FABRICATION OF REINFORCEMENT BARS

FLOW OF CONSTRUCTION ACTIVITY


FABRICATION OF FORMWORKS FABRICATION OF STEEL TRUSSES

BUILDING PERMIT MOBILIZATION CONSTRUCTION OF STAKE OUT EXCAVATION


TEMPORARY FACILITIES
PLACEMENT OF RC BARS OF
FOOTING FOUNDATION
INSTALLATION OF STARTER BARS OF COLUMNS INSTALLATION OF RC BARS OF CHB
COMPACTION OF
STRUCTURAL BACKFILL
BACKFILL CONCRETE POURING OF INSTALLATION OF RC BARS FOR
FOOTING AND TIE BEAMS PROVISION OF FORMWORKS TIE BEAMS
FOR TIE BEAMS

POURING OF CONCRETE
INSTALLATION OF RC INSTALLATION OF FORMWORKS POURING OF CONCRETE PREPARATION OF
OF SLAB – ON - GRADE
BARS FOR COLUMNS FOR COLUMNS AT MID OF COLUMN FORMWORKS FOR BEAMS
HEIGHT AND GIRDERS AND
REMAINING COLUMN
INSTALLATION OF REBAR COLUMN AT SECOND FLOOR AND ROOF BEAMS
HEIGHT

PURING OF CONCRETE PREPARATION OF FORMS PURING OF REMAINING PREPARATION OF


COLUMN AT SECOND AND SHORING AT SECOND COLUMN HEIGHT, LAYING OF RC BARS FOR SHORING AND
FLOOR, BEAMS AND FLOOR COLUMNS, ROOF BEAMS, GIRDERS AND SUSPENDED SLAB FORMWORKS FOR
GIRDERS BEAMS SUSPENDED SLAB SUSPENDED SLAB

INSTALLATION OF STEEL INSTALLATION OF ROOF SHEETS INSTALLATION OF DOORS,


TRUSSES PURLINS, SAG-RODS AND INSTALLATION WINDOWS AND OTHER PAINTING WORKS
BRACINGS ARCHITECTURAL AND
SANITARY FIXURES
TESTING &
CHB LAYING AT GROUND AND SECOND FLOOR
COMMISSIONING OF
ELECTRICAL CONDUITS
OCCUPANCY
PLASTERING OF CHB EXTERIOR 1 YEAR WARRANTY DEMOBILIZATION
AND INTERIOR WALLS PERMIT