Professional Documents
Culture Documents
To cite this article: Rahul K. Dubey, Subhransu Ranjan Samantaray & Bijay Ketan
Panigrahi (2014) Adaptive Distance Relaying Scheme for Transmission Network
Connecting Wind Farms, Electric Power Components and Systems, 42:11, 1181-1193, DOI:
10.1080/15325008.2014.921953
CONTENTS
Abstract—This article presents an adaptive distance relay setting for
1. Introduction a power transmission network connecting more than one wind farm.
2. Background The ideal trip characteristics of the distance relay is greatly affected
in the presence of complex mutual coupling of transmission lines, as
3. Apparent Impedance Calculation the apparent impedance is significantly affected. Similarly, the reach
for Transmission Line Connecting setting of the relay for the lines connecting wind farms is signifi-
with Two Wind Farms cantly affected, as the relaying voltage fluctuates continuously. Thus,
the proposed study focuses on developing an adaptive relay setting for
4. Results and Analysis of Transmission Line with Wind Farms
a transmission network including more than one wind farm and con-
5. Adaptive Distance Relay Setting Method sidering variations in operating conditions of wind farms and mutual
6. Case Study coupling of transmission lines together. The proposed relay algorithm
7. Discussion is extensively tested on two-terminal as well as multi-terminal power
networks with wide variations in operating parameters. The perfor-
8. Conclusions mance testing of the proposed adaptive relay characteristics for faults
Funding and faults during power swing indicates the potential ability of the
References approach in handling distance relaying in a transmission system.
Appendix A
1. INTRODUCTION
The mutual coupling between transmission lines is common
in power systems and has a significant effect on behavior
of the relay protection during faults involving ground. The
positive- and negative-sequence mutual impedances are negli-
gible; however; the zero-sequence mutual coupling may be sig-
nificant and should be considered when setting ground relays
[1–3]. In the area of digital protection techniques [4], adaptive
relaying concepts provide another opportunity for improved
performance [5–7]. In [7], the trip boundary was set adaptively
assuming supervisory control and data acquisition (SCADA)
or phasor measurement units (PMU) voltages, and line flows of
all parts of the system are available. A neural network approach
has been proposed using real and reactive power at the relay
location as the input vector [9]. Such an approach provides
an approximate solution, and the neural network needs huge
Keywords: adaptive relay setting, distance relaying, multi-terminal line,
transmission line protection, wind farms, power swing, real-time digital training sets for developing a generalized scheme. Similarly,
simulator the integration of wind farms in a power system is increasing
Received 30 July 2013; accepted 1 May 2014
day by day to a larger extent [10]. The most difficult part in
Address correspondence to Dr. Subhransu Ranjan Samantaray, School of
