2,000 2,000
1,739
Thousand Cubic Metres
Thousand Tonnes
1,000 1,000
461
500 500
0 0
Jun- Jul- Aug- Sep- Oct- Nov- Dec- Jan- Feb- Mar- Apr- May- Jun-
2014 2014 2014 2014 2014 2014 2014 2015 2015 2015 2015 2015 2015
Month-Year
Granite (Thousand Tonnes) Cement (Thousand Tonnes) RMC (Thousand Cubic Metres)
Page 1/5
Monthly Demands for Steel Bars
300
250
200
166
Thousand Tonnes
150
100
50
0
Jun- Jul- Aug- Sep- Oct- Nov- Dec- Jan- Feb- Mar- Apr- May- Jun-
2014 2014 2014 2014 2014 2014 2014 2015 2015 2015 2015 2015 2015
Month-Year
Page 2/5
Market Prices of Granite, Sand, Cement and Ready-Mixed Concrete
60 140
99.9 99.9
100
40
93.0 92.8
Cement (RHS) 80
Sand (LHS)
30
23.2 22.8 60
20
Granite (LHS) 19.9 19.2 40
10 20
0 0
Jun- Jul- Aug- Sep- Oct- Nov- Dec- Jan- Feb- Mar- Apr- May- Jun- Jul-
2014 2014 2014 2014 2014 2014 2014 2015 2015 2015 2015 2015 2015 2015p
Month-Year
p - preliminary; RHS- Right Hand Side Y-Axis; LHS- Left Hand Side Y-axis
Market Prices (without delivery) of 20mm Granite ($/Tonne) Market Prices (without delivery) of Sand ($/Tonne)
Market Prices of Cement in Bulk ($/Tonne) Market Prices of RMC Grade 40P ($/Cubic Metre)
750
700
650
$/Tonne
600
550
506.6
500 490
450
Jun- Jul- Aug- Sep- Oct- Nov- Dec- Jan- Feb- Mar- Apr- May- Jun- Jul-
2014 2014 2014 2014 2014 2014 2014 2015 2015 2015 2015 2015 2015 2015p
Month-Year
Apr 2015 96.88 391.37 2.56 135.57 70.87 179.57 310.64 459.37 596.48 29.96 1077.43 1195.84
May 2015 213.16 526.32 11.72 20.77 79.02 450.74 287.61 114.53 196.97 11.04 788.48 1123.40
Jun 2015 P 148.46 303.36 0.00 88.99 326.38 357.00 141.61 13.98 1184.95 34.80 1801.40 798.13
p
= Preliminary figures
Page 3/5
VALUE OF PROGRESS PAYMENTS CERTIFIED BY DEVELOPMENT TYPE AND SECTOR
(Data as at 23 July 2015) ($ Million)
Apr 2015 P 455.00 670.00 10.00 260.00 40.00 500.00 245.00 85.00 555.00 100.00 1305.00 1615.00
May 2015 P 420.00 685.00 15.00 240.00 30.00 460.00 260.00 160.00 510.00 120.00 1235.00 1665.00
Jun 2015 P 450.00 670.00 8.00 260.00 52.00 490.00 275.00 110.00 545.00 100.00 1330.00 1630.00
p
= Preliminary figures
JTC Space @ Gul: Erection of 2 Blocks of 3-Storey Terrace Industrial Id Architects LBD Engineering
Factory with an Ancillary Office comprising 14 units at Gul
Circle (Contract Cost: $35.31m)
Additions and Alterations to the Existing Frontier, Punggol Institutional Architects Guan Ho
Green, Punggol View and Sengkang Green Primary Schools Project Group Construction Co
(Contract Cost: $24.98m)
Completion of Outstanding Works for the Construction of Civil Not Applicable McConnell Dowell
Service Tunnels, Access Shafts and Ancillary Works at Engineering South East Asia
Banyan Avenue in Jurong Island (Contract Cost: $18.89m)
Resurfacing of Taxiways at Singapore Changi Airport Civil RSP Architects Ley Choon
Engineering Planners & Constructions And
Engineers Engineering
HDB Building Works at Yishun N4 C19 comprising 469 units Residential HDB In-House BHCC
and Contingency Works (Contract Cost: $63.80m) Construction
HDB Building Works at Hougang N9 C18 comprising 791 Residential ADDP LBD Engineering
units and Contingency Works (Contract Cost: $75.92m) Architects
Intercontinental Hotel: Phases 1 & 2 Reconstruction of the Commercial SCDA Gennal Industries
Existing 10-Storey Hotel comprising 227 Rooms with a Sky Architects
Terrace, 2 Basement Carparks and an Outdoor Refreshment
Area at Nanson Road
Thomson-East Coast MRT Line: Advanced Sewer Diversion Civil Parsons Ed Zublin Ag,
Package 2 (Contract Cost: $78.60m) Engineering Brinckerhoff Singapore Branch
Widening of Woodlands Road, Choa Chu Kang Link and Civil Not Applicable Hwa Seng Builder
Stagmont Ring (Contract Cost: $46.86m) Engineering
Page 4/5
Development
Project Description Consultant Contractor
Type
CONTRACT COST (ABOVE S$90M)
High Park Residences: Erection of 6 Blocks of 23 to 25- Residential P&T China Construction
Storey Condominium Development comprising 1,376 units, 4 Consultants (South Pacific)
Units of 3-Storey Bungalows, 10 Units of 3-Storey Semi- Development Co
Detached Houses and 9 Shops at Fernvale Road/Sengkang
West Way
Erection of a 7-Storey Single User Data Centre with Ancillary Industrial XCube Kienta Engineering
Facilities at Yung Ho Road Architects Construction
Erection of 2 Blocks of 10-Storey, 3 Blocks of 9-Storey Multi- Industrial SAA Architects Tiong Seng
User General Industrial Factory with a Workers' Dormitory, a Contractors
Heavy Vehicle Parking Facility and Commercial Space at
Tuas Avenue (Contract Cost: $277.27m)
Earthworks at Gali Batu (Contract Cost: $133.73m) Civil Not Applicable Chye Joo
Engineering Construction
Expansion of KPE/TPE Interchange including a Link Road to Civil Not Applicable Hwa Seng Builder
Punggol Central (Contract Cost: $185.06m) Engineering
52 Jurong Gateway Road #11-01 Singapore 608550 Tel : 1800-3425 2222 Fax : 6325 4800
Email Address : bca_enquiry@bca.gov.sg Web Site Address : http://www.bca.gov.sg
_______________________________________________________________________________________________________________________________________________________________________________
For Enquiries on Construction Materials, please contact Ms Noor Ain Bte Salleh at Tel : 6804 4536
For Enquiries on Construction Statistics, please contact Ms Siti Aloyah at Tel : 6804 4504