Well Control Question of the Day

Drilling & Completions - Sumatra Operation


IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1 Sesuai Chevron Well Control Policy, berapakah jumlah barrier yang harus Dua buah independent barrier, bisa hydrostatic barrier dan/atau Barrier
terpasang selama operasi normal? mechanical barrier. Policy
As per Chevron Well Control Policy, how many barriers need to be installed Two independent barrier, it could be hydrostatic barrier and/or mechanical
during normal operation? barrier.
2 Sesuai Chevron Well Control Policy, berapakah jumlah barrier yang harus Dua buah barrier. Mechanical barrier. Barrier
terpasang sebelum bisa melepaskan BOP/tree/well head? Apa jenis barrier- Policy
nya?
As per Chevron Well Control Policy, how many barriers need to be installed Two barriers. Mechanical barrier.
before nippling down BOP/tree/well head? What is the barrier type for
this?
3 Berikan contoh mechanical barrier. BOP, packer, check valve, x-mas tree, casing yang sudah disemen dan Barrier
belum diperforasi. Mechanical barrier harus di-test dulu sebelum dapat Policy
dianggap sebagai sebuah barrier.
Provide some example of mechanical barrier. BOP, packer, check valve, x-mas tree, cemented & unperforated casing.
Mechanical barrier shall be tested before can be considered as a barrier.

4 Berikan contoh hydrostatic barrier. Drilling mud, brine, oil. Hydrostatic barrier harus dimonitor secara berkala Barrier
untuk memastikan tidak ada perubahan sehingga dapat dianggap sebagai Policy
sebuah barrier.
Provide some example of hydrostatic barrier. Drilling mud, brine, oil. Hydrostatic barrier needs to be monitored
periodically to make sure there are no changes and can be considered as a
barrier.
5 Berapa jumlah mechanical barrier yang Anda miliki jika terdapat susunan Satu buah mechanical barrier. BOP stack dianggap sebagai satu buah
berikut ini di atas wellhead: Annular BOP, Blind/Shear Ram dan Pipe Ram? mechanical barrier walaupun memiliki Annular BOP dan beberapa buah
Ram BOP karena menggunakan sumber tenaga yang sama.
How many mechanical barrier do you have if the following are installed on One mechanical barrier. BOP stack is considered as a single mechanical
top of the wellhead: Annular BOP, Blind/Shear Ram dan Pipe Ram? barrier eventhough consists of Annular BOP and multiple Ram BOPs
because they are using the same power source.
6 Apa yang dimaksud dengan tekanan hidrostatik (HP)? Tekanan hidrostatik (HP) adalah tekanan yang disebabkan oleh berat dari Basic
sebuah kolom fluida. Concept
What is hydrostatic pressure (HP)? Hydrostatic pressure (HP) is pressure exerted by the weight of a fluid
column.
7 Bagaimana rumus untuk menghitung tekanan hidrostatik (HP) pada sebuah HP (psi) = 0.052 x Mud Weight (ppg) x True Vertical Depth (ft) Basic
sumur? Concept
What is the formula/equation to calculate hydrostatic pressure (HP) in a HP (psi) = 0.052 x Mud Weight (ppg) x True Vertical Depth (ft)
well?
Page 1 of 21 Rev. 5 Oct 2012
Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
8 Betul atau salah: tekanan hidrostatik bergantung pada ukuran lubang (hole Salah. Tekanan hidrostatik hanya bergantung pada berat fluida (MW) dan Barrier
Basic
size) dan measure depth (MD). true vertical depth (TVD). Policy
Concept

True or false: hydrostatic pressure depends on hole size and measured False. Hydrostatic Pressure only depends on fluid weight (MW) and true
depth (MD). vertical depth (TVD).

9 Apa yang dimaksud dengan kondisi underbalance? Kondisi di mana bottom hole pressure (BHP) lebih kecil dibandingkan Basic
dengan tekanan formasi (FP) sehingga memungkinkan masuknya influx ke Concept
dalam sumur.
What is underbalance condition? Condition when bottom hole pressure (BHP) is less than formation pressure
(FP) thus creating possibility for influx in the well.

10 Apa yang dimaksud dengan fracture pressure (FR)? Tekanan yang jika dilampaui maka dapat menyebabkan pecahnya formasi. Basic
Jika formasi pecah maka akan terjadi loss circulation. Concept
What is fracture pressure (FR)? Pressure when exceeded will likely to break the formation. If the formation
breaks then loss circulation will occur.
11 Pada kondisi tekanan formasi apa yang dapat menyebabkan situasi well Semua kondisi tersebut dapat menyebabkan situasi well control: Basic
control: sub-normal, normal atau abnormal? * sub-normal: loss circulation menyebabkan fluid level turun sehingga Concept
menyebabkan kondisi underbalance dan memungkinkan masuknya influx
ke dalam sumur.
* normal: kita cenderung mempunyai kewaspadaan yang lebih rendah
ketika beroperasi di sumur yang bertekanan normal sehingga lupa/tidak
memperhatikan pengisian lubang ketika tripping --> fluid level drop dan
memungkinkan masuknya influx ke dalam sumur.
* abnormal: ditemukannya tekanan lebih tinggi yang tidak diharapkan pada
kedalaman yang lebih dangkal sehingga menyebabkan kondisi
underbalance dan memungkinkan masuknya influx ke dalam sumur.
What formation pressure that can cause a well control situation: sub- All well conditions can cause well control situation:
normal, normal or abnormal? * sub-normal: loss circulation causes the fluid level to drop and creating
underbalance condition thus allowing influx in the well.
* normal: we tend to have lower awareness when operating in a normal
pressure well and forget/do not fill the hole properly when tripping --> fluid
level could drop and allows influx in the well.
* abnormal: unexpected higher pressure found in shallower depth causes
underbalance condition and allows influx in the well.

Page 2 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
12 Efek ECD pada BHP akan lebih besar pada sirkulasi yang mana: forward Reverse circulation. Pada reverse circulation maka fluida dari annulus Barrier
Basic
(normal) circulation atau reverse circulation? Mengapa? masuk ke dalam string/tubing yang biasanya lebih sempit sehingga Policy
Concept
menghasilkan tekanan friksi yang lebih besar dibandingkan dengan forward
circulation. ECD berhubungan dengan tekanan friksi.

Effect of ECD on BHP will be higher on which circulation: forward (normal) Reverse circulation. On reverse circulation, fluid from annulus flows into the
circulation or reverse circulation? Why? string/tubing which is normally smaller thus creating higher friction
pressure compares to forward circulation. ECD is related to friction
pressure.
13 Apa yang dimaksud dengan kondisi "pipe light"? Kondisi di mana berat pipa terapung yang ada di dalam lubang lebih ringan Basic
dibandingkan dengan gaya yang dihasilkan oleh tekanan sumur pada Concept
penampang pipa tersebut sehingga, jika tidak ditahan, pipa dapat didorong
keluar sumur oleh gaya tersebut.

What is "pipe light" condition? Condition when the buoyed weight of the pipe in the hole is lighter than the
upward force created by the well pressure on the cross section of the pipe
thus, if the pipes are not held, pipes could be pushed out of the hole.

14 Apa yang dimaksud dengan kondisi "pipe heavy"? Kondisi di mana berat pipa terapung yang ada di dalam lubang lebih berat Basic
dibandingkan dengan gaya yang dihasilkan oleh tekanan sumur pada Concept
penampang pipa tersebut sehingga, jika tidak ditahan, maka pipa dapat
meluncur masuk ke dalam sumur yang bertekanan tersebut.

