You are on page 1of 118

DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1103 (1) Lighting Fixtures and Lamps
COST SHEET I.D. : 1103 (1)
QUANTITY : 1.00 L.S. NUMBER OF HOURS: 7.50 hr.

Computation :

Installation of Fixtures = 1.00 x 4 personnel


U/H : 1 set/hr = 4.00 set/hr.
Number of Hours = 30.00 / 4.00
= 7.50 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

1 x 20 W BOX TYPE FLF set 0.00 420.00 -

6" D PINLIGHT WITH 18W 220 V CFL set 30.00 280.00 8,400.00

SUB-TOTAL (A) 8,400.00


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 2 7.50 68.940 1,034.10


Unskilled 2 7.50 53.060 795.90

SUB-TOTAL (B) 1,830.00


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 10,230.00

(E) ADD INDIRECT COST


1. OCM 15% 1,534.50
2. Contractor's Profit 10% 1,023.00
3. VAT 5% 639.38
TOTAL INDIRECT COST 3,196.88

TOTAL COST (D+E) 13,426.88

UNIT COST 13,426.88


DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1101 (33) Wires and Wiring Devices
COST SHEET I.D. : 1101 (33)
QUANTITY : 1.00 L.S. NUMBER OF HOURS: 12.00 hr.

Computation :

Installation of Wiring = 18.75 x 2 personnel


U/H : 18.75 ln.m./hr = 37.50 ln.m./hr.
Number of Hours = 360.00 / 37.50
= 9.60 hr
Installation of Devices = 1.25 x 2 personnel
U/H : 1.25 pc/hr = 2.50 pc/hr.
Number of Hours = 6.00 / 2.50
= 2.40 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Electrical Wire, THHN, 5.5mm², Stranded Wire metre 80.00 37.00 2,960.00
Electrical Wire, THHN, 3.5mm², Stranded Wire metre 280.00 24.00 6,720.00
Two(2) Gang Thumbler Switch, Flush Type pc 6.00 120.00 720.00
Rubberized Electrical Tape roll 10.00 30.00 300.00

SUB-TOTAL (A) 10,700.00


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 2 12.00 68.940 1,654.56


Unskilled 2 12.00 53.060 1,273.44

SUB-TOTAL (B) 2,928.00


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 13,628.00

(E) ADD INDIRECT COST


1. OCM 15% 2,044.20
2. Contractor's Profit 10% 1,362.80
3. VAT 5% 851.75
TOTAL INDIRECT COST 4,258.75

TOTAL COST (D+E) 17,886.75

UNIT COST 17,886.75


DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1100 (10) Conduits, Boxes & Fittings
COST SHEET I.D. : 1100 (10)
QUANTITY : 1.00 L.S. NUMBER OF HOURS: 35.68 hr.

Computation :
= 87 / 3
= 29 pcs

Installation Conduits = 4.50 x 2 personnel


U/H : 4.50 ln.m./hr = 9.00 ln.m./hr.
Number of Hours = 190.00 / 9.00
= 21.11 hr
Installation Boxes&Fit = 3.50 x 2 personnel
U/H : 3.50 pc/hr = 7.00 pc/hr.
Number of Hours = 102.00 / 7.00
= 14.57 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

PVC, Conduit Pipe, (3m x 19mmØ) pc 190.00 92.00 17,480.00


Junction Box, 4" x 4", PVC with cover pc 51.00 31.00 1,581.00
Utility Box, 2" x 4", PVC pc 51.00 30.00 1,530.00
Automatic Circuit Breaker, 15A, 2P set 5.00 313.00 1,565.00
Automatic Circuit Breaker, 20A, 2P set 5.00 313.00 1,565.00
Automatic Circuit Breaker, 50A, 2P set 2.00 442.00 884.00
Automatic Circuit Breaker, 70A, 2P set 5.00 650.00 3,250.00
Panel Box, Flush Type, 4 Branches set 1.00 1,205.00 1,205.00
Panel Box, Flush Type, 10 Branches set 1.00 1,850.00 1,850.00

SUB-TOTAL (A) 30,910.00


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 2 35.68 68.940 4,919.56


Unskilled 2 35.68 53.060 3,786.36

SUB-TOTAL (B) 8,705.92


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 39,615.92

(E) ADD INDIRECT COST


1. OCM 15% 5,942.39
2. Contractor's Profit 10% 3,961.59
3. VAT 5% 2,476.00
TOTAL INDIRECT COST 12,379.98

TOTAL COST (D+E) 51,995.90

UNIT COST 51,995.90


DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1018(1) Glazed Tiles and Trims
COST SHEET I.D. : 1018(1) PRODUCTION RATE: 0.59 sq.m./hr.
QUANTITY : 6.60 sq.m. NUMBER OF HOURS: 11.28 hr.
Computation : 71.55

Floor Area = 1.100 x 1.50 X 4


= 6.60 sq.m.

Cement = 6.60 x 0.086 = 1


Sand = 6.60 x 0.01 = 0.10
Grout, Tile = 6.60 x 0.25 = 2
Installation = 0.1950 x 3 personnel
U/H : 0.1950 m²/hr = 0.59 sq.m./hr.
Number of Hours = 6.60 / 0.59
= 11.28 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Ceramic Glazed Tiles sq.m. 6.60 850.00 5,610.00


Cement, Portland bags 1.00 240.00 240.00
Sand, Washed cu.m. 0.10 1,100.00 110.00
Tile Grout kg 2.00 40.00 80.00

SUB-TOTAL (A) 6,040.00


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 1 11.28 68.940 777.64


Unskilled 2 11.28 53.060 1,197.03

SUB-TOTAL (B) 1,974.67


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 8,014.67


(E) ADD INDIRECT COST
1. OCM 15% 1,202.20
2. Contractor's Profit 10% 801.47
3. VAT 5% 500.92
TOTAL INDIRECT COST 2,504.59

TOTAL COST (D+E) 10,519.26

UNIT COST 1,593.83


DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1046(2).a1 CHB Non Load Bearing (Including Reinforcing Steel)
COST SHEET I.D. : 1046(2).a1 PRODUCTION RATE: 2.13 sq.m./hr.
QUANTITY : 240.13 sq.m. NUMBER OF HOURS: 112.99 hr.
Computation : 383.37 138.69 522.06

Wall Area 1 (Lower) = 54.82 x 3.80


= 208.32 sq.m.

Wall Area 2(Upper) = 38.30 x 1.90


= 72.77 sq.m.

= 40.96 sq.m. (Area of Door &Window to be subtracted to total area)

Total No. Of CHB 4" = 240.13 x 12.50 + 1% for breakages


= 3,032 pcs
Cement (Mortar) = 240.13 x 0.763
Class C = 183.22 say 184 bag
Sand (Mortar) = 240.13 x 0.0844
Class C = 20.30 say 20 cu.m.

Reinforcing Steel : 600mm x 600mm Spacing of Reinforcing Steel


(for Horizontal Bars) = 240.13 x 2.13 = 511.48
(forVertical Bars) = 240.13 x 2.15 = 516.28
1,027.76 meters
= 1,027.76 / 6
= 171.29 say 171 lengths of 10mmØ x 6.00 m Deformed Bars
kgs of G.I. Tie Wire = 240.13 x 0.032
= 8.00 kgs
CHB Laying = 0.5313 x 4 personnel
U/H : 0.5313 m²/hr = 2.13 sq.m./hr.
Number of Hours = 240.13 / 2.13
= 112.99 hr
(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST
CHB 6" pcs 3,032.00 12.00 36,384.00
Cement, Portland bags 184.00 240.00 44,160.00
Sand, Washed cu.m. 20.00 1,100.00 22,000.00
10mmØ x 6.00 m Deformed Bars kgs 633.04 41.00 25,954.64
# 16 Tie Wire G.I. kgs 8.00 50.00 400.00
SUB-TOTAL (A) 128,898.64
QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours
Skilled 2 112.99 68.940 15,579.06
Unskilled 2 112.99 53.060 11,990.50
SUB-TOTAL (B) 27,569.56
QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours
NONE
SUB-TOTAL (C) -
(D) TOTAL DIRECT COST : (A+B+C) 156,468.20
(E) ADD INDIRECT COST
1. OCM 15% 23,470.23
2. Contractor's Profit 10% 15,646.82
3. VAT 5% 9,779.26
TOTAL INDIRECT COST 48,896.31
TOTAL COST (D+E) 205,364.51
UNIT COST 855.22
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1027(1) Cement Plaster Finish
COST SHEET I.D. : 1027(1) PRODUCTION RATE: 4.75 sq.m./hr.
QUANTITY : 480.26 sq.m. NUMBER OF HOURS: 101.11 hr.

Computation : 1,764.81

Area of CHB Walls = 480.26 sq.m.


Cement (Plaster) = 480.26 x 0.144
Class C = 69.16 say 70 bag

Sand (Plaster) = 480.26 x 0.016


Class C = 8.00 cu.m.

Wall Plastering = 1.1875 x 4 personnel


U/H : 1.1875 m²/hr = 4.75 sq.m./hr.
Number of Hours = 480.26 / 4.75
= 101.11 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Cement, Portland bags 70.00 240.00 16,800.00


Sand, Washed cu.m. 8.00 1,100.00 8,800.00

SUB-TOTAL (A) 25,600.00


QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours

Skilled 2 101.11 68.940 13,941.05


Unskilled 2 101.11 53.060 10,729.79

SUB-TOTAL (B) 24,670.84


QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 50,270.84

(E) ADD INDIRECT COST


1. OCM 15% 7,540.63
2. Contractor's Profit 10% 5,027.08
3. VAT 5% 3,141.93
TOTAL INDIRECT COST 15,709.64

TOTAL COST (D+E) 65,980.48

UNIT COST 137.38


DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 900 (1).c2 Structural Concrete (Footings and Slab on Fill)
COST SHEET I.D. : 900 (1).c2 PRODUCTION RATE: 2.66 cu.m./hr.
QUANTITY : 37.23 cu.m. NUMBER OF HOURS: 13.99 hr.

Computation : 23.98

Slab on Fill = 0.20 x 12.700 x 6.00 +


0.00 x 3.025 x 1.500
= 15.24 cu.m.

Column Footing (F1) = 1.20 x 1.20 x 0.70


= 1.01 x 12 footings
0 = 12.12 cu.m.
0

Wall Footing (WF1) = 0.60 x 0.25 x 65.79

= 9.87 cu.m.

Total Volume = 15.24 + 12.12 + 9.87 +

= 37.23 cu.m.

No. Of Bags (Cement) = 37.23 x 9.00 = 336 bag


No. Of Volume (Sand) = 37.23 x 0.50 = 19 cu.m.
No. Of Volume(Gravel) = 37.23 x 1.00 = 38 cu.m.

Concreting :
One Bagger Mix = 0.4763 x 12 personnel
U/H : 0.4763 m³/hr = 5.716 m³/hr
Number of Hours = 37.23 / 5.716 = 6.51 hr.
Placing of Concrete = 0.415 x 12 personnel
U/H : 0.415 m³/hr = 4.980 m³/hr
Number of Hours = 37.23 / 4.980 = 7.48 hr.

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST


Cement, Portland bags 336.00 234.33 78,734.88
Sand, Washed cu.m. 19.00 1,100.00 20,900.00
Gravel, 3/4" cu.m. 38.00 1,100.00 41,800.00
SUB-TOTAL (A) 141,434.88
QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours

Construction Foreman 1 13.99 95.000 1,329.05


Skilled 4 13.99 68.940 3,857.88
Unskilled 8 13.99 53.060 5,938.48

SUB-TOTAL (B) 11,125.41


QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours

1-Bagger Concrete Mixer 1 6.51 172.00 1,119.72


Concrete Vibrator (½" 38 - 40 min) 1 7.48 91.25 682.55
SUB-TOTAL (C) 1,802.27

(D) TOTAL DIRECT COST : (A+B+C) 154,362.56


(E) ADD INDIRECT COST
1. OCM 15% 23,154.38
2. Contractor's Profit 10% 15,436.26
3. VAT 5% 9,647.66
TOTAL INDIRECT COST 48,238.30

TOTAL COST (D+E) 202,600.86


UNIT COST 5,441.87
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 900(1)c4 Structural Concrete for Column (Class A, 28 days)
COST SHEET I.D. : 900(1)c4 PRODUCTION RATE: 2.66 cu.m./hr.
QUANTITY : 9.24 cu.m. NUMBER OF HOURS: 3.48 hr.

Computation :
Column (C1) = 0.45 x 0.30 x 5.70
= 0.77 x 12 columns
= 9.24 cu.m.
No. Of Bags (Cement) = 9.24 x 9.00 = 84 bag
No. Of Volume (Sand) = 9.24 x 0.50 = 5 cu.m.
No. Of Volume(Gravel) = 9.24 x 1.00 = 9 cu.m.
Concreting :
One Bagger Mix = 0.4763 x 12 personnel
U/H : 0.4763 m³/hr = 5.716 m³/hr
Number of Hours = 9.24 / 5.716 = 1.62 hr.
Placing of Concrete = 0.415 x 12 personnel
U/H : 0.415 m³/hr = 4.98 m³/hr
Number of Hours = 9.24 / 4.98 = 1.86 hr.

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Cement, Portland bags 84.00 234.33 19,683.72


Sand, Washed cu.m. 5.00 1,100.00 5,500.00
Gravel, 3/4" cu.m. 9.00 1,100.00 9,900.00

SUB-TOTAL (A) 35,083.72


QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours

Construction Foreman 1 3.48 95.000 330.60


Skilled 4 3.48 68.940 959.64
Unskilled 8 3.48 53.060 1,477.19

SUB-TOTAL (B) 2,767.43


QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours

1-Bagger Concrete Mixer 1 1.62 172.00 278.64


Concrete Vibrator (½" 38 - 40 min) 1 1.86 91.25 169.73

SUB-TOTAL (C) 448.37

(D) TOTAL DIRECT COST : (A+B+C) 38,299.52

(E) ADD INDIRECT COST


1. OCM 15% 5,744.93
2. Contractor's Profit 10% 3,829.95
3. VAT 5% 2,393.72
TOTAL INDIRECT COST 11,968.60
TOTAL COST (D+E) 50,268.12
UNIT COST 5,440.27
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 900(1)c6 Structural Concrete for Beams (Class A, 28 days)
COST SHEET I.D. : 900(1)c6 PRODUCTION RATE: 2.66 cu.m./hr.
QUANTITY : 6.58 cu.m. NUMBER OF HOURS: 2.47 hr.

Computation : 23.98
RB1 (Roof Beams) = 109.64 x 0.20 x 0.30
Concreting = 6.58 cu.m.

No. Of Bags (Cement) = 6.58 x 9.00 = 60 bag


No. Of Volume (Sand) = 6.58 x 0.50 = 4 cu.m.
No. Of Volume(Gravel) = 6.58 x 1.00 = 7 cu.m.

Concreting :
One Bagger Mix = 0.4763 x 12 personnel
U/H : 0.4763 m³/hr = 5.716 m³/hr
Number of Hours = 6.58 / 5.716 = 1.15 hr.
Placing of Concrete = 0.415 x 12 personnel
U/H : 0.415 m³/hr = 4.980 m³/hr
Number of Hours = 6.58 / 4.980 = 1.32 hr.

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Cement, Portland bags 60.00 234.33 14,059.80


Sand cu.m. 4.00 1,100.00 4,400.00
Gravel cu.m. 7.00 1,100.00 7,700.00

SUB-TOTAL (A) 26,159.80


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Construction Foreman 1 2.47 95.000 234.65


Skilled 4 2.47 68.940 681.13
Unskilled 8 2.47 53.060 1,048.47

SUB-TOTAL (B) 1,964.25


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

1-Bagger Concrete Mixer 1 1.15 172.00 197.80


Concrete Vibrator (½" 38 - 40 min) 1 1.32 91.25 120.45

SUB-TOTAL (C) 318.25

(D) TOTAL DIRECT COST : (A+B+C) 28,442.30


(E) ADD INDIRECT COST
1. OCM 15% 4,266.35
2. Contractor's Profit 10% 2,844.23
3. VAT 5% 1,777.64
TOTAL INDIRECT COST 8,888.22

TOTAL COST (D+E) 37,330.52

UNIT COST 5,673.33


DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 804(4) Gravel Fill
COST SHEET I.D. : 804(4) PRODUCTION RATE: 2.00 cu.m./hr.
QUANTITY : 6.62 cu.m. NUMBER OF HOURS: 3.31 hr.

Computation : 33.56

Slab on Fill = 0.05 x 12.700 x 6.00 +


0.00 x 3.025 x 1.50 +
= 3.81 cu.m.
Column Footing (F1) = 0.05 x 1.20 x 1.20
= 0.07 x 12 footings
= 0.84 cu.m.

Wall Footing (WF1) = 0.05 x 0.60 x 65.79

= 1.97 cu.m.

Total Volume = 3.81 + 0.84 + 1.97 +

= 6.62 cu.m.

Gravel Bed (manual) = 1.1825 x 2 personnel


U/H : 1.1825 m³/hr = 2.37 m³/hr
Number of Hours = 6.62 / 2.37
= 2.80 hr.
Plate Compactor = 13.00 x 1 unit
U/H : 13.00 m³/hr = 13.00 m³/hr
Number of Hours = 6.62 / 13.00
= 0.51 hr.

