CRONOGRAMA VALORIZADO

PROYECTO: EDIFICACION

LUGAR : XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
DISTRITO : XXXXX PROVINCIA : XXXX DPTO:XXXXX
1° MES (30 dias) 2° MES (30 dias)
PART. DESCRIPCION UND METRADO P. UNT. TOTAL
% AVANCE MONTO S/. % AVANCE MONTO S/.
01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M. und 1.00 850.00 850.00 100.00% 850.00 0.00% -
01.02 ALMACEN, OFICINA Y CASETA DE GUARDIANIA mes 1.50 3,250.00 4,875.00 50.00% 2,437.50 50.00% 2,437.50
01.03 SERVICIOS HIGIENICOS PROVISIONALES m2 5.25 61.57 323.24 100.00% 323.24 0.00% -
01.04 INSTALACION PROVISIONAL DE ENERGIA ELECTRICA glb 1.00 200.00 200.00 100.00% 200.00 0.00% -
01.05 PAGO MENSUAL DE USO DE ENERGIA ELECTRICA mes 1.50 50.00 75.00 50.00% 37.50 50.00% 37.50
01.06 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS glb 1.00 1,000.00 1,000.00 50.00% 500.00 50.00% 500.00
01.07 LIMPIEZA DEL TERRENO MANUAL m2 63.00 0.42 26.46 100.00% 26.46 0.00% -
01.08 SEGURIDAD Y SALUD EN EL TRABAJO
01.08.01 EQUIPO DE PROTECCION INDIVIDUAL und 8.00 66.60 532.80 90.00% 479.52 10.00% 53.28
01.08.02 EQUIPO DE PROTECCION COLECTIVA glb 1.00 323.00 323.00 100.00% 323.00 0.00% -
01.08.03 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 74.00 74.00 100.00% 74.00 0.00% -
02 ESTRUCTURAS
02.01 OBRAS PRELIMINARES
02.01.01 TRAZO, NIVELES Y REPLANTEO m2 63.00 1.62 102.06 100.00% 102.06 0.00% -
02.02 MOVIMIENTO DE TIERRAS
02.02.01 NIVELACION INTERIOR Y APISONADO MANUAL m2 54.00 10.00 540.00 100.00% 540.00 0.00% -
02.02.02 EXCAVACION DE ZANJA m3 26.13 48.15 1,258.16 100.00% 1,258.16 0.00% -
02.02.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 1.18 14.08 16.61 100.00% 16.61 0.00% -
02.02.04 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 63.00 19.22 1,210.86 100.00% 1,210.86 0.00% -
02.02.05 ELIMINACION MATERIAL EXCEDENTE m3 24.60 20.29 499.13 100.00% 499.13 0.00% -
02.03 OBRAS DE CONCRETO -
02.03.01 CONCRETO SIMPLE
02.03.01.01 CONCRETO PARA SOLADO DE 4", MEZCLA 1:12 m2 11.40 28.94 329.92 100.00% 329.92 0.00%
02.03.01.02 CONCRETO PARA CIMIENTO CORRIDO, MEZCLA 1:10 + 30% P.G. m3 7.44 246.26 1,830.69 100.00% 1,830.69 0.00% -
02.03.01.03 ENCOFRADO Y DESENCOFRADO PARA CIMIENTO CORRIDO m2 20.18 35.47 715.78 100.00% 715.78 0.00% -
02.03.01.04 CONCRETO PARA SOBRECIMIENTO, MEZCLA 1:8 + 25% P.M. m3 1.54 286.92 441.86 100.00% 441.86 0.00% -
02.03.01.05 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 20.57 37.30 767.26 100.00% 767.26 0.00%
02.03.01.06 FALSO PISO DE 4" DE CONCRETO 1:10 m2 48.39 40.42 1,955.92 100.00% 1,955.92 0.00%
02.03.02 CONCRETO ARMADO
02.03.02.01 ZAPATAS
02.03.02.01.01 CONCRETO ZAPATAS f'c=210 kg/cm2 m3 6.84 509.70 3,486.35 100.00% 3,486.35 0.00% -