What is "pipe heavy" condition? Condition when the buoyed weight of the pipe in the hole is heavier than
the upward force created by the well pressure on the cross section of the
pipe thus, if the pipes are not held, pipes could slip down into the under
pressured well.
15 Berapakah tekanan pre-charge pada botol accumulator? Minimum 1,000 psi pada sistem 3,000 psi. BOP Closing
System
What is the pre-charge pressure on accumulator bottles? Minimum 1,000 psi on a 3,000 psi system.
16 Berapakah tekanan operasi maksimum pada botol accumulator? 3,000 psi. BOP Closing
System
What is the maximum operating pressure on accumulator bottles? 3,000 psi.
17 Berapakah tekanan operasi minimum pada botol accumulator? Minimum 200 psi di atas tekanan pre-charge. BOP Closing
System
What is the minimum operating pressure on accumulator bottles? Minimum 200 psi above the pre-charge pressure.

Page 3 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
18 Pada accumulator, valve apakah yang digunakan agar tekanan accumulator By-pass valve. Barrier
BOP Closing
(3,000 psi) masuk ke manifold sehingga shear ram dapat digunakan untuk Policy
System
memotong pipa?
On accumulator, which valve is used to enable the accumulator pressure By-pass valve.
(3,000 psi) to fill the manifold so the shear ram can be used to cut a pipe?

19 Bagaimana posisi 4-way valve ketika operasi normal/drilling: open atau 4-way valve untuk BOP harus selalu di posisi open. BOP Closing
close? 4-way valve untuk HCR harus selalu di posisi close. System
What is the normal position for a 4-way valve while normal/drilling 4-way valve for BOP must be in open position.
operation: open or close? 4-way valve for HCR must be in close position.
20 Kapan 4-way valve diperbolehkan di posisi block? Hanya ketika perbaikan atau rig moving. BOP Closing
System
When can the 4-way valve be in the block position? Only on repair or rig moving.
21 Berapakah waktu maksimum untuk menutup Annular BOP dengan ukuran Harus menutup dalam waktu 30 detik. BOP Closing
lebih kecil dari 18-3/4" dan Ram BOP? System
What is the maximum time to close Annular BOP less than 18-3/4" and Should be closed in 30 seconds.
Ram BOP?
22 Berapakah waktu maksimum untuk menutup Annular BOP dengan ukuran Harus menutup dalam waktu 45 detik. BOP Closing
lebih besar dari 18-3/4"? System
What is the maximum time to close Annular BOP larger than 18-3/4"? Should be closed in 45 seconds.

23 Berapakah kapasitas minimum fluida reservoir yang harus dimiliki oleh Kapasitas minimumnya sebanyak 2x volume usable fluid. BOP Closing
sebuah accumulator? System
What is the minimum reservoir fluid capacity on an accumulator? Minimum capacity is 2x usable fluid volume
24 Apakah kita boleh mengunci 4-way valve untuk blind/shear ram pada Tidak boleh. Karena akan menghalangi pengoperasian 4-way valve tersebut BOP Closing
accumulator unit? Mengapa? dari remote panel tanpa ada intervensi. System
Can we lock the 4-way valve for blind/shear ram on an accumulator unit? We cannot lock it. Because it will prevent the 4-way valve to be operated
Why? from remote panel without intervention.
25 Apakah kegunaan air pump & electric pump pada accumulator unit? Sebagai sumber tenaga untuk memompakan hydraulic fluid dari reservoir BOP Closing
ke dalam botol-botol accumulator dan menjaga tekanannya tetap 3,000 System
psi.
What is the purpose of air pump & electric pump on an accumulator unit? As power source to pump hydraulic fluid from reservoir to accumulator
bottles and maintain the pressure at 3,000 psi.
26 Apakah kegunaan regulator pada accumulator unit? Untuk menurunkan tekanan hydraulic fluid dari 3,000 psi ke tekanan yang BOP Closing
dapat digunakan untuk mengoperasikan Annular BOP, Ram BOP dan juga System
HCR valve.
What is the purpose of regulator on an accumulator unit? To lower hydraulic fluid pressure from 3,000 psi to a more usable pressure
to operate Annular BOP, Ram BOP and HCR valve.
Page 4 of 21 Rev. 5 Oct 2012
Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
27 Mengapa handle 4-way valve untuk Blind/Shear Ram perlu diberi cover Agar tidak dioperasikan secara tidak disengaja. Cover/protection tersebut Barrier
BOP Closing
atau protection? diharapkan membuat orang yang akan mengoperasikan Blind/Shear Ram Policy
System
tahu dan sadar atas apa yang akan dikerjakannya.
Why does 4-way valve handle for Blind/Shear Ram need to be covered or To avoid it being operated unintentionally. Cover/protection will make
protected? someone who is going to operate Blind/Shear Ram to fully understand and
aware on what he is about to do.
28 Berapakah tekanan di pressure gauge Manifold pada sebuah unit 1,500 psi BOP Closing
accumulator? System
What is the pressure on Manifold pressure gauge on accumulator unit? 1,500 psi

29 Berapakah tekanan di pressure gauge Annular pada sebuah unit 500 psi - 1500 psi BOP Closing
accumulator? System
What is the pressure on Annular pressure gauge on accumulator unit? 500 psi - 1500 psi

30 Apakah kegunaan by-pass valve pada accumulator unit? Untuk mem-by-pass tekanan accumulator (3,000 psi) agar mengalir BOP Closing
langsung ke manifold untuk mengoperasikan shear ram. System

What is the purpose of by-pass valve on accumulator unit? To by-pass accumulator pressure (3,000 psi) to flow directly to manifold in
order to operate shear ram.

31 Air pump/electric pump pada accumulator terus menyala secara berkala Menandakan kemungkinan adanya kebocoran pada accumulator --> pompa BOP Closing
walaupun tidak ada fungsi BOP yang dijalankan, menandakan apakah hal berusaha mempertahankan tekanan yang turun karena adanya kebocoran. System
itu?
Air/electric pump on accumulator keep running automatically in a periodic It indicates the possibility of leaking in the accumulator --> the pumps are
time eventhough no BOP is funcitoned. What does this indicate? trying to maintain accumulator pressure that is dropping due to leak.

32 Mengapa hydraulic line yang menghubungkan accumulator dengan rams Ketika Shear Ram akan digunakan maka tekanan accumulator akan di-by- BOP Closing
dan HCR harus di-test dengan 3,000 psi? pass sehingga semua hydraulic line pada manifold akan terisi dengan 3,000 System
psi sehingga harus di-test dengan tekanan sebesar itu.

Why does the hydraulic line that connects accumulator with rams and HCR When using Shear Ram, accumulator pressure will be by-passed and all
need to be tested with 3,000 psi? hydraulic lines will be filled with 3,000 psi thus need to be tested with the
same pressure.