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Gravel cu.m. 6.62 1,100.00 7,282.00

SUB-TOTAL (A) 7,282.00


QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours

Unskilled 4 3.31 53.060 702.51

SUB-TOTAL (B) 702.51


QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours

Plate Compactor, 400-500 Gasoline 1 0.51 123.00 62.73

SUB-TOTAL (C) 62.73

(D) TOTAL DIRECT COST : (A+B+C) 8,047.24

(E) ADD INDIRECT COST


1. OCM 15% 1,207.09
2. Contractor's Profit 10% 804.72
3. VAT 5% 502.95
TOTAL INDIRECT COST 2,514.76

TOTAL COST (D+E) 10,562.00

UNIT COST 1,595.47


Republic of the Philippines
Department of Public Works and Highways
Cebu 2nd District Engineering Office
Lawaan I, Talisay City, Cebu
Contract ID :
Contract Name : Rehab/Completion of Multipurpose Building
Location of the Contract : Barangay Bae, Sibonga, Cebu

APPROVED BUDGET FOR THE CONTRACT


Total Project Duration : 30 Calendar Days
TOTAL
MARK-UPS, % Value
ESTIMATED MARK-UP
ITEM NO. DESCRIPTION QTY. UNIT (5 x
DIRECT COST
OCM Profit % 8)

.(1) .(2) .(3) .(4) .(5) .(6) .(7) .(8) .(9)

B.5 Project Billboard / Signboard 2.00 each 4,826.00 15% 10% 25% P 1,206.50
B.7 Occupational Safety and Health Program 1.00 month 5,560.00 0% 10% 10% P 556.00
B.9 Mobilization / Demobilization 1.00 L.S. 3,776.00 0% 0% 0% -
801 (1) Removal of Structures and Obstruction 1.00 L.S. 5,940.12 15% 10% 25% P 1,485.03
802(2) Surplus Common Excavation 53.08 m3 22,530.34 15% 10% 25% P 5,632.59
804(1)a Embankment (from structure excavation) 38.05 m3 2,928.49 15% 10% 25% P 732.12
804(4) Gravel Fill 6.62 m3 8,047.24 15% 10% 25% P 2,011.81
900 (1).c2 Structural Concrete (Footings and Slab on Fill) 37.23 m3 154,362.56 15% 10% 25% P 38,590.64
900(1)c4 Structural Concrete for Column (Class A, 28 days) 9.24 m3 38,299.52 15% 10% 25% P 9,574.88
900(1)c6 Structural Concrete for Beams (Class A, 28 days) 6.58 m3 28,442.30 15% 10% 25% P 7,110.58
Reinforcing Steel of Reinforced Concrete Structures,
902(1).a 2,861.62 kg 170,549.48 15% 10% 25% P 42,637.37
Grade 40
903(1) Forms and Falseworks 1.00 L.S. 33,132.97 15% 10% 25% P 8,283.24

1003(1).a1 Ceiling with Metal Frame 62.12 m2 42,580.46 15% 10% 25% P 10,645.12

1008 (1).a Aluminum Glass Windows (Sliding Type) 25.84 m2 59,709.86 15% 10% 25% P 14,927.47

1010 (2).b Doors (Wooden Panel) 15.12 m2 74,404.62 15% 10% 25% P 18,601.16

Fabricated Metal Roofing Accessory, gauge 26


1013(2).a2 23.30 ln.m. 6,195.40 15% 10% 25% P 1,548.85
(Flashings)
Republic of the Philippines
Department of Public Works and Highways
Cebu 2nd District Engineering Office
Lawaan I, Talisay City, Cebu
Contract ID :
Contract Name : Rehab/Completion of Multipurpose Building
Location of the Contract : Barangay Bae, Sibonga, Cebu

APPROVED BUDGET FOR THE CONTRACT


Total Project Duration : 30 Calendar Days
TOTAL
MARK-UPS, % Value
ESTIMATED MARK-UP
ITEM NO. DESCRIPTION QTY. UNIT (5 x
DIRECT COST
OCM Profit % 8)

.(1) .(2) .(3) .(4) .(5) .(6) .(7) .(8) .(9)


Fabricated Metal Roofing Accessory, gauge 24
1013(2).b1 12.50 ln.m. 7,189.92 15% 10% 25% P 1,797.48
(Gutters)
Prepainted Metal Sheets, above 0.427 mm (Long
1014(1).b1 78.00 m2 41,248.76 15% 10% 25% P 10,312.19
SPan)

1018(1) Glazed Tiles and Trims 6.60 m2 8,014.67 15% 10% 25% P 2,003.67

1027(1) Cement Plaster Finish 480.26 m2 50,270.84 15% 10% 25% P 12,567.71

1032(1).a Painting Works (Masonry/Concrete) 480.26 m2 49,008.04 15% 10% 25% P 12,252.01

1032(1).b Painting Works (Wood) 30.24 m2 7,255.51 15% 10% 25% P 1,813.88

1046(2).a1 CHB Non Load Bearing (Including Reinforcing Steel) 240.13 m2 156,468.20 15% 10% 25% P 39,117.05

1047(2)a Structural Steel, Trusses 1,702.20 kg 116,370.97 15% 10% 25% P 29,092.74

1047(2)b Structural Steel, Purlins 226.26 kg 21,795.34 15% 10% 25% P 5,448.84

1047(7)b Metal Structure Accessories, Sagrods 22.32 kg 2,206.44 15% 10% 25% P 551.61

1047(3)c Metal Structure Accessories, Turnbuckle 12.00 each 2,320.26 15% 10% 25% P 580.07
Republic of the Philippines
Department of Public Works and Highways
Cebu 2nd District Engineering Office
Lawaan I, Talisay City, Cebu
Contract ID :
Contract Name : Rehab/Completion of Multipurpose Building
Location of the Contract : Barangay Bae, Sibonga, Cebu

APPROVED BUDGET FOR THE CONTRACT


Total Project Duration : 30 Calendar Days
TOTAL
MARK-UPS, % Value
ESTIMATED MARK-UP
ITEM NO. DESCRIPTION QTY. UNIT (5 x
DIRECT COST
OCM Profit % 8)

.(1) .(2) .(3) .(4) .(5) .(6) .(7) .(8) .(9)

1047(4) Metal Structure Accessories, Cross Bracing 43.20 kg 3,654.40 15% 10% 25% P 913.60

1100 (10) Conduits, Boxes & Fittings 1.00 L.S. 39,615.92 15% 10% 25% P 9,903.98

1101 (33) Wires and Wiring Devices 1.00 L.S. 13,628.00 15% 10% 25% P 3,407.00

1103 (1) Lighting Fixtures and Lamps 1.00 L.S. 10,230.00 15% 10% 25% P 2,557.71

TOTAL P 1,190,562.63 P 295,862.45


P 1,190,562.63 P 295,862.46
- (0.01)

PREPARED BY: A P P R O V E D:

MENCHU B. MONTEMAYOR
OIC, Construction Section
Republic of the Philippines
tment of Public Works and Highways
Cebu 2nd District Engineering Office
Lawaan I, Talisay City, Cebu

BUDGET FOR THE CONTRACT

Unit Cost
Total Indirect Cost
VAT (5+9) 5% Total Cost (5+11) (Adjusted)
(9+10)
( 12/ 3 )
.(10) .(11) .(12) .(13)

P 301.63 P 1,508.13 P 6,334.13 P 3,167.07


P 305.80 P 861.80 P 6,421.80 P 6,421.80
P 188.80 P 188.80 P 3,964.80 P 3,964.80
P 371.26 P 1,856.29 P 7,796.41 P 7,796.41
P 1,408.15 P 7,040.74 P 29,571.08 P 557.10
P 183.03 P 915.15 P 3,843.64 P 101.02
P 502.95 P 2,514.76 P 10,562.00 P 1,595.47
P 9,647.66 P 48,238.30 P 202,600.86 P 5,441.87
P 2,393.72 P 11,968.60 P 50,268.12 P 5,440.27
P 1,777.64 P 8,888.22 P 37,330.52 P 5,673.33

P 10,659.34 P 53,296.71 P 223,846.19 P 78.22

P 2,070.81 P 10,354.05 P 43,487.02 P 43,487.02

P 2,661.28 P 13,306.40 P 55,886.86 P 899.66

P 3,731.87 P 18,659.34 P 78,369.20 P 3,032.86

P 4,650.29 P 23,251.45 P 97,656.07 P 6,458.73

P 387.21 P 1,936.06 P 8,131.46 P 348.99


Republic of the Philippines
tment of Public Works and Highways
Cebu 2nd District Engineering Office
Lawaan I, Talisay City, Cebu

BUDGET FOR THE CONTRACT

Unit Cost
Total Indirect Cost
VAT (5+9) 5% Total Cost (5+11) (Adjusted)
(9+10)
( 12/ 3 )
.(10) .(11) .(12) .(13)

P 449.37 P 2,246.85 P 9,436.77 P 754.94

P 2,578.05 P 12,890.24 P 54,139.00 P 694.09

P 500.92 P 2,504.59 P 10,519.26 P 1,593.83

P 3,141.93 P 15,709.64 P 65,980.48 P 137.38

P 3,063.00 P 15,315.01 P 64,323.05 P 133.93

P 453.47 P 2,267.35 P 9,522.86 P 314.91

P 9,779.26 P 48,896.31 P 205,364.51 P 855.22

P 7,273.19 P 36,365.93 P 152,736.90 P 89.73

P 1,362.21 P 6,811.05 P 28,606.39 P 126.43

P 137.90 P 689.51 P 2,895.95 P 129.75

P 145.02 P 725.09 P 3,045.35 P 253.78


Republic of the Philippines
tment of Public Works and Highways
Cebu 2nd District Engineering Office
Lawaan I, Talisay City, Cebu

BUDGET FOR THE CONTRACT

Unit Cost
Total Indirect Cost
VAT (5+9) 5% Total Cost (5+11) (Adjusted)
(9+10)
( 12/ 3 )
.(10) .(11) .(12) .(13)

P 228.40 P 1,142.00 P 4,796.40 P 111.03

P 2,476.00 P 12,379.98 P 51,995.90 P 51,995.90

P 851.75 P 4,258.75 P 17,886.75 P 17,886.75

P 639.37 P 3,196.66 P 13,426.62 P 13,426.62

P 74,321.28 P 370,183.73 P 1,560,746.35


P 74,321.28 P 370,183.74 P 1,560,746.37
- (0.01) (0.02)

LESLIE ANTHONY S. MOLINA


District Engineer
Republic of the Philippines
Department of Public Works and Highways
Cebu 2nd District Engineering Office
Lawaan I, Talisay City, Cebu

Project : Rehab/Completion of Multipurpose Building


Location : Barangay Bae, Sibonga, Cebu
Appropriation : P 500,000.00 Date :
Source of Funds : NEP C.Y. 2018 Starting time :
Classification : Building Total Project Duration (C.D.) :

PROGRAM OF WORK/BUDGET COST


% of EQUIPMENT
DESCRIPTION OF WORKS TO BE DONE
Total DESCRIPTION
PART A : OTHER GENERAL REQUIREMENTS 1.19% ( PLEASE SEE DETAILED EST
PART B : REMOVAL OF STRUCTURES AND OBSTRUCTIONS 0.50%
PART C : EXCAVATION 1.89%
PART D : EMBANKMENT 0.92%
PART E : REINFORCED CONCRETE 18.57%
PART F : REINFORCING STEEL 14.33%
PART G : FORMWORKS AND FALSEWORKS 2.78%
PART H : CARPENTRY AND JOINERY WORKS 3.58%
PART I : ALUMINUM GLASS WINDOWS 5.02%
PART J : WOODEN DOORS AND WINDOWS 6.25%
PART K : CORRUGATED METAL ROOFING 1.12%
PART L : PREPAINTED METAL SHEETS 3.46%
PART M : CERAMIC/GRANITE TILES 0.67%
PART N : CEMENT PLASTER FINISH 4.22%
PART O : PAINTING, VARNISHING AND OTHER RELATED WORKS 4.73%
PART P : MASONRY WORKS 13.14%
PART Q : METAL STRUCTURES 12.29%
CONDUITS, BOXES & FITTINGS (CONDUIT WORKS/ CONDUIT
PART R : ROUGH-IN)
3.33%

PART S : WIRES AND WIRING DEVICES 1.14%


PART T : LIGHTING FIXTURES AND LAMPS 0.86%
TOTAL: 100.00%
ESTIMATED COST OF THE PROJECT
DESCRIPTION QUANTITY UNIT
PART A : OTHER GENERAL REQUIREMENTS ( PLEASE SEE DETAILED ESTIMATES)
PART B : REMOVAL OF STRUCTURES AND OBSTRUCTIONS
PART C : EXCAVATION
PART D : EMBANKMENT
PART E : REINFORCED CONCRETE
PART F : REINFORCING STEEL
PART G : FORMWORKS AND FALSEWORKS
PART H : CARPENTRY AND JOINERY WORKS
PART I : ALUMINUM GLASS WINDOWS
PART J : WOODEN DOORS AND WINDOWS
PART K : CORRUGATED METAL ROOFING
PART L : PREPAINTED METAL SHEETS
PART M : CERAMIC/GRANITE TILES
PART N : CEMENT PLASTER FINISH
PART O : PAINTING, VARNISHING AND OTHER RELATED WORKS
PART P : MASONRY WORKS
PART Q : METAL STRUCTURES
PART R : CONDUITS, BOXES & FITTINGS (CONDUIT WORKS/ CONDUIT ROUGH-IN)
PART S : WIRES AND WIRING DEVICES
PART T : LIGHTING FIXTURES AND LAMPS

TOTAL:

1. Labor P 231,878.70 A. Sub-Total


2. Materials P 923,119.69 B. Const.Engineering
3. Rental of Equipment P 35,564.24 C.Taxes (VAT, etc.)
4. Direct Cost P 1,190,562.63 D. Soil Exploration
5. OCM, Profit, Q.C. MOB P 295,862.46 E. TOTAL ESTIMATED COST
6. Engineering Overhead -
7. VAT P 74,321.28
8. TOTAL P 1,560,746.37

PREPARED BY: CHECKED BY:

MARVIN A. BENSIG HELEN GRACE B. YA


Engineering Assistant Chief, Planning and Design

RECOMMENDING APPROVAL: A P P R O V E D:

PAZ P. ADLAWAN LESLIE ANTHONY S. MO


OIC, Assistant District Engineer District Engineer
ic of the Philippines
ublic Works and Highways
strict Engineering Office
I, Talisay City, Cebu

March 6, 2018
Upon approval
30

WORK/BUDGET COST
EQUIPMENT
REQUIRED
( PLEASE SEE DETAILED ESTIMATES)

D COST OF THE PROJECT


TOTAL
14,162.00
5,940.12
22,530.34
10,975.73
221,104.38
170,549.48
33,132.97
42,580.46
59,709.86
74,404.62
13,385.32
41,248.76
8,014.67
50,270.84
56,263.55
156,468.20
146,347.41
39,615.92
13,628.00
10,230.00

P 1,190,562.63

P 1,190,562.63

P 370,183.74

P 1,560,746.37

HELEN GRACE B. YAP


Chief, Planning and Design Section

LESLIE ANTHONY S. MOLINA


District Engineer
BILL OF QUANTITIES

Project : PROPOSED COMMERCIAL RESIDENTIAL BUILDING


Location : GREYROCKS PANGDAN, NAGA
Client : GABUT AVALINO TAGNIPEZ

UNIT RATE
ITEM NO. DESCRIPTION QUANTITY UNIT AMOUNT
MATERIALS

PART A MASONRY WORKS AND FINISHES

CHB 6" 3,032.00 pcs P 16.00 P 48,512.00

Cement, Portland 735.00 bags P 240.00 P 176,400.00

Sand 56.10 cu.m. P 1,100.00 P 61,710.00

Gravel, 3/4" 60.62 cu.m. P 1,100.00 P 66,682.00

Ceramic Tiles 6.60 sq.m. P 850.00 P 5,610.00

Stone Bricks (Cladding) 8.30 sq.m. P 1,350.00 P 11,205.00

Tile Grout 2.00 kgs P 40.00 P 80.00

Sub-Total of Part A P 370,199.00

PART B REINFORCING STEEL

16mmØ x 6.00 m Deformed Bars 1,924.18 kgs P 41.00 P 78,891.38

10mmØ x 6.00 m Deformed Bars 937.44 kgs P 41.00 P 38,435.04

Sub-Total of Part B P 117,326.42

PART C CARPENTRY AND FORMWORKS

¼" x 4' x 8' Ordinary Plywood 13.00 pcs P 325.00 P 4,225.00

Coco Lumber 1,149.48 bd.ft. P 15.00 P 17,242.20

Fiber Cement Board 4' x 8' x 4.5mm 21.00 sheet P 540.00 P 11,340.00

Metal Furring (12mmx38mmx5mx0.80mm) 19.00 length P 140.00 P 2,660.00

Carrying Channel (12mmx38mmx5mx0.80mm) 15.00 length P 130.00 P 1,950.00

Wal Angle (25mmx25mmx3m) 25.00 length P 45.00 P 1,125.00

Hardiflex Board ½" x 4" x 8" 2.00 sheet P 1,500.00 P 3,000.00

Sub-Total of Part C P 41,542.20

PART D CONSTRUCTION HARDWARES

Welding Rod ½"Ø E-70 Series 57.00 kgs P 67.00 P 3,819.00

Acetylene 11.00 kgs P 80.00 P 880.00

Oxygen 11.00 kgs P 45.00 P 495.00

Red Lead Primer Oxide 10.00 gal. P 570.00 P 5,700.00

# 16 Tie Wire G.I. 24.00 kgs P 50.00 P 1,200.00

Assorted C.W. Nails 22.00 kgs P 31.00 P 682.00

Hardiflex Screw 497.00 pcs P 1.50 P 745.50

Blind Rivets 1/8" x 3/8" 248.00 pcs P 0.50 P 124.00

J-Bolt 6mmØ 642.00 pcs P 1.50 P 963.00

Roof Sealant 25.00 tube P 150.00 P 3,750.00

Sub-Total of Part D P 18,358.50


PART E METAL STRUCTURES AND ROOFING

2" x 2" x 1/4" (Angle Bar) 1,341.00 kgs P 53.00 P 71,073.00

1 1/2" x 1 1/2" x 1/4" (Angle Bar) 305.76 kgs P 53.00 P 16,205.28


UNIT RATE
ITEM NO. DESCRIPTION QUANTITY UNIT AMOUNT
MATERIALS

1" x 1" x 1/4" (Angle Bar) 69.30 kgs P 53.00 P 3,672.90

LC 2" x 4" x 1.0mm thk. 212.40 kgs P 53.00 P 11,257.20

Sag Rods and Cross Bracings 65.52 kgs P 41.00 P 2,686.32

Turn Buckle 5/8" 12.00 pcs P 190.00 P 2,280.00


UNIT RATE
ITEM NO. DESCRIPTION QUANTITY UNIT AMOUNT
MATERIALS

2" x 6" x 1.0mm Rectangular Tube 9.00 pc P 1,336.30 P 12,026.70

1" x 3" Flat Bar for Canopy Support 2.00 pc P 2,278.10 P 4,556.20

Pre-painted Pre-formed Side Flashing 23.30 ln.m. P 190.00 P 4,427.00

Pre-Painted Metal Roofing, Gauge 26 Long Span 78.00 sq.m. P 450.00 P 35,100.00

Pre-painted Pre-formed Gutter 12.50 ln.m. P 190.00 P 2,375.00

Polycarbonate Sheet 7.00 Sheets P 900.00 P 6,300.00

Sub-Total of Part E P 171,959.60

PART F DOORS AND WINDOWS

(W-1) Sliding Windows (Glass) 4.00 set P 10,752.00 P 43,008.00

Area = (1.20x 1.6)

(W-2) Fixeds (Glass) 1.00 set P 7,008.00 P 7,008.00

Area = (4.325x 2.7)

(W-3) Fixeds (Glass) 1.00 set P 3,888.00 P 3,888.00

Area = (2.4x 2.7)

