You are on page 1of 9

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/284084774

A numerical evaluation of continuous backfilling in cemented paste backfilled


stope through an application of wick drains

Article  in  International Journal of Mining Science and Technology · November 2015


DOI: 10.1016/j.ijmst.2015.09.004

CITATIONS READS

9 194

2 authors:

Li Li Pengyu Yang
Polytechnique Montréal Polytechnique Montréal
79 PUBLICATIONS   1,150 CITATIONS    11 PUBLICATIONS   45 CITATIONS   

SEE PROFILE SEE PROFILE

All content following this page was uploaded by Pengyu Yang on 24 October 2017.

The user has requested enhancement of the downloaded file.


International Journal of Mining Science and Technology 25 (2015) 897–904

Contents lists available at ScienceDirect

International Journal of Mining Science and Technology


journal homepage: www.elsevier.com/locate/ijmst

A numerical evaluation of continuous backfilling in cemented paste


backfilled stope through an application of wick drains
Li Li, Yang Pengyu ⇑
Department of Civil, Geological and Mining Engineering, École Polytechnique de Montréal, Montreal H3C3A7, Canada

a r t i c l e i n f o a b s t r a c t

Article history: Cemented paste backfill (CPB) is gaining popularity in many underground mines worldwide. Sufficient
Received 6 November 2014 water is added into CPB to make a flowable material for pipe transportation. Barricades are built near
Received in revised form 21 January 2015 the drawpoints to prevent in-rush of the fill slurry. To avoid barricade failures resulting from excessive
Accepted 23 March 2015
backfill pressures, backfilling is typically performed with a plug pour followed by a final pour. The inter-
Available online 3 November 2015
val between the two pours should be shortened or removed to increase mining productivity and avoid
pipe clogging. Recently, Li proposed to apply wick drains in backfilled stopes to promote drainage and
Keywords:
consolidation. The preliminary simulations by considering an instantaneous filling indicated that the
Mines
Cemented paste backfill
drainage of CPB can be significantly accelerated by using wick drains. Barricade was not considered.
Backfilled stopes Here, some new numerical modellings are presented with more representative filling sequences, stope
Numerical analyses geometry, and different draining configurations. The results illustrate that the stope can be backfilled
Drainage continuously by using wick drains.
Wick drains Ó 2015 Published by Elsevier B.V. on behalf of China University of Mining & Technology.

1. Introduction In the past three decades, CPB has been developed and widely
adopted in many underground mines in Canada, Australia, China,
Underground mining involves creating voids (i.e. stopes) that and elsewhere. Generally consisting of 70–85% (solid weight) of
could endanger ground stability when the stope dimensions are full tailings, CPB has many operational and environmental benefits
too large. This may impact the ore recovery and dilution rates, [6,12]. However, sufficient amount of water is added into the back-
cause ground subsidence, and lead to serious safety issues. On fill to make a flowable material for pipe transportation from sur-
the other hand, the mining practice produces a large amount of face backfill plant to underground voids (Fig. 1, left picture).
mine wastes including waste rock and tailings. Usually, the former Because of the flowability of backfill, barricades have to be built
is stacked in the form of waste rock piles while the latter is depos- near the drawpoints to prevent the in-rush of backfill (Fig. 1, right
ited at tailing impoundments. In both cases, the mine wastes are picture).
disposed on the ground surface and occupy a lot of land, and Once placed in the stope, CPB’s particles tend to settle down
may cause instability and acid mine drainage [1–3]. To date, sev- under self-weight, leading to establishment of excess pore-water
eral methods have been developed to address these problems, pressure (PWP) [13–18]. The process of the dissipation of the
among which stope backfilling is considered as the optimal excess PWP is a well-known phenomenon called self-weight con-
method. solidation or sedimentation [18–23]. Due to the development of
In general, mining backfill plays the role of ensuring stability of the excess PWP and to avoid excessive backfill loads exerted on
regional ground and local stopes, increasing ore recovery rate and barricades, stope filling is typically divided into a plug pour and
minimizing ore dilution [4–11]. The surface disposal of mine a final pour in practice, separated by an interval of several days
wastes can be disposed by backfilling, which is regarded as an [17,24,25]. For the sake of barricade stability, this interval is
environmental friendly solution [1,2]. Mining backfill is typically necessary, even obligatory in some cases. Alternatively, the rising
classified as rockfill, hydraulic backfill and cemented paste backfill rate (i.e. speed, influenced by the flow rate of backfill feeding and
(CPB); each has some advantages and limitations [6]. stope geometries) of the backfilling should be low enough [16].
On the other hand, from an economic point of view, this interval
is undesirable because it slowdowns the production and occasions
pipe clogging. Consequently, one seeks a fast and continuous back-
⇑ Corresponding author. Tel.: +1 514 3404711.
filling by means of improved drainage and consolidation of backfill.
E-mail address: pengyu.yang@polymtl.ca (P. Yang).