Page 5 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
33 Tekanan apa yang dijadikan batas tekanan maksimum ketika melakukan Tekanan yang paling lemah diantara tekanan berikut: tekanan rating BOP, Barrier
Bullheading
bullheading? tekanan rating wellhead, tekanan burst casing, tekanan burst tubing atau Policy
tekanan pecah formasi (fract pressure).
Which pressure is considered as maximum pressure limit when performing Lowest pressure from the following: BOP rating pressure, wellhead rating
bullheading? pressure, casing burst pressure, tubing burst pressure or formation fract
pressure.
34 Mengapa pump rate (SPM) ketika bullheading harus dimulai dari yang Untuk mendapatkan injectivity rate yang memastikan jika fluida dapat Bullheading
paling rendah? dipompakan masuk kembali ke dalam formasi.
Why do we need to start with the lowest pump rate (SPM) when To obtain injectivity rate and confirms that fluid can be pumped back into
performing bullheading? the formation.
35 Berapa banyak volume kill fluid yang dipompakan ketika melakukan Paling sedikit sejumlah volume tubing/string ditambah dengan volume Bullheading
bullheading? casing dari ujung tubing hingga ke lubang perforasi paling bawah.

What is the volume of kill fluid to be pumped while bullheading? At least equal to tubing/string volume plus the casing volume from tubing
tail to the bottom perforation.
36 Ketika menghitung berat Kill Fluid yang akan dipompakan ketika Kedalaman perforasi yang paling atas. Bullheading
bullheading, kedalaman perforasi mana yang digunakan?
When calculating Kill Fluid weight to be pumped for bullheading, which Top perforation depth.
perforation depth is used?
37 Ketika bekerja dengan Coiled Tubing Unit (CTU), data apa yang perlu Tubing management program yang mencatat jumlah bend cycle fatigue Coiled Tubing
dimintakan kepada penyedia coiled tubing? dan sisa masa pakai string coiled tubing.
When working with Coiled Tubing Unit (CTU), what data do we need to Tubing management program that records number of bend cycle fatigue
request to the coiled tubing provider? and remaining service life of the coiled tubing string.
38 Faktor apa saja yang mempengaruhi limit dari coiled tubing? OD coiled tubing, wall thickness, ovality, material yield strength dan adanya Coiled Tubing
kerusakan di badan coiled tubing.
What factors affecting the coiled tubing limit? Coiled tubing OD, wall thickness, ovality, material yield strength and
damage on coiled tubing.
39 Berapa batas ke-ovalan (ovality) coiled tubing sehingga diturunkan rating- Batas maksimum ovality = 3% (CVX) sementara API adalah 5%. Coiled Tubing
nya atau tidak dapat dipakai lagi?
What is the ovality limit for a coiled tubing before it is derated or junked? Maximum ovality limit = 3% (CVX) while API is 5%.

40 Berapakah rate pompa (SPM) yang direkomendasikan untuk operasi killing Serendah mungkin untuk meminimalkan friksi atau ECD. Constant
well? Bottom Hole
What is the recommended pump rate (SPM) for killing well operation? As low as possible to minimize friction or ECD. Pressure

Page 6 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
41 Mengapa sangatlah penting bagi Mud Eng/Mud Boy untuk memastikan jika Agar lumpur yang dipompakan homogen. Fluida yang homogen sangat Barrier
Constant
MW yang dipompakan ketika killing well selalu tetap sama? penting ketika killing untuk memungkinkan kita menjaga konstan BHP. PolicyHole
Bottom
Pressure
Why is it important for Mud Eng/Mud Boy to ensure consistent MW is To make sure fluid being pumped is homogen. Homogen fluid is important
being pumped while killing a well? during killing to enable us to maintain BHP constant.
42 Apakah tekanan Slow Circulating Rate (SCR) perlu diukur secara berkala? Tidak perlu. Tekanan SCR bisa didapatkan ketika sirkulasi sudah dimulai Constant
setelah memperoleh SIDPP & ICP --> SCR = ICP - SIDPP. Pada Driller's Bottom Hole
Method, SCR tidak dibutuhkan pada sirkulasi pertama. Pressure
Do we need to periodically measure the Slow Circulating Rate (SCR) No. SCR pressure can be obtained when circulation is started after
pressure? obtaining SIDPP & ICP --> SCR = ICP - SIDPP. In Driller's Method, SCR is not
required for the first circulation.
43 Mengapa tidak direkomendasikan untuk menggunakan pump rate (SPM) Karena pump rate (SPM) yang tinggi akan menimbulkan ECD yang tinggi Constant
yang tinggi untuk killing well? juga dan tidak menguntungkan ketika killing. Bottom Hole
Why is high pump rate (SPM) not recommended for killing well? High pump rate (SPM) creates high ECD that is not good for killing Pressure
operation.
44 Pada saat mensirkulasikan kick, tekanan apa yang harus dijaga konstan Tekanan casing yang tertera pada saat itu. Constant
ketika mengubah kecepatan pompa? Bottom Hole
When circulating a kick, which pressure that needs to be kept constant Current casing pressure. Pressure
while changing the pump speed?
45 Sehubungan dengan prinsip U-tube, bagaimana caranya membuat Ubah tekanan di casing sebesar perubahan yang diinginkan pada drill pipe. Constant
perubahan tekanan pada drill pipe ketika sedang melakukan sirkulasi Setelah lag time terlampaui maka tekanan di drill pipe juga akan berubah Bottom Hole
melalui choke? dengan jumlah yang sama. Pressure
Related to U-tube principle, how do we make any adjustment on the drill Make the adjustment by the required amount on casing pressure. After the
pipe pressure while circulating through the choke? lag time, drill pipe pressure will change accordingly.
46 Apa yang dimaksud dengan Bring Pumps Up to Speed (BPUTS)? Proses memulai/menghentikan pompa dengan menjaga konstan tekanan Constant
casing agar bottom hole pressure tetap konstan dan tidak ada influx yang Bottom Hole
masuk lagi. Pressure
What is Bring Pumps Up to Speed (BPUTS)? Process of starting/stopping the pump while maintaining bottom hole
pressure constant by keeping the casing pressure constant to avoid more
influx in the hole.
47 Ketika mematikan sumur, metode killing apa yang harus digunakan? CVX well control policy menyatakan Driller's Method sebagai metode untuk Driller's
killing. Method
What killing method needs to be used for killing a well? CVX well control policy states Driller's Method as the standard killing
method.
48 Apakah tujuan dari sirkulasi pertama pada Driller's Method? Mengeluarkan influx dari dalam sumur. Driller's
Method
What is the purpose of the first circulation of the Driller's Method? To remove influx from the well.

