Professional Documents
Culture Documents
net/publication/284084774
CITATIONS READS
9 194
2 authors:
Li Li Pengyu Yang
Polytechnique Montréal Polytechnique Montréal
79 PUBLICATIONS 1,150 CITATIONS 11 PUBLICATIONS 45 CITATIONS
All content following this page was uploaded by Pengyu Yang on 24 October 2017.
a r t i c l e i n f o a b s t r a c t
Article history: Cemented paste backfill (CPB) is gaining popularity in many underground mines worldwide. Sufficient
Received 6 November 2014 water is added into CPB to make a flowable material for pipe transportation. Barricades are built near
Received in revised form 21 January 2015 the drawpoints to prevent in-rush of the fill slurry. To avoid barricade failures resulting from excessive
Accepted 23 March 2015
backfill pressures, backfilling is typically performed with a plug pour followed by a final pour. The inter-
Available online 3 November 2015
val between the two pours should be shortened or removed to increase mining productivity and avoid
pipe clogging. Recently, Li proposed to apply wick drains in backfilled stopes to promote drainage and
Keywords:
consolidation. The preliminary simulations by considering an instantaneous filling indicated that the
Mines
Cemented paste backfill
drainage of CPB can be significantly accelerated by using wick drains. Barricade was not considered.
Backfilled stopes Here, some new numerical modellings are presented with more representative filling sequences, stope
Numerical analyses geometry, and different draining configurations. The results illustrate that the stope can be backfilled
Drainage continuously by using wick drains.
Wick drains Ó 2015 Published by Elsevier B.V. on behalf of China University of Mining & Technology.
1. Introduction In the past three decades, CPB has been developed and widely
adopted in many underground mines in Canada, Australia, China,
Underground mining involves creating voids (i.e. stopes) that and elsewhere. Generally consisting of 70–85% (solid weight) of
could endanger ground stability when the stope dimensions are full tailings, CPB has many operational and environmental benefits
too large. This may impact the ore recovery and dilution rates, [6,12]. However, sufficient amount of water is added into the back-
cause ground subsidence, and lead to serious safety issues. On fill to make a flowable material for pipe transportation from sur-
the other hand, the mining practice produces a large amount of face backfill plant to underground voids (Fig. 1, left picture).
mine wastes including waste rock and tailings. Usually, the former Because of the flowability of backfill, barricades have to be built
is stacked in the form of waste rock piles while the latter is depos- near the drawpoints to prevent the in-rush of backfill (Fig. 1, right
ited at tailing impoundments. In both cases, the mine wastes are picture).
disposed on the ground surface and occupy a lot of land, and Once placed in the stope, CPB’s particles tend to settle down
may cause instability and acid mine drainage [1–3]. To date, sev- under self-weight, leading to establishment of excess pore-water
eral methods have been developed to address these problems, pressure (PWP) [13–18]. The process of the dissipation of the
among which stope backfilling is considered as the optimal excess PWP is a well-known phenomenon called self-weight con-
method. solidation or sedimentation [18–23]. Due to the development of
In general, mining backfill plays the role of ensuring stability of the excess PWP and to avoid excessive backfill loads exerted on
regional ground and local stopes, increasing ore recovery rate and barricades, stope filling is typically divided into a plug pour and
minimizing ore dilution [4–11]. The surface disposal of mine a final pour in practice, separated by an interval of several days
wastes can be disposed by backfilling, which is regarded as an [17,24,25]. For the sake of barricade stability, this interval is
environmental friendly solution [1,2]. Mining backfill is typically necessary, even obligatory in some cases. Alternatively, the rising
classified as rockfill, hydraulic backfill and cemented paste backfill rate (i.e. speed, influenced by the flow rate of backfill feeding and
(CPB); each has some advantages and limitations [6]. stope geometries) of the backfilling should be low enough [16].
On the other hand, from an economic point of view, this interval
is undesirable because it slowdowns the production and occasions
pipe clogging. Consequently, one seeks a fast and continuous back-
⇑ Corresponding author. Tel.: +1 514 3404711.
filling by means of improved drainage and consolidation of backfill.
