Professional Documents
Culture Documents
METHODS OF DELIVERING
MAJOR GAS PROJECTS
BY Mike Beehler, PE
Business “as usual” will not allow our industry to: DESIGN-BID-BUILD APPROACH
• Expand distribution into unserved markets during The Design-Bid-Build process is often referred to as the
a time of record low commodity prices. traditional approach or the multiple-contract approach
in which multiple construction contracts are bid and
• Enhance the safety of our transmission and
awarded as lump sum projects based on plans and
distribution systems to be in compliance with
specifications prepared by an engineer. The project
federal and state mandates.
owner hires the design engineer, purchases equipment
• Replace aged infrastructure (like cast iron directly, and hires one or more contractors to perform
pipe) that has served its useful purpose and the construction under separate contracts. The contracts
depreciable life and needs to be replaced to are structured to allow multiple specialty contractors to
improve system efficiency and safety. perform the specific trade-related work in an effort to
• Build out new gas transmission lines to support minimize subcontracting and reduce contractor markups.
newly developed gas-fired electric generation The engineer may help to pre-qualify contractors and
due to the Clean Power Plan (CPP) and the may make recommendations as to contractor selection.
elimination of once through coding at coastal
fossil plants. An illustration of a typical project organization for
a Design-Bid-Build project is shown in Figure 1.
This report provides the latest perspectives on the three
primary methods for delivering major gas projects: ADVANTAGES OF DESIGN-BID-BUILD APPROACH
Design-Bid-Build, Design-Build and EPCM/ 1. The owner can select an engineer that has its trust
Program Management. Each of these methods and confidence and is separate from the construction
is described and the potential advantages and process. The owner works directly with the engineer
disadvantages of using each method are identified. to implement the utility’s design philosophies and
These methods are then evaluated in the context standard practices into the design.
of the following project requirements:
2. The owner can have input as the design progresses
• Safety – The ability to see that all workers are and up to the time the plans and specifications are
protected from danger, risk or injury. issued for bid without incurring costly change orders.
• Performance – The ability to successfully It is not necessary for the owner to identify all its
complete a complex, high-profile project. requirements at the beginning of the project.
• Schedule – The ability to meet critical 3. Designs and bid evaluations can be performed to
construction, operational and financial dates. account for the life cycle costs of design decisions
instead of just the initial capital cost.
• Accountability – The ability to survive an internal
or external audit. 4. The contracts can be structured to minimize the
amount of subcontracting by prime contractors,
• Legal – The ability to enter into contracts that
minimizing contractor markups. Equipment is
protect the broad interests of an asset owner.
purchased directly from the supplier, eliminating
• Quality – The ability to deliver quality design, contractor markups. Since the construction contracts
materials and workmanship. are smaller and more specialized a larger number of
• Cost Control – The ability to control project costs qualified contractors may be available to bid the work,
and possible change orders. resulting in lower project costs.
• Public Relations – The ability to handle 5. The owner controls the contingency pool for
community and stakeholder interaction during all the project.
phases of the project. 6. The owner has direct control over the selection
of material vendors and contractors for the project.
© 2015 PAGE 2 OF 15
WHITE PAPER / METHODS OF DELIVERING MAJOR GAS PROJECTS
OWNER
ENGINEERING SPECIALTY CONSULTANTS
Design, Geotech, Surveying Environmental, Land, Public Relations, Legal
Construction Management, Field Inspection
CONSTRUCTION PROCUREMENT
1. The owner is responsible for controlling the 5. Owner manpower and costs to coordinate and manage
interfaces and coordination among all the equipment the interfaces among the construction contracts
and materials suppliers and the various construction are increased over approaches that have a single
contractors. This may be overwhelming and result in contractor to handle such interfaces.
delayed schedules or in increased costs. 6. The owner is exposed to multiple contractor claims for
2. Total project costs cannot be confirmed until the final impacted productivity, late delivery of owner-furnished
construction contract is completed. materials, weather delays and labor disputes.