http://dx.doi.org/10.1016/j.ijmst.2015.09.004
2095-2686/Ó 2015 Published by Elsevier B.V. on behalf of China University of Mining & Technology.
898 L. Li, P. Yang / International Journal of Mining Science and Technology 25 (2015) 897–904

Hook Wick Drift Drift


drain

Hook
Step 1 Step 2

Wick drain
Blasting
hole

Draw point Drift Draw point Drift

Drift Hook Wick Drift


drain

Step 3 Step 4

Backfill
Fig. 1. A stope being backfilled (left) with a barricade constructed near the

Wick drain
drawpoint (right).
Barricade

A number of works have been reported on improving the drai-


Drift Drift
nage of barricade by using different porous materials [26–28], but
few works on improving the drainage of CPB. Until recently, Li pro-
posed to use wick drains in backfilled stopes to improve drainage Fig. 3. Flowchart of conceptual application of a wick drain in a backfilled stope
[9,29].
and consolidation [9,29]. The concept is straightforward. Without
wick drains, the drainage of backfill typically occurs vertically in
3. Numerical modeling of continuous filling
one dimension (upward and downward). Once wick drains are
used, the drainage of backfill can occur in both horizontal and ver-
3.1. Model configuration
tical directions, thereby improving the drainage of the backfill sig-
nificantly. This has been confirmed by some preliminary numerical
Fig. 4 presents a schematic view of CPB backfilled stope with a
results obtained with GeoStudio 2007 [30]. However, the prelimi-
barricade located in an access drift near the drawpoint. Here, a
nary numerical models considered only one or two wick drains
nearly impervious mechanical barricade is considered. As shown
vertically placed in the backfilled stope, considering one layer
in Fig. 4, H (m), Hplug (m) and Hfinal (m) represent the total height,
instantaneous backfilling. The barricade was not taken into
plug pour height and final pour height of CPB, respectively; B (m)
account. In this work, the conceptual introduction of wick drain
and L (m) are the stope width and length, respectively; Hd (m)
in backfilled stope is briefly recalled. New numerical modelings
and Ld (m) are the height and width of drift and barricade, respec-
using GeoStudio 2007 are presented with more representative fill-
tively. The stope and drift geometries of the numerical modeling
ing sequences, stope geometry, and different configurations of
are given in Table 1.
draining system. It is aimed to investigate the possibility of contin-
Table 2 lists some hydraulic and mechanical properties of CPB
uous filling of CPB using wick drains.
and wick drains taken for the numerical modeling. A rising rate
of 0.1 m/h is taken for the backfilling operation. This corresponds
to a backfill flow rate of 30 m3/h when the base section of the stope
2. Conceptual application of wick drains in backfilled stopes is 10 m  30 m. In practice, a rising rate of 0.2 –0.4 m/h has been
reported depending on the backfill flow rate and section area of
In civil engineering, wick drains (or prefabricated vertical the stope [17]. The CPB is considered as a soft linear-elastic mate-
drains) are commonly used to promote the drainage and consolida- rial with saturated hydraulic conductivity (also termed as coeffi-
tion of silty and clayey soils [31–37]. A wick drain is usually com- cient of permeability) of ksat = 1.0  107 m/s (i.e. 0.00864 m/day)
posed of a Polypropylene core and geotextile fabric as shown in and a coefficient of volume change mv = 0.0002 kPa1. The varia-
Fig. 2. The Polypropylene core plays the role of draining channel tions of the hydraulic properties of CPB are plotted in Fig. 5. The
while the geotextile acts as the filter. Compared with the other ver- variations of volumetric water content and hydraulic conductivity
tical drains such as sand or waste rock columns, the installation of as a function of the suction are presented in Fig. 5a and b, respec-
wick drains is more convenient in backfilled stopes. Fig. 3 shows tively. As self-weight consolidation develops, the hydraulic
the conceptual application of a wick drain in a backfilled stope conductivity decreases as the effective stress increases, as shown
[9,29]. in Fig. 5c.