Electrical Sciences, Indian Institute of Technology Bhubaneswar a wind farm is the uncontrolled wind speed, leading to volt-
Bhubaneswar-751013, Orissa, India. E-mail: sbh samant@yahoo.co.in age and frequency fluctuation [11–13]. Thus, protection issues
1181
1182 Electric Power Components and Systems, Vol. 42 (2014), No. 11
(Z 1L13 + Z 1S N ) Z 0S M ∗ Z 0S N
Z F2 = , (17) Z 0M D = . (35)
Z 1L12 + Z 1SW + Z 1L23 + Z 1S N Z 0L3 + Z 0S M + Z 0S N
Z E Q3 = Z 1S M + Z 1L23
Thus, the sequence currents between W to F are expressed
(Z 1L13 + Z 1S N ) ∗ (Z 1L12 + Z 1SW ) as
+ . (18)
Z 1L13 + Z 1SW + Z 1L12 + Z 1S N
G 1 VPREF
I1W = I2W = G 1 I1F = , (36)
Z + 3 ∗ R f
The pre-fault voltage at F is given by
G 0 VPREF
VPREF = E AW − Z 1SW IZ1SW − n ∗ Z 1L1 IPREF . (19) I0W = G 0 I0F = , (37)
Z + 3 ∗ R f
During a single-line-to-ground fault in phase a, the positive-,
where
negative-, and zero-sequence currents through fault resistance
RF are given by Z 1N
G1 = ,
Z 1W + Z 1N
VPREF
I1F = I2F = I0F = , (20)
Z + 3 ∗ R f G0 =
Z 0N
,
Z 0W + Z 0N
where
I AW = IPREF + I1L = IPREF + I1L1 + I0L1 + I2L1 , (38)
Z = Z ZEROSEQ + Z +VESEQ + Z −VESEQ , (21)
V AW = (I1F + I2F + I0F )R f + (IPREF + I1L1 + I2L2 )
Z 0W ∗ Z 0N ∗ n ∗ Z 1L1 + I0L1 ∗ n ∗ Z 0L1 + I0L2 ∗ n ∗ Z 0W 12
Z ZEROSEQ = + Z 0W N , (22)
Z 0W + Z 0N + I0L3 ∗ n ∗ Z 0W 13 . (39)
Z 1W ∗ Z 1N
Z +V E S E Q = Z −VESEQ = + Z 1W N , (23)
Z 1W + Z 1N
The apparent impedance measured at relaying point W is
Z 1L1 ∗ Z 1N D ∗ n
Z 1W = Z 1SW + , (24) V AW
n ∗ Z 1L1 + Z 1W D + Z 1N D Z AW = , (40)
I AW + K 0L1 I0L1 + K 0W 12 I0L2 + K 0W 13 I0L3
Z 0L1 ∗ Z 0N D ∗ n
Z 0W = Z 0SW + , (25) where
n ∗ Z 0L1 + Z 0W D + Z 0N D
Z 0L1 − Z 1L1
Z 1W D ∗ Z 1N D ∗ n K 0L = ,
Z 1N = Z 1M D + , (26) Z 1L1
n ∗ Z 1L1 + Z 1W D + Z 1N D Z 0W 12
K 0W 12 = ,
Z 0W D ∗ Z 0N D ∗ n Z 1L1
Z 0N = Z 0M D + , (27) Z 0W 13
n ∗ Z 0L1 + Z 0W D + Z 0N D K 0W 13 = . (41)
Z 1L1
Z 1W D ∗ Z 1L1 ∗ n
Z 1W N = , (28) Further simplification leads to
n ∗ Z 1L1 + Z 1W D + Z 1N D
Z 0L1 ∗ Z 0W D ∗ n Z AW = n ∗ Z 1L1
Z 0W N = , (29)
n ∗ Z 0L1 + Z 0W D + Z 0N D 3 ∗ Rf
+
IPREF ( Z +3∗R f )
Z 1L3 ∗ Z 1S N + 2 ∗ G 1 + G 0 ∗ (1 + K 0L )
Z 1W D = (1 − n) ∗ Z 1L1 + ,(30) VPREF
Z 1L3 + Z 1S N + Z 1S M +G 0 ∗ del x12 ∗ K 0W 12 + G 0 ∗ del x13 ∗ K 0W 13 ,(42)
Z 0L3 ∗ Z 0S N where delx12 and delx13 are the ratios of the zero-sequence
Z 0W D = (1 − n) ∗ Z 0L1 + ,(31)
Z 0L3 + Z 0S N + Z 0S M current in the healthy lines to the zero-sequence current in
Z 1L3 ∗ Z 1S M faulted line, given as follows:
Z 1N D = Z 1L2 + , (32)
Z 1L3 + Z 1S M + Z 1S N I0L2 C1 + C2 C3
del x12 = =− , (43)
Z 0L3 ∗ Z 0S M I0L1 C4 + C3 C5
Z 0N D = Z 0L2 + , (33)
Z 0L3 + Z 0S M + Z 0S N
Z 1S M ∗ Z 1S N I0L3 C1 − C6 C7
Z 1M D = , (34) del x13 = =− , (44)
Z 1L3 + Z 1S M + Z 1S N I0L1 C3 + C4 C7
Dubey et al.: Adaptive Distance Relaying Scheme for Transmission Network Connecting Wind Farms 1185
δ1 10 10 10
δ2 15 10 5
h1 0.98 0.98 0.98
h2 0.98 0.98 0.98
FIGURE 6. Trip boundaries for transmission system with FIGURE 7. Trip boundaries for transmission system with
change in second wind farm loading level keeping first wind change in wind farm 2 voltage amplitude ratio keeping wind
farm loading level constant. farm 1 voltage amplitude ratio constant.