(D-1) Tanguile Paneled Door on 50 x 150mm Thk 9.00 set P 7,728.00 P 69,552.00
Mahogany jamb complete with hardware and
accessories cylinder type lockset

Sub-Total of Part E P 123,456.00

PART G ELECTRICAL WORKS

Electrical Works 1.00 L.S. P 95,210.88 P 95,210.88

Sub-Total of Part G P 95,210.88


PART H PLUMBING WORKS

Plumbing Works 1.00 L.S. P 343,116.36 P 343,116.36

Sub-Total of Part H P 343,116.36

MATERIAL COST 1,281,168.96

PART I LABOR COST (35% Material Cost)

LABOR COST 448,409.14

PART J CONTINGENCIES (10% Labor Cost + 10% Material Cost)

Contigency Cost 172,957.81

TOTAL COST (H +I + J) 1,902,535.91

PREPARED BY:

LEONARD B. ABAO
Licensed Civil Engineer
Republic of the Philippines
Department of Public Works and Highways
Cebu 2nd District Engineering Office
Lawaan I, Talisay City, Cebu

Rehab/Completion of Multipurpose Building


Barangay Bae, Sibonga, Cebu

ESTIMATED COST OF PROPOSED WORK


DIRECT COST
ITEM NO. DESCRIPTION % QUANTITY UNIT
TOTAL

PART A OTHER GENERAL REQUIREMENTS

B.5 Project Billboard / Signboard 0.41% 2.00 each P 4,826.00

B.7 Occupational Safety and Health Program 0.47% 1.00 month P 5,560.00

B.9 Mobilization / Demobilization 0.32% 1.00 L.S. P 3,776.00

Sub-Total of Part A 1.19% P 14,162.00

PART B REMOVAL OF STRUCTURES AND OBSTRUCTIONS

801 (1) Removal of Structures and Obstruction 0.50% 1.00 L.S. P 5,940.12

Sub-Total of Part B 0.50% P 5,940.12

PART C EXCAVATION

802(2) Surplus Common Excavation 1.89% 53.08 m3 P 22,530.34

Sub-Total of Part C 1.89% P 22,530.34

PART D EMBANKMENT

804(1)a Embankment (from structure excavation) 0.25% 38.05 m3 P 2,928.49

804(4) Gravel Fill 0.68% 6.62 m 3


P 8,047.24
Sub-Total of Part D 0.92% P 10,975.73

PART E REINFORCED CONCRETE

900 (1).c2 Structural Concrete (Footings and Slab on Fill) 12.97% 37.23 m3 P 154,362.56
Structural Concrete for Column (Class A, 28
900(1)c4 3.22% 9.24 m3 P 38,299.52
days)
900(1)c6 Structural Concrete for Beams (Class A, 28 days) 2.39% 6.58 m3 P 28,442.30

Sub-Total of Part E 18.57% P 221,104.38

PART F REINFORCING STEEL


Reinforcing Steel of Reinforced Concrete
902(1).a 14.33% 2,861.62 kg P 170,549.48
Structures, Grade 40
Sub-Total of Part F 14.33% P 170,549.48

PART G FORMWORKS AND FALSEWORKS


903(1) Forms and Falseworks 2.78% 1.00 L.S. P 33,132.97
Sub-Total of Part G 2.78% P 33,132.97

PART H CARPENTRY AND JOINERY WORKS

1003(1).a1 Ceiling with Metal Frame 3.58% 62.12 m2 P 42,580.46

Sub-Total of Part H 3.58% P 42,580.46


PART I ALUMINUM GLASS WINDOWS
1008 (1).a Aluminum Glass Windows (Sliding Type) 5.02% 25.84 m2 P 59,709.86
Sub-Total of Part I 5.02% P 59,709.86
PART J WOODEN DOORS AND WINDOWS
1010 (2).b Doors (Wooden Panel) 6.25% 15.12 m2 P 74,404.62
Sub-Total of Part J 6.25% P 74,404.62
Republic of the Philippines
Department of Public Works and Highways
Cebu 2nd District Engineering Office
Lawaan I, Talisay City, Cebu

Rehab/Completion of Multipurpose Building


Barangay Bae, Sibonga, Cebu

ESTIMATED COST OF PROPOSED WORK


DIRECT COST
ITEM NO. DESCRIPTION % QUANTITY UNIT
TOTAL

PART K CORRUGATED METAL ROOFING


Fabricated Metal Roofing Accessory, gauge 26
1013(2).a2 0.52% 23.30 ln.m. P 6,195.40
(Flashings)
Fabricated Metal Roofing Accessory, gauge 24
1013(2).b1 0.60% 12.50 ln.m. P 7,189.92
(Gutters)
Sub-Total of Part K 1.12% P 13,385.32

PART L PREPAINTED METAL SHEETS


Prepainted Metal Sheets, above 0.427 mm (Long
1014(1).b1 3.46% 78.00 m2 P 41,248.76
SPan)
Sub-Total of Part L 3.46% P 41,248.76
PART M CERAMIC/GRANITE TILES
1018(1) Glazed Tiles and Trims 0.67% 6.60 m2 P 8,014.67
Sub-Total of Part M 0.67% P 8,014.67
PART N CEMENT PLASTER FINISH
1027(1) Cement Plaster Finish 4.22% 480.26 m2 P 50,270.84
Sub-Total of Part N 4.22% P 50,270.84
PART O PAINTING, VARNISHING AND OTHER RELATED WORKS
1032(1).a Painting Works (Masonry/Concrete) 4.12% 480.26 m2 P 49,008.04
1032(1).b Painting Works (Wood) 0.61% 30.24 m2 P 7,255.51
Sub-Total of Part O 4.73% P 56,263.55
PART P MASONRY WORKS
CHB Non Load Bearing (Including Reinforcing
1046(2).a1 13.14% 240.13 m2 P 156,468.20
Steel)
Sub-Total of Part P 13.14% P 156,468.20

PART Q METAL STRUCTURES


1047(2)a Structural Steel, Trusses 9.77% 1,702.20 kg P 116,370.97
1047(2)b Structural Steel, Purlins 1.83% 226.26 kg P 21,795.34
1047(7)b Metal Structure Accessories, Sagrods 0.19% 22.32 kg P 2,206.44
1047(3)c Metal Structure Accessories, Turnbuckle 0.19% 12.00 each P 2,320.26
1047(4) Metal Structure Accessories, Cross Bracing 0.31% 43.20 kg P 3,654.40
Sub-Total of Part Q 12.29% P 146,347.41

PART R CONDUITS, BOXES & FITTINGS (CONDUIT WORKS/ CONDUIT ROUGH-IN)


1100 (10) Conduits, Boxes & Fittings 3.33% 1.00 L.S. P 39,615.92
Sub-Total of Part R 3.33% P 39,615.92

PART S WIRES AND WIRING DEVICES


1101 (33) Wires and Wiring Devices 1.14% 1.00 L.S. P 13,628.00
Sub-Total of Part S 1.14% P 13,628.00

PART T LIGHTING FIXTURES AND LAMPS


1103 (1) Lighting Fixtures and Lamps 0.86% 1.00 L.S. P 10,230.00
Sub-Total of Part T 0.86% P 10,230.00

GRAND TOTAL 100.00% P 1,190,562.63


blic of the Philippines
Public Works and Highways
District Engineering Office
an I, Talisay City, Cebu

ion of Multipurpose Building


y Bae, Sibonga, Cebu

T OF PROPOSED WORK
DIRECT COST ADJUSTED
UNIT COST UNIT COST

P 2,413.00 P 3,167.07

P 5,560.00 P 6,421.80

P 3,776.00 P 3,964.80

P 5,940.12 P 7,796.41

P 424.46 P 557.10

P 76.96 P 101.02

P 1,215.60 P 1,595.47

P 4,146.19 P 5,441.87

P 4,144.97 P 11,968.60

P 4,322.54 P 5,673.33

P 59.60 P 78.22

P 33,132.97 P 43,487.03

P 685.45 P 899.66

P 2,310.75 P 3,032.86

P 4,920.94 P 6,458.73
blic of the Philippines
Public Works and Highways
District Engineering Office
an I, Talisay City, Cebu

ion of Multipurpose Building


y Bae, Sibonga, Cebu

T OF PROPOSED WORK
DIRECT COST ADJUSTED
UNIT COST UNIT COST

P 265.90 P 348.99

P 575.19 P 754.94

P 528.83 P 694.09

P 1,214.34 P 1,593.83

P 104.67 P 137.38

P 102.04 P 133.93
P 239.93 P 314.91

P 651.60 P 855.22

P 68.37 P 89.73
P 96.33 P 126.43
P 98.85 P 129.75
P 193.36 P 253.78
P 84.59 P 111.03

P 39,615.92 P 51,995.90

P 13,628.00 P 17,886.75

P 10,230.00 P 13,426.88
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1003(1).a1 Ceiling with Metal Frame
COST SHEET I.D. : 1003(1).a1 PRODUCTION RATE: 0.62 sq.m./hr.
QUANTITY : 62.12 sq.m. NUMBER OF HOURS: 100.84 hr.
Computation : 259.49
Horizontal Ceiling = 12.30 x 5.05
(Including Eaves Area) = 62.12 / 2.9768
= 20.87 say 21 sheets - (4.5 mm thk Fiber Cement Board)

Metal Furring = 62.12 x 1.50 m./sq.m.


(38mmx12mmx5m) = 93.18 / 5.00
= 18.64 say 19 lengths
Carrying Channel = 62.12 x 1.20 m./sq.m.
(38mmx12mmx5m) = 74.54 / 5.00
= 14.91 say 15 lengths
Wal Angle = 62.12 x 1.20 m./sq.m.
(25mmx25mmx3m) = 74.54 / 3.00
= 24.85 say 25 lengths
Hardiflex Screw = 62.12 x 8 pc./sq.m.
= 496.96 say 497 pc
Blind Rivets = 62.12 x 4 pc./sq.m.
1/8" x 3/8" = 248.48 say 248 pc
note: 1 keg = 45 kgs
Assorted Nails = 62.12 / 2,500
= 0.0248 x 45 kg/keg
= 1 kgs
Frameworks = 0.6375 x 4 personnel
U/H : 0.6375 m²/hr = 2.55 sq.m./hr.
Number of Hours = 62.12 / 2.55
= 24.36 hr
Board Installation = 0.85 x 4 personnel
U/H : 0.85 m²/hr = 3.400 sq.m./hr.
Number of Hours = 62.12 / 3.40
= 18.27 x 30% - No. Of hours for installation will be
= 5.481 hr added for the total no. Of hours.
Installation = 1.75 x 4 personnel
U/H : 1.75 m²/hr = 7.00 sq.m./hr.
Number of Hours = 497.00 / 7.00
= 71.00 hr
(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST
Fiber Cement Board 4' x 8' x 4.5mm sheet 21.00 540.00 11,340.00
Metal Furring (12mmx38mmx5mx0.80mm) length 19.00 140.00 2,660.00
Carrying Channel (12mmx38mmx5mx0.80mm) length 15.00 130.00 1,950.00
Wal Angle (25mmx25mmx3m) length 25.00 45.00 1,125.00
Hardiflex Screw pc 497.00 1.50 745.50
Blind Rivets 1/8" x 3/8" pc 248.00 0.50 124.00
Assorted Nails kgs 1.00 31.00 31.00
SUB-TOTAL (A) 17,975.50
QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours
Skilled 2 100.84 68.940 13,903.82
Unskilled 2 100.84 53.060 10,701.14
SUB-TOTAL (B) 24,604.96
QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours
NONE
SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 42,580.46


(E) ADD INDIRECT COST
1. OCM 15% 6,387.07
2. Contractor's Profit 10% 4,258.05
3. VAT 5% 2,661.28
TOTAL INDIRECT COST 13,306.40
TOTAL COST (D+E) 55,886.86

UNIT COST 899.66


DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 903(1) Forms and Falseworks
COST SHEET I.D. : 903(1)
QUANTITY : 1.00 L.S. NUMBER OF HOURS: 31.46 hr.
Computation :
Beam Formworks = 0.20 + 0.30 x 2
x 12.000 l.m.
= 9.60 / 2.98 plywood / m²
No. of Plywood = 3 x 25.06 = 75.18 bd.ft. (2" x 2")
Beam Scaffoldings (Ver) = 12.00 x 4.00 = 48.00 bd.ft. (2" x 2")
Beam Scaffoldings (Hor) = 12.00 x 4.70 = 56.40 bd.ft. (2" x 2")
Column Formworks = 0.30 x 2 +
0.45 x 2 x 3.00 l.m. ht.
= 4.50 x 6 no. of columns
= 27.00 / 2.98 plywood / m²
No. of Plywood = 10 x 29.67 = 296.70 bd.ft. (2" x 2")
Column Scaffoldings (Ver) = 18.00 x 4.70 = 84.60 bd.ft. (2" x 2")
Column Scaffoldings (Hor) = 18.00 x 21.00 = 378.00 bd.ft. (2" x 2")
Column Scaffoldings (Bra) = 18.00 x 11.70 = 210.60 bd.ft. (2" x 2")
Assorted C.W.Nails = 1,149.48 / 2,500 x 45
Note: 1 keg = 45 kgs = 21.00 kg
FORMWORKS
Formworks :
Installation = 0.2725 x 6 personnel
U/H : 0.2725 m²/hr = 1.64 m²/hr
Number of Hours = 36.60 / 1.64 = 0.61 hr.
Stripping = 0.825 x 6 personnel
U/H : 0.8250 m²/hr = 4.95 m²/hr
Number of Hours = 36.60 / 4.95 = 7.39 hr.
SCAFFOLDINGS :
Installation = 0.3575 x 6 personnel
U/H : 0.3575 m²/hr = 2.145 m²/hr
Number of Hours = 36.60 / 2.145 = 17.06 hr.
Stripping = 0.9550 x 6 personnel
U/H : 0.9550 m²/hr = 5.730 m²/hr
Number of Hours = 36.60 / 5.73 = 6.39 hr.

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Coco Lumber bd.ft. 1,149.48 15.00 17,242.20


Assorted C.W. Nails kgs 21.00 31.00 651.00
¼" x 4' x 8' Ordinary Plywood pcs 13.00 325.00 4,225.00

SUB-TOTAL (A) 22,118.20


QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours

Skilled 2 31.46 68.940 4,337.70


Unskilled 4 31.46 53.060 6,677.07

SUB-TOTAL (B) 11,014.77


QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 33,132.97


(E) ADD INDIRECT COST
1. OCM 15% 4,969.95
2. Contractor's Profit 10% 3,313.30
3. VAT 5% 2,070.81
TOTAL INDIRECT COST 10,354.06
TOTAL COST (D+E) 43,487.03
UNIT COST 43,487.03
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 902(1).a Reinforcing Steel of Reinforced Concrete Structures, Grade 40
COST SHEET I.D. : 902(1).a PRODUCTION RATE: 29.82 kgs./hr.
QUANTITY : 2,861.62 kg NUMBER OF HOURS: 95.96 hr.

Note : See details computation for the total quantity

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST


16mmØ x 6.00 m Deformed Bars kgs 1,924.18 41.00 78,891.38
10mmØ x 6.00 m Deformed Bars kgs 937.44 41.00 38,435.04
# 16 Tie Wire G.I. kgs 24.00 50.00 1,200.00
SUB-TOTAL (A) 118,526.42
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
Skilled 6 95.96 68.940 39,692.89
SUB-TOTAL (B) 39,692.89
QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate
Bar Cutter 1 56.11 219.75 12,330.17
SUB-TOTAL (C) 12,330.17
(D) TOTAL DIRECT COST : (A+B+C) 170,549.48
(E) ADD INDIRECT COST
1. OCM 15% 25,582.20
2. Contractor's Profit 10% 17,054.95
3. VAT 5% 10,659.33
TOTAL INDIRECT COST 53,296.48
TOTAL COST (D+E) 223,845.96

UNIT COST 78.22


DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 902(1).a Reinforcing Steel of Reinforced Concrete Structures for One-Storey, Grade 40
COST SHEET I.D. : 902(1).a PRODUCTION RATE: 29.82 kgs./hr.
QUANTITY : 2,861.62 kg NUMBER OF HOURS: 95.96 hr.

RB1 AND RB1 = 109.64 x 6 x 1


Main Bars = 657.85 meter length

= 657.85 / 6
= 110 lengths of 16mmØ x 6.00 m Deformed Bars

RB1 (Roof Beams) = 1.00 x 732 x 1


Stirrups = 732.00 meter length
= 732.00 / 6
= 122 lengths of 10mmØ x 6.00 m Deformed Bars

= 732.00 x 0.30 / 53
# 16 Tie Wire G.I. = 5.00 kgs of G.I. Tie Wire

Column (C-1) = 6 x 5.70 x 12 Columns


Vertical Bars = 410.40 / 6
= 69 lengths of 16mmØ x 6.00 m Deformed Bars
Column (C-1) = 3.00 / 0.10 x 1.10 meter
Stirrups = 33.00 / 6 x 12 Columns
= 66 x 1 (Single Tie)
= 66 lengths of 10mmØ x 6.00 m Deformed Bars
= 3.00 / 0.10 x 6
= 180.00 x 0.30 / 53
= 1.02 x 12 Columns
= 13.00 kgs of G.I. Tie Wire

Footing (F-1) = 12 x 1.00 x 12 Footings


Vertical Bars = 144.00 / 6
= 24 lengths of 12mmØ x 6.00 m Deformed Bars
= 36.00 x 0.30 / 53
= 0.20 x 12 Footings
= 3.00 kgs of G.I. Tie Wire

Ground Floor Slab 1 = 12.70 / 0.40 x 6.00 +


6.00 / 0.40 x 12.70 +
= 381.00 / 6
= 64 lengths of 10mmØ x 6.00 m Deformed Bars
= 12.700 / 0.40 x
6.000 / 0.40 +

= 476 x 0.30 / 53.00


= 3.00 kgs of G.I. Tie Wire

Ground Floor Slab 2 = / 0.40 x 0.00 +


/ 0.40 x 0.00 +
= 0.00 / 6
= 0 lengths of 10mmØ x 6.00 m Deformed Bars
= 0.00 / 0.40 x
0.00 / 0.40 +
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 902(1).a Reinforcing Steel of Reinforced Concrete Structures for One-Storey, Grade 40
COST SHEET I.D. : 902(1).a PRODUCTION RATE: 29.82 kgs./hr.
QUANTITY : 2,861.62 kg NUMBER OF HOURS: 95.96 hr.
= 0 x 0.30 / 53.00
= 0.00 kgs of G.I. Tie Wire

Fabrication = 8.50 x 6 personnel


U/H : 8.50 kg/hr = 51.00 kgs/hr
Number of Hours = 2,861.62 / 51.00
= 56.11 hr
Placing = 11.9675 x 6 personnel
U/H : 11.9675 kg/hr = 71.81 kgs/hr
Number of Hours = 2,861.62 / 71.81
= 39.85 hrs
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 802(2) Surplus Common Excavation
COST SHEET I.D. : 802(2) PRODUCTION RATE: 0.75 cu.m./hr.
QUANTITY : 53.08 cu.m. NUMBER OF HOURS: 70.77 hr.