Geotextile fabric
H final

Final pour
L
Barricade
B
H

Ld
Polypropylene core
H plug

Plug Hd

Fig. 2. A commercial wick drain made of geosynthetic material (samples provided


by AMERDRAINÒ). Fig. 4. A CPB backfilled stope and a barricade in an access drift [27].
L. Li, P. Yang / International Journal of Mining Science and Technology 25 (2015) 897–904 899

Table 1 Further discussion on how to estimate the loads on barricades is


Stope and drift geometries (m). not the scope of this paper. Hereafter, the allowable barricade load
Stope size Drift size Plug height Final pour height P is estimated based on the geostatic pressure of the plug, without
HBL Hd  Ld Hplug Hfinal considering the arching effect. For the configuration defined here,
30  10  30 55 9 21 the allowable barricade load P is given as follows (with a factor
of safety equals 1.0):
 
1
Usually, the hydraulic conductivity of wick drains is much P ¼ cLD HD Hplug  HD
2
higher than that of CPB, so the drainage of the backfill around a  
wick drain is dominated by the drainage of the CPB [9,30]. The 1
¼ 20 kN=m3  5 m  5 m  9 m   5 m ¼ 3250 kN
main role of wick drains is to provide low pressure (close to nil) 2
channels to facilitate the drainage. In this case, it is assumed that
the wick drains have the same hydraulic and mechanical proper- This value will be used as a load threshold on the barricade for suc-
ties as those of the CPB. It should be noted that the unit weight cessful continuous backfilling.
of wick drains is taken as 20 kN/m3 instead of weightless shown
in Li [9,29]. In addition, these properties are assumed to be con- 3.3. Numerical modeling of stress evolution with filling and draining of
stant with the evolution of saturation and effective stresses. In CPB
GeoStudio 2007, a wick drain is represented by a 5 cm-thick inter-
face element that corresponds to a typical wick drain 4 mm thick The stress evolution in a CPB backfilled stope (filling and drain-
and 100 mm wide [30]. ing) with and without wick drains is analyzed with GeoStudio,
which is a commercial software based on the finite element
method. This software package includes several modules to
3.2. Allowable barricade load address various geotechnical problems. In this analysis, the
‘‘SIGMA/W” module is used with the ‘‘Coupled stress/PWP” option,
The drainage and consolidation of hydraulic backfill is com- which means a direct coupled hydro-mechanical process.
pleted almost instantaneously, resulting in water ponding on the Fig. 6 shows typical GeoStudio models of a backfilled stope with
top of the backfill. Abundant water bleeding is commonly observed 5 drain holes on the barricade (Fig. 6a), and with 5 wick drains
at the downstream of the barricade. Arching effect should be con- installed within the backfill and through the barricade (Fig. 6b).
sidered in barricade load design [38,39]. For both models, the vertical rock walls and barricades are fixed
In the case of CPB, the barricade design remains a topic of horizontally but set free in the vertical direction. The displace-
debate in pressure consideration. Some ones argue that the pres- ments of horizontal rock walls are prevented along both axes. Drai-
sures on barricades would be very small because no or little water nage is allowed through the top of the backfill, drain holes and
bleeding is observed. In geotechnique engineering, it is well known wick drains, while the rock walls are modeled as impervious. To
that the water bleeding is not a reliable indicator of the excess PWP simulate the filling operation with a rising rate of 0.1 m/h, the fill
dissipation [18]. Recent in-situ experiments have revealed that the is divided into 60 layers (i.e. 0.5 m per layer) and 5 h are allocated
arching effect can be absent shortly after placing CPB [17]. This to each layer for draining and consolidating before the placement
tends to indicate that the total overburden stresses should be used of the next layer on the top of current layer. This simulation proce-
in barricade load design. On the other hand, these experimental dure is repeated until the fill reaches the planned height (30 m)
results of excess PWP show also that the process of drainage and without interruption between the plug pour (at a height of 9 m)
consolidation can start very quickly. When the rising rate of CPB and final pour (the remaining 21 m). In the following subsections,
is low, the barricade design based on overburden may lead to an the stress distributions obtained by numerical modeling without
over-conservative barricade design. and with wick drains are presented at each stage of fill pouring.