E-mail address: pengyu.yang@polymtl.ca (P. Yang).
http://dx.doi.org/10.1016/j.ijmst.2015.09.004
2095-2686/Ó 2015 Published by Elsevier B.V. on behalf of China University of Mining & Technology.
898 L. Li, P. Yang / International Journal of Mining Science and Technology 25 (2015) 897–904
Hook
Step 1 Step 2
Wick drain
Blasting
hole
Step 3 Step 4
Backfill
Fig. 1. A stope being backfilled (left) with a barricade constructed near the
Wick drain
drawpoint (right).
Barricade
Geotextile fabric
H final
Final pour
L
Barricade
B
H
Ld
Polypropylene core
H plug
Plug Hd
Table 2
Some typical hydraulic and mechanical properties of CPB and wick drains.
Material type Saturated hydraulic Coefficient of volume Young’s modulus E0 (kPa) Unit weight c (kN/m3) Poisson’s ratio l
conductivity ksat (107 m/s) change mv (kPa1)
Backfill 1.0 0.0002 5000 20 0.334
Wick drains 1.0 0.0002 5000 20 0.334
0.5 1×10-2 1
Hydraulic conductivity (m/day)
1×10-3
Water content (m3/m3)
0.4
1×10-4
k-modifier
0.3
1×10-5
0.2
1×10-6
30 30
28 28
(a) (b)
26 26
24 24
22 22
20 20
18 18
16 16
14 14
y (m)
Wick
y (m)
12 12
drains
10 10
Drain
8 holes 8
6 6
4 4
2 2
0 0
-2 -2
-4 -4
-6 -6
-5 0 5 10 -5 0 5 10
x (m) x (m)
Fig. 6. GeoStudio models of a backfilled stope: (a) with no wick drains but 5 drain holes through the barricade; (b) with 5 wick drains within the backfill and through the
barricade.
3.3.1. Stress distributions at the stage of the plug pour the barricade are further detailed in Fig. 9. Nonlinear distributions
The distribution of excess PWP immediately after placing the are observed along the barricade height in both cases. Also, one
last layer of the plug pouring is illustrated in Fig. 7. In the absence notices that the horizontal total stresses are much smaller than
of wick drains (Fig. 7a), excess PWP could partly dissipate at the the geostatic overburden pressures of the plug pour.
end of the plug pouring due to drainage and consolidation upward
to the backfill surface and downward through the 5 drain holes 3.3.2. Stress distributions at the stage of the final pour
during the 90 hours’ filling. An excess PWP between 20 and Fig. 10 shows the excess PWP distribution immediately after
50 kPa is still observed near the barricade, which indicates that placing the last layer of the final pour for the case of 5 drain holes
the drainage and consolidation are in progress. With the use of 5 (Fig. 10a) and 5 wick drains (Fig. 10b). Again, one observes the dis-
wick drains, the excess PWP on the barricade is close to nil, which sipation of a large portion of the excess PWP near the barricade
means that the drainage and consolidation are almost complete even in the absence of wick drains (Fig. 10a), resulting in a
(Fig. 7b). remaining value close to 120 kPa. As indicated in Fig. 10b, after
The distribution of horizontal total stress immediately after introducing 5 wick drains, the drainage and consolidation are
placing the last layer of the plug pouring is shown in Fig. 8. It is almost complete and excess PWP is close to zero near the
observed that the horizontal total stresses along the barricade barricade.
are largely reduced (by around 50% at the mid-height) after using Fig. 11 shows the horizontal total stress distribution immedi-
5 wick drains. The distributions of horizontal total stresses along ately after placing the last layer of the final pour. In the case of
6 6
(a) (b)
4 20 4
40
2 2
60 5 5
5
y (m)
y (m)
0 15
0
80 25
40
100
-2 -2
5
60
120
5
-4 -4
140 5
-6 -6
-5 0 5 10 -5 0 5 10
x (m) x (m)
Fig. 7. Numerical results of the excess PWP (kPa) distribution shortly after placing the last layer of the plug pouring: (a) with no wick drains but 5 drain holes through the
barricade; (b) with 5 wick drains within the backfill and through the barricade.