02.03.02.01.02 ENCOFRADO Y DESENCOFRADO PARA ZAPATAS m2 16.97 35.47 601.93 100.00% 601.93 0.00% -
02.03.02.01.03 ACERO CORRUGADO FY=4200 kg/cm2 GRADO 60 kg 168.38 7.38 1,242.64 100.00% 1,242.64 0.00%
02.03.02.02 VIGA DE CIMENTACION
02.03.02.02.01 CONCRETO PARA VIGAS DE CIMENTACION, F'C=210KG/CM2 m3 3.24 456.07 1,477.67 100.00% 1,477.67 0.00% -
02.03.02.02.02 ENCOFRADO Y DESENCOFRADO PARA VIGA DE CIMENTACION m2 25.90 48.24 1,249.42 100.00% 1,249.42 0.00%
02.03.02.02.03 ACERO CORRUGADO FY=4200 kg/cm2 GRADO 60 kg 332.29 7.38 2,452.30 100.00% 2,452.30 0.00% -
02.03.02.03 COLUMNAS
02.03.02.03.01 CONCRETO PARA COLUMNAS, F'C=210KG/CM2 m3 3.26 620.23 2,021.95 100.00% 2,021.95 0.00% -
02.03.02.03.02 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2 37.60 48.24 1,813.82 100.00% 1,813.82 0.00%
02.03.02.03.03 ACERO CORRUGADO FY=4200 kg/cm2 GRADO 60 kg 529.38 7.38 3,906.82 100.00% 3,906.82 0.00% -
02.03.02.04 VIGAS
02.03.02.04.01 CONCRETO PARA VIGAS, F'C=210KG/CM2 m3 4.83 520.12 2,512.18 100.00% 2,512.18 0.00% -
02.03.02.04.02 ENCOFRADO Y DESENCOFRADO PARA VIGAS m2 33.73 45.54 1,536.06 100.00% 1,536.06 0.00%
02.03.02.04.03 ACERO CORRUGADO FY=4200 kg/cm2 GRADO 60 kg 713.61 7.38 5,266.44 100.00% 5,266.44 0.00% -
02.03.02.05 LOSAS ALIGERADAS
02.03.02.05.01 CONCRETO PARA LOSA ALIGERADA, F'C=210KG/CM2 m3 5.51 499.31 2,751.20 100.00% 2,751.20 0.00% -
02.03.02.05.02 ENCOFRADO Y DESENCOFRADO PARA LOSA ALIGERADA m2 36.23 37.08 1,343.41 100.00% 1,343.41 0.00% -
02.03.02.05.03 ACERO CORRUGADO FY=4200 kg/cm2 GRADO 60 kg 290.06 7.38 2,140.64 100.00% 2,140.64 0.00%
02.03.02.05.04 LADRILLO HUECO DE ARCILLA 15X30X30, PARA TECHO ALIGERADO und 409.09 3.97 1,624.09 100.00% 1,624.09 0.00% -
02.03.02.05.05 MESA DE CONCRETO ARMADO MAS ENCHAPE PARA LAVADERO m3 2.11 214.75 453.12 100.00% 453.12 0.00%
03 ARQUITECTURA
03.01 ALBAÑILERIA
03.01.01 MURO DE SOGA LADRILLO KING KONG m2 47.85 80.01 3,828.48 100.00% 3,828.48 0.00% -
03.01.02 ACERO DE REFUERZO kg 150.00 1.58 237.00 100.00% 237.00 0.00% -
03.02 REVOQUES, ENLUCIDOS Y MOLDURAS
03.02.01 TARRAJEO DE MUROS INTERIORES Y EXTERIORES m2 156.59 41.15 6,443.68 100.00% 6,443.68 0.00% -
03.02.02 TARRAJEO DE VIGAS m2 17.92 56.65 1,015.17 100.00% 1,015.17 0.00% -
03.02.03 TARRAJEO COLUMNAS m2 5.64 56.65 319.51 100.00% 319.51 0.00% -
03.02.04 VESTIDURAS DE DERRAMES EN PUERTAS, VENTANAS Y VANOS m 49.32 15.29 754.10 100.00% 754.10 0.00% -
03.02.05 BRUÑAS DE 1 X 1 cm m 330.00 2.57 848.10 100.00% 848.10 0.00% -
03.02.06 TARRAJEO EN CIELORASO m2 49.11 36.20 1,777.78 100.00% 1,777.78 0.00% -
03.03 PISOS Y PAVIMENTOS
03.03.01 PISO CERAMICO COLOR BLANCO DE 30X30CM INTERIOR m2 48.39 52.21 2,526.44 0.00% - 100.00% 2,526.44
03.04 VEREDAS
03.04.01 VEREDA DE CONCRETO FC=175KG/CM2, INCL. ENCOFRADO m2 9.00 63.51 571.59 100.00% 571.59 0.00% -
