LABOR ESTIMATE

WORK DESCRIPTION MANPOWER

CONCRETING
1 Plain Flooring 2 men
2 Reinforced Flooring 2 men
3 Column and Beam 2 men
FINISHING
Rough Flooring 2 men
CHB Joints 2 men
PLASTERING
CHB 2 men
LAYING
CHB 2 men
Glazed Tile 4" x 4" 2 men
Glazed Tile 6" x 6" 2 men
BREAKING
Breaking Old R-C Flooring 2 men
INSTALLATION
Water Closet 2 men
Lavatory 2 men
GI Sheets 32" x 8" on Steel Frames 2 men
GI Sheets 32" x 8" on Wooden Frames 2 men
GI Sheets 32" x 12" on Steel Frames 2 men
GI Sheets 32" x 12" on Wooden Frames 2 men
Fabricating & Installation of Gutter
2 men
Downspout Ridge Roll 32" x 8" GI Sheets
GI Pipe 1/2 dia x 20" 2 men
Doors and Windows Jamb 1 man
Door (Complete of Hinges and Knob) 1 man
Plywood Board 4" x 8" 2 men
Wooden Post 4" x 4" x 18' 2 men
Wood Jalousies Windows 30" x 45" 1 man
FABRICATION
Doors (Excluding Planning of Frames) 1 man
PLANNING
Rough Lumber (including Alignment) 2" x 4"
1 man
x 18'
Rough Lumber (No Alignment) 1 man
MANHOUR

pour 1.2 cu.m. Concrete/ day


pour 0.84 cu.m. Concrete/ day
pour 0.5 cu.m. Concrete/ day

finishes 72 sqm. / day


finishes 420 pcs / day

plasters 8 sqm / day

lay 100 pcs/ day


lay 100 pcs/ day
lay 72 pcs/ day

break 0.30 cum. / day

1 set wc / day
1 set lav / day
11 sheets/ day
20 sheets/ day
10 sheets/ day
15 sheets/ day

5 sheets/ day

20 lights/ day
340 bd ft/ day
2 pcs door/ day
15 sheets/ day
6 pcs or 96 bd ft/ day
2 pcs or 18.75 bd ft/ day

3 pcs/ day

4 pcs or 48 bd ft/ day


120 bd ft/ day
CONSTRUCTION WORK CAPACITIES IN MANHOURS

WORK DESCRIPTION MANHOUR


I. EARTHWORK
a. Excavation 182 to 2.89 manhour/ cu.m.
b. Backfill 134 manhour/ cu.m.

II. FORMWORK
a. Footing, grade, column 2.5 manhour/ sq.m.
b. Beams, bond beams, floor slab 2.8 manhour/ sq.m.
c. Roof beams and bond beams 3.01 man hour/ sq.m.
d. Roof Slabs 3.34 man hour/ sq.m.
e. Retaining Walls 2.4 man hour/ sq.m.
f. Stairs and Landing 2.48 man hour/ sq.m.
g. Form Oil application 6.0 man hour/ 10 sq.m.

III. REINFORCEMENT
a. Footings up to roofing ave. 9.0 manhour/ 100 kilos
b. Grade slab EWP 13.0 man hour/ 100 sq.m.
c. Floor membrane 15.0 man hour/ 100 sq.m.
d. Roof beams and bond beams 2.88 manhour/ cu.m.
e. Stairs 2.6 man hours/ cu.m.
f. Roof Slab 2.91 manhour/ day for 7 days
g. Equipment
1. Vibrator 16 min/ cu.m.
2. Crane with concrete bucket 4 cu.m./ man hour

CAPABILITIES OF MANUAL LABOR PER HOUR

Unit Type of Work Capability

1 man a. Excavating Loam or sand 0.76 cu.m.


b. Excavating Clay or Heavy Soil 0.61 cu.m.
c. Excavating Rock 0.38 cu.m.
d. Backfilling 1.22 cu.m.
e. Spreading, tamping and Grading 2.09 cu.m.
f. Placing escombro fill 2.0 cu.m.
g. Placing binders 4.0 cu.m.
h. Cleaning undergrowth and small bush 20 sq.m.
i. Cleaning underground and brush 12" dia 20 sq.m.

1 mason & 1
a. Laying of CHB and adobe 22 pcs
helper
b. Cement Finish 28 sq.m.