Table 2
Some typical hydraulic and mechanical properties of CPB and wick drains.

Material type Saturated hydraulic Coefficient of volume Young’s modulus E0 (kPa) Unit weight c (kN/m3) Poisson’s ratio l
conductivity ksat (107 m/s) change mv (kPa1)
Backfill 1.0 0.0002 5000 20 0.334
Wick drains 1.0 0.0002 5000 20 0.334

0.5 1×10-2 1
Hydraulic conductivity (m/day)

1×10-3
Water content (m3/m3)

0.4

1×10-4
k-modifier

0.3
1×10-5

0.2
1×10-6

0.1 1×10-7 0.1


1 10 100 1 10 100 1 10 100
Matric suction (kPa) Matric suction (kPa) Effective stress (kPa)
(a) Volumetric water content function (b) Hydraulic conductivity function (c) hydraulic conductivity reduction modifier

Fig. 5. Hydraulic properties of the CPB[9].


900 L. Li, P. Yang / International Journal of Mining Science and Technology 25 (2015) 897–904

30 30

28 28
(a) (b)
26 26

24 24

22 22

20 20

18 18

16 16

14 14
y (m)

Wick

y (m)
12 12
drains
10 10
Drain
8 holes 8

6 6

4 4

2 2

0 0

-2 -2

-4 -4

-6 -6
-5 0 5 10 -5 0 5 10
x (m) x (m)

Fig. 6. GeoStudio models of a backfilled stope: (a) with no wick drains but 5 drain holes through the barricade; (b) with 5 wick drains within the backfill and through the
barricade.

3.3.1. Stress distributions at the stage of the plug pour the barricade are further detailed in Fig. 9. Nonlinear distributions
The distribution of excess PWP immediately after placing the are observed along the barricade height in both cases. Also, one
last layer of the plug pouring is illustrated in Fig. 7. In the absence notices that the horizontal total stresses are much smaller than
of wick drains (Fig. 7a), excess PWP could partly dissipate at the the geostatic overburden pressures of the plug pour.
end of the plug pouring due to drainage and consolidation upward
to the backfill surface and downward through the 5 drain holes 3.3.2. Stress distributions at the stage of the final pour
during the 90 hours’ filling. An excess PWP between 20 and Fig. 10 shows the excess PWP distribution immediately after
50 kPa is still observed near the barricade, which indicates that placing the last layer of the final pour for the case of 5 drain holes
the drainage and consolidation are in progress. With the use of 5 (Fig. 10a) and 5 wick drains (Fig. 10b). Again, one observes the dis-
wick drains, the excess PWP on the barricade is close to nil, which sipation of a large portion of the excess PWP near the barricade
means that the drainage and consolidation are almost complete even in the absence of wick drains (Fig. 10a), resulting in a
(Fig. 7b). remaining value close to 120 kPa. As indicated in Fig. 10b, after
The distribution of horizontal total stress immediately after introducing 5 wick drains, the drainage and consolidation are
placing the last layer of the plug pouring is shown in Fig. 8. It is almost complete and excess PWP is close to zero near the
observed that the horizontal total stresses along the barricade barricade.
are largely reduced (by around 50% at the mid-height) after using Fig. 11 shows the horizontal total stress distribution immedi-
5 wick drains. The distributions of horizontal total stresses along ately after placing the last layer of the final pour. In the case of

6 6
(a) (b)
4 20 4
40
2 2
60 5 5
5
y (m)
y (m)

0 15
0
80 25
40

100
-2 -2
5
60

120
5
-4 -4
140 5

-6 -6
-5 0 5 10 -5 0 5 10
x (m) x (m)

Fig. 7. Numerical results of the excess PWP (kPa) distribution shortly after placing the last layer of the plug pouring: (a) with no wick drains but 5 drain holes through the
barricade; (b) with 5 wick drains within the backfill and through the barricade.
L. Li, P. Yang / International Journal of Mining Science and Technology 25 (2015) 897–904 901

6 6
(a) (b)
4 4
20
40 20
2 2
60
40

y (m)
y (m)
0 0
80 60 20

40
-2 -2
100
120
-4 140 -4 60
80

-6 -6
-5 0 5 10 -5 0 5 10
x (m) x (m)

Fig. 8. Numerical results of the horizontal total stress (kPa) distribution shortly after placing the last layer of the plug pour backfill: (a) without wick drains; (b) with 5 wick
drains within the backfill and through the barricade.