03.04.02 JUNTA DE DILATACION e=1" m 9.00 9.54 85.86 100.00% 85.86 0.00% -
03.05 CONTRAZOCALOS
03.05.01 CONTRAZOCALO CERAMICA 10x20 cm. m 35.00 19.58 685.30 0.00% - 100.00% 685.30
03.06 ZOCALOS
03.06.01 ZOCALO DE CERAMICA 20 X 30cm m2 14.74 48.23 710.91 0.00% - 100.00% 710.91
03.07 CARPINTERIA DE MADERA
03.07.01 PUERTA P-01 und 1.00 500.00 500.00 0.00% - 100.00% 500.00
03.07.02 PUERTA CONTRAPLACADA 35mm CON TRIPLAY 4mm INCLUYE MARCO und 1.00 500.00 500.00 0.00% - 100.00% 500.00
03.07.03 PUERTA CONTRAPLACADA 35mm CON TRIPLAY 4mm INCLUYE MARCO und 1.00 500.00 500.00 0.00% - 100.00% 500.00
03.07.04 VENTANAS CON HOJAS DE ALUMINIO m2 12.21 90.00 1,098.90 0.00% - 100.00% 1,098.90
03.08 CERRAJERIA
03.08.01 BISAGRAS CAPUCHINA ALUMINIZADA DE 4" und 4.00 38.49 153.96 0.00% - 100.00% 153.96
03.08.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 6.00 35.49 212.94 0.00% - 100.00% 212.94
03.08.03 CERRADURA PARA PUERTA und 1.00 100.00 100.00 0.00% - 100.00% 100.00
03.08.04 CERRADURA DE PERILLA EN PUERTA C.I. und 2.00 106.49 212.98 0.00% - 100.00% 212.98
03.09 VIDRIOS, CRISTALES Y SIMILARES
03.09.01 VIDRIO SEMIDOBLE INCOLORO CRUDO p2 12.21 12.86 157.02 0.00% - 100.00% 157.02
03.10 PINTURA
03.10.01 PINTURA LATEX EN CIELO RASO m2 44.52 9.46 421.16 0.00% - 100.00% 421.16
03.10.02 PINTURA LATEX EN MUROS INTERIORES Y EXTERIORES m2 156.59 24.79 3,881.87 0.00% - 100.00% 3,881.87
03.10.03 PINTURA LATEX EN VIGAS Y COLUMNAS m2 23.56 24.79 584.05 0.00% - 100.00% 584.05
03.10.04 BARNIZ EN VENTANAS m2 6.24 13.61 84.93 0.00% - 100.00% 84.93
03.10.05 BARNIZ EN PUERTAS DE MADERA m2 7.00 14.49 101.43 0.00% - 100.00% 101.43
04 INSTALACIONES ELECTRICAS
04.01 SALIDA PARA CENTRO DE LUZ pto 9.00 52.95 476.55 100.00% 476.55 0.00% -
04.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE pto 5.00 78.66 393.30 100.00% 393.30 0.00% -
04.03 ARTEFACTO FLUORESCENTE TIPO E2 und 7.00 83.59 585.13 0.00% - 100.00% 585.13
04.04 FOCO LUZ LED (AHORRADOR) und 2.00 31.45 62.90 0.00% - 100.00% 62.90
04.05 TABLERO DE DISTRIBUCION und 1.00 229.43 229.43 0.00% - 100.00% 229.43
05 INSTALACIONES SANITARIAS
05.01 SISTEMA DE DESAGUE
05.01.01 SALIDA DESAGUE DE PVC SAL 2" pto 3.00 32.42 97.26 100.00% 97.26 0.00% -
05.01.02 SALIDA DESAGUE DE PVC-SAL 4" pto 3.00 76.01 228.03 100.00% 228.03 0.00% -
05.01.03 SALIDA VENTILACION DE PVC-SAL 4" pto 1.00 80.21 80.21 100.00% 80.21 0.00% -
05.01.04 REGISTRO DE BRONCE 4" und 2.00 56.42 112.84 0.00% - 100.00% 112.84
05.01.05 TRAMPA "P" PVC DESAGUE DE PVC-SAL 4" pto 2.00 56.71 113.42 100.00% 113.42 0.00% -
05.01.06 SUMIDERO DE BRONCE ROSCADO 2" und 1.00 136.67 136.67 100.00% 136.67 0.00% -
05.01.07 CAJAS DE REGISTRO DE DESAGUE 12" x 24" und 1.00 370.16 370.16 100.00% 370.16 0.00% -