1 Carpenter &
a. Erecting Forms 1.86 sq.m.
1 helper
b. Removing Forms 1.86 sq.m.
CAPABILITIES OF MANUAL LABOR PER HOUR

Item Type of Work Capability

Dozer a. Clearing 500 sq.m./ hr


b. Stripping 200 sq.m./ hr
c. Excavation 25 cu.m./ hr
d. Quarrying 50 cu.m./ hr
e. Pushing 3 sq.m./ hr

Grader Sub-graving 300 sq.m./ hr


Spreading 40 cu.m./ hr

Pay Loader a. Loading 30 cu.m./ hr

Crane Shovel a. Loading 35 cu.m./ hr

Sheep's Foot a. Static roling (12 passes - 15 cm lift) 135 cu.m./ hr

Roller b. Vibratory Rolling ( 4 passes - 15 cm lift) 135 cu.m./ hr

Tractor -
Drawn Roller ( a. Vibratory Rolling ( 6 passes - 20 cm lift) 240 cmph
1-d)

No. 3w road
a. Static rolling (6 passes - 20 cm lift) 24 cmph
roller

Tandem Roller a. Static rolling (6 passes - 20 cm lift) 24 cmph

5-T dump
a. Hauling Common Borrow 3.5 cmpt
truck
b. Hauling Selected borrow base course 5 cmpt

NOTE: CMPH = CUM/ HR; CMPT = CU.M./ TRUCK

2 1/2 T hauling common borrow 2.5 cu.m. / trip


dump truck hauling sbbc 2.0 cu.m. / trip
buggy hauling conc. Mixer 0.17 cu.m. / trip
wheel borrow hauling aggregates 0.07 cu.m. / trip
water truck watering 1000 sq.m/ hr
asphalt
spraying asphalt prime 300 sq.m/ hr
distributor
16-S con
9 cm. Hr
mixer
rock crusher crushing mixed sand and gravel 30.m./ hr
concrete
cibrating conc. Mix 40 cu.m./ hr
vibrator
conc. Floor
finishing con. Floor 140 sq.m./ hr
finisher
scraper towed
hauling heap capacity 11 cu.m/ hr
12 cy cap

scraper tor-
hauling heap capacity 22 cu.m/ hr
mapull 45 ton
percussion drillings hard rock 0.23 m/ hr
drilling loose rock 0.30 m/ hr
drilling limestone 0.38 m/ hr
drilling sticky clay 0.49 m/ hr
drilling loose clay 0.76 m/ hr

Note: 1 metric ton of asphalt conc. Covers 8 sq.m. Of pavement 0.005m. Thick or 0.43 cu.m.
Asphalt concrete
UNIT MANHOUR ITEM OF WORK

1 Common Excavation (Manual) 6.0 MH/ cu.m


2 Common Excavation (Machine) 0.5 MH/ cu.m
3 Hook Excavation (Manual and Machine) 8.0 MH/ cu.m
4 Structural Backfill (Manual) 5.0 MH/ cu.m
5 Structural Backfill (Machine) 2.0 MH/ cu.m
6 Hauling Spoils 1.0 MH/ cu.m
7 Trenching by Hand 6.0 MH/ cu.m
8 Trenching by Machine 0.2 MH/ cu.m
9 Piping Installation
Asbestos Cement Pipe
1/2 " Ø 20 MH/ 100 BF
3/4 " Ø 20 MH/ 100 BF
1"Ø 20.5 MH/ 100 BF
1 " - 1/4" Ø 22.5 MH/ 100 BF
1 " - 1/2" Ø 25 MH/ 100 BF
2" Ø 25 MH/ 100 BF
2 " - 1/2" Ø 30 MH/ 100 BF
3" Ø 33 MH/ 100 BF
3 " - 1/2" Ø 35 MH/ 100 BF
4" Ø 40 MH/ 100 BF
Cast Iron Pipe
2" Ø 66.1 mh/ 100 lf
4" Ø 100.2 mh/ 100 lf
6" Ø 150.3
8" Ø 200.4
10" Ø 300.6
12" Ø 317.3
14" Ø 367.4
16" Ø 417.5

PVC Pipes
1/2 " Ø 20 MH/ 100 BF
3/4 " Ø 20 MH/ 100 BF
1"Ø 22.5
1 " - 1/4" Ø 22.5
1 " - 1/2" Ø 25
2" Ø 25
2 " - 1/2" Ø 30
3" Ø 33
3 " - 1/3" Ø 35
4" Ø 40
5" Ø 50
6" Ø 75
CONCRETE FOUNDATION AND ELEVATED CONCRETE UNIT MANHOURS