Horizontal total stress Fig. 12 shows the distribution of horizontal total stress along
(kPa) the barricade after placing the last layer of the final pour. Again,
0 30 60 90 120 150 180
it is noted that the horizontal total stress distributions for both
cases are nonlinear along the barricade. In the absence of wick
ov

-1
drains, the horizontal total stresses are quite larger than the geo-
erb

Ge n pr
Wi

ur
Wi

static overburden pressures (see Fig. 9) of the plug, on which the


os ess
de
tho
th

tat

-2
ut
5

ic re

maximum allowable load on the barricade is based. This implies


y (m)

wi

wi
ck

u
ck

-3 that the continuous filling of the entire stope is not possible. In


dra

dra
ins

the case with 5 wick drains, Fig. 12 illustrates that the horizontal
ins

-4
total stresses close to the top and base of the barricade are lower
-5 than the plug’s geostatic pressures (80 and 180 kPa, respectively,
see Fig. 9). However, the plug’s geostatic pressures near the mid-
Fig. 9. Distributions of the horizontal total stresses along the barricade shortly after height of the barricade are exceeded. Therefore, the loads exerted
placing the last layer of the plug pouring obtained by numerical modeling and
on the barricade should be compared with the design load P to
based on the geostatic overburden pressure.
see whether the barricade failure would occur in such condition.

3.4. Stability analysis of the barricade


no wick drains, Fig. 11a shows that the horizontal total stress can
reach up to 360 kPa near the barricade, while it ranges between As shown in Figs. 9 and 12, drainage and consolidation during
120 and 180 kPa after using wick drains (Fig. 11b). the filling operation have taken place, resulting in arching effect

40
24 24

22 80 (a) 5 (b)
22 5
5
120 15 5
15

20 20

18 160 18

16 200 16

14 14
y (m)

12 12
280
y (m)

10 10

8 8
35
45
15

6 360 6

4 4

400
2 2

0 0
440
5
160

-2 -2
480 5
24
36

5
0
0

-4 -4

-6 -6
-5 0 5 10 -5 0 5 10
x (m) x (m)

Fig. 10. Numerical results of the excess PWP (kPa) distribution after placing the last layer of the final pouring: (a) with no wick drains but 5 drain holes through the barricade;
(b) with 5 wick drains within the backfill and through the barricade.
902 L. Li, P. Yang / International Journal of Mining Science and Technology 25 (2015) 897–904

24 24
40
20
22 22
(a) (b)
80
20 20
120 60
18 18

16 16 100
200
14 14

12 12 140

y (m)
y (m)

280
10 10

8 8 180

6 360 6

220
4 400 4

2
2 440 260

42
0 0

0
440 280 100

0
22

180
-2 -2
36
40

320

26
-4
0

-4 520

0
140
-6 -6
-5 0 5 10 -5 0 5 10
x (m) x (m)

Fig. 11. Numerical results of the horizontal total stress (kPa) distribution shortly after placing the last layer of the final pouring: (a) with no wick drains but 5 drain holes
through the barricade; (b) with 5 wick drains within the backfill and through the barricade.

Horizontal total stress

Final
0 wick drain; 0 drain hole

pour
(kPa)
0 10 0 20 0 30 0 40 0 50 0 600 14000 0 wick drain; 5 drain hole
1 wick drain; 5 drain hole
12000
Loads on barricade (kN)

5 wick drain; 0 drain hole


overb

-1 10000 Designed barricade load


With
With

urden
Geos
out w

8000
-2
5 wic

tatic
y (m)

press
ick d

6000
Plug
pour
k dra

-3
ure
rains

4000
ins

-4 2000
0
-5 5 10 15 20 25 30
Fill height (m)
Fig. 12. Distribution of the horizontal total stress along the barricade shortly after
placing the last layer of the final pour obtained by numerical modeling and based on Fig. 13. Comparison between the barricade design load and variation of the
geostatic overburden pressure. barricade loads during filling for several scenarios of draining system, obtained by
numerical modeling.

