BELLAVITA

2/15/2019
Gross Maximum Quantity
Manpower Productivity Material Used Inner End Inner Unit
FABRICATION
Fabrication of Water line 1/2" PPR pipe 5 5 pcs
Initial Testing (Leak/Hydro) 1MP 5 sets/day 1/2" PPR Elbow 3 3 pcs
1/2" PPR Tee 4 4 pcs
1/2" PPR Coupling 1 1 pcs
CLEARING,STAKING/LAY-OUT
Clearing 1MP 8 Units/day
Lay-out 3MP 22 Units/Week
SLAB MILESTONE
Slab Phase 1
Installation of Septic tank, Cover, Tapping to sewer line Septic Tank 1 1 set
Installation of Sanitary line CHB 10 10 pcs
Construction of Catch Basin 4MP 4 units/week Cement( CB & ST Cover) 2 2 bags
Backfilling and Compaction Solvent 1/2 1/2 can
Flow Test
Lot Leveling
Slab Phase 2 PE Sheet 28 28 l.m
Installation of PE Sheet, Rebars, Water line, Electrical conduit with 10mm dia. RSB 43 43 pcs
House Keeping Tie Wire 1 1 kg
1/2" Elec. Conduit Pipe 10 10 pcs
3/4" Elec. Conduit Pipe 2 2 pcs
7MP 12 units/week
1/2" Elec. Conduit Long Elbow 13 13 pcs
3/4" Elec. Conduit Long Elbow 2 2 pcs
Solvent 1/2 1/2 can
Nylon(Pull Wire) 20 20 l.m
Tape 1/4 1/4 roll
Slab Phase 3
Installation and Dismantling of Form
5MP 20 units/week RMC 4 4 cum.
Concrete Pouring
House Keeping
Slab Fabrication 4" PVC Pipe 6 6 pcs
Sanitary Line 3" PVC Pipe 1 1 pcs
2" PVC Pipe 4 4 pcs
2" 90deg. Bend 5 4 pcs
2" 45deg. Bend 3 3 pcs
3" 90deg. Bend 1 1 pcs
3" 45deg. Bend 1 1 pcs
2MP 9 units/day 4" 45deg. Bend 3 3 pcs
4" x 2" Tee 1 1 pcs
2" P-Trap 1 1 pcs
2MP 9 units/day

4" x 3" Wye 1 1 pcs


4" x 2" Wye 3 3 pcs
4" x 4" Wye 1 1 pcs
4" End Plug 1 1 pcs
Tape 1/4 1/4 roll
Rebars 10mm dia. RSB 33 33 pcs
4MP 4 units/day
Tie Wire 1 1 kg
WALL MILESTONE
Wall Rebar 10mm dia. RSB 46 46 pcs
Fabrication and Installation of Wall Reinforcement Tie Wire 1 1 kg
Installation of Water line with bracing and spacers 1/2" Elec. Conduit Pipe 7 7 pcs
Installation of Electrical Conduit and Boxes with Bracing and Spacer 3/4" Elec. Conduit Pipe 1 1 pcs
House Keeping 3/4"Elec. Conduit Short Elbow 1 1 pcs
Utility box (Switch & Outlet) 8 8 pcs
Panel board Box 1 1 pcs
9MP 14 units/week 2" PVC Pipe 4 4 pcs
2" 90deg. Pvc Bend 2 2 pcs
1/2" PPR Threaded Elbow 3 3 pcs
1/2" PPR Threaded Tee 2 2 pcs
PPR End Cup 3 3 pcs
Tape 1/2 1/2 roll
Nylon(Pull Wire) 20 20 l.m
Cement(Spacer) 1/8 1/8 bags
Wall
Application of Form oil Form Oil 8 8 liter
Installation and Dismantling of Wall Form Door Jamb(Main) 1 1 pcs
Proper Installation of Door Jambs (Steel Door) and Window Block- Door Jamb(Service) 1 1 pcs
20-24MP 12 units/week
Concrete Pouring 10mm dia. RSB(welded for Door Jamb) 1 1 pcs
Cleaning of Wall Form RMC 4 4 cum
Repairing of Wall Form
House keeping (Cleaning of Units and lot perimeter)
CR WALL
Fabrication and Installation of Rebar 10mm dia. RSB 6 6 pcs