3. Delays in completion of one contract may impact 7. The owner is responsible for errors and omissions
other contracts, resulting in potential additional project in design.
delays and/or costs to the owner. 8. The owner has ultimate responsibility for site safety.
© 2015 PAGE 3 OF 15
WHITE PAPER / METHODS OF DELIVERING MAJOR GAS PROJECTS
OWNER
SPECIALTY CONSULTANTS
Environmental, Land, Public Relations, Legal
DESIGN-BUILD
TEAM
© 2015 PAGE 4 OF 15
WHITE PAPER / METHODS OF DELIVERING MAJOR GAS PROJECTS
ADVANTAGES OF DESIGN-BUILD APPROACH Some owners may take bids on specialized equipment
The project cost and schedule can be defined very early and then assign those contracts to the Design-Build
in the project. If the scope is well defined and the owner contractor. This allows the owner to select this primary
identifies its requirements in the Design-Build contract, equipment and still obtain overall system guarantees.
there should be few, if any, change orders. The owner can Generally the owner is not involved in the
obtain a high degree of confidence on cost, schedule, detailed design decisions and has very limited
and performance from a single responsible party. Owners time, if any, to review design drawings.
with limited staff to dedicate to the project can rely on Scope and schedule need to be clearly defined very
the Design-Build contractor to coordinate each phase early in the project. Changes in scope or schedule
of the project. The owner can use its limited staff to after award will most likely cause the Design-Build
monitor the contractor to confirm that the project meets contractor to revise the price of the project.
the requirements of the contract. The project schedule The owner will receive the contractor’s standard drawing
can be condensed with close coordination of the design, formats unless otherwise specified in the bid documents.
procurement and construction activities by the Design- And, unless specified, the owner may also not receive
Build contractor allowing the owner to better define detailed documentation, calculations, or manuals,
the project prior to issuing EPC bid documents. Design- since the engineer typically only produces those
Build contractors may have innovative approaches that documents necessary for construction of the project.
are less costly than the owner’s standard practices and
may meet the owner’s requirements at a reduced cost. EPCM/PROGRAM MANAGEMENT APPROACH
All contractual issues between the Design-Build contractor EPCM (engineer, procure, construction management)
and the subcontractors are the direct responsibility of the and Program Management are very similar in concept
Design-Build contractor. Lower material and equipment and have many of the same pros and cons. The primary
costs may be passed though to the owner during the difference between the two delivery systems is related to
bidding process due to the volume buying power of the the scale of the project or program. EPCM would more
Design-Build contractor. likely be used for smaller-scale efforts of shorter duration.
© 2015 PAGE 5 OF 15
WHITE PAPER / METHODS OF DELIVERING MAJOR GAS PROJECTS
The program manager provides detailed managerial The master plan provides the framework for
support and added technical value to the owner the program manager to assist the owner
and is normally involved in the earliest stages of a in many other ways, including:
project. A program manager offers current planning
methodologies, public involvement and testimony PRELIMINARY PHASE
capabilities, design experience, knowledge of • Define project scope
construction methods and pricing, an understanding of
• Develop estimated contract costs
competitive market conditions, and effective scheduling
• Develop preliminary schedules
and cost control systems. Program management is
successful when the project’s planning, permitting, • Identify potential resources
design and construction phases are effectively integrated • Review RFP provisions for uniformity, clarity
into a single process. The program manager can deliver and completeness
a project(s) with consistently successful results in • Develop evaluation criteria for various resources
several areas of measurement over the course of several • Interview engineers, vendors and contractors
years by developing an overall master plan for the
• Evaluate proposals
project(s). The master plan might include such tasks as:
• Make recommendations for selection
• Develop the program goals, objectives,
and priorities. DESIGN PHASE
• Provide for the integration of all program • Confirm program scope and concept
components and functions by responsibility, • Develop design schedules
including administrative, regulatory, financial,
• Conduct and coordinate design review
engineering, construction, commissioning,
• Conduct value engineering review
documentation, procurement and operations.
• Monitor design progress
• Provide an organizational chart.
• Conduct constructability reviews
• Provide a directory of team members with
• Coordinate agency approvals
locations, telephone and fax numbers.