Page 7 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
49 Lumpur apa yang digunakan pada sirkulasi pertama Driller's Method: Lumpur lama (Original Mud Weight). Barrier
Driller's
lumpur lama atau lumpur baru? Policy
Method
Which mud is used in the first circulation of the Driller's Method: old mud Old mud (Original Mud Weight).
or kill mud?
50 Tekanan mana yang harus tetap dijaga konstan selama sirkulasi pertama Tekanan pada drill pipe sesuai dengan Initial Circulating Pressure (ICP). Driller's
pada Driller's Method? Method
Which pressure needs to be kept constant during first circulation of the Drill pipe pressure, as per Initial Circulating Pressure (ICP).
Driller's Method?
51 Setelah semua influx keluar dan sumur di-shut in lagi, bagaimana DP dan CP seharusnya menunjukkan angka yang sama yaitu sebesar SIDPP Driller's
seharusnya pembacaan tekanan pada DP dan CP? di kondisi awal. Method
After all influx is out and the well is shut-in, what should be the reading on DP and CP should show the same pressure which is the same as the initial
DP and CP? SIDPP.
52 Apakah tujuan dari sirkulasi kedua pada Driller's Method? Mematikan sumur setelah semua influx berhasil dikeluarkan pada sirkulasi Driller's
pertama Driller's Method. Method
What is the purpose of the second circulation of the Driller's Method? To kill the well after all influx is circulated out from the well in the first
circulation of the Driller's Method.
53 Lumpur apa yang digunakan pada sirkulasi kedua Driller's Method: lumpur Lumpur baru (Kill Mud Weight). Driller's
lama atau lumpur baru? Method
Which mud is used in the second circulation of the Driller's Method: old New mud (Kill Mud Weight).
mud or new mud?
54 Tekanan apa yang digunakan untuk menghitung Kill Mud Weight: SIDPP SIDPP karena drill pipe terisi seluruhnya dengan lumpur sementara di Driller's
atau SICP? annulus masih terdapat influx. Method
What pressure is used to calculate the Kill Mud Weight: SIDPP or SICP? SIDPP since drill pipe is filled entirely with mud or fluid while the annulus
still has influx in it.
55 Kedalaman apa yang digunakan untuk menghitung Kill Mud Weight: True Vertical Depth (TVD). Driller's
Measure Depth (MD) atau True Vertical Depth (TVD)? Method
What depth is used to calculate Kill Mud Weight: Measured Depth (MD) or True Vertical Depth (TVD).
True Vertical Depth (TVD)?
56 Pada sirkulasi kedua dari Driller's Method, tekanan apa yang dijaga konstan Tekanan casing sebesar SICP di akhir sirkulasi pertama Driller's Method Driller's
ketika memompakan KMW dari permukaan hingga sampai ke bit? yang seharusnya sama dengan SIDPP di saat awal. Method

In the first circulation of the Driller's Method, what pressure is kept Casing pressure per SICP at the end of the first circulation of the Driller's
constant while pumping the KMW from surface to the bit? Method which should be equal to the initial SIDPP.

Page 8 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
57 Pada sirkulasi kedua dari Driller's Method, tekanan apa yang dijaga konstan Tekanan drillpipe sebesar Final Circulating Pressure (FCP). Barrier
Driller's
ketika memompakan KMW dari bit sampai kembali ke permukaan? Policy
Method

In the second circulation of the Driller's Method, what pressure is kept Drillpipe pressure pas er Final Circulating Pressure (FCP).
constant while pumping the KMW from the bit back to surface?

58 Apa yang perlu diwaspadai jika acid yang disirkulasikan ke dalam sumur Ketika kembali ke permukaan, acid tersebut mungkin membawa gas Fluid
telah kembali ke permukaan? sebagai hasil reaksi kimia dengan formasi.
What needs to be awared of when circulating acid from downhole back to When back on surface, acid might have gas as the result of chemical
the surface? reaction with the formation.
59 Apakah fungsi fluida yang digunakan sebagai packer fluid? * memberikan tekanan pada packer & seal agar tidak bocor Fluid
* memberikan tekanan diferensial pada tubing & casing
* tujuan khusus seperti mencegah korosi
What is the purpose of packer fluid? * provide pressure on packer & seal to prevent it from leaking
* provide differential pressur on tubing & casing
* special purpose such as preventing corrosion
60 Apa yang perlu dilakukan agar tidak terjadi kick? Menjaga lubang selalu terisi penuh dengan berat lumpur yang dibutuhkan Kick
Detection
What needs to be done to prevent kick from occuring? Maintain the hole full with required mud weight.

61 Sebutkan 3 indikator positif terjadinya kick * Terdapat aliran lumpur ketika pompa mati Kick
* Penambahan laju alir dengan rate pompa yang tetap Detection
* Pit gain (penambahan lumpur pada pit)
What are the 3 positive kick indicator? * Flow with the pumps off
* Increase in flow with constant pump rate
* Pit gain
62 Apa yang harus dilakukan ketika terjadi drilling break? Matikan pompa, periksa apakah ada aliran lumpur. Kick
Detection
How to react on a drilling break? Shut down pumps, check for flow.
63 Mengapa berat lumpur yang digunakan harus lebih berat dibandingkan Untuk mencegah influx masuk ke dalam sumur. Kick
dengan tekanan formasi? Detection
Why does the mud weight being used need to be heavier than the To prevent influx from coming into the well.
formation pressure?
64 Mengapa perlu dilakukan space out sebelum menutup BOP? Agar tool joint tidak berada di dalam BOP stack. Kick
Detection
Why do you need to space out before closing the BOP? To avoid having tool joint in the BOP stack.

Page 9 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
65 Beri contoh possible kick indicator * Drilling break Barrier
Kick
* Perubahan bentuk cutting Policy
Detection
* Kenaikkan temperatur di flow line
* Perubahan rheology pada mud
* Kenaikkan kadar Cl
What are the possible kick indicators? * Drilling break
* Change in cutting size
* Increase in flow line temperature
* Change in mud rheology
* Increase in Cl content
66 Apakah yang dimaksud dengan swabbing? Swabbing adalah efek dari menarik pipa terlalu cepat sehingga Kick
menghasilkan pengurangan tekanan di dalam lubang yang kemudian Detection
memungkinkan influx untuk masuk.
What does swabbing mean? Swabbing is the effect of pulling pipe too fast that creates pressure
reduction downhole thus allowing influx in the well.

67 Posisi bit sudah dicabut hingga ke dalam casing ketika crew menyadari Tripping in kembali ke bottom dan mensirkulasi lumpur paling sedikit 1x Kick
adanya perbedaan volume untuk mengisi lubang. Dilakukan flow check dan bottom up untuk memastikan tidak ada influx yang masuk karena Detection
hasilnya negatif (tidak ada aliran). Apa tindakan yang paling baik untuk swabbing.
dilakukan terhadap situasi ini?
Bit has been pulled inside the casing when crew noticed volume different to Tripping back to bottom and circulate at least 1x bottom up to make sure
fill the hole. Flow check turns out to be negative (no flow from the well). there is no influx in the well due to swabbing.
What is the best action for this situation?
68 Pada operasi rig saat ini, apa yang harus dilakukan jika terjadi kick sekarang Jawaban sesuai dengan operasi rig saat ini. Kick
ini? Detection
With your current rig operation, what needs to be done if there is a kick Answer as per current rig operation.
right now?
69 Apa yang harus dilakukan oleh Mud Eng/Mud Boy jika melihat perubahan Melaporkan kepada Driller karena perubahan bentuk/jumlah cutting Kick
bentuk/jumlah cutting yang keluar di shaker? merupakan possible kick indicator. Detection
What should the Mud Eng/Mud Boy do if they notice changes on the Report to Driller as the changes on the shape/amount of cuttings are
shape/amount of cuttings coming out of the shaker? possible kick indicators.
70 Apakah kegunaan dari trip tank? Untuk mengetahui jika ada penambahan/pengurangan volume yang tidak Kick
sesuai dengan volume pipa yang dimasukkan atau dicabut. Detection

What is the purpose of trip tank? To identify deviation on mud volume being filled to/received from the well
that does not match with the pipe volume being tripped in or pulled out.

Page 10 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
71 Ketika sedang tripping out, ternyata volume mud yang diisikan ke dalam Check flow. Jika positf maka shut in well dan jika negatif maka bersiap Barrier
Kick
lubang lebih sedikit dari volume pipa yang dicabut. Apa yang terjadi? Apa untuk trip kembali ke bottom. Policy
Detection
tindakan yang terbaik?
When tripping out, volume of mud pumped into the well is less than Check flow. If positive then shut in well and if negative then prepare to trip
volume of pipe being pulled. What happen? What is the proper action? back to bottom.