Computation : 114.01
Column Footing (F1) = 1.20 x 1.20 x 1.70
= 2.450 x 12 footings
= 29.40 cu.m.

Wall Footing (WF1) = 0.60 x 0.60 x 65.79


= 23.680 cu.m.

Total Volume = 29.40 + 23.68


= 53.08 cu.m.
Excavation (manual) = 0.125 x 6 personnel
U/H : 0.125 m³/hr = 0.75 m³/hr
Number of Hours = 53.08 / 0.75
= 70.77 hr.

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

NONE

SUB-TOTAL (A) -
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Unskilled 6 70.77 53.060 22,530.34

SUB-TOTAL (B) 22,530.34


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 22,530.34


(E) ADD INDIRECT COST
1. OCM 15% 3,379.55
2. Contractor's Profit 10% 2,253.03
3. VAT 5% 1,408.15
TOTAL INDIRECT COST 7,040.73
TOTAL COST (D+E) 29,571.07

UNIT COST 557.10


DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 804(1)a Embankment (from structure excavation)
COST SHEET I.D. : 804(1)a PRODUCTION RATE: 3.14 cu.m./hr.
QUANTITY : 38.05 cu.m. NUMBER OF HOURS: 12.10 hr.

Computation : 70.15

Column Footing (F1) = 1.20 x 1.20 x 1.40


= 2.02 x 12 footings
= 24.24 cu.m.

Wall Footing (WF1) = 0.60 x 0.35 x 65.79


= 13.81 cu.m.

Total Volume = 24.24 + 13.81


= 38.05 cu.m.

Backfilling (manual) = 1.0375 x 4 personnel


U/H : 1.0375 m³/hr = 4.15 m³/hr
Number of Hours = 38.05 / 4.15
= 9.17 hr.
Plate Compactor = 13.00 x 1 unit
U/H : 13.00 m³/hr = 13.00 m³/hr
Number of Hours = 38.05 / 13.00
= 2.93 hr.

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

NONE

SUB-TOTAL (A) -
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
Unskilled 4 12.10 53.060 2,568.10

SUB-TOTAL (B) 2,568.10


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

Plate Compactor, 400-500 Gasoline 1 2.93 123.00 360.39

SUB-TOTAL (C) 360.39

(D) TOTAL DIRECT COST : (A+B+C) 2,928.49


(E) ADD INDIRECT COST
1. OCM 15% 439.27
2. Contractor's Profit 10% 292.85
3. VAT 5% 183.03
TOTAL INDIRECT COST 915.15

TOTAL COST (D+E) 3,843.64


UNIT COST 101.02
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1008 (1).a Aluminum Glass Windows (Sliding Type)
COST SHEET I.D. : 1008 (1).a PRODUCTION RATE: 0.68 sq.m./hr.
QUANTITY : 25.84 m2 NUMBER OF HOURS: 38.28 hr.

Computation : 128.275

Installation = 0.3375 x 2 personnel


U/H : 0.3375 m²/hr = 0.68 sq.m./hr.
Number of Hours = 25.84 / 0.68
= 38.28 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

(W-1) Sliding Windows (Glass) set 4.00 10,752.00 43,008.00


Area = (1.20x 1.6) = 1.92 m²

(W-2) Fixeds (Glass) set 1.00 7,008.00 7,008.00


Area = (4.325x 2.7) = 11.68 m²

(W-3) Fixeds (Glass) set 1.00 3,888.00 3,888.00


Area = (2.4x 2.7) = 6.48 m²

SUB-TOTAL (A) 53,904.00


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 2 38.28 68.940 5,278.05

SUB-TOTAL (B) 5,278.05


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

Minor Tools (10% of Labor Cost) 527.81

SUB-TOTAL (C) 527.81

(D) TOTAL DIRECT COST : (A+B+C) 59,709.86

(E) ADD INDIRECT COST


1. OCM 15% 8,956.48
2. Contractor's Profit 10% 5,970.99
3. VAT 5% 3,731.87
TOTAL INDIRECT COST 18,659.34

TOTAL COST (D+E) 78,369.20

UNIT COST 3,032.86


DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1010 (2).b Doors (Wooden Panel)
COST SHEET I.D. : 1010 (2).b PRODUCTION RATE: 0.00 sq.m./hr.
QUANTITY : 15.12 sq.m. NUMBER OF HOURS: 63.99 hr.

Computation : 46.71
Installation = 0.2363 x 1 personnel
U/H : 0.2363 m²/hr = 0.2363 sq.m./hr.
Number of Hours = 15.12 / 0.2363
= 63.99 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

(D-1) Tanguile Paneled Door on 50 x


150mm Thk Mahogany jamb complete
set 9.00 7,728.00 69,552.00
with hardware and accessories cylinder
type lockset

Area = (0.9 x 2.10) = 1.68 m²

SUB-TOTAL (A) 69,552.00


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 1 63.99 68.940 4,411.47

SUB-TOTAL (B) 4,411.47


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

Minor Tools (10% of Labor Cost) 441.15

SUB-TOTAL (C) 441.15

(D) TOTAL DIRECT COST : (A+B+C) 74,404.62


(E) ADD INDIRECT COST
1. OCM 15% 11,160.69
2. Contractor's Profit 10% 7,440.46
3. VAT 5% 4,650.29
TOTAL INDIRECT COST 23,251.44

TOTAL COST (D+E) 97,656.06


UNIT COST 6,458.73
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1013(2).a2 Fabricated Metal Roofing Accessory, gauge 26 (Flashings)
COST SHEET I.D. : 1013(2).a2 PRODUCTION RATE: 21.18 sq.m./hr.
QUANTITY : 23.30 ln.m. NUMBER OF HOURS: 1.10 hr.
Computation : 316.61
Flashing for Existing Roof = 23.30 / 2.35

Flashing for New Roof = 0.00 / 2.35


( Back to Back)

Installation Flashing = 5.3125 x 4 personnel


U/H : 5.3125 ln.m./hr = 21.250 ln.m./hr.
Number of Hours = 23.30 / 21.250 = 1.10 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Pre-painted Pre-formed Side Flashing ln.m. 23.30 190.00 4,427.00


Roof Sealant tube 10.00 150.00 1,500.00

SUB-TOTAL (A) 5,927.00


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 2 1.10 68.940 151.67


Unskilled 2 1.10 53.060 116.73

SUB-TOTAL (B) 268.40


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 6,195.40

(E) ADD INDIRECT COST


1. OCM 15% 929.31
2. Contractor's Profit 10% 619.54
3. VAT 5% 387.21
TOTAL INDIRECT COST 1,936.06

TOTAL COST (D+E) 8,131.46

UNIT COST 348.99


DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1013(2).b1 Fabricated Metal Roofing Accessory, gauge 24 (Gutters)
COST SHEET I.D. : 1013 (2).b1 PRODUCTION RATE: 10.59 ln.m./hr.
QUANTITY : 12.50 ln.m. NUMBER OF HOURS: 1.18 hr.
Computation : 316.61

Gutter = 12.50 / 2.30


= 5.43 say 5 pcs. (Including Lapping)

Fascia Board = 12.50 x 0.30


= 3.75 / 2.98
= 1.26 say 2 sheets of Hardiflex Board 12mm thk
J-Bolt 6mmØ = 2.30 x 8 pcs/sq.m. (Including Wastages)
= 18 pcs.

Installation Gutter = 5.3125 x 4 personnel


U/H : 5.3125 ln.m./hr = 21.250 ln.m./hr.
Number of Hours = 12.50 / 21.250 = 0.59 hr
Installation FasciaBoard = 0.85 x 4 personnel
U/H : 0.85 pcs./hr = 3.400 pc./hr.
Number of Hours = 2.00 / 3.400 = 0.59 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Pre-painted Pre-formed Gutter ln.m. 12.50 190.00 2,375.00


J-Bolt 6mmØ pcs 18.00 1.50 27.00
Hardiflex Board ½" x 4" x 8" sheet 2.00 1,500.00 3,000.00
Roof Sealant tube 10.00 150.00 1,500.00

SUB-TOTAL (A) 6,902.00


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 2 1.18 68.940 162.70


Unskilled 2 1.18 53.060 125.22

SUB-TOTAL (B) 287.92


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 7,189.92

(E) ADD INDIRECT COST


1. OCM 15% 1,078.49
2. Contractor's Profit 10% 718.99
3. VAT 5% 449.37
TOTAL INDIRECT COST 2,246.85

TOTAL COST (D+E) 9,436.77

UNIT COST 754.94


DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1014(1).b1 Prepainted Metal Sheets, above 0.427 mm (Long SPan)
COST SHEET I.D. : 1014(1).b1 PRODUCTION RATE: 4.26 sq.m./hr.
QUANTITY : 78.00 sq.m. NUMBER OF HOURS: 18.29 hr.
Computation : 316.61
Length of Roofing = 12.50 / 0.985
6.00 = 12.69 say 13 sheets w/6m of length for one side.

J-Bolt 6mmØ = 78.00 x 8 pcs/sq.m. (Including Wastages)


= 624 pcs.
Installation Roofing = 1.0660 x 4 personnel
U/H : 1.0660 m²/hr = 4.26 sq.m./hr.
Number of Hours = 78.00 / 4.26 = 18.29 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST


Pre-Painted Metal Roofing, Gauge 26 Long
sq.m. 78.00 450.00 35,100.00
Span
J-Bolt 6mmØ pcs 624.00 1.50 936.00
Roof Sealant tube 5.00 150.00 750.00

SUB-TOTAL (A) 36,786.00


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 2 18.29 68.940 2,521.83


Unskilled 2 18.29 53.060 1,940.93

SUB-TOTAL (B) 4,462.76


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 41,248.76

(E) ADD INDIRECT COST


1. OCM 15% 6,187.31
2. Contractor's Profit 10% 4,124.88
3. VAT 5% 2,578.05
TOTAL INDIRECT COST 12,890.24

TOTAL COST (D+E) 54,139.00

UNIT COST 694.09


DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1032(1).a Painting Works (Masonry/Concrete)
COST SHEET I.D. : 1032(1).a PRODUCTION RATE: 8.37 sq.m./hr.
QUANTITY : 480.26 sq.m. NUMBER OF HOURS: 57.41 hr.

Computation : 1,977.07

Total Area = 480.26 sq.m.

Neutralizer = 480.26 / 35 + 5% wastages


= 15.00 gals
Patching Compound = 480.26 / 35 + 5% wastages
= 15.00 gals
Flatwall Latex = 480.26 / 35 + 5% wastages
= 15.00 gals
Semi-Gloss Latex = 480.26 / 35 + 5% wastages
= 15.00 x 2 coat
= 30 gals
Tinting Color = 15 gals
Masonry Paint = 2.0913 x 4 personnel
U/H : 2.0913 m²/hr = 8.37 sq.m./hr.
Number of Hours = 480.26 / 8.37
= 57.41 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Concrete Neutalizer gals 15.00 440.00 6,600.00


Patching Compound gals 15.00 90.00 1,350.00
Flatwall Latex Primer gals 15.00 550.00 8,250.00
Semi-Gloss Latex gals 30.00 550.00 16,500.00
Tinting Color pint 15.00 70.00 1,050.00
Paint Roller pcs 10.00 65.00 650.00
Paint Brush pcs 10.00 60.00 600.00

SUB-TOTAL (A) 35,000.00


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 2 57.41 68.940 7,915.69


Unskilled 2 57.41 53.060 6,092.35

SUB-TOTAL (B) 14,008.04


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 49,008.04


(E) ADD INDIRECT COST
1. OCM 15% 7,351.21
2. Contractor's Profit 10% 4,900.80
3. VAT 5% 3,063.00
TOTAL INDIRECT COST 15,315.01

TOTAL COST (D+E) 64,323.05

UNIT COST 133.93


DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1032(1).b Painting Works (Wood)
COST SHEET I.D. : 1032(1).b PRODUCTION RATE: 5.76 sq.m./hr.
QUANTITY : 30.24 sq.m. NUMBER OF HOURS: 5.25 hr.
Computation : 115.88
Total Area = 77.24 sq.m.
Glazing Putty = 77.24 / 35 + 5% wastages
= 3 gals
Flatwall Enamel (Primer) = 77.24 / 35 + 5% wastages
= 3 gals
Enamel Quick Dry (Q.D.E) = 77.24 / 35 + 5% wastages
= 3 gals
Paint Thinner = 77.24 / 35 + 5% wastages
= 3 gals
Tinting Color = 2 pint
Wood Paint = 2.8812 x 2 personnel
U/H : 2.8812 m²/hr = 5.76 sq.m./hr.
Number of Hours = 30.24 / 5.76
= 5.25 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Glazing Putty gals 3.00 550.00 1,650.00


Flatwall Enamel (Primer) gals 3.00 550.00 1,650.00
Enamel Quick Dry (Q.D.E) gals 3.00 600.00 1,800.00
Paint Thinner gals 3.00 250.00 750.00
Tinting Color pint 2.00 70.00 140.00
Paint Roller pcs 5.00 65.00 325.00
Paint Brush pcs 5.00 60.00 300.00

SUB-TOTAL (A) 6,615.00


QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours

Skilled 1 5.25 68.940 361.94


Unskilled 1 5.25 53.060 278.57

SUB-TOTAL (B) 640.51


QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 7,255.51

(E) ADD INDIRECT COST


1. OCM 15% 1,088.33
2. Contractor's Profit 10% 725.55
3. VAT 5% 453.47
TOTAL INDIRECT COST 2,267.35

TOTAL COST (D+E) 9,522.86


UNIT COST 314.91
DETAILED UNIT PRICE ANALYSIS
NAME : IMPROVEMENT, REPAIR AND REHABILITATION OF MULTIPURPOSE BUILDING
LOCATION : BARANGAY SAN ISIDRO, TALISAY CITY
PAY ITEMS : 1036(1).a Polycarbonate Sheet (Roof w/ framing)
COST SHEET I.D. : 1036(1).a PRODUCTION RATE: 2.33 kgs./hr.
QUANTITY : 7.00 sheets NUMBER OF HOURS: 3.00 hr.

Computation : 6,075.72
Polycarbonate Sheet : 1 set
= 1.00 x 20
= 20.00 x 1 set
= 20.00 / 2.88
= 6.94 say 7 sheets

2" x 6" x 1.0mm =


Rectangular Tube =
Framing = 50.60 / 6
= 8.43 say 9 lengths

Welding Rod = 167.85 / 1,000 x 30


= 5.04 say 5 kgs
Red Lead = 21.60 / 25 + 5% wastages
= 1 gals
Fab/Erect/Install of Frame = 17.00 x 4 personnel
U/H : 17 kg/hr = 68.00 kg./hr.
Number of Hours = 167.85 / 68.00
= 2.47 hr
Painting of Angle = 4.25 x 4 personnel
U/H : 4.25 pcs./hr = 17.00 pcs./hr
Number of Hours = 9.00 / 17.000
= 0.53 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Polycarbonate Sheet Sheets 7 900 6,300.00


2" x 6" x 1.0mm Rectangular Tube pc 9 1336.30 12,026.70
1" x 3" Flat Bar for Canopy Support pc 2 2278.10 4,556.20
Turn Buckle pc 2 500.00 1,000.00
Welding Rod ½"Ø E-70 Series kg 5.00 67.00 335.00
Acetylene kg 5.00 80.00 400.00
Oxygen kg 5.00 45.00 225.00
Red Lead Primer Oxide gal 1.00 570.00 570.00

SUB-TOTAL (A) 25,412.90


QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours

Skilled 2 3.00 66.540 399.24


Unskilled 2 3.00 51.300 307.80

SUB-TOTAL (B) 707.04


QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours

Welding Machine AC Output 300Amps 2 2.47 187.00 923.78

SUB-TOTAL (C) 923.78

(D) TOTAL DIRECT COST : (A+B+C) 27,043.72


(E) ADD INDIRECT COST
1. OCM 15% 4,056.56
2. Contractor's Profit 10% 2,704.37
3. 5% VAT 5% 1,690.23
TOTAL INDIRECT COST 8,451.16

TOTAL COST (D+E) 35,494.88

UNIT COST 5,070.70


DETAILED UNIT PRICE ANALYSIS

NAME : IMPROVEMENT, REPAIR AND REHABILITATION OF MULTIPURPOSE BUILDING


LOCATION : BARANGAY SAN ISIDRO, TALISAY CITY
PAY ITEMS : 1039(2) Stone Bricks (Cladding)
COST SHEET I.D. : 1039(2) PRODUCTION RATE: 1.89
QUANTITY : 8.30 m 2
NUMBER OF HOURS: 4.39

Computation : 46.71

Columns : 1.50 x 3 x 12
Paraphet 2.00 x 1.90 x 1

Total Cladding Area = 8.30 sq.m.

Installation = 0.2363 x 8 personnel


U/H : 0.2363 m²/hr = 1.8904 sq.m./hr.

