METHOD STATEMENT FOR FOOTING


In generally a mix proportion of cement, sand coarse aggregate and water for different grade as specified in
tender for designated work location with reinforcement tied at location called R.C.C. The determination of the
proportion of cement, aggregate and water to attain the required grade of concrete will be made by designing the
concrete mix. Such concrete shall be called ‘Design mix concrete’.

SCOPE OF WORK:
 Cleaning & clearing unwanted debris from concreting area.
 Mixing of concrete by ready mix concrete.
 Transporting and placing of concrete.
 Compacting.
 Curing.

RESOURCES:
a) MACHINERIES:
 RMC
 Concrete Pump/ Tower crane
a) EQUIPMENTS:
 Vibrator as per required
 Needle as per required
 Auto level with staff & Total Station
 5 & 30 M tape, Tower crane, Concrete Bucket and funnel.
a) MAN POWER:
 Skilled and Unskilled labor force
d) TOOLS:
 Shovel, Pan, Trowel,

e) MATERIALS:
 Cement,
 Fine aggregate
 Coarse aggregate (of designated size)
 Water
 Admixture as per tender specification

1
BOSCH BAN-700 MANAGEMENT TRAINING CENTER

DRAWINGS/DETAILS: Generally Drawings or Details are required to collect well


ahead of work commencement

 Marking Plan
 Relevant structural drawing

SPECIFIC WORK METHOD STATEMENT: -

a) Preparation of works:

 Prior to commencement of work, clear the unwanted debris/loose material from concreting area.
 Establish the marks for height and level of concreting.
 A joint inspection will be done for orientation, shape, size, thickness of concrete.
 Supervisor should be familiar with the latest construction drawing and method statement.
 A program is to be prepared for the work in line with the main construction program.
 Plant and equipment will be assessed on case by case basis for each concreting location.

b) Execution of works:

i) SURVEY:- Footing, Column marking will be done on PCC surface as per drawing and checked
with consultant before start steel tieing
ii) REINFORCEMENT: -

 Bar cutting and bending schedule will be submitted to PMC.


 Reinforcement bars will be cut and bent according to the bar bending schedule.
 The reinforcement will be tied using 18 G GI binding wire (double binding).
 The cover to the reinforcement will be given as specified in drawing with PVC cover
blocks.
 Loose and unwanted material will be cleaned before placing the reinforcement.

iii) SHUTTERING: -

2
BOSCH BAN-700 MANAGEMENT TRAINING CENTER

 The making of footing form work board shall be made by using 12mm of size
1220x2440mm water proofing plywood which will be backed by MS frame work
50x25mm box section at 300mm c/c both way
 The form work casted and fixed by using the tie rod at 450c/c horizontally in 3
layer for height of the board
 The grid lines will be transferred to fix the form work accordingly.
 Shuttering will be done using clean & good shuttering forms as per required
level, line, shape and size.

 The joints of shuttering forms will be sealed with adhesive tape to prevent slurry
escape.
 Shuttering surface touching with concrete shall be oiled using suitable shuttering
oil.
 Adequate support and cross bracing will be provided by CT props to maintain the
vertical and horizontal of the form work
 Checking will be done for level, shape, size, support of shuttering.
 Scaffolding will done for concreting.
 Top level of concrete will be marked.

iv) CONCRETING: -

 The proportion of cement, sand, coarse aggregate with water will be mixed as per specific
grade in concrete plant.
 With the help of Auto level & staff or tube level and with respect to approved bench mark,
final level of concreting will be marked. Mixed concrete will be placed to appropriate
location and leveled with help of shovel and wooden mallet.
 Leveled concrete will be compacted layer by layer with needle vibrator to get the required
compaction.
 The whole process of transporting, levelling and compacting of concrete will be done as per
design mix of mixing cement with water to get the required compaction and to allow all the
interstices to be filled with mortar.
 Slump to be checked.
 Cube to be casted for testing
 After final setting of concrete, the surface will be kept continuously wet for 10days.
 Deshuttering will be done after 24 hours