1 GRADE MEMBER
Formwork 2.54 MH/ SQM
Concreting 8.54 MH/ SQM
Rebars Work 0.071 MH/ KG
Finishing 0.4 MH/ SQM

2 SUSPENDED MEMBER
Formwork 3.28 MH/ M
Concreting 16.70 MH/ CU.M.
Rebars Work 0.08 MH / KG
Finishing 0.80 MH/ SQM
3 ROOFING AND SIDING
Metal Roofing 0.09 mh/ sq. Ft
Non-Metal Roofing 0.10 MH/ CU. FT
Metal Sidings 0.117 MH/ SQ. FT
Non-Metal Sidings 0.133 MH/ SQ FT

4 ARCHITECTURAL SPECIALTIES

1 DOOR EXCLUDING FINISH HARDWARES


HC Plywood Flush Type 0.29 MH / SQ FT
SC Plywood Flush Type 0.286 MH / SQ FT
Steel Siding 0.86 MH / SQ FT
Steel Hinge 0.715 MH / SQ FT
Alum. Roll-up (Manually Operated) 0.715 MH / SQ FT
Cyclone Wire Sliding Door 0.715 MH / SQ FT

2 WINDOWS
Fixed Glass on Steel Frame 0.286 MH / SQ FT
Fixed G.I> Louver 0.429 MH / SQ FT
Fixed Asbestos Louver 0.429 MH / SQ FT
Metal Louver 0.286 MH / SQ FT

3 PARTITION (INC. FRAMEWORK)


1/2" thk Single Wall Plywood 0.23 MH / SQ FT
1/4" thk Double Wall Plywood 0.314 MH / SQ FT
Wooden Louver 0.314 MH / SQ FT
Cyclone Wire 6a # 10 Partition 0.0236 MH / SQ FT

4 FLOOR FINISH MH/ SQ FT


Plain Cement 1.33
Colored Cement 1.40
Pebble Washout 2.86
Granulithic 2.86
Marble Tile 2.86
Vinyl 1.67
Unglazed 4.00
Asphalt 1.67

5 CEILING INCLUDING FRAMING MH/ SQ FT


1/4 thk plywood 0.17
Acoustic Tile with Plywood Backing 0.29
Concealed Acoustic Tile Ceiling with Alum-T
- Runnes 0.29
3/16" Thk Asbestos 0.17

5 CEILING INCLUDING FRAMING MH/ SQ FT


Light Structural Steel Frame 168.00
Heavy Structural Steel Frame 64.00
Misc. Iron (Platforms - Walkways)
Stairs, stringers, handrails 112
Stair, treads, gratingd 20
Painting of Stl frame Crew 5M/ day
Concrete demolition Breaks - 2.5 cu.m./ day
MISCELLANEOUS LABOR OUTPUT

Excavation 1.35 cu.m./ mday


Backfill 3.87 cu.m./ mday
Disposal of Spoils 4.7
Formwork 2.7
Steel Works 10 kg. / mday
Concreting .91 cu.m./ mday
Finishing 11.8 cu.m./ md
Sct. Abchor Bolts 16.5 kg/ mday
Sct. Anchor Boxes 4.4 Units/ md
Demolition (Adobe Wall) 0.5 cu.m./ md
Excavation Crane & Clamshew w/o Lab and 2 operators 80.0 cu.m./ md
CHB Zocallo Wall 2.4 sqm/ md
Grave Fill 3.87 cum./md
Ground Floor Slab 1.00 cum./md
Wood Columns 70.00 BF/ MD
Tag Flooring 112.00 BF/ MD
Plywood Partition 80 SQ FT/ MD
Ceiling Framing 44 BF/ MD
Siding Framing 60BF/ MD
Stone Cut Siding 112 BF/ MD
Roof Framing 33BF/ MD
GI Roofing GA 26 105BF/ MD
GI Gutter (Cut and Shape) 50LF/ MD
GI Butter (install) 18LF/ MD
GI D.S. (Cut and Shape) 27 LF/ MD
GI D.S. (Install) 60 LF/ md
Vertified Tile Floor Finish 1.5 sqm/ md
Inst. Casing Plates 45LF / md
Inst. Steel Sliding Door 10 sq ft/ md
Place Metal Nosing 3 steps/ md

ROOFING AND WATER PROOFING


Inst. Asbestos Roofing 10 shts/ md
Inst. Alum or GI Roofing 10 shts/ md
Inst. GI Gutter # 24 16 lf/ md
Cooper Cladding Roof Deck 52 lf/ md
Install Membrane Water proofing 29 sqm/ md
Fabricate GI Gutters 2.3 shts/ md