Installation of Electrical Conduit and Boxes with proper bracing an Tie Wire 1/4 1/4 kg
Application of Form oil 1/2" Elec. Conduit Pipe 1 1 pcs
Installation and Dismantling of CR Form Utility Box 1 1 pcs
Proper Installation of Door Jamb (PVC) 4-6MP 12 units/week Cement 5 5 bags
Concrete Pouring (Jobmix) Sand 0.28 0.28 cum
Dismantling Gravel 0.56 0.56 cum
Cleaning of Wall Formworks Form Oil 2 2 liter
House keeping
ROOFING WORKS
Installation of Rafters,Battens,Nailers C-Purlins 100mm x 45mm x 0.8mm 4 4 pcs
Installation of Roof sheet,Flashing,Capping C-Purlins 150mm x 45mm x 2.0mm 1 1 pcs
Installation of Facia board,Perforated tray (Spandrel-Ceiling Eaves) HT-Battens 45mm x 25mm x 0.8mm 13 13 pcs
Painting (3 Coats) of Facia Board with Mesh Tape and Patching C Roof Sheet (0.40mm x 1220mm) 4 4 pcs
Application of Sealant Perforated Rib Tray (Spandrel - Front) 28 28 pcs
Housekeeping Perforated Rib Tray (Spandrel - Rear) 28 28 pcs
End Moulding(Wall Angle) 7 7 pcs
Front Flashing 3 3 pcs
End Wall Capping 3 0 pcs
3MP 5 units/week
Common Wall Capping 3 6 pcs
10mm dia x 75mm Dynabolt 7 pcs
Tekscrew(long) 68 68 pcs
Tekscrew(Short) 78 78 pcs
1/2" x 4' x 8' Ficem Board 1.5 1.5 pcs
Flat Latex 0.4 0.4 gal
Screw 40 40 pcs
Blind Rivets 116 116 pcs
Sealant 1.5 1.5 tube
KITCHEN COUNTER
Excavation of K.C Foundation
Fabrication and Installation of Rebar
Pouring of K.C Foundation 10mm dia. RSB 3 3 pcs
Application of Form oil Cement 2 2 bags
Installation and Dismantle of K.C Form Sand 1/8 1/8 cum
Installation of Block-out (K.C drain) 4MP 20 units/week Gravel (3/8") 1/4 1/4 cum
Concrete Pouring (Jobmix) 2" PVC Pipe 1/2 1/2 pcs
Installation of P-trap 2" P-Trap 1 1 pcs
Cleaning of Forms Form oil 1 1 Liter
Ponding test Tie Wire 1/4 1/4 kg
House Keeping
CR FINISHING
Ceiling and Skim Coat 1/4" x 4'x 8' Ficem board 1 1 pcs
Installation of Ceiling Frame and Board Metal Purring 2 2 pcs
Painting (Ceiling) Wall Angle 2 2 pcs
Application of Skim Coat 1MP 2 units/day Blind Rivets 18 18 pcs
Screw 35 35 pcs
Paint(Flat Latex) 0.25 0.25 gal
Skim Coat 1 1 bags
Tiles and Fixtures 20cm x 20cm Tiles 80 80 pcs
Installation of Tiles Adhesive 1 1 bags
Application of Tile Grout Tile Grout 4 4 kgs
Installation of Plumbing Fixtures Cement 2 2 bags
2MP 1 Unit/day
Ponding Test Water Closet 1 1 set
Housekeeping Wall Hung Lavatory 1 1 set
Shower 1 1 set
Floor Drain Strainer 1 1 pcs
WALL SKIMCOAT
Wall
Wall Buffing
Application of Skim Coat (inside-2 coats)(outside-1 coat,only the t Skim Coat 3 2.5 bags
Wall Skirt (Chip o Plaster) 10MP 13 Units/day
House keeping
T-Wall
Skim Coat 1/8 1/8 bags
Application of Skim Coat (imperfection only)
SAND BLAST
Exterior Wall
Block out grove(Using tape) Cement 1.5 1 bags