• Conduct budget compliance reviews
• Describe the relationships between the program
• Interface with existing operations
management staff and the owner as well as future
consultants, contractors, construction managers,
CONSTRUCTION PHASE
facilities users, government agencies, intervenors
• Contractor mobilization
and other groups.
• Site logistics plan
• Describe the key program management tasks
• Construction safety program
and establish the procedural basis for executing
program management functions. • On-site contractor coordination
• Schedule conformance reviews
• Establish state-of-the-art management controls
to effectively manage time, quality, costs and • Project payment applications
resources to achieve a high level of performance. • Change orders
© 2015 PAGE 6 OF 15
WHITE PAPER / METHODS OF DELIVERING MAJOR GAS PROJECTS
Program Management still requires that designs are completed, materials are procured and projects are built.
The program manager may recommend either the Design-Bid-Build approach or the Design-Build approach for each
individual project within the construction program. An illustration of a typical project organization for the Program
Management approach is shown in Figure 3.
OWNER
SPECIALTY CONSULTANTS
PROGRAM MANAGER Environmental, Land, Public Relations, Legal
ADVANTAGES OF PROGRAM applying specific resources when and where they are
MANAGEMENT APPROACH needed to maintain project objectives.
1. This approach provides a comprehensive, continuous 4. The program manager provides current knowledge of
level of service for the owner with staff or a third design and construction resources, material vendors
party overseeing the entire process from project and best practices. Program managers typically
planning to project closeout. are involved in the largest, most complex projects
in the country and the world. They bring a unique
2. The owner has more control of design and
perspective and understanding to the owner.
construction processes throughout the project. The
program manager provides timely cost and schedule 5. Bid packages for engineering, materials and
information to the owner, allowing informed decisions contracting can be staged based on project needs
on cash flow and providing accurate information to such as outage windows, financial objectives, seasonal
internal and external stakeholders. weather, permitting requirements and environmental
restrictions.
3. The owner can avoid hiring additional staff for specific
project-related functions. The program manager can 6. The program manager can be provided with penalties
easily increase or decrease resources on the program or incentives to maintain schedule and budget.
© 2015 PAGE 7 OF 15
WHITE PAPER / METHODS OF DELIVERING MAJOR GAS PROJECTS
© 2015 PAGE 8 OF 15
WHITE PAPER / METHODS OF DELIVERING MAJOR GAS PROJECTS
TRIR DART
5 2.5 5
4 2.0 4
3 1.5 3
2 1.0 2
1 0.5 1
0 0.0 0
2014 2008 2009 2010 2011 2012 2013 2014 2008 2009 2010 2011 2012 2013 2014 2008
Burns & McDonnell Burns & McDonnell Burn
istics Construction Industry Institute Bureau of Labor Statistics Construction Industry Institute Bureau of Labor Statistics Cons
R TRIRTABLE 1:DART
Total Recordable Incident Rate (TRIR). TABLE 2: Days Away, Restrictions and Transfers (DART). EMR TRIR DA
0.15 0.01 0.37 0.15 0.
© 2015 PAGE 9 OF 15
WHITE PAPER / METHODS OF DELIVERING MAJOR GAS PROJECTS
© 2015 PAGE 10 OF 15
WHITE PAPER / METHODS OF DELIVERING MAJOR GAS PROJECTS
Financial and procedural accountability for a project strong language that indicates to the bidder for
realistically lies with the party having ultimate control equipment or labor the importance and complexity of
over the design, procurement and construction. the overall project. Well-crafted RFP’s lead to strong
Projects developed under the Design-Bid-Build and contracts with competent, qualified suppliers that
Program Management approaches are more easily offer a fair and balanced approach to managing the
audited than a Design-Bid project since all contracts risk, milestones and deliverables of the project.
for engineering services, materials and equipment and
construction labor are held by the owner. The Design- Good RFPs and strong contracts are ultimately the
Bid-Build and Program Management approaches spread responsibility of the owner and its legal counsel. However,
out project accountability over several contracts with the owner can obtain valuable input on the perspective
several personnel from either the owner or the program of vendors and contractors regarding contract terms
manager, acting as the owner’s agent, administering the and conditions from an engineering consultant that
effort to document the project and maintain records. prepares plans and specifications or a program
Therefore, the owner has more direct access to the manager that works in the design and/or construction
significant documentation of the project, i.e., drawings, industry. The Design-Build approach does not provide
specifications, cost estimates, contracts, expenditures, the owner with this important third party perspective.
etc., as well as the documentation of design and Therefore, we evaluate the legal requirement as follows:
construction decisions made throughout the project.