TRUSSES
Truss Fabrication 46 bf/ md
Truss Erection 40 bf/ md
Posts 60 - 90 bf/ md
Girts 50- 75 bf/ md
Plates 90 - 120 bf/ md
Purlins 40 - 60 bf / md
Facia Boards 25 -35 bf/ md

CABINETS
Framing 30 - 60 bf / md
Boarding 40 - 80 bf / md
Plywood Sheating 75 - 150 sq ft / md
Cabinet and Doors 40 - 80 sq ft / md

DOORS AND WINDOWS


Inst. Wooden Windows 30 sq ft/ md
Inst. Sash Glass 75 sq ft/ md
Inst. Steel Window 17 sq ft/ md
Inst. Wood Panel Doors 22 sq ft/ md
Inst. Lock Set 5 sets/ md
Inst Wood Flush Doors 20 sq ft/ md
Inst. Flush Bolst 2 pairs/ md
Inst. Astragal 80 lf/ md
Vitrified the Wall Fin. 1.34 sq.m./ md
Painting 00-300 sq ft/ md
Floor Hardener 2 sq.m/ md
Copper Water Stop Cut & Shape 60 lf/ md
Copper Water Stop , Install 38 lf/ md
EXCAVATION

Soil Hand Excavation Manhour/ Cu.m.

Soft Clay Dry 2.5


Wet 3.51
Hard Medium Dry 4.9
Wet 8.5
Hard Adobe Dry 13.5
Wet 13.5

BACKFILL
Manhour/ cu.m.
Labor Operator Oil
Hand Place & Tamped by Hand 2.77
Loader & Tamped by Vibratory
Roller 0.4 0.02

GRAVEL FILL
Hand Place & Tamped by Vibratory
Roller 1.42 0.33 0.02

SELECTED FILL
Hand Place & Tamped by Roller 3.3 0.33 0.02
Loader & Tamped by Vibratory
Roller 0.4 0.02
Preparation of SOF 1.7 sq.m.

DEMOLITION
ITEM MANHOURS
Unit Laborer Airtool/ Operator

With Pneumatic Breaker sq.m. 0.16 0.46


by Hand with Sledge sq.m. 3.24

ELEVATED SLABS
With Pneumatic Breaker cu.m. 3.28 2.72
by Hand with Sledge cu.m. 16.24

CONCRETE WALLS
With Pneumatic Breaker cu.m. 1.03 2.06
by Hand with Sledge cu.m. 14.41

REMOVE CONCRETE CURBS


With Pneumatic Breaker L.m. 0.36
by Hand with Sledge L.m. 1.48
CUT CONCRETE OPENING
Pneumatic Chisels cu.m. 7.96
Hand Chisels 7 cu.m. 18.34

FORMWORKS
MANHOURS PER SQUARE METER
ITEMS MANHOURS
Carpenter Laborer Total
Continous Wall Type (CHB) 0.70 0.40 1.10
Foundation on Pile Caps 1.50 0.65 2.15
Grade Beam or FTB 0.75 0.40 1.15
Walls Grond to 8' High 1.10 0.72 1.82
Walls 8' to 16' High 1.21 0.78 1.99
Walls 16' to 20' High 1.35 0.90 2.25
Columns 1.22 0.80 2.02
Beams & Girders 1.90 1.22 3.12
Elevated Slabs (Word Shores) 1.15 1.16 2.31
Elevated Slabs (Adjusted Shores) 0.70 0.90 1.60

SCAFFOLDINGS

LENGTH MANHOURS PER SECTION


Erect Dismantle Total
1 or 2 section high:

1 to 2 section long 1.2 0.35 1.55


3 to 5 section long 0.75 0.5 1.25
6 section or more long 0.65 0.35 1

more than 2 section high

1 to 2 section long 1.4 1 2.4


3 to 5 section long 0.85 0.6 1.45
6 section or more long 0.75 0.4 1.15

CONCRETING
MANHOURS
Item Laborer Carpenter Optr

Continous Wall Type Footings


Job Mix 5.1 0.05
Chute 0.75 0.05
Buggies 0.98
Spread Type Footings
Job Mix 5.1 0.05
Chute 0.86 0.07
Buggies 1.14
Footing Tie Beam
Job Mix 5.1 0.05
Chute 0.9 0.07
Buggies 1.48
Foundation or Basement Walls
Job Mix 5.1 0.05
Chute 0.9 0.07
Buggies 1.48
Columns
By hand & Pulley 8.51
Porta-lift 6.35 0.08
Crane, Bucket & Buggies 2.02 0.16
Retaining Wall to 10' High
By hand & Pulley 12.71
Porta-lift 10.6 0.08
Tooled Joint Finish 3.67 1.22
Plain Cement Finish
(Louvers Blocks) 4 0.47
Glazed Tiles 6.38 2.13
Rubbed Concrete 4.27 0.11
Total
2.77