Number of Hours = 8.30 / 1.8904


= 4.39 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE

Stone Bricks (Cladding) m² 8.30 1,350.00

SUB-TOTAL (A)
QUANTITY
(B) LABOR COST Hourly Rate
No. Of Personnel Total Hours

Skilled 8 4.39 66.540

SUB-TOTAL (B)
QUANTITY
(C) EQUIPMENT COST Hourly Rate
No. Of Equipment Total Hours

NONE

SUB-TOTAL (C)

(D) TOTAL DIRECT COST : (A+B+C)


(E) ADD INDIRECT COST
1. OCM 15%
2. Contractor's Profit 10%
3. VAT 5%
TOTAL INDIRECT COST
TOTAL COST (D+E)

UNIT COST
LED UNIT PRICE ANALYSIS

sq.m./hr.
hr.

pc/pcs
pc/pcs

TOTAL COST

11,205.00

11,205.00

TOTAL COST

2,336.88

2,336.88

TOTAL COST

13,541.88

2,031.28
1,354.19
846.37
4,231.84
17,773.72

2,141.41
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1047(2)a Structural Steel, Trusses
COST SHEET I.D. : 1047(2)a PRODUCTION RATE: 58.64
QUANTITY : 1,702.20 kg NUMBER OF HOURS: 29.03

Computation : 6,075.72
HT-1 : 6 set

2" x 2" x 1/4" = 24.782 x 2 no. of angle bar


Angle Bar = 49.564 x 6 set
Top & Bot Chord = 297.38 / 6
King Post = 49.56 say 50 lengths

1 1/2" x 1 1/2" x 1/4" = 13.525 x 1 no. of angle bars


Angle Bar = 13.525 x 6 set
Web Members = 81.15 / 6
= 13.53 say 14 lengths

1 " x 1 " x 1/4" = 24.000 x 1 no. of angle bars


Fascia Board Frame = 24.000 x 1 set
= 24.00 / 6
= 4.00 say 4 lengths

Welding Rod = 1,702.20 / 1,000 x 30


= 51.07 say 51 kgs
Red Lead = 75.17 / 25 + 5%
= 4 gals
Fab/Erect/Install of Angle = 17.00 x 4 personnel
U/H : 17 kg/hr = 68.00 kg./hr.
Number of Hours = 1,702.20 / 68.00
= 25.03 hr
Painting of Angle = 4.25 x 4 personnel
U/H : 4.25 pcs./hr = 17.00 pcs./hr
Number of Hours = 68.00 / 17.000
= 4.00 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE

2" x 2" x 1/4" (Angle Bar) kg 1,341.00 53.00


1 1/2" x 1 1/2" x 1/4" (Angle Bar) kg 305.76 53.00
1" x 1" x 1/4" (Angle Bar) kg 55.44 53.00
Red Lead Primer Oxide gal 4.00 570.00
Welding Rod ½"Ø E-70 Series kg 51.00 138.33
Acetylene kg 3.00 80.00
Oxygen kg 3.00 45.00

SUB-TOTAL (A)
QUANTITY
(B) LABOR COST Hourly Rate
No. Of Personnel Total Hours

Skilled 2 29.03 68.940


Unskilled 2 29.03 53.060

SUB-TOTAL (B)
QUANTITY
(C) EQUIPMENT COST Hourly Rate
No. Of Equipment Total Hours

Welding Machine AC Output 300Amps 2 25.03 187.00

SUB-TOTAL (C)

(D) TOTAL DIRECT COST : (A+B+C)


(E) ADD INDIRECT COST
1. OCM 15%
2. Contractor's Profit 10%
3. 5% VAT 5%
TOTAL INDIRECT COST

TOTAL COST (D+E)

UNIT COST
ED UNIT PRICE ANALYSIS

kgs./hr.
hr.

wastages

TOTAL COST

71,073.00
16,205.28
2,938.32
2,280.00
7,054.83
240.00
135.00

99,926.43

TOTAL COST

4,002.66
3,080.66

7,083.32

TOTAL COST

9,361.22

9,361.22

116,370.97

17,455.65
11,637.10
7,273.19
36,365.94

152,736.91

89.73
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1047(2)b Structural Steel, Purlins
COST SHEET I.D. : 1047(2)b PRODUCTION RATE: 17.09 kgs./hr.
QUANTITY : 226.26 kg NUMBER OF HOURS: 13.24 hr.
Computation : 3,366.18 ### 4,071.69
Roof Purlins (HT-1)
1" x 1" x 1/4" = 0.075 x 54
Clip Angle = 4.05 / 6
= 0.68 say 1 lengths

LC 2" x 4" x 1.0mm thk. C- = 13.00 x 9


PURLINS = 117.00 / 6.00
= 19.50 say 20 lengths

Welding Rod = 226.26 / 1,000 x 30


= 6.79 say 7.00 kgs
Red Lead = 54.48 / 25 + 5% wastages
= 3 gals
Fab/Erect/Install of Purlins = 4.50 x 4 personnel
U/H : 4.50 kg/hr = 18.00 kg./hr.
Number of Hours = 212.40 / 18.00
= 11.80 hr
Painting of Purlins = 4.25 x 4 personnel
U/H : 4.25 pcs./hr = 17.00 pcs./hr
Number of Hours = 20.00 / 17.000
= 1.18 hr
Fab/Erect/Install of Angle = 17.00 x 4 personnel
U/H : 17 kg/hr = 68.00 kg./hr.
Number of Hours = 13.86 / 68.00
= 0.20 hr
Painting of Angle = 4.25 x 4 personnel
U/H : 4.25 pcs./hr = 17.00 pcs./hr
Number of Hours = 1.00 / 17.000
= 0.06 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST


LC 2" x 4" x 1.0mm thk. kg 212.40 53.00 11,257.20
Angle Bar 25 x 25 x 6mm kg 13.86 53.00 734.58
Acetylene kg 3.00 80.00 240.00
Oxygen kg 3.00 45.00 135.00
Red Lead Primer Oxide gal 3.00 570.00 1,710.00
SUB-TOTAL (A) 14,076.78
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
Skilled 2 13.24 68.940 1,825.53
Unskilled 2 13.24 53.060 1,405.03
SUB-TOTAL (B) 3,230.56
QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate
Welding Machine AC Output 300Amps 2 12.00 187.00 4,488.00
SUB-TOTAL (C) 4,488.00
(D) TOTAL DIRECT COST : (A+B+C) 21,795.34
(E) ADD INDIRECT COST
1. OCM 15% 3,269.30
2. Contractor's Profit 10% 2,179.53
3. 5% VAT 5% 1,362.21
TOTAL INDIRECT COST 6,811.04
TOTAL COST (D+E) 28,606.38
UNIT COST 126.43
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1047(7)b Metal Structure Accessories, Sagrods
COST SHEET I.D. : 1047(7)b PRODUCTION RATE: 18.00 kgs./hr.
QUANTITY : 22.32 kg NUMBER OF HOURS: 1.24 hr.
Computation : 3,366.18 ### 4,071.69

Sag Rods 10mmØ = 5.360 x 6


= 32.16 / 6
= 6 lengths
Welding Rod = 22.32 / 1,000 x 30
= 0.67 say 1.00 kgs
Fab/Erect/Install of Bar = 4.50 x 4 personnel
U/H : 4.50 kg/hr = 18.00 kg./hr.
Number of Hours = 22.32 / 18.00
= 1.24 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST


Sag Rods and Cross Bracings kgs 22.32 41.00 915.12
Welding Rod ½"Ø E-70 Series kg 1.00 150.00 150.00
Acetylene kg 3.00 80.00 240.00
Oxygen kg 3.00 45.00 135.00
SUB-TOTAL (A) 1,440.12
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
Skilled 2 1.24 68.940 170.97
Unskilled 2 1.24 53.060 131.59
SUB-TOTAL (B) 302.56
QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate
Welding Machine AC Output 300Amps 2 1.24 187.00 463.76
SUB-TOTAL (C) 463.76
(D) TOTAL DIRECT COST : (A+B+C) 2,206.44
(E) ADD INDIRECT COST
1. OCM 15% 330.97
2. Contractor's Profit 10% 220.64
3. 5% VAT 5% 137.90
TOTAL INDIRECT COST 689.51
TOTAL COST (D+E) 2,895.95
UNIT COST 129.75
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1047(3)c Metal Structure Accessories, Turnbuckle
COST SHEET I.D. : 1047(3)c PRODUCTION RATE: 80.00 kgs./hr.
QUANTITY : 12.00 each NUMBER OF HOURS: 0.15 hr.

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST


Turn Buckle 5/8" pc 12.00 190.00 2,280.00
SUB-TOTAL (A) 2,280.00
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
Skilled 2 0.15 68.940 20.68
Unskilled 2 0.15 53.060 15.92
SUB-TOTAL (B) 36.60
QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate
Minor Tools (10% of Labor Cost) 3.66
SUB-TOTAL (C) 3.66
(D) TOTAL DIRECT COST : (A+B+C) 2,320.26
(E) ADD INDIRECT COST
1. OCM 15% 348.04
2. Contractor's Profit 10% 232.03
3. 5% VAT 5% 145.02
TOTAL INDIRECT COST 725.09
TOTAL COST (D+E) 3,045.35
UNIT COST 253.78
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1047(4) Metal Structure Accessories, Cross Bracing
COST SHEET I.D. : 1047(4) PRODUCTION RATE: 18.00 kgs./hr.
QUANTITY : 43.20 kg NUMBER OF HOURS: 2.40 hr.
Computation : 3,366.18 ### 4,071.69

Cross Bar 12mmØ = 3.60 x 2 x 6


= 43.20 / 6
= 8 lengths
Welding Rod = 43.20 / 1,000 x 30
= 1.30 say 1.00 kgs
Fab/Erect/Install of Bar = 4.50 x 4 personnel
U/H : 4.50 kg/hr = 18.00 kg./hr.
Number of Hours = 43.20 / 18.00
= 2.40 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST


12mmØ x 6.00 m Deformed Bars kgs 43.20 41.00 1,771.20
Welding Rod ½"Ø E-70 Series kg 1.00 150.00 150.00
Acetylene kg 2.00 80.00 160.00
Oxygen kg 2.00 45.00 90.00
SUB-TOTAL (A) 2,171.20
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
Skilled 2 2.40 68.940 330.91
Unskilled 2 2.40 53.060 254.69
SUB-TOTAL (B) 585.60
QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate
Welding Machine AC Output 300Amps 2 2.40 187.00 897.60
SUB-TOTAL (C) 897.60
(D) TOTAL DIRECT COST : (A+B+C) 3,654.40
(E) ADD INDIRECT COST
1. OCM 15% 548.16
2. Contractor's Profit 10% 365.44
3. 5% VAT 5% 228.40
TOTAL INDIRECT COST 1,142.00
TOTAL COST (D+E) 4,796.40
UNIT COST 111.03
)
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : B.5 Project Billboard / Signboard
COST SHEET I.D. : B.5 PRODUCTION RATE: 2.00 set/Project
QUANTITY : 2.00 each NUMBER OF HOURS:

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Tarpaulin ft2 32.00 P 50.00 P 1,600.00


Brace (Lumber) bd.ft. 37.00 P 40.00 P 1,480.00
Common Wire Nails kgs. 2.00 P 35.00 P 70.00
Marine Plywood, ¼ x 4 x 8 pc. 2.00 P 350.00 P 700.00

SUB-TOTAL (A) 3,850.00


QUANTITY
(B) LABOR COST Daily Rate TOTAL COST
No. Of Personnel Total Hours

Skilled 1 8 68.940 551.52


Unskilled 1 8 53.060 424.48

SUB-TOTAL (B) 976.00


QUANTITY
(C) EQUIPMENT COST Daily Rate TOTAL COST
No. Of Equipment Total days

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 4,826.00

(E) ADD INDIRECT COST


1. OCM 15% 723.90
2. Contractor's Profit 10% 482.60
3. 5% VAT 5% 301.63
TOTAL INDIRECT COST 1,508.13

TOTAL COST (D+E) 6,334.13

UNIT COST 3,167.07


DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : B.7 Occupational Safety and Health Program
COST SHEET I.D. : B.7 PRODUCTION RATE:
QUANTITY : 1.00 month NUMBER OF HOURS:
1,680.00

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Hard Hat pcs 4.00 170.00 680.00


Reflectorized Safety Vest pcs 4.00 295.00 1,180.00
Safety Shoes pcs 4.00 850.00 3,400.00
Gloves, PVC-Coated Knitwrist pcs 4.00 75.00 300.00

SUB-TOTAL (A) 5,560.00


QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours

SUB-TOTAL (B) -
QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 5,560.00

(E) ADD INDIRECT COST


1. OCM 0% -
2. Contractor's Profit 10% 556.00
3. 5% VAT 5% 305.80
TOTAL INDIRECT COST 861.80

TOTAL COST (D+E) 6,421.80

UNIT COST 6,421.80


DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : B.9 Mobilization / Demobilization
COST SHEET I.D. : B.9
QUANTITY : 1.00 L.S.
14.00

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

NONE

SUB-TOTAL (A) -
QUANTITY
(B) LABOR COST Daily Rate TOTAL COST
No. Of Personnel Total Day

NONE

SUB-TOTAL (B) -
QUANTITY
(C) EQUIPMENT COST Daily Rate TOTAL COST
No. Of Equipment Total Day

Service Trucck 5mt 1 3,776.00

SUB-TOTAL (C) 3,776.00

(D) TOTAL DIRECT COST : (A+B+C) 3,776.00

(E) ADD INDIRECT COST


1. OCM -
2. Contractor's Profit -
3. 5% VAT 5% 188.80
TOTAL INDIRECT COST 188.80

TOTAL COST (D+E) 3,964.80

UNIT COST 3,964.80


DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 801 (1) Removal of Structures and Obstruction
COST SHEET I.D. : 801 (1) PRODUCTION RATE: 0.06 each / hr
QUANTITY : 1.00 L.S. NUMBER OF HOURS: 17.77 hr

Computation : 26.32

Removal of Existing Roof = 4.03 x 4.50


= 18.11 sq.m.
Removal of Existing Ceiling = 4.03 x 4.50
= 18.11 sq.m.

Correction of Adjacent Roof = 1.00 x 4.50


= 4.50 sq.m.

Correction Adjacent Ceiling = 1.00 x 4.50


= 4.50 sq.m.

Total Area = 45.22 sq.m.


Demolition of Structures = 0.9894 x 6 personnel
U/H : 0.9894m2/hr = 5.940 m³/hr
Number of Hours = 45.22 / 5.940 = 7.61 hr.
- - - - - -- - - - - - - - - - -----------------------------------------
Removal of Existing Tiles = 3.500 x 3.030
Total Area = 10.61 sq.m.

Demolition of Structures = 0.1950 x 6 personnel


U/H : 0.195m2/hr = 1.170 m³/hr
Number of Hours = 10.61 / 1.170 = 9.07 hr.
- - - - - -- - - - - - - - - - -----------------------------------------
Existing Concrete Column 1 = 0.20 x 0.20 x 2.20
= 0.09 x 2 Columns
= 0.18 cu.m.

Existing Concrete Column 2 = 0.20 x 0.20 x 0.60


= 0.02 x 2 Columns
= 0.04 cu.m.

Existing Concrete Wall 1 = 0.20 x 0.60 x 4.50


= 0.54 cu.m.

Existing Concrete Wall 2 = 0.20 x 0.60 x 10.40


= 1.25 cu.m.

Existing Concrete Wall 3 = 0.20 x 0.40 x 2.50


To be replaced by a Column = 0.20 cu.m.

Total Volume = 2.210 cu.m.


Demolition of Structures = 0.4763 x 6 personnel
U/H : 0.4763m3/hr = 2.860 m³/hr
Number of Hours = 2.21 / 2.860 = 0.77 hr.
- - - - - -- - - - - - - - - - -----------------------------------------
Existing Grills = 0.60 x 37.00
Main Members = 22.200 x 1.45 kg/m
= 32.19 kgs
Denolition of Trusses = 17.00 x 6 personnel
U/H : 17 kg/hr = 102.00 kg./hr.
Number of Hours = 32.19 / 102.00 = 0.32 hr.

DETAILED UNIT PRICE ANALYSIS


NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 801 (1) Removal of Structures and Obstruction
COST SHEET I.D. : 801 (1) PRODUCTION RATE: 0.06 each / hr
QUANTITY : 1.00 L.S. NUMBER OF HOURS: 17.77 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

SUB-TOTAL (A) -
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Unskilled 6 17.77 53.060 5,657.26

SUB-TOTAL (B) 5,657.26


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

Minor Tools (5% of Labor) 282.86 282.86

SUB-TOTAL (C) 282.86

(D) TOTAL DIRECT COST : (A+B+C) 5,940.12


(E) ADD INDIRECT COST
1. OCM 15% 891.02
2. Contractor's Profit 10% 594.01
3. VAT 5% 371.26
TOTAL INDIRECT COST 1,856.29

TOTAL COST (D+E) 7,796.41


UNIT COST 7,796.41
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1003(8) Flooring (Wood)-Plywood Marine (0.019 x 1.4m x 2.44m)
COST SHEET I.D. : 1003(8)
QUANTITY : bd.ft. NUMBER OF HOURS: 0.00 hr.
Computation :
= 11.50 x 3.70
= 42.55 / 2.98 plywood / m²
No. of Plywood = 15 x 3.00 = 45.00
Assorted C.W.Nails = 45.00 / 2,500 x 45
Note: 1 keg = 45 kgs = 1.00 kg

Installation = 0.2725 x 6 personnel


U/H : 0.2725 m²/hr = 1.64 m²/hr
Number of Hours = 45.00 / 1.64 = 0.00 hr.

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Assorted C.W. Nails kgs 1.00 31.00 31.00


Plywood Marine (0.019m x 1.4m x2.44m) pcs 15.00 1,050.00 15,750.00

SUB-TOTAL (A)
QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours

Skilled 2 0.00 64.730 -


Unskilled 4 0.00 49.770 -

SUB-TOTAL (B)
QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours

NONE

SUB-TOTAL (C)

(D) TOTAL DIRECT COST : (A+B+C) -

(E) ADD INDIRECT COST


1. OCM 15% -
2. Contractor's Profit 10% -
3. VAT 5% -
TOTAL INDIRECT COST -
TOTAL COST (D+E) -
UNIT COST
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1047(1) Structural Steel (Steel Stairs)
COST SHEET I.D. : 1047(1)
QUANTITY : L.S. NUMBER OF HOURS: 7.11

Computation : 6,075.72
Landing : 3 set
3" x 3" x 1/4" = 4.00 x 1 no. of angle bar
Angle Bar = 4.00 x 3 set
= 12.00 / 6
= 2.00 say 2 lengths

Slanting Angle Beam : 2 set


3" x 3" x 1/4" = 2.05 x 1 no. of angle bar
Angle Bar = 2.05 x 2 set
= 4.10 / 6
= 0.68 say 1 lengths

Rise and Tread Framing : 12 set


2" x 2" x 1/4" = 3.80 x 1 no. of angle bar
Angle Bar (Edge) = 3.80 x 12 set
= 45.60 / 6
= 7.60 say 8 lengths

Rise and Tread Framing : 12 set


1 1/2" x 1 1/2" x 1/4" = 0.40 x 1 no. of angle bar
Angle Bar (Mid) = 0.40 x 12 set
= 4.80 / 6
= 0.80 say 1 lengths

Rise and Tread Framing : 2 set


2" x 2" x 1/4" = 5.04 x 1 no. of angle bar

Angle Bar (Edge) - Diagonal


= 5.04 x 2 set
= 10.08 / 6
= 1.68 say 2 lengths

Rise and Tread Framing : 2 set


1 1/2" x 1 1/2" x 1/4" = 0.40 x 1 no. of angle bar
Angle Bar (Mid) - Diagonal = 0.40 x 2 set
= 0.80 / 6
= 0.13 say 1 lengths

G.I. Columns : 2 set


GI Pipe Schedule 40 Dia (76mm) = 2.80 x 2
= 5.60 / 6
= 0.93 say 1 lengths

G.I. Columns : 6 set


GI Pipe Schedule 40 Dia (76mm) = 1.40 x 6
= 8.40 / 6
= 1.40 say 2 lengths

Milled Steel Plates : 9 set


Checkered FY36 = 0.20 x 1
Rectangular = 0.20 x 9
= 1.80 sq.m.