72 Mud Boy menimbang berat lumpur yang keluar dari flow line sebanyak 3x Kemungkinan masuknya influx ke dalam lubang. Mud Boy harus Kick
dan menemukan lumpur semakin ringan. Apa yang terjadi? Apa yang harus memberitahukan kepada Driller. Detection
dilakukan oleh Mud Boy?
Mud Boy measured the mud weight coming out of the flow line for 3x and Possibility of influx in the well. Mud Boy needs to inform the Driller.
found the mud is getting lighter. What happen? What should be done by
the Mud Boy?
73 Jika mud yang dipompakan ternyata mengandung gas yang terlarut, apa Gas terlarut akan memperingan lumpur sehingga HP berkurang dan dapat Kick
dampaknya pada sumur? menyebabkan kondisi underbalance. Detection
If mud being pumped has gas in it, what is the impact to the well? Dissolve gas will lightened the mud thus reducing HP and creating
underbalance condition.
74 Apakah kegunaan dari choke drill? Untuk melatih choke operator dalam mengoperasikan choke dan juga men- Kick
check akurasi pressure gauge. Detection
What is the purpose of choke drill? To train the choke operator in operating the choke and also to check
pressure gauge accuracy.
75 Apakah yang dimaksud dengan influx? Masuknya fluida yang tidak dinginkan yang berasal dari sumur. Kick
Detection
What is influx? Undesired flow of formation fluid into the well.

76 Mengapa influx bisa masuk ke dalam sumur? Influx bisa masuk jika tekanan hidrostatik (HP) di dalam sumur lebih kecil Kick
dari tekanan formasi. Detection
What causes influx to flow into the well? Influx can flow into the well when hydrostatic pressure (HP) in the well is
less than the formation pressure.
77 Mungkinkah terjadi kick ketika sedang Waiting On Cement (WOC)? Dapat terjadi. Ketika semen mulai mengeras dan bertransisi dari fase cair Kick
Mengapa? (liquid) ke padat maka ia kehilangan HP untuk menahan tekanan formasi Detection
sementara semen belum cukup keras (compressive strength masih rendah)
dan belum dapat menahan tekanan formasi tersebut.

Can a kick happen while Waiting On Cement (WOC)? Why? Yes it can. When cement starts to gel and in transition from liquid phase to
solid phase it looses its hydrostatic pressure (HP) while it has not develop
enough compressive strength to withstand the formation pressure.

Page 11 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
78 Apa yang perlu diperhatikan ketika memompakan beberapa fluida dengan Fluid yang lebih ringan dapat mengakibatkan penurunan tekanan Barrier
Kick
berat yang berbeda (misal: memompakan water ahead diikuti dengan hidrostatik (HP) dan menyebabkan well menjadi underbalance. Policy
Detection
spacer, per-flush, lead & tail slurry)?
What needs to be awared of when pumping some fluids with different fluid Lighter fluid can cause reduction in hydrostatic pressure (HP) and inducing
densities (example: pumping water ahead followed by spacer, pre-flush, underbalance in the well.
lead & tail slurry)?
79 Apa yang dapat terjadi pada sumur jika rangkaian pipa dicabut dengan Dapat menyebabkan swabbing. Kick
sangat cepat? Detection
What could happen with the well if drill string is being pulled very fast from It could cause swabbing.
the well?
80 Apa yang dapat terjadi pada sumur jika rangkaian pipa dimasukkan dengan Dapat terjadi surge pressure yang tinggi sehingga dapat menyebabkan Kick
sangat cepat? pecahnya formasi. Detection
What could happen with the well if drill string is being run very fast into the It could cause high surge pressure and break the formation.
well?
81 Mengapa loss circulation dapat menyebabkan kick? Loss circulation menyebabkan fluid level turun sehingga tekanan Kick
hidrostatik berkurang dan well menjadi underbalance. Detection

How can loss circulation causing a kick? Loss circulation could cause drop in fluid level thus reducing hydrostatic
pressure and causing underbalance in the well.

82 Hal apa saja yang dapat menyebabkan loss circulation? * Tripping in terlalu cepat (surge pressure) Kick
* ECD yang terlalu tinggi Detection
* Komunikasi dengan zona loss
What could cause loss circulation? * Tripping in to fast (surge pressure)
* High ECD
* Communication with a loss zone
83 Sehubungan dengan well control, dragging ketika mencabut pipa dapat Swabbing --> dragging dapat disebabkan oleh cutting yang menumpuk Kick
menyebabkan apa? sehingga dapat mengakibatkan swab. Detection
Related to well control, what could happen if you experience drag while Swabbing --> dragging could be caused by cutting bed that might cause
pulling the pipe? swabbing.
84 Pada operasi apa saja kita harus memiliki rencana/plan untuk situasi well Pada SEMUA operasi. Kick
control? Detection
On which operation that we need to have plan for well control situation? On ALL operation.

Page 12 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
85 Untuk Hard Shut-in, hanya diperlukan satu step untuk menutup sumur, Menutup Annular BOP --> diskusikan perbedaannya dengan Soft Shut-in Barrier
Kick
yaitu ……. untuk menunjukkan mengapa CVX memilih Hard Shut-in, yaitu waktu yang Policy
Detection
lebih singkat sehingga pada akhirnya volume influx akan lebih sedikit.

For Hard Shut-in, there is only one step needed to shut-in the well, which is Close Annular BOP --> discuss the difference with Soft Shut-in to show why
……. CVX chose Hard Shut-in, which is to minimize the time and ultimately will
minimize influx volume.
86 Betul atau salah: swabbing hanya mungkin terjadi ketika bit berada di open Salah. Swabbing juga dapat terjadi ketika bit berada di dalam casing Kick
hole. Jelaskan jawabannya. terlebih lagi jika bit dalam kondisi balling. Detection

True or false: swabbing can only happened when the bit is in the open hole False. Swabbing could also occur with the bit inside the casing especially if
section. Explain the answer. the bit is in balling condition.

87 Mengapa crew di mud tank harus berhati-hati agar tidak ada air berlebihan Karena jika ada banyak air yang masuk ke dalam active pit akan dapat Kick
yang masuk ke dalam active pit yang digunakan dalam operasi drilling atau menurunkan berat lumpur yang ada di dalamnya sehingga menyebabkan Detection
workover? berkurangnya tekanan hidrostatik (HP) di dalam lubang dan pada akhirnya
menyebabkan sumur menjadi underbalance.
Why does the crew in the mud tank need to take extra caution to ensure Excessive water in the active pit could lower the mud weight inside thus
there is no excessive water get into the active pit that is being used in reducing hydrostatic pressure (HP) in the well and causing underbalance in
drilling or workover operation? the well.
88 Apa yang dimaksud dengan Trip Drill? Well control drill yang dilakukan saat tripping ketika bit sudah berada di Kick
dalam casing. Simulasikan terjadinya kick (dengan memanipulasi PVT/mud Detection
logger jika tersedia atau melalui pemberitahuan secara langsung) dan lihat
reaksi Driller serta crew dalam melakukan 3S. Umumkan jika itu hanyalah
latihan sebelum Driller menutup BOP.

What is Trip Drill? Well control drill that is done while tripping with the bit already inside the
casing. Simulate kick (by manipulating PVT/mud logger if available or by
direct information) and observe Driller & Crew reaction in performing the
3S. Declare it is merely a drill before Driller close the BOP.

