Professional Documents
Culture Documents
The attached specification, revised as indicated below, is issued herewith. If this is a later revision than
the specification now in your possession, please destroy the previous issue.
Rev. Rev.
Revised By Page(s) Summary of Revisions
No. Date
0 L.W. Hunt / 05-Sep-02 All Rewritten and renumbered.
B.A. Schalke / This specification supercedes Pipeline
H.M. Yamauchi Specification SP-2002.
1 L.W. Hunt / 30-Apr-03 All To suit Operations and Maintenance
B.A. Schalke / Requirements.
H.M. Yamauchi
2 H.M. Yamauchi 03-Jun-04 Page 5 CSA Z662 Latest Edition
PREPARED BY:
_________________________________
H.M. Yamauchi, AScT.
Senior Pipeline & Integrity Engineering Specialist
Pipeline Engineering, Canada West
APPROVED BY:
_________________________________
L.W. Hunt, P.Eng.
Team Leader, System Integrity
Duke Energy Gas Transmission, Canada
Date: _________________________________
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 2 OF 16
TABLE OF CONTENTS
1.0 SCOPE................................................................................................................... 5
2.0 DEFINITIONS......................................................................................................... 5
3.0 REFERENCES....................................................................................................... 5
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 3 OF 16
8.6 Reporting........................................................................................................................................................14
11.0 COATING.......................................................................................................... 14
12.8 Coupon............................................................................................................................................................15
TABLE
Table 1 – Station and Pipeline: High Pressure Gas Service................................................................................T-1
FIGURES
Figure 1 – Half Coupling.........................................................................................................................................F-1
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 4 OF 16
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 5 OF 16
1.0 SCOPE
This Specification:
• Outlines the criteria to be used in the selection of welded branch connections, and
provides installation and weld practices for connections, and sleeves onto gas pipeline
system.
• Applies to all welded connections, such as branches, sleeves, and pressurized spit tees,
installed on both in-service and de-pressured pipeline systems. The connections shall
satisfy the requirements of CSA Z662.
• Outlines a general procedure for hot tap drilling operation.
2.0 DEFINITIONS
• CIF - Contoured Insert Fitting; a branch connection fitting designed with integral
reinforcement and installed by butt welding to the header.
• De-pressured Pipeline - Pipeline blown down to atmospheric pressure.
• Engineering refers to DEGT Engineers, System Integrity or Technical Services
engineering personnel.
• Full Encirclement Sleeve, or Saddle and Sleeve. A full encirclement type of
reinforcement shown as "Sleeve Type" and “Saddle and Sleeve Type” in CSA Z662.
• Header - The carrier pipe, which may or may not have pressurized gas, to which a
branch connection is attached.
• In-Service Pipeline - Pipeline under pressure in which the gas may or may not be flowing
during welding.
• MOP - Maximum Operating Pressure to which a pipeline system has been qualified.
• NPS - Nominal Pipe Size.
• PQR – Procedure Qualification Record.
• Pressurized Split Tee – A branch connection split full encirclement sleeve welded onto
header forming a pressure vessel.
• Repair Sleeve – Split full encirclement repair sleeve, applied over an imperfection (loss of
wall thickness), on the header forming a pressure vessel, when ends are welded to
header.
• Stub - Pipe section, used for a branch connection.
• Welded Branch Connection - The direct connection of stub and/or fitting to the header.
• Weldolet, Sockolet, Thredolet and Elbolet - Trade names for integrally reinforced
welded-on type branch connection fittings.
• WPS – Weld Procedure Specification.
3.0 REFERENCES
• Canadian Standard Association Z662 Oil and Gas Pipeline Systems, latest edition
• CGSB Standard CAN/CGSB-48-9712, latest edition
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 6 OF 16
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 7 OF 16
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 8 OF 16
• Carbon equivalent. Where such is not available through a material test report, filings
(approximately 10 grams) shall be obtained from the header and sent to metallurgical lab
for chemical analysis. Other method, as approved by Engineering, may be employed to
confirm chemistry of header, and
• Product and its flow rate.
Engineering will input above applicable information into a computer program to determine,
and will advise, whether or not the welding parameters of applicable welding procedures is
suitable for the site specific welding location.
5.3 HEADER SUPPORT
The header shall be adequately supported, where required, to prevent any negative effects
caused by addition of branch and/or sleeve connections.
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 9 OF 16
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 10 OF 16
7.2.8 Weld size indicated on Figures 1, 2, 4, 5B, 6B, and 7 are minimal and shall be confirmed by
engineering for each case.
7.3 INSTALLATION AND WELDING REQUIREMENTS
7.3.1 Half Coupling (see Figure 1) and Weldolets (see Figure 2)
• Clean and preheat.
• Weld fitting to header using applicable welding procedure.
7.3.2 Stub with Reinforcing Pad (see Figure 4)
• Cut and fit branch and pad to the required dimensions. Ensure existance of drilled vent
hole in pad.
• Clean and preheat.
• Weld branch to header (weld #1) using applicable welding procedure. Inspect weld #1,
by magnetic particle clause 8.3 before placement of pad.
