Project manager
CONTRACTOR:
DESIGNED BY DATE
CHECKED BY DATE
TITLE:
Pasare Ghe. October 2018
Reliability Run Test Procedure
APPROVED BY DATE
This document is restricted. Neither he whole nor any part of this document may be disclosed to any third party without the
prior written consent of BLACK SEA POWER GENERATING FZCO, in which the copyright of this document is vested. All
copyrights reserved. Neither the whole nor any part of this document may be reproduced, stored in any retrieval system or
transmitted in any form or by any means (electronic, mechanical, reprographic, recording or otherwise) without the prior
consent of the copyright owner
Page 1 of 10
Contents
1 PURPOSE .......................................................................................................................... 3
2 DEFINITIONS ..................................................................... Error! Bookmark not defined.
3 TEST TOOLS...................................................................................................................... 3
4 PRE-CHECK ITEMS ........................................................... Error! Bookmark not defined.
5 TEST PROCEDURE ........................................................................................................... 5
Page 2 of 10
1. PURPOSE
1.1. The purpose of Reliability Run (RR) is to demonstrate and prove the
continuous reliable operation.
2. RR TEST TOOLS
2.2 The reliability run test will reveal the actual values reached by the plant
parameters in continuous operation under normal conditions by means
of instrumentation from the automation and control system with which
the technological plant is actually equipped. Mainly the performance
values will be measured recorded, processed from value indicated at
dedicated instruments already installed in the System (e.g pH Meter,
online analizers etc.);
3. PRE-CHECK ITEMS
The following items should be completed before system reliability run test:
Page 3 of 10
C. Trial run
D. Initial operation
Page 4 of 10
4. RELIABILITY RUN (RR) TEST PROCEDURE
4.1 RR will commence after the BSPG has notified MOE of readiness to
commence the test and it shall be agreed by MOE.
4.2 Plant will be operated by WWT station operation staff under the direct
supervision of BSPG.
4.3 Unit will be required to operate under the working conditions of the plant
according to operating procedures and within the limits of output
specified, without failure or interruption resulting from faults of
equipment, for a period of fifteen days, during which time such unit will
be operated continuously at Full capacity (depending of waste water
flow needed to be treated) providing proper parameters for treated
water delivered onto the river as per contract specification. If due to
unavailability of design chemicals substances needed to be used in
treatment of waste water during period of RR test, the unit treating
capacity will be adjusted accordingly based on maximum allowable
total flow and in this case it will not necessitate of repetition of test
hours.
Page 5 of 10
4.5.3 If it is necessary to shutdown the unit due to natural calamity
or for the safety of personnel, plant or equipment, the RR shall be
considered to have been suspended for the period shutdown.
4.5.4 If unit is tripped or shutdown due to or arising from defects in
design, material or workmanship (but not otherwise) sufficient to
prevent the agreed usage of the Unit, the RR trial period for the unit or
part shall recommence after the contractor has remidied the cause
Page 6 of 10
6. ACCEPTANCE CRITERIA OF RELIABILITY RUN
6.1 The 15 Days (360 hours) running of the plant in accordance with the
Test Procedure is considered as successful completion of RR
6.2 During the period of RR interruption (no cleaned water delivered onto
the river) or trip in one main equipment for storrage / discharge of subproducts
resulting from cleaning waste water process is not more than 3 hours
6.3 In the RR period (360 hours), number of hours of shutdown until the
recovery plant, cumulatively not more than 12 hours
6.4 At the end of RR test, if all the works have been done and closed
successfully, a concluding Certificate shall be issued (by RR comitee)
according Annex 2
7.3 The reliability run test for waste water treatment plant will be carried out
mainly with automation operation and occasionally manual / local comand
operation in continuous run under real conditions for 15 days and checks on
every 4 hours.
7.4 In case the malfunction or fault break out under auto operation during
reliability run test, the reliability run test will be restarted after necessary action
to be taken to restore running / operationing good condition.
7.5 The verified parameters such like flow rate, pressure, temperature,
chemical and phisical measured through online analysers and etc. will be
written down / recorded on the attached check sheet (template) (Annex 3).
Page 7 of 10
Annex 1
Annex 2
Page 8 of 10
Annex 3
ITEM NAME
ITEM No.
JUDGEMNT
AVERAGE
NO. CHECKITEM GUARANTEE UNIT 4hr 8hr 12hr 16hr 20hr 24hr REMARK
1 FLOW 70 m3/hr
2 pH 7~9
Oil &
3 〈10 mg/L
Grease
Settleable
6 Nil mg/L
Solids
* NOTE
Operator should be measure flow & pH value of treated water discharged every 4hrs. Others item measure after
24hr.
Page 9 of 10
Annex 4 - RELIABILITY RUN RECORDS
No DATE HOURS TYPE OF Actual running TIME OF EVENT INDICATION RECTIFICATION REMARK
DISTURBANCE state of the plant
WWT
MAX MIN START FINISH
Page 10 of 10