PRESENTED BY
GOLDEN FUTURE MYANMAR POWER
April 4th 2019
GFMP
TABLE OF CONTENT
1. Introduction
2. Scope of Work
3. Method of Statement for Excavation, Pipe Laying and Back Filling
4. Method of Statement for Manhole Casting
5. Method of Statement for Lamp post Erection
6. Method of Statement for Cabling
7. Method of Statement for Transformer Installation
8. Method of Statement for MV/LV Panel Installation
9. Method of Statement for Termination of MV Cable
10.Method of Statement for Lighting Fixture Installation
11.Method of Statement for Fabrication of Support
GFMP
1. INTRODUCTION
This Method of Statement is issued as a confidential document and at all times
remains the property of GFMP. This MOS is a live document and will be
updated from time to time to incorporate changing site circumstance and
client’s recommendations. Copies of this plan will be provided to
subcontractors and other parties working under GFMP.
2. SCOPE OF WORK
Supply, Delivery and Installation of Electrical System.
Producer
Provide copies of the shop drawings, copy of the permit to
work & necessary instructions. Briefly introduce the
workers on the safety aspects & safe work procedures.
Barricade the area of working.
Mark out area to be excavated with marker paint
Bring excavator onto site following safety procedures
listed above
Ensure trained banksman is available to watch excavation
work
Dig out ground as per contract drawings to required size
and depth
All excavations must be left safe at the end of each day
The bottom of trench will be compacted prior to
installation of sand bedding for the pipe
The pipe will be laydown as indicated on the approved
shop drawings and according to manufacturer’s writing
instruction
After pipe laying, back fill will start step by step.
Producer
Provide copies of the shop drawings, copy of the permit to
work & necessary instructions. Briefly introduce the
GFMP
Producer
Provide copies of the shop drawings, copy of the permit to
work & necessary instructions. Briefly introduce the
workers on the safety aspects & safe work procedures.
Barricade the area of working.
Mark out area to be excavated with marker paint
After excavation put precast base at excavated area and
back filling.
GFMP