Dubey et al.: Adaptive Distance Relaying Scheme for Transmission Network Connecting Wind Farms 1187
δ1 10 10 10 δ1 15 10 5
δ2 10 10 10 δ2 10 10 10
h1 0.98 0.98 0.98 h1 0.98 0.98 0.98
h2 0.98 1 1.1 h2 0.98 0.98 0.98
TABLE 2. Summary of varying wind farm 2 voltage level TABLE 4. Summary of varying wind farm 1 loading level
δ1 10 10 10
δ2 10 10 10 5. ADAPTIVE DISTANCE RELAY SETTING
h1 0.98 1 1.1 METHOD
h2 0.98 0.98 0.98
To achieve an accurate adaptive relay setting for the
TABLE 3. Summary of varying wind farm 1 voltage level distance relay at the wind farm side, information from
three ends is required. The grid-side voltage, current, and
impedance information is necessary to compute factors
flow from the wind farm to the grid through a transmission line h 1 , h 2 δ1 , δ2 , G 1 , G 0 , del x12 , and del x13 . The flowchart of the
network, and thus, the impedance stays in the positive region. proposed adaptive relay setting algorithm is shown in Fig-
ure 10, which uses local information for developing the relay
tripping characteristics. Table 5 depicts the summary of actual
4.6. Relay Setting for Transmission System with Change and estimated apparent impedance for fault conditions with
in Wind Farm 1 Loading Level Keeping Wind Farm variations in operating parameters. Figure 11 presents varia-
2 Operating Parameter Constant tions in Rapp and Xapp , with different fault resistance for fixed
This section deals with the impact of variations in the first power system operating conditions, and Figure 12 presents the
wind farm’s parameters on the tripping boundaries of the relay corresponding values with variation in wind farm loading level
with no change in the second wind farm’s parameters. Figure 9 δ. The extensive test results indicate that the maximum error
shows the adaptive tripping boundaries for different loading stays within 3%, showing the efficacy of the proposed distance
levels. It is observed that for lower values of δ 1 (Table 4), relay setting.
the trip boundary characteristic is the reverse of the results
presented in Section 4.3.
FIGURE 8. Trip boundaries for transmission system with FIGURE 9. Trip boundaries for transmission system with
change in wind farm 1 voltage amplitude ratio keeping wind change in wind farm 1 loading level keeping wind farm 2
farm 2 voltage amplitude ratio constant. loading level constant.
1188 Electric Power Components and Systems, Vol. 42 (2014), No. 11
TABLE 5. Summary of actual and estimated apparent impedance for faults with wide variations in operating condition
FIGURE 13. Impedance trajectory during power swing. FIGURE 15. Impedance trajectory for high-impedance fault
during power swing.
6. CASE STUDY
0.15 sec. It is noticed that the impedance trajectory enters the
6.1. Adaptive Relay Setting During Power Swing set boundary after 10 ms (half-cycle) and settles down.
Power swing is a critical issue and must be handled by the relay It is observed that the impedance trajectory enters the trip-
carefully. In the case of power swing [14–16], load angle may ping boundaries of the proposed adaptive relay zone and ex-
keep changing from 0◦ to 360◦ ; the relay must not respond to isting MHO relay in the case of a faulty situation (Rf = 10
the power swing and must effectively work for faults during a ), but in the case of a high-impedance fault during a power
power swing. A three-phase fault is simulated (at 32 km from swing (Figure 15), the impedance trajectory enters the tripping
relaying point W in line 1) for a load angle of 160◦ between boundaries of the proposed adaptive relay zone only and does
buses W and N during a fast swing with frequency 6 Hz. The not enter the zone of the existing MHO relay. Therefore, the
performance of the proposed adaptive relay setting scheme for existing MHO relay fails to operate during a high-impedance
a power swing and a fault during power swing is shown in fault. However, the reliability of the proposed adaptive distance
Figures 13 and 14, respectively. It is clearly observed that the relay is much better than the MHO relay, as the impedance tra-
power swing and fault during power swing are distinguished, jectory for a high-impedance faults (Rf = 50 ) enters the
and thus, the reliability of the relay is improved. Figure 14 adaptive distance relay while not entering into the MHO re-
shows the fault impedance trajectory for the fault initiated at lay characteristic. To measure the performance further, the
FIGURE 14. Impedance trajectory for fault during power FIGURE 16. Impedance trajectory during power swing on
swing. RTDS platform.