Milled Steel Plates : 3 set


Checkered FY36 = 1.00 x 1
Square/Triangular = 1.00 x 3
= 3.00 sq.m.
Total Area = 1.80 + 3.00
Checkered FY36 (12.5mm) = 4.80 sq.m.

=
Welding Rod = 423.92 / 1,000 x 30
= 12.72 say 13 kgs
Red Lead = 19.22 / 25 + 5%
= 1 gals
Fab/Erect/Install of Angle = 17.00 x 4 personnel
U/H : 17 kg/hr = 68.00 kg./hr.
Number of Hours = 423.92 / 68.00

DETAILED UNIT PRICE ANALYSIS


NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1047(1) Structural Steel (Steel Stairs)
COST SHEET I.D. : 1047(1)
QUANTITY : 1.00 L.S. NUMBER OF HOURS: 0.00

= 6.23 hr
Painting of Angle = 4.25 x 4 personnel
U/H : 4.25 pcs./hr = 17.00 pcs./hr
Number of Hours = 15.00 / 17.000
= 0.88 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE

3" x 3" x 1/4" (Angle Bar) kg 118.64 53.00


2" x 2" x 1/4" (Angle Bar) kg 265.80 53.00
1 1/2" x 1 1/2" x 1/4" (Angle Bar) kg 39.48 53.00
Milled Steel, Checkered FY36 (6.0mm) kg 150.70 45.00
GI Pipe Schedule 40 Dia (76mm) pc 3.00 2,003.00
Red Lead Primer Oxide gal 1.00 570.00
Welding Rod ½"Ø E-70 Series kg 13.00 138.33
Acetylene kg 5.00 80.00
Oxygen kg 5.00 45.00

SUB-TOTAL (A)
QUANTITY
(B) LABOR COST Hourly Rate
No. Of Personnel Total Hours

Skilled 2 7.11 68.940


Unskilled 2 7.11 53.060

SUB-TOTAL (B)
QUANTITY
(C) EQUIPMENT COST Hourly Rate
No. Of Equipment Total Hours

Welding Machine AC Output 300Amps 2 6.23 187.00

SUB-TOTAL (C)

(D) TOTAL DIRECT COST : (A+B+C)


(E) ADD INDIRECT COST
1. OCM 15%
2. Contractor's Profit 10%
3. 5% VAT 5%
TOTAL INDIRECT COST

TOTAL COST (D+E)

UNIT COST
ED UNIT PRICE ANALYSIS
wastages

ED UNIT PRICE ANALYSIS

TOTAL COST

6,287.92
14,087.40
2,092.44
6,781.65
6,009.00
570.00
1,798.29
400.00
225.00

TOTAL COST

980.33
754.51

TOTAL COST

2,330.02

(0.18)
-
(0.01)
(0.19)

(0.19)
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1722(2) Railings
COST SHEET I.D. : 1722(2)
QUANTITY : ln.m. NUMBER OF HOURS: 4.23 hr.

Computation :

50mmØ G.I.Pipe = 21.64 x 1 no. of stair


Stair Rail = 21.64 / 6.00
= 3.61 say 4 lengths

Welding Rod = 56.80 / 1,000 x 30


= 1.70 say 2.00 kgs
Red Lead = 3.77 / 25 + 10% wastages
= 1 gals
Fab/Install of Railings = 16.855 x 2 personnel
U/H : 16.855 kg/hr = 33.71 kg./hr.
Number of Hours = 56.80 / 33.71
= 1.68 hr
Painting of Railings = 4.25 x 2 personnel
U/H : 4.25 ln.m./hr = 8.50 ln.m./hr.
Number of Hours = 21.64 / 8.50
= 2.55 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

G.I. Pipe, 50mmØ length 4.00 1,500.00 6,000.00


Welding Rod ½"Ø E-70 Series kg 2.00 138.33 276.66
Acetylene kg 5.00 80.00 400.00
Oxygen kg 5.00 45.00 225.00
Red Lead Primer Oxide gal 1.00 570.00 570.00

SUB-TOTAL (A)
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 1 4.23 68.940 291.62


Unskilled 1 4.23 53.060 224.44

SUB-TOTAL (B)
QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

Welding Machine DC Output 500Amps 1 1.68 391.00 658.82

SUB-TOTAL (C)

(D) TOTAL DIRECT COST : (A+B+C) -

(E) ADD INDIRECT COST


1. OCM 15% -
2. Contractor's Profit 10% -
3. VAT 5% -
TOTAL INDIRECT COST -

TOTAL COST (D+E) -

UNIT COST
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1001(6).b Catch Basin
COST SHEET I.D. : 1001(6).b
QUANTITY : 1.00 each NUMBER OF HOURS: 2.19 hr.

Computation : 12.00

Excavation = 0.60 x 0.60 x 0.70


Catch Basin = 0.25 x 1 no. of catch basin
= 0.25 cu.m.

Concrete Works = 0.10 x 0.50 x 0.50 +


R.C. T/B Slab 0.10 x 0.50 x 0.50
= 0.05 x 1 no. of catch basin
= 0.05 cu.m.
No. Of Bags (Cement) = 0.05 x 9.00 = 1.00 bag
No. Of Volume (Sand) = 0.05 x 0.50 = 1.00 cu.m.
No. Of Volume(Gravel) = 0.05 x 1.00 = 1.00 cu.m.

Rein. Steel Works = 0.50 / 0.23 x 0.50 +


Top Slab 0.50 / 0.23 x 0.50
= 2.17 / 6.00 x 1
= 1 lengths of 10mmØ x 6.00 m Deformed Bars
= 0.50 / 0.23 x
0.50 / 0.23 x 1
= 5 x 0.30 / 53.00
= 0.10 kgs of G.I. Tie Wire
Bottom Slab = 0.50 / 0.23 x 0.50 +
0.50 / 0.23 x 0.50
= 2.17 / 6.00 x 1
= 1 lengths of 10mmØ x 6.00 m Deformed Bars
= 0.50 / 0.23 x
0.50 / 0.23 x 1
= 5 x 0.30 / 53.00
= 0.10 kgs of G.I. Tie Wire

Total No. Of CHB 6" = 1.00 x 12.50 + 1% for breakages


= 13 pcs
Cement (Mortar) = 1.00 x 0.763
Class C = 0.76 say 1 bag
Sand (Mortar) = 1.00 x 0.0844
Class C = 0.08 say 1 cu.m.
Reinforcing Steel : 600mm x 600mm Spacing of Reinforcing Steel
(for Horizontal Bars) = 1.00 x 2.13 = 2.13
(forVertical Bars) = 1.00 x 2.15 = 2.15
4.28 meters
= 4.28 / 6
= 0.71 say 1 lengths of 10mmØ x 6.00 m Deformed Bars
kgs of G.I. Tie Wire = 1.00 x 0.032
= 0.00 kgs

Excavation (manual) = 0.125 x 3 personnel


U/H : 0.125 m³/hr = 0.38 m³/hr
Number of Hours = 0.25 / 0.38 = 0.67 hr.

Concreting :
Manual Mix = 0.0513 x 3 personnel
U/H : 0.0513 m³/hr = 0.154 m³/hr
Number of Hours = 0.05 / 0.154 = 0.32 hr.
Placing of Concrete = 0.415 x 3 personnel
U/H : 0.415 m³/hr = 1.245 m³/hr
Number of Hours = 0.05 / 1.245 = 0.04 hr.
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1001(6).b Catch Basin
COST SHEET I.D. : 1001(6).b
QUANTITY : 1.00 each NUMBER OF HOURS: 2.19 hr.

Fabrication = 8.50 x 3 personnel


U/H : 8.50 kg/hr = 26 kgs/hr
Number of Hours = 11.11 / 26 = 0.44 hr
Placing = 11.9675 x 3 personnel
U/H : 11.9675 kg/hr = 35.903 kgs/hr
Number of Hours = 11.11 / 35.903
= 0.31 x 30% - No. Of hours for placing will be added
= 0.09 hr for the total no. Of hours.
CHB Laying = 0.5313 x 3 personnel
U/H : 0.5313 m²/hr = 1.59 sq.m./hr.
Number of Hours = 1.00 / 1.59 = 0.63 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

CHB 6" pcs 13.00 16.00 208.00


Cement, Portland bags 2.00 234.33 468.66
Sand, Washed cu.m. 2.00 1,100.00 2,200.00
Gravel cu.m. 1.00 1,100.00 1,100.00
10mmØ x 6.00 m Deformed Bars kgs 11.11 41.00 455.51
# 16 Tie Wire G.I. kgs 0.20 50.00 10.00

SUB-TOTAL (A) 4,442.17


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Construction Foreman 1 2.19 91.920 201.63


Skilled 1 2.19 66.540 145.96
Unskilled 2 2.19 51.300 225.06

SUB-TOTAL (B) 572.65


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 5,014.82


(E) ADD INDIRECT COST
1. OCM 15% 752.22
2. Contractor's Profit 10% 501.48
3. VAT 5% 313.43
TOTAL INDIRECT COST 1,567.13

TOTAL COST (D+E) 6,581.95

UNIT COST 6,581.95


DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1001(9) Storm Drainage and Downspout
COST SHEET I.D. : 1001(9)
QUANTITY : 1.00 L.S. NUMBER OF HOURS: 52.06 hr.
Computation :
Installation of PVC3"Ø = 0.900 x 4 personnel
U/H : 0.900 pc/hr = 3.60 pc./hr.
Number of Hours = 18.00 / 3.60
= 5.00 hr

No. Of Bags (Cement) = 10.00 x 0.39 = 4.00 bag


No. Of Volume (Sand) = 10.00 x 0.07 = 0.70 cu.m.
Laying of 6"Ø RCPC = 0.0531 x 4 personnel
U/H : 0.0531 ln.m./hr = 0.21 ln.m./hr.
Number of Hours = 10.00 / 0.21
= 47.06 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Downspout : 6 DS
PVC Pipes, 3"Ø length 18.00 440.00 7,920.00
PVC Elbow, 3"Ø x 90° pcs 6.00 52.00 312.00
PVC Elbow, 3"Ø x 45° pcs 12.00 40.00 480.00
Solvent Cement pcs 7.00 200.00 1,400.00

Storm Drainage
RCPC, 6"Ø or equivalent pcs 10.00 400.00 4,000.00
Cement, Portland bags 4.00 234.33 937.32
Sand, Washed cu.m. 0.70 1,100.00 770.00

SUB-TOTAL (A) 15,819.32


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 2 52.06 66.540 6,928.14


Unskilled 2 52.06 51.300 5,341.36

SUB-TOTAL (B) 12,269.50


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 28,088.82


(E) ADD INDIRECT COST
1. OCM 15% 4,213.32
2. Contractor's Profit 10% 2,808.88
3. VAT 5% 1,755.55
TOTAL INDIRECT COST 8,777.75

TOTAL COST (D+E) 36,866.57

UNIT COST -
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1001(7).b Septic Vault "Type E"
COST SHEET I.D. : 1001(7).b
QUANTITY : 1.00 each NUMBER OF HOURS: 40.58 hr.

Computation :

Excavation = 1.20 x 4.30 x 1.60


Septic Tank = 8.26 cu.m.

Concrete Works = 0.10 x 1.20 x 4.3000 +


R.C. T/B Slab 0.15 x 1.20 x 4.3000
= 1.29 cu.m.
R.C. Wall = 0.10 x 13.40 x 2.375
= 3.18 cu.m.
R.C. Beam = 0.15 x 0.30 x 1.20
= 0.05 cu.m.
No. Of Bags (Cement) = 4.52 x 9.00 = 41.00 bag
No. Of Volume (Sand) = 4.52 x 0.50 = 3.00 cu.m.
No. Of Volume(Gravel) = 4.52 x 1.00 = 5.00 cu.m.

Rein. Steel Works = 1.20 / 0.20 x 4.30 +


Top Slab 4.30 / 0.20 x 1.20
= 51.60 / 6.00
= 9 lengths of 10mmØ x 6.00 m Deformed Bars
= 1.20 / 0.20 x
4.30 / 0.20
= 129 x 0.30 / 53.00
= 0.70 kgs of G.I. Tie Wire
Bottom Slab = 1.20 / 0.30 x 4.30 +
4.30 / 0.30 x 1.20
= 34.40 / 6.00
= 6 lengths of 10mmØ x 6.00 m Deformed Bars
= 1.20 / 0.30 x
4.30 / 0.30
= 57 x 0.30 / 53.00
= 0.30 kgs of G.I. Tie Wire
Wall = 13.40 / 0.20 x 2.38 +
2.38 / 0.20 x 13.40
= 318.25 / 6.00
= 53 lengths of 10mmØ x 6.00 m Deformed Bars
= 13.40 / 0.20 x
2.38 / 0.20
= 796 x 0.30 / 53.00
= 4.60 kgs of G.I. Tie Wire
Beam = 4 x 1.20
Horizontal Bars = 5 / 6.00
= 1 lengths of 16mmØ x 6.00 m Deformed Bars
Beam = 1.20 / 0.20 x 0.90
Stirrups = 5.40 / 6
= 1 lengths of 10mmØ x 6.00 m Deformed Bars
= 1.20 / 0.20 x 4
= 24.00 x 0.30 / 53
= 0.20 kgs of G.I. Tie Wire
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1001(7).b Septic Vault "Type E"
COST SHEET I.D. : 1001(7).b
QUANTITY : 1.00 each NUMBER OF HOURS: 40.58 hr.

Excavation (manual) = 0.125 x 5 personnel


U/H : 0.125 m³/hr = 0.63 m³/hr
Number of Hours = 8.26 / 0.63 = 13.22 hr.

Concreting :
Manual Mix = 0.0513 x 5 personnel
U/H : 0.0513 m³/hr = 0.257 m³/hr
Number of Hours = 4.52 / 0.257 = 17.62 hr.
Placing of Concrete = 0.415 x 5 personnel
U/H : 0.415 m³/hr = 2.075 m³/hr
Number of Hours = 4.52 / 2.075 = 2.18 hr.

Fabrication = 8.50 x 5 personnel


U/H : 8.50 kg/hr = 43 kgs/hr
Number of Hours = 264.92 / 43 = 6.23 hr
Placing = 11.9675 x 5 personnel
U/H : 11.9675 kg/hr = 59.838 kgs/hr
Number of Hours = 264.92 / 59.838
= 4.43 x 30% - No. Of hours for placing will be added
= 1.33 hr for the total no. Of hours.

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Cement, Portland bags 41.00 234.33 9,607.53


Sand, Washed cu.m. 3.00 1,100.00 3,300.00
Gravel cu.m. 5.00 1,100.00 5,500.00
16mmØ x 6.00 m Deformed Bars kgs 9.48 41.00 388.68
10mmØ x 6.00 m Deformed Bars kgs 255.44 41.00 10,473.04
# 16 Tie Wire G.I. kgs 5.80 50.00 290.00
PVC Tee, Single Branch, 4" pcs 3.00 137.00 411.00
PVC Cleanout w/ Plug & Sealing Ring, 4" pcs 2.00 62.00 124.00

SUB-TOTAL (A) 30,094.25


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Construction Foreman 1 40.58 91.920 3,730.27


Skilled 1 40.58 66.540 2,700.31
Unskilled 4 40.58 51.300 8,327.38

SUB-TOTAL (B) 14,757.96


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 44,852.21


(E) ADD INDIRECT COST
1. OCM 15% 6,727.83
2. Contractor's Profit 10% 4,485.22
3. VAT 5% 2,803.26
TOTAL INDIRECT COST 14,016.31

TOTAL COST (D+E) 58,868.52


DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1001(7).b Septic Vault "Type E"
COST SHEET I.D. : 1001(7).b
QUANTITY : 1.00 each NUMBER OF HOURS: 40.58 hr.

UNIT COST 58,868.52


DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1001(8) Sewer Line Works
COST SHEET I.D. : 1001(8)
QUANTITY : 1.00 L.S. NUMBER OF HOURS: 129.28 hr.

Computation :

Installation of PVC2"Ø = 0.2125 x 4 personnel


U/H : 0.2125 pc/hr = 0.85 pc./hr.
Number of Hours = 28.00 / 0.85
= 32.94 hr

Installation of PVC4"Ø = 0.1038 x 4 personnel


U/H : 0.1038 pc/hr = 0.42 pc./hr.
Number of Hours = 40.00 / 0.42
= 96.34 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Male / Female Toilet : 4 CR


PVC Pipes, 2"Ø length 28.00 295.00 8,260.00
PVC Pipes, 4"Ø length 40.00 585.00 23,400.00
PVC Elbow, 2"Ø x 90° pcs 24.00 30.00 720.00
PVC Wye, Single Branch, 2" x 2" pcs 16.00 83.00 1,328.00
PVC Wye, Single Branch, 2" x 4" pcs 8.00 100.00 800.00
PVC Wye, Single Branch, 4" x 4" pcs 16.00 130.00 2,080.00
PVC P-Trap w/ Plug & Sealing Ring, 2" pcs 12.00 110.00 1,320.00
PVC P-Trap w/ Plug & Sealing Ring, 4" pcs 8.00 280.00 2,240.00
PVC Cleanout w/ Plug & Sealing Ring, 2" pcs 4.00 23.00 92.00
PVC Cleanout w/ Plug & Sealing Ring, 4" pcs 4.00 62.00 248.00
Solvent Cement pcs 16.00 200.00 3,200.00

SUB-TOTAL (A) 43,688.00


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 2 129.28 66.540 17,204.58


Unskilled 2 129.28 51.300 13,264.13

SUB-TOTAL (B) 30,468.71


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 74,156.71


(E) ADD INDIRECT COST
1. OCM 15% 11,123.51
2. Contractor's Profit 10% 7,415.67
3. VAT 5% 4,634.79
TOTAL INDIRECT COST 23,173.97

TOTAL COST (D+E) 97,330.68

UNIT COST -
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1002(5) Plumbing
COST SHEET I.D. : 1002(5)
QUANTITY : 0.00 L.S. NUMBER OF HOURS: 7.00 hr.