and non-linear stress distribution along the height of the barricade. paused at a height of 22 m. When 5 wick drains are introduced,
The backfill loads exercised on the barricade can be obtained by the applied loads are always below the barricade design load dur-
integrating the horizontal total stresses over the barricade area. ing the entire filling, indicating a possible continuous filling.
Fig. 13 illustrates the backfill loads exercised on the barricade
obtained numerically for several scenarios of draining system: no 4. Discussion
draining system (0 drain hole, 0 wick drain; details not shown), 5
drain holes through the barricade but no wick drain, 5 drain holes The hydraulic conductivity of hydraulic backfill is several orders
combined with 1 wick drain (details not shown), and 5 wick drains. of magnitude larger than that of CPB, which contains a large
The allowable barricade load P (3250 kN, obtained by the plug’s amount of fine particles (<20 lm). The excess PWP in a hydraulic
geostatic pressure) is also plotted for the sake of comparison. backfill dissipates quite quickly, leading to the bleeding of a lot
The results shown in Fig. 13 indicate that a filling interval is of free water from barricades and at the top of the backfill. The
obligated once the plug pour is complete at a filling height of drainage of bleeding water is mostly dominated by the draining
9 m if there is no draining system installed in the barricade. With capacity of the barricades. Therefore, the application of wick drains
5 drain holes passing through the barricade but no wick drain, it is proposed specifically for CPB having limited permeability.
is observed that the barricade design load is exceeded when the Wick drain is only one type of vertical drains widely used in
filling height reaches around 15 m. To ensure the barricade stabil- foundation engineering. Sand columns are the other type of verti-
ity, the filling then has to be halted to allow the dissipation of cal drains commonly used in civil engineering to accelerate the
excess PWP. With the combination of one wick drain and 5 drain drainage and consolidation of soft soils [31]. In mining engineering,
holes in the barricade, Fig. 13 indicates that the filling has to be waste rocks have been introduced into tailing impoundments to
L. Li, P. Yang / International Journal of Mining Science and Technology 25 (2015) 897–904 903