1190 Electric Power Components and Systems, Vol. 42 (2014), No. 11
proposed method is tested on a real-time digital simulator FIGURE 19. Interconnection of wind farm to grid through
(RTDS) module. The performance of the proposed relay for multi-terminal line.
a power swing and a fault during power swing on the RTDS
platform are shown in Figures 16, 17, and 18 (high-impedance
a multi-terminal (three-terminal T-type) network on the trip-
case), respectively. In recent articles [16–19], theory and al-
ping characteristics of the relay.
gorithms for out-of-step protection during a power swing and
Simulation results indicate that the measured apparent
high-impedance fault detection were discussed in detail.
impedance (ZAPP ) is significantly affected not only by vari-
ations in fault locations (0–95%) and fault resistance (0–500
6.2. Adaptive Relay Setting for Multi-terminal Line
) but also by variations in initial parameters, as defined in
Connecting with Wind Farm
Section 4. ZAPP for the trip zone of lines 1 and 2 is shown in
The proposed adaptive relay setting approach is also tested Figure 20, which clearly shows the efficacy of the proposed
on multi-terminal lines, as shown in Figure 19. The apparent adaptive relay setting and clearly distinguishes the tripping
impedance formula for a multi-terminal line given in Appendix zones for different sections of the multi-terminal lines. A sim-
A. Extensive computer simulation for a wind-connected multi- ilar observation is made for faults in lines 1 and 3, as shown
terminal network has been conducted to examine the impact of in Figure 21.
FIGURE 18. Impedance trajectory for high-impedance fault FIGURE 20. Trip boundaries for fault classification in lines 1
during power swing on RTDS platform. and 2.
Dubey et al.: Adaptive Distance Relaying Scheme for Transmission Network Connecting Wind Farms 1191
FIGURE 21. Trip boundaries for fault classification in lines 1 FIGURE 23. Impedance trajectory for a-g fault on RTDS
and 3. platform when two wind farms are connected to grid.
FUNDING
FIGURE 22. Impedance trajectory for a-g faults when two This research work has been supported by Prime Minister’s Fel-
wind farms are connected to grid. lowship for Doctoral Research, being implemented jointly by
1192 Electric Power Components and Systems, Vol. 42 (2014), No. 11
Science & Engineering Research Board (SERB) and Confed- [17] Rao, J. G., and Pradhan, A. K., “Differential power based
eration of Indian Industry (CII), with industry partner Robert symmetrical fault detection during power swing,” IEEE Trans.
Bosch. Power Delivery, Vol. 27, No. 3, pp. 1557–1564, July 2012.
[18] Dubey, R., and Samantaray, S. R., “Wavelet singular entropy-
REFERENCES based symmetrical fault-detection and out-of-step protection
during power swing,” IET Generat. Transm. Distribut., Vol. 7,
[1] Jongepier, G., and van der Sluis, L., “Adaptive distance protec- No. 10, pp. 1123–1134, October 2013.
tion of a double circuit line,” IEEE Trans. Power Delivery, Vol. [19] Aziz, M. S. A., Hassan, M. A. M., and Zahab, E. A., “High-
9, No. 3, pp. 1289–1297, July 1994. impedance faults analysis in distribution networks using an
[2] Rockefeller, G. D., “Fault protection with a digital computer,” adaptive neuro fuzzy inference system,” Elect. Power Compon.
IEEE Trans. Power App. Syst., Vol. PAS-88, No. 4, pp. 438–461, Syst., Vol. 40, No. 11, pp. 1300–1318, August 2012.
April 1969.
[3] Sachdev, M. S. (coordinator), “Computer relaying,” IEEE Tu-
APPENDIX A
torial Course Text Pub. 79EH0148-7-PWR, 1979.
[4] Ghorbani, A., Mozafari, B., and Ranjbar, A. M., “Digital dis- The apparent impedance calculation of multi-terminal line
tance protection of transmission lines in the presence of SSSC,” (Figure 19) with initial conditions [8, 12] is derived as
Int. J. Elect. Power Energy Syst., Vol. 43, pp. 712–719, Decem-
ber 2012.
follows:
[5] Xia, Y. Q., Li, K. K., and David, A. K., ”Adaptive relay setting h 1 = 0.97, h 2 = 1.01, Z 1SW = Z 0SW = 5e j85 ,
for standalone digital distance protection,” IEEE Trans. Power
Delivery, Vol. 9, No. 1, pp. 480–491, 1993. Z 1S M = Z 0S M = 20e j85 , Z 1S N = Z 0S N = 10e j85 .