Computation :
Installation = 1.000 x 2 personnel
U/H : 1.00 set/hr = 2.00 set/hr. fittings
Number of Hours = 14.00 / 2.00
= 7.00 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Male / Female Toilet : 4 CR


Water Closet incl. fittings & acc., Dual
set 4.00 7,500.00 30,000.00
Flush Type
Lavatory or Equivalent set 4.00 7,000.00 28,000.00
Floor Drain pcs 5.00 300.00 1,500.00
Water Meter or Equivalent set 1.00 1,700.00 1,700.00
Kitchen Sink set 2.00 1,950.00 3,900.00
Miscellaneous Fixtures (10%) 6,510.00

SUB-TOTAL (A) 71,610.00


QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours

Skilled 1 7.00 66.540 465.78


Unskilled 1 7.00 51.300 359.10

SUB-TOTAL (B) 824.88


QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 72,434.88

(E) ADD INDIRECT COST


1. OCM 15% 10,865.23
2. Contractor's Profit 10% 7,243.49
3. VAT 5% 4,527.18
TOTAL INDIRECT COST 22,635.90

TOTAL COST (D+E) 95,070.78

UNIT COST -
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1002(6) Cold Waterline Works
COST SHEET I.D. : 1002(6)
QUANTITY : 0.00 L.S. NUMBER OF HOURS: 47.69 hr.

Computation :
Installation of 3/4"Ø = 1.8975 x 2 personnel
U/H : 1.8975 ln.m./hr = 3.80 ln.m./hr.
Number of Hours = 32.00 / 3.80
= 8.43 hr

Installation of1½"Ø = 1.4263 x 2 personnel


U/H : 1.4263 ln.m./hr = 2.85 ln.m./hr.
Number of Hours = 112.00 / 2.85
= 39.26 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Male / Female Toilet : 4 CR


PPRC PN/20 CWL, 38mmØ length 28.00 1,219.93 34,158.04
PPRC PN/20 CWL, 20mmØ length 8.00 365.06 2,920.48
PPR Type, Coupling, 38mmØ pcs 28.00 70.81 1,982.68
PPR Type, Coupling, 20mmØ pcs 8.00 18.73 149.84
PPR Type, Gate Valve, 38mmØ pcs 2.00 1,338.66 2,677.32
PPR Type, Elbow, 38mmØ x 90° pcs 2.00 134.67 269.34
PPR Type, Elbow, 20mmØ x 90° pcs 68.00 27.17 1,847.56
PPR Type, Tee Equal, 20mmØ pcs 24.00 31.89 765.36
PPR Type, Tee Reducer, 38x20mmØ pcs 12.00 128.89 1,546.68
PPR Type, Elbow Reducer, 38x20mmØ pcs 2.00 58.60 117.20
PPR Type, Female Adaptor, 20x3/4" pcs 16.00 202.95 3,247.20
G.I. Nipple, 20mmØx2" pcs 12.00 26.00 312.00
Bronze Faucet, 20mmØ pcs 5.00 140.00 700.00
Miscellaneous Fixtures (10%) 5,069.37

SUB-TOTAL (A) 55,763.07


QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours

Skilled 1 47.69 66.540 3,173.29


Unskilled 1 47.69 51.300 2,446.50

SUB-TOTAL (B) 5,619.79


QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 61,382.86

(E) ADD INDIRECT COST


1. OCM 15% 9,207.43
2. Contractor's Profit 10% 6,138.29
3. VAT 5% 3,836.43
TOTAL INDIRECT COST 19,182.15

TOTAL COST (D+E) 80,565.01

UNIT COST -
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1003(1).a1 Carpentry for Ceiling with Insulation
COST SHEET I.D. : 1003(1).a1 PRODUCTION RATE: #DIV/0! sq.m./hr.
QUANTITY : 0.00 sq.m. NUMBER OF HOURS: 0.00 hr.
Computation : 259.49

Interior Ceiling = 7.00 x 12.99


= 90.93 / 2.9768
= 30.55 say 31 sheets - (4.5 mm thk Fiber Cement Board)
Exterior Ceiling = 12.99 x 1.00 x 1 +
12.99 x 1.00 x 1 +
9.40 x 0.60 x 2
= 37.26 / 2.9768
= 12.52 say 13 sheets - (4.5 mm thk Fiber Cement Board)
Metal Furring = 0.00 x 1.50 m./sq.m.
(38mmx12mmx5m) = 0.00 / 5.00
= 0.00 say 0 lengths
Carrying Channel = 0.00 x 1.20 m./sq.m.
(38mmx12mmx5m) = 0.00 / 5.00
= 0.00 say 0 lengths
Wal Angle = 0.00 x 1.20 m./sq.m.
(25mmx25mmx3m) = 0.00 / 3.00
= 0.00 say 0 lengths
Hardiflex Screw = 0.00 x 8 pc./sq.m.
= 0.00 say 0 pc
Blind Rivets = 0.00 x 4 pc./sq.m.
1/8" x 3/8" = 0.00 say 0 pc
note: 1 keg = 45 kgs
Assorted Nails = 0.00 / 2,500
= 0.0000 x 45 kg/keg
= 0 kgs
Frameworks = 0.6375 x 4 personnel
U/H : 0.6375 m²/hr = 2.55 sq.m./hr.
Number of Hours = 0.00 / 2.55
= 0.00 hr
Board Installation = 0.85 x 4 personnel
U/H : 0.85 m²/hr = 3.400 sq.m./hr.
Number of Hours = 0.00 / 3.40
= 0.00 x 30% - No. Of hours for installation will be
= 0.000 hr added for the total no. Of hours.
Installation = 1.75 x 4 personnel
U/H : 1.75 m²/hr = 7.00 sq.m./hr.
Number of Hours = 0.00 / 7.00
= 0.00 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST


Fiber Cement Board 4' x 8' x 4.5mm sheet 44.00 540.00 23,760.00
Metal Furring (12mmx38mmx5mx0.80mm) length 0.00 140.00 -
Carrying Channel (12mmx38mmx5mx0.80mm) length 0.00 130.00 -
Wal Angle (25mmx25mmx3m) length 0.00 45.00 -
Hardiflex Screw pc 0.00 1.50 -
Blind Rivets 1/8" x 3/8" pc 0.00 0.50 -
Ceiling Vent (1" x 12" x 4' with screen) pc 20.00 245.00 4,900.00
½" thk Insulation, 1-Side Aluminum Foil sq.m. 122.11 95.00 11,600.07
Assorted Nails kgs 0.00 31.00 -
SUB-TOTAL (A) -
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
Skilled 2 0.00 66.540 -
Unskilled 2 0.00 51.300 -
SUB-TOTAL (B) -
QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate
NONE
SUB-TOTAL (C) -
(D) TOTAL DIRECT COST : (A+B+C) -
(E) ADD INDIRECT COST
1. OCM 15% -
2. Contractor's Profit 10% -
3. VAT 5% -
TOTAL INDIRECT COST -

TOTAL COST (D+E) -


UNIT COST -
DETAILED UNIT PRICE ANALYSIS
NAME : #REF!
LOCATION : #REF!
PAY ITEMS : 1011(1).b Roll-Up Door (Manual)
COST SHEET I.D. : 1011(1).b PRODUCTION RATE: 0.47 sq.m./hr.
QUANTITY : 1.00 set NUMBER OF HOURS: 2.12 hr.

Computation : 46.71
Installation = 0.2363 x 2 personnel
U/H : 0.2363 m²/hr = 0.4726 sq.m./hr.
Number of Hours = 1.00 / 0.4726
= 2.12 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Roll-Up Door (Manual) set 1.00 25,000.00 25,000.00


Area = (4 x 3.5) = 14.00 m²

SUB-TOTAL (A) 25,000.00


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 2 2.12 66.540 282.13

SUB-TOTAL (B) 282.13


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) 25,282.13


(E) ADD INDIRECT COST
1. OCM 15% 3,792.32
2. Contractor's Profit 10% 2,528.21
3. VAT 5% 1,580.13
TOTAL INDIRECT COST 7,900.66

TOTAL COST (D+E) 33,182.79


UNIT COST 33,182.79
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1018(1) 200x200mm Vitrified Glazed Tiles Wall Finish
COST SHEET I.D. : 1018(1) PRODUCTION RATE: #DIV/0! sq.m./hr.
QUANTITY : 0.00 sq.m. NUMBER OF HOURS: 0.00 hr.
Computation : 71.55

Glazed Tile 200mmx200mm

Female / Male Toilet = 6.50 x 1.60 x 1 no. of CR


Wall Area = 10.40 sq.m.

Tile 200mmx200mm = 10.40 / 0.04 = 260


Cement = 0.00 x 0.086 = 0
Sand = 0.00 x 0.01 = 0.00
Grout, Tile = 0.00 x 0.25 = 0
Installation = 0.1950 x 3 personnel
U/H : 0.1950 m²/hr = 0.59 sq.m./hr.
Number of Hours = 0.00 / 0.59
= 0.00 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Glazed Tile 200mmx200mm pc 260.00 14.00 3,640.00


Cement, Portland bags 0.00 240.00 -
Sand, Washed cu.m. 0.00 1,100.00 -
Tile Grout kg 0.00 40.00 -

SUB-TOTAL (A) -
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 1 0.00 66.540 -


Unskilled 2 0.00 51.300 -

SUB-TOTAL (B) -
QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) -


(E) ADD INDIRECT COST
1. OCM 15% -
2. Contractor's Profit 10% -
3. VAT 5% -
TOTAL INDIRECT COST -

TOTAL COST (D+E) -

UNIT COST -
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1018(2) 200x200mm Vitrified Unglazed Tiles Floor Finish
COST SHEET I.D. : 1018(2) PRODUCTION RATE: #DIV/0! sq.m./hr.
QUANTITY : 0.00 sq.m. NUMBER OF HOURS: 0.00 hr.
Computation : 16.26

Glazed Tile 200mmx200mm

Total = 7.00 x 13.00


= 91.00 x 1
= 91.00 sq.m.

Tile 200mmx200mm = 91.00 / 0.04 = 2275


Cement = 0.00 x 0.086 = 0
Sand = 0.00 x 0.01 = 0.00
Grout, Tile = 0.00 x 0.25 = 0
Installation = 0.1950 x 3 personnel
U/H : 0.1950 m²/hr = 0.59 sq.m./hr.
Number of Hours = 0.00 / 0.59
= 0.00 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Unglazed Tile 200mmx200mm pc 2,275.00 12.00 27,300.00


Cement, Portland bags 0.00 240.00 -
Sand, Washed cu.m. 0.00 1,100.00 -
Tile Grout kg 0.00 40.00 -

SUB-TOTAL (A) -
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 1 0.00 66.540 -


Unskilled 2 0.00 51.300 -

SUB-TOTAL (B) -
QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) -


(E) ADD INDIRECT COST
1. OCM 15% -
2. Contractor's Profit 10% -
3. VAT 5% -
TOTAL INDIRECT COST -

TOTAL COST (D+E) -

UNIT COST -
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1036(1).a Polycarbonate Sheet (Roof w/ framing)
COST SHEET I.D. : 1036(1).a PRODUCTION RATE: 3.00 kgs./hr.
QUANTITY : 12.00 sheets NUMBER OF HOURS: 4.00 hr.

Computation : 6,075.72
Polycarbonate Sheet : 1 set
= 6.30 x 5.4 no. of angle bar
= 34.02 x 1 set
= 34.02 / 2.88
= 11.81 say 12 sheets

2" x 6" x 1.0mm = 6.30 x 9 +


Rectangular Tube = 5.40 x 2
Framing = 67.50 / 6
= 11.25 say 12 lengths

Welding Rod = 223.80 / 1,000 x 30


= 6.71 say 7 kgs
Red Lead = 28.80 / 25 + 5% wastages
= 2 gals
Fab/Erect/Install of Frame = 17.00 x 4 personnel
U/H : 17 kg/hr = 68.00 kg./hr.
Number of Hours = 223.80 / 68.00
= 3.29 hr
Painting of Angle = 4.25 x 4 personnel
U/H : 4.25 pcs./hr = 17.00 pcs./hr
Number of Hours = 12.00 / 17.000
= 0.71 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Polycarbonate Sheet Sheets 12 849 10,188.00


2" x 6" x 1.0mm Rectangular Tube pc 12 1336.30 16,035.60
1" x 3" Flat Bar for Canopy Support pc 2 2278.10 4,556.20
Turn Buckle pc 2 500.00 1,000.00
Welding Rod ½"Ø E-70 Series kg 7.00 67.00 469.00
Acetylene kg 5.00 80.00 400.00
Oxygen kg 5.00 45.00 225.00
Red Lead Primer Oxide gal 2.00 570.00 1,140.00

SUB-TOTAL (A) 34,013.80


QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours

Skilled 2 4.00 66.540 532.32


Unskilled 2 4.00 51.300 410.40

SUB-TOTAL (B) 942.72


QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours

Welding Machine AC Output 300Amps 2 3.29 187.00 1,230.46

SUB-TOTAL (C) 1,230.46

(D) TOTAL DIRECT COST : (A+B+C) 36,186.98


(E) ADD INDIRECT COST
1. OCM 15% 5,428.05
2. Contractor's Profit 10% 3,618.70
3. 5% VAT 5% 2,261.69
TOTAL INDIRECT COST 11,308.44

TOTAL COST (D+E) 47,495.42

UNIT COST 3,957.95


DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1039(1) Aluminum Cladding
COST SHEET I.D. : 1039(1) PRODUCTION RATE: 1.89
QUANTITY : 123.00 m 2
NUMBER OF HOURS: 65.07

Computation : 46.71

Cladding Area Left Side : 2.00 x 6 x 1


1.00 x 6 x 1
0.60 x 6 x 1
= 22.00 m 2

Cladding Area Front Side : 0.40 x 7.5 x 5


1.00 x 22.30 x 1
1.50 x 11.25 x 1
0.60 x 22.30 x 1
= 68.00 m 2

Cladding Area Front Side : 1.00 x 27 x 1


Slanting Area 1.00 x 6.00 x 1
= 33.00 m2

Total Cladding Area = 123.00 m2

Installation = 0.2363 x 8 personnel


U/H : 0.2363 m²/hr = 1.8904 sq.m./hr.

Number of Hours = 123.00 / 1.8904


= 65.07 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE

ALUMINUM COMPOSITE PANEL ON ALUMINUM


m² 123.00 2,300.00
FRAME

SUB-TOTAL (A)
QUANTITY
(B) LABOR COST Hourly Rate
No. Of Personnel Total Hours

Skilled 8 65.07 66.540

SUB-TOTAL (B)
QUANTITY
(C) EQUIPMENT COST Hourly Rate
No. Of Equipment Total Hours
NONE

SUB-TOTAL (C)

(D) TOTAL DIRECT COST : (A+B+C)


(E) ADD INDIRECT COST
1. OCM 15%
2. Contractor's Profit 10%
3. VAT 5%
TOTAL INDIRECT COST

TOTAL COST (D+E)

UNIT COST
LED UNIT PRICE ANALYSIS

sq.m./hr.
hr.

pc/pcs
pc/pcs
pc/pcs

pc/pcs
pc/pcs
pc/pcs
pc/pcs

pc/pcs
pc/pcs

TOTAL COST

282,900.00

282,900.00

TOTAL COST

34,638.06

34,638.06

TOTAL COST
-

317,538.06

47,630.71
31,753.81
19,846.13
99,230.64

416,768.70

3,388.36
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1039(2) Stone Bricks (Cladding)
COST SHEET I.D. : 1039(2) PRODUCTION RATE: 1.89
QUANTITY : 45.80 m 2
NUMBER OF HOURS: 24.23

Computation : 46.71

Cladding Area Front Side : 1.00 x 20.32 x 1


4.10 x 5.60 x 1
0.45 x 5.60 x 1

Total Cladding Area = 45.80 sq.m.

Installation = 0.2363 x 8 personnel


U/H : 0.2363 m²/hr = 1.8904 sq.m./hr.

Number of Hours = 45.80 / 1.8904


= 24.23 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE

Stone Bricks (Cladding) m² 45.80 1,350.00

SUB-TOTAL (A)
QUANTITY
(B) LABOR COST Hourly Rate
No. Of Personnel Total Hours

Skilled 8 24.23 66.540

SUB-TOTAL (B)
QUANTITY
(C) EQUIPMENT COST Hourly Rate
No. Of Equipment Total Hours

NONE

SUB-TOTAL (C)

(D) TOTAL DIRECT COST : (A+B+C)


(E) ADD INDIRECT COST
1. OCM 15%
2. Contractor's Profit 10%
3. VAT 5%
TOTAL INDIRECT COST
TOTAL COST (D+E)

UNIT COST
LED UNIT PRICE ANALYSIS

sq.m./hr.
hr.

pc/pcs
pc/pcs
pc/pcs

TOTAL COST

61,830.00

61,830.00

TOTAL COST

12,898.11

12,898.11

TOTAL COST

74,728.11

11,209.22
7,472.81
4,670.51
23,352.53
98,080.64

2,141.50
DETAILED UNIT PRICE ANALYSIS
NAME : #REF!
LOCATION : #REF!
PAY ITEMS : 1046(1).2 CHB Non Load Bearing (Including Reinforcing Steel) Front Side Area
COST SHEET I.D. : 1046(1).2 PRODUCTION RATE: 2.13 sq.m./hr.
QUANTITY : 51.29 sq.m. NUMBER OF HOURS: 24.13 hr.
Computation : 383.37 138.69 522.06

= 22.30 x 2.30
CHB Wall at Front Side
= 51.29 sq.m.
Total No. Of CHB 4" = 51.29 x 12.50 + 1% for breakages
= 648 pcs
Cement (Mortar) = 51.29 x 0.394
Class C = 20.21 say 21 bag
Sand (Mortar) = 51.29 x 0.0435
Class C = 2.20 say 2 cu.m.