Page 13 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
89 Apa yang dimaksud dengan Pit Drill? Well control drill yang dilakukan ketika operasi rutin. Simulasikan terjadinya Barrier
Kick
kick (dengan memanipulasi PVT/mud logger jika tersedia atau melalui Policy
Detection
pemberitahuan secara langsung) dan lihat reaksi Driller serta crew dalam
melakukan 3S, umumkan jika itu hanyalah latihan sebelum Driller menutup
BOP. Catat waktu yang dibutuhkan crew untuk merespon, harus kurang
dari satu menit.
What is Pit Drill? Well control drill that is done during normal operation. Simulate kick (by
manipulating PVT/mud logger if available or by direct information) and
observe Driller & Crew reaction in performing the 3S. Declare it is merely a
drill before Driller close the BOP. Record the time needed by the crew to
respond, it has to be less than one minute.

90 Apa yang harus dilakukan jika ada permintaan untuk memperdalam lubang STOP, hitung kembali Kick Tolerance, buat MOC dan Risk Assessment (RA). Kick
(deepening) yang tidak ada di rencana/program awal? Deepening baru bisa dikerjakan jika MOC & RA telah disetujui oleh semua Tolerance
pihak yang terlibat.
What should be done when there is a request to deepen the well that is not STOP, recalculate Kick Tolerance, develop MOC and Risk Assessment (RA).
in the initial plan/program? Deepening can only be executed if MOC & RA have been approved by all
involve parties.
91 Sirkulasi pertama Driller's Method baru dimulai namun Casing Pressure Tetap melanjutkan sirkulasi dan JANGAN menurunkan CP. Jika CP dijaga Kick
(CP) sudah mendekati MISICP, apa yang harus dilakukan? agar lebih kecil dari MISICP maka well akan menjadi underbalance dan Tolerance
lebih banyak lagi influx yang masuk.
First circulation of the Driller's Method was just started but the Casing Keep circulating and do NOT decrease CP. If CP is maintained lower than
Pressure (CP) is getting close to MISICP, what should we do? the MISICP, the well will be underbalanced and more influx will flow into
the well.
92 Ketika drilling mendekati casing point ternyata volume kick yang dapat * Reset PVT alarm untuk dapat mendeteksi pit gain lebih dini. Kick
diterima oleh well berkurang. Apa yang dapat dilakukan? * Shut-in sumur jika ditemukan possible kick indicator. Tolerance
While drilling close to the casing point, the kick volume that can be * Reset PVT alarm to detect pit gain immediately.
contained in the well is getting less. What should we do? * Shut-in well on possible kick indicator.
93 Apa yang dimaksud dengan 3S ketika Drilling? * Space out Shut-in
* Shut down pump
* Shut in well
What is 3S while drilling? * Space out
* Shut down pump
* Shut in well

Page 14 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1
94 BOP apa yang digunakan ketika men-shut in well? BOP yang paling atas (biasanya Annular BOP). Barrier
Shut-in
Policy
Which BOP is used to shut in a well? Uppermost BOP (typically the Annular BOP).

95 Kepada siapa Driller atau crew perlu meminta ijin sebelum menutup sumur TIDAK PERLU MEMINTA IJIN DARI SIAPA PUN --> Driller mempunyai Shut-in
ketika terjadi kick? otoritas untuk segera menutup sumur ketika terjadi kick.

Whom the Driller or crew should asked permission to before shutting in a NO NEED TO ASK FOR PERMISSION --> Driller has the authority to
well on a kick? immediately shut in the well on a kick.
96 Shut in tipe apa yang digunakan di Chevron, hard atau soft shut in? Hard shut in. Shut-in

Which type of shut in is used in Chevron, hard shut in or soft shut in? Hard shut in.

97 Mengapa Chevron menggunakan hard shut in? Karena lebih cepat untuk menutup sumur sehingga meminimalkan volume Shut-in
influx yang masuk ke dalam sumur.
Why does Chevron use hard shut in? Because it is faster to shut in the well thus minimizing the influx volume
into the well.
98 Ketika sedang beroperasi, bagaimana posisi HCR dan choke jika HCR ditutup dan choke juga ditutup. Shut-in
menggunakan Hard shut in?
While operating, what is HCR and choke position when using hard shut in? HCR is closed and choke is also closed.

99 Bagaimana langkah menutup sumur menggunakan hard shut in? Space out agar tool joint di atas floor kemudian tutup Annular BOP dan Shut-in
buka HCR.
What are the steps to shut in the well when using hard shut in? Space out to make sure tool joint is above the floor and then close the
Annular BOP and open the HCR.
100 Jelaskan mengenai 3S ketika sedang tripping. * Pasang FOSV & kemudian tutup. Shut-in
* Space out.
* Shut in well dengan menutup BOP yang paling atas.
Explain 3S while tripping. * Stab in FOSV & close the same.
* Space out.
* Shut in well by closing the uppermost BOP.
101 Apa yang harus dilakukan Driller setelah men-shut in well jika terjadi kick? Memastikan tidak ada kebocoran pada peralatan dan mulai mencatat Shut-in
tekanan di DP dan Casing secara periodik (misal: per 5 menit).

What should the Driller do after shut-in a well when a kick occurs? Make sure there is no leaking on equipments and start to record drill pipe
pressure and casing pressure periodically (example: every 5 min.)

Page 15 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1 Mengapa semua crew harus menjauh dari rotary table ketika akan
102 Untuk menghindari adanya trapped gas di antara BOP dan Choke line yang Barrier
Shut-in
membuka BOP setelah selesai killing well? dapat terlepas dengan tiba-tiba ketika BOP dibuka. Policy

Why do all crews need to stay away from the rotary table when about to To avoid sudden release of trapped gas between the BOP and the Choke
open a BOP after killing a well? line when the BOP is open.
103 Selama operasi killing, BOP ditutup dan string tidak dapat digerakkan Situasi well control lebih beresiko dibandingkan dengan stuck pipe Shut-in
sehingga ada kemungkinan untuk stuck pipe. Apa yang harus dilakukan? sehingga disarankan untuk tidak menggerakkan pipa. Jika pipa digerakkan
maka akan beresiko untuk merusak rubber element pada Annular BOP
sehingga bisa bocor yang berarti situasi menjadi lebih berbahaya lagi.

While killing operation, BOP is closed and string cannot be moved thus Well control situation has more risk compare to stuck pipe thus it is
creating risk of stuck pipe. What should we do? suggested to keep the pipe static. If pipe is moved then it will create a risk
of damaging the rubber element on the Annular BOP and possibility of BOP
leaking that might lead to even more dangerous situation.

104 Data-data apa saja yang perlu dicatat oleh Driller setelah mengetahui Waktu terjadinya kick, jumlah pit gain, SIDPP dan SICP. Shut-in
adanya kick dan men-shut in sumur?
What data needs to be rocorded by the Driller upon identifying a kick and Time of kick, pit gain, SIDPP and SICP.
shutting in the well?
105 Fluida apa yang dapat dipompakan ke dalam lubang ketika terjadi steam Fluida apa saja yang tersedia di lokasi (air, lumpur, brine, etc.) Steam Kick
kick?
What fluid can be pumped into the hole on a steam kick? Any available fluid in the location (water, mud, brine, etc.)

106 Apa yang harus dilakukan untuk mencegah berubahnya brine/drilling mud * Memastikan tekanan hidrostatik di dalam sumur cukup untuk mencegah Steam Kick
menjadi steam? terbentuknya steam --> gunakan Steam Table
* Menjaga agar temperatur di dalam lubang tetap di bawah boiling point-
nya --> dengan meminimalkan static time (waktu di mana lumpur tidak
disirkulasikan) yang dapat menyebabkan temperatur menjadi naik.