[6] Li, K. K., Lai, L. L., and David, A. K., “Stand alone intelligent δ1 = 200 , δ2 = 100 , Z 1W J = Z 1W N 1 = 37.76e j86 ,
digital distance relay,” IEEE Trans. Power Delivery, Vol. 15, Z 0W J = Z 0W N 1 = 134.49e j81.3 , Z 1J N = 37.76e j86 .
No. 1, pp. 137–142, February 2000.
[7] Phadke, A. G., and Thorp, J. S., Computer Relaying for Power Z 0J N = 134.49e j81.3 , Z 1J M = 18.88e j86 ,
Systems, 2nd ed., Hoboken, NJ: Wiley, 2009. Z 0J M = 67.25e j81.3 .
[8] Xia, Y. Q., David, A. K., and Li, K. K., “High resistance faults
on multi-terminal lines: Analysis, simulated studies an adaptive
distance relaying scheme,” IEEE Trans. Power Delivery, Vol. 9, Case 1: Apparent Impedance Calculation for
No. 1, pp. 492–501, 1994. Multi-terminal HV Line Connected to Wind Farm When
[9] Li, K. K., Lai, L. L., and David, A. K., “Stand alone intelligent Fault (LG) Occurs at F1
digital distance relay,” IEEE Trans. Power Delivery, Vol. 15,
No. 1, pp. 137–142, February 2000.
The expression of apparent impedance measured by a relay for
[10] Brahma, S. M., and Girgis, A. A., “Development of adaptive fault occurring in transmission line 1 is
protection schemes for distribution systems with high penetra- 3 ∗ RF
tion of distribution generation,” IEEE Trans. Power Delivery, Z AW = n ∗ Z 1L1 + ,
χW S11 + 2χ1 + χ0 (1 + β0 )
Vol. 19, No. 1, pp. 56–63, January 2004.
[11] Eriksen, P. B., “System operation with high wind genera- where
tion,” IEEE Power Energy Mag., Vol. 5, No. 6, pp. 65–74,
November–December 2005. 3R F + Z λW S1
Z 1S N F1
[12] Pradhan, A. K., and Joos, G., “Adaptive distance relay setting χW S11 = , χ1 = ,
for lines connecting wind farms”, IEEE Trans. Energy Conver- (1 − Z 1W λW S1 ) Z 1SW F1 + Z 1S N F1
sion, Vol. 22, No. 1, pp. 206–213, March 2007. Z 0S N F1 Z 0W F1 − Z 1W F1
χ0 = , β0 =
[13] Kamel, A., Alaam, M. A., Azmy, A. M., and Abdelaziz, A. Y., Z 0SW F1 + Z 0S N F1 Z 1W F1
“Protection coordination for distribution systems in presence
Z 0W J − Z 1W J
of distributed generators,” Elect. Power Compon. Syst., Vol. 41, = .
No. 15, pp. 1555–1566, November 2013. Z 1W J
[14] Paudyal, S., Gokaraju, R., and Sachdev, M. S., “Application of (1 − λ)
equal area criterion conditions in the time domain for out-of- λW S1 = ,
(Z 1M L + Z N L ) (Z 1W + Z 1N 1 )
step protection,” IEEE Trans. Power Delivery, Vol. 25, No. 4,
pp. 600–609, April 2010. Z 1N L
λ= h 1 e− jδ1 − h 1 e− jδ1 − h 2 e− jδ2 ,
[15] Paudyal, S., Gokaraju, R., Sachdev, M. S., and Cheng, S., “Out- Z 1N L + Z 1M L
of-step detection using energy equilibrium criterion in time do- Z 1W = Z 1SW + Z 1W F1 .
main,” Elect. Power Compon. Syst., Vol. 37, No. 7, pp. 714–739,
June 2009. Z 1N L Z 1M L
Z 1N 1 = Z 1SNEQU + Z 1F1N 1 , Z 1SNEQU = ,
[16] Samantaray, S. R., Dubey, R. K., and Chitti Babu, B., “A novel Z 1N L + Z 1M L
time-frequency transform based spectral energy function for Z 0N L Z 0M L
fault detection during power swing,” Elect. Power Compon. Z 0SNEQU = , Z 1W L = Z 1SW + Z 1W J .
Syst., Vol. 40, No. 8, pp. 881–897, April 2012.
Z 0N L + Z 0M L
Dubey et al.: Adaptive Distance Relaying Scheme for Transmission Network Connecting Wind Farms 1193