Project Requirement — Legal
A Design-Build project provides the owner with little Design-Bid-Build High
direct control over how the project is completed.
Design-Build Medium
The Design-Build contract is typically the only
Program Management High
contract held for the project and the Design-Build
contractor represents the single point of responsibility
with which all accountability for the project lies.
QUALITY
Quality is defined as the ability to deliver accurate
Project accountability will be only as good as the
design, materials that meet specifications, and good
records maintained by that single contractor and
workmanship. Megaprojects are uniquely challenging.
the owner may have limited access to those records
Several parts of the project(s) may be first-time
during the course of the project. Reviewing project
installations for an asset owner, large installations
documentation and record keeping after completion of
of certain technologies and/or materials or have
the project does not allow the owner to require possible
heavy impacts on customers and communities. In
adjustments of the project as needed. Therefore, we
addition, intervenors will be keenly aware of the
evaluate the accountability requirement as follows:
project(s) and will be watching the daily work effort.
There will be little patience for lifestyle-impacting
Project Requirement — Accountability
delays due to simple mistakes such as missed utility
Design-Bid-Build High
locations or catastrophic mistakes that our industry
Design-Build Low has recently experienced. The assurance of quality
Program Management High is fundamental to the success of the project.
© 2015 PAGE 11 OF 15
WHITE PAPER / METHODS OF DELIVERING MAJOR GAS PROJECTS
dependent on its ability to review vendor drawings and Project Requirement — Quality
its ability and willingness to travel to manufacturing
Design-Bid-Build High
facilities to view and inspect fabrication of major
Design-Build Medium
materials and equipment especially those items that
impact critical project milestones. Finally, the owner Program Management High
must commit resources to inspect the installation of
the project to make sure that the contractor follows the COST CONTROL
plans and meets the specifications of the contract. Cost Control is defined as the ability to control
project costs and possible change orders.
The Design-Bid-Build approach provides an engineer that Project cost risk is directly related to:
works directly for the owner. The owner may contract • The accuracy of the scope used to prepare
with the engineer to implement quality control measures the project budget
such as drawing review schedules, visiting specific
• Variations in material quantities required to
manufacturers, use of standards and philosophies, and
construct the project such as pipe, cut/fill
application of drawing standards. The scope of the
quantities, number of underground conflicts, etc.
engineer’s work can be written to prepare equipment
specifications and to make plant visits at regular • The accuracy of equipment cost estimates
intervals. Further, the engineer can provide construction • Expected labor cost and productivity
management and field inspection as part of the scope of
• Equipment and materials escalation due
work. A scope of work that includes design, plant visits
to market conditions, inflation, currency
and construction management will protect the interests
valuations, political interests, weather, shipping
of the owner and generally delivers reasonable quality.
challenges, etc.
© 2015 PAGE 12 OF 15
WHITE PAPER / METHODS OF DELIVERING MAJOR GAS PROJECTS
costs, 2) better management and tracking tools and Communication with stakeholders — such as the press,
3) a specific focus on cost control. neighborhood associations, community groups and
elected government officials — must be provided by
The Design-Build contractor receives a fee for accepting the project team for each segment of the project.
risk in the project. Design-Build contracting shifts risk Responsibility for this type of general communication
away from the owner. The contractor is responsible for typically lies with the owner’s public relations or
the scope of the project within the limits defined in the communications department or a special media
contract. Risk factors for the contractor include material consultant. A special media consultant could be placed
quantities, equipment cost, labor cost and productivity, under the responsibility of a program manager or be
materials escalation, etc. The cost risks that remain with one of the requirements for selecting the program
the owner are primarily due to changes in scope and manager. Engineers, vendors and contractors working
unexpected events (force majeure). However, the Design- in the context of the Design-Build approach may
Build contractor’s ability to be innovative in design and not be prepared for communication with the general
construction may offset some of this added cost. public, especially on large or controversial projects.