accelerate the drainage and reduce the potential of liquefaction References


[40–42]. In underground stopes, the access to mined stopes is dan-
gerous and limited. The construction of sand or waste rock col- [1] Aubertin M, Bussière B, Bernier L. Environnement et gestion des rejets miniers
(CD-ROM). Montréal: Presses Internationales Polytechnique; 2002.
umns would be difficult, if not impossible. Alternatively, drain [2] Benzaazoua M, Bussière B, Demers I, Aubertin M, Fried É, Blier A. Integrated
tubes [43] can also be used in backfilled stopes to accelerate the mine tailings management by combining environmental desulphurization and
drainage and consolidation of CPB. cemented paste backfill: application to mine doyon. Miner Eng
2008;21:330–40.
The numerical simulations show that continuous filling of a [3] Ben Abdelghani F, Aubertin M, Simon R, Therrien R. Numerical simulations of
30 m high stope at a rising rate of 0.1 m/h without interruption water flow and contaminants transport near mining wastes disposed in a
between the plug and final pour is possible by using wick drains. fractured rock mass. Int J Min Sci Technol 2015;25(1):37–45.
[4] Thomas EG, Nantel JH, Notley KR. Fill technology in underground metalliferous
However, it should be noted that the results presented here are
mines. Kingston: International Academic Services; 1979.
not associated with any practical application. The geometries and [5] Singh KH, Hedley DGF. Review of fill mining technology in Canada. In:
material properties are based on typical values from literatures Proceedings of the conference on the application of rock mechanics to cut and
[14–16] and the GeoStudio Manual [30]. Moreover, the numerical fill mining. Lulea: Institution of Mining and Metallurgy; 1980. p. 1–3.
[6] Hassani F, Archibald JF. Mine backfill (CD-ROM). Montreal: CIM; 1998.
modelings are simplified in several aspects. For instance, the [7] Miao XX, Zhang JX, Feng MM. Waste-filling in fully-mechanized coal mining
hydraulic properties of backfill in the drift are assumed to be the and its application. J China Univ Min Technol 2008;18(4):479–82.
same as those in the stope. Due to the limited drift width (Ld), [8] Zhang Q, Zhang JX, Huang YL, Ju F. Backfilling technology and strata behaviors
in fully mechanized coal mining working face. Int J Min Sci Technol 2012;22
the 2D (strain plane) modeling tends to overestimate the dissipa- (2):151–7.
tion of excess PWP, and therefore underestimate the horizontal [9] Li L. A new concept of backfill design-application of wick drains in backfilled
total stress and loads exerted on the barricade by the backfill. This stopes. Int J Min Sci Technol 2013;23(5):763–70.
[10] Yang PY, Li L. Investigation of the short-term stress distribution in stopes and
may place the design on the non-conservative side. Besides, it drifts backfilled with cemented paste backfill. Int J Min Sci Technol 2014;24
should be mentioned that a factor of safety equal to 1.0 has been (1):223–9.
used in previous analyses. In practice, a factor of safety between [11] Zhang Q, Zhang JX, Guo S, Gao R, Li WK. Design and application of solid, dense
backfill advanced mining technology with two pre-driving entries. Int J Min Sci
1.5 and 2 (or higher) should be applied, depending on the uncer- Technol 2015;25(1):127–32.
tainty of the parameters used in barricade design and the conse- [12] Brackebusch FW. Basics of paste backfill systems. Min Eng 1994;46
quences of the barricade failure. (10):1175–8.
[13] Grabinsky MW. In situ monitoring for ground truthing paste backfill designs.
In addition, some more aspects should be considered when
In: Proceedings of Paste 2010. Toronto: 2010. p. 85–98.
applying wick drains in practical projects. For example, the effec- [14] El Mkadmi N, Aubertin M, Li L. The effect of transient drainage on the stress
tive openings of geotextile fabric of wick drains should be selected state in backfilled mine stopes. In: Proceedings of 2011 Pan-Am CGS
by considering the granularity of the backfill to avoid the internal Geotechnical Conference. Toronto; 2011. p. 1139.
[15] El Mkadmi N, Aubertin M, Li L. Numerical analysis of the early response of
erosion and clogging. Also, the geotextile fabric should be strong paste backfill in a vertical stope. In: Proceedings of Mines without Borders,
enough to resist failures such as stretching and tearing. These CIM Conference and Exhibition. Montreal: 2011. p. 68–78.
aspects are beyond the scope of the paper, but should be taken into [16] El Mkadmi N, Aubertin M, Li L. Effect of drainage and sequential filling on the
behavior of backfill in mine stopes. Can Geotech J 2014;51(1):1–15.
account when designing wick drains for backfilled stopes. [17] Thompson BD, Grabinsky MW, Bawden WF. In-situ measurements of
cemented paste backfill at the Cayeli Mine. Can Geotech J 2012;49:755–72.
[18] Li L, Alvarez IC, Aubertin JD. Self-weight consolidation of a slurried deposition:
5. Conclusions tests and interpretation. Int J Geotech Eng 2013;7(2):205–13.
[19] Gibson RE. The progress of consolidation in clay layer increasing in thickness
with time. Géotechnique 1958;8(4):171–82.
Numerical simulations have been performed with multi-layer [20] Gibson RE, Schiffman RL, Cargill KW. The theory of one-dimensional
filling, more representative stope geometry, and different draining consolidation of saturated clays. II. Finite nonlinear consolidation of thick
configurations. It is shown that drainage and consolidation can homogeneous layers. Can Geotech J 1981;18(2):280–93.
[21] Dromer JB, Aubertin M, Kennedy G, Pedroni L, Bussière B. A new testing system
take place during filling, depending on the hydraulic properties to investigate the sedimentation and consolidation of sludge and slurry. In:
and rising rate of backfill. This has been confirmed by numerical Proceedings of 57th Canadian Geotechnical Conference. Québec city; 2004.
results and in-situ measurements reported in the literatures. Thus, [22] Pedroni L, Dromer JB, Aubertin M, Kennedy G. Properties of treatment
sludge during sedimentation and consolidation tests. In: Proceedings of the
the complete ignorance of the arching effect in a stope with CPB 7th International Conference on Acid Rock Drainage. St. Louis; 2006. p.
may result in an over-conservative barricade design. An optimal 26–30.
barricade design should allow for the backfill rising rate, hydraulic [23] Aubertin M. R.M. Self-weight consolidation problems related to surface and
underground disposal of fine-grained mine wastes. In: Proceedings of 66th
properties of the backfill, and barricade geometry and position in
Canadian Geotechnical Conference. Montreal; 2013.
the access drift. [24] Thompson BD, Bawden WF, Isagon I, Grabinsky MW. Increasing paste and
The numerical results also show that a stope can be filled con- hydraulic backfilling efficiency through instrumentation. In: Proceedings of
tinuously without interruption between the plug pour and final 23rd World Mining Congress. Montreal; 2013.
[25] Li L. An analytical solution for determining the required strength of a side-
pour, owing to the application of wick drains. These results indi- exposed mine backfill containing a plug. Can Geotech J 2014;51(5):508–19.
cate that the application of wick drains in mine backfilled stopes [26] Sivakugan N, Rankine K, Rankine R. Permeability of hydraulic fills and
is promising for accelerating the drainage and consolidations of barricade bricks. Geotech Geol Eng 2006;24:661–73.
[27] Li L, Aubertin M. Limit equilibrium analysis for the design of backfilled stope
backfill. Nevertheless, due to several limitations involved in the barricades made of waste rock. Can Geotech J 2011;48(11):1713–28.
numerical modelings, this work should be considered as concep- [28] Yang PY, Brochu-Baekelmans M, Li L, Aubertin M. An improved solution for
tual and the numerical results shown here should not directly be sizing barricades made of waste rock to retain cemented paste backfill. In:
Proceedings of 67th Canadian Geotechnical Conference. Regina; 2014.
applied to any practical project. More work is required to refine [29] Li L. Application of wick drains in backfilled stopes for accelerating the
the numerical modelings and analyses. drainage. In: Proceedings of the 23rd World Mining Congress. Montreal; 2013.
[30] GeoStudio. Stress-deformation modeling with SIGMA/W 2007: an engineering
methodology. Calgary: GEO-SLOPE International Ltd.; 2010.
Acknowledgments [31] Bowles JE. Foundation analysis and design. Singapore: The McGraw-Hill
Companies; 1996.
[32] Zhu G, Yin J-H. Finite element consolidation analysis of soils with vertical
The authors acknowledge the financial support of the Natural drain. Int J Numer Anal Met 2000;24:337–66.
Sciences and Engineering Research Council of Canada (RGPIN), [33] Landau RE, Lamie MC, Modeer VA. Wick drain research at an Illinois project
the Institut de recherche Robert-Sauvé en santé et en sécurité du site. In: Proceedings of the United Engineering Foundation/ASCE Geo-Institute
Soft Ground Technology Conference-Soft Ground Technology. Reston; 2000. p.
travail (IRSST) and the industrial partners of the Research Institute 259–69.
on Mines and the Environment (RIME UQAT-Polytechnique).
904 L. Li, P. Yang / International Journal of Mining Science and Technology 25 (2015) 897–904