Reinforcing Steel : 600mm x 600mm Spacing of Reinforcing Steel


(for Horizontal Bars) = 51.29 x 2.13 = 109.25
(forVertical Bars) = 51.29 x 2.15 = 110.27
219.52 meters
= 219.52 / 6
= 36.59 say 37 lengths of 10mmØ x 6.00 m Deformed Bars
kgs of G.I. Tie Wire = 51.29 x 0.032
= 2.00 kgs
CHB Laying = 0.5313 x 4 personnel
U/H : 0.5313 m²/hr = 2.13 sq.m./hr.
Number of Hours = 51.29 / 2.13
= 24.13 hr
(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST
CHB 4" pcs 648.00 12.00 7,776.00
Cement, Portland bags 21.00 240.00 5,040.00
Sand, Washed cu.m. 2.00 1,100.00 2,200.00
10mmØ x 6.00 m Deformed Bars kgs 136.97 41.00 5,615.77
# 16 Tie Wire G.I. kgs 2.00 50.00 100.00
SUB-TOTAL (A) 20,731.77
QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours
Skilled 2 24.13 66.540 3,211.22
Unskilled 2 24.13 51.300 2,475.74
SUB-TOTAL (B) 5,686.96
QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours
NONE
SUB-TOTAL (C) -
(D) TOTAL DIRECT COST : (A+B+C) 26,418.73
(E) ADD INDIRECT COST
1. OCM 15% 3,962.81
2. Contractor's Profit 10% 2,641.87
3. VAT 5% 1,651.17
TOTAL INDIRECT COST 8,255.85
TOTAL COST (D+E) 34,674.58
UNIT COST 676.05
DETAILED UNIT PRICE ANALYSIS
NAME : #REF!
LOCATION : #REF!
PAY ITEMS : 1046(1).3 CHB Non Load Bearing (Including Reinforcing Steel) Rear Side
COST SHEET I.D. : 1046(1).3 PRODUCTION RATE: 2.12 sq.m./hr.
QUANTITY : 55.80 sq.m. NUMBER OF HOURS: 26.26 hr.
Computation : 383.37 138.69 522.06

= 27.90 x 2.00
CHB Wall at Rear Side
= 55.80 sq.m.
Total No. Of CHB 4" = 55.80 x 12.50 + 1% for breakages
= 705 pcs
Cement (Mortar) = 55.80 x 0.394
Class C = 21.99 say 22 bag
Sand (Mortar) = 55.80 x 0.0435
Class C = 2.40 say 2 cu.m.

Reinforcing Steel : 600mm x 600mm Spacing of Reinforcing Steel


(for Horizontal Bars) = 55.80 x 2.13 = 118.85
(forVertical Bars) = 55.80 x 2.15 = 119.97
238.82 meters
= 238.82 / 6
= 39.80 say 40 lengths of 10mmØ x 6.00 m Deformed Bars
kgs of G.I. Tie Wire = 55.80 x 0.032
= 2.00 kgs
CHB Laying = 0.5313 x 4 personnel
U/H : 0.5313 m²/hr = 2.13 sq.m./hr.
Number of Hours = 55.80 / 2.13
= 26.26 hr
(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST
CHB 4" pcs 705.00 12.00 8,460.00
Cement, Portland bags 22.00 240.00 5,280.00
Sand, Washed cu.m. 2.00 1,100.00 2,200.00
10mmØ x 6.00 m Deformed Bars kgs 148.08 41.00 6,071.28
# 16 Tie Wire G.I. kgs 2.00 50.00 100.00
SUB-TOTAL (A) 22,111.28
QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours
Skilled 2 26.26 66.540 3,494.68
Unskilled 2 26.26 51.300 2,694.28
SUB-TOTAL (B) 6,188.96
QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours
NONE
SUB-TOTAL (C) -
(D) TOTAL DIRECT COST : (A+B+C) 28,300.24
(E) ADD INDIRECT COST
1. OCM 15% 4,245.04
2. Contractor's Profit 10% 2,830.02
3. VAT 5% 1,768.77
TOTAL INDIRECT COST 8,843.83
TOTAL COST (D+E) 37,144.07
UNIT COST 665.66
DETAILED UNIT PRICE ANALYSIS
NAME : #REF!
LOCATION : #REF!
PAY ITEMS : 1046(1).4 CHB and decorative louver blocks (Including Reinforcing Steel) Right Side
COST SHEET I.D. : 1046(1).4 PRODUCTION RATE: 2.13 sq.m./hr.
QUANTITY : 55.20 sq.m. NUMBER OF HOURS: 25.97 hr.
Computation : 383.37 138.69 522.06

= 24.00 x 2.30
CHB Wall at Rear Side
= 55.20 sq.m.

Total No. Of CHB 4" = 55.20 x 12.50 + 1% for breakages


= 697 pcs
Cement (Mortar) = 55.20 x 0.394
Class C = 21.75 say 22 bag
Sand (Mortar) = 55.20 x 0.0435
Class C = 2.40 say 2 cu.m.

Reinforcing Steel : 600mm x 600mm Spacing of Reinforcing Steel


(for Horizontal Bars) = 55.20 x 2.13 = 117.58
(forVertical Bars) = 55.20 x 2.15 = 118.68
236.26 meters
= 236.26 / 6
= 39.38 say 39 lengths of 10mmØ x 6.00 m Deformed Bars
kgs of G.I. Tie Wire = 55.20 x 0.032
= 2.00 kgs
CHB Laying = 0.5313 x 4 personnel
U/H : 0.5313 m²/hr = 2.13 sq.m./hr.
Number of Hours = 55.20 / 2.13
= 25.97 hr
(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST
CHB 4" pcs 697.00 12.00 8,364.00
Decorative Louver Blocks pcs 160.00 20.00 3,200.00
Cement, Portland bags 22.00 240.00 5,280.00
Sand, Washed cu.m. 2.00 1,100.00 2,200.00
10mmØ x 6.00 m Deformed Bars kgs 144.38 41.00 5,919.58
# 16 Tie Wire G.I. kgs 2.00 50.00 100.00
SUB-TOTAL (A) 25,063.58
QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours
Skilled 2 25.97 66.540 3,456.09
Unskilled 2 25.97 51.300 2,664.52
SUB-TOTAL (B) 6,120.61
QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours
NONE
SUB-TOTAL (C) -
(D) TOTAL DIRECT COST : (A+B+C) 31,184.19
(E) ADD INDIRECT COST
1. OCM 15% 4,677.63
2. Contractor's Profit 10% 3,118.42
3. VAT 5% 1,949.01
TOTAL INDIRECT COST 9,745.06
TOTAL COST (D+E) 40,929.25
UNIT COST 741.47
DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1047(2)c Purlins
COST SHEET I.D. : 1047(2)c PRODUCTION RATE: 15.70 kgs./hr.
QUANTITY : 460.24 kg NUMBER OF HOURS: 29.32 hr.
Computation : 3,366.18 705.51 4,071.69
65
1" x 1" x 1/4" = 0.075 x 80
Clip Angle = 6.00 / 6
= 1.00 say 1 lengths

LC 2" x 4" x 1.0mm thk. C- = 24.20 x 9


PURLINS = 217.80 / 6.00
= 36.30 say 36 lengths

Welding Rod = 460.24 / 1,000 x 30


= 13.81 say 14.00 kgs
Red Lead = 98.93 / 25 + 5% wastages
= 5 gals
Fab/Erect/Install of Purlins = 4.50 x 4 personnel
U/H : 4.50 kg/hr = 18.00 kg./hr.
Number of Hours = 447.04 / 18.00
= 24.84 hr
Painting of Purlins = 4.25 x 4 personnel
U/H : 4.25 pcs./hr = 17.00 pcs./hr
Number of Hours = 36.00 / 17.000
= 2.12 hr
Fab/Erect/Install of Angle = 17.00 x 4 personnel
U/H : 17 kg/hr = 68.00 kg./hr.
Number of Hours = 13.20 / 68.00
= 0.19 hr
Painting of Angle = 4.25 x 4 personnel 460.24
U/H : 4.25 pcs./hr = 17.00 pcs./hr
Number of Hours = 37.00 / 17.000
= 2.18 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST


LC 2" x 4" x 1.0mm thk. C-PURLINS kg 447.04 53.00 23,693.12
Angle Bar 25 x 25 x 6mm kg 13.20 53.00 699.60
Welding Rod ½"Ø E-70 Series kg 14.00 150.00 2,100.00
Acetylene kg 4.00 80.00 320.00
Oxygen kg 4.00 45.00 180.00
Red Lead Primer Oxide gal 5.00 399.00 1,995.00
SUB-TOTAL (A) 28,987.72
QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate
Skilled 2 29.32 66.540 3,901.91
Unskilled 2 29.32 51.300 3,008.23
SUB-TOTAL (B) 6,910.14
QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate
Welding Machine AC Output 300Amps 2 25.03 187.00 9,361.22
SUB-TOTAL (C) 9,361.22
(D) TOTAL DIRECT COST : (A+B+C) 45,259.08
(E) ADD INDIRECT COST
1. OCM 15% 6,788.86
2. Contractor's Profit 10% 4,525.91
3. 5% VAT 5% 2,828.69
TOTAL INDIRECT COST 14,143.46
TOTAL COST (D+E) 59,402.54
UNIT COST 129.07
500000

1,560,746.37

500000

500000.000
98.34
-

0
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1047(3) Sag Rod, Cross Bar & Turn Buckle
COST SHEET I.D. : 1047(3) PRODUCTION RATE: 17.96 kgs./hr.
QUANTITY : 45.27 kg NUMBER OF HOURS: 2.52 hr.

Computation : 365.56

Sag Rod 12mmØ = 5.50 x 3 x 1


= 16.50 / 6
= 3 lengths
Cross Bar 16mmØ = 6.26 x 2 x 1
= 12.52 / 6
= 3 lengths
Welding Rod = 45.27 / 1,000 x 30
= 1.36 say 1.00 kgs
Fab/Erect/Install of Bar = 4.50 x 4 personnel
U/H : 4.50 kg/hr = 18.00 kg./hr.
Number of Hours = 45.27 / 18.00
= 2.52 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

12mmØ x 6.00 m Deformed Bars kgs 16.21 41.00 664.61


16mmØ x 6.00 m Deformed Bars kgs 29.06 41.00 1,191.46
Turn Buckle 5/8" pc 4.00 190.00 760.00
Welding Rod ½"Ø E-70 Series kg 1.00 150.00 150.00
Acetylene kg 4.00 80.00 320.00
Oxygen kg 4.00 45.00 180.00

SUB-TOTAL (A) 3,266.07


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 2 2.52 66.540 335.36


Unskilled 2 2.52 51.300 258.55

SUB-TOTAL (B) 593.91


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

Welding Machine AC Output 300Amps 2 2.52 187.00 942.48

SUB-TOTAL (C) 942.48

(D) TOTAL DIRECT COST : (A+B+C) 4,802.46

(E) ADD INDIRECT COST


1. OCM 15% 720.37
2. Contractor's Profit 10% 480.25
3. VAT 5% 300.15
TOTAL INDIRECT COST 1,500.77

TOTAL COST (D+E) 6,303.23

UNIT COST 139.24


DETAILED UNIT PRICE ANALYSIS

NAME : #REF!
LOCATION : #REF!
PAY ITEMS : 1051(1) Metal Railings
COST SHEET I.D. : 1051(1)
QUANTITY : 289.70 meter NUMBER OF HOURS: 45.76 hr.

Computation :
= 0.00 x 1 no. of ramp
32mmØ G.I.Pipe
1" x 3" x 6M Rectangular
Tubing = 104.00 / 6.00
Stair Raillings (Horizontal) = 17.33 say 18 lengths

1" x 3" x 6M Rectangular


Tubing = 29.70 / 6.00
Stair Raillings (Vertical) = 4.95 say 5 lengths

1" x 1" x 6M Rectangular


Tubing = 156.00 / 6.00
Stair Raillings (Horizontal) = 26.00 say 26 lengths

Welding Rod = 393.85 / 1,000 x 30


= 11.82 say 12.00 kgs
Red Lead = 22.80 / 25 + 10% wastages
= 2 gals
Fab/Install of Railings = 16.855 x 2 personnel
U/H : 16.855 kg/hr = 33.71 kg./hr.
Number of Hours = 393.85 / 33.71
= 11.68 hr
Painting of Railings = 4.25 x 2 personnel
U/H : 4.25 ln.m./hr = 8.50 ln.m./hr.
Number of Hours = 289.70 / 8.50
= 34.08 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST


1" x 3" x 6M Rectangular Tubing length 23.00 543.20 12,493.60
1" x 1" x 6M Rectangular Tubing length 26.00 266.20 6,921.20
Welding Rod ½"Ø E-70 Series kg 12.00 150.00 1,800.00
Acetylene kg 3.00 80.00 240.00
Oxygen kg 3.00 45.00 135.00
Red Lead Primer Oxide gal 2.00 399.00 798.00

SUB-TOTAL (A) 22,387.80


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Skilled 1 45.76 66.540 3,044.87


Unskilled 1 45.76 51.300 2,347.49

SUB-TOTAL (B) 5,392.36


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

Welding Machine DC Output 500Amps 1 11.68 391.00 4,566.88

SUB-TOTAL (C) 4,566.88

(D) TOTAL DIRECT COST : (A+B+C) 32,347.04

(E) ADD INDIRECT COST


1. OCM 15% 4,852.06
2. Contractor's Profit 10% 3,234.70
3. VAT 5% 2,021.69
TOTAL INDIRECT COST 10,108.45

TOTAL COST (D+E) 42,455.49


UNIT COST 146.55
DETAILED UNIT PRICE ANALYSIS

NAME : Rehab/Completion of Multipurpose Building


LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 1009(1).a Metal Louvers (Gym Louver)
COST SHEET I.D. : 1009(1).a PRODUCTION RATE: 1.17 sq.m./hr.
QUANTITY : 278.00 sq.m. NUMBER OF HOURS: 237.31 hr.

Computation : 128.275

Louver Area Left Side : 5.80 x 1.5 x 3 pcs


6.00 x 2.6 x 1 pc/pcs
= 42.00 sq.m.

Louver Area Right Side : 6.00 x 2.3 x 5 pcs


= 69.00 sq.m.

Louver Area Front Side : 5.13 x 3.4 x 4 pcs


5.60 x 2.00 x 1 pc/pcs
= 81.00 sq.m.

Louver Area Rear Side : 5.30 x 4 x 3 pcs


6.90 x 3.21 x 1 pc/pcs
= 86.00 sq.m.

Total Louver Area = 278.00 sq.m.

Fab/Erect/Install of Angle = 17.00 x 4 personnel


U/H : 17 kg/hr = 68.00 kg./hr.
Number of Hours = 13,665 / 68.00
= 200.96 hrs
Painting of Angle = 4.25 x 4 personnel
U/H : 4.25 pcs./hr = 17.00 pcs./hr
Number of Hours = 618.00 / 17.000
= 36.35 hr

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Metal Louver (Gym Louver) sq.m. 278.00 2,236.00 621,608.00


Framing = 2"x 3" BI TUBING 6M 2" X 3" (3mm)
Blade = STEEL PLATE GI # 20

Welding Rod ½"Ø E-70 Series kg 169.00 67.00 11,323.00


Acetylene kg 20.00 80.00 1,600.00
Oxygen kg 20.00 45.00 900.00

SUB-TOTAL (A) 635,431.00


QUANTITY Hourly
(B) LABOR COST TOTAL COST
No. Of Personnel Total Hours Rate

Fixed Louver Installer 4 237.31 66.540 63,162.43

SUB-TOTAL (B) 63,162.43


QUANTITY Hourly
(C) EQUIPMENT COST TOTAL COST
No. Of Equipment Total Hours Rate

Welding Machine AC Output 300Amps 1 200.96 187.00 37,579.52

SUB-TOTAL (C) 37,579.52

(D) TOTAL DIRECT COST : (A+B+C) 736,172.95

(E) ADD INDIRECT COST


1. OCM 15% 110,425.94
2. Contractor's Profit 10% 73,617.30
3. VAT 5% 46,010.81
TOTAL INDIRECT COST 230,054.05
TOTAL COST (D+E) 966,227.00

UNIT COST 3,475.64


DETAILED UNIT PRICE ANALYSIS
NAME : Rehab/Completion of Multipurpose Building
LOCATION : Barangay Bae, Sibonga, Cebu
PAY ITEMS : 903(1) Forms and Falseworks
COST SHEET I.D. : 903(1)
QUANTITY : 1.00 L.S. NUMBER OF HOURS: #REF! hr.
Computation :
Beam Formworks = #REF! + #REF! x 2
x #REF! l.m.
= #REF! / 2.98 plywood / m²
No. of Plywood = #REF! x 25.06 = #REF! bd.ft. (2" x 2")
Beam Scaffoldings (Ver) = #REF! x 4.00 = #REF! bd.ft. (2" x 2")
Beam Scaffoldings (Hor) = #REF! x 4.70 = #REF! bd.ft. (2" x 2")
Column Formworks = Err:509 x 2 +
Err:509 x 2 x 3.50 l.m. ht.
= Err:509 x Err:509 no. of columns
= Err:509 / 2.98 plywood / m²
No. of Plywood = Err:509 x 29.67 = Err:509 bd.ft. (2" x 2")
Column Scaffoldings (Ver) = Err:509 x 4.70 = Err:509 bd.ft. (2" x 2")
Column Scaffoldings (Hor) = Err:509 x 21.00 = Err:509 bd.ft. (2" x 2")
Column Scaffoldings (Bra) = Err:509 x 11.70 = Err:509 bd.ft. (2" x 2")
Slab Formworks = #REF! x #REF! x #REF! +
#REF! x #REF! x #REF! +
#REF! x #REF! x #REF!
= #REF! / 2.98 plywood / m²
No. of Plywood = #REF!
= #REF! x 6.10 = #REF! bd.ft. (2" x 2")
Assorted C.W.Nails = #REF! / 2,500 x 45
Note: 1 keg = 45 kgs = #REF! kg
FORMWORKS
Formworks :
Installation = 0.2725 x 6 personnel
U/H : 0.2725 m²/hr = 1.64 m²/hr
Number of Hours = #REF! / 1.64 = 0.61 hr.
Stripping = 0.825 x 6 personnel
U/H : 0.8250 m²/hr = 4.95 m²/hr
Number of Hours = #REF! / 4.95 = #REF! hr.
SCAFFOLDINGS :
Installation = 0.3575 x 6 personnel
U/H : 0.3575 m²/hr = 2.145 m²/hr
Number of Hours = #REF! / 2.145 = #REF! hr.
Stripping = 0.9550 x 6 personnel
U/H : 0.9550 m²/hr = 5.730 m²/hr
Number of Hours = #REF! / 5.73 = #REF! hr.

(A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Coco Lumber bd.ft. #REF! 15.00 #REF!


Assorted C.W. Nails kgs #REF! 31.00 #REF!
¼" x 4' x 8' Ordinary Plywood pcs #REF! 325.00 #REF!

SUB-TOTAL (A) #REF!


QUANTITY
(B) LABOR COST Hourly Rate TOTAL COST
No. Of Personnel Total Hours

Skilled 2 #REF! 66.540 #REF!


Unskilled 4 #REF! 51.300 #REF!

SUB-TOTAL (B) #REF!


QUANTITY
(C) EQUIPMENT COST Hourly Rate TOTAL COST
No. Of Equipment Total Hours

NONE

SUB-TOTAL (C) -

(D) TOTAL DIRECT COST : (A+B+C) #REF!

(E) ADD INDIRECT COST


1. OCM 15% #REF!
2. Contractor's Profit 10% #REF!
3. VAT 5% #REF!
TOTAL INDIRECT COST #REF!
TOTAL COST (D+E) #REF!
UNIT COST #REF!

You might also like