Project Schedule Check List

Acceptable
No Description Remark
Yes No

1 Project Start&completion Date √

2 Compliance To Contract Milestones √

3 Working Calendar √

4 Duration Provided For Review/approval Of Submittals √

5 closure Activities(duration & predecessors/successors) √

6 Engineering Activities(shop Drawings, design Validation,etc) ×

7 Procurement Activities(submittal,approval,po,delivary) ×

8 Activities With Out Predecessors Or Successor √

9 Constraints Used In Schedule √

10 Float(look For Activities With Big Float & negative Float) √

11 Cost Loading √

12 Logic/sequence Of Work √

13 Activity Level(breakdown Sufficient For Proper Control) √

14 Activity Durations(construction Activity Not Longer than One Month) √

15 Loading Labor &non Labor resource With P/u=zero ×

16 Project Coding System √

17 Resource Break Down &id √

18 All Construction Activities With Cost Loading for Material Resource √

19 Resource/labor Hours Loading ×

20 Calendar Name&level(project Level) √

21 Critical Activities Account With Range(10-20%)of number Of Total Activities √

22 Project Id √

23 Loops & invalid Relation For Activities √

24 Matching With Executing On Site Progress ×

25 Use Expected Finish Date √

26 Scheduling Progressed Activities Use Retained √

27 View Log Error √

28 Duration Type(fixed Duration&unit)for All Activities √

29 Resources Must Be(auto Compute Actual&calculate Cost From Units √

Remarks

Name:
Planning Engineer
Signature :