[34] Hawlader BC, Imai G, Muhunthan B. Numerical study of the factors affecting [39] Li L, Aubertin M. Horizontal pressure on barricades for backfilled stopes: part II
the consolidation of clay with vertical drains. Geotext Geomembr submerged conditions. Can Geotech J 2009;46(1):47–56.
2002;20:213–39. [40] James M, Aubertin M, Wijewickreme D, Wilson GW. A laboratory investigation
[35] Welker AL, Gilbert RB. Calibration of flow and transport model with a bench- of the dynamic properties of tailings. Can Geotech J 2011;48(11):1587–600.
scale prefabricated vertical drain remediation system. J Geotech Geoenviron [41] Pépin N, Aubertin M, James M. Seismic table investigation of the effect of
Eng 2003;129(1):81–90. inclusions on the cyclic behaviour of tailings. Can Geotech J 2012;49
[36] Das BM. Principles of foundation engineering. Pacific Grove: Brooks/Cole; (4):416–26.
2004. [42] Jaouhar EM. Analyse de l’effet d’inclusions drainantes sur la consolidation de
[37] Ghandeharioon A, Indraratna B, Rujikiatkamjorn C. Laboratory and finite- sols fins et de résidus miniers. Montréal: École Polytechnique de Montréal;
element investigation of soil disturbance associated with the installation of 2012.
mandrel-driven prefabricated vertical drains. J Geotech Geoenviron Eng [43] Blond E, Saunier P. Laboratory evaluation of the performance of tubular
2012;138(3):295–308. drainage geocomposites for ore filtration and acid leachate collection. In:
[38] Li L, Aubertin M. Horizontal pressure on barricades for backfilled stopes: part I Proceedings of Geosynthetics Mining Solutions. Vancouver; 2014. p. 99–106.
fully drained conditions. Can Geotech J 2009;46(1):37–46.

View publication stats

You might also like