• Place pad over and centered on the branch. If necessary, grind longitudinal weld crown
flush with the outside of the header so that the pad fits solidly on the header. Grinding
shall not extend into the parent metal of the header. Adequately tack weld then complete
weld #2.
• Complete welds #3 and #4.
• Contour welds by grinding as required.
• After inspection, plug vent hole in pad using line coating material (do not plug hole with
weld).
7.3.3 Stub with Full Encirclement Sleeve and Saddle (see Figures 5A, 5B and 5C)
• Cut and fit branch. Prepare encirclement sleeve according to details given in Figure 5C.
The separation between the two halves shall be 4 mm + 2 mm.
• Clean and preheat.
• Line-up, preheat and tack branch. Weld branch (see Figure 5B) to header (weld #1)
using applicable welding procedure. Inspect weld #1, magnetic particle clause 8.3 before
placement of sleeve.
• Place half of sleeve with the hole over and centered on the branch. If necessary, grind
longitudinal weld crown flush with the outside of the header. Grinding shall not extend
into the parent metal of the header. Install the second half of the sleeve. If pipeline
pressure during sleeve installation is greater than 50% MOP, heat both sleeve halves to
near 65ºC to 85ºC. Maintain this temperature and clamp sleeves tightly using a
cable/chain and load binding tool or a yoke type clamp and tack weld straps to sleeve.
Using two welders, where available, working simultaneously, opposite each other,
complete the welds on each joining strap (weld #2) with welding progressing outwards
from the center of the seam (see Figure 5A). No weld shall be made between the sleeve
and the header.
• With two welders, where available, working again simultaneously, complete weld #3
between the split sleeve and the branch using applicable weld procedure with a back
stepping sequence as shown on Figure 5B. Contour and inspect weld #3 by magnetic
particle clause 8.3, before installing the saddle.
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 11 OF 16
• Place saddle over branch and complete weld #4 then weld #5 (see Figure 5B), using
applicable weld procedure.
• Contour welds as required.
• Inspect welds, by magnetic particle clause 8.3.
• After inspection, plug vent hole in pad using line coating material (do not plug hole with
weld).
7.3.4 Stub with Full Encirclement Saddle (see Figures 6A and 6B)
• Cut and fit branch according to details given in Figure 6B. The separation between two
halves shall be 4 mm + 2 mm.
• Clean and preheat.
• Line-up and tack branch. Weld branch to header (weld #1) using applicable welding
procedure. Contour and inspect weld #1, by magnetic particle clause 8.3 before inserting
the saddle.
• Place half of encirclement saddle with the hole over and centered on the branch. If
necessary, grind longitudinal weld down flush with the outside of the header. Grinding
shall not continue into the parent metal. Install the second half of the saddle. If pipeline
pressure during saddle installation is greater than 50% MOP, heat both saddle halves to
near 65°C - 85°C. Maintain this temperature and clamp sleeves tightly using a
cable/chain and load binding tool or a yoke type clamp and tack weld straps to sleeve.
Using two welders (where available) working simultaneously, opposite each other,
complete the second weld on each joining strap (welds #2 and #2A), as applicable, with
welding progressing outwards from the center of the seam. No weld shall be made
between the sleeve and the header.
• With two welders (where available) working again simultaneously, complete weld #3,
Figure 6B between the saddle and the branch using applicable weld procedure.
• Inspect weld by magnetic particle clause 8.3.
7.3.5 Stub with Reinforcing Saddle (see Figure 7)
• Cut and fit branch to the required dimensions. Drill vent hole 3.2 mm in saddle if there is
no hole.
• Clean and preheat.
• Weld branch to header (weld #1) using applicable welding procedure. Contour and
inspect weld #1, by magnetic particle clause 8.3 before inserting the saddle.
• Place saddle over and centered on the branch. If necessary, grind longitudinal weld
crown flush with outside of the header so that the saddle fits solidly on the header.
Grinding shall not extend into the parent metal. With two welders, where available,
working simultaneously, complete weld #2 using applicable weld procedure.
• With two welders, where available, complete weld #3 using applicable weld procedure.
• Inspect welds by magnetic particle clause 8.3.
• After inspection, plug vent hole in saddle using line coating material (do not plug hole with
weld).
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 12 OF 16
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 13 OF 16
• After the long seams have cooled to approximately 75ºC, and any imperfection at ends of
long seam ground out to solid metal, one end of sleeve together with header shall be
preheated and welded, by two welders working diametrically opposite to each other, in
accordance to applicable qualified welding procedure.
• A buttering technique, where specified in WPS, shall be used to reinforce the pipe,
minimize the depth of penetration of the HAZ hardness and reduce the risk of under bead
cracking. Additional reinforcement shall be applied over the buttering passes where the
gap between the fitting and the pipe exceeds 1.5 mm.
• The buttering layers shall be deposited with 1/8” diameter electrode. The first bead shall
be depositied as close as possible to the fitting without impinging or making any
attachment to it, see Figure 8B. The fillet leg length and gap between the pipe and fitting
shall determine the number of buttering runs required. Starts and stops shall be
staggered by not less then 25 mm.