0.42

1.77

3.65

0.42
1.7

Total

0.62
3.24

6
16.24

3.09
14.41

0.36
1.48
7.96
18.34

URS
Oiler Total

0.05 5.2
0.8
0.98

0.05 5.2
0.93
1.14

0.05 5.2
0.97
1.48

0.05 5.2
0.97
1.48

8.51
0.08 6.51
0.16 2.34

12.71
0.08 10.76
4.89

4.47
8.51
4.38
CARPENTRY & MILLE WORKS

STRUCTURAL LUMBER

Item Manhour Per Thousand Foot Board Measure Manhours


Carpenter Helper Total

Sills 18.75 5.12 23.87


Bracing 23.44 6.06 29.50
Floor Joist 15.94 7.00 22.94
Roof Joist 17.00 5.44 22.44
Beams 9.40 7.00 16.40
Columns & Post 31.88 8.88 40.76
Girders 11.73 9.35 21.08
Ordinary Rafters 21.56 6.06 27.62
Bridging & Blocking 34.00 6.44 40.44
Trusses 44.69 8.56 53.25
Purlins 37.50 8.63 46.13
Nailers 17.00 5.44 22.44
30.00 8.05 38.05

LOADING DOCKS (PER 1000 FOOT BOARD MEASURE)


Framing 18.75 4.19 22.94
Roof Decking Lumber 13.12 6.06 19.18
Roof Decking Plywood (sqm) 0.13 0.01 0.14
Bumpers 45.00 22.94 67.94

SUB-FLOORING
T & G Laid Regular 15.00 4.66 19.66
T & G Diagonal 16.88 4.66 21.54
Plywood Sub-Flooring (sqm) 0.10 0.04 0.14
Plank Flooring 10.79 4.19 14.98

WALL COVERINGS (Manhour per Square Meter)


Item Carpenter Helper Total
Wall Papers 0.13 0.13
Gypsum Board 0.32 0.16 0.48
Asbestos Cement Bd. 0.6 0.16 0.76
Plywood Panelling 6 0.16 6.16
Fiberboard 0.4 0.16 0.56

INTERIOR TRIM

Item Carpenter Helper Total


Baseboard (lm) 0.2 0.05 0.25
Beam Casing (lm) 0.16 0.05 0.21
Mouldings (lm) 0.11 0.03 0.14
Knocked Down Wood Paneling (sqm) 0.78 0.22 1
Door Casing (lm) 0.16 0.01 0.17
Door Stops (opening) 0.94 0.04 0.98
Door Saddles (each) 0.25 0.03 0.28
Window Casings (lm) 0.16 0.01 0.17
Window Stools & Apron (lm) 0.05 0.01 0.06
Window Stops (lm) 0.14 0.01 0.15
Wood Handrail (lm) 0.66 0.05 0.71
Prefab Wood Stair (Plight) 0.4 0.05 0.45

WALLS AND CEILING (PER SQ.M.)

Item Carpenter Helper Total


Double Wall Partition 6.68 2.22 8.9
Plywood Ceiling 7.15 2.38 9.53
Accoustic Tile Out Runner 5.63 1.87 7.5
Accoustic Tile on Plywood Ceiling 1.37 1.37
Wire Mesh Pat on Wood Frame 4.67 1.56 6.23
Wire Mesh Partition 4.21 1.4 5.61

DOORS AND WINDOWS

Item Carpenter Helper Total


Steel Awning Window 7.94 2.65 10.59
Steel Casement Window 6.34 2.12 8.46
Aluminum Sliding Window 4.12 1.38 5.5
Jalousie Windows on Aluminum Frame 1.73 0.57 2.3
Hollow Metal Door Single Swing 12.61 4.79 17.4
Fixed Glass on Wood Frame 1.73 0.57 2.3
Hollow Metal Door Double Swing 12.61 4.79 17.4
Steel Sliding Doors 9.45 3.15 12.6
Aluminum Door Single Swing 6.3 2.1 8.4
Aluminum Sliding Doors 4.72 1.58 6.3
Wooden Panel Door 11.63 3.87 15.5
Wooden Flush Door 11.63 3.87 15.5
Wooden Sliding Door 8.72 2.91 11.63