Form CETI-TTR-MMXVIII

TRANSFORMER Revision
TEST REPORT Revision Date
Control No.

CLIENT DETAILS
Client Date
Address Sales Order No.

TRANSFORMER SPECIFICATIONS
Transformer ID Serial Number
KVA Rating Vector Group
Primary Voltage Phase
Secondary Voltage Frequency
Winding Materials Insulation Class
Insulating Fluid Cooling Class

INSULATION RESISTANCE TEST


Measured Resistance Polarization
Test Connection Test Voltage Test Result
1 MINUTE 10 MINUTES Index
PRI – SEC  Passed  Failed  N/A
PRI-GND  Passed  Failed  N/A
SEC-GND  Passed  Failed  N/A
WINDING RESISTANCE TEST
Primary Side
Test Point Test Current H1-H2 Test Current H2-H3 Test Current H1-H3 Test Result
TAP 1  Passed  Failed  N/A
TAP 2  Passed  Failed  N/A
TAP 3  Passed  Failed  N/A
TAP 4  Passed  Failed  N/A
TAP 5  Passed  Failed  N/A
Secondary Side
Test Point Test Current x1-x2 Test Current x2-x3 Test Current x1-x3 Test Result
-  Passed  Failed  N/A
Test Point Test Current x0-x1 Test Current x0-x2 Test Current x0-x3 Test Result
-  Passed  Failed  N/A
TRANSFORMER TURNS-RATIO TEST
Test Computed Percent Percent Percent
H1-H2 H2-H3 H1-H3 Test Result
Point Ratio Deviation Deviation Deviation
TAP 1  Passed  Failed  N/A
TAP 2  Passed  Failed  N/A
TAP 3  Passed  Failed  N/A
TAP 4  Passed  Failed  N/A
TAP 5  Passed  Failed  N/A

DIELECTRIC BREAKDOWN VOLTAGE TEST


TEST Trial 1 Trial 2 Trial 3 Trial 4 Trial 5 Test Result
 Passed  Failed  N/A

TEST SUMMARY REMARKS


 Passed
 Further Investigation Required
 Failed
The signatures of the below specimen certify that the above details are true and correct to the best of their knowledge.
CERTIFICATION
DATE COMPANY POSITION
Signed
Signed
Signed

Office Address: Unit 4-L Amber Place Bldg., No. 67 Bayani Rd, AFPOVAI Phase 4, Fort Bonifacio, Taguig City
Phone: (02)804–1725 / (02)697–6359
E-mail: info@coulombenergytechnik.com

You might also like