What should be done to prevent brine/drilling mud from changing into * Make sure the hydrostatic pressure in the well is high enough to prevent
steam? steam --> use Steam Table
* Maintaining temperature in the well below its boiling point --> by
minimizing static time (time when the mud is not circulated) that would
caused temperature to increase.

Page 16 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1 Apa yang dapat dilakukan untuk mendeteksi tanda-tanda terjadinya steam Melakukan fingerprinting pada temperatur di flow line. Jika temperatur
107 Barrier
Steam Kick
kick? semakin tinggi maka kemungkinan lumpur di lubang sedang dipanasi dan Policy
dapat berubah menjadi steam.
What can be done to detect signs of steam kick? Fingerprinting on flow line temperature. If the temperature is increasing
then there is possibility the mud in the hole is being heated up and could
turned into steam.
108 Apa yang harus dilakukan oleh crew yang berada di rig floor jika steam Menjauh dari rig floor dan JANGAN mencoba memasang FOSV atau IBOP. Steam Kick
sudah mulai keluar dari dalam sumur atau string?
What should the crew on the rig floor do when steam is coming out of the Keep away from the rig floor and do NOT attempt to install FOSV or IBOP.
well or string?
109 Apakah fungsi weep/vent hole pada Ram BOP? Untuk mengetahui jika ada kebocoran pada primary seal. Surface BOP
What is the purpose of a weep/vent hole on Ram BOP? To identify any leak on primary seal. equipment
110 Apakah Annular BOP bisa digunakan untuk menutup lubang yang kosong Bisa, tetapi packing element-nya akan rusak dan perlu diganti sesudahnya. Surface BOP
(tidak ada pipa di dalamnya)? equipment
Can Annular BOP be used to close on an empty hole (with no pipe in it)? Yes it can, but the packing element will be damaged and need to be
replaced.
111 Apakah Annular BOP dapat digunakan untuk menutup lubang dengan Tidak. Karena spiral DC memiliki alur pada permukaannya sehingga akan Surface BOP
spiral DC di dalamnya tanpa kebocoran? Jika tidak, mengapa? terjadi kebocoran jika ditutup dengan Annular BOP. equipment

Can Annular BOP be used to close on a spiral DC without any leak? If not, No. Spiral DC has profile on its surface that would create leaks when closed
why? with an Annular BOP.
112 Apakah shear ram dapat memotong pipa pada tool joint-nya? Tidak, shear ram hanya dapat memotong pada bagian body pipa. Surface BOP
equipment
Can a shear ram cut a pipe on its tool joint? No, shear ram can only cut pipe on its body.
113 Apa beda FOSV dan IBOP? FOSV: memiliki ball valve, dibuka/tutup dengan menggunakan kunci, dapat Surface BOP
dilalui oleh wireline, tidak dapat mencegah aliran dari dalam string. equipment
IBOP: memiliki stick yang berfungsi untuk menahan valve agar tetap dalam
posisi terbuka, tidak dapat dilalui oleh wireline, mencegah aliran balik dari
dalam string.

What is the different between FOSV and IBOP? FOSV: has a ball valve, open/close with a wrench, wireline can pass through
it, could not prevent flow from inside the well.
IBOP: has a stick to hold the valve to keep it in open position, wireline could
not passed, prevent flow back from the string.

Page 17 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1 Jika mendapatkan kick ketika sedang tripping in/out, apa yang harus
114 FOSV. Karena FOSV memiliki ID yang lebih besar dibandingkan IBOP Barrier
Surface BOP
dipasangkan pada pipa terlebih dahulu: FOSV atau IBOP? Mengapa? sehingga lebih mudah dipasangkan jika ada aliran/kick dari dalam string. Policy
equipment
Setelah FOSV terpasang dan ditutup, barulah kemudian dipasang IBOP di
atasnya.
If a kick is taken while tripping in/out, what should be installed first on the FOSV. Because FOSV has larger ID compares to IBOP thus it is easier to be
pipe: FOSV or IBOP? Why? installed when there ins a kick/flow from inside the string. Once FOSV is
installed and closed, install IBOP on top of it.
115 Bagaimana seharusnya posisi FOSV dan IBOP ketika sedang tidak dipakai? Harus dalam posisi open agar tersedia untuk dipasangkan. Surface BOP
Posisi buka atau tutup? equipment
What is the position of FOSV and IBOP when not being used? Must be in open position to make it easier to install it.
116 Berapa kali ring gasket pada connection BOP boleh digunakan? Satu kali. Jika connection antar BOP dibongkar maka ring gasket harus Surface BOP
diganti dengan yang baru. equipment
How many times can we use a ring gasket on BOP connection? One time. If the connection between BOPs are disconnected then ring
gasket needs to be replaced with a new one.
117 Sesuai guideline Chevron, Ram BOP tipe apa yang dipasang paling atas Blind ram. Surface BOP
(persis di bawah Annular BOP)? equipment
As per Chevron guideline, what type of Ram BOP is installed on the top Blind ram.
(right under the Annular BOP)?
118 Apakah shear ram dapat digunakan untuk memotong kabel wireline? Tidak, harus menggunakan cable cutter. Surface BOP
equipment
Can a shear ram be used to cut a wire line? No, it has to be done with cable cutter.

119 Ketika melakukan test BOP, test pressure mana yang dilakukan lebih dulu: Low pressure dulu baru kemudian high pressure. Karena ada kebocoran Surface BOP
high pressure atau low pressure? Mengapa? yang mungkin tertutup jika dikenakan high pressure lebih dulu sehingga equipment
tidak terlihat bocor ketika dilanjutkan dengan low pressure test.

When testing a BOP, which pressure test is performed first: high pressure or Low pressure test first and then high pressure. There are some leaks that
low pressure? Why? might be plugged when exposed to high pressure thus the leaks are not
visible when the test is continued with the low pressure test.

120 Kapan pressure test pada peralatan well control harus dilakukan? * Sebelum spud in atau setelah dipasang. Surface BOP
* Setelah dilepas (disconnect) atau dilakukan perbaikan tapi hanya terbatas equipment
pada peralatan yang diperbaiki saja.
* Tidak melebihi 21 hari.
When does pressure test on well control equipment need to be performed? * Before spud in or after installation.
* After disconnect or repair but only on the affected equipment.
* Not to exceed 21 days.

Page 18 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1 Mengapa pada operasi drilling harus menggunakan bit float valve?
121 Untuk mencegah masuknya influx ke dalam string. Barrier
Surface BOP
Policy
equipment
Why do we need to use bit float valve on drilling operation? To prevent influx from coming into the string.
122 Apakah Annular BOP dapat menutup lubang dengan pipa screen liner di Tidak. Karena screen liner memiliki lubang-lubang sehingga influx tetap Surface BOP
dalamnya tanpa ada kebocoran? bisa mengalir ke atas meskipun annular BOP ditutup. equipment
Can an Annular BOP closing in on a hole with pipe screen liner in it? No. Screen line has perforated holes on it that enable influx to flow to the
surface eventhough Annular BOP is closed.
123 Ketika melakukan test BOP, ditemukan cairan keluar dari weep/vent hole Hentikan test, perbaiki dulu ram BOP dan test lagi hingga tidak ada Surface BOP
pada Ram BOP. Apa yang harus dilakukan? kebocoran. equipment
When performing BOP test, fluid was found coming out of the weep/vent Stop the test, fix ram BOP and retest until no more leak is observed.
hole on Ram BOP. What should be done?
124 Bit float jenis apa yang harus dipasang pada string ketika drilling? CVX Policy menyatakan jika Solid Flot harus terpasang pada operasi drilling.

