ASTA POWERPROJECT
UPDATING PROGRESS
 
Maintaining baselines in your schedule is a best practice, and the tip below outlines the
process of managing and creating baselines in ASTA. You also can use this to create “What If”
scenarios for your schedule.

Before updating progress on any project, you should create a baseline first. This allows you to
compare your progress to the original plan (baseline).

To create a baseline in Asta, select the Project tab and choose the Baseline Manager
command.

These  tech  tips  are  offered  free  of  charge  in  the  spirit  of  sharing  knowledge  with  others.  They  do  not  include  technical  support,  should  you  have  a  problem  with  them.  We  are  always  interested  in  how  they  
can  be  improved;  please  do  not  hesitate  to  email  us  your  comments.  These  tips  have  been  thoroughly  tested  by  our  consultants  in  a  variety  of  environments.  Please  read  these  tech  tips  thoroughly  and  be  
sure  that  you  understand  them  before  trying  to  use  them.  We  cannot  be  responsible  for  issues  that  develop  because  of  the  configuration  of  your  hardware,  technical  environment  or  application  of  the  tech  
memos.  If  you  are  not  sure,  then  we  urge  you  to  contact  Oracle  technical  support  or  your  local  support  consultant  for  assistance.  
UPDATING PROGRESS IN ASTA POWERPROJECT

This dialog box appears:

Select NEW (baseline Wizard appears):

Page 2
UPDATING PROGRESS IN ASTA POWERPROJECT

Enter a name and description, however detailed needed for future reference. Could be used to
describe included/excluded scope so its clear to others just what it includes. Some examples of
baseline names to get into the habit of using descriptive names could be:

Construction 05/05/2016
Engineering 04/01/2016
Funding Approved 03/01/2016
Engineering incl Change Order #2

Having a baseline that would include the modifications for the change order could pay
dividends if a forensics analysis has to be done post project-description of what was included
in the CO could be included. If a project goes on for 2+ years, having these descriptions can
be really helpful to recall what was done and when.

Select Next:

Page 3
UPDATING PROGRESS IN ASTA POWERPROJECT

Save the baseline name, saved either to the same location as the current schedule, or to a
network drive for others to access, and to automatically be backed up. Click Next:

Gives you opportunity to select all tasks or specific ones (available when multiple components
of project exist). Select Next:

Page 4
UPDATING PROGRESS IN ASTA POWERPROJECT

Summarizes all functions thru the baseline creation activity. Finish button will complete the
baseline creation and take you back to the Baseline/What If Manager. After multiple baselines
are created, this screen is the manager allowing assigning of different baseline depending on
the need.

Other functions on this screen:

Merge – Include extra data into the baseline that wasn’t available at the time of the original
creation or data that was left out. Lastly, it could be added scope that came after the baseline
was created.

Delete – Delete the baseline from the list of selectable.

Set as Current – The primary baseline desired to view when baseline utility is active. Only 1
baseline can be set to Current. This baseline is the schedule that is used for comparison and
calculations when comparing plan to actual data.

Revert to – Through the planning process, the scheduler might create a “What If” scenario to
see how certain work package sequencing may influence start-up for instance. The revert to
allows for a scenario to be adopted as the project plan. At the time of Revert, the user can
specify the options in the table as to what specifically is intended to be reverted.

Import – Ability to bring in another file from your computer and add to the baseline list. This
could be a previously saved file or maybe a template file from a past project that is similar.

Page 5