05.01.08 TUBERIA DE DESAGUE DE 4" m 8.00 20.77 166.16 100.00% 166.16 0.00% -
05.01.09 TUBERIA DE DESAGUE DE 2" m 6.00 16.65 99.90 100.00% 99.90 0.00% -
05.01.10 INSTALACION DE BIODIGESTOR, A TODO COSTO glb 1.00 2,000.00 2,000.00 0.00% - 100.00% 2,000.00
05.02 APARATOS SANITARIOS
05.02.01 INODORO ONE PIECE BLANCO und 1.00 246.00 246.00 0.00% - 100.00% 246.00
05.02.02 LAVATORIO IMPORTADO CON PEDESTAL COLOR und 1.00 153.50 153.50 0.00% - 100.00% 153.50
05.02.03 LAVADERO DE ACERO INOXIDABLE DOS POZAS CON ESCURRIDERO und 1.00 377.50 377.50 0.00% - 100.00% 377.50
05.02.04 COLOCACION DE DIFUSOR DE DUCHA und 1.00 173.55 173.55 0.00% - 100.00% 173.55
05.02.05 INSTALACION DE APARATOS SANITARIOS und 4.00 105.08 420.32 0.00% - 100.00% 420.32
05.02.06 ACCESORIOS PARA BAÑO glb 1.00 172.52 172.52 0.00% - 100.00% 172.52
05.03 SISTEMA DE AGUA FRIA
05.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2" pto 4.00 95.39 381.56 100.00% 381.56 0.00% -
04.03.02 RED DE DISTRIBUCION CON TUBERIA DE PVC C-10 DE 1/2" m 24.00 12.51 300.24 100.00% 300.24 0.00% -
04.03.03 CAJA DE REGISTRO DE AGUA DE 1/2"-3/4" und 1.00 44.16 44.16 0.00% - 100.00% 44.16
04.03.04 VALVULA COMPUERTA DE 1/2" und 1.00 56.68 56.68 0.00% - 100.00% 56.68
04.03.05 LLAVE DE LAVATORIO und 1.00 130.00 130.00 0.00% - 100.00% 130.00
CRONOGRAMA VALORIZADO
PROYECTO: EDIFICACION

LUGAR : XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
DISTRITO : XXXXX PROVINCIA : XXXX DPTO:XXXXX
1° MES (30 dias) 2° MES (30 dias)
PART. DESCRIPCION UND METRADO P. UNT. TOTAL
% AVANCE MONTO S/. % AVANCE MONTO S/.
04.03.06 LLAVE DE LAVADERO COCINA und 2.00 164.00 328.00 0.00% - 100.00% 328.00
04.03.07 TANQUE DE AGUA DE ETERNIT DE 1000 LITROS INCLUYE ACC. INTERNOS und 1.00 790.16 790.16 0.00% - 100.00% 790.16
06 EQUIPAMIENTO DE AULA
06.01 ADQUISICION DE SILLAS DE 0.30 DE ANCHO x 0.60 DE ALTO und 15.00 80.00 1,200.00 0.00% - 100.00% 1,200.00
06.02 ADQUISICION DE MESAS DE MADERA und 15.00 80.00 1,200.00 0.00% - 100.00% 1,200.00
06.03 ADQUISICION DE MESA Y SILLA PARA DOCENTE und 1.00 200.00 200.00 0.00% - 100.00% 200.00
06.04 ESTANTE 3 REPISAS und 3.00 120.00 360.00 0.00% - 100.00% 360.00
07 VARIOS
07.01 JUNSTA DE CONSTRUCCION CON TEKNOPORT m 22.05 7.76 171.11 100.00% 171.11 0.00% -
07.02 ROTURA DE PROBETAS und 5.00 80.00 400.00 100.00% 400.00 0.00% -
TOTAL COSTO DIRECTO S/. 94,398.21 70,095.36 24,302.86
GASTOS GENERALES 10% 9,439.82 7,009.54 2,430.29
UTILIDAD 7% 6,607.87 4,906.68 1,701.20
SUB TOTAL 110,445.90 82,011.57 28,434.34
IGV (18%) 19,880.26 14,762.08 5,118.18
PRESUPUESTO TOTAL 130,326.16 96,773.65 33,552.52
PRESUPUESTO TOTAL ACUMULADO 96,773.65 130,326.16
% AVANCE MENSUAL 74.25% 25.75%
% AVANCE ACUMULADO 74.25% 100.00%