The definition of cost, restated, is the ability to Communication with the public on the project site
control project costs and possible change orders. is important. In some cases, the Design-Bid-Build or
The Design-Build method may be more costly to Design-Build teams may be able to provide adequate
the owner because of the risk burden placed on the communication with homeowners, business owners,
contractor but, if the scope is well-defined, the price passersby, technical staff from local government or
and potential change orders are controlled. Therefore, permitting agencies, or law enforcement. However,
we evaluate the cost control requirement as follows: a well–qualified construction manager and team of
inspectors watching the interests of the owner and
Project Requirement — Cost Control prepared to handle specific questions can be more
Design-Bid-Build Low effective. Working with utility or internal staff public
relations personnel, they can be available to notify
Design-Build High
property owners of advancing construction, solve
Program Management Medium
immediate ingress/egress issues, coordinate service
outages, provide right-of-way restoration mediation,
PUBLIC RELATIONS etc. The construction manager and inspectors can
The definition of public relations is the ability to
be owner’s staff, can be a contractor under the
handle community interaction during construction.
oversight of the program manager, or can be part of
Truth and consistency are the fundamentals of public
the program manager’s trained staff. Therefore, we
relations whether in the office or on the project
evaluate the public relations requirement as follows:
site. Public relations personnel should be involved
in the project as early as possible. Staff needs to
Project Requirement — Public Relations
know the concerns of stakeholders and know the
Design-Bid-Build High
mitigation proposed to alleviate those concerns.
Early involvement of some members of the utility Design-Build Medium
or program management team provides continuity Program Management High
of message to the public through project completion.
© 2015 PAGE 13 OF 15
WHITE PAPER / METHODS OF DELIVERING MAJOR GAS PROJECTS
SUMMARY OF RESULTS
A sample analysis of project requirements is summarized in Table 3 and 4. The scoring is based on three points
for a “High” rating, two points for a “Medium” rating, and one point for a “Low” rating. The scores for two project
requirements, Accountability and Legal, that might be considered most important to other utilities addressing similar
needs were doubled in the tabulation shown in Table 3. An alternative was evaluated emphasizing Cost Control and
is shown in Table 4. Safety was double weighted in all cases.
© 2015 PAGE 14 OF 15
WHITE PAPER / METHODS OF DELIVERING MAJOR GAS PROJECTS
The Design-Bid-Build and Design-Build approaches MIKE BEEHLER, PE, is a vice president at
clearly have distinct advantages and disadvantages. Burns & McDonnell. After working as a transmission
The Summary of Results seems to favor the use of engineer and project manager for two IOUs, Mike led
Design-Bid-Build over Design-Build. Interestingly, initial development of critical infrastructure protection
a change in the sample weighting to de-emphasize for Burns & McDonnell. He initiated the application of
Accountability and Legal and emphasize Cost sustainable principles into T&D design preceding the
Control keeps Program Management as the preferred development the Envision program and PEER. Mike has
method of delivering major projects and rates written and presented extensively on the subjects of
Design-Build over Design-Bid-Build. Changes in reliability-centered maintenance, program management
“weighting” various project requirements important and the smart grid. More recently, Mike has written,
to your organization may help you reach your own presented and consulted on industry megatrends,
conclusions. However, a well-qualified program EPC project delivery, “the value of the grid” and the
manager should complement the advantages and growth of the gas industry. Mike earned a Bachelor
strengthen areas of weakness of both methods. of Science in civil engineering from the University of
Arizona and a Master of Business Administration from
the University of Phoenix. He is a registered professional
engineer in eight states, a member of IEEE, and a
Fellow in the American Society of Civil Engineers.
9969-MET-0316
© 2015 PAGE 15 OF 15