L. Li, P. Yang / International Journal of Mining Science and Technology 25 (2015) 897–904 901
6 6
(a) (b)
4 4
20
40 20
2 2
60
40
y (m)
y (m)
0 0
80 60 20
40
-2 -2
100
120
-4 140 -4 60
80
-6 -6
-5 0 5 10 -5 0 5 10
x (m) x (m)
Fig. 8. Numerical results of the horizontal total stress (kPa) distribution shortly after placing the last layer of the plug pour backfill: (a) without wick drains; (b) with 5 wick
drains within the backfill and through the barricade.
Horizontal total stress Fig. 12 shows the distribution of horizontal total stress along
(kPa) the barricade after placing the last layer of the final pour. Again,
0 30 60 90 120 150 180
it is noted that the horizontal total stress distributions for both
cases are nonlinear along the barricade. In the absence of wick
ov
-1
drains, the horizontal total stresses are quite larger than the geo-
erb
Ge n pr
Wi
ur
Wi
tat
-2
ut
5
ic re
wi
wi
ck
u
ck
dra
ins
the case with 5 wick drains, Fig. 12 illustrates that the horizontal
ins
-4
total stresses close to the top and base of the barricade are lower
-5 than the plug’s geostatic pressures (80 and 180 kPa, respectively,
see Fig. 9). However, the plug’s geostatic pressures near the mid-
Fig. 9. Distributions of the horizontal total stresses along the barricade shortly after height of the barricade are exceeded. Therefore, the loads exerted
placing the last layer of the plug pouring obtained by numerical modeling and
on the barricade should be compared with the design load P to
based on the geostatic overburden pressure.
see whether the barricade failure would occur in such condition.
40
24 24
22 80 (a) 5 (b)
22 5
5
120 15 5
15
20 20
18 160 18
16 200 16
14 14
y (m)
12 12
280
y (m)
10 10
8 8
35
45
15
6 360 6
4 4
400
2 2
0 0
440
5
160
-2 -2
480 5
24
36
5
0
0
-4 -4
-6 -6
-5 0 5 10 -5 0 5 10
x (m) x (m)
Fig. 10. Numerical results of the excess PWP (kPa) distribution after placing the last layer of the final pouring: (a) with no wick drains but 5 drain holes through the barricade;
(b) with 5 wick drains within the backfill and through the barricade.
902 L. Li, P. Yang / International Journal of Mining Science and Technology 25 (2015) 897–904
24 24
40
20
22 22
(a) (b)
80
20 20
120 60
18 18
16 16 100
200
14 14
12 12 140
y (m)
y (m)
280
10 10
8 8 180
6 360 6
220
4 400 4
2
2 440 260
42
0 0
0
440 280 100
0
22
180
-2 -2
36
40
320
26
-4
0
-4 520
0
140
-6 -6
-5 0 5 10 -5 0 5 10
x (m) x (m)
Fig. 11. Numerical results of the horizontal total stress (kPa) distribution shortly after placing the last layer of the final pouring: (a) with no wick drains but 5 drain holes
through the barricade; (b) with 5 wick drains within the backfill and through the barricade.
Final
0 wick drain; 0 drain hole
pour
(kPa)
0 10 0 20 0 30 0 40 0 50 0 600 14000 0 wick drain; 5 drain hole
1 wick drain; 5 drain hole
12000
Loads on barricade (kN)
urden
Geos
out w
8000
-2
5 wic
tatic
y (m)
press
ick d
6000
Plug
pour
k dra
-3
ure
rains
4000
ins
-4 2000
0
-5 5 10 15 20 25 30
Fill height (m)
Fig. 12. Distribution of the horizontal total stress along the barricade shortly after
placing the last layer of the final pour obtained by numerical modeling and based on Fig. 13. Comparison between the barricade design load and variation of the
geostatic overburden pressure. barricade loads during filling for several scenarios of draining system, obtained by
numerical modeling.
and non-linear stress distribution along the height of the barricade. paused at a height of 22 m. When 5 wick drains are introduced,
The backfill loads exercised on the barricade can be obtained by the applied loads are always below the barricade design load dur-
integrating the horizontal total stresses over the barricade area. ing the entire filling, indicating a possible continuous filling.
