19)
(0.19)
DETAILED UNIT PRICE ANALYSIS
Computation :
SUB-TOTAL (A)
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
SUB-TOTAL (B)
QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate
SUB-TOTAL (C)
UNIT COST
DETAILED UNIT PRICE ANALYSIS
Computation : 12.00
Concreting :
Manual Mix = 0.0513 x 3 personnel
U/H : 0.0513 m³/hr = 0.154 m³/hr
Number of Hours = 0.05 / 0.154 = 0.32 hr.
Placing of Concrete = 0.415 x 3 personnel
U/H : 0.415 m³/hr = 1.245 m³/hr
Number of Hours = 0.05 / 1.245 = 0.04 hr.
DETAILED UNIT PRICE ANALYSIS
NONE
SUB-TOTAL (C) -
Downspout : 6 DS
PVC Pipes, 3"Ø length 18.00 440.00 7,920.00
PVC Elbow, 3"Ø x 90° pcs 6.00 52.00 312.00
PVC Elbow, 3"Ø x 45° pcs 12.00 40.00 480.00
Solvent Cement pcs 7.00 200.00 1,400.00
Storm Drainage
RCPC, 6"Ø or equivalent pcs 10.00 400.00 4,000.00
Cement, Portland bags 4.00 234.33 937.32
Sand, Washed cu.m. 0.70 1,100.00 770.00
NONE
SUB-TOTAL (C) -
UNIT COST -
DETAILED UNIT PRICE ANALYSIS
Computation :
Concreting :
Manual Mix = 0.0513 x 5 personnel
U/H : 0.0513 m³/hr = 0.257 m³/hr
Number of Hours = 4.52 / 0.257 = 17.62 hr.
Placing of Concrete = 0.415 x 5 personnel
U/H : 0.415 m³/hr = 2.075 m³/hr
Number of Hours = 4.52 / 2.075 = 2.18 hr.
NONE
SUB-TOTAL (C) -
Computation :
NONE
SUB-TOTAL (C) -
UNIT COST -
DETAILED UNIT PRICE ANALYSIS
Computation :
Installation = 1.000 x 2 personnel
U/H : 1.00 set/hr = 2.00 set/hr. fittings
Number of Hours = 14.00 / 2.00
= 7.00 hr
NONE
SUB-TOTAL (C) -
UNIT COST -
DETAILED UNIT PRICE ANALYSIS
Computation :
Installation of 3/4"Ø = 1.8975 x 2 personnel
U/H : 1.8975 ln.m./hr = 3.80 ln.m./hr.
Number of Hours = 32.00 / 3.80
= 8.43 hr
NONE
SUB-TOTAL (C) -
UNIT COST -
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1003(1).a1 Carpentry for Ceiling with Insulation
COST SHEET I.D. : 1003(1).a1 PRODUCTION RATE: #DIV/0! sq.m./hr.
QUANTITY : 0.00 sq.m. NUMBER OF HOURS: 0.00 hr.
Computation : 259.49
Computation : 46.71
Installation = 0.2363 x 2 personnel
U/H : 0.2363 m²/hr = 0.4726 sq.m./hr.
Number of Hours = 1.00 / 0.4726
= 2.12 hr
NONE
SUB-TOTAL (C) -
SUB-TOTAL (A) -
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
SUB-TOTAL (B) -
QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate
NONE
SUB-TOTAL (C) -
UNIT COST -
DETAILED UNIT PRICE ANALYSIS
SUB-TOTAL (A) -
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
SUB-TOTAL (B) -
QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate
NONE
SUB-TOTAL (C) -
UNIT COST -
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1036(1).a Polycarbonate Sheet (Roof w/ framing)
COST SHEET I.D. : 1036(1).a PRODUCTION RATE: 3.00 kgs./hr.
QUANTITY : 12.00 sheets NUMBER OF HOURS: 4.00 hr.
Computation : 6,075.72
Polycarbonate Sheet : 1 set
= 6.30 x 5.4 no. of angle bar
= 34.02 x 1 set
= 34.02 / 2.88
= 11.81 say 12 sheets
Computation : 46.71
SUB-TOTAL (A)
QUANTITY
(B) LABOR COST Hourly Rate
No. Of Personnel Total Hours
SUB-TOTAL (B)
QUANTITY
(C) EQUIPMENT COST Hourly Rate
No. Of Equipment Total Hours
NONE
SUB-TOTAL (C)
UNIT COST
LED UNIT PRICE ANALYSIS
sq.m./hr.
hr.
pc/pcs
pc/pcs
pc/pcs
pc/pcs
pc/pcs
pc/pcs
pc/pcs
pc/pcs
pc/pcs
TOTAL COST
282,900.00
282,900.00
TOTAL COST
34,638.06
34,638.06
TOTAL COST
-
317,538.06
47,630.71
31,753.81
19,846.13
99,230.64
416,768.70
3,388.36
DETAILED UNIT PRICE ANALYSIS
Computation : 46.71
SUB-TOTAL (A)
QUANTITY
(B) LABOR COST Hourly Rate
No. Of Personnel Total Hours
SUB-TOTAL (B)
QUANTITY
(C) EQUIPMENT COST Hourly Rate
No. Of Equipment Total Hours
NONE
SUB-TOTAL (C)
UNIT COST
LED UNIT PRICE ANALYSIS
sq.m./hr.
hr.
pc/pcs
pc/pcs
pc/pcs
TOTAL COST
61,830.00
61,830.00
TOTAL COST
12,898.11
12,898.11
TOTAL COST
74,728.11
11,209.22
7,472.81
4,670.51
23,352.53
98,080.64
2,141.50
DETAILED UNIT PRICE ANALYSIS
NAME : #REF!
LOCATION : #REF!
PAY ITEMS : 1046(1).2 CHB Non Load Bearing (Including Reinforcing Steel) Front Side Area
COST SHEET I.D. : 1046(1).2 PRODUCTION RATE: 2.13 sq.m./hr.
QUANTITY : 51.29 sq.m. NUMBER OF HOURS: 24.13 hr.
Computation : 383.37 138.69 522.06
= 22.30 x 2.30
CHB Wall at Front Side
= 51.29 sq.m.
Total No. Of CHB 4" = 51.29 x 12.50 + 1% for breakages
= 648 pcs
Cement (Mortar) = 51.29 x 0.394
Class C = 20.21 say 21 bag
Sand (Mortar) = 51.29 x 0.0435
Class C = 2.20 say 2 cu.m.
= 27.90 x 2.00
CHB Wall at Rear Side
= 55.80 sq.m.
Total No. Of CHB 4" = 55.80 x 12.50 + 1% for breakages
= 705 pcs
Cement (Mortar) = 55.80 x 0.394
Class C = 21.99 say 22 bag
Sand (Mortar) = 55.80 x 0.0435
Class C = 2.40 say 2 cu.m.
= 24.00 x 2.30
CHB Wall at Rear Side
= 55.20 sq.m.
1,560,746.37
500000
500000.000
98.34
-
0
DETAILED UNIT PRICE ANALYSIS
Computation : 365.56
NAME : #REF!
LOCATION : #REF!
PAY ITEMS : 1051(1) Metal Railings
COST SHEET I.D. : 1051(1)
QUANTITY : 289.70 meter NUMBER OF HOURS: 45.76 hr.
Computation :
= 0.00 x 1 no. of ramp
32mmØ G.I.Pipe
1" x 3" x 6M Rectangular
Tubing = 104.00 / 6.00
Stair Raillings (Horizontal) = 17.33 say 18 lengths
Computation : 128.275
NONE
SUB-TOTAL (C) -