• Weld bead 2 and 3, or its equivalent, shall be ground down to approximately 1.5 to
2.0 mm above the pipe surface.
• Weld bead 6, or its equivalent, with 1/8” electrode, shall be deposited as close as
possible to the extremity of weld bead 3, or its equivalent, without impinging on to the
pipe wall.
• Only after the first sleeve end weld has cooled to approximately 75ºC, the opposite end
of sleeve shall be preheated and welded as stated above. The two ends shall not be
welded simultaneously.
• The longitudinal weld and sleeve fillet weld to header shall be inspected by ultrasonic
clause 8.4 and by magnetic particle clause 8.3.
• After successful visual and non-destructive testing of the welds and hot tap equipment
installation on the welded fitting, the installation shall be pressure tested, with either
nitrogen or air at pressure not exceeding 90% of the header internal pressure. Soap
solution or an equivalent leak indicator equal shall be used on all welds.
• Tapping may commence after successful test.
7.3.8 Sleeve
The sleeve designed to specific requirements, shall be installed as stated in above
Clause 7.3.7 with the following additions and exceptions:
a) Addition
i) Engineering shall be advised of the following:
- Description of pipeline to which sleeve is to be applied and
- Description of sleeve to be applied to determine the tensile force to be applied to
the sleeve prior to welding the long seam.
ii) Clamping force shall be applied to sleeve as advised by Engineering.
iii) Epoxy filler shall be applied as determined by Engineering.
b) Exceptions
i) Sleeve end shall be welded on the header as determined by Engineering.
ii) Tapping (drilling), and pressure testing for sleeve application is not a requirement,
unless otherwise advised by Engineering.
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 14 OF 16
8.0 INSPECTION
8.1 QUALIFICATION
All nondestructive testing inspectors, of welders, shall be qualified in accordance with the
requirements of CGSB Standard CAN/CGSB-48.9712.
8.2 VISUAL INSPECTION
Visual examination shall be carried out prior to, during and after completion of all welding. All
welds shall meet the requirements of Z662 and this Specification.
8.3 MAGNETIC PARTICLE INSPECTION
All completed fillet and combination groove/fillet welds shall be examined by wet fluorescent
Magnetic Particle Inspection (“MPI”) to ensure no surface cracks exist. MPI shall be carried
out in accordance with the requirements of MPI-1 Rev. 0.
8.4 ULTRASONIC INSPECTION
All fillet welds joining header to sleeve or to reinforcing pad shall be examined by Ultrasonic,
in accordance with UT-1 Rev. 0.
8.5 RADIOGRAPHIC INSPECTION
All butt welds shall be examined by radiographic technique in accordance to the requirements
of RT-1 Rev. 0.
8.6 REPORTING
Results of visual, magnetic particle ultrasonic, and radiographic inspections shall be
recorded.
10.0 REPAIRS
Weld defects, including cracks less than 25 mm in length, may be repaired. Crack location
shall be established. Complete removal of the crack shall be confirmed by magnetic particle
inspection, as per Clause 8.3. Cracks 25 mm and greater in length shall be reviewed by
engineering prior to repair.
Before weld repairs are made, defects shall be entirely removed to sound metal.
Preheat temperature of at least 150°C shall be used when effecting repairs. Preheating shall
extend to a distance of at least 150 mm from any point of the area to be repaired. Care shall
be taken to prevent overheating, and no part shall be heated to a temperature in excess of
240°C.
All repair welds shall be made using a low hydrogen process. Back-weld, other than for CIF,
is not permitted.
11.0 COATING
The complete assembly shall be cleaned and coated in accordance with the requirements of
WEI Specification No. SP-51-20-15 or engineering approved specification.
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 15 OF 16
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M PAGE 16 OF 16
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M
TABLE
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M TABLE - PAGE 1 OF 1
1 1-1/2 2 3 4 6 8 10 12 16 18 20 24 30 36 42
T RT RT L/RT L L L L L L L L L L L L 160* 1
T RT RT W W W W W W W W W W W 80* 2
T RTS RTS RTS RTS c/C c/C c/C c/C 10 BRANCH SIZE (NPS)
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M
FIGURES
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M FIGURES - PAGE 1 OF 13
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M FIGURES - PAGE 2 OF 13
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M FIGURES - PAGE 3 OF 13
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M FIGURES - PAGE 4 OF 13
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M FIGURES - PAGE 5 OF 13
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M FIGURES - PAGE 6 OF 13
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M FIGURES - PAGE 7 OF 13
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M FIGURES - PAGE 8 OF 13
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M FIGURES - PAGE 9 OF 13
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M FIGURES - PAGE 10 OF 13
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M FIGURES - PAGE 11 OF 13
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M FIGURES - PAGE 12 OF 13
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc
Specification
BRANCH CONNECTIONS AND WELDING ON IN-SERVICE PIPELINES REVISION 2 – JUNE 3, 2004
Operations & Maintenance - 2003
SP-51-32 – O&M FIGURES - PAGE 13 OF 13
w:\admin\specifications\current\pipeline\sp-51-32-project-specific\51-32rv2-ps-o&m.doc