Sand Blasting of Exterior Wall including exposed Foundation Sand 4.5 3 bags
Housekeeping 2MP 2 units/day
T-Wall Cement 0.1 0.1 bags
Block out grove(Using tape) Sand 0.3 0.3 bags
Sand Blasting of T-Wall
PAINTING WORKS
Exterior Wall,Doors,Windows,Kitchen Counter Primer Flat Latex 2.6 1.4 gal
Painting of Exterior Walls, Doors,Windows,Kitchen Counter(sidings) Top Coat (SR-011 Winter Morning) 0.45 0.9 gal
Top Coat (SR-083 Linen Cream) 0.25 0 gal
Top Coat (SR-608 Seal Gray) 1.3 0.2 gal
QDE Brown (Steel Door and Window) 0.65 0.65 gal
T-Wall Primer Flat Latex 0.3 0.3 gal
Painting of T-Wall Top Coat (SR-914 Mud' O Pie) 0.24 0.24 gal
WINDOWS
Installation Window Glass (Front) 4 4 pcs
Installation of Windows (Front,Rear,Toilet) Window Glass (Rear) 2 2 pcs
Installation of Glass Window Glass (Toilet) 1 1 pcs
2MP 8 Units/week
Application of Sealant Welding Electrodes 4 4 pcs
Cement Tapping Cement (tapping) 1/8 1/8 bags
Sealant 3 3 tube
Fabrication Z-Bar(Front) 1.5 1.5 pcs
Fabrication of Window Frame with accessories (Front,Rear,Toilet) I-bar(Front) 0.25 0.25 pcs
Painting(Red Oxide) T-bar(Front) 0.15 0.15 pcs
Z-Bar(Rear) 1.05 1.05 pcs
I-bar(Rear) 0.15 0.15 pcs
2MP 15 units/week Z-Bar(Toilet) 0.65 0.65 pcs
Casement Window Hinges 10 10 pcs
Handle 5 5 pcs
Welding Electrodes 25 25 pcs
Red Oxide 0.07 0.07 gal
Paint Thinner 0.035 0.035 gal
ELECTRICAL WORKS
Wiring and Installation of Electrical fixtures (Outlet, receptacle, Sw 3.5mm² THHN Wire(Line) 110 110 l.m
Continuity Test 8.0mm² THHN Wire(Line) 34 34 l.m
House keeping (Cleaning of lot perimeter) 8.0mm² THHN Wire (Ground) 19 19 l.m
1/2" Flexible Conduit pipe 15 15 l.m
3/4" PVC Conduit Pipe 4 4 pcs
Two Gang Outlet 6 6 pcs
Single Gang Switch 2 2 pcs
Two Gang Switch 1 1 pcs
3" Receptacle 4 4 pcs
Junction box 4 4 pcs
Panel Board 1 1 pcs
Electrical Tape 1 1 roll
1/2" Grounding Rod 1 1 pcs
FLOOR FINISH
Floor Buffing Skim Coat 3 3 bags
Application of Floor Skimcoat Steel Door(Main) 1 1 pcs
Installation of Main and Service door with Lockset Steel Door(Service) 1 1 pcs
House keeping Door Knob Lockset and Hinges 2 2 set
ADDITIONAL WORKS
Pathwalk
Lay-out, Excavation and Hauling of Materials
Gravel Bedding and Compaction Gravel (Bedding)
5MP Varies Varies
Installation and Dismantle of Form RMC
Concreting
House keeping
SEP Fabrication and Erection 10mm dia. RSB 10 pcs
Rebar cut, bend, assemble = 350 3/4" Electrical Conduit Pipe 3 pcs
Formworks, Conduit rough-ins and Concreting (RMC) = 350 3/4" Elec. Conduit long elbow 4 pcs
Dismantling Formworks = 100 3/4" Elec. Conduit Tee 2 pcs
Excavation, Erection of SEP = 900 Tie Wire 0.25 kg
Rebar installation & concreting of footing = 300 (Job Mix) Cement 2 bags
Concreting Sand 0.1 cum.
House keeping Gravel 0.2 cum.