Which type of bit float valve shall be installed in the string while drilling? CVX Policy stated that Solid Float must be installed during drilling
operation.
125 Ketika sedang mensirkulasikan kick, ditemukan cairan keluar dari weep Gunakan Plasctic Injection untuk memperbaiki seal ram yang bocor. Surface BOP
hole pada Ram BOP. Apa yang harus dilakukan? equipment
When circulating a kick, fluid was found coming out of the weep hole on Use Plastic Injection to temporary fix the leaking seal. Once well is under
Ram BOP. What should be done? control, repair the BOP.
126 Mengapa bloey line pada choke manifold harus lurus (tidak boleh memiliki Untuk meminimalkan friksi dan kemungkinan line bocor karena terkikis Surface BOP
sudut dan berbelok-belok)? oleh pasir yang terbawa oleh gas. equipment
Why does boloey line on a choke manifold has to be straight (no slopes and To minimize friction and posibility of leaksing due to erroded by sand that
turns)? comes with the gas.
127 Alat apa yang harus disiapkan di atas floor jika menggunakan beberapa Cross over yang sesuai dengan ukuran pipa yang dipakai di dalam lubang Surface BOP
ukuran pipa sementara hanya tersedia satu ukuran FOSV dan IBOP? dan FOSV/IBOP. equipment

What tool need to be available on the floor when using some different pipe Cross over that matches different pipe size being used in the hole and
sizes while there is only one size of FOSV and IBOP? FOSV/IBOP.
128 Mengapa salah satu wing valve pada wellhead harus dibuka ketika sedang Untuk mengetahui jika ada kebocoran pada test plug dan untuk mencegah Surface BOP
melakukan test BOP dengan menggunakan test plug? terkumpulnya tekanan di dalam casing jika test plug bocor. equipment

Why does one of the wing valve on the wellhead need to be kept open To identify any leak on test plug and to prevent pressure build up in the
while testing the BOP with a test plug? casing if the test plug leaks

Page 19 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1 Fluida apa yang digunakan untuk test BOP?
129 Air. Ini untuk mencegah adanya solid (dari mud) yang dapat menyumbat Barrier
Surface BOP
kebocoran pada seal BOP sehingga tidak terlihat. Policy
equipment
What fluid can be used for testing the BOP? Water. This is to prevent any solid (from mud) that could plug any leaks on
the BOP seal and make it undetectable.
130 Berapa besar tekanan yang direkomendasikan untuk low pressure test 200 - 300 psi. Surface BOP
pada peralatan BOP (Annular, Ram, Choke)? equipment
What is the recommended pressure for low pressure test on BOP 200 - 300 psi.
equipments (Annular, Ram, Choke)?
131 Berapa besar tekanan yang direkomendasikan untuk high pressure test 70% dari working pressure Annular BOP. Surface BOP
pada Annular BOP? equipment
What is the recommended pressure for high pressure test on Annular BOP? 70% of Annular BOP working pressure.

132 Berapa lama pressure harus ditahan ketika test BOP? Minimum 5 menit. Surface BOP
equipment
How long do we need to hold pressure on BOP test? Minimum 5 minutes.
133 Apa yang harus dilakukan jika gas keluar dari mud return line (blow- Shut-in well dan hentikan sirkulasi. Pompakan lumpur ke dalam Mud Gas Surface BOP
through) pada Mud Gas Separator dan mengalir kembali ke mud pit? Separator untuk mengembalikan mud leg sebelum memulai kembali equipment
sirkulasi dengan menggunakan pump rate yang lebih rendah.
What needs to be done if gas comes out from the mud return line (blow-
Shut-in well and stop circulation. Pump mud into the Mud Gas Separator to
through) on a Mud Gas Separator and flow back to the mud pit? re-establish mud leg before restarting the circulation using lower pump
rate.
134 Apa yang dimaksud dengan "well bore pressure assisted" pada BOP? Artinya, pada beberapa jenis BOP, tekanan dari dalam sumur akan ikut Surface BOP
membantu penutupan BOP tersebut. Semakin besar tekanan sumur maka equipment
semakin besar pula gaya yang dihasilkan untuk membantu penutupan BOP
tersebut.
What does "well bore pressure assisted" mean for BOP? It means, on some types of BOP, pressure from the well will assists to close
the BOP. Higher wellbore pressure will result higher force to help closing
the BOP.
135 Bolehkah dilakukan pengelasan, pemotongan, penambalan, melubangi atau Tidak boleh. Penandaan hanya boleh menggunakan dot stamp. Surface BOP
v-stamp pada BOP atau alat penahan tekanan lainnya? equipment

Can we weld, cut, fill, drill or v-stamp BOP or other pressure contain No, you can't. Marking can only be made using dot stamp.
equipment?
136 Apa yang harus diperhatikan ketika akan membuka valve atau peralatan Selalu beranggapan jika dibalik valve atau peralatan tersebut terdapat Surface BOP
lainnya yang digunakan untuk menahan tekanan? tekanan yang dapat membahayakan. equipment
What needs to be awared of when opening a valve or other pressure Always assume there is pressure behind the valve or those equipments that
containment equipment? can be dangerous.

Page 20 of 21 Rev. 5 Oct 2012


Well Control Question of the Day
Drilling & Completions - Sumatra Operation
IndoAsia Business Unit
Rig : ____________
Date /
No Pertanyaan/Question Jawaban/Answer Topik
Crew Shift
1 Gas apakah yang digunakan untuk mengisi rubber bladder di dalam botol
137 Nitrogen, karena sifatnya yang tidak mudah panas ketika dikompres dan Barrier
Surface BOP
accumulator? dikembangkan. Policy
equipment
What is the gas used to fill the rubber bladder inside an accumulator Nitrogen, because it does not get hot when being compressed or expanded.
bottle?
138 Jika terdapat perbedaan pressure rating pada Annular BOP, Ram BOP dan Pressure rating yang terendah di antara semua peralatan tersebut. Surface BOP
well head yang terpasang, maka pressure rating manakah yang harus equipment
digunakan sebagai batasan maksimum?
If there is a different pressure rating on installed Annular BOP, Ram BOP Lowest pressure rating among those equipments.
and well head, which pressure rating should be used as the maximum
limit?
139 Mengapa grease harus diinjeksikan ke antara dua buah ram yang Braided line mempunyai celah di antara jalinannya yang memungkinkan gas Wireline
digunakan dalam operasi wireline dengan braided line? untuk masuk ke dalamnya dan naik ke permukaan. Injeksi grease
diperlukan untuk mencegah hal ini.
Why does grease need to be injected between the two rams used for Braided line has gaps between its wire that would enable gas to pass
wireline operation with braided line? through to the surface. Grease injection is needed to prevent it.

140 Berapakah besarnya tekanan injeksi grease pada double ram di wireline Minimum 20% di atas tekanan sumur. Wireline
operation untuk mencegah masuknya tekanan sumur?
What is the grease injection pressure on the double ram in wireline Minimum 20% higher than the wellbore pressure.
operation to prevent wellbore pressure from coming in?

Page 21 of 21 Rev. 5 Oct 2012