Fig. 13 illustrates the backfill loads exercised on the barricade
obtained numerically for several scenarios of draining system: no 4. Discussion
draining system (0 drain hole, 0 wick drain; details not shown), 5
drain holes through the barricade but no wick drain, 5 drain holes The hydraulic conductivity of hydraulic backfill is several orders
combined with 1 wick drain (details not shown), and 5 wick drains. of magnitude larger than that of CPB, which contains a large
The allowable barricade load P (3250 kN, obtained by the plug’s amount of fine particles (<20 lm). The excess PWP in a hydraulic
geostatic pressure) is also plotted for the sake of comparison. backfill dissipates quite quickly, leading to the bleeding of a lot
The results shown in Fig. 13 indicate that a filling interval is of free water from barricades and at the top of the backfill. The
obligated once the plug pour is complete at a filling height of drainage of bleeding water is mostly dominated by the draining
9 m if there is no draining system installed in the barricade. With capacity of the barricades. Therefore, the application of wick drains
5 drain holes passing through the barricade but no wick drain, it is proposed specifically for CPB having limited permeability.
is observed that the barricade design load is exceeded when the Wick drain is only one type of vertical drains widely used in
filling height reaches around 15 m. To ensure the barricade stabil- foundation engineering. Sand columns are the other type of verti-
ity, the filling then has to be halted to allow the dissipation of cal drains commonly used in civil engineering to accelerate the
excess PWP. With the combination of one wick drain and 5 drain drainage and consolidation of soft soils [31]. In mining engineering,
holes in the barricade, Fig. 13 indicates that the filling has to be waste rocks have been introduced into tailing impoundments to
L. Li, P. Yang / International Journal of Mining Science and Technology 25 (2015) 897–904 903
[34] Hawlader BC, Imai G, Muhunthan B. Numerical study of the factors affecting [39] Li L, Aubertin M. Horizontal pressure on barricades for backfilled stopes: part II
the consolidation of clay with vertical drains. Geotext Geomembr submerged conditions. Can Geotech J 2009;46(1):47–56.
2002;20:213–39. [40] James M, Aubertin M, Wijewickreme D, Wilson GW. A laboratory investigation
[35] Welker AL, Gilbert RB. Calibration of flow and transport model with a bench- of the dynamic properties of tailings. Can Geotech J 2011;48(11):1587–600.
scale prefabricated vertical drain remediation system. J Geotech Geoenviron [41] Pépin N, Aubertin M, James M. Seismic table investigation of the effect of
Eng 2003;129(1):81–90. inclusions on the cyclic behaviour of tailings. Can Geotech J 2012;49
[36] Das BM. Principles of foundation engineering. Pacific Grove: Brooks/Cole; (4):416–26.
2004. [42] Jaouhar EM. Analyse de l’effet d’inclusions drainantes sur la consolidation de
[37] Ghandeharioon A, Indraratna B, Rujikiatkamjorn C. Laboratory and finite- sols fins et de résidus miniers. Montréal: École Polytechnique de Montréal;
element investigation of soil disturbance associated with the installation of 2012.
mandrel-driven prefabricated vertical drains. J Geotech Geoenviron Eng [43] Blond E, Saunier P. Laboratory evaluation of the performance of tubular
2012;138(3):295–308. drainage geocomposites for ore filtration and acid leachate collection. In:
[38] Li L, Aubertin M. Horizontal pressure on barricades for backfilled stopes: part I Proceedings of Geosynthetics Mining Solutions. Vancouver; 2014. p. 99–106.
fully drained conditions. Can Geotech